Beruflich Dokumente
Kultur Dokumente
Presented to:
18th International Conference on Fluidized Bed
Combustion
May 22 - 25, 2005
Toronto, Ontario, Canada
BR-1765
ABSTRACT
The paper provides an update on B&W Internal
Recirculation (IR) CFB boilers featuring a two-stage solids
collection system. The paper describes the latest commercial
projects, operating experience and developments in boiler
design and process. Those concern solids collection system,
erosion protection, etc.
BACKGROUND
The major distinction between circulating fluidized bed
(CFB) boilers competing in todays market is in the type of the
solids separator. CFB boilers with large cyclone separators
connected to the furnace outlet (hot-cyclone type) were
introduced in mid-1970s and are being offered by several boiler
manufacturers. CFB boilers with impact separators, offered by
The Babcock & Wilcox Company (B&W) and its licensees,
entered the market more than ten years later and since then
Fig. 1 U-beam primary separators plan view.
have been gaining acceptance.
B&W CFB boilers feature a two-stage solids separator 70 % of incoming solids) directly to the furnace and seven
with a primary stage being an impact solids separator located at rows of external U-beams with solids recycle through L-
the furnace exit and collecting the bulk of the solids (95-97%) valves [2].
that are returned to the furnace by gravity. The primary - Third generation (first started-up in 1996) - Two rows of
separator is arranged as an array (Figure 1) of U-shaped vertical in-furnace U-beams and three or four rows of external U-
elements (U-beams). The secondary separation stage, typically beams with all solids internally recycled within the furnace
a multicyclone dust collector (MDC), is located in the lower in this IR-CFB separator [3].
gas temperature region of the boiler convection pass, i.e., 480 F
to 950 F (250 C to 510 C). In some cases the first fields of an Operational experience along with continued R&D have
electrostatic precipitator are used as the secondary separator. led to design updates of the third generation of the separator
The fine particles collected by the secondary separator are shown in Figure 2. Featured are total of four rows (two in-
returned to the furnace via a pneumatic (in earlier designs) or furnace and two external) of segmented U-beams. Each beam
gravity transport system. consists of about 3-foot (0.9 m) long segments supported off a
water-cooled tube. Supporting tubes for the first three rows
The U-beam separator has evolved through three B&W (along the gas flow) are the furnace rear wall tubes; those for
CFB boiler design generations: the last row are fed from a separate header.
- First generation (first started-up in 1986) - All U-beams The design allows independent thermal expansion of each
(11 rows) installed external to the furnace with solids segment and eliminates the need for the hopper under external
recycle through non-mechanical controllable L-valves [1]. U-beams that was required for providing a room for thermal
- Second generation (first started-up in 1989) - Two rows of expansion of long stainless steel beams hung from the roof.
in-furnace U-beams discharging collected particles (about
Gas
Flow
In-Furnace
U-Beams
Furnace
Over the same period, the design of the MDC separator has
been improved for better efficiency, reliability and
maintainability. The current design (Figure 3) has a top gas
inlet and a side gas outlet. The cyclone elements have 9 in.
(229 mm) diameter regardless of the boiler capacity. The MDC
solids recycle system has evolved from a dense-phase
pneumatic transport (first generation) to a dilute-phase Fig. 4 Ebensburg CFB boiler.
pneumatic transport (second generation) to gravity conveying
(third generation). boiler (Figure 4) burns high-ash (average 45% ash) Western
Pennsylvania waste bituminous coal.
The latest MDC separator improvement has to do with the
cyclone elements material. The cyclone sleeves and spin vanes The unit was designed for 55 MWe capacity (465 klb/hr or
were made of high hardness (550 BHN) cast iron providing 211 t/hr steam flow), but was uprated in 1995 and again in 1997
their reliable operation but associated with certain maintenance and since then has been operated at 10% overload. Boiler
expenses. Replacing cast iron material with ceramics of the performance and availability are shown in Table 1 and Figure
same element configuration resulted in drastic reduction of 5, respectively. The Ebensburg plant has received the
wear and corresponding need in the elements replacement (see Association of Independent Power Producers of Pennsylvania
more below in MDC experience). (ARIPPA) award for the highest availability among plants
firing coal mine waste fuels.
The second-generation CFB boiler at Ebensburg,
Pennsylvania, in a cogeneration plant commissioned in early The CFB boiler at Southern Illinois University (SIU) in
1991, exemplifies the long-term boiler performance. This Carbondale, Illinois, represents the third generation design.
Table 1
Ebensburg Operating Data
Emissions
NOx, ppm (lb/106 Btu) <100 (<0.14)
SO2, ppm (lb/106 Btu) <300 (<0.60)
CO, ppm (lb/106 Btu) <230 (<0.20)
Operating experience of B&W coal-fired CFB boilers has Load Turndown Ratio without Auxiliary Fuel 5:1
clearly confirmed their efficient performance and high
reliability. Emissions
NOx, ppm (lb/106 Btu) <100 (<0.14)
SO2, % removal 90
CO, ppm (lb/106 Btu) <200 (<0.17)
DESIGN FEATURES
The design of a solids separator is the core of a CFB Ca/S Molar Ratio 2.3
combustion technology since it has major impact on the boiler
layout, cost, fuel and sorbent utilization, operational flexibility
and reliability.
