Sie sind auf Seite 1von 6

Costing for 15KL RCC tank

Sl.No Description of work Units Qty Rate Amount


1 Dismantling of RCC Cu.Mtr 2.4 10500 25200
2 Excavation work Cu.Mtr 24 495 11880
3 Carting away from debris Cu.Mtr 24 250 6000
4 Refilling work Cu.Mtr 15 250 3750
3 Wet-Mix Cu.Mtr 4 2900 11600
4 P.C.C Cu.Mtr 2.5 5500 13750
5 R.C.C Cu.Mtr 28.82 7600 219032
6 Shuttering work Sq.Mtr 169.2 650 109980
7 Plastering work Sq.Mtr 97.5 365 35587.5
8 Water proofing work Sq.Mtr 53.5 1250 66875
9 Acid tile linning work Sq.Mtr 53.5 3100 165850
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 4000 65 260000
12 Cement Bags 125 385 48125
13 Misc. LS 1 30000 30000
Total 1012630
10.5

Costing for 10KL RCC tank


Sl.No Description of work Units Qty Rate Amount
1 Dismantling of RCC Cu.Mtr 2.4 10500 25200
2 Excavation work Cu.Mtr 24 495 11880
3 Carting away from debris Cu.Mtr 24 250 6000
4 Refilling work Cu.Mtr 15 250 3750
3 Wet-Mix Cu.Mtr 4 2900 11600
4 P.C.C Cu.Mtr 2.5 5500 13750
5 R.C.C Cu.Mtr 26.9 7600 204440
6 Shuttering work Sq.Mtr 150 650 97500
7 Plastering work Sq.Mtr 87.9 365 32083.5
8 Water proofing work Sq.Mtr 43.9 1250 54875
9 Acid tile linning work Sq.Mtr 43.9 3100 136090
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 4000 65 260000
12 Cement Bags 125 385 48125
13 Misc. LS 1 30000 30000
Total 940293.5
9.5

Costing for 5KL RCC tank


Sl.No Description of work Units Qty Rate Amount
1 Dismantling of RCC Cu.Mtr 1.8375 10500 19293.75
2 Excavation work Cu.Mtr 18.375 495 9095.625
3 Carting away from debris Cu.Mtr 18.375 250 4593.75
4 Refilling work Cu.Mtr 10 250 2500
3 Wet-Mix Cu.Mtr 3.0625 2900 8881.25
4 P.C.C Cu.Mtr 1.85 5500 10175
5 R.C.C Cu.Mtr 16.014 7600 121706.4
6 Shuttering work Sq.Mtr 83.66 650 54379
7 Plastering work Sq.Mtr 47.62 365 17381.3
8 Water proofing work Sq.Mtr 25.62 1250 32025
9 Acid tile linning work Sq.Mtr 25.62 3100 79422
10 Bore packing in tank Nos 4 1250 5000
11 Reinforcement Steel Kgs 2500 65 162500
12 Cement Bags 125 385 48125
13 Misc. LS 1 30000 30000
Total 605078.1
6.1
BOQ for 15KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 4 2 2 0.15 2.4

2 Excavation work Cu.Mtr 4 2 2 1.5 24

3 Carting away from debris Cu.Mtr 24


4 Refilling work Cu.Mtr 15

4 Wet-Mix Cu.Mtr 4 2 2 0.25 4

5 P.C.C Cu.Mtr 4 2 2 0.1 1.6


Cu.Mtr 4 1.5 1.5 0.1 0.9
2.5
6 R.C.C
Footing Cu.Mtr 4 1.8 1.8 0.5 6.48
Column Cu.Mtr 4 0.75 0.5 2 3
Tie beam Cu.Mtr 1 17 0.5 0.7 5.95
Wall starter Cu.Mtr 1 12 0.2 0.1 0.24
Slab Concrete Cu.Mtr 1 3 4 0.3 3.6
Reintaining wall Cu.Mtr 2 2.5 3 0.2 3
Reintaining wall Cu.Mtr 2 3.5 3 0.2 4.2
Top slab Cu.Mtr 1 2.5 3.5 0.2 1.75
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
28.82
7 Shuttering work
Footing Sq.Mtr 4 7.2 0.5 14.4
Column Sq.Mtr 4 2.5 2 20
Tie beam Sq.Mtr 1 17 2 34
Slab Sq.Mtr 1 3 4 12
Reintaining wall Sq.Mtr 4 3.5 3 42
Reintaining wall Sq.Mtr 4 2.5 3 30
Slab Sq.Mtr 1 3 4 12
Starter 2 12 0.2 4.8
169.2
8 Plastering work
Column Sq.Mtr 4 2.5 1 10
Tie beam Sq.Mtr 1 17 2 34
External Sq.Mtr 1 12 3 36
Slab Top & Bottom Sq.Mtr 2 2.5 3.5 17.5
97.5
9 Water proofing work Sq.Mtr 1 12 3 36
Sq.Mtr 2 2.5 3.5 17.5
53.5
10 Acid tile linning work Sq.Mtr 1 12 3 36
Sq.Mtr 2 2.5 3.5 17.5
53.5

