Sie sind auf Seite 1von 3

Instruction manual

1. Set up the schedule table


Enter workstreams, tasks and activities with a index in columns B and C
Adjust the time line by entering the start date of the schedule in cell D4. Then adjust the the months in row 8

2. Define the time schedule for each workstream, task and activity
You can enter three dates per item: the planned start date, the planned end date and the critical deadline
A grey line is automatically drawn from the start to the end date
Usually each item is marked with "Not Started" in column E in the beginning

3. Addition information
You may enter additional information, e.g. responsibilities or interdependencies

4. Status
As long as the start date of an item is in the future and the activity is marked with "Not Started" the Status is white
If the acitivity is started and the item is in time (<end date) the status is green
If the acitivity is finished the status is always green
The status turns red if the item is not in time (end date is passed and acitivity is not started or started) or the activity
e months in row 8

critical deadline

rted" the Status is white

d or started) or the activity is not started and the start date is passed
371586087.xlsSchedule 3

[PROJECT NAME]

Project start date (Please enter Monday of first week) 6/1/2007

Project plan

Status June 2007 July 2007 August 2007


Responsible Necessary Pre- Dura-
[F=Finished, End Deadline
Project task / activity department / preliminary requisite for Start date tion
NS= Not started, date (Date)
person activity activity (days)
S=Started] 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Timeline 14/11/17 ### ######### ######### ######### ######### ###### ######### ######### ######### ######### ###### ######### ######### ######### ######### ###### ######### ######### ######### ######### ###### ######### ######### ######### ######### ###### ######### ######### ######### ######### ###### ######### ######### ###

Milestones

A Workstream A S 6/25/2007 64 8/28/2007 8/31/2007

A1 Task A1 S 6/25/2007 37 8/1/2007 8/31/2007

A2 Task A2 S 7/1/2007 45 8/15/2007 8/31/2007

A2.1 Activity A2.1 S 7/1/2007 45 8/15/2007 8/23/2007

A2.2 Activity A2.2 S 7/7/2007 32 8/8/2007 8/31/2007

A3 Task A3 S 7/10/2007 49 8/28/2007 8/31/2007

A3.1 Activity A3.1 S 7/10/2007 36 8/15/2007 8/23/2007

A3.2 Activity A3.2 S 7/14/2007 109 10/31/2007 10/31/2007

11/14/2017 3

Das könnte Ihnen auch gefallen