IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)

EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Concrete Grade
Road Name Ayagama-Egaloya Road Pay Item 1001(1)
IPC No 23 Reference 7.1.1
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Volume Total Qty Test No RICF No
(m) (m) (m) (m) Height No

13+825.5 13+851.6 1 26.10 0.80 0.05 0.05 0.10 0.05 1.04

13+851.6 13+871.9 1 20.30 0.50 0.05 0.05 0.10 0.05 0.51


LHS
13+871.9 13+880.4 1 8.50 0.80 0.05 0.05 0.10 0.05 0.34

13+880.4 13+922.67 1 42.27 0.80 0.05 0.05 0.10 0.05 1.69 3.58

- - -

- - -

- - -

- - -

- - -

- - -

- - -

- - -
- - -

- - -

- - -

CUMILATIVE QUANTITY Cu.m. 3.58 3.58 -

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Concrete Grade C 15
1001(1)

31 March 2016

Month Remarks Sketch

Screed
SITE ENGINEER (CEA)
IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Concrete Grade
Road Name Ayagama-Egaloya Road Pay Item 1001(2)
IPC No 23 Reference 7.1.2
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Volume Total Qty Test No RICF No
(m) (m) (m) (m) Height No

1 26.10 0.80 0.15 0.15 0.30 0.15 3.13

1 10.00 0.10 0.61 0.62 1.23 0.62 0.62

1 10.00 0.10 0.61 0.60 1.21 0.61 0.61

13+825.5 13+851.6 1 10.00 0.10 0.62 0.58 1.20 0.60 0.60

1 10.00 0.10 0.60 0.60 1.20 0.60 0.60

1 6.10 0.10 0.58 0.56 1.14 0.57 0.35


LHS
1 6.10 0.10 0.60 0.59 1.19 0.60 0.37

1 20.30 0.50 0.15 0.15 0.30 0.15 1.52

13+851.6 13+871.9 1 10.00 0.10 0.56 0.50 1.06 0.53 0.53

1 10.30 0.10 0.50 0.52 1.02 0.51 0.53

1 8.50 0.80 0.15 0.15 0.30 0.15 1.02


13+871.9 13+880.4
1 8.50 0.10 0.52 0.47 0.99 0.50 0.43 10.31

- - -
- - -

- - -

- - -

- - -

CUMILATIVE QUANTITY Cu.m. 10.31 10.31

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


LITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Concrete Grade C 20
1001(2)

31 March 2016

Month Remarks Sketch

Base

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Base

L Wall

L Wall

Base

Inner Wall
SITE ENGINEER (CEA)
IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Concrete Grade
Road Name Ayagama-Egaloya Road Pay Item 1001(2)
IPC No 23 Reference 7.1.2
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Volume Total Qty Test No RICF No
(m) (m) (m) (m) Height No
Previous Page Quantity 10.31 10.31
1 42.27 0.8 0.15 0.15 0.30 0.15 5.07
1 10.00 0.10 0.47 0.57 1.04 0.52 0.52

1 10.00 0.10 0.60 0.58 1.18 0.59 0.59

1 10.00 0.10 0.57 0.50 1.07 0.54 0.54

1 10.00 0.10 0.58 0.54 1.12 0.56 0.56

1 10.00 0.10 0.50 0.59 1.09 0.55 0.55

13+880.4 13+922.67 LHS 1 10.00 0.10 0.54 0.57 1.11 0.56 0.56

1 4.85 0.10 0.59 0.61 1.20 0.60 0.29

1 4.85 0.10 0.57 0.60 1.17 0.59 0.29

1 3.05 0.10 0.52 0.46 0.98 0.49 0.15

1 3.05 0.10 0.50 0.47 0.97 0.49 0.15

1 4.37 0.10 0.56 0.55 1.11 0.56 0.24


1 4.37 0.10 0.57 0.58 1.15 0.58 0.25 9.76

- - -

- - -

- - -

CUMILATIVE QUANTITY Cu.m. 4.69 20.07

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


LITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Concrete Grade C 20
1001(2)

31 March 2016

Month Remarks Sketch

Base
Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall
Outer Wall

SITE ENGINEER (CEA)


IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Formwork smoo
Road Name Ayagama-Egaloya Road Pay Item 1008(1)
IPC No 23 Reference 7.2.12
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Area Total Qty Test No RICF No
(m) (m) (m) (m) Height No

