Sie sind auf Seite 1von 6

Proceedings of the 19th IAHR-APD Congress 2014, Hanoi, Vietnam

ISBN 978604821338-1

FLOOD ESTIMATION UNDER CHANGING CLIMATES

JAMES E. BALL(1)
(1) School of Civil and Environmental Engineering, University of Technology Sydney, Sydney, Australia, james.ball@uts.edu.au

ABSTRACT
Design flood estimation remains a problem for many professionals involved in the management of rural and urban
catchments. Advice is required regarding design flood characteristics for many design problems including the design of
culverts and bridges necessary for cross drainage of transport routes, the design of urban drainage systems, the design of
flood mitigation levees and other flood mitigation structures, design of dam spillways, and many environmental flow
problems. This advice is complicated further by the increasing requirement to consider the impact of changing climatic
states on design floods. Presented herein is a discussion of the design flood problem for both current and future climate
states.

Keywords: Floods, Hydroinformatics, Design, Climate Change

1. INTRODUCTION characteristic of concern has been the flood flow rate. This
historical focus of the design flood problem is shown by
Design flood estimation remains a problem for many
Robinson (1987) who, in discussing selection of design
engineering hydrologists. Advice is required regarding
floods, notes Hydrologic structures are required to perform in
design flood characteristics for the design of culverts and
a predictable manner over a wide range of discharges. In
bridges necessary for cross drainage of transport routes,
Australia this can vary from zero to very large flows.
the design of urban drainage systems, the design of flood
mitigation levees and other flood mitigation structures, An important aspect of estimating design flood
design of dam spillways, and many other situations. The characteristics is the need to consider both the hazard
flood characteristic of most importance depends on the arising from the magnitude of the design flood
nature of the problem under consideration, but typically it characteristic and the likelihood of that hazard occurring
is one of the following: or being exceeded. In other words there is a need to
consider the relationship between the magnitude and the
Flood flow rate typically, it is the peak flow rate of
exceedance probability of a design flood characteristic.
the flood hydrograph that is the desired design flood An example of this relationship is shown in Figure 1.
hydrograph characteristic; From a design flood perspective, therefore, it is the
Flood level similar to the flood flow rate, it is the analysis of data leading to the relationship shown in
peak flood level during the flood hydrograph that is Figure 1 that is fundamental to the estimation of the
the commonly desired design flood hydrograph quantile for the desired flood characteristic.
characteristic;
Flood rate of rise this design flood characteristic is a
concern when planning is undertaken for operational
floods;
Flood volume this design flood characteristic
becomes a concern when the design flood volume is a
major factor in the design problem. This situation
occurs when storage of a significant portion of a flood
hydrograph is used as part of a flood management
system; or
System failure the usual design flood problem is
located at a single point. There are a number of
design problems, however, where the issue becomes
one of multiple points within a system. Typical
examples of these problems include urban drainage
systems where the individual components of the Figure 1. Hazard - Probability Plot for Styx River at Jeogla
system are not statistically independent which is a
common assumption, and transportation routes with There are many approaches for the estimation of design
multiple cross drainage structures of one or more flood characteristics for current climate regimes with the
river systems. appropriateness of these approaches dependent on the
problem. For estimation of design flood characteristics
While all of these flood characteristics have been noted as under future changed climate regimes, there is a need to
being of interest to flood designers, the dominant assess the suitability of these alternative approaches.

1
Most of the approaches currently used can be framed as been recorded if a gauging station were located at the
an exercise in data mining since the available data is point of interest (a Catchment Modelling method).
analysed to develop the desired relationship between the Selection between the two alternative approaches for use
hazard arising from the magnitude of the flood when sufficient historical data is not available usually
characteristic and the likelihood of that hazard occurring. depends on the need for the design flood estimate (i.e. the
problem being considered) and, typically, will vary with
The purpose of this paper is to provide an overview of application.
alternative approaches for generation of the information
necessary for estimation of a design flood quantile. Also It is worth noting that, for estimation of design flood
included will be a discussion of the associated quantiles for future climate regimes, only techniques that
assumptions for these alternative approaches. can be categorised as Regional Flood Frequency
Furthermore, the implications of non-stationary climatic Estimation and Catchment Modelling are available as
conditions on the estimation of flood quantiles are sufficient historical data cannot be available.
explored.

