LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

Method Statement
LDIP-P4-MS-BW-M-0 6

SANITARY FIXTURES INSTALLATION FOR


M&E WORK FOR BUILDING

NISHIMATSU CONSTRUCTION VIETNAM CO., LTD


IP OFFICE - LONG DUC INDUSTRIAL PARK PROJECT

GUIDANCE NOTES

1. Where this page is over-stamped with the words Controlled Copy this means:
a) Distribution is centralized - in this case from the Quality Manager.
b) Each copy is issued to a particular person or organization. If no longer required it should be
returned.
c) It is not to be photocopied either in whole or in part. Additional copies are available on request.
d) Copy holders will be automatically issued with any amendments. Responsibility for
incorporating such amendments rests with the copy holder.

01 12-Jan.-13 MR NHT MR PHONG

REV. DATE ME SAFETY BUILDING OTHER

No. ENGINEER OFFICER MANAGER

PREPARED BY REVIEWED BY REVIEWED BY

LDIP/MS/M/DOC/17 Page 1/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

Table of Contents

1. General...............................................................................................3
1.1 Purpose.........................................................................................3
1.2 Specification and BOQ.................................................................3
1.3 Referred construction drawings....................................................3
2. Scope of Works ..................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................3
3. Construction procedure and method statement.................................3
3.1 Scope of the manual....................................................................3
3.2 Execution of work........................................................................4
3.2.1 Flow chart.............................................................................4
3.2.2 Execution.............................................................................5
3.3 List of instrument & Material.........................................................12
4. Construction schedule........................................................................12
5. Organization.......................................................................................13
6. Inspection and test procedure............................................................14
7. Safety control......................................................................................15
8. Environmental control.........................................................................15
9. Risk assessment.................................................................................15
Attachments........................................................................................16

LDIP/MS/M/DOC/17 Page 2/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

CONTENT:

1 General:

1.1 Purpose:

The purpose of this method of statement is to guide and implement the standard
installation procedure of sanitary fixture for IP Office
1.2 Specification and BOQ:

Based on Contract document

1.3 Referred drawings:

Construction drawings of IP Office.

2 Scope of works:

The sanitary fixtures included all toilet area fixtures and pantry sink.

3 Construction procedure and method statement:

3.1. Scope of the manual

The scope of method statement covers Sanitary Fixtures Schedule, Accessories


Schedule, and Method of Installation, including detailed Standard Information for
Plumbing related work. Works will be carried out base on construction schedule and
approved shop drawings for M&E work for building at Long Duc Industrial Park such
as IP Office.

3.2 Execution of the work


LDIP/MS/M/DOC/17 Page 3/16File : 370962789.doc
LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

3.2.1 Work flow chart

Submission of Method
statement; get approval

Preparation work

Sanitary Fixture Installation


Works

Not
Rectification Inspection with
of Work NKC-THIKECO/ approved
NCC

Approved
JAC/KOTM/REE/
Cleaning
SEC & Touch up

Representative

LDIP/MS/M/DOC/17 Page 4/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

3.2.2. Execution

i. Preparation.

- Checks all shop drawings and confirm latest drawings are used.
- Confirm all material procured against material approval list.
- Ensure that fabrication details and methods are fully comprehended by the
workers.
- Prepare and check sanitary fixtures and necessary accessories including anchor
bolts for fixtures supports.
- Prepare tools and equipment such as, electric drilling machine, bar bubble level.
- Prepare safety signs and secure barricade working area.
- Workers with personal safety equipment.

ii. Sanitary Fixtures Installation works

Water closet installation

PLAN VIEW OF WATER CLOSET

LDIP/MS/M/DOC/17 Page 5/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

ELEVATION OF WATER CLOSET

LDIP/MS/M/DOC/17 Page 6/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

- Coordinate schedule of wall and floor finishing work before installation.


- Prepare protection for concrete floor slab area wooden sheet or plastic sheet for
protection.
- Mark anchor location point for support fix connection.
- Drill for anchor bolts setting and bracket support installation.
- Set install Water Closet bowl level check and fix tight anchor bolt.
- Set fix tank assembly flush lever and tank fittings and tighten joint.
- Connect angle valve and flexible hose for water supply.
- Recheck all joint connection tightness and proceed to water test.
- Clean up installed equipment and apply silicon around the water closet bowl.

Wash basin installation

PLAN VIEW OF WASH BASIN

LDIP/MS/M/DOC/17 Page 7/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

ELEVATION OF WASH BASIN

LDIP/MS/M/DOC/17 Page 8/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

- Coordinate schedule of wall finishing work before installation.


- Prepare protection for concrete floor slab area wooden sheet or plastic sheet for
protection.
- Mark anchor location point for support (bracket) fix connection.
- Drill for anchor bolts setting and bracket support installation.
- Set install Wash Basin level check and fix tight anchor bolt.
- Set fix faucet, install angle valve, and flexible hose for water supply.
- Connect p-trap wash basin drain to wall PVC pipe and keep tight connection, seal
gap to PVC with sealant or rubber and cover with escutcheon plate.
- Recheck all joint connection tightness and proceed to water test.

Urinal installation

PLAN VIEW OF URINAL

LDIP/MS/M/DOC/17 Page 9/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

ELEVATION OF URINAL

LDIP/MS/M/DOC/17 Page 10/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

- Coordinate schedule of wall finishing work before installation.


