Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 6/11/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report S S S S S S S S S S S
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Piping Activity
1 Fit up & weld stub tube 4 joint. 1 Continues fit up & weld stub tube (F/W = finish) Weld = Remaining 1 joint. 1 Continues weld stub tube 1 joint.

2 Continues Tube Instaiiation fit up and weld (RHS top) 8 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 8 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 8 joint
3 Continues cut on RH tubes inside of boiler (RHS top) 30 joint 3 Continues cut on RH tubes inside of boiler (RHS top) 54 joint 3 Continues cut on RH tubes inside of boiler (RHS top) 30 joint
4 Continues cut on RH tubes inside of boiler (LHS top) Finish today 4 Continues cut on RH tubes inside of boiler (Front left top) 4 Continues cut on RH tubes inside of boiler (Front left top)
5 Continues tube RH fit up & weld inside boiler (LHS top) 8 joint 5 Continues tube RH fit up & weld inside boiler (LHS top) 8 joint 5 Continues tube RH fit up & weld inside boiler (LHS top) 8 joint
6 Preparation spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 6 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 6 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
7 Continues machine beveling tube RHS/LHS top. 7 Continues machine beveling tube RHS/LHS top. 7 Continues machine beveling tube RHS/LHS top.

Item Position Day Night Today Piping Activity Photo


MANPOWER
1 Site Engineer 1 0 1
2 QA Engineer 1 1 2
3 Safety 1 2 3
4 QA,QC Superviser 1 1 2
5 Superviser 7 2 9
6 Admin Staff 1 0 1
7 Welder 17 3 20
8 Fitter A,B 32 9 41
9 Electricain 1 2 3
10 Fire Watch 5 2 7
11 Store/General 4 0 4
12 Rigger 6 0 6
77 22 99
Piping Activity Photo
Total (Man-Day)
The TJEL manpower combine foe SPC Sub-Contact

Note : Progress Erection


No. Description Fit up Weld RT
1 RHS top (145 joints) 20 20 11
2 LHS top (145 joints) 20 20 11
3 Front side (297 joints) 0 0 0

Total 40 40 22

Note : Progress Cut tube


No. Description Joint Cut Balance
1 RHS top 145 93 52
2 LHS top 145 145 0
3 Front side 297 60 237 Remak : Cut tube RHS top, cutting 2 step now cut the bottom side first = 52 tube ( Balance top side)

Total 587 298 289


In penthouse butt joint = 4, stub-in to header = 3
Project repair rate = (5/40)*100 = 13%