The resilience of U-beams to operating conditions RDZ experience. The patented Reduced Diameter Zone
associated with excessive temperatures and increased gas (RDZ) design (Figure 8) was introduced at Ebensburg in the
velocities contrasts to that of vortex finders (a part of hot- year 2000. The RDZ consists of a reduced diameter tube
cyclones) which are made of similar materials and exposed to a section mating to a specially shaped ceramic tile. The reduced
similar gas/solids environment. Vortex finder failures have diameter tube section on each tube slopes away from the solids
been reported with a substantial detrimental effect on boiler falling down the wall along the surface profile of the tube
performance and considerable maintenance cost panel, thereby eliminating the discontinuity adjacent to the
tube. RDZ installation at Ebensburg resulted in increasing time
span between the outages from six months (dictated by
MDC experience. At Ebensburg, due to the waste coal's high refractory interface maintenance requirements) to a year or
ash content and ash abrasiveness, about 20% of the MDC more.
internal elements made of high hardness cast iron were being
replaced during each yearly outage to avoid a loss of MDC Plant outage schedule is now determined primarily by
efficiency. At other B&W CFB boilers burning high-sulfur auxiliary equipment maintenance requirements. Due to lack of
bituminous coal, circulating solids are typically less abrasive as necessity, the plant also stopped renewing tube protective
compared to the Ebensburg unit, and the MDC internal coating above the refractory interface, thus effectively
elements have either not required replacement or have been eliminating maintenance of this furnace area.
replaced as needed during planned outages. For example, at
SIU, firing medium-ash high-sulfur coal, the first replacement
of about 20% of the MDC internals took place in the fifth year Maintenance cost. The maintenance cost of the solids
of operation. separators in the B&W CFB boilers is intrinsically low. At
Ebensburg, the total maintenance cost for U-beams and L-
Four years ago at Ebensburg, worn-out cast iron elements valves over 10 years of operation was about $20,000. The
started being replaced with the elements made of ceramics average maintenance cost for the MDC with cast iron collection
having the same design. During the last yearly outage no wear elements was about $25,000 per year, which was virtually
was found on any of the ceramic elements. eliminated with introduction of ceramic collection elements.
There was no loss of power generation due to U-beam or L-
90
Collection Efficiency, %
80
70
60
20 40 60 80 100
REFERENCES
[1] F. Belin, et al., Waste Wood Combustion in Circulating
Fluidized Bed Boilers, Proceedings of the Second
International Conference in Circulating Fluidized Beds, 1988.
about 3-foot (0.9 m) long segments supported off a water- [4] D. R. Hajicek et al., The Impact of Coal Quality on
cooled tube. Supporting tubes for the first three rows (along Circulating Fluidized Bed Combustor Performance, EPRI
the gas flow) are the tubes of the furnace rear wall; those for the Coal Quality Conference, 1992.
last row are fed from a separate header. The U-beam segments
are made of SA240TP309H material, which was also used in [5] W. vom Berg and K.-H. Puch, Verwertung von
previous B&W CFB projects. Ruckstanden aus Wirbelschichtfeuerungsanlagen, Vortrage
VGB Konferenz, Wirbelschihtsysteme 1992.
Pendant superheater banks are located downstream of the
U-beams in the horizontal convection pass. Steam from the [6] M. Gierse, Aspects of the Performance of Three Different
drum flows through the side walls of the pendant superheater Types of Industrial Fluidized Bed Boilers, Proceedings of the
enclosure, then through the primary superheater bank followed 3rd International Conference on Circulating Fluidized Beds,
by the wing walls and the secondary superheater bank to the 1990.
main steam outlet.
[7] U. Muschelknautz and E. Muschelknautz, Improvements
The MDC is located immediately downstream of the of Cyclones in CFB Power Plants and Quantitative Estimation
horizontal convection pass. Further in the gas path it is on Their Effects on the Boiler Solids Inventory, Proceedings
followed by the economizer and tubular air heater (air inside of the 6th International Conference on Circulating Fluidized
tubes). The air heater is side-split for the primary and Beds, 1999.
secondary air. After the air heater, gas flows through a
baghouse and an induced draft (ID) fan to a stack.
Disclaimer
Solids collected by the MDC are recycled back to the Although the information presented in this work is believed
furnace through six recycle lines utilizing inclined screw to be reliable, this work is published with the understanding
conveyors and gravity feed. that The Babcock & Wilcox Company and the authors are
supplying general information and are not attempting to render
IR-CFB scale-up or provide engineering or professional services. Neither The
With the current design approach, IR-CFB boilers with a Babcock & Wilcox Company nor any of its employees make any
design similar to that described above are offered for capacities warranty, guarantee, or representation, whether expressed or
up to 200 MWe (600 MWth). implied, with respect to the accuracy, completeness or
usefulness of any information, product, process or apparatus
discussed in this work; and neither The Babcock & Wilcox
CONCLUSIONS Company nor any of its employees shall be liable for any losses
Lessons learned from 18 years of B&Ws CFB technology or damages with respect to or resulting from the use of, or the
application have led to development of the reliable, low-cost inability to use, any information, product, process or apparatus
IR-CFB boiler design. Long-term operating experience of the discussed in this work.