BSC6900 UMTS

V900R014C00

N68E-21-N Cabinet Installation Guide

Issue 01
Date 2012-04-26

HUAWEI TECHNOLOGIES CO., LTD.


Copyright Huawei Technologies Co., Ltd. 2012. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior written
consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or representations
of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute the warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website: http://www.huawei.com
Email: support@huawei.com

Issue 01 (2012-04-26) Huawei Proprietary and Confidential i


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide About This Document

About This Document

Overview
This document contains information related to the installation of the N68E-21-N cabinet. The
information consists of how to install the cabinet, accessories, external power cables, and PGND
cables; how to attach engineering labels to the power cables and PGND cables; other reference
information.

Product Version
The following table lists the product version related to this document.

Product Name Product Version

BSC6900 V900R014C00

Intended Audience
This document is intended for installation personnel.

Organization
1 Overview of the N68E-21-N Cabinet
The N68E-21-N cabinet features a modular design. It provides sufficient space for installing
devices such as subracks and power distribution box to facilitate capacity expansion and
maintenance.
2 Changes in the N68E-21-N Cabinet Installation Guide
This chapter describes the changes in the N68E-21-N Cabinet Installation Guide.
3 Preparing for the N68E-21-N Cabinet Installation
Before installing the N68E-21-N cabinet, you need to unpack the cases and check the items in
the cases. Ensure that all the tools required for the installation are available.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential ii


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide About This Document

4 Installing the N68E-21-N Cabinet

The N68E-21-N cabinet installation involves installing the cabinet, accessories, external power
cables, and PGND cables. It also involves checking the power-on status of the cabinet, and
attaching engineering labels to the cabinet, external power cables, and PGND cables.

5 Installing the N68E-21-N Cabinet on a Concrete Floor

This chapter describes how to install the N68E-21-N cabinet on a concrete floor.

6 Installing the N68E-21-N Cabinet on an ESD Floor

This chapter describes how to install the N68E-21-N cabinet on an ESD floor.

7 Installing the Power Cables and PGND Cables for the N68E-21-N Cabinet

This section describes how to install the power cables and PGND cables between the N68E-21-
N cabinet and the power distribution frame (PDF). When combining the N68E-21-N cabinets,
you also need to install the PGND cables between the cabinets.

8 Installing the Accessories for the N68E-21-N Cabinet

This chapter describes how to install the front and back doors as well as side panels for the
N68E-21-N cabinet and how to install the PGND cables for the doors and side panels.

9 Attaching the Engineering Labels to the Cabinets

This chapter describes how to attach the engineering labels, including row and column labels,
to the cabinets.

10 Attaching the Engineering Labels to the Power Cables and PGND Cables

After installing the power cables and PGND cables, you should remove the temporary labels
from the cables and then attach the engineering labels.

11 Checklist for the Cabinet Installation

This chapter describes the items and specifications for checking the cabinet installation.

Conventions
Symbol Conventions

The symbols that may be found in this document are defined as follows.

Symbol Description

Indicates a hazard with a high level of risk, which if not


avoided, will result in death or serious injury.

Indicates a hazard with a medium or low level of risk, which


if not avoided, could result in minor or moderate injury.

Indicates a potentially hazardous situation, which if not


avoided, could result in equipment damage, data loss,
performance degradation, or unexpected results.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential iii


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide About This Document

Symbol Description

Indicates a tip that may help you solve a problem or save


time.

Provides additional information to emphasize or supplement


important points of the main text.

General Conventions
The general conventions that may be found in this document are defined as follows.

Convention Description

Times New Roman Normal paragraphs are in Times New Roman.

Boldface Names of files, directories, folders, and users are in


boldface. For example, log in as user root.

Italic Book titles are in italics.


Courier New Examples of information displayed on the screen are in
Courier New.

Command Conventions
The command conventions that may be found in this document are defined as follows.

Convention Description

Boldface The keywords of a command line are in boldface.

Italic Command arguments are in italics.

[] Items (keywords or arguments) in brackets [ ] are optional.

{ x | y | ... } Optional items are grouped in braces and separated by


vertical bars. One item is selected.

[ x | y | ... ] Optional items are grouped in brackets and separated by


vertical bars. One item is selected or no item is selected.

{ x | y | ... }* Optional items are grouped in braces and separated by


vertical bars. A minimum of one item or a maximum of all
items can be selected.

[ x | y | ... ]* Optional items are grouped in brackets and separated by


vertical bars. Several items or no item can be selected.

GUI Conventions
The GUI conventions that may be found in this document are defined as follows.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential iv


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide About This Document

Convention Description

Boldface Buttons, menus, parameters, tabs, window, and dialog titles


are in boldface. For example, click OK.

> Multi-level menus are in boldface and separated by the ">"


signs. For example, choose File > Create > Folder.

Keyboard Operations
The keyboard operations that may be found in this document are defined as follows.

Format Description

Key Press the key. For example, press Enter and press Tab.

Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt
+A means the three keys should be pressed concurrently.

Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A means
the two keys should be pressed in turn.

Mouse Operations
The mouse operations that may be found in this document are defined as follows.

Action Description

Click Select and release the primary mouse button without moving
the pointer.

Double-click Press the primary mouse button twice continuously and


quickly without moving the pointer.

Drag Press and hold the primary mouse button and move the
pointer to a certain position.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential v


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide Contents

Contents

About This Document.....................................................................................................................ii


1 Overview of the N68E-21-N Cabinet.........................................................................................1
2 Changes in the N68E-21-N Cabinet Installation Guide.........................................................3
3 Preparing for the N68E-21-N Cabinet Installation..................................................................4
3.1 Unpacking the Cases and Checking the Items....................................................................................................5
3.2 Tools Required for Installing the N68E-21-N Cabinet....................................................................................10

4 Installing the N68E-21-N Cabinet............................................................................................12


5 Installing the N68E-21-N Cabinet on a Concrete Floor........................................................13
5.1 Materials Required for Installing the N68E-21-N Cabinet on a Concrete Floor..............................................14
5.2 Positioning the N68E-21-N Cabinet on a Concrete Floor................................................................................14
5.3 Securing the N68E-21-N Cabinet to the Concrete Floor..................................................................................20
5.4 Combining the N68E-21-N Cabinets...............................................................................................................26

6 Installing the N68E-21-N Cabinet on an ESD Floor.............................................................29


6.1 Materials Required for Installing the N68E-21-N Cabinet on the ESD Floor.................................................31
6.2 Introduction to the Shockproof Support...........................................................................................................31
6.2.1 Shockproof Support Assembly................................................................................................................31
6.2.2 Fastening the Lock Catches on the Shockproof Support Assembly........................................................33
6.2.3 Cutting Guide Rails for the Shockproof Support....................................................................................34
6.3 Positioning the N68E-21-N Cabinet on the ESD Floor....................................................................................37
6.4 Assembling the Shockproof Support................................................................................................................42
6.5 Installing Floating Nuts on the Shockproof Support........................................................................................48
6.6 Securing the Shockproof Support on the Concrete Floor.................................................................................49
6.7 Securing the N68E-21-N Cabinet on the ESD Floor........................................................................................52
6.8 Combining the N68E-21-N Cabinets...............................................................................................................59

7 Installing the Power Cables and PGND Cables for the N68E-21-N Cabinet..................61
7.1 Power Cables and PGND Cables to Be Installed.............................................................................................63
7.1.1 Power Cables...........................................................................................................................................63
7.1.2 PGND Cables..........................................................................................................................................67
7.2 Power and PGND Cable Connections..............................................................................................................68
7.3 Principles of Routing and Binding the Power Cables and PGND Cables........................................................69

Issue 01 (2012-04-26) Huawei Proprietary and Confidential vi


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide Contents

7.4 Installing the Power Cables and PGND Cables Between the N68E-21-N Cabinet and the PDF....................70
7.4.1 Overhead and Underfloor Cabling Modes...............................................................................................70
7.4.2 Installing the Power Cables and PGND Cables Between the N68E-21-N Cabinet and the PDF in Overhead
Cabling Mode...................................................................................................................................................73
7.4.3 Installing the Power Cables and PGND Cables Between the N68E-21-N Cabinet and the PDF in
Underfloor Cabling Mode................................................................................................................................75
7.5 Installing the PGND Cables Between Adjacent N68E-21-N Cabinets............................................................79
7.6 Checking the Power-on Status..........................................................................................................................80

8 Installing the Accessories for the N68E-21-N Cabinet.........................................................82


8.1 Accessories to Be Installed for the N68E-21-N Cabinet..................................................................................83
8.2 Installing the Side Panels for the N68E-21-N Cabinet.....................................................................................83
8.3 Installing the Front and Back Doors for the N68E-21-N Cabinet....................................................................85
8.4 Installing the PGND Cables for the Doors and Side Panels of the N68E-21-N Cabinet.................................87

9 Attaching the Engineering Labels to the Cabinets...............................................................89


10 Attaching the Engineering Labels to the Power Cables and PGND Cables..................91
11 Checklist for the Cabinet Installation...................................................................................92

Issue 01 (2012-04-26) Huawei Proprietary and Confidential vii


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 1 Overview of the N68E-21-N Cabinet

1 Overview of the N68E-21-N Cabinet

The N68E-21-N cabinet features a modular design. It provides sufficient space for installing
devices such as subracks and power distribution box to facilitate capacity expansion and
maintenance.

Appearance of the N68E-21-N Cabinet


Figure 1-1 shows the N68E-21-N cabinet.

Figure 1-1 Appearance of the N68E-21-N cabinet

N68E-21-N Cabinet Engineering Specifications


Table 1-1 describes N68E-21-N cabinet engineering specifications.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 1


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 1 Overview of the N68E-21-N Cabinet

Table 1-1 N68E-21-N cabinet engineering specifications


Item Value

Dimension (H x W x D) 2130 mm (height) x 600 mm (width) x 800 mm


(depth)

Height of the available space 44 U

Weight Rack: 105 kg; empty cabinet: 155 kg; full


configuration: 380 kg

Power supply Four routes of -48 V DC power supply

EMC l Meets the requirements of GR 1089


l Meets the requirements of ETSI EN300 386
l Meets the requirements of Council directive
89/336/EEC

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 2


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 2 Changes in the N68E-21-N Cabinet Installation Guide

2 Changes in the N68E-21-N Cabinet


Installation Guide

This chapter describes the changes in the N68E-21-N Cabinet Installation Guide.

01 (2012-04-26)
This is the first commercial release of V900R014C00.
Compared with Draft A (2012-02-15), this issue does not include any new topics.
Compared with Draft A (2012-02-15), this issue does not incorporate any changes.
Compared with Draft A (2012-02-15), this issue does not exclude any topics.

Draft A (2012-02-15)
This is the Draft A release of V900R014C00.
Compared with V900R013C00 01 (2011-04-25), this issue does not include any new topics.
Compared with V900R013C00 01 (2011-04-25), this issue does not incorporate any changes.
Compared with V900R013C00 01 (2011-04-25), this issue does not exclude any topics.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 3


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

3 Preparing for the N68E-21-N Cabinet


Installation

About This Chapter

Before installing the N68E-21-N cabinet, you need to unpack the cases and check the items in
the cases. Ensure that all the tools required for the installation are available.

3.1 Unpacking the Cases and Checking the Items


This section describes how to unpack the cases and check the items in the cases to facilitate
subsequent cabinet installation.
3.2 Tools Required for Installing the N68E-21-N Cabinet
The tools required for installing the N68E-21-N cabinet are tools for measuring, marking,
drilling, and fastening, small tools, auxiliary tools, meters, and some special tools.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 4


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

3.1 Unpacking the Cases and Checking the Items


This section describes how to unpack the cases and check the items in the cases to facilitate
subsequent cabinet installation.

