QC~PLAN.

Project No. & Name:


Name of Client/ Consultant:
SL ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.
No. DOCUMENT OF INSP./TEST AT LOCATION
1 Check for all Drawing Verification, 100% -Pre tiling check signed by respective Engineer /
concealed service Contract Specs. service discipline Engineer/ Foremen (if Foremen/
conduits BS 8000 Part 11 appilcable) Quality Engineer
BS 5385
2 Preparation of back- Drawing Visual, 100% - Background free from contamination & Engineer /
ground/substrate/ Contract Specs. loose material Foremen/
backing/base BS 8000 Part 11 - Dry & sound Quality Engineer
BS 5385

3 Setting out Drawing Visual, 100% - Minimum cutting of tiles Engineer /


Contract Specs. - Uniform joint width in vertical & horizontal Foremen/
BS 8000 Part 11 - Cut courses shall be kept minimum Quality Engineer
BS 5385 - Tile rows truly horizontal / vertical
- Establish datum levels
- The conduits, electrical cables & electrical
boxes and sanitary fixture sleeves
are fixed secuely in position
- Incorporate movement joints
4 Bedding materials and Drawing Visual, 100% - Bedding materials and methods as Engineer /
methods Contract Specs. per specification Foremen/
BS 8000 Part 11 - Proportioning and mixing of cement sand Quality Engineer
BS 5385 mortar and adhesives as per specification /
Mfr's. data sheet manufacturer's instructions
Bedding Materials
- Adhesives
- Cement based
Bedding methods
- Notched trowelling
- Cement sand mortar
- Semi-dry mix
QC~PLAN.
Project No. & Name:
Name of Client/ Consultant:

SL ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.


No. DOCUMENT OF INSP./TEST AT LOCATION
5 Laying of tiles Drawing Visual, 100% - Appropriate bedding methods Engineer /
Contract Specs. - Proportioning and mixing of cement / organic Foremen/
BS 8000 Part 11 based adhesives as per spec. / mfr's. Quality Engineer
BS 5385 instructions
Mfr's. data sheet - Control overall level of finished floor with
series of spot levels
- Line up floor tile joints with joints in
skirting tiles
- Where adjoining surfaces are in different
plane ensure the joints are continuous
- Stopping strips & divider strips installed
at change of floors
- Cut tiles neatly and accurately
- Joints made good around pipes & floor
drains
- Avoid cut courses
- Provide cut courses as wide as possible
- Surface irregularity within 3 mm
6 Curing Drawing Visual, 100% -Cure for period required Engineer /
Contract Specs. (3 days if not specified) Foremen/
Quality Engineer

7 Grouting Drawing Visual, 100% - Joints free from loose material Engineer /
Contract Specs. - Jointing mortar stiff, slump free & Foremen/
BS 8000 Part 11 workable Quality Engineer
BS 5385 - Joints filling material for wall shall be stiff
Mfr's. data sheet and self supporting
- Tiles not disturbed
- No air trapped
- Surplus jointing material cleaned from tile
- Finish joints neatly & face of tile cleaned
and polished
- Use coloured grout if specified
QC~PLAN.
Project No. & Name:
Name of Client/ Consultant:

SL ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.


No. DOCUMENT OF INSP./TEST AT LOCATION
8 Movement joint Drawing Visual, 100% - Appropriate sealant Engineer /
Contract Specs. - Fixing of sealant as per manufacturer's Foremen/
BS 8000 Part 11 data sheet Quality Engineer
BS 5385 Tolerances
Mfr's. data sheet - Less than 6 mm wide 1 mm
- 6 mm or more 2 mm

9 Protection Drawing Visual, 100% - Protected from rain & dust Engineer /
Contract Specs. - No traffic permitted for 24 hours Foremen/
BS 8000 Part 11 - Light foot traffic allowed after 24 hours Quality Engineer
BS 5385 - Normal traffic allowed after 7 days
Mfr's. data sheet -Covered with polyethene sheet/ paper
board sheet/ plywood etc.

10 Final Inspection Drawing Visual, 100% - Pattern, slope & finishing to match Engineer /
Contract Specs. drawings Foremen/
- Free from stains & spatter Quality Engineer
QC~PLAN.
Ceramic Tiling (Wall & Floor)
Doc.No.CIVIL QC~Plan- 017/ REV. 0
RECORD

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0
Daily tiling log
CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0
QC~PLAN.
Ceramic Tiling (Wall & Floor)
Doc.No.CIVIL QC~Plan- 017/ REV. 0

RECORD

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0

--

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0
QC~PLAN.
Ceramic Tiling (Wall & Floor)
Doc.No.CIVIL QC~Plan- 017/ REV. 0

RECORD

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0

Daily tiling log


CIVIL QC~Form- 016-01/ REV 0
Ceramic Tiling (Wall & Floor)
CIVIL QC~Form- 017-01/ REV 0

Ceramic Tiling (Wall & Floor)


CIVIL QC~Form- 017-01/ REV 0