Summary of Road Opening : Traffic Management Measures for Main Carriageway Opening
Future Road
4 Traffic Management Measures for Main Carriageway Opening 9,626,935.21
Opening :
5 Maintenance Total Maintenance Cost (From 11 March 2017 to 31 August 2017) 1,183,632.91
Sub-total 12,482,407.27
6 Future Road Saving by use of 6000m second hand Precast Concrete Barriers (TCB) available from
(1,308,780.00)
Opening : outside source
Total 11,173,627.27
Notes:
1 Stage 3: Concrete barriers are paid for installation only of second hand Precast Concrete Barrier (TCB), Source from outside
and J&P owned barriers
2 Future Road For every 1000m of second hand barrier used over and above 6000m included above a further saving of
Opening : QAR 218,130 is possible.
3 Overall Precast Concrete Barrier (TCB) = 16,012 m
Quantity Polyethylene Road Safety Barrier = 8,649 m
4 Handing over
Assumed all roads will be handed over by end August 2017
Page 1 of 73
Traffic Management Measures for Main Carriageway Opening
UNIT ESTIMATED
S. No. ITEM DESCRIPTION UNIT QTY. REMARKS
RATE AMOUNT
Stage 1 : Traffic Management Measures for Main Carriageway Opening
Refer Stage 1 - Measurements
1 Traffic Signs ( Multiple Types) NR. 87.00 sum 178,839.73
Refer Stage 1 - Rate Build Ups - Traffic Signs Installation
Refer Stage 1 - Measurements
2 Installation of Polyethylene Road Safety Barrier M. 160.00 160.59 25,694.40
Refer Rate Analysis for Polyethylene Road Safety Barrier
Refer Stage 1 - Measurements
3 Solar Panel Lights NR. 537.00 39.74 21,340.38
Refer Rate Analysis for Solar Warning Light
Refer Stage 1 - Measurements (SC verified the Qty)
4 Supply and Installation of Cones NR. 1,614.00 27.50 44,385.00
Refer Rate Analysis for Traffic Cone
Refer Quoation from TMS: RSA 1 nr @ QAR 5000
5 Stage 3 for detailed design (Review of Shopdrawings) NR. 6.00 5,786.00 34,716.00
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
Subtotal 304,975.51
Removal of Traffic Management Measures for Main Carriageway Opening
1 Removal Traffic Signs ( Multiple Types) NR. 115.00 sum 23,236.23
2 Removal of Polyethylene Road Safety Barrier M. 160.00 24.78 3,964.80
3 Removal Solar Panel Lights NR. 537.00 3.87 2,078.19
4 Removal of Cones NR. 1,614.00 8.40 13,557.60
-
Subtotal 42,836.82
Page 2 of 73
Traffic Management Measures for Main Carriageway Opening
ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 2 : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 94.00 sum 30,149.56 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Stage 2 - Rate Build Ups - Traffic Signs Installation
2 Install Traffic Signs ( Multiple Types) NR. 63.00 sum 42,604.23 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Stage 2 - Rate Build Ups - Traffic Signs Installation
3 Supply and Install Solar Panel Lights NR. 1,285.00 39.74 51,065.90 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
4 Install Solar Panel Lights NR. 537.00 3.87 2,078.19 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
5 Supply and Installation of Cones NR. 4,665.00 27.50 128,287.50 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
6 Installation of Cones NR. 1,614.00 8.40 13,557.60 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
7 Stage 3 for detailed design (Review of Shopdrawings) NR. 6.00 5,786.00 34,716.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
Subtotal 302,458.98
Page 3 of 73
Traffic Management Measures for Main Carriageway Opening
ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 3 : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 5.00 sum 7,100.71 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
2 Install Traffic Signs ( Multiple Types) NR. 74.00 sum 41,184.08 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
Total number of street lighting poles to be protected = 386 nrs
No. of barriers required (2 nrs for each pole) = 386 x 2 = 772 nrs
Installation only of second hand Precast Concrete Barrier (TCB)
3 M. 881.60 253.67 223,635.47 Available no. of barriers with J&P = 482 nrs
Source from outside source (to protect the street lighting poles)
Total length of the balance barriers required = 290 x 3.04 = 881.60m
Refer Rate Analysis for Precast Concrete Barrier
Installation only of second hand Precast Concrete Barrier (TCB) Available no. of barriers with J&P = 482 nrs
J&P owned barriers to protect the street lighting poles M. 1,465.28 18.85 27,620.53 Total length of the balance barriers required = 482 x 3.04 = 1,465.28m
= 482 nrs x 3.04m = 1,465.28m Refer Rate Analysis for Precast Concrete Barrier
4 Supply and Installation of Polyethylene Road Safety Barrier M. 2,840.00 160.59 456,075.60 Qty as given by J&P Site Engineer.