Prerequisites
l Site preparation for the installation is complete.
l The cases that contain the cabinets and components are delivered to the site.

Context
l When carrying or placing the equipment, you should ensure that it does not collide with
doors, walls, shelves, or other objects.
l When transporting or installing the equipment, components, or parts, you should avoid
touching their uncoated metal surfaces with sweaty or dirty gloves.

Procedure
Step 1 Unload the cases.

CAUTION
When unloading the cases, you should place the cases in sequence. Ensure that the labels on the
cases face the same direction.

Step 2 Check whether the number of cases on site matches the Packing List and whether the place of
delivery is the same as the actual installation place.

If... Then...

The number of cases on site matches that in the Packing List Go to Step 4.

The number of cases on site does not match that in the Packing List Go to Step 3.

Step 3 Stop unpacking the cases. Ask the project supervisor to send the Cargo Problems Report that is
signed by the customer to the local Huawei office within three days.

Step 4 Check whether the cases are intact.

If... Then...

Any case is seriously damaged or soaked Go to Step 5.

The cases are intact Go to Step 6.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 5


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

Step 5 Stop unpacking the cases, find out the causes, and contact the local Huawei office to further
handle the problem.

CAUTION
To protect the equipment and find out the causes, perform the following actions: Move the
unpacked equipment indoors for proper storage, take photos of the storage environment, the
rusted or corroded equipment, packing cases, and packing materials. Keep these photos for future
verification. Store the packing cases and materials properly.

Step 6 Unpack the wooden cases.

CAUTION
l Before unpacking, move the wooden cases into or close to the equipment room if enough
space is available. This prevents damage to the cabinets during the transportation.
l When you unpack the wooden cases, unpack the one containing the packing list first. Then,
you can find items rapidly according to the names, codes, positions, and quantities in the
Packing List.
l The following description takes the wooden case that contains the cabinet as an example.
The methods of unpacking other types of wooden cases are similar.

1. Place the wooden case on the ground. Ensure that the side with the wooden frame faces the
bottom.
2. Use a wrench, a flat-head screwdriver, or a claw hammer to straighten the tongues on the
four sides of the cover, as shown in Figure 3-1.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 6


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

Figure 3-1 Straightening the tongue

3. Remove the cover. If the wooden case contains a carton, take out the carton and then open
it according to Step 7. If the wooden case contains a cabinet, go to the next step. See Figure
3-2.

Figure 3-2 Removing the cover

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 7


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

4. Use the same method to remove the side boards from the wooden case, as shown in Figure
3-3.

Figure 3-3 Removing side boards

5. Erect the cabinet with the BOTTOM side down.

CAUTION
This operation needs three to five installers. Prevent the cabinet from falling during the
erection to avoid personnel injury.

6. Remove the bottom of the case, that is, the side with the wooden frame.
7. Remove the packing foam from the corners and edges of the cabinet.
8. Remove the vacuum plastic bag.
Step 7 Unpack the carton, as shown in Figure 3-4.

Figure 3-4 Unpacking a carton

1 Carton label 2 Strap 3 Pressure-sensitive tape

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 8


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

4 Foam plate 5 Board label 6 Board

1. Check the types and quantities of the items in the carton according to the carton label.
2. Use diagonal pliers to cut the straps.
3. Rip the tape along the joint seams by using the paper knife. Do not insert the knife too deep,
or else the items may be damaged.
4. Unpack the carton and take out the items.

Step 8 Unpack boards.

CAUTION
l Electronic components are extremely sensitive to static electricity. When unpacking the
boards, wear an ESD wrist strap or a pair of ESD gloves properly.
l The ESD bag contains desiccant to keep the bag dry. When taking the board from a cold dry
place to a hot damp place, wait at least 30 minutes before unpacking. Otherwise, moisture
condensed on the board surface may damage the board.

1. Check that no evident damage is on the board packages.


2. Open the packages and ensure that the boards are in good condition. For any board problem,
contact the order management engineer at the local Huawei office.

Step 9 Check whether the unpacked boards need to be installed immediately, and then proceed
accordingly.

If... Then...

The unpacked boards need to be installed Place the boards on an ESD surface and
immediately discharge the static electricity.

The unpacked boards need not be installed Pack the boards with the original materials and
immediately place them in a cool dry place away from direct
sunlight or strong electromagnetic radiation.

Step 10 Check the items. Check the items one by one according to the names, types, and quantities
described in the Packing List.
The acceptance of items covers the following aspects:
l Appearance: Check whether there is any visible defect, looseness, distortion, or damage;
check whether the labels are legible and whether the nameplates and decorating plates are
available and meet the requirements.
l Integrity: Ensure that all the parts and accessories required for the installation of cabinets are
available.
l Computer: Check whether the monitor, keyboard, and mouse are intact and in good condition.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 9


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

l Board: Ensure that the type and quantity of the boards are consistent with those in the Packing
List. Ensure that no printed circuit board is broken and no component is detached from the
board.
NOTE

The project supervisor should take the major role in the inspection of equipment and components whose
electric characteristics are likely to have been affected.

If... Then...

The packing list indicates "shortage of Inform the order management engineer at the
articles" local office. Then, sign the Packing List together
with the customer.

There are any short, wrong, extra, or Representatives of Huawei and the customer
damaged items must sign the Unpacking Inspection Memo and
Packing List. The installation supervisor must fill
in the Cargo Problems Report and inform the
order management engineer at the local office in
three days. The installation supervisor must keep
the problematic items intact and the inner and
outer packing intact for future investigation and
verification.

The shipment is intact Place the inspected items by type. Then,


representatives of Huawei and the customer sign
the Packing List.

----End

3.2 Tools Required for Installing the N68E-21-N Cabinet


The tools required for installing the N68E-21-N cabinet are tools for measuring, marking,
drilling, and fastening, small tools, auxiliary tools, meters, and some special tools.

Common Tools
Table 3-1 lists the common tools required for installing the N68E-21-N cabinet.

Table 3-1 Common tools required for installing the N68E-21-N cabinet

Type Tool

Measuring tools Long tape, 50 m ribbon tape, 5 m tape measure, 400 mm level bar, and
level instrument

Marking tools Marking pen, pencil

Drilling tools Percussion drill with matching bits of 6, 8, 10, 12, 14, and 16,
and vacuum cleaner

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 10


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 3 Preparing for the N68E-21-N Cabinet Installation

Type Tool

Fastening tools Flat-head screwdrivers (M3 to M6)


Phillips screwdrivers (M3 to M6)
Adjustable wrench
Socket wrenches (M6, M8, M10, M12, M14, M17, M19)
Double offset ring wrenches (M6, M8, M10, M12, M14, M17, M19)
Combination wrenches (M17 and M19)
Long-arm wrench

Small tools Sharp-nose pliers, diagonal pliers, pliers, hand-held electric drill, file,
handsaw, crowbar, rubber hammer, and claw hammer

Auxiliary tools Paper knife, bellows, plumb, fork, ladder, heat gun, and PVC insulation
tape

Special Tools
The special tools required for installing the N68E-21-N cabinet are the earth resistance meter,
ESD wrist strap, ESD gloves, cable peeler, safety knife, and multi-purpose crimping pliers.

Meters
The meters required for installing the N68E-21-N cabinet are the multimeter and 500 V
megohmmeter (for testing insulation resistance).

NOTE

The meters must be checked and certified.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 11


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 4 Installing the N68E-21-N Cabinet

4 Installing the N68E-21-N Cabinet

The N68E-21-N cabinet installation involves installing the cabinet, accessories, external power
cables, and PGND cables. It also involves checking the power-on status of the cabinet, and
attaching engineering labels to the cabinet, external power cables, and PGND cables.

Prerequisites
l The equipment is unpacked and accepted.
l The tools required for the installation are available.

Procedure
Step 1 Install the N68E-21-N cabinet.

If... Then...

You install the N68E-21-N cabinet on an See 6 Installing the N68E-21-N Cabinet on
ESD floor, an ESD Floor.

You install the N68E-21-N cabinet on a See 5 Installing the N68E-21-N Cabinet on
concrete floor, a Concrete Floor.

You install the N68E-21-N cabinet on other Contact Huawei for technical support.
types of floor,

Step 2 Install the power cables and PGND cables for the N68E-21-N cabinet by referring to 7 Installing
the Power Cables and PGND Cables for the N68E-21-N Cabinet.
Step 3 Install the accessories for the N68E-21-N cabinet by referring to 8 Installing the Accessories
for the N68E-21-N Cabinet.
Step 4 Attach the engineering labels to the cabinet by referring to 9 Attaching the Engineering Labels
to the Cabinets.
Step 5 Attach the engineering labels to the external power cables and PGND cables by referring to 10
Attaching the Engineering Labels to the Power Cables and PGND Cables.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 12


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

5 Installing the N68E-21-N Cabinet on a


Concrete Floor

About This Chapter

This chapter describes how to install the N68E-21-N cabinet on a concrete floor.

Prerequisites
l The cabinet to be installed is delivered to the site, unpacked, and accepted.
l The materials required for installing the N68E-21-N cabinet are available.
5.1 Materials Required for Installing the N68E-21-N Cabinet on a Concrete Floor
The N68E-21-N cabinet can be directly installed on a concrete floor, so other types of materials
are not required. The number of N68E-21-N cabinets to be installed depends on the actual
requirements.
5.2 Positioning the N68E-21-N Cabinet on a Concrete Floor
The steps for positioning the N68E-21-N cabinet on a concrete floor are as follows: determining
cabinet positions, marking the positions, drilling holes, and installing expansion bolt
assemblies.Combining the adjacent N68E-22 Cabinets is recommended, and the SFP+ High-
Speed Cables can be installed when the length of the cables is not long enough.
5.3 Securing the N68E-21-N Cabinet to the Concrete Floor
This section describes how to secure the N68E-21-N cabinet to the concrete floor.
5.4 Combining the N68E-21-N Cabinets
This section describes how to combine multiple N68E-21-N cabinets.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 13


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

5.1 Materials Required for Installing the N68E-21-N Cabinet


on a Concrete Floor
The N68E-21-N cabinet can be directly installed on a concrete floor, so other types of materials
are not required. The number of N68E-21-N cabinets to be installed depends on the actual
requirements.

5.2 Positioning the N68E-21-N Cabinet on a Concrete Floor


The steps for positioning the N68E-21-N cabinet on a concrete floor are as follows: determining
cabinet positions, marking the positions, drilling holes, and installing expansion bolt
assemblies.Combining the adjacent N68E-22 Cabinets is recommended, and the SFP+ High-
Speed Cables can be installed when the length of the cables is not long enough.

Prerequisites
l For positioning, the M12x102 expansion bolt assemblies are available.
l The Equipment Room Floor Plan is available.
l The following tools are available - tape measure, marker, hammer drill with the 16 and
18 bits, vacuum cleaner, safety goggles, dustproof cover for electronic equipment, socket
wrench, and rubber hammer.

Procedure
Step 1 According to the dimensions specified in the equipment room floor plan that is provided by the
customer or the site survey personnel, use a tape measure to determine the cabinet positions, as
shown in Figure 5-1.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 14


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-1 Equipment room floor plan (unit: mm)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 15


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

CAUTION
If the installation positions have to be changed on site, it is recommended that the new positions
meet the following requirements:
l The distance between two rows of cabinets should be at least 1,000 mm.
l The distance between the wall and the cabinet side that is the closest to the wall should be
at least 800 mm.
l The distance between the wall and the cabinet front/back that is the closest to the wall should
be at least 800 mm.
l The width of the aisles in the equipment room should be at least 1,000 mm.

