Beruflich Dokumente
Kultur Dokumente
SECTION 2
DEMOLITION
DEMOLISHING STRUCTURES
GENERAL
- GS 2013 / S2 / Page 1 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
DEMOLITION SUB-CONTRACTOR
" If the sub-contractor or any of his agents or employees are found to have offered
or given advantage, gratuity, bonus, discount, bribe or loan of any sort to any
agent or employee of the Contractor, Hong Kong Housing Authority or Housing
Department, the Contractor shall at liberty forthwith terminate the employment of
the sub-contractor under the sub-contract. The Contractor, Hong Kong Housing
Authority or Housing Department shall hold the sub-contractor liable for any loss or
damage which the Contractor, Hong Kong Housing Authority or Housing
Department may thereby sustain. "
(2) Before execution of the sub-contract works, submit to the SO a signed copy of the
sub-contract or written confirmation signed by the Contractor and the sub-
contractor confirming that the conditions stated in Sub-clause (1) above have been
included into the sub-contract.
- GS 2013 / S2 / Page 2 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
DESIGN
GENERAL
(1) Comply with all requirements relevant to demolition works issued by the
Government of HKSAR and / or all relevant statutory authorities;
(2) Where this Specification includes provisions additional to, or more stringent than
those of the Building Regulations, the provisions of this Specification will prevail
overall.
2.07 Non-compliance
(1) In the event of non-compliance with the restrictions specified regarding the
method of demolition to be employed and the sequence of operations to be
followed, an Instruction to cease work may be issued by the SO;
(2) The contractor shall bear any extra time or cost compensation in respect of or
resulting from such Instruction to cease work.
- GS 2013 / S2 / Page 3 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(c) Check that assumptions made in the design of temporary works and
method statements are validated on Site;
(d) Prepare a risk assessment report with the Safety Officer including an
inspection schedule for all staff such as RSE, site engineer, Safety Officer,
site agent, site supervisor / foreman on all critical activities in demolition
work;
(e) Pay regular site visits for proper control of the works and submit reports
after each visit to certify the work is safe;
(f) Carry out inspections on other activities which, in his professional
judgement, are critical and require close supervision;
(3) The frequency of RSE's visits shall be a minimum of two visits per each month;
(4) In case of change of RSE, the new RSE has to endorse and re-submit the method
statements prepared by the former RSE and take up the role of Contractor's
Representative and the highest grade TCP in the Contractor's Stream under SP;
(5) Where demolition works affecting slopes and retaining wall, appoint a Registered
Geotechnical Engineer (RGE) registered under Buildings Ordinance for the
preparation and endorsement of the geotechnical report / supporting
documentation for the submissions as mentioned in above Sub-clause (1).
2.09 Survey
Prior to commencement of Work,
(1) Visit the Site and inspect the appropriate drawings and demolition plan as issued
by SO to ascertain the extent and scope of the demolition works required;
(2) Identify demolition procedures for any unconventional structural elements.
(1) Within 14 days following the notified date for the commencement of the Works,
carry out survey on the presence of wastewater, hazardous materials, matters
arising from toxic chemicals, etc. and possible presence of materials which can
contribute to contaminations on the environment;
(2) Submit method of removal for SOs approval within 14 days in case of any of these
materials being identified.
- GS 2013 / S2 / Page 4 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
- GS 2013 / S2 / Page 5 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(3) The method statements shall also comply with the following codes:
- GS 2013 / S2 / Page 6 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
Submit Form ICU 14A to notify the SO of the completion of the demolition works as
detailed in the demolition plan at least 32 days prior to the completion of the demolition
works.
MATERIALS
2.21 Hardcore
Brick rubble or other hard materials as clause 3.09 (b) arising from the demolition may
be re-used as hardcore.
- GS 2013 / S2 / Page 7 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
WORKMANSHIP
GENERAL
2.23 Sequence
(1) Do not proceed with the demolition of the building and associated structures
before all reusable and recyclable materials as specified in clause 2.20 are
removed from the building or the structure;
(2) Unless otherwise approved by SO, carry out demolition work on a floor to floor
basis commencing at roof / top floor level as applicable;
(3) Do not dismantle any existing steel props forming part of the structural
strengthening works in a floor prior to the demolition of that floor;
(4) Ensure all operators and workers involved understand clearly the method and
sequence of demolition. Draw sketches with explanation in Chinese illustrating the
work sequences and post them in a conspicuous position on Site.
SUPERVISION
- GS 2013 / S2 / Page 8 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(3) The submitted SP shall include the following additional safety supervision
requirements at critical stages of the works unless otherwise approved by SO:
Contractor's Stream
Critical Stages of the Works
AS CR/T5Note T4 T3 T2 T1
Full Full
Cantilevered Structures Bi-weekly Bi-weekly Full Time -
Time Time
Full Full
Factory Block Bi-weekly Bi-weekly Full Time -
Time Time
Note: As specified in clause 2.08, the RSE shall take up the role of Contractor's
Representative (CR) and the highest grade TCP in Contractor's Stream under
SP.
(2) The appointed TCP shall oversee the entire process of demolition works and whose
duties include but not limited to:
(3) Post details of appointed TCPs in the specified Form ICU20 in a prominent position
adjacent the Works.