Refer Rate Analysis for Polyethylene Road Safety Barrier
5 Installation of Polyethylene Road Safety Barrier M. 160.00 24.78 3,964.80 Qty as given by J&P Site Engineer.
Refer Rate Analysis for Polyethylene Road Safety Barrier
6 Supply and Install Solar Panel Flashlights NR. 463.00 39.74 18,399.62 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
7 Install Solar Panel Flashlights NR. 537.00 3.87 2,078.19 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
Page 4 of 73
Traffic Management Measures for Main Carriageway Opening
ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 3 : Traffic Management Measures for Main Carriageway Opening
8 Installation of Safety Cones NR. 500.00 8.40 4,200.00 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
9 Stage 3 Road Safety Audit NR. 6.00 5,786.00 34,716.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
10 Stage 4 Road Safety Audit NR. 6.00 13,886.40 83,318.40 Refer Quoation from TMS: RSA 1 nr @ QAR 12000
Total Cost = QAR 12000 + 15.72% OH&P = QAR 13886.40
Subtotal 902,293.40
Page 5 of 73
Traffic Management Measures for Main Carriageway Opening
ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Future Road Opening : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 173.00 sum 316,874.09 Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
2 Supply and Installation of Precast Concrete Barrier (TCB) M. 16,012.00 471.80 7,554,461.60 Qty taken from the Barrier Layout for Future Road Opening
Refer Rate Analysis for Precast Concrete Barrier
3 Supply and Installation of Polyethylene Road Safety Barrier M. 5,649.00 160.59 907,172.91 Qty taken from the Barrier Layout for Future Road Opening
Out 8649nr of barriers required 3000nr barriers are from Stage 3.
Refer Rate Analysis for Polyethylene Road Safety Barrier
4 Installation Only of Polyethylene Road Safety Barrier M. 3,000.00 24.78 74,340.00 3000nr barriers from Stage 3.
Refer Rate Analysis for Polyethylene Road Safety Barrier
4 Supply and Install Solar Panel Flashlights NR. 8,221.00 39.74 326,702.54 Qty given by J&P Site Engineer (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
5 Supply and Installation of Safety Cones NR. 5,000.00 27.50 137,500.00 Qty given by J&P Site Engineer (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
6 Stage 3 Road Safety Audit NR. 12.00 5,786.00 69,432.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
7 Stage 4 Road Safety Audit NR. 12.00 13,886.40 166,636.80 Refer Quoation from TMS: RSA 1 nr @ QAR 12000
Total Cost = QAR 12000 + 15.72% OH&P = QAR 13886.40
8 Double Handling sum 1.00 73,815.27 73,815.27
Subtotal 9,626,935.21
Page 6 of 73
Traffic Management Measures for Main Carriageway Opening
Page 7 of 73
Traffic Management Measures for Main Carriageway Opening
Maintenance Cost
Replacement Cost
30% of the total material cost for flash lights 16,944.60
30% of the total material cost for cones 31,081.05
Total Maintenance Cost for Stage 2 48,025.65 48,025.65
Maintenance Cost
4 labourers @ QAR 15 (G/DS/3/G),
38,520.00
for 107 days (107 x 6 hrs) = QAR (4 x 15 x 107 x 6)
1 Water Bowser @ QAR 120 (G/DS/8/C),
77,040.00
for 107 days (107 x 6 hrs) = QAR (1 x 120 x 107 x 6)
1 Truck Mounted Attenuator (TMA) @ QAR 306.25,
196,612.50
for 107 days (107 x 6 hrs) = QAR (1 x 306.25 x 107 x 6)
Sub-total 1 312,172.50
