Sie sind auf Seite 1von 41

PROJECT : Proposed Forty - Two Storey ( Ri

LOCATION : E. Rodriguez Sr., Brgy. , Kalusuga


SUBJECT : Two Weeks Look - Ahead
DATE : September 26 - Oct. 9, 2014

A Activities QTY Unit Start

Foundation

Excavation Works
1,100.39 Cu.m 26-Sep-14
MF - 2

27.04 Cu.m 5-Oct-14


F-1 : along grid line H'/3

73.96 Cu.m 7-Oct-14


F-5 : along grid line G/3

73.96 Cu.m 9-Oct-14


F-5 : along grid line E/3

604.80 Cu.m 12-Oct-14


MF - 1

BackFilling and Compaction

- Along Grid Line - 7 - P / -B - 10 2-Oct-14

- Along Grid Line -3 - 6 - / D - G 20-Oct-14

CF - 1 ; Cistern and Holding Tank


Re-bar
Form Works
Concreting 168.89 Cu.m
MF - 2
Re-bar 29-Sep-14
Form Works 29-Sep-14
Concreting 579.15 Cu.m

F-1 : along grid line H'/3


Re-bar 5-Oct-14
Form Works 5-Oct-14
Concreting 5.41 Cu.m

F-5 : along grid line G/3


Re-bar 6-Oct-14
Form Works 6-Oct-14
Concreting 30.51 Cu.m
F-5 : along grid line E/3
Re-bar 8-Oct-14
Form Works 8-Oct-14
Concreting 30.51 Cu.m
MF - 1
Re-bar 14-Oct-14
Form Works 14-Oct-14
Concreting 378.00 Cu.m

Wall of Cistern and Holding Tank


Re-bar 27-Sep-14
Form Works 27-Sep-14
Concreting 272.80 Cu.m
Top of Slab of the Cistern and Holding Tank
Re-bar 1-Oct-14
Form Works 1-Oct-14
Concreting 30.75 Cu.m

Column 1st Lif

Along grid line 9/A' & A ; P / A' & A ( C - 3; C - 5; C - 6 )


Re-bar 27-Sep-14
Form Works 27-Sep-14
Concreting 4.92 Cu.m

Along grid line P /7 - 8 ; F/ 7 - 8 ( SW - 2)


Re-bar 9-Oct-14
Form Works 9-Oct-14
Concreting Cu.m

Along grid line 3/H' ( C- 14)


Re-bar 6-Oct-14
Form Works 6-Oct-14
Concreting 0.60 Cu.m

Along grid line 3/G ( C- 7)


Re-bar 7-Oct-14
Form Works 7-Oct-14
Concreting 1.44 Cu.m

Along grid line 3/E ( C- 7)


Re-bar 9-Oct-14
Form Works 9-Oct-14
Concreting 1.44 Cu.m

Along grid line 6/E&G ( C- 9)


Re-bar 15-Oct-14
Form Works 15-Oct-14
Concreting 2.88 Cu.m

Along grid line 4&5/E-G ( SW-1)


Re-bar 17-Oct-14
Form Works 17-Oct-14
Concreting 10.08 Cu.m
d Forty - Two Storey ( Rio Tower - The Capital )
guez Sr., Brgy. , Kalusugan, Quezon City
eks Look - Ahead
ber 26 - Oct. 9, 2014

Sept. 2
Finish Dur 26 27 28 29 30 1 2 3 4 5 6 7
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue

29-Sep-14 4 275.09625 275.09625 275.09625 275.09625

5-Oct-14 1

7-Oct-14 1

9-Oct-14 1

12-Oct-14 1

13-Oct-14 12

23-Oct-14 4
5-Oct-14 7
5-Oct-14 7
6-Oct-14

6-Oct-14 2
6-Oct-14 2
7-Oct-14

7-Oct-14 2
7-Oct-14 2
8-Oct-14

9-Oct-14 2
9-Oct-14 2
10-Oct-14

15-Oct-14 2
15-Oct-14 2
16-Oct-14

29-Sep-14 3
29-Sep-14 3
30-Sep-14
3-Oct-14 3
3-Oct-14 3
4-Oct-14

28-Sep-14 2
28-Sep-14 2
19-Sep-14

10-Oct-14 2
10-Oct-14 2
11-Oct-14

7-Oct-14 2
7-Oct-14 2
8-Oct-14

8-Oct-14 2
8-Oct-14 2
9-Oct-14

10-Oct-14 2
10-Oct-14 2
11-Oct-14

16-Oct-14 2
16-Oct-14 2
17-Oct-14

18-Oct-14 2
18-Oct-14 2
19-Oct-14
Sept. 26 - Oct. 7, 2014
8 9 10 11 12 13 14 15 16 17 18 19 20 21
Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue
22 23
Wed Thu
24
Fri
: Proposed Forty - Two Storey ( Rio TowerPROJECT
- The Capital )
: E. Rodriguez Sr., Brgy. , Kalusugan, Quezon
LOCATIONCity
: Two Weeks Look - Ahead SUBJECT
: Jan. 5 - 20, 2015 DATE

Jan. 5 - 20, 201


Item Activities QTY Unit Start Finish Dur 5 6 7 8 9 10 11 12
Mon Tue Wed Thu Fri Sat Sun Mon
1 5th Floor
Area 2 / Area 3 of 3rd Floor
Column / Shear Wall 1st Lif
Re-bar 5-Jan-15 6-Jan-15 2
Form Works 5-Jan-15 6-Jan-15 2
Concreting ( 10,000 Psi ) 29.48 Cu.m 7-Jan-15 7-Jan-15 1
3rd floor slab ( 8,000 Psi ) 65.00 Cu.m

Supeded Slab and Beams


Form Works 5-Jan-15 8-Jan-15 4
Re-bar 5-Jan-15 8-Jan-15 4
Concreting 86.79 Cu.m 9-Jan-15 9-Jan-15 1
column ( 10,000Psi ) 9.83 Cu.m
Beams ( 8,000 Psi ) 44.41 Cu.m
Slab ( 8,000 Psi ) 32.56 Cu.m
Area 3

Column / Shear Wall 1st Lif


Re-bar 7-Jan-15 9-Jan-15 3
Form Works 7-Jan-15 10-Jan-15 4
Concreting ( 10,000 Psi ) 38.16 Cu.m 11-Jan-15 10-Jan-15 0

Supeded Slab and Beams


Re-bar 10-Jan-15 12-Jan-15 3
Form Works 10-Jan-15 12-Jan-15 3
Concreting 128.03 Cu.m 13-Jan-15 13-Jan-15 1
column ( 10,000 Psi ) 12.72 Cu.m
Beams ( 8,000 Psi ) 67.25 Cu.m
Slab ( 8,000 Psi ) 48.06 Cu.m

2 6th Floor
Area 1
Column / Shear Wall 1st Lif
Re-bar 9-Jan-15 11-Jan-15 3
Form Works 9-Jan-15 11-Jan-15 3
Concreting ( 10, 000 Ps 39.49 Cu.m 12-Jan-15 12-Jan-15 1

Supeded Slab and Beams


Re-bar 10-Jan-15 19-Jan-15 10
Form Works 10-Jan-15 19-Jan-15 10
Concreting 143.68 Cu.m 20-Jan-15 20-Jan-15 1

Prepared By : Noted By :

Engr. Noe N. Silagan Engr. Elmer A. Tarco


AGA&SONS_PIC AGA&SONS_Project Manager
5 - 20, 2015
13 14 15 16 17 18 19 20
Tue Wed Thu Fri Sat Sun Mon Tue
: Proposed Forty - Two Storey ( Rio Tower PROJECT
- The Capital )
: E. Rodriguez Sr., Brgy. , Kalusugan,LOCATION
Quezon City
: Two Weeks Look - Ahead SUBJECT
: Jan. 12 - 26, 2015 DATE