3. AT-SITE FLOOD FREQUENCY ANALYSIS


2. APPROACHES FOR ESTIMATION OF As shown in Figure 2, where sufficient historical
CURRENT CLIMATE DESIGN FLOOD information is available, estimation of the desired flood
QUANTILES parameter can be undertaken using at-site flood frequency
The desired flood characteristics to be used for the design analysis methods (see, for example, Jin and Stedinger
must be interpreted from a statistical viewpoint. This 1989, and Kuczera 1999). When these methods are
contrasts with the analysis of the flood characteristics for a applied, the desired design flood quantile is obtained from
historical event where a deterministic viewpoint is an analysis of the statistical pattern of the recorded data.
appropriate for consideration of the desired flood Most FFA techniques are based on the calibration of a
characteristics. There are two alternative situations when statistical model to the recorded historical data; in this
design flood characteristics are required; these are: context, the calibration consists of determining the generic
Sufficient historical information available; and values of the distribution parameters that result in
development of a relationship between flood magnitude
Insufficient historical information not available.
and exceedance probability that replicates historical data.
Based on these two alternative situations, a conceptual As part of this calibration process, the reliability of
framework for estimation of design flood quantiles has historical data needs consideration to ensure that robust
been developed and is shown schematically in Figure 2. predictions are attainable; this is achieved usually through
This conceptual framework is being used in the estimation of the confidence limits for the statistical
development of the current revision to Australian Rainfall model.
and Runoff; a summary of this revision was presented by
An inherent assumption for application of FFA
Ball and Phillips (2005) while more complete details are
approaches is that the historical data is stationary. In other
available from www.arr.org.au.
words, the statistical characteristics of the historical data
remain constant with time. A number of studies (see, for
example, Kiem and Franks, 2004) have shown that this
assumption is not valid over short time frames due to
climatic cycles such as the Interdecadal Pacific Oscillation
Catchment (IPO) but may be approximately valid over long time
Modelling
Insufficient periods. In this context, a long time period is one where
Historical Data data is available for at least one full climatic cycle (and
Regional Flood
Frequency preferably more).
Design Flood
Estimate
Estimate The appropriateness of estimating design floods under
At-Site Flood future climate regimes using FFA techniques, therefore,
Sufficient
Historical Data
Frequency needs to consider both the availability of data and the
Analysis applicability of the assumption of stationarity. As
historically recorded data cannot be available for future
climate regimes, the expected lack of stationarity in the
data does not preclude application of FFA approaches; it
Figure 2. Design Flood Estimation Approaches is the absence of the historical data that precludes
application of FFA techniques for prediction of design
flood quantiles under future climate regimes.
As shown in Figure 2, where sufficient historical
information is available, estimation of the desired flood
quantile can be undertaken using at-site flood frequency 4. REGIONAL FLOOD FREQUENCY
analysis methods (FFA). ESTIMATION
When sufficient historical information is not available, Regional Flood Frequency Estimation methods (RFFE) are
estimation of the desired flood quantile can be obtained a category of data-driven design flood quantile estimation
either through use of a regional regression model (a techniques based on regression; in other words, recorded
Regional Flood Frequency Estimation method) or through data and estimated flood quantiles are analysed to enable
generation of data equivalent to the data that would have
prediction of design flood quantiles at locations remote