Add 15.72% of Overhead and Profit 49,073.52
Sub-total 2 361,246.02
Replacement Cost
10% of the total material cost for PE barriers 36,183.00
30% of the total material cost for flash lights 9,300.00
30% of the total material cost for cones 2,475.00
Total Maintenance Cost for Stage 3 409,204.02 409,204.02
4. Future road opening (From 1 May 2017 to 31 August 2017, 99 working days) 3.73
Maintenance Cost
4 labourers @ QAR 15 (G/DS/3/G), 59,400.00
for 99 days (99 x 10 hrs) = QAR (4 x 15 x 99 x 10)
1 Water Bowser @ QAR 120 (G/DS/8/C), 118,800.00
for 99 days (99 x 10 hrs) = QAR (1 x 120 x 99 x 10)
1 Truck Mounted Attenuator (TMA) @ QAR 306.25,
303,187.50
for 99 days (99 x 10 hrs) = QAR (1 x 306.25 x 99 x 10)
Sub-total 1 481,387.50
Add 15.72% of Overhead and Profit 75,674.12
Sub-total 2 557,061.62
Replacement Cost
10% of the total material cost for PE barriers 68,132.59
30% of the total material cost for flash lights 76,455.30
30% of the total material cost for cones 24,750.00
Total Maintenance Cost for Future Road Openings 726,399.51 726,399.51
Page 8 of 73
Traffic Management Measures for Main Carriageway Opening
Rate Analysis for Pre-cast Concrete Barrier, Type M, Type M, Size 0.15/0.32m x 1.345m x 3.04m
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate Remarks
10.93% 4.79%
Precast Concrete Barrier (3.04m Length)
Precast concrete barrier Type M, Size 0.15/0.32m x 1.345m Refer CC's
nr 1.00 - - 1,149.12
x 3.04m LPO.
Reflective Strips m 3.04 - - 33.00
Cost of installation including transportation within the Site
sum 1.00 9.50 47.81 -
(Loading, Transporting and Unloading)
Page 9 of 73
Traffic Management Measures for Main Carriageway Opening
Page 10 of 73
Traffic Management Measures for Main Carriageway Opening
Rate Analysis for Polyethylene Road Safety Barrier, Joint Type #WR 1027, Size: 2000mm(L)x500mm(W)x800mm(H)
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate Remarks
10.93% 4.79%
Polyethylene Road Safety Barrier (2.00m Length)
Polyethylene Road Safety Barrier, Joint Type #WR 1027, Refer CC's
nr 1.00 - - 195.00
Size: 2000mm(L)x500mm(W)x800mm(H), Colour RED. LPO.
Reflective Strips m 2.00 - - 33.00
Cost of installation including transportation within the Site
nr 1.00 7.20 29.13 -
(Loading, Transporting and Unloading)
Filling in the PE Barrier with dune sand and water (5% of
sum 1.00 - - 13.22
the base cost)
Unit Rate / nr Install Polyethylene Road Safety Barrier (2.00m Length) nr 1.00 7.20 29.13 13.22 - - 49.55
Unit Rate / m Install Polyethylene Road Safety Barrier (2.00m Length) m 1.00 24.78
Page 11 of 73
Traffic Management Measures for Main Carriageway Opening
Cost Break-down for the Installation of Polyethylene Road Safety Barrier (2.00m Length)
Page 12 of 73
Traffic Management Measures for Main Carriageway Opening
10.93% 4.79%
Solar Warning Light
Solar Warning Light, 2way Flashing Solar and Battery Road Refer CC's
nr 1.00 - - 31.00 3.39 1.48 35.87
Maxi Light. LPO.
Refer CC's
Installation of Solar Warning Light nr 1.00 3.34 - - 0.37 0.16 3.87
Rate
Unit Rate / nr Supply and install Solar Warning Light nr 1.00 3.34 - 31.00 3.76 1.64 39.74
Page 13 of 73
Traffic Management Measures for Main Carriageway Opening
10.93% 4.79%
Traffic Cone (5kg)
Supply and install Traffic Cone, Red and White, Height 1m, Refer CC's
nr 1.00 1.70 5.56 16.50
Weight 5kg LPO.