Jan. 12 - 26, 2
Item Activities QTY Unit Start Finish Dur 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun
1 5th Floor
Area 3
Supeded Slab and Beams
Re-bar 10-Jan-15 14-Jan-15 5
Form Works 10-Jan-15 14-Jan-15 5
Concreting 128.03 Cu.m 14-Jan-15 14-Jan-15 1
column ( 10,000 Psi ) 12.72 Cu.m
Beams ( 8,000 Psi ) 67.25 Cu.m
Slab ( 8,000 Psi ) 48.06 Cu.m
2 6th Floor
Area 1
Column / Shear Wall 1st Lif
Re-bar 12-Jan-15 13-Jan-15 2
Form Works 12-Jan-15 13-Jan-15 2
Concreting ( 10, 000 Psi 39.49 Cu.m 14-Jan-15 14-Jan-15 1
Supeded Slab and Beams
Re-bar 12-Jan-15 16-Jan-15 5
Form Works 12-Jan-15 16-Jan-15 5
Concreting 143.68 Cu.m 17-Jan-15 17-Jan-15 1
Column ( 10,000Psi ) 13.16 Cu.m
Beams ( 8,000 Psi ) 72.90 Cu.m
Slab ( 8,000 Psi ) 57.62 Cu.m
Area 2
Column / Shear Wall 1st Lif
Re-bar 13-Jan-15 16-Jan-15 4
Form Works 13-Jan-15 16-Jan-15 4
Concreting ( 10,000 Psi ) 29.48 Cu.m 17-Jan-15 17-Jan-15 1
Supeded Slab and Beams
Form Works 16-Jan-15 19-Jan-15 4
Re-bar 16-Jan-15 19-Jan-15 4
Concreting 86.79 Cu.m 20-Jan-15 20-Jan-15 1
column ( 10,000Psi ) 9.83 Cu.m
Beams ( 8,000 Psi ) 44.41 Cu.m
Slab ( 8,000 Psi ) 32.56 Cu.m
Area 3
Column / Shear Wall 1st Lif
Re-bar 17-Jan-15 19-Jan-15 3
Form Works 17-Jan-15 19-Jan-15 3
Concreting ( 10,000 Psi ) 38.16 Cu.m 20-Jan-15 20-Jan-15 1
Supeded Slab and Beams
Re-bar 19-Jan-15 25-Jan-15 7
Form Works 19-Jan-15 25-Jan-15 7
Concreting 128.03 Cu.m 26-Jan-15 26-Jan-15 1
column ( 10,000 Psi ) 12.72 Cu.m
Beams ( 8,000 Psi ) 67.25 Cu.m
Slab ( 8,000 Psi ) 48.06 Cu.m

Prepared By : Noted By :

Engr. Noe N. Silagan Engr. Elmer A. Tarco


AGA&SONS_PIC AGA&SONS_Project Manager
Jan. 12 - 26, 2015
19 20 21 22 23 24 25 26
Mon Tue Wed Thu Fri Sat Sun Mon
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
DATE : Feb. 7 - Feb. 17, 2015

Feb. 7 - 17, 2015


Item Activities Start Finish Dur 7 8 9 10 11 12 13 14 15 16 17 18
Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
1 STRUCTURAL WORKS
GROUND FLOOR
Compaction 9-Feb-15 9-Feb-15 1
FTD 9-Feb-15 9-Feb-15 1
Gravel Bedding 9-Feb-15 9-Feb-15 1
Re-bar 9-Feb-15 9-Feb-15 1
Form Works 9-Feb-15 9-Feb-15 1
Concreting 9-Feb-15 9-Feb-15 1
7th Floor
Area 3
Supeded Slab and Beams
Re-bar 7-Feb-15 11-Feb-15 5
Form Works 7-Feb-15 11-Feb-15 5
Concreting 11-Feb-15 11-Feb-15 1
Area 4 ( Swimming pool Area )
Column
Re-bar 8-Feb-15 14-Feb-15 7
Form Works 8-Feb-15 14-Feb-15 7
Concreting 14-Feb-15 14-Feb-15 1
8th Floor
1st Lif of Column ( G.L 9/A-L;L/7-8;A/7-8 )
Re-bar 12-Feb-15 13-Feb-15 2
Form Works 12-Feb-15 13-Feb-15 2
Concreting 13-Feb-15 13-Feb-15 1
1st Lif of Column / Shear Wall (J/7-8;K'/7-8;H/7-8)
Re-bar 13-Feb-15 14-Feb-15 2
Form Works 13-Feb-15 14-Feb-15 2
Concreting 14-Feb-15 14-Feb-15 1
1st Lif of Column / Shear Wall (G/3-8;E/3-6;B/3-6)
Re-bar 15-Feb-15 16-Feb-15 2
Form Works 15-Feb-15 16-Feb-15 2
Concreting 16-Feb-15 16-Feb-15 1