Step 2 Draw lines.


1. According to the dimensions specified in the Equipment Room Floor Plan, determine the
position of the benchmark line that is parallel to the front of the cabinets.
2. According to Figure 5-2 or Figure 5-3, use a tape measure to determine several marking
points. Use a marker to draw two straight lines parallel to the benchmark line. The spacing
between the two straight lines is 408 mm.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 16


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-2 Installation holes for one cabinet (unit: mm)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 17


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-3 Installation holes for a row of cabinets (unit: mm)

CAUTION
Ensure that line drawing is accurate, as imprecise drawing may hamper the installation.

3. Determine the position of the installation hole for the first expansion bolt assembly. With
this position as a reference, mark the installation holes of other expansion bolt assemblies.
4. After all the hole positions are marked, ensure that the distance between the holes is
accurate.
Step 3 Drill the holes.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 18


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

NOTE

Ensure that you drill the holes accurately, as imprecise holes may hamper the installation.
l Before drilling holes, ensure that the positions of the holes are correct based on the Figure 5-2 or
Figure 5-3.
l For some types of concrete floors on which drilling is not suitable, you should consult the architectural
engineers and get their permission before drilling holes.
l Check the thickness of the concrete floor before drilling holes and note that penetrating the concrete
floor is forbidden. If the concrete floor is not thick enough to hold the expansion bolt assemblies,
exchange the expansion bolt assemblies for the proper type.
l Take measures to protect the electronic equipment from dust before drilling holes, for example, cover
the electronic equipment with dustproof cover.
l Use a vacuum cleaner to remove the dust during the drilling. Before removing the dustproof cover from
the electronic equipment, you should clean up the pieces of concrete that have accumulated during the
drilling.
l You must wear safety goggles during the drilling to protect your eyes from the dust.
1. Install the 16 bit and fix the scaleplate on the hammer drill to ensure that the drilling depth
ranges from 85 mm to 90 mm.
NOTE

The drilling depth must not be less than 85 mm or more than 90 mm. Otherwise, the expansion bolt
assembly cannot be properly installed and fastened.
2. Align the drill bit upright to the drilling position. Use both hands to hold the drill stock
firmly, and drill a hole. Use a vacuum cleaner to remove the dust during the drilling.
NOTE

If the ground is too hard or slippery to position the drill bit stably, use a chisel to dig a pit before
drilling holes. If a reinforcing steel bar is found where the hole is drilled, stop using the hole and drill
another one a little inward along the diagonal.
3. Remove the dust in the hole, measure the depth of the hole, and check whether the hole is
slanting. If the depth of the hole is not appropriate or if the hole is slanting, re-drill the hole.
If the slanting hole cannot be corrected, stop using the hole.
4. Replace the 16 bit with the 18 bit, and then drill the hole until its diameter meets the
requirement.
NOTE

If the slanting hole cannot be corrected, stop using the hole and drill another one.

Step 4 Install the expansion bolt assemblies. Figure 5-4 shows how to install the expansion bolt
assembly.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 19


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-4 Installing an expansion bolt assembly

1 Bolt 2 Flat washer 3 Steel tube

4 Plastic tube 5 Expansion tube 6 Conical nut

1. Remove the dust inside and outside the holes by using the vacuum cleaner.
2. Measure the distance between the holes. If the distance does not meet the specifications,
reposition and drill new holes.
3. Insert the expansion bolt assembly vertically into the installation hole on the ground.
4. Hammer the expansion bolt assembly by using the rubber hammer until the expansion bolt
assembly reaches the bottom of the installation hole, as shown in Figure 5-4.
5. Use the socket wrench to loosen the bolt, and then remove the bolt, flat washer, and steel
tube. Properly store the bolt, flat washer, and steel tube for future installation.

----End

Follow-up Procedure
Record the positioning result in the corresponding table provided in Hardware Installation
Record.

5.3 Securing the N68E-21-N Cabinet to the Concrete Floor


This section describes how to secure the N68E-21-N cabinet to the concrete floor.

Prerequisites
l For installation, the N68E-21-N cabinet is available.
l The following materials are available- the insulating spacers, flat washers 12, spring
washers 12, adjusting pads (optional), and expansion bolt assemblies.
l The following tools are available- the multimeter, level bar, and torque wrench.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 20


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Context

CAUTION
The cabinet has a high center of gravity. Therefore, do not lift or push the cabinet alone. Moving
a cabinet requires at least two people and a pallet truck, to ensure personnel and equipment
safety.

Procedure
Step 1 Remove the protection covers from the front and the back of the cabinet.

Step 2 Remove the metal packing accessories from the cabinet columns, as shown in Figure 5-5.

Figure 5-5 Removing the metal packing accessories

Step 3 Remove the lowest subrack and store it for future use as follows:

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 21


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

NOTE
The components installed in the lower part (5 U high, 1 U = 44.45 mm) of the cabinet will hamper the
cabinet installation. Therefore, you must remove the components before the cabinet installation and reinstall
them after the cabinet installation.
1. At the back of the subrack, remove the M3 screw on the right side of the plastic cover of
the power cable terminal, and loosen the M3 screw on the left side until the plastic cover
is movable. Do not remove the M3 screw on the left side. See Figure 5-6.

Figure 5-6 Rear view of the subrack

1 PDB monitoring cable 2 Power cables 3 PGND cables

4 Plastic cover 5 M3 screw 6 Subrack holding the board

2. Remove the power cables. Figure 5-6 shows the positions of the power cables.

CAUTION
When removing the cables from the back of the subrack, identify the positions of the cables
for future reinstallation.

3. Remove the PGND cables and PDB monitoring cable from the back of the subrack. Figure
5-6 shows the positions of the cables.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 22


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

4. Use the cable ties to bind these cables to the mounting bars, and properly store the screws
and nuts for future use.
5. In front of the cabinet, use the Phillips screwdriver to remove all the eight M6x12 screws
that fix the subrack to the cabinet, and store them for future use.

CAUTION
Three people are required to remove the subrack. Ensure personal safety.

6. One person pushes the subrack out along the guide rail from the back of the cabinet. The
other two people hold the mounting ears and the bottom of the subrack to pull the subrack
out of the cabinet from the front.
7. Keep the subrack for future installation.
Step 4 As shown in Figure 5-7, put two insulating spacers on the floor.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 23


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-7 Installing the N68E-21-N cabinet on the concrete floor

1 Bolt 2 Spring washer 12 3 Flat washer

4 Plain washer 5 Insulating tube 6 Steel tube

7 Installation hole for the cabinet 8 Insulating spacer 9 Adjusting pad (optional)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 24


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Step 5 Put the cabinet in the planned position. Align the installation holes at the bottom of the cabinet
with the holes for installing the expansion bolt assemblies.
Step 6 Use the level bar to check the levelness of the cabinet. If the cabinet is not level, adjust it by
inserting adjusting pads between the insulating spacer and the floor. See Figure 5-7.

CAUTION
Ensure that the adjusting pads are inserted between the insulating spacer and the floor. If they
are inserted between the insulating spacer and the cabinet, the insulating spacer cannot function
well.

Step 7 As shown in Figure 5-7, put the steel tube, insulating tube, and plain washer on the installation
hole. Ensure that the convex part of the insulating tube faces downwards.
Step 8 Fit the spring washer 12 and flat washer on the bolt, and insert the bolt into the steel tube, as
shown in Figure 5-7.
Step 9 Diagonally tighten the four expansion bolt assemblies to 80 Nm.
Step 10 Measure the resistance between the fixing bolt of the cabinet and the ground bolt at the bottom
of the cabinet.
1. Set the multimeter to the megohm scale.
2. Measure the resistance between the fixing bolt and the ground bolt, See Figure 5-8.

Figure 5-8 Insulation test

1 Resistance tester 2 Fixing bolt 3 Ground bolt

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 25


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

If... Then...

The resistance is greater than or equal to five The cabinet is insulated from the ground. Go
megohms, to Step 15.

The resistance is smaller than five megohms, The cabinet is not insulated from the ground.
Go to Step 11.

Step 11 Uninstall the cabinet.

Step 12 Check whether the improper insulation is caused by missing or damaged insulating parts.
The insulating parts of the N68E-22 and N68E-21-N cabinets are the insulating spacers and
insulating tubes.

Step 13 Secure the cabinet again.

Step 14 Repeat the insulation test starting from Step 10 until the resistance is greater than or equal to
five megohms.

Step 15 Install the removed subrack back into the cabinet.


1. Two people hold the mounting ears of the subrack and the bottom of the subrack, and slide
the subrack into the cabinet along the guide rail. Use the eight M6x12 screws to fix the
subrack to the cabinet.
2. At the back of the cabinet, connect the PGND cables, power cables, and PDB monitoring
cable, and then reinstall the two plastic covers, as shown in Figure 5-6.

----End

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

5.4 Combining the N68E-21-N Cabinets


This section describes how to combine multiple N68E-21-N cabinets.

Prerequisites
For the installation, wrench and climbing ladder tools are available.

Context
Combining the cabinets is accomplished using connecting plates that connect the adjacent
cabinets after the cabinet installation. The connecting plates, which ensure that the cabinets are
upright, are already installed on the top of the cabinets at delivery.
NOTE

The cabinets cannot be installed back to back. When multiple cabinets are combined, they should be
installed side by side.

Figure 5-9 and Figure 5-10 show how to fix the connecting plates to combine cabinets.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 26


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-9 Installing connecting plates on the top of two adjacent cabinets

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 27


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 5 Installing the N68E-21-N Cabinet on a Concrete Floor

Figure 5-10 Installing connecting plates on the door heads of two adjacent cabinets

Procedure
Step 1 Reach the top of the cabinet using a climbing ladder.
Step 2 Install the connecting plates on the top of two adjacent cabinets, as shown in Figure 5-9.
Step 3 Install the connecting plates on the door heads of two adjacent cabinets, as shown in Figure
5-10.
Step 4 Ensure that the horizontal and vertical deviation of the cabinets is within specifications.
Step 5 Ensure that all of the cabinets are at the same level and stand side by side closely.

----End

Follow-up Procedure
Record the operation result in the corresponding table provided in Hardware Installation Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 28


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

6 Installing the N68E-21-N Cabinet on an ESD


Floor

About This Chapter

This chapter describes how to install the N68E-21-N cabinet on an ESD floor.

Prerequisites
l The cabinet to be installed is delivered to the site, unpacked, and accepted.
l The materials required for installing the N68E-21-N cabinet are available.

Context

CAUTION
During the cabinet installation, you may need to cut the ESD floor or some components of the
support. When doing the cutting, wear a pair of gloves to prevent injury.