2.27 Flagman
(1) Provide, operate and maintain, including all necessary cables, wirings, lightings
and other accessories, a video recording system to record the entire demolition
process with the following essential features:
(a) The video cameras used in the system should be of high resolution,
lowlight and colour type;
(b) Power backup should be provided to cater for accidental breakdown of the
power supply to the system;
(c) Videos captured by the system shall be recorded continuously without
break unless agreed by SO; and
(d) Videos shall be captured in a format acceptable to SO.
- GS 2013 / S2 / Page 9 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(2) Install a minimum of 6 nos. of video cameras per block at strategic locations as
specified by SO. Re-locate the video cameras from time to time to suit the
progress of the demolition works as instructed by SO;
(3) Securely protect the video cameras from being damaged or blocked so that the
entire demolition process including movement of debris and the overall sequences
of demolition can be recorded;
(4) Design and construct all necessary temporary works, including any supporting
frames and protections, for the video cameras and their accessories, even at high
level;
(5) Provide the software and hardware for SO's viewing the recorded videos and keep
the videos for at least 14 days;
(6) Post sufficient notices at conspicuous positions to notify the workers and staff
about the purpose of video recording system in accordance with Data Protection
Principles set out in the Personal Data (Privacy) Ordinance.
- GS 2013 / S2 / Page 10 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
- GS 2013 / S2 / Page 11 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(b)
(i) Unless otherwise specified, construct bamboo scaffolding in single row;
(ii) Construct bamboo scaffolding in double row unless otherwise specified
below:-
- The scaffolding is solely used for fixing enclosure sheeting to confine dust
and debris within the building under demolitions; and;
- No workers shall be working on the scaffolding except for installing,
repairing, dismantling of the scaffolding and during emergency; and
- Single row scaffolding is stable.
(c) Maintain height of screen at a minimum level of 1000 mm above the structure
being demolished;
(d) Construct screen in 3 layers, with minimum overlapping width of 300 mm,
and fix screen to the frame at regular intervals - the innermost net of
minimum 3.5 mm diameter heavy duty nylon (maximum mesh grid opening
50 mm), tarpaulin sheet and the outermost nylon net of minimum 1.0 mm
diameter (maximum mesh grid opening 20 mm), all materials use shall resist
ultra-violet light deterioration;
(e) For scaffoldings higher than 15 m above the ground floor level, provide steel
brackets anchored to the existing structure or other support system at
interval of not more than 15 m to support the scaffolding;
(f) Tie scaffolding to the buildings at intervals of not more than 4 m in both
horizontal and vertical directions to firm supports to guard against storms /
typhoon. Check ties effectively restraining scaffolding at all times, particularly
before and after storms / typhoons;
(g) Dismantling of the scaffolds shall coincide with the demolition progress. When
the wall ties are disconnected due to the demolition of the building structure,
the unsecured section of the scaffoldings shall be removed accordingly. In all
times, the unbraced sections shall not be higher than 2 m from the nearest
anchor;
(h) Inspect and reinstate the ties for scaffolding if any of the ties are fixed onto
materials or fixtures specified in 2.20.
(4) Provide additional protective canopy for blocks close to the streets as directed by
SO;
(5) Carry out vibration monitoring at locations specified by SO during demolition and
the peak particle velocities at these locations specified shall not exceed 15 mm /
second for prolonged vibration caused by mechanical demolition;
(6) Maintain safe ingress and egress for adjoining properties at all the times.
2.32 Catchfan
(1) Construct catchfan to the satisfaction of SO to prevent fall of demolition debris
around perimeter of building under demolition;
(2) Construct catchfan at a vertical distance of not more than 10 m below the working
floor;
(3) Erect sloping catchfan with a horizontal extension of at least 1500 mm from the
exterior face of the scaffold;
- GS 2013 / S2 / Page 12 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(4) The typical angle of inclination shall be 20 to 45 from the horizontal plane.
- GS 2013 / S2 / Page 13 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(8) Use steel props of minimum bearing capacity 25 kN (45 kN for local area under
temporary ramp);
(9) Secure and wedge tight top and bottom supports of props. Fix bracings / ties to
the props to provide lateral restraints in at least two directions;
(10) Do not allow mobile equipment to move to within 2 m of the building edge, 1 m of
any floor opening or on to any cantilevered structures;
(11) Provide adequate spreader for props bearing on ground, where necessary, to avoid
any undue settlement.
- GS 2013 / S2 / Page 14 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
DEMOLITION WORKS
- GS 2013 / S2 / Page 15 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
2.49 Levelling
Unless otherwise Instructed, level off the site to the satisfaction of SO on completion of
the work.
- GS 2013 / S2 / Page 16 of 17 -
SECTION 2 DEMOLITION GENERAL SPECIFICATION 2013
(4) The operators shall have completed a training course in " Demolition of Building
Course for Plant Operators " organized by the Construction Industry Council
Training Authority (CICTA) and obtained the relevant certificate and shall have at
least three years experience in operating the particular plant or equipment.
Equivalent training and certificates issued by a recognised examining body may
also be favourably considered by SO for meeting the requirement;
(5) Notify SO within 7 days of the change in the appointment of the operator and
provide the personal particulars, qualifications and experience of the new operator.
*****
- GS 2013 / S2 / Page 17 of 17 -