1 10.00 0.61 0.62 1.23 0.62 6.20

1 10.00 0.61 0.60 1.21 0.61 6.10

1 10.00 0.62 0.58 1.20 0.60 6.00


13+825.5 13+851.6
1 10.00 0.60 0.60 1.20 0.60 6.00

LHS 1 6.10 0.58 0.56 1.14 0.57 3.48

1 6.10 0.60 0.59 1.19 0.60 3.66

1 10.00 0.56 0.50 1.06 0.53 5.30


13+851.6 13+871.9
1 10.30 0.50 0.52 1.02 0.51 5.25

13+871.9 13+880.4 1 8.50 0.52 0.47 0.99 0.50 4.25 46.24

- - -

- - -

- - -

- - -
- - -

- - -

- - -

- - -

- - -

- - -

CUMILATIVE QUANTITY Sq.m. 46.24 46.24 -

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Formwork smooth finish
1008(1)

31 March 2016

Month Remarks Sketch

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

L Wall

L Wall

Inner Wall
SITE ENGINEER (CEA)
IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Formwork smoo
Road Name Ayagama-Egaloya Road Pay Item 1008(1)
IPC No 23 Reference 7.2.12
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Area Total Qty Test No RICF No
(m) (m) (m) (m) Height No

Previous Page Quantity 46.24 46.24

1 10.00 0.47 0.57 1.04 0.52 5.20

1 10.00 0.60 0.58 1.18 0.59 5.90

1 10.00 0.57 0.50 1.07 0.54 5.40

1 10.00 0.58 0.54 1.12 0.56 5.60

1 10.00 0.50 0.59 1.09 0.55 5.50

1 10.00 0.54 0.57 1.11 0.56 5.60


13+880.4 13+922.67 LHS
1 4.85 0.59 0.61 1.20 0.60 2.91

1 4.85 0.57 0.60 1.17 0.59 2.86

1 3.05 0.52 0.46 0.98 0.49 1.49

1 3.05 0.50 0.47 0.97 0.49 1.49

1 4.37 0.56 0.55 1.11 0.56 2.45

1 4.37 0.57 0.58 1.15 0.58 2.53 46.93


- - -

- - -

- - -

- - -

- - -

CUMILATIVE QUANTITY Sq.m. 93.17 93.17 -

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Formwork smooth finish
1008(1)

31 March 2016

Month Remarks Sketch

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall
SITE ENGINEER (CEA)
IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Form work roug
Road Name Ayagama-Egaloya Road Pay Item 1008(2)
IPC No 23 Reference 7.2.13
Sheet No 01 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Area Total Qty Test No RICF No
(m) (m) (m) (m) Height No

2 0.80 0.20 0.20 0.40 0.20 0.32

2 26.10 0.20 0.20 0.40 0.20 10.44

2 0.10 0.61 0.62 1.23 0.62 0.12

2 0.10 0.61 0.60 1.21 0.61 0.12

1 10.00 0.61 0.62 1.23 0.62 6.20


13+825.5 13+851.6
1 10.00 0.61 0.60 1.21 0.61 6.10

1 10.00 0.62 0.58 1.20 0.60 6.00

1 10.00 0.60 0.60 1.20 0.60 6.00

1 6.10 0.58 0.56 1.14 0.57 3.48

1 6.10 0.60 0.59 1.19 0.60 3.66 42.44

2 0.50 0.20 0.20 0.40 0.20 0.20

2 20.30 0.20 0.20 0.40 0.20 8.12

13+851.6 13+871.9
13+851.6 13+871.9 2 0.10 0.56 0.50 1.06 0.53 0.11

1 10.00 0.56 0.50 1.06 0.53 5.30

1 10.30 0.50 0.52 1.02 0.51 5.25 18.98

2 0.80 0.10 0.10 0.20 0.10 0.16

2 8.50 0.20 0.20 0.40 0.20 3.40


13+871.9 13+880.4
2 0.10 0.52 0.47 0.99 0.50 0.10

1 8.50 0.52 0.47 0.99 0.50 4.25 7.91

- - -

CUMILATIVE QUANTITY Sq.m. 69.33 69.33

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Form work rough finish
1008(2)

31 March 2016

Month Remarks Sketch

Screed & Base Sides

Screed & Base

Inner Wall Side

Outer Wall Side

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Screed & Base Sides

Screed & Base


Inner Wall Side

Inner Wall

Inner Wall

Screed & Base Sides

Screed & Base

Inner Wall Side

Inner Wall

SITE ENGINEER (CEA)


IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
EMPLOYER ENGINEER
Road Development Authority Consulting Engineers & Architects Associated (PVT) Ltd
AGREED MEASUREMENT RECORD
Contract No RDA/RNIP/PRP3/Phase-1 (Lot2) /C12 Description Form work roug
Road Name Ayagama-Egaloya Road Pay Item 1008(2)
IPC No 23 Reference 7.2.13
Sheet No 02 Date 31 March 2016
Length Width Height 1 Height 2 Av. IPC
From To Side Times 1+2 Area Total Qty Test No RICF No
(m) (m) (m) (m) Height No