6.1 Materials Required for Installing the N68E-21-N Cabinet on the ESD Floor
This section describes the materials required for installing the N68E-21-N cabinet on the ESD
floor. The required materials are the N68E-21-N cabinet and shockproof support assembly.
6.2 Introduction to the Shockproof Support
This section describes the shockproof support, which is made of several components and needs
to be assembled on site.
6.3 Positioning the N68E-21-N Cabinet on the ESD Floor
Positioning the N68E-21-N cabinet on the ESD floor involves the following steps: determining
cabinet positions, marking the positions, and drilling holes.Combining the adjacent N68E-22
Cabinets is recommended, and the SFP+ High-Speed Cables can be installed when the length
of the cables is not long enough.
6.4 Assembling the Shockproof Support
This section describes how to assemble the shockproof support. The methods of assembling the
shockproof support are similar in the scenarios of combining an even number of cabinets in a

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 29


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

row, combining an odd number of cabinets in a row, and installing a single cabinet. The following
takes a single cabinet as an example to describe how to assemble the shockproof support.
6.5 Installing Floating Nuts on the Shockproof Support
After the shockproof support is assembled, the floating nuts must be installed to fix the N68E-21-
N cabinet on the shockproof support.
6.6 Securing the Shockproof Support on the Concrete Floor
This section describes how to drill holes, install the expansion bolt assemblies, and secure the
shockproof support on the concrete floor.
6.7 Securing the N68E-21-N Cabinet on the ESD Floor
This section describes how to secure the N68E-21-N cabinet on the ESD floor.
6.8 Combining the N68E-21-N Cabinets
This section describes how to combine multiple N68E-21-N cabinets.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 30


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

6.1 Materials Required for Installing the N68E-21-N Cabinet


on the ESD Floor
This section describes the materials required for installing the N68E-21-N cabinet on the ESD
floor. The required materials are the N68E-21-N cabinet and shockproof support assembly.
Table 6-1 lists the materials required for installing the N68E-21-N cabinet on the ESD floor.

Table 6-1 Materials

Name Sub- Quantity Remarks


Item

Shockproof Support N+1, for N The support needs to be assembled on site.


support cabinets For the ESD floors of different heights (H),
assembly the installation of the supports is of the
following types:
l For H 325 mm, no special processing
is required. This height is presented as an
example in this section.
l For 205 mm H < 325 mm, the
installation method is the same as that
used when H 325 mm but the support
needs to be customized.
l For H < 205 mm, the installation method
is different from that used in the previous
two scenarios and the support needs to be
customized.

Guide rail N, for N Each guide rail is 1,200 mm long. It needs


cabinets to be cut as required.

N68E-21-N - Depends on -
cabinet the site
requirements

6.2 Introduction to the Shockproof Support


This section describes the shockproof support, which is made of several components and needs
to be assembled on site.

6.2.1 Shockproof Support Assembly


This section describes the components of the shockproof support assembly. The components are
the horizontal beam/guide rail, lock catch, column connector, floating nut, column, base, angle
bracket, and expansion bolt.
Table 6-2 illustrates the components of the shockproof support assembly.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 31


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Table 6-2 Components of the shockproof support assembly

Horizontal beam/guide rail Column

Base

Lock catch

Angle bracket

Column connector

Floating nut

Expansion bolt

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 32


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

NOTE

l The horizontal beam/guide rail, column, base, column connector, and angle bracket are the main
components of the shockproof support assembly.
l The lock catch is used to secure the components.
l The floating nut is used to secure the cabinet on the guide rail. There are teeth on the floating nut.
Pre-tightening is implemented through the meshing of the teeth on the floating nut and the teeth on
the guide rail, and with the aid of the spring of the plastic pad on the floating nut.
l The expansion bolt is used to fix the support on the concrete floor.

6.2.2 Fastening the Lock Catches on the Shockproof Support


Assembly
This section describes how to fasten the lock catches on the shockproof support assembly.

Context
Lock catches are used to connect all the components of the shockproof support assembly. Both
the lock catch and the U-steel (horizontal beam/guide rail/column) have teeth. When the
components are assembled, mesh the teeth of the lock catch and the components to pre-tighten
them, as shown in Figure 6-1. The tightened support is shockproof.

Figure 6-1 Teeth of the U-steel and lock catch

Procedure
Step 1 Pre-tighten the lock catch. Press the bolt of the lock catch while turning the bolt to 90 degrees
clockwise. With the rotation of the bolt, the nut also rotates 90 degrees. Then, the two pieces are
pre-tightened, as shown in Figure 6-2.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 33


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-2 Tightening the lock catch

1 M10 bolt 2 Washer 3 Nut

Step 2 Tighten the lock catch. Use a socket wrench to tighten the bolt to 40 Nm clockwise.

----End

6.2.3 Cutting Guide Rails for the Shockproof Support


Before assembling the shockproof support, you should cut the guide rails according to the type
of the combined cabinets. According to the number of combined cabinets, there are three types:
an even number of cabinets combined in a row, an odd number of cabinets combined in a row,
and a single cabinet installed. If the guide rails on site are already cut, skip this procedure.

Prerequisites
l The materials required for the cutting are available. The required materials are the guide
rails.
l The tools required for the cutting are available. The required tools are the tape measure,
file, sandpaper, and metal cutter.

Context
The guide rail is 1,200 mm long and the cabinet is 600 mm wide. Therefore,
l For combining an even number of cabinets in a row, it is not necessary to cut the guide rail.
Figure 6-3 shows the guide rails for combining an even number of cabinets in a row.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 34


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-3 Guide rails for combining an even number of cabinets in a row

l To combine an odd number of cabinets in a row, cut a 1,200 mm long guide rail into two
600 mm long guide rails. Figure 6-4 shows the guide rails for combining an odd number
of cabinets in a row.

Figure 6-4 Guide rails for combining an odd number of cabinets in a row

l To install a single cabinet, cut a 1,200 mm long guide rail into two 600 mm long guide
rails. Figure 6-5 shows the guide rails for installing a single cabinet.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 35


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-5 Guide rails for installing a single cabinet

CAUTION
In underfloor cabling mode, the guide rail may block part of the cabling space. Therefore, for
installations using underfloor cabling with a large number of cables, ensure beforehand that the
guide rails will not affect the cabling.

Procedure
Step 1 Choose a scheme of cutting the guide rails according to the type of the combined cabinets.

If... Then...

An odd number of cabinets are combined in a row or Go to Step 2.


a single cabinet is installed,

An even number of cabinets are combined in a row, Cutting guide rails is unnecessary.

Step 2 Use the metal cutter to cut a 1,200 mm long guide rail into two 600 mm long guide rails.

Step 3 Use the file or sandpaper to smooth the cut surfaces of the guide rails.

Step 4 Apply antirust paint on the cut surfaces.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 36


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

6.3 Positioning the N68E-21-N Cabinet on the ESD Floor


Positioning the N68E-21-N cabinet on the ESD floor involves the following steps: determining
cabinet positions, marking the positions, and drilling holes.Combining the adjacent N68E-22
Cabinets is recommended, and the SFP+ High-Speed Cables can be installed when the length
of the cables is not long enough.

Prerequisites
l For positioning, the Equipment Room Floor Plan material is available.
l The following tools are available - the tape measure, panel lifter, electric saw, marker,
hammer drill with 16 and 18 drill bits, vacuum cleaner, safety goggles, dustproof cover
for electronic equipment, and rubber hammer.

Procedure
Step 1 According to the dimensions specified in the equipment room floor plan that is provided by the
customer or the site survey personnel, use a tape measure to determine the cabinet positions, as
shown in Figure 6-6.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 37


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-6 Equipment room floor plan (unit: mm)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 38


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

CAUTION
If the installation positions have to be changed on site, it is recommended that the new positions
meet the following requirements:
l The distance between two rows of cabinets should be at least 1,000 mm.
l The distance between the wall and the cabinet side that is the closest to the wall should be
at least 800 mm.
l The distance between the wall and the cabinet front/back that is the closest to the wall should
be at least 800 mm.
l The width of the aisles in the equipment room should be at least 1,000 mm.

Step 2 Draw lines.


1. According to the dimensions specified in the Equipment Room Floor Plan, determine the
position of the benchmark line that is parallel to the front of the cabinets.
2. According to Figure 6-7 and Figure 6-8, use a tape measure to determine several marking
points. Use a marker to draw two straight lines parallel to the benchmark line. The spacing
between the two straight lines is 408 mm.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 39


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-7 Installation holes for one cabinet (unit: mm)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 40


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-8 Installation holes for a row of cabinets (unit: mm)

CAUTION
Line drawing is one of the primary tasks for cabinet installation. The quality of the line
drawing directly affects the quality of the whole cabinet installation.

3. On the two straight lines, determine the position of the installation hole for the first cabinet.
With this position as reference, mark the installation holes for other cabinets.
4. After all the drilling positions are marked, measure them again to ensure that they meet the
requirements described in Figure 6-7 or Figure 6-8.

Step 3 Drill the holes. Drill holes according to the lines drawn on the ESD floor. The diameter of each
hole is 14 mm. For the positions of the holes, see Figure 6-7 or Figure 6-8.

Step 4 Cut the ESD floor. Use the panel lifter to move the ESD floor to be cut and cut the ESD floor
in each position for cabling. Figure 6-9 shows the positions for cutting the ESD floor.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 41


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-9 Positions for cutting the ESD floor (unit: mm)

Step 5 Remove the ESD floor supports from the installation area.

----End

Follow-up Procedure
Clear the installation area for future installation.

6.4 Assembling the Shockproof Support


This section describes how to assemble the shockproof support. The methods of assembling the
shockproof support are similar in the scenarios of combining an even number of cabinets in a
row, combining an odd number of cabinets in a row, and installing a single cabinet. The following
takes a single cabinet as an example to describe how to assemble the shockproof support.

Prerequisites
l For the assembling, the following components are available - the horizontal beam/guide
rail, lock catch, column connector, floating nut, column, base, angle bracket, and expansion
bolt.
l The following tools are available - the level bar, torque wrench, and metal cutter.
l For combining an odd number of cabinets in a row or for installing a single cabinet, cutting
a guide rail is complete. For combining an even number of cabinets in a row, guide rails
need not be cut beforehand.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 42


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Procedure
Step 1 Place the bases on the concrete floor.
Step 2 Insert the columns until they reach the bottom of the bases, and pre-tighten the columns and the
bases by using the lock catches, as shown in Figure 6-10.

Figure 6-10 Installing the columns

Step 3 Pre-tighten the column connectors onto the top of the columns by using the lock catches. Ensure
that the top surface of each support plate soldered to the column connectors and the top surface
of each column are at the same level, as shown in Figure 6-11.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 43


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-11 Installing the column connectors

Step 4 Place the two guide rails onto the column connectors. Pre-tighten the guide rails to the column
connectors by using the lock catches. Adjust the positions of the bases and ensure that each guide
rail projects 10-15 mm beyond both sides of the column. See Figure 6-12.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 44


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-12 Installing the guide rails

Step 5 Pre-tighten each angle bracket to the corresponding column by using two lock catches. Ensure
that the top surface of the angle brackets and the top surface of the columns are at the same level.
Four angle brackets need to be pre-tightened, as shown in Figure 6-13.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 45


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-13 Installing the angle brackets

Step 6 Place two horizontal beams onto the columns. Ensure that the beams are in close contact with
the corresponding angle brackets. Adjust the positions of the columns. Ensure that the distance
between the two guide rails is 457.5 mm. Pre-tighten the horizontal beam and the corresponding
angle bracket by using two lock catches.
Step 7 Adjust the height of the columns. Ensure that the height of the support is 3-5 mm greater than
the distance between the concrete floor and the lower surface of the ESD floor.
Step 8 Adjust the positions of the horizontal beams and guide rails. Ensure that they are at the same
level. The distance between the two guide rails should be 457.50.5 mm.
Step 9 Tighten all the lock catches to 40 Nm.
Step 10 Check whether the column connectors need to be cut.

If... Then...

The column connectors are already cut to The assembling of the shockproof support is
the proper length, complete.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 46


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

If... Then...