2
from gauged catchments. As a result RFFE methods are contributions of the predictor variables to the estimated
applicable only in regions where the catchment and design quantile.
climatic conditions are similar to those used for The use of RFFE methods developed for current climate
development of the regression relationships. This regimes to estimate design flood quantiles for future
applicability has implications on the use of RFFE methods climate regimes is based on the assumption that projected
to estimate design flood quantiles with future climate changes in the catchment and climate conditions can be
regimes. reflected by changes in the selected predictor variables.
All RFFE techniques are based on the results of an FFA at For example, Haddad et al. (2011) found that rainfall
monitored locations. Hence, the reliability of an RFFE intensity was a useful predictor variable while the major
method is constrained by the reliability of the FFA at catchment related predictor variable was the catchment
monitored locations. Once the FFA information is area. If these two predictor variables are used to estimate
available, development of an RFFE technique consists of design flood quantiles for future climate regimes, then it is
two principal steps: only the rainfall intensity that will need adjustment as the
catchment related predictor variables would be expected
(i) Formation of regions or the formation of regions to remain consistent.
comprising catchments with similar flood response.
Historically, these regions have been assumed to be
based on geographic proximity but this is not an 5. CATCHMENT MODELLING
essential assumption; and
Catchment modelling techniques are the third approach
(ii) Development of regional estimation models through used for estimation of the design flood quantile.
the development of regression equations, or models, Conceptually, the aim of catchment modelling is to
to predict design flood quantiles. generate data that would have been recorded if catchment
monitoring had been in place for the event, or sequence of
In developing an RFFE, formation of regions can be based events, being considered. Hence, the generated data
on proximity in geographic or catchment attribute space. should have the same characteristics as the historical data
The regions are based on the explicit assumption of that could have been monitored at the site or sites of
regional homogeneity. The decision on what constitutes interest. Furthermore, data generated using catchment
a homogeneous region for the purposes of regional flood modelling techniques should be analysed using the same
estimation depends on the methods used, more techniques as applied to the historical data obtained from
specifically on the extent to which differences in flood catchment monitoring.
characteristics can be expressed through parameters in the Situations where catchment modelling maybe needed
regionalisation method. Further details are given by include:
Rahman et al. (2011).
Events of a suitable magnitude have not been
In developing an RFFE technique suitable for application recorded and there is a need to extrapolate from
in Australia, Haddad et al. (2011) discuss the predictor recorded events to more extreme flood events;
variables found to be significant in predicting design flood Data has not been monitored at the point of interest
quantiles for existing catchment and climate conditions. and there is a need to generate data at a point remote
There are numerous ways of categorising the main from the monitoring points; and
predictor variables. Nonetheless, for the discussion Changed management options for a catchment are
herein, the main predictor variables will be categorised as being considered and there is a need to predict the
being either rainfall related or catchment related. For impacts of the proposed changes on the design flood
application in Australia, the main predictor variables have characteristics prior to implementation of the
been found to be: proposed catchment management strategy.
Rainfall related predictor variables - the design
rainfall intensity for a duration representative of the Alternative techniques for generation of the desired data
catchment response time, and the gradient of the can be categorised as:
Intensity-Frequency-Duration relationship; and
Catchment related predictor variables catchment Single burst (either the design peak burst of an event
area and a factor representing catchment shape. or the design total event) technique;
Monte-Carlo technique (see, for example, Weinmann
The basis of the regression undertaken by Haddad et al. et al., 2002); or
(2011) was a generalised least squares technique which Continuous simulation technique (see, for example,
can be expressed as Wagener and Wheater, 2006).
n
0 X
k 1
i ik i i (1) Historically, applications of techniques considering a
single burst have been the more popular. The alternative
(1)
approaches, however, are gaining in popularity as
Where is the prediction, k are the regression computing capacity increases.
coefficients, Xik are the predictor variables, i and i are the
random and residual model error respectively. In the Where the single burst technique has been implemented
interpretation of equation 1, it should be noted that the with an assumption that the frequency of the rainfall is
predictor variable coefficients represent the relative transformed to the frequency of the resultant flood

