Sie sind auf Seite 1von 1

S10 Pgina : 1

Precios y cantidades de recursos requeridos por tipo


Obra 0102002 VALLERY ALEJANDRA ZEBALLOS URBANO
Subpresupuesto 007 EXAMEN PARCIAL
Fecha 10/02/2013
Lugar 180401 ZABALLOS - ALEJANDRA - URBANO
Cdigo Recurso Unidad Cantidad Precio S/. Parcial S/.

MANO DE OBRA
0101010007 121022035 P OPERARIO hh 39,614.6624 19.18 759,809.22
0101010008 121022035 P OFICIAL hh 41,881.6201 15.92 666,755.39
0101010009 121022035 P PEON hh 22,906.8480 14.43 330,545.82
0101010011 121022035 P CAPATAZ hh 4,214.1559 21.10 88,918.69

1,846,029.12
MATERIALES
02010500010008 121022035 P ASFALTO RC-250 gal 804.0656 6.98 5,612.38
02040100010006 121022035 P ALAMBRE NEGRON 8 kg 2,702.4000 3.95 10,674.48
0204030005 121022035 P ACERO DE REFUERZO kg 27,600.0000 3.15 86,940.00
02041200010009 121022035P CLAVOS C/C 2 1/2", 3",4" kg 35.5221 3.39 120.42
02041200010010 121022035P CLAVOS PARA MADERA CON CABEZA DE 3" kg 1,351.2000 4.66 6,296.59
0204180008 121022035 P PLANCHA DE FIERRO 1/16"X1.20X2.4M pza 3,974.4000 101.69 404,156.74
02070100010006 121022035 P PIEDRA CHANCADA 1/2" Y3/4" m3 3,654.5600 63.56 232,283.83
02070200010005 121022035P ESCORIA m3 236.2560 76.27 18,019.25
02070200010006 121022035 P ARENA GRUESA m3 2,008.0000 46.61 93,592.88
02070200010007 121022035 P ARENA FINA m3 12.0640 50.85 613.45
02070400010007 121022035 P MATERIAL GRANULAR PRECESADO TM1" m3 12,481.4400 29.66 370,199.51
0210010002 121022035 P FIBRA DE VIDRIO kg 16,560.0000 19.07 315,799.20
0213010008 121022035 P CEMENTO PORTLAND TIPO I (42.5 kg) bol 34,778.5600 18.22 633,665.36
02130600010004 121022035P OCRE COLOR ROJO kg 513.6000 5.00 2,568.00
02190100100009 121022035P CONCRETO PREMEZCLADO F'C= 175 kg/cm2 m3 6,205.9200 293.59 1,821,996.05
PUESTO EN OBRA
0222090005 121022035 P RESINA PARA VIDRIO gal 1,380.0000 19.49 26,896.20
0231010006 121022035 P MADERA TORNILLO p2 25,672.8000 5.08 130,417.82
0231010007 121022035 P TRIPLAY DE 4X8X19 pln 1,080.9600 88.98 96,183.82
02380100020005 121022035 P LIJA DE FIERRO #80 plg 916.3200 2.12 1,942.60
0240020016 121022035 P PINTURA BASE gal 2,208.0000 16.95 37,425.60
02400300040002 121022035 P PINTURA ESMALTE IMPERMEABLE kg 2,208.0000 38.14 84,213.12
0240080024 121022035 P CATALIZADOR DE RESINA gal 1,380.0000 42.37 58,470.60
0240080025 121022035 P THINNER gal 552.0000 15.25 8,418.00
0255080015 121022035 P SOLDADURACELLLORD 1/8 kg 690.0000 12.71 8,769.90
0265060002 121022035 P TUBO DE FIERRO pza 2,760.0000 88.98 245,584.80
0267110022 121022035 P LAMINA REFLECTIVA ALTA INTENSIDAD jgo 3,698.4000 152.54 564,153.94
0276020077 121022035 P DISCO DE CORTE und 552.0000 12.71 7,015.92
0276020078 121022035 P DISCO DE DESBASTE und 1,104.0000 12.71 14,031.84
0290130022 131022005P AGUA und 738.9440 5.00 3,694.72
0290130023 121022035 P AGUA und 640.3200 5.00 3,201.60

5,292,958.62
EQUIPOS
0301010044 121022035P HERRAMIENTAS MANUALES %mo 55,386.06
0301030011 121022035 P SOLDARA ELECT, MONOF..ALTERNA hm 14,720.1840 25.42 374,187.08
03011000060003 121022035 P RODILLO LISO VIBRATORIO AUTOPROPULSADO hm 65.4864 134.18 8,786.97
70-100
0301100007 121022035 P RODILLO VIBRATORIO hm 3.5280 91.60 323.16
0301100008 121022035 P COMPACTADORA VIBRATORIA TIPO PLANCHA 4 hm 910.0800 25.08 22,824.81
HP
03011600010005 121022035 P CARGADOR SOBRE LLANTAS hm 4.1280 153.14 632.16
121022035 PCARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3
03012000010004 121022035 P MOTONIVELADORA 130 - 135 HP hm 7.0560 221.68 1,564.17
03012000010005 121022035 P MOTONIVELADORA 180 - 200 HP hm 27.6576 221.68 6,131.14
03012200050005 121022035 P CAMION CISTERNA 3000 gl (AGUA) hm 12.8976 157.86 2,036.02
03012900010005 121022035P VIBRADOR A GASOLINA 1 3/4", 4HP hm 2,990.1575 8.00 23,921.26
03012900030004 121022035 P MEZCLADORA DE TROMPO 9 P3 (8 HP) hm 2,141.7328 15.00 32,125.99
03013400030005 121022035 P ESMERIL hm 7,359.8160 11.02 81,105.17

609,023.99

Total S/. 7,748,011.73

Fecha : 01/11/2017 01:04:59