1st Lif of Column / Shear Wall (4/E-G;6/E-G;Elevator Shaf)


Re-bar 15-Feb-15 16-Feb-15 2
Form Works 15-Feb-15 16-Feb-15 2
Concreting 16-Feb-15 16-Feb-15 1
Area 1
Supeded Slab and Beams
Re-bar 14-Feb-15 17-Feb-15 4
Form Works 13-Feb-15 17-Feb-15 5
Concreting 17-Feb-15 17-Feb-15 1

Prepared By : Noted By :

Engr. Noe N. Silagan Engr. Elmer Tercio


AGA&SONS_PIC AGA&SONS_PM
19
Thu
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
Period Cover : Feb. 14 - March 4, 2015
Date : Feb. 14, 2015

Feb. 14 - March 1, 20
Item Activities Start Finish Dur 14 15 16 17 18 19 20 21 22
Sat Sun Mon Tue Wed Thu Fri Sat Sun
1 STRUCTURAL WORKS
GROUND FLOOR
Compaction 15-Feb-15 16-Feb-15 2
FTD 16-Feb-15 16-Feb-15 1
Gravel Bedding 17-Feb-15 17-Feb-15 1
Soil Poisoning 17-Feb-15 17-Feb-15 1
Re-bar 18-Feb-15 18-Feb-15 1
Form Works 18-Feb-15 18-Feb-15 1
Concreting 18-Feb-15 18-Feb-15 1
6th Floor
Stripping Works
Area - 1
Area - 2 16-Feb-15 19-Feb-15 4
7th Floor
Area 4: Suspended Slab
Re-bar 14-Feb-15 14-Feb-15 1
Form Works 14-Feb-15 14-Feb-15 1
Concreting 14-Feb-15 14-Feb-15 1
Area 5: Suspended Slab
Re-bar 14-Feb-15 17-Feb-15 4
Form Works 14-Feb-15 17-Feb-15 4
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
Period Cover : Feb. 14 - March 4, 2015
Date : Feb. 14, 2015

Feb. 14 - March 1, 20
Item Activities Start Finish Dur 14 15 16 17 18 19 20 21 22
Sat Sun Mon Tue Wed Thu Fri Sat Sun

Concreting 17-Feb-15 17-Feb-15 1


Area 6: Suspended Slab
Re-bar 14-Feb-15 22-Feb-15 9
Form Works 14-Feb-15 22-Feb-15 9
Concreting 22-Feb-15 22-Feb-15 1
7th Floor Amenities Level
- Walk Pat
Re-bar 16-Feb-15 18-Feb-15 3
Form Works 16-Feb-15 18-Feb-15 3
Concreting 18-Feb-15 18-Feb-15 1
8th Floor
- 7th - 8th Floor
Area 1: Vertical 1st Lif ( Shear Wall and Column )
Re-bar 16-Feb-15 16-Feb-15 1
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
Period Cover : Feb. 14 - March 4, 2015
Date : Feb. 14, 2015

Feb. 14 - March 1, 20
Item Activities Start Finish Dur 14 15 16 17 18 19 20 21 22
Sat Sun Mon Tue Wed Thu Fri Sat Sun

Form Works 16-Feb-15 16-Feb-15 1


Concreting 16-Feb-15 16-Feb-15 1
Area 2: Vertical 1st Lif ( Shear Wall and Column )
Re-bar 15-Feb-15 19-Feb-15 5
Form Works 15-Feb-15 19-Feb-15 5
Concreting 19-Feb-15 19-Feb-15 1
Area 3: Vertical 1st Lif ( Shear Wall and Column )
Re-bar 18-Feb-15 20-Feb-15 3
Form Works 19-Feb-15 21-Feb-15 3
Concreting 21-Feb-15 21-Feb-15 1
Area 1
Supeded Slab and Beams
Re-bar 14-Feb-15 17-Feb-15 4
Form Works 13-Feb-15 17-Feb-15 5
Concreting 17-Feb-15 17-Feb-15 1
Area 2 : Suspended Slab
Re-bar 18-Feb-15 21-Feb-15 4
Form Works 20-Feb-15 21-Feb-15 2
Concreting 21-Feb-15 21-Feb-15 1
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
Period Cover : Feb. 14 - March 4, 2015
Date : Feb. 14, 2015