The column connectors are not cut and the 1. Loosen some of the lock catches.
cutting tool is unavailable on site, 2. Move the columns inward along the guide
rails until the columns are aligned with the
ends of the guide rails.
3. Tighten all the lock catches.
The assembling of the shockproof support is
complete.

There is another situation, Go to Step 11.

Step 11 Use the metal cutter to cut the column connectors that project beyond the guide rails. Figure
6-14 shows the assembled support.

Figure 6-14 Assembled support (unit: mm)

CAUTION
After cutting the column connectors, smooth the cut surfaces and brush antirust paint on the
cross section.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 47


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

6.5 Installing Floating Nuts on the Shockproof Support


After the shockproof support is assembled, the floating nuts must be installed to fix the N68E-21-
N cabinet on the shockproof support.

Prerequisites
l The shockproof support is assembled.
l For the installation, the torque wrench and rubber hammer are available.

Procedure
Step 1 Place the assembled support under the ESD floor and loosen the lock catches that connect the
bases and the columns.

Step 2 Put the ESD floor back to the original position on the floor framework and use a rubber hammer
to hammer the ESD floor. Ensure that the top surface of the support clings to the ESD floor.

Step 3 Tighten the lock catches that connect the bases and the columns to 40 Nm.

Step 4 Remove the ESD floor.

Step 5 Install four floating nuts at both ends of the two guide rails. Ensure that the floating nuts are
symmetrical around the center of the support. The positions of the floating nuts are shown in
Figure 6-15.

Figure 6-15 Installing floating nuts (unit: mm)

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 48


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

NOTE

l There are teeth on the floating nut. Pre-tightening is implemented through the meshing of the teeth on
the floating nut and the teeth on the guide rail, and with the aid of the spring of the plastic pad on the
floating nut.
l If you want to move a floating nut, press the plastic pad and meanwhile move the floating nut along
the guide rail.

----End

6.6 Securing the Shockproof Support on the Concrete Floor


This section describes how to drill holes, install the expansion bolt assemblies, and secure the
shockproof support on the concrete floor.

Prerequisites
l For the installation, the shockproof support component is available.
l The following tools are available - the socket wrench, tape measure, panel lifter, marker,
hammer drill with 12 drill bit, vacuum cleaner, safety goggles, dustproof cover for
electronic equipment, and rubber hammer.

Procedure
Step 1 Place the removed ESD floor on the assembled support. Align the installation holes for the ESD
floor with the floating nuts.
Step 2 Use a marker to mark the installation holes for the bases, as shown in Figure 6-16.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 49


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-16 Installing the bases

1 ESD floor 2 Installation hole aligning with the floating nut 3 Installation hole for the base

Step 3 Remove the ESD floor and the support and mark the holes for drilling on the concrete floor.
NOTE

Ensure that you drill the holes accurately, as imprecise holes may hamper the installation.
l For some types of concrete floors on which drilling is not suitable, you should consult the architectural
engineers and get their permission before drilling holes.
l Check the thickness of the concrete floor before drilling holes and note that penetrating the concrete
floor is forbidden. If the concrete floor is not thick enough to hold the expansion bolt assemblies,
exchange the expansion bolt assemblies for the proper type.
l Take dustproof measures on the electronic equipment before drilling holes, for example, cover the
electronic equipment with dustproof cover.
l Use a vacuum cleaner to remove the dust during the drilling.
l Before removing the dustproof cover from the electronic equipment, clean up the pieces of concrete
that have accumulated during the drilling.
l You must wear safety goggles during the drilling to protect your eyes from the dust.
1. Drill the marked holes on the concrete floor by using a 12 hammer drill.
2. Dig a pit by using a chisel before drilling holes and ensure that the depth of the drilled holes
ranges from 70 mm to 75 mm.
3. Use both hands to hold the drill stock firmly, and drill the marked holes vertically
downwards. Use a vacuum cleaner to remove the dust during the drilling.
4. Measure the depth of the hole. If the depth is not 70-75 mm, drill the hole again.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 50


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

5. If the hole is slanting, drill the hole again.


Step 4 Install the expansion bolt assemblies. Figure 6-17 shows an expansion bolt assembly.

Figure 6-17 Installing an expansion bolt assembly

1 M8x75 bolt 2 Large flat washer 3 Steel tube

4 Plastic tube 5 Expansion tube 6 Nut

1. Insert the expansion bolt assembly vertically into the installation hole for the support.
2. Use the rubber hammer to hammer the expansion bolt assembly until the steel tube is 3-5
mm above the ground.
3. Use the torque wrench to remove the bolt, and then remove the flat washer and the steel
tube. Store them for future use.
Step 5 Fix the support, See Figure 6-18.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 51


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-18 Securing the support

1 M8x75 bolt 2 Large flat washer 3 Steel tube

4 Plastic tube 5 Expansion tube 6 Nut

CAUTION
When fixing the support, you must use the large flat washer to replace the flat washer provided
with the expansion bolt assembly.

1. Place the support in the installation position and ensure that the installation hole for the
base aligns with the hole for the expansion bolt assembly.
2. Insert the steel tube into the hole for the expansion bolt assembly through the installation
hole for the base.
3. Install the large flat washer on the bolt, insert the bolt into the steel tube, and then tighten
the bolt to 25 Nm.
4. Repeat Step 5.2 through Step 5.3 to tighten other bolts to 25 Nm diagonally.

----End

6.7 Securing the N68E-21-N Cabinet on the ESD Floor


This section describes how to secure the N68E-21-N cabinet on the ESD floor.

Prerequisites
l For the installation, the N68E-21-N cabinet is available.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 52


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

l The following materials are available - protective materials, insulating spacer, spring
washer 12, plain washer, insulating tube, cable ties, and expansion bolt assembly
(expansion bolt, steel tube, and large flat washer).
l The following tools are available - the Phillips screwdriver, level bar, torque wrench, socket
wrench, diagonal pliers, and multimeter.

Procedure
Step 1 Remove the cabinet.

Step 2 Remove the protective covers from the front and the back of the cabinet.

Step 3 Remove the metal packing accessories from the cabinet columns, as shown in Figure 6-19.

Figure 6-19 Removing the metal packing accessories

Step 4 Remove the lowest subrack and store it for future use as follows:
NOTE
The components installed in the lower part (5 U high, 1 U = 44.45 mm) of the cabinet will hamper the
cabinet installation. Therefore, you must remove the components before the cabinet installation and reinstall
them after the cabinet installation.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 53


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

1. At the back of the subrack, remove the M3 screw on the right side of the plastic cover of
the power cable terminal, and loosen the M3 screw on the left side until the plastic cover
is movable. Do not remove the M3 screw on the left side. See Figure 6-20.

Figure 6-20 Rear view of the subrack

1 PDB monitoring cable 2 Power cables 3 PGND cables

4 Plastic cover 5 M3 screw 6 Subrack holding the board

2. Remove the power cables from the back of the subrack. Figure 6-20 shows the positions
of the power cables.

CAUTION
When removing the cables from the back of the subrack, identify the positions of the cables
for future reinstallation.

3. Remove the PGND cables and PDB monitoring cable from the back of the subrack. Figure
6-20 shows the positions of the cables.
4. Use the cable ties to bind these cables to the mounting bars, and properly store the screws
and nuts for future use.
5. In front of the cabinet, use the Phillips screwdriver to remove all the eight M6x12 screws
that fix the subrack to the cabinet, and store them for future use.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 54


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

CAUTION
Three people are required to remove the subrack. Ensure personal safety.

6. One person pushes the subrack out along the guide rail from the back of the cabinet. The
other two people hold the mounting ears and the bottom of the subrack to pull the subrack
out of the cabinet from the front.
7. Keep the subrack for future installation.

Step 5 Before securing the cabinet, restore the ESD floor under the cabinet and align the installation
holes in the ESD floor with the floating nuts.

Step 6 Lay two insulating spacers for each cabinet on the floor. Then, align the installation holes of the
insulating spacers with those of the cabinet, as shown in Figure 6-21.

Figure 6-21 Fixing the cabinet to the support

1 M12x80 bolt 2 Spring washer 12 3 Large flat washer

4 Thick washer 5 Insulating tube 6 Steel tube

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 55


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

7 Cabinet 8 Insulating spacer 9 ESD floor

10 Support

Step 7 Put the cabinet in the planned position. Align the installation holes at the bottom of the cabinet
with those for the insulating spacers.
Step 8 Put the insulating tube, thick washer, and steel tube on the installation hole in turn. Ensure that
the convex part of the insulating tube faces down.
Step 9 Fit the spring washer 12 and large flat washer on the bolt. Insert the bolt through the cabinet
installation hole into the floating nut in the beam on the support. Use the torque wrench to pre-
tighten the bolt.
Step 10 Repeat Step 8 and Step 9 to install the four bolts. Diagonally tighten the four bolts to 40 Nm.
Figure 6-22 shows the cabinet fixed to the support.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 56


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-22 N68E-21-N cabinet fixed to the support

Step 11 Measure the resistance between the fixing bolt of the cabinet and the ground bolt at the bottom
of the cabinet.
1. Set the multimeter to the megohm scale.
2. Measure the resistance between the fixing bolt and the ground bolt, See Figure 6-23.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 57


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-23 Insulation test

1 Resistance tester 2 Fixing bolt 3 Ground bolt

If... Then...

The resistance is greater than or equal to The cabinet is insulated from the ground. The
five megohms, insulation test is complete.

The resistance is smaller than five megohms, The cabinet is not insulated from the ground.
Go to Step 12.

Step 12 Uninstall the cabinet.


Step 13 Check whether the improper insulation is caused by missing or damaged insulating parts.
The insulating parts refer to the insulating spacer and insulating tube required for the cabinet
installation.
Step 14 Secure the cabinet again.
Step 15 Repeat the insulation test starting from Step 11 until the resistance is greater than or equal to
five megohms.
Step 16 Install the removed subrack back into the cabinet.
1. Two people hold the mounting ears of the subrack and the bottom of the subrack, and slide
the subrack into the cabinet along the guide rail. Use the eight M6x12 screws to fix the
subrack to the cabinet.
2. At the back of the cabinet, connect the PGND cables, power cables, and PDB monitoring
cable, and then reinstall the two plastic covers, as shown in Figure 6-20.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 58


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

6.8 Combining the N68E-21-N Cabinets


This section describes how to combine multiple N68E-21-N cabinets.

Prerequisites
For the installation, wrench and climbing ladder tools are available.

Context
Combining the cabinets is accomplished using connecting plates that connect the adjacent
cabinets after the cabinet installation. The connecting plates, which ensure that the cabinets are
upright, are already installed on the top of the cabinets at delivery.
NOTE

The cabinets cannot be installed back to back. When multiple cabinets are combined, they should be
installed side by side.

Figure 6-24 and Figure 6-25 show how to fix the connecting plates to combine cabinets.

Figure 6-24 Installing connecting plates on the top of two adjacent cabinets

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 59


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 6 Installing the N68E-21-N Cabinet on an ESD Floor

Figure 6-25 Installing connecting plates on the door heads of two adjacent cabinets

Procedure
Step 1 Reach the top of the cabinet using a climbing ladder.
Step 2 Install the connecting plates on the top of two adjacent cabinets, as shown in Figure 6-24.
Step 3 Install the connecting plates on the door heads of two adjacent cabinets, as shown in Figure
6-25.
Step 4 Ensure that the horizontal and vertical deviation of the cabinets is within specifications.
Step 5 Ensure that all of the cabinets are at the same level and stand side by side closely.