- Prepare protection for concrete floor slab area wooden sheet or plastic sheet for
protection.
- Mark anchor location point for support (bracket) fix connection.
- Drill for anchor bolts setting and bracket support installation.
- Set initial install Urinal, level check and fix tight anchor bolt.
- Set fix drain pipe sealer and re-install urinal fixtures, check level and tightness of
bracket support.
- Set fix flush valve for water supply.
- Recheck all joint connection tightness, apply silicon around urinal and proceed to
water test.

iii. Testing works

Water closet test operation

- Open Isolation valve and check all angle valve connection of fixtures for leak. If
leak repair connection immediately and proceed to testing.
- Test flush tank operation and adjust ball float valve for volume requirement.
- Check tank connection for leak.
- Repeat 3 times flushing for visual inspection.

Wash basin testing of joint connection

- Open Isolation valve and check all angle valve connection of fixtures for leak. If
leak repair connection immediately and proceed to testing.
- Plug drain of wash basin and fill up water up to overflow rim
- Unplug drain and check p trap connection for leak.
- Repeat 3 times for visual inspection.
- Regulate faucet water supply pressure through angle valve, minimized volume
water not to splash to wash basin when you open faucet.

Urinal test operation

- Open Flush valve and check all flush valve connection of fixtures for leak. If leak
repair connection immediately and proceed to testing.
- Test flush valve operation and adjust for volume requirement.
- Check drain connection for leak.
- Repeat 3 times flushing for visual inspection.

3.3. Instrument list

LDIP/MS/M/DOC/17 Page 11/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

No. Name Quantity Remark


1 Electrical extension cable 01 Set

2 Drilling machine 01 Set

3 Cutting & Grinding Machine 01 Set

4 Level Instrument 01 Set

5 Marker 01 Set

6 Hand Tools 01 Set

4. Construction schedule:

Installation of sanitary fixture will be closely coordinated with building work with
following approved construction schedule of building work

Please find the attached sheets: Mater Schedule

LDIP/MS/M/DOC/17 Page 12/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

5. Organization

MAIN CONTACTOR
NCC Project Manager

Building Manager

Safety Survey M&E QA/ QC


Manager Engineer Engineer Manager

SUBCONTACTOR
SANYO E&C

M&E Manager

Site Manager

Mechanical Safety, QA/QC


Engineer Officer

M&E Piping
Team

LDIP/MS/M/DOC/17 Page 13/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

6. Inspection and test procedure:

6.1 Purpose and Scope

We will follow the Management System and Quality Control plan

Sanitary fixtures inspection procedure

- Checking sanitary fixtures and accessories before installation


- Setting out location and level as per approval plan.
- Install sanitary fixtures and accessories, following correction procedure as
per method of statement
- Final inspection

6.2 Procedure

Form Material-Equipment request for approval: RFA-LDIP-P4-MS-BW-M-06,


Inspection and Testing Plan: ITP-LDIP-P4-MS-BW-M-06, Internal Inspection
Checklist: IIC-LDIP-P4-MS-BW-M-06, Request For Inspection: RFI-LDIP-P4-MS-BW-
M-06 and Photo Report shall be used to verify the works.
Verification is that the drawings are Good for Construction and that all formalities of
works are complied with:

Construction drawings/ working drawings, site instruction


Requirement of technical specification, inspection flowcharts
Completion of previous works and supplementary works
Request of inspection (item, place, time, attendant, stage)
Equipment/ plant/ instruments used for inspection/ test

The Site Engineer shall ensure that permit to work is issued from the construction
drawing and working drawing prior to commencing for each stage and also prior
permission to placement of each layer of material is issued by the Engineer if any.

LDIP/MS/M/DOC/17 Page 14/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

6.3 Inspection and testing plan

Please find the attached sheets: ITP-LDIP-P4-MS-BW-M-06

6.4 Documentation

Material-Equipment request for approval: RFA-LDIP-P4-MS-BW-M-06


Inspection and Testing Plan: ITP-LDIP-P4-MS-BW-M-06
Internal Inspection Checklist: IIC-LDIP-P4-MS-BW-M-06
Request For Inspection: RFI-LDIP-P4-MS-BW-M-06
Photo Report

7. Safety control:

As per the contractors safety obligations and policy, we will follow our
Occupational, Health, Safety and Rehabilitation plan and our Project Safety
Plan.
Take care when workers working over-head (installation of high level conduit).
Take care when workers doing on scaffolding.
Take care when workers doing with electrical equipment and welding machine.
Take care of building work surrounding.

8. Environmental control

We shall follow our Environment Management system

All works will be carried out in accordance with the requirements of the approved
Environmental Management Plan.

9. Risk assessment

Find the attached sheets: RA-LDIP-P4-MS-BW-M-06

LDIP/MS/M/DOC/17 Page 15/16File : 370962789.doc


LONG DUC INVESTMENT CO., LTD.

LONG DUC INDUSTRIAL PARK PROJECT

NISHIMATSU CONTRUCTION VIETNAM CO., LTD LDIP-P4-MS-BW-M-06

ATTACHMENTS

1. Risk assessment
Risk assessment- Conduit Works: RA-LDIP-P4-MS-BW-M-06
2. Inspection and test procedure
a. Material-Equipment request for approval: RFA-LDIP-P4-MS-
BW-M-06
b. Inspection and Testing Plan: ITP-LDIP-P4-MS-BW-M-06
c. Internal Inspection checklist: IIC-LDIP-P4-MS-BW-M-06
d. Request For Inspection: RFI-LDIP-P4-MS-BW-M-06
e. Photo Report
3. Attached Drawings.
4. Attached Master Schedule.