Feb. 14 - March 1, 20
Item Activities Start Finish Dur 14 15 16 17 18 19 20 21 22
Sat Sun Mon Tue Wed Thu Fri Sat Sun

Area 3 : Suspended Slab


Re-bar 21-Feb-15 24-Feb-15 4
Form Works 22-Feb-15 24-Feb-15 3
Concreting 24-Feb-15 24-Feb-15 1
2 Archictural Works
2.1 Masonry Works
a.) Installation of CHB
B.) Plastering Works
C. ) Rub - Concrete
2nd floor
2.2 ) Pre-cast Works
a.) Fabrication of Wall Panel
a.1) Ground Floor
R.C Wall ( Cast and Place Method )
a.2 ) 2nd floor
Low wall panel
b.) Installation of Wall Panel
b.1) Ground Floor
R.C Wall ( Cast and Place Method )
PROJECT : Proposed Forty - Two Storey ( Rio Tower - The Capital )
LOCATION : E. Rodriguez Sr., Brgy. , Kalusugan, Quezon City
SUBJECT : Two Weeks Look - Ahead
Period Cover : Feb. 14 - March 4, 2015
Date : Feb. 14, 2015

Feb. 14 - March 1, 20
Item Activities Start Finish Dur 14 15 16 17 18 19 20 21 22
Sat Sun Mon Tue Wed Thu Fri Sat Sun

b.2 ) 2nd floor


Low wall panel
2.3 ) Steel Works
a. ) Installation of steel hand rail
Ground floor to 2nd floor ( Mock - Up )
2nd floor to 3rd floor ( Mock - up )
2.4 ) Painting Works
a. ) Application of Concrete neutralizer
2nd floor

Prepared By : Noted By :

Engr. Noe N. Silagan Engr. Elmer Tercio


AGA&SONS_PIC AGA&SONS_PM
Feb. 14 - March 1, 2015
23 24 25 26 27 28 1 2 3 4
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Feb. 14 - March 1, 2015
23 24 25 26 27 28 1 2 3 4
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Feb. 14 - March 1, 2015
23 24 25 26 27 28 1 2 3 4
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Feb. 14 - March 1, 2015
23 24 25 26 27 28 1 2 3 4
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
Feb. 14 - March 1, 2015
23 24 25 26 27 28 1 2 3 4
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
PROJECT : Proposed Eighteen Sto
LOCATION : Paco, Manila
SUBJECT : Two Weeks Look - Ahe
Period Cover : Sept. 11 - 24, 2016
Date : Jan. 25, 2016- Feb. 4,

Item Activities Start Finish Dur 25


Mon
A STRUCTURAL WORKS

A.1 Sub - Structure

1 Earth Works

- Excavation Works ( along bet. C - D / bet. 1 - 3 ) 25-Jan-16 9-Feb-16 15


- Backfilling and Compaction Works ( along C - D / 5 - 7 ) 25-Jan-16 4-Feb-16 10

2 Pile Cup and Tie Beam


- Along Grid line A/1,2,3 ; C/3,4 ; D/3,4
Form Works
Re - Bar
Concreting

A.2 Super - Structure

1 Area - 1
- Column 1st Lif GL(A,C,D/6,7,8)
Form Works
Re - Bar
Concreting

- Suspended beam and slab


Form Works
Re - Bar
Concreting

Prepared By : Noted By :

Engr. Noe N. Silagan Engr. Milvelle Leyson


PIC _ ASCD P.M _ ASCD
een Storey Residential bldng ( PGMH_MAHOGANY )

ok - Ahead
016
Feb. 4, 2016

Jan. 25, 2016 - Feb. 4, 2016


26 27 28 29 30 31 1 2 3 4 5 6 7
Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun

LEGEND :
EXCAVATION WORKS
BACKFILL AND COMPACTION
FORM WORKS
RE-BAR
CONCRETING WORKS