----End

Follow-up Procedure
Record the operation result in the corresponding table provided in Hardware Installation Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 60


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

7 Installing the Power Cables and PGND


Cables for the N68E-21-N Cabinet

About This Chapter

This section describes how to install the power cables and PGND cables between the N68E-21-
N cabinet and the power distribution frame (PDF). When combining the N68E-21-N cabinets,
you also need to install the PGND cables between the cabinets.

Prerequisites
l The N68E-21-N cabinet is installed.
l The power cables and PGND cables for the N68E-21-N cabinet are available.
7.1 Power Cables and PGND Cables to Be Installed
This lists the power cables and PGND cables to be installed on site.
7.2 Power and PGND Cable Connections
The following power cables and PGND cables should be installed on site: power cables and
PGND cables between the power distribution box and the PDF, and the PGND cables between
the cabinets.
7.3 Principles of Routing and Binding the Power Cables and PGND Cables
When installing the power cables and PGND cables, you should follow the routing and binding
principles.
7.4 Installing the Power Cables and PGND Cables Between the N68E-21-N Cabinet and the
PDF
There are two methods of installing the power cables and PGND cables between the N68E-21-
N cabinet and the PDF: overhead cabling and underfloor cabling. Select one of them as required.
7.5 Installing the PGND Cables Between Adjacent N68E-21-N Cabinets
This section describes how to connect the upper, middle, and lower PGND busbars of one
N68E-21-N cabinet to those of its adjacent cabinet by using the PGND cables.
7.6 Checking the Power-on Status

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 61


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

This section describes how to check the power supply to the cabinet. It also describes how to
ensure that the power supply to the subracks and the power supply to the fan boxes and boards
in the subracks are normal.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 62


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

7.1 Power Cables and PGND Cables to Be Installed


This lists the power cables and PGND cables to be installed on site.

7.1.1 Power Cables


The power cables are mandatory and are of two categories: external power cables and internal
power cables. The power cables are the -48 V power cables and the RTN power cables.
The external power cables connect the Power Distribution Frame (PDF) to the power distribution
box at the top of the cabinet. The external power cables need to be installed on site. The internal
power cables connect the power distribution box to the modules inside the cabinet. The internal
power cables are installed before the cabinet is delivered.

Cabinet Configured with High-Power Power Distribution Box


Table 7-1 describes the external power cables when the BSC6900 is configured with the high-
power power distribution box. Table 7-2 and Table 7-3 describe the internal power cables when
the BSC6900 is configured with the high-power power distribution box.

Table 7-1 External power cables


Name Color Cross- Connector Connector Quantity
Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Externa Blue 25/35 2-hole JG OT Four per cabinet


l -48 V terminal/-48 V terminal/-48 V
power DC input port on DC output port
cable the power on the PDF
distribution box

Externa Black 25/35 2-hole JG OT Four per cabinet


l RTN terminal/-48 V terminal/-48 V
power DC input port on DC output port
cable the power on the PDF
distribution box

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 63


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Table 7-2 Internal power cables (1)


Name Color Cross- Connector Connector Quantity
Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Internal Blue 10 OT OT Two per subrack


-48 V terminal/-48 V terminal/-48 V
DC DC input port DC output port
power on the power on the subrack
cable distribution
box

Internal Black 10 OT OT Two per subrack


RTN terminal/-48 V terminal/-48 V
power DC input port DC output port
cable on the power on the subrack
distribution
box

Table 7-3 Internal power cables (2)


Name Color Cross- Connector Connector Quantity
Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Internal Blue 2 OT D-type Two per independent


-48 V terminal/-48 V connector/ fan subrack
DC DC input port Power input
power on the power port on the
cable distribution independent
box fan subrack

Internal Black 2 OT D-type Two per independent


RTN terminal/-48 V connector/ fan subrack
power DC input port Power input
cable on the power port on the
distribution independent
box fan subrack

Figure 7-1 shows the external power cable.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 64


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-1 External power cable

(1) OT terminal (2) 2-hole JG terminal

Figure 7-2 shows the internal power cable for subracks.

Figure 7-2 Internal power cable for subracks

Figure 7-3 shows the internal power cable for the independent fan subrack.

Figure 7-3 Internal power cable for the independent fan subrack

Cabinet Configured with Common Power Distribution Box


Table 7-4 describes the external power cables when the BSC6900 is configured with the
common power distribution box. Table 7-5 describes the internal power cables when the
BSC6900 is configured with the common power distribution box.

Table 7-4 External power cables

Name Color Cross- Connector Connector Quantity


Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Externa Blue 25/35 Cord end OT Four per cabinet


l -48 V terminal/-48 V terminal/-48 V
power DC input port on DC output port
cable the power on the PDF
distribution box

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 65


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Name Color Cross- Connector Connector Quantity


Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Externa Black 25/35 Cord end OT Four per cabinet


l RTN terminal/-48 V terminal/-48 V
power DC input port on DC output port
cable the power on the PDF
distribution box

Table 7-5 Internal power cables


Name Color Cross- Connector Connector Quantity
Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2
mm2

Internal Blue 8 Cord end OT Two per subrack


-48 V terminal/-48 V terminal/-48 V
DC DC input port DC output port
power on the power on the subrack
cable distribution
box

Internal Black 8 Cord end OT Two per subrack


RTN terminal/-48 V terminal/-48 V
power DC input port DC output port
cable on the power on the subrack
distribution
box

The internal power cable and the external power cable have the same appearance when the
BSC6900 is configured with the common power distribution box. Figure 7-4 shows the external/
internal power cable.

Figure 7-4 External/Internal power cable

X1: Cord end terminal X2: OT terminal

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 66


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

7.1.2 PGND Cables


The PGND cables consist of external PGND cable, inter-cabinet PGND cables, PGND cable for
the power distribution box, PGND cables for the subrack, PGND cable for the independent fan
subrack, and PGND cables for the cabinet door. The PGND cable is mandatory.
Each cabinet must be configured with one external PGND cable. When the cabinets are
combined, three inter-cabinet PGND cables must be installed between every two adjacent
cabinets. Other PGND cables are already installed in the cabinet before delivery.
Table 7-6 describes the PGND cables.

Table 7-6 PGND cables


Cable Color Cross- Connect Connector Quantity
Name Sectional or Type Type 2/
Area 1/ Installation
Installati Position 2
mm2
on
Position
1

External Green and 25/35 OT OT terminal/ One per


PGND yellow terminal/ PGND output cabinet
cable Groundin port on the PDF
g bolt at
the top
rear of
each
cabinet

Inter- Green and 6 OT OT terminal/ Three


cabinet yellow terminal/ PGND busbar of between
PGND PGND each cabinet every two
cable busbar of adjacent
each cabinets
cabinet

PGND Green and 6 OT OT terminal/Port One per


cable for yellow terminal/ for PGND cable power
the power PGND on the power distribution
distributio busbar of distribution box box
n box each
cabinet

PGND Green and 6 OT OT terminal/Port Two per


cable for yellow terminal/ for the PGND subrack
the subrack PGND cable on the
busbar of subrack
each
cabinet

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 67


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Cable Color Cross- Connect Connector Quantity


Name Sectional or Type Type 2/
Area 1/ Installation
Installati Position 2
mm2
on
Position
1

PGND Green and 6 OT OT terminal/ Eight per


cable for yellow terminal/ Grounding bolt cabinet
the cabinet Groundin on the cabinet
door g bolt on door
the base

PGND Green and 6 OT OT terminal/ One per


cable for yellow terminal/ Grounding point independent
the PGND of the fan subrack
independe busbar of independent fan
nt fan each subrack
subrack cabinet

The PGND cable for the independent fan subrack is different from the other PGND cables for
the BSC6900. Figure 7-5 shows the PGND cable for the independent fan subrack. Figure 7-6
shows the other PGND cables.

Figure 7-5 PGND cable for the independent fan subrack

Figure 7-6 Other PGND cables

7.2 Power and PGND Cable Connections


The following power cables and PGND cables should be installed on site: power cables and
PGND cables between the power distribution box and the PDF, and the PGND cables between
the cabinets.
Figure 7-7 shows the connections of the power cables and PGND cables.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 68


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-7 Connections of the power cables and PGND cables

NOTE

l Each cabinet must be configured with nine cables: four -48 V power cables, four RTN power cables,
and one PGND cable. Here, the four -48 V power cables and four RTN power cables are connected to
the rear panel of the power distribution box; the PGND cable is connected to the ground bolt (labeled

) at the rear top of the cabinet.


l The rear panel of the power distribution box is connected to the PDF through the external power cables
and is connected to the subracks through the internal power cables. For details of the power distribution,
see Distribution of Power Switches on the Power Distribution Box.
l It is recommended that the PGND cable of the cabinet be connected to the closest ground bar. When
the PDF is far from the cabinet, for example, the PDF is not in the same equipment room as the cabinet,
you should connect the PGND cable for the cabinet to the closest ground bar co-grounded with the
PDF rather than connect the PGND cable directly to the PDF.

CAUTION
Ensure that the 1 (-) and 1 (+) input terminals in areas A and B of the power distribution box are
connected to the 63 A output terminal of the PDF. Ensure that the 3 (-) and 3 (+) input terminals
in areas A and B are connected to the 100 A output terminal of the PDF. You must avoid
misconnections, which may affect the power requirements.

7.3 Principles of Routing and Binding the Power Cables and


PGND Cables
When installing the power cables and PGND cables, you should follow the routing and binding
principles.

Routing Principles
l Before routing the power cables and PGND cables, you should wrap the connectors with
PVC insulation tape to prevent the connectors from contacting the wiring terminals of the
PDF.
l The layout of power cables and PGND cables should facilitate future expansion.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 69


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

l The power cables and PGND cables should be routed separately from the signal cables.
l When power cables or PGND cables are laid parallel to signal cables, you should leave at
least 10 mm between the power cables (or PGND cables) and the signal cables inside the
cabinet and at least 100 mm outside the cabinet.
l When bending the power cables and PGND cables, you should ensure that the bending
radius is five times longer than the diameter of the cable.
l When adopting the underfloor cabling mode, you should reserve extra length of the power
cables at the cable inlet of the power distribution box on top of the cabinet. The purpose is
to facilitate plugging in and pulling out the cables. In addition, the cables must be laid neatly
at the top of the cabinet.
l When connecting power cables to the wiring terminals of the power distribution box, you
should route them in a straight manner and ensure that the cables are curved smoothly at
the bend, without crossing.

Binding Principles
l The power cables and PGND cables are bound separately from the signal cables.
l The space between the cable ties should be 200 mm.
l The types (100 mm, 150 mm, 300 mm, and 295 mm) of cable ties should be determined
on the basis of the number of cables.
l The cable ties should face the same direction.
l After binding the cables tightly, you should cut off the surplus part of each cable tie
completely for indoor cable ties and leave 3 mm to 5 mm for outdoor cable ties. The tails
of the cable ties should be trimmed.

7.4 Installing the Power Cables and PGND Cables Between


the N68E-21-N Cabinet and the PDF
There are two methods of installing the power cables and PGND cables between the N68E-21-
N cabinet and the PDF: overhead cabling and underfloor cabling. Select one of them as required.