3
characteristic, it can be argued that the method as applied model being used to analyse the catchment response to a
is an RFFE technique where the catchment model is a rainfall event. If the probability of the event is required
complex regression relationship. This question becomes also, then the catchment simulation technique that needs
more relevant when implementation of the approach to be employed is either a Monte-Carlo or a Continuous
requires values of the parameters to be selected on the Simulation approach.
basis that the transformation of rainfall frequency to flood
Inherent in the use of a catchment model for prediction of
frequency is ensured. An example of this approach
flood flows under future climate regimes are assumptions
(commonly referred to as AEP neutrality) is provided by
related to the parameters necessary for implementation of
Hill et al. (1998) who developed a method of estimating
the modelling system. While many of these parameters
loss model parameters that are likely to result in the
have the appearance of a physical basis, the values
frequency of the rainfall being transferred to the frequency
implemented tend to be empirically derived; in other
of the design flood flow. Implicit in the adoption of this
words, the parameter values adopted are those that result
approach is the assumption that AEP neutral parameter
in the best calibration and validation of the catchment
values are available from studies analogous to that of Hill
modelling system rather than a value that is derived from
et al. (1998).
the physical system. Hence, for application of the
It is possible to use a single burst approach without the catchment modelling system to assess the catchment
assumption of AEP neutrality. In these circumstances, the response under future climate regimes, it is necessary to
catchment model is being used to analyse the catchment assume that the values of these parameters will remain
response to a design rainfall event. In these situations, the consistent with those determined for the current climate
probability of the flood event is unknown. regime. As a result, the impact of factors influencing
floods incorporated in these catchment modelling system
When either of the other two alternative techniques,
parameters cannot be determined in a rigorous manner.
namely a Monte Carlo or a Continuous Simulation
These factors include:
technique, are applied for generation of the data, it is
necessary to undertake a statistical analysis of the Changes in soil structure;
generated data to develop an estimate of the design flood Changes in vegetation; and
quantile. This statistical analysis is required as the aim of Geomorphic changes to drainage networks arising
either technique is the generation of data that could have from changes in flow regimes.
been recorded if a gauge was present and the catchment
conditions reflected in the model parameters occurred. Application of a catchment simulation approach under
Hence, application of a catchment simulation approach current climate regimes requires calibration and validation
using these techniques reflects a different conceptual basis of the modelling system parameters and structure prior to
to that necessary for a single burst approach with AEP use for estimation of the design flood characteristics.
neutrality. These different conceptual bases are shown During this calibration phase, the primary aim is the
schematically in Figure 3. selection of parameter values that ensure the modelling
system adequately replicates the catchment response; in
Catchment other words, the primary aim is determination of generic
Modelling for values for the many parameters in the modelling system.
Design Floods
While the need for estimation of parameter values is
needed for any flood estimation technique, the focus
herein will be on the estimation of parameter values for
Data use in catchment modelling techniques. Fundamental to
AEP Neutral
Generation this discussion is the concept that all predictions obtained
from systems of models for prediction of catchment
response to either individual storm events or sequences of
storm events will contain residuals, or differences between
Monte-Carlo Continuous the predicted and recorded values. While these residuals
Single Event arise from multiple sources during the modelling process,
Simulation Simulation
the principle sources, following Kuczera et al. (2006), can
Figure 3. Alternative Catchment Simulation Approaches
be classified as:

Process errors;
The utility of applying a catchment simulation approach Structural errors;
for estimation of design flood quantiles under future Parameter errors; and
climate regimes needs to consider the relevant conceptual
Data errors.
basis. AEP neutral parameter values are unlikely to be
available as the studies necessary for development of
these values requires historical flow data for the future The process errors arise from the difference between the
climate regime; historical flow data will not be available conceptual process incorporated in the modelling system
until the future climate regime occurs. and the actual process within the catchment; in other
words, the process errors arise from the need for
Hence, when considering future climate regimes, the representation of physical processes in a mathematical
conceptual basis for application of catchment simulation formulation. The magnitudes of these errors are
that needs to be employed is one of predicting the data influenced directly by the degree of simplification within
that will be recorded when the future climate regime the modelling system. For example, use of one-
occurs. In other words, application of catchment dimensional and two-dimensional river models result in
simulation in these situations requires the catchment differing simplifications and different errors. It is worth

