Beruflich Dokumente
Kultur Dokumente
1
Crashing Activities
2
Time-Cost Tradeoffs in CPM
Basic Assumption: Some activities can be
expedited, at a cost
Why accelerate an activity?
Complete the task in a shorter duration,
thereby reducing the duration of the critical
path, thereby reducing the length of the
project
Avoid late penalties
Earn early completion incentive payments
Time Cost Problem: Determine the
optimum project duration based on time-
cost tradeoffs
Project & Activity Costs
PROJECT DIRECT COSTS: Directly assigned to work
package or activity
Normal costs for normal time
Direct labor expenses
Materials
Equipment
Subcontractors
INDIRECT EXPENSES: Cannot be associated with
any work package or activity
Overhead expenses
including supervisory expenses
administration
contractual penalties or early completion incentives
Consulting
TIME-COST RELATIONSHIP
Crashing costs increase as project duration decreases
Indirect costs increase as project duration increases
Reduce project length as long as crashing costs are less than
indirect costs
Min total cost = Total project cost
optimal project
time
Crash cost
time 5
Time & Costs: Normal vs. Crash
For the time-only CPM project schedule, we
typically assume that activity duration is fixed at
its NORMAL TIME, or the duration with the lowest
direct activity cost (i.e., NORMAL COST).
Normal
N
cost Cj
Time
Crash time tcj Normal time tN
j
CRASHING EXAMPLE
8
CRASH COST AND DURATIONS
11
CRASHING NEEDS TO START WITH?
SD = $60/day (least-cost slope)
Maximum of 10 days can be cut from this
schedule by reducing the duration of activity D
to the crash duration of 20 days.
12
PROJECT DATA NOW
Now Overall duration for project completion is 130
days
Now there are Multiple critical paths (B-F-E and B-C-D-
E)
Total DIRECT cost = $48300 + {$60 X10}= $48900.
Total Indirect Cost= $ 300 X 130= $ 39000
Total Cost of Project Completion=
$48900+ $ 39000 = $87900
( Overall cost & time gone down because of crashing !)
Further improvement Possible? Lets see
13
Available options for further crashing
1) Crash B @ $200/day ( Can be crashed for Max 5 days)
2) Crash E @ $ 120/day ( Can be crashed for Max 10 days)
3) Crash C and F @ ( $600 + $ 300) : $900/day
( Can be crashed for Max 10 days)
14
Updated Project costing now
Updated project duration= 120 days
Project Crashing activity E by 10 days will cost = $120*10 =
$1200
Updated Direct cost= $48900+ $1200= $ 50100
Updated In-Direct Cost= 120X300= $36000
Revised Project cost= $50100+ $36000= $ 86100
( Overall cost & time further gone down because of crashing !)
15
Further Improvement Possible?
Project duration = 120 days
Total project cost = $86100
There are now three critical paths:-
A
B-C-D-E
B-F-E
16
Available options for further crashing
1) Crash A&B @ ($200+ $100) : $300/day
( Can be crashed for Max 5 days [Why?])
Please note Cost incurred in crashing A &B is equal to cost saving
in the form of Indirect Cost therefore this option enable us to
reduce project completion time without any cost !
17
Updated Project costing now
Updated project duration= 115 days
Project Crashing activity A&B by 5 days will cost = $300X5 =
$1500
Updated Direct cost= $50100+ $1500= $ 51600
Updated In-Direct Cost= 115X300= $34500
Revised Project cost= $ 51600 + $34500 = $ 86100
22