7.4.1 Overhead and Underfloor Cabling Modes


According to the conditions of the equipment room, the cables can be led into the cabinet in
either overhead cabling mode or underfloor cabling mode.
External cables can be led into the cabinet through either the upper cable hole or the lower cable
hole. Each corner at the top and bottom of the cabinet provides a rectangular cable hole, as shown
in Figure 7-8.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 70


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-8 Cable holes of the cabinet

If the cable hole is covered with a rodent-proof cover, you need to remove the cover before the
cabling. Then, lead the cables through the cable hole and bind the cables. Place the rodent-proof
cover on the cable hole, and mark the area to be cut based on the cross section of the bound
cables. Then, use scissors to cut the area. Finally, reinstall the rodent-proof cover. Ensure that
the bound cables fit in well with the cover, that is, the cables fully occupy the hole and no side
clearance is left.

Overhead Cabling Mode


In overhead cabling mode, the cables are led out of the cabinet through the cable hole at the top
of the cabinet or through other paths upward, as shown in Figure 7-9. The cables for the related
devices in the cabinet are led out of the cabinet along the side of the cabinet. The overhead
cabling mode is suitable for equipment rooms with concrete floors.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 71


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-9 Overhead cabling mode

Underfloor Cabling Mode


In underfloor cabling mode, the cables are led out of the cabinet through the cable hole at the
bottom of the cabinet or through other paths downward, as shown in Figure 7-10. The underfloor
cabling mode is suitable for equipment rooms with ESD floors. When the underfloor cabling
mode is used, ensure that the height of the piled cables does not exceed 3/4 of the height of the
space under the ESD floor.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 72


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-10 Underfloor cabling mode

7.4.2 Installing the Power Cables and PGND Cables Between the
N68E-21-N Cabinet and the PDF in Overhead Cabling Mode
This section describes how to install the power cables and PGND cables between the N68E-21-
N cabinet and the PDF in overhead cabling mode.

Prerequisites
l The N68E-21-N cabinet that needs to be installed with power cables and PGND cables is
installed.
l The output power switches on the PDF are set to OFF.
l All the switches on the power distribution box of the N68E-21-N cabinet are set to OFF.
l For the installation, the power cables and PGND cables are available.
l The cable ties are available.
l The tools required are available - the diagonal pliers, handsaw, cable cutter, wrench, and
Phillips screwdriver.

Context
This document takes the PDF shipped with the Huawei equipment as an example to describe
how to install the cables. For details, see the documents shipped with the PDF. If other types of
DC power distribution cabinets are used on site, see the relevant documents for the cable
installation.

Figure 7-11 shows how to install the power cables and PGND cables between the N68E-21-N
cabinet and the PDF in overhead cabling mode.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 73


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-11 Installing the power cables and PGND cables between the N68E-21-N cabinet and
the PDF in overhead cabling mode

Procedure
Step 1 Determine the length of the required power cables and PGND cables by referring to the related
engineering design or by measuring the actual cabling route.
Step 2 Uncoil the power cable roll and the PGND cable roll on site. Obtain appropriate length of cables
by using the tape measure or other measuring instrument. Then, cut the cables by using the
handsaw (teeth space: 0.8 mm) or the wire cutter (KT35). When cutting the cables, you should
leave a little slack.

CAUTION
When laying out the cable, you should replace it with a new one if the reserved length is
insufficient. Do not make connectors or solder joints.

Step 3 Attach temporary labels to both ends of the cables and ensure that the contents of the labels are
appropriate for the easy recognition of cables. The contents of the temporary labels can be
consistent with those of the formal labels or can be determined according to your requirements.
Step 4 Lay the power cables and PGND cable according to the requirements for routing cables and
engineering requirements.
1. Lead the power cables and PGND cable out of the PDF through the upper cable outlet.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 74


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

CAUTION
l If the height difference between the cable tray and the top of the cabinet exceeds 800
mm, a downward cable ladder must be used.
l Ensure that the bending radius is five times longer than the diameter of the cable.

2. Lead the cables to the cable tray.


3. Lead the cables to the top of each N68E-21-N cabinet along the cable tray.

Step 5 Connect the power cables and the PGND cables to the N68E-21-N cabinet.
1. Find the 2-hole JG terminals from the accessories, and then make terminals for the power
cables and PGND cables on the N68E-21-N cabinet side by referring to Assembling the
JG Terminal and the Power Cable.
2. Fix the wiring terminal of the PGND cable to the ground bolt at the top back of the N68E-21-
N cabinet. The ground bolt is labeled .
3. Lead the RTN and -48 V power cables through the cable hole at the top of the cabinet until
they reach the input terminals of the power distribution box. Connect the RTN power cables
to the wiring terminal labeled + and the -48 V power cables to the wiring terminal labeled
-. Then, fasten the screws.

CAUTION
Input power is not allowed in the 2(+) and 2(-) input terminals. Connect the RTN and -48
V power cables respectively to input terminals 1(+), 1(-), and 3(+), 3(-).

Step 6 Connect the other end of the power cable to the PDF, and connect the other end of the PGND
cable to the PDF or the closest protection ground bar.
1. Remove the PVC insulation tape from the connectors of the cables. Determine the length
of the cables according to their installation positions, and then cut off the excess.
2. Determine the type of connectors for the power cables and PGND cables on the PDF side
according to the cable connection principle of the PDF and the engineering requirements.
Then, make connectors.
3. Connect the PGND cables, RTN power cables, and -48 V power cables to the corresponding
wiring posts on the PDF. Fasten all the screws.

----End

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

7.4.3 Installing the Power Cables and PGND Cables Between the
N68E-21-N Cabinet and the PDF in Underfloor Cabling Mode
This section describes how to install the power cables and PGND cables between the N68E-21-
N cabinet and the PDF in underfloor cabling mode.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 75


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Prerequisites
l The N68E-21-N cabinet that needs to be installed with power cables and PGND cables is
installed.
l The output power switches on the PDF are set to OFF.
l All the switches on the power distribution box of the N68E-21-N cabinet are set to OFF.
l For the installation, the power cables and PGND cables are available.
l The cable ties are available.
l The following tools are available - the diagonal pliers, cable cutter, wrench, and Phillips
screwdriver.

Context
This document takes the PDF shipped with the Huawei equipment as an example to describe
how to install the cables. For details, see the documents shipped with the PDF. If other types of
DC power distribution cabinets are used on site, see the relevant documents for the cable
installation.
Figure 7-12 shows how to install the power cables and PGND cables between the N68E-21-N
cabinet and the PDF in underfloor cabling mode.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 76


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Figure 7-12 Installing the power cables and PGND cables between the N68E-21-N cabinet and
the PDF in underfloor cabling mode

Procedure
Step 1 Determine the length of the required power cables and PGND cables by referring to the related
engineering design or by measuring the actual cabling route.
Step 2 Uncoil the power cable roll and the PGND cable roll on site. Obtain appropriate length of cables
by using the tape measure or other measuring instrument. Then, cut the cables by using the
handsaw (teeth space: 0.8 mm) or the wire cutter (KT35). When cutting the cables, you should
leave a little slack.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 77


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

CAUTION
When laying out the cable, you should replace it with a new one if the reserved length is
insufficient. Do not make connectors or solder joints.

Step 3 Attach temporary labels to both ends of the cables and ensure that the contents of the labels are
appropriate for the easy recognition of cables. The contents of the temporary labels can be
consistent with those of the formal labels or can be determined according to your requirements.

Step 4 Lay the power cables and PGND cable according to the requirements for routing cables and
engineering requirements.
1. Lead the cables out of the PDF through the lower cable hole. Under the ESD floor, route
the cables to the cable hole under each N68E-21-N cabinet. For the positions of the cable
holes for the N68E-21-N cabinet, see 7.4.1 Overhead and Underfloor Cabling Modes.
2. Lead the cables into the cabinet through the cable hole in the lower part of the N68E-21-
N cabinet. Along the back column of the cabinet, lead the cables upwards to the top of the
cabinet through the cable holes in the upper enclosure.
3. Cut appropriate size areas in the rodent-proof plastic cover plates, and then reinstall the
cover plates on the cable holes in the upper and lower enclosures. For the cover plate that
covers the cable hole in the upper enclosure, use screws to fix it.

Step 5 Connect the power cables and the PGND cables to the N68E-21-N cabinet.
1. Make 2-hole JG terminals for the power cables and PGND cables on the N68E-21-N cabinet
side by referring to Assembling the JG Terminal and the Power Cable.
2. Fix the wiring terminal of the PGND cable to the ground bolt at the top back of the cabinet.
The ground bolt is labeled .
3. Lead the RTN and -48 V power cables through the cable hole at the top of the cabinet until
they reach the input terminals of the power distribution box. Connect the RTN power cables
to the wiring terminal labeled + and the -48 V power cables to the wiring terminal labeled
-. Then, fasten the screws.

CAUTION
Input power is not allowed in the 2(+) and 2(-) input terminals. Connect the RTN and -48
V power cables respectively to input terminals 1(+), 1(-), and 3(+), 3(-).

Step 6 Connect the cables to output terminals of the PDF.


1. Remove the PVC insulation tape from the connectors of the cables. Determine the length
of the cables according to their installation positions, and then cut off the excess.
2. Determine the type of connectors for the power cables and PGND cables on the PDF side
according to the cable connection principle of the PDF and the engineering requirements.
Then, make connectors.
3. Connect the PGND cables, RTN power cables, and -48 V power cables to the corresponding
wiring posts on the PDF.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 78


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

7.5 Installing the PGND Cables Between Adjacent N68E-21-


N Cabinets
This section describes how to connect the upper, middle, and lower PGND busbars of one
N68E-21-N cabinet to those of its adjacent cabinet by using the PGND cables.

Prerequisites
l The cabinets to be connected with the PGND cables are installed.
l The switches on the power distribution boxes of all the cabinets are set to OFF.
l All the related power distribution switches on the PDF are set to OFF.

Procedure
Step 1 Use the PGND cables to connect the upper, middle, and lower PGND busbars of adjacent
cabinets, as shown in Figure 7-13.

Figure 7-13 PGND cables between adjacent N68E-21-N cabinets

----End

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 79


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

7.6 Checking the Power-on Status


This section describes how to check the power supply to the cabinet. It also describes how to
ensure that the power supply to the subracks and the power supply to the fan boxes and boards
in the subracks are normal.

Prerequisites
l The power cables and PGND cables are installed between the cabinet and the PDF.
l The power cables and PGND cables are installed in the cabinet.
l The subracks, fan boxes, and boards are installed in the cabinet.
l The tools required for the installation are available. The required tool is the multimeter.

Context
The cabinet uses the DC power supply. Technical Specifications of the Power Distribution Box
lists the specifications for the input power of the cabinet.

CAUTION
Correctly wear the ESD wrist strap. Ensure that the ESD wrist strap is properly connected to the
ESD connector on the cabinet.

Procedure
Step 1 Set the corresponding output switches on the PDF to OFF and all the output switches on the
power distribution box of the cabinet to OFF.

Step 2 Set the multimeter to the resistance scale and then measure the resistance at the power output
terminal for the PDF and at the input and output terminals for the power distribution box of the
cabinet. Ensure that there is no short-circuit between the -48V working power and the RTN
working ground. Ensure that there is no short-circuit between the -48V working power and the
PGND protection ground.

Step 3 Set the corresponding output switches on the PDF to ON and all the output switches on the power
distribution box of the cabinet to OFF.
Then, the power distribution box enters the self-check state. (The RUN and ALM LEDs on the
power distribution box are on at the same time and the buzzer sounds.) When the self-check is
complete, the power distribution box requests for registration at the SCUa board (the RUN LED
on the power distribution box blinks at 2 Hz) until the registration is successful (the RUN LED
blinks at 0.5 Hz). For the description about the status of LEDs on the power distribution box,
see LEDs on the Power Distribution Box.