11 Bore packing in tank Nos 4

BOQ for 10KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 4 2 2 0.15 2.4

2 Excavation work Cu.Mtr 4 2 2 1.5 24

3 Carting away from debris Cu.Mtr 24


4 Refilling work Cu.Mtr 15

4 Wet-Mix Cu.Mtr 4 2 2 0.25 4

5 P.C.C Cu.Mtr 4 2 2 0.1 1.6


Cu.Mtr 4 1.5 1.5 0.1 0.9
2.5
6 R.C.C
Footing Cu.Mtr 4 1.8 1.8 0.5 6.48
Column Cu.Mtr 4 0.75 0.5 2 3
Tie beam Cu.Mtr 1 17 0.5 0.7 5.95
Wall starter Cu.Mtr 1 12 0.2 0.1 0.24
Slab Concrete Cu.Mtr 1 3 4 0.3 3.6
Reintaining wall Cu.Mtr 2 2.5 2.2 0.2 2.2
Reintaining wall Cu.Mtr 2 3.5 2.2 0.2 3.08
Top slab Cu.Mtr 1 2.5 3.5 0.2 1.75
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
26.9
7 Shuttering work
Footing Sq.Mtr 4 7.2 0.5 14.4
Column Sq.Mtr 4 2.5 2 20
Tie beam Sq.Mtr 1 17 2 34
Slab Sq.Mtr 1 3 4 12
Reintaining wall Sq.Mtr 4 3.5 2.2 30.8
Reintaining wall Sq.Mtr 4 2.5 2.2 22
Slab Sq.Mtr 1 3 4 12
Starter 2 12 0.2 4.8
150
8 Plastering work
Column Sq.Mtr 4 2.5 1 10
Tie beam Sq.Mtr 1 17 2 34
External Sq.Mtr 1 12 2.2 26.4
Slab Top & Bottom Sq.Mtr 2 2.5 3.5 17.5
87.9
9 Water proofing work Sq.Mtr 1 12 2.2 26.4
Sq.Mtr 2 2.5 3.5 17.5
43.9
10 Acid tile linning work Sq.Mtr 1 12 2.2 26.4
Sq.Mtr 2 2.5 3.5 17.5
43.9

11 Bore packing in tank Nos 4

BOQ for 5KL RCC tank

Sl.No Description of work Units Nos L B D Qty


1 Dismantling of RCC Cu.Mtr 1 3.5 3.5 0.15 1.8375

2 Excavation work Cu.Mtr 1 3.5 3.5 1.5 18.375

3 Carting away from debris Cu.Mtr 18.375


4 Refilling work Cu.Mtr 10

4 Wet-Mix Cu.Mtr 1 3.5 3.5 0.25 3.0625

5 P.C.C Cu.Mtr 1 3.5 3.5 0.1 1.225


Cu.Mtr 1 2.5 2.5 0.1 0.625
1.85
6 R.C.C
Footing Cu.Mtr 1 3.5 3.5 0.5 6.125
Column Cu.Mtr 4 0.5 0.5 1.5 1.5
Tie beam Cu.Mtr 1 8 0.3 0.5 1.2
Wall starter Cu.Mtr 1 8 0.2 0.1 0.16
Slab Concrete Cu.Mtr 1 2.7 2.7 0.3 2.187
Reintaining wall Cu.Mtr 2 2.1 2 0.2 1.68
Reintaining wall Cu.Mtr 2 2.1 2 0.2 1.68
Top slab Cu.Mtr 1 2.1 2.1 0.2 0.882
Inside IPS flooring Cu.Mtr 1 2 3 0.1 0.6
16.014
7 Shuttering work
Footing Sq.Mtr 1 14 0.5 7
Column Sq.Mtr 4 2 1.5 12
Tie beam Sq.Mtr 1 8 2 16
Slab Sq.Mtr 1 2.7 2.7 7.29
Reintaining wall Sq.Mtr 4 2.1 2 16.8
Reintaining wall Sq.Mtr 4 2.1 2 16.8
Slab Sq.Mtr 1 2.1 2.1 4.41
Starter 2 8.4 0.2 3.36
83.66
8 Plastering work
Column Sq.Mtr 4 2 0.75 6
Tie beam Sq.Mtr 1 8 2 16
External Sq.Mtr 1 8.4 2 16.8
Slab Top & Bottom Sq.Mtr 2 2.1 2.1 8.82
47.62
9 Water proofing work Sq.Mtr 1 8.4 2 16.8
Sq.Mtr 2 2.1 2.1 8.82
25.62
10 Acid tile linning work Sq.Mtr 1 8.4 2 16.8
Sq.Mtr 2 2.1 2.1 8.82
25.62

11 Bore packing in tank Nos 4