Unit Rate / nr Supply and install Traffic Cone nr 1.00 1.70 5.56 16.50 2.60 1.14 27.50
Unit Rate / nr Install Traffic Cone nr 1.00 1.70 5.56 - 0.79 0.35 8.40
Page 14 of 73
Traffic Management Measures for Main Carriageway Opening
01. Traffic Cone, Red and White, Height 1m, Weight 5kg nr 200.00 16.50 3,300.00 Refer CC's LPO.
Page 15 of 73
Traffic Management Measures for Main Carriageway Opening
Rate Analysis for F-Shape Regid Concrete Barrier (3.04m Length), SGM 100b
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate
10.93% 4.79%
F-Shape Regid Concrete Barrier (3.04m Length)
Precast concrete barrier Type M, Size 0.15/0.32m x 1.345m
nr 1.00 - - 1,149.12 Refer CC's LPO.
x 3.04m
Transportation Cost with the Site (Loading, Transporting
sum 1.00 17.68 24.67 -
and Unloading)
Reflective Strips m 3.00 - - 33.00
Page 16 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.
QAR. 178,839.73
Page 17 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
QAR. -
Collection
Page 1 178,839.73
Page 2 -
Page 18 of 73
Temporary Traffic Signs
6/1/2017
Page 19 of 73 3/5
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.
Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06
UF : Utilization Factor
Page 20 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.
Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81
UF : Utilization Factor
Page 21 of 73
Traffic Management Measures for Main Carriageway Opening
00032 CA
00026 CA
00023 CA
00030 CA
00025 CA
00031 CA
TOTAL
NO OF
LANES
QTY.
Unit
STAGE 1 DESCRIPTION REMARKS
CC
Supply and install temporary traffice signs including all necessary fitings complete and as detailed on Drawings and describe in Qatar traffice Manual
Sign Ref. R108-R
1 (Size: 1200mm) nr 26 4.00 2.00 14.00 2.00 22.00
Sign Ref. R108-L
2 (Size: 1200mm) nr 4 - 4.00 4.00
Sign Ref. T200
3 (Size: 1200mm) nr 12 2.00 1.00 4.00 1.00 1.00 9.00
BARRIERS
3 Installation of Polyethylene Road Safety Barrier m 160 20.00 100.00 20.00 140.00
Contractor QS on
receives verbal inst from
6 Supply & Instalation Of Cones Nr 1614 1,614.00 site engineer (Henok)
Page 22 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.
Sign Ref. R108-R Only Installation
1 nr 23 710.07 16,331.62
(Size: 1200mm)
Page 23 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
-
18 Electronic Arrow Board T302 Only installation Nr 14 710.07 9,940.99
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 1 1,855.70 1,855.70
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 1 1,855.70 1,855.70
standard)
Sign Ref. (100m)
21 nr - 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr - 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 100
23 nr - 710.07 0.00
(Size: 1200mm)
Sign Ref. Give Way
24 nr - 710.07 0.00
(Size: 1200mm)
QAR. 13,652.39
Collection
Page 24 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Page 25 of 73
Temporary Traffic Signs
18 Electronic Arrow Board T302 Only installation no 613.61 613.61 96.46 710.07 -
Barriers
6/1/2017
Page 26 of 73 4/7
Temporary Traffic Signs
2 way flashing Solar and Battery road maxi light 1285 nr 42.29
2 way flashing Solar and Battery road maxi light Only installation 537 3.87
LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80
Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00
6/1/2017
Page 27 of 73 5/7
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.
Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06
UF : Utilization Factor
Page 28 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.
Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81
UF : Utilization Factor
Page 29 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Traffic Signs
Removal temporary traffic signs including all necessary fittings
complete as detailed on Drawings and described in Qatar Traffic
Manual.