Step 4 Set the multimeter to the voltage scale. Ensure that the output voltage of the PDF and the input
voltage of the power distribution box range from -40 V to -57 V.

Step 5 On a per subrack basis, set the corresponding two switches on the power distribution box to
ON.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 80


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 7 Installing the Power Cables and PGND Cables for the
N68E-21-N Cabinet Installation Guide N68E-21-N Cabinet

Step 6 Set the multimeter to the voltage scale. Use the multimeter to check whether the output voltage
of the power distribution box ranges from -40 V to -57 V. Check whether the fan box in the
subrack can be normally started and whether the power supply to the boards in the subrack is
normal.
l Normally, when the subrack is powered on, the STATUS LED on the panel of the fan box
blinks. In case of exceptions, immediately turn off the switches of the power distribution box
and PDF. Check whether the output voltage of the power distribution box is normal and
whether the power cables are installed properly. For the description about the status of LEDs
on the fan box, see LED on the Fan Box.
l Normally, when the subrack is powered on, the RUN LED on the panel of the board is ON
or blinks. If all the LEDs on a board are off, the board or the corresponding slot may be faulty.
Contact Huawei for technical support. For the description about the status of LEDs on the
board, see LEDs on the Boards.
l If the LEDs on all the boards in a subrack are off, immediately turn off the switches of the
power distribution box and PDF. Check whether the output voltage of the power distribution
box is normal and whether the power cables are installed properly.
Step 7 Repeat Step 5 and Step 6 to check the power supply to the three subracks in one cabinet.
Step 8 Repeat Step 1 through Step 7 to check the power supply to each cabinet.

----End

Follow-up Procedure
Record the check result in the corresponding table provided in Hardware Installation Record.
Set the corresponding output switches on the PDF to OFF and all the output switches on the
power distribution box of the cabinet to OFF.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 81


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

8 Installing the Accessories for the N68E-21-N


Cabinet

About This Chapter

This chapter describes how to install the front and back doors as well as side panels for the
N68E-21-N cabinet and how to install the PGND cables for the doors and side panels.

Prerequisites
l The cabinet is installed.
l The accessories for the cabinet are delivered to the site.
8.1 Accessories to Be Installed for the N68E-21-N Cabinet
The accessories to be installed for the N68E-21-N cabinet are front and back doors, side panels,
and the corresponding PGND cables.
8.2 Installing the Side Panels for the N68E-21-N Cabinet
A single N68E-21-N cabinet has four side panels, with two side panels on both the left and right
sides. When multiple N68E-21-N cabinets are combined in a row, a total of four side panels
need to be installed at the two ends of the cabinet row. When the N68E-21-N cabinet is combined
with other types of cabinets, you need to install the side panels where the cabinets are combined.
8.3 Installing the Front and Back Doors for the N68E-21-N Cabinet
This section describes how to install the front and back doors (four in total) for the N68E-21-N
cabinet.
8.4 Installing the PGND Cables for the Doors and Side Panels of the N68E-21-N Cabinet
Each door and each side panel of the cabinet need to be installed with a PGND cable.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 82


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

8.1 Accessories to Be Installed for the N68E-21-N Cabinet


The accessories to be installed for the N68E-21-N cabinet are front and back doors, side panels,
and the corresponding PGND cables.
Table 8-1 lists the accessories to be installed for the N68E-21-N cabinet.

Table 8-1 Accessories to be installed for the N68E-21-N cabinet


Accesso Installation Position Remarks
ry

Side See Exploded View of the N68E-21-N Side panels need to be installed at
panel Cabinet. both ends of a row of combined
cabinets. The side panels are
classified into left panels and right
panels.

Front and Both the front and back doors have


back a double-door structure: one left
doors door and one right door. The
methods of installing the front and
back doors are the same.

PGND The PGND cables connect the


cables for front and back doors as well as side
the doors panels to the base of the cabinet.
and side
panels

8.2 Installing the Side Panels for the N68E-21-N Cabinet


A single N68E-21-N cabinet has four side panels, with two side panels on both the left and right
sides. When multiple N68E-21-N cabinets are combined in a row, a total of four side panels
need to be installed at the two ends of the cabinet row. When the N68E-21-N cabinet is combined
with other types of cabinets, you need to install the side panels where the cabinets are combined.

Prerequisites
l For the installation, the side panels and M6x12 countersunk screws are available.
l A Phillips screwdriver with a long handle is available.

Context
Figure 8-1 shows how to install the side panels for the N68E-21-N cabinet.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 83


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

Figure 8-1 Installing the side panels for the N68E-21-N cabinet

1 M6x12 countersunk screw 2 Installation hole for the countersunk screw 3 Floating nut
4 Notch on the side panel 5 M6x16 screw assembly

Procedure
Step 1 Loosen the M6x16 screw assembly on the cabinet.
Step 2 Fit the three installation notches on the side panel downwards to the M6x16 screw assembly.

CAUTION
Figure 8-1 shows the direction of the installation notch.

Step 3 Fix the side panel into the open slot on the door head.
Step 4 Tighten the two M6x12 countersunk screws and the three M6x16 screw assemblies.

----End

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 84


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

8.3 Installing the Front and Back Doors for the N68E-21-N
Cabinet
This section describes how to install the front and back doors (four in total) for the N68E-21-N
cabinet.

Prerequisites
l To facilitate the operation, the front and back doors should be installed after the installation
of other hardware is complete.
l For the installation, the front and back doors of the cabinet are available.

Context
Figure 8-2 shows how to install the front and back doors for the N68E-21-N cabinet.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 85


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

Figure 8-2 Installing the front and back doors for the N68E-21-N cabinet

1 Movable pivot 2 Lower pivot 3 Pivot hole

Procedure
Step 1 Insert the lower pivot of the door into the pivot hole on the lower enclosure of the cabinet. Then,
install the lower edge of the door.
Step 2 Pull down the movable pivot, align the hole of the movable pivot with the pivot hole on the
upper enclosure of the cabinet, and then release the movable pivot to fix the door onto the cabinet.

----End

Follow-up Procedure
Record the installation result in the corresponding table provided in Hardware Installation
Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 86


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

8.4 Installing the PGND Cables for the Doors and Side
Panels of the N68E-21-N Cabinet
Each door and each side panel of the cabinet need to be installed with a PGND cable.

Prerequisites
l For the installation, the PGND cables for the doors and side panels are available.
l The following tools are available - the Phillips screwdriver and wrench.

Context
Figure 8-3 shows how to install the PGND cables for the doors and side panels of the N68E-21-
N cabinet.

Figure 8-3 Installing the PGND cables for the doors and side panels of the N68E-21-N cabinet

1 Front/rear door 2 Side panel 3 Ground screw on the 4 PGND cable for the
front/rear door front/rear door

5 Ground screw on the side 6 PGND cable for the side 7 Ground screws on the 8 Base
panel panel base

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 87


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 8 Installing the Accessories for the N68E-21-N Cabinet

Procedure
Step 1 Connect the PGND cables for the side panels. In a row of cabinets, connect the ground screw
on each of the left panels of the left-most cabinet to that at the bottom of the left-most cabinet
by using the PGND cable; connect the ground screw on each of the right panels of the right-
most cabinet to that at the bottom of the right-most cabinet by using the PGND cable, as shown
in Figure 8-3.
Step 2 Connect the PGND cables for the front and rear doors of each cabinet, as shown in Figure
8-3.

----End

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 88


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 9 Attaching the Engineering Labels to the Cabinets

9 Attaching the Engineering Labels to the


Cabinets

This chapter describes how to attach the engineering labels, including row and column labels,
to the cabinets.

Context
Figure 9-1 shows the row label.

Figure 9-1 Row label

Figure 9-2 shows the column label.

Figure 9-2 Column label

Procedure
Step 1 Attach the row labels to the cabinets.

Attach the row labels to the side panels of the cabinets that stand near the aisle at the two ends
of each cabinet row.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 89


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 9 Attaching the Engineering Labels to the Cabinets

If there is more than one row of cabinets, attach label A to the side panels at the two ends of the
first cabinet row that is the closest to the door of the equipment room, label B to the second row,
label C to the third row, and so on.
Step 2 Attach the column labels to the cabinets.
Attach the column labels to the door head of the cabinet front, with label 00 to the first cabinet
near the main aisle, 01 to the second one, 02 to the third one, and so on.

----End

Follow-up Procedure
Record the operation result in the corresponding table provided in Hardware Installation Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 90


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS 10 Attaching the Engineering Labels to the Power Cables and
N68E-21-N Cabinet Installation Guide PGND Cables

10 Attaching the Engineering Labels to the


Power Cables and PGND Cables

After installing the power cables and PGND cables, you should remove the temporary labels
from the cables and then attach the engineering labels.

Prerequisites
l The power cables and PGND cables are installed.
l A ballpoint pen and labels for attaching are available.

Procedure
Step 1 Remove the temporary labels from the power cables and PGND cables.
Step 2 Attach the engineering labels to the power cables and PGND cables by referring to Labeling
Power Cables.

----End

Follow-up Procedure
Record the operation result in the corresponding table provided in Hardware Installation Record.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 91


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 11 Checklist for the Cabinet Installation

11 Checklist for the Cabinet Installation

This chapter describes the items and specifications for checking the cabinet installation.
Table 11-1 lists the items and specifications for checking the cabinet installation.

Table 11-1 Checklist for the cabinet installation


SN Item

1 The cabinet layout complies with the engineering design.

2 The supports are positioned and spaced according to the schematic drawing of
installation holes if the equipment room has an ESD floor.

3 All supports are properly fixed to the floor if the equipment room has an ESD floor.

4 The support assembly is properly installed if the equipment room has an ESD floor.

5 All the front pallets for the ESD floor are installed at the same height if the equipment
room has an ESD floor that needs to be supported by front pallets.

6 The cabinet is well insulated from the support or ground.

7 The cover plates are properly installed at the top and bottom of the cabinet.

8 The accessories such as the side panel, front door, and rear door are properly
installed.

9 The row labels, column labels, and product labels are properly attached.

10 The ESD wrist strap is inserted into the ESD installation hole of the cabinet.

11 The connecting plates of the combined cabinets are properly installed.

12 The shockproof parts between multiple rows of cabinets are insulated.

13 All the screws are fastened. The flat washers and spring washers are mounted. The
spring washers are placed between the flat washers and the screws.

14 The cabinets are stable and orderly placed.

15 The adjacent cabinets are close to each other and are in alignment.

Issue 01 (2012-04-26) Huawei Proprietary and Confidential 92


Copyright Huawei Technologies Co., Ltd.
BSC6900 UMTS
N68E-21-N Cabinet Installation Guide 11 Checklist for the Cabinet Installation

SN Item

16 The vertical deviation of the cabinet is less than 3 mm.

17 All the cabinet side panels facing the aisle are properly aligned, with the maximum
deviation of 5 mm.

18 The surfaces of the cabinets are clean without any fingerprint or smudge. The paint
on the surfaces of the cabinets is intact. There is no dust, excessive cable tie ends,
or other sundries in the cabinets (even at dead corners).

19 All the labels, tags, and nameplates are complete, legible, and correct.

20 The front and rear doors of the cabinet open and close easily.

21 The modules in one cabinet are aligned from the top down.

22 All the filler panels are installed.

23 All the boards are installed in proper positions, and the DIP switches of the boards
are properly set.

24 The components and the connecting wires or cables of the cabinets are not detached
or damaged.

25 The paint on the components of the cabinets is in overall good condition.