1 Project Schedule
-Work Programme
-Manpower Loading
-Equipment Loading
-Org. Chart
-HSE Plans, HSE KPIs for the project, Emergency action plans for
construction phase
3 Engineering
-BED for HVAC system (Mechanical) 18-Sep-15
> Design Philosopy 18-Sep-15
> Unit selection 18-Sep-15
> Cooling capacity calculation 18-Sep-15
> HVAC system Scope of Work 18-Sep-15
> Air conditioner location 18-Sep-15
> Ducting single line 18-Sep-15
> Refrigerant piping single line 18-Sep-15
-STQ
1. STQ-Civil ( AHU room extension) -001 18-Sep-15
2. STQ-Electrical (HVAC panel new cables)-002 18-Sep-15
4 Materials
DELIVERY
1. Air Conditioner 20-Nov-15 4-Jan-16
2. Fresh Air Fan 10-Nov-15 8-Mar-16
3. Internal Dampers 20-Nov-15 8-Mar-16
4. External Dampers 15-Sep-15
5. Split Unit Air Conditioner 30-Sep-15 10-Dec-15
6. Duct Heater 30-Sep-15 8-Mar-16
7. Exhaust Fan 30-Sep-15 8-Mar-16
8. Carbon Filter c/w housing 7-Dec-15
9. Ammonia Gas Detector 10-Nov-15
10. Control Panel TBA
11. Fire Doors TBA 8-Mar-16
12. Ducting and Flexible TBA 8-Mar-16
5 Construction Works
- Safety Briefing TBA
- Work Leader TBA
- Fire Watcher TBA
- Equipment mobilization plan TBA
- Installation plan TBA
- Scaffolding TBA
- Mobile / Lorry Crane TBA
- JKJ 103 Form TBA
- Porta Cabin TBA
- Tools & Oxy-Acetylene TBA
- Distribution Board TBA
- Installation Works
- Punch List
1.Mechanical TBA
2.Electrical TBA
3.Civil TBA
PROJECT TRACKING
1 Project Schedule
-HSE Plans, HSE KPIs for the project, Emergency action plans for
construction phase Approved
3 Engineering
-BED for HVAC system (Mechanical) 18-Sep-15 Approved
> Design Philosopy 18-Sep-15 Approved
> Unit selection 18-Sep-15 Approved
> Cooling capacity calculation 18-Sep-15 Approved
> HVAC system Scope of Work 18-Sep-15 Approved
> Air conditioner location 18-Sep-15 Approved
> Ducting single line 18-Sep-15 Approved
> Refrigerant piping single line 18-Sep-15 Approved
-STQ
1. STQ-Civil ( AHU room extension) -001 18-Sep-15 Approved
2. STQ-Electrical (HVAC panel new cables)-002 18-Sep-15 Approved
4 Materials
DELIVERY
1. Air Conditioner 30-Dec-15 Delivered
2. Fresh Air Fan 24-Feb-16 Delivered
3. Internal Dampers 2-Feb-15 Delivered
4. External Dampers 29-Feb-16 Delivered
5. Split Unit Air Conditioner 30-Sep-15 Delivered
6. Duct Heater 22-Dec-15 Delivered
7. Exhaust Fan 30-Sep-15 Delivered
8. Carbon Filter c/w housing 23 Feb 2016 Delivered
9. Ammonia Gas Detector 10-Nov-15 Delivered
10. Control Panel 25-Apr-16 Delivered
11. Fire Doors 12-Jan-16 Delivered
12. Ducting and Flexible 22-Dec-16 Delivered
5 Construction Works
- Safety Briefing TBA
- Work Leader TBA
- Fire Watcher TBA
- Equipment mobilization plan TBA
- Installation plan TBA
- Scaffolding TBA
- Mobile / Lorry Crane TBA
- JKJ 103 Form TBA Submitted to DOSH. In Progress
- Porta Cabin TBA Completed
- Tools & Oxy-Acetylene TBA
- Distribution Board TBA
Completed
Completed
Completed
Completed
Awaiting for AHU Room Extension
Completed
Completed
In Progress 1/9/2016 5/9/2016 Team 2
Completed
Completed
Completed
In Progress 16/8/2016 17/8/2016 Team 1
Awaiting for AHU Room Extension
Completed
Completed
Completed
Completed
Completed
Completed
In Progress 8/8/2016 13/8/2016 Team 2
In Progress 20/9/2016 26/9/2016 Team 2
Completed
In Progress 1/9/2016 19/9/2016 Team 1
Completed
Completed
Completed