Page 30 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
-
18 Electronic Arrow Board T302 Nr 14 378.85 5,303.92
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 2 378.85 757.70
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 4 378.85 1,515.41
standard)
Sign Ref. (100m)
21 nr 4.00 378.85 1,515.41
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr 4.00 378.85 1,515.41
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 100
23 nr 36.00 378.85 13,638.66
(Size: 1200mm)
Sign Ref. Give Way
24 nr 8.00 378.85 3,030.81
(Size: 1200mm)
QAR. 27,277.32
Collection
Page 1 32,202.40
Page 2 27,277.32
Page 31 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
BARRIERS
Collection
Page 1 7,051.14
Page 32 of 73
Temporary Traffic Signs
18 Electronic Arrow Board T302 Only installation 14 no 327.39 327.39 51.47 378.85 5,303.92
Barriers
6/1/2017
Page 33 of 73 4/8
Temporary Traffic Signs
2 way flashing Solar and Battery road maxi light 1285 nr 3.87
2 way flashing Solar and Battery road maxi light Only installation 537 3.87
LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80
Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00
6/1/2017
Page 34 of 73 5/8
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign Removal
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.
Sand bag m - Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. - Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. - Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. - Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06
UF : Utilization Factor
Page 35 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.
Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81
UF : Utilization Factor
Page 36 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Removal 2 way flashing Solar and Battery road maxi light
- Traffic Management Measures
BOQ Qty: 1,822.00 No
Performance rate : 55.00 No/day
6.88 No/hr.
UF : Utilization Factor
Page 37 of 73
Traffic Management Measures for Main Carriageway Opening
00032 CA
00026 CA
00023 CA
00030 CA
00025 CA
00031 CA
TOTAL
NO OF
LANES
QTY.
Unit
STAGE 2 DESCRIPTION REMARKS
CC
Supply and install temporary traffic signs including all necessary fittings complete as detailed on Drawings and described in Qatar Traffic Manual.
-
Sign Ref. R108-R Only Installation
1 (Size: 1200mm) nr 26 2.00 1.00 12.00 2.00 6.00 23.00
Sign Ref. R108-L Only Installation
2 (Size: 1200mm) nr 4 4.00 2.00 1.00 7.00
Sign Ref. T200
3 (Size: 1200mm) nr 13 2.00 1.00 2.00 1.00 1.00 7.00
Sign Ref. T224 (600m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
4 Plank) nr 2 1.00 1.00 6 lanes
Page 38 of 73
Traffic Management Measures for Main Carriageway Opening
00032 CA
00026 CA
00023 CA
00030 CA
00025 CA
00031 CA
TOTAL
NO OF
LANES
QTY.
Unit
STAGE 2 DESCRIPTION REMARKS
CC
BARRIERS
Page 39 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Page 40 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
QAR. 5,680.56
Page 41 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Collection
Page 1 42,604.24
Page 2 5,680.56
Page 42 of 73
Temporary Traffic Signs
18 Electronic Arrow Board T302 Only installation 14 no 613.61 613.61 96.46 710.07 9,940.99
6/1/2017
Page 43 of 73 4/6
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.
Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06
UF : Utilization Factor
Page 44 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.
Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81
UF : Utilization Factor
Page 45 of 73
Traffic Management Measures for Main Carriageway Opening
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
REMOVED
REMOVED
REMOVED
REMOVED
REMOVED
REMOVED
NO OF LANES
RE INST.
RE INST.
RE INST.
RE INST.
RE INST.
RE INST.
CC Stage 2
TOTAL QUANTITY
UNIT
STAGE 2 DESCRIPTION REMARKS
Supply and install temporary traffic signs including all necessary fittings complete as detailed on Drawings and described in Qatar Traffic Manual. - - -
- - -
Sign Ref. R108-R Only Installation
1 (Size: 1200mm) nr 26 2 - 1.00 4.00 8.00 2.00 6.00 13.00 10.00 -
Sign Ref. R108-L Only Installation
2 (Size: 1200mm) nr 4 4.00 2.00 1.00 3.00 4.00 -
Sign Ref. T200
3 (Size: 1200mm) nr 13 2.00 1.00 2.00 1.00 1.00 2.00 5.00 -
Sign Ref. T224 (600m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
4 Plank) nr 2 1.00 1.00 - - 6 lanes
Page 46 of 73
Traffic Management Measures for Main Carriageway Opening
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
SUPPLY/INST
REMOVED
REMOVED
REMOVED
REMOVED
REMOVED
REMOVED
NO OF LANES
RE INST.