4
noting, however, that additional complexity in the process When values for spatially distributed parameters are
model may not result in a reduction in residuals due to the sought, the concept of equifinality becomes increasingly
increased number of parameters necessary for the more relevant. This is illustrated in Error! Reference source not
complex model. found. where the Sum of Squared Error (SSE) for various
values of the conceptual
width of a single
subcatchment is shown fo
10,000 alternative values. As
shown in this figure, similar
values of the SSE can be
obtained over a wide range of
values.
Also illustrated in this figure
is the need to consider sets of
parameter values rather than
the value of a single
parameter. The same value
of the conceptual width
Figure 4. Alternative Rainfall Loss Models parameter can result in many
values of the SSE; these
Structural errors are the result of the manner in which the multiple SSE values are the result of different values for
various process models are combined to provide the the other parameters necessary for the operation of the
catchment modelling system. In many situations, catchment modelling system.
alternative structures are available. For example, shown
The last form of error is the data errors. While there are
in Figure 4 are the two alternative conceptual model
many types of data errors, the characteristic of these errors
structures presented by Ball et al. (2011) for incorporation
are that they represent the difference between the true
of rainfall losses in a catchment model. As illustrated
value of the monitored data and the value recorded in the
through this example, structural errors are linked to
database. An example of errors of this type are those
conceptualisation of processes in the catchment model.
errors arising from the need to extrapolate the rating table
Hence, the distinction between a process model and a
for a gauging station above the highest gauging to enable
structural error is diffuse and, in many cases, difficult to
transformation of the recorded level to an equivalent flow;
quantify. This difficulty is shown also through
errors arising from this source were the focus of Kuczera
consideration of Umakhanthan and Ball (2005) who
(1999). Note that, in addition to the extrapolation error, a
investigated the influence of the rainfall model (the spatial
measurement error associated with the recording of the
and temporal distribution of rainfall across the
level also occurs.
catchment). Errors in the rainfall model could be
classified as either a process error or a structural error As previously discussed, the focus of the calibration and
depending on the viewpoint of the analyst. validation of a catchment modelling system for generation
of data necessary for design flood estimation is
The third form of errors are the parameter errors. For
minimisation of the residual. While the parameter error
discussion of parameter errors, there are two alternative
generally is the major concern, the alternative forms of
cases that need consideration. The first of these cases is
error cannot be neglected. The need for this is discussed
where sufficient moniotored data is available for
by Choi and Ball (2002) who showed that minimising the
estimation of the parameter values using data from the
prediction residual can result in degraded predictions for
catchment. The second case occurs where there is
alternative events. In other words, the parameter values
insufficient data available for estimation of parameter
that minimise the prediction residual include corrections
values using data from the catchment and hence
for the non-parameter errors that occurred during the
estimation of parameter values is based on regional
event.
relationships and other inference models. An example of
the use of inference models for estimation of parameter
values is presented by Choi and Ball (2002) who
investigated the use of land-use classifications for 6. CONCLUSIONS
prediction of the imperviousness of subcatchments. Within Australia, Pilgrim (1987) is the primary guideline
document used for prediction of design flood quantiles.
In both cases, parameter errors arise from differences
While this edition of Australian Rainfall and Runoff and
between the true value of the parameter and that used in
the simulation. Residuals arising from errors of this type its predecessors have served the engineering profession
and the general community well, in the period since the
have been the focus of significant historical research with
release of the previous edition, a number of developments
a significant volume of this research focussed on the
have arisen. Consideration of these developments
problem of obtaining optimal or near optimal values for
resulted in the decision by Engineers Australia to prepare
the modelling system parameters. Arising from this
research has been the concept of equifinality (see Beven another edition of Australian Rainfall and Runoff. As part
of this revision, the problem of estimating design flood
and Binley (1992) which can be paraphrased as there are
quantiles has been recast as a problem in data generation
multiple sets of parameter values that will result in similar
and analysis; in other words, a the problem of estimating
system performance.
design flood quantiles has been recast as a problem in
hydroinformatics.