Previous Page Quantity 69.33 69.33

13+880.4 13+922.67 LHS 2 0.80 0.20 0.20 0.40 0.20 0.32

2 42.27 0.20 0.20 0.40 0.20 16.91

2 0.10 0.47 0.57 1.04 0.52 0.10

2 0.10 0.60 0.58 1.18 0.59 0.12

1 0.10 0.47 0.57 1.04 0.52 0.05

1 0.10 0.60 0.58 1.18 0.59 0.06

1 0.10 0.57 0.50 1.07 0.54 0.05

1 0.10 0.58 0.54 1.12 0.56 0.06

1 0.10 0.50 0.59 1.09 0.55 0.06

1 0.10 0.54 0.57 1.11 0.56 0.06

1 0.10 0.59 0.61 1.20 0.60 0.06


1 0.10 0.57 0.60 1.17 0.59 0.06

1 0.10 0.52 0.46 0.98 0.49 0.05

1 0.10 0.50 0.47 0.97 0.49 0.05

1 0.10 0.56 0.55 1.11 0.56 0.06

1 0.10 0.57 0.58 1.15 0.58 0.06 18.13

- - -

- - -

- - -

CUMILATIVE QUANTITY Sq.m. 87.46 87.46

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICER (CEA)


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)
CONTRACTOR
CATIC - Eng.
MEASUREMENT RECORD
Form work rough finish
1008(2)

31 March 2016

Month Remarks Sketch

Screed & Base Sides

Screed & Base

Inner Wall Side

Outer Wall Side

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

Inner Wall
Outer Wall

Inner Wall

Outer Wall

Inner Wall

Outer Wall

SITE ENGINEER (CEA)


IMPROVEMENT AND REHABILITATION OF PRIORITY ROAD PROJEC

EMPLOYER ENGINEER
Road Development Authority C.E.A

AGREED MEASUREMENT RECORD

Contract No RDA/RNIP/PRP3/Phase-1 (Lot2)/C12 Description


Location Ayagama - Egaloya Road Pay Item
IPC No. 23 Reference
Sheet No 1 Date
Mass Unit
No. Cut Total
Bar Dia. per Weight
From To Side Times of Length Weight
Mark (mm) metre Weight (kg)
Bars (m) (kg)
(kg)

1 01 10 51 2.180 0.6173 1.346 68.65

1 02 10 10 9.975 0.6173 6.157 61.57

1 01 10 51 2.150 0.6173 1.327 67.68


13+825.5 13+851.6
1 02 10 10 10.000 0.6173 6.173 61.73

1 01 10 31 2.120 0.6173 1.309 40.58

1 02 10 9 6.075 0.6173 3.750 33.75 333.96

1 01 10 51 1.590 0.6173 0.981 50.03

1 02 10 7 9.975 0.6173 6.157 43.10


13+851.6 13+871.9
1 01 10 52 1.590 0.6173 0.981 51.01

1 02 10 7 10.275 0.6173 6.343 44.40 188.54

1 01 10 41 1.350 0.6173 0.833 34.15


13+871.9 13+880.4
1 02 10 6 8.000 0.6173 4.938 29.63 63.78
LHS
1 01 10 51 2.060 0.6173 1.272 64.87

1 02 10 9 9.975 0.6173 6.157 55.41

1 01 10 51 2.050 0.6173 1.265 64.52


1 02 10 9 10.000 0.6173 6.173 55.56

1 01 10 51 2.060 0.6173 1.272 64.87

1 02 10 9 10.000 0.6173 6.173 55.56


13+880.4 13+922.67
1 01 10 25 2.140 0.6173 1.321 33.03

1 02 10 10 4.850 0.6173 2.994 29.94

1 01 10 16 1.930 0.6173 1.191 19.06

1 02 10 9 3.050 0.6173 1.883 16.95

1 01 10 23 2.090 0.6173 1.290 29.67

1 02 10 9 4.345 0.6173 2.682 24.14 513.58

CUMILATIVE QUANTITY kg 1,099.86 1,099.86

PREPARED BY CONTRACTOR'S REPRESENTATIVE TECHNICAL OFFICE


ITATION OF PRIORITY ROAD PROJECT 3 (PRP3)

ENGINEER CONTRACTOR
C.E.A CATIC - ENG.

MEASUREMENT RECORD

Tor as reinforcement

1002(1)

7.2.11
31 March 2016

Remarks IPC No Month RICF No

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

L Wall Main

L Wall
Distribution

Wall Main

Wall
Distribution

Wall Main
Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

Wall Main

Wall
Distribution

1,099.86

TECHNICAL OFFICER (CEA) SITE ENGINEER (CEA)