RE INST.
RE INST.
RE INST.
RE INST.
RE INST.
CC Stage 2
TOTAL QUANTITY
UNIT
STAGE 2 DESCRIPTION REMARKS
BARRIERS
Page 47 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.
QAR. 248,011.71
Page 48 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Page 49 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV
Collection
Page 1 248,011.71
Page 2 68,862.39
Page 50 of 73
Temporary Traffic Signs
Barriers
6/1/2017
Page 51 of 73 4/7
Temporary Traffic Signs
LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80
Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00
6/1/2017
Page 52 of 73 5/7
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.
Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06
UF : Utilization Factor
Page 53 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.
Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81
UF : Utilization Factor
Page 54 of 73
1149.12
Page 55 of 73
Page 56 of 73
Page 57 of 73
Page 58 of 73
Page 59 of 73
Page 60 of 73
Page 61 of 73
Page 62 of 73
Page 63 of 73
Page 64 of 73
Page 65 of 73
J&P (OVERSEAS) LTD 09 MAY - 2017
P.O. Box 19389
Doha, State of Qatar
Quotation 1374/09-05
All Rates are subject to the attached standard terms and conditions
Validity: Our prices will remain valid for 30 days
Regards,
SHEBIN M. A.
Accounting Department, TMS
TMSQatar
Terms and Conditions of Contract
1. These terms and conditions constitute a contract between Traffic Management Solutions (TMS) and, (The
Client) for the supply of services as per the attached quotation / pricing schedule.
2. The Client is deemed to accept these conditions by virtue of your written or verbal instruction, interview
or engagement of TMS, its workforce, associated companies or nominated sub-contractors.
3. All conditions are deemed accepted and no variations will be valid or accepted unless agreed in writing
with a Senior Manager of TMS.
4. Prior to engagement or assignment, TMS will confirm the details of the contract including rates, service to
be provided etc. in writing for the Clients approval.
5. The client should issue an official purchase order to formally accept and engage TMS but where this
process is not in operation or is not practicable, TMS will accept and confirm a verbal instruction.
6. The client agrees to pay in full the rates quoted and charged by TMS as notified prior to or at
commencement of the engagement/assignment.
7. No deduction for retention will be made in any circumstance.
8. To be agreed but generally a minimum 10% advanced payment will be required.
Service Agreements
TMSQatar
J&P (OVERSEAS) LTD 01-FEBRUARY-2017
P.O. Box 19389
Doha, State of Qatar
Quotation 1271/01-02
All Rates are subject to the attached standard terms and conditions
Validity: Our prices will remain valid for 30 days
Regards,
SHEBIN M. A.
Accounting Department, TMS
TMSQatar
Terms and Conditions of Contract
1. These terms and conditions constitute a contract between Traffic Management Solutions (TMS) and, (The
Client) for the supply of services as per the attached quotation / pricing schedule.
2. The Client is deemed to accept these conditions by virtue of your written or verbal instruction, interview
or engagement of TMS, its workforce, associated companies or nominated sub-contractors.
3. All conditions are deemed accepted and no variations will be valid or accepted unless agreed in writing
with a Senior Manager of TMS.
4. Prior to engagement or assignment, TMS will confirm the details of the contract including rates, service to
be provided etc. in writing for the Clients approval.
5. The client should issue an official purchase order to formally accept and engage TMS but where this
process is not in operation or is not practicable, TMS will accept and confirm a verbal instruction.
6. The client agrees to pay in full the rates quoted and charged by TMS as notified prior to or at
commencement of the engagement/assignment.
7. No deduction for retention will be made in any circumstance.
8. To be agreed but generally a minimum 10% advanced payment will be required.
Service Agreements
TMSQatar
Page 70 of 73
Page 71 of 73
Page 72 of 73
Page 73 of 73