5
Jin, M and Stedinger, JR, (1989), Flood
250 frequency analysis with regional and historical
information, Water Resources Research,
200
25(5):925-936.
Kiem, AS and Franks, SW, (2004),
Multidecadal variability of drought risk -
150
eastern Australia, Hydrological Processes,
18(11):20392050
Sum Squared Error

100 Kuczear, G, (1999), Comprehensive at-site


flood frequency analysis using Monte Carlo
Bayesian inference, Water Resources Research,
35(5):1551-1558.
50

Kuczera, G, Kavetski, D, Franks, S and Thyer,


0 M, (2006), Towards a Bayesian total error
0 200 400 600 800 1000 1200
analysis of conceptual rainfall-runoff models:
Subcatchment Width
Characterising model error using storm-
dependent parameters, Journal of Hydrology,
Figure 5. Subcatchment Conceptual Width
331(1-2):161-177.
Pilgrim, DH, (1987), Australian Rainfall and
In addition, the desire to predict design flood quantiles
Runoff: A guide to flood estimation, The Institution of
for potential future climate states further emphasizes the
Engineers Australia, Barton, ACT, Australia.
need to consider the philosophy of the analysis
Rahman, A, Haddad, K, Zaman, M, Kuczera, G and
approaches and the assumptions used in generation of the
Weinmann, PE, (2011), Design flood estimation in
necessary data for the analysis approach for assessment of
ungauged catchments: A comparison between the
the reliability of the predictions.
Probabilistic Rational Method and Quantile Regression
Technique for NSW, Australian Journal of Water
Resources, 14(2):127-139.
ACKNOWLEDGEMENTS
Robinson, DK, (1987), Selection of design floods, Chapter
The ideas expressed herein have been developed as part of 12 in Pilgrim, DH, Australian Rainfall and Runoff: A
the revision of Australian Rainfall and Runoff. This Guide to Flood Estimation, The Institution of
revision has been supported by the Department of Climate Engineers Australia, Barton, ACT, Australia.
Change and Energy Efficiency, Geosciences Australia, and Umakhanthan, K and Ball, JE, (2005), Rainfall Models for
Catchment Simulation, Australian Journal of Water
the Bureau of Meteorology. In addition, there has been
Resources, 9(1):55-67.
extensive in-kind support from the members of Engineers
Wagener, T and Wheater, HS, (2006), Parameter
Australia.
estimation and regionalisation for continuous rainfall-
runoff models including uncertainty, Journal of
Hydrology, 320:132-154.
REFERENCES Weinmann, PE, Rahman, A, Hoang, TMT, Laurenson EM,
Ball, JE, Babister, KM, and Retallick, M, (2011), Revisiting and Nathan RJ, (2002), Monte Carlo simulation of flood
the design flood problem, Proceedings 34th IAHR frequency curves from rainfall - the way ahead,
Congress, Brisbane, Australia, pp 31-38, ISBN 978-0- Australian Journal of Water Resources, 6(1):71-80
85825-868-6
Ball, JE and Phillips, BC, (2005), Guiding Australian
Hydrologic and Hydraulic Practice into the 21st
Century Development of 4th edition of Australian
Rainfall & Runoff, Proc. XXX1 IAHR Congress, Seoul,
Korea, Sept 2005.
Beven, K, and Binley, A, (1992), The future of distributed
models: model calibration and uncertainty prediction,
Hydrological Processes, 6:279-298.
Choi, KS and Ball, JE, (2002), A generic calibration
approach: Monitoring the calibration, Proc. 2002
Hydrology and Water Resources Symposium, Melbourne,
Australia, I.E.Aust.
Haddad, K, Rahman, A, and Weinmann, PE, (2011),
Estimation of major floods: Applicability of a simple
probabilistic model, Australian Journal of Water
Resources, 14(2):117-126.
Hill, PI, Mein, RG and Siriwardena, L, (1998), How much
rainfall becomes runoff? Loss modelling for flood
estimation, Industry Report 98/5, Cooperative Research
Centre for Catchment Hydrology, Department of Civil
Engineering, Monash University, Clayton, Australia,
ISSN 1039-7361

Das könnte Ihnen auch gefallen