JSA DATE REVIEWED

PREPARED BY APPROVED

TYPE OF ACTIVITY:

CATEGORY OF ACTIVITY:

REQUIRED RECOMMENDED PPES:HARDHAT, SAFETYSHOES,HANDGLOVES,REFLECTIVEJACKET,FULLBODY SAFETY HARNESS AND


SAFETYGOGGELS.

SL.NO SEQUNCE OF JOB POTENTIAL HAZARDS. RECOMMENDED OFSAFE JOB WHAT COULD CORRECTIVE
BASIC PROCEDURS. GO WRONG ?. ACTION.
STEPS.

1. Deployment of 1. Physical injury, lack of 1. All the workers should 1. Leads 1. Conduc
1. work men. awareness undergo the induction to t job
2. Unaware about work program. body related
location and unfit workers 2. TBT conduct on daily basis injury. safety
3. Medically/physically unfit 3. Ensure workers are fit trainin
4. Drug & alcohol through medical test by gs
certified doctor. 2. Do not
4. Inspect and provide bypass
recommended job ppes. site
5. All workers have valid gate safety
pass. rules
6. Aware about company rules
and regulation.

2. Site area 1. Slip trip, falls 1. Get the area clearance


clearance 2. Damage to material from DRL authorized
3. Physical hazards persons.
2. Housekeeping should be
done.
JSA DATE REVIEWED

PREPARED BY APPROVED

3. Tool box meeting conduct


before start the work
4. Obstacle free access to be
provided

3. Shifting of 4. Cut injury due to sharp 1. Wear cotton hand gloves to avoid
coving & tools edges. cut injury..
from site store 5. Sprain in body due to 2 Do not carry more than 20 kgs .
to work place. lifting of overload 3. Good communication between
material workers
6. fall of material while 4. Stack the material properly &
shifting. barricade the material.
7. Slip , trip anf fall. 5. Obstacle free access to be provided
6. Good housekeeping

1. Cut injury due to sharp 1. Wear cotton hand gloves to


4. Lifting &
edges. avoid cut injury..
installation of
2. Sprain in body due to lifting 2. Do not carry more than 20
male coving and
of overload material kgs .
silicon sealant (
3. Fall of material 3. Good communication
max 10 mtere
4. Fall of person between workers
height)
5. slip trip fall. 4. Material shifted by tested
6. Defective tools and PP rope from bottom to top
equipment on mobile
7. Failure of scissor / boom lift. scaffold/Boom/scissor lift.
8. Topple of boom / scissor lift 5. All tools and tackles shall be
9. overload of boom / scissor secured in a bag.
lift 6. Always use toe guard on
10. Topple of scaffold scaffold while working on
JSA DATE REVIEWED

PREPARED BY APPROVED

11. over reaching scaffold.


12. .Overhead line / cables 7. Use full body safety harness
13. overreaching more than 1.8 meter height.
8. Obstacle free access to be
provided
9. Good housekeeping
10. All tools must be inspected on
daily basis through DRL
checklist.
11. Check scissor / boom lift on
daily basis through approved
DRL checklist
12. Always work with scissor /
boom lift on level and hard
surface.
13. Always carry weight on boom
/ scissor lift below the weight
capacity.
14. Scaffolding must be
inspected on daily basis
through DRL checklist.
15. Scaffolding wheels must be
locked.
16. Allmunium scaffold erected
as per DRL standard and
attach 4 out riggers for
external support
17. Before started of work always
check overhead power cable and
remove or relocate the cable as
required.
18. Daily give TBT to all workers .
JSA DATE REVIEWED

PREPARED BY APPROVED

1. Ensure work permit before


5. Electric panel 1. Electric shock during the start of any work activity.
operation handling of the electrical 2. Using of rubber coated hand 1. Perma
panel. gloves during panel operation nent
2. Sharp edge 3. All sharp edges will be disabili
3. Electrical hazards rounded off or protected. ty/fata
4. Improper earthing 4. Use rubber mate in front of l
5. Electrical spark/ fire hazards electrical panel
6. Improper insulation 5. Provide the 30mA ELCB for all
7. Presence of water and electrical connection 2. Electri
moisture 6. Only authorized person will c
operate the panel shock/
7. Always connected double fatal
earthing in all electrical during
panel. the
8. Always kept fire extinguisher handli
near the electrical panel. ng of
9. Always use double insulated the
power tools. electri
10. Provide whether protection cal
or shed on electrical panel. equip
ment

1. Joint and damaged cables are


6. Electric supply 1. Joints in electrical cables not allowed use male and
to all power may cause electric shock. female plug top for jointing
hand tools 2. Improper insulation the cable.
2. Provide the 30mA ELCB for all
JSA DATE REVIEWED

PREPARED BY APPROVED

electrical connection
3. Maintained electrical cable
height (min 7 ft from ground
level)
4. Ensure cable should be kept
in dry place
5. Ensure all electrical panel
have gland/edge protection
6. Skilled and authorized worker
should be deputed for
electrical work
7. Always use double insulated
power tools.

1. Keep the working area clean


and debris free.
7. House keeping 1. Slip, trip and fall
2. Always look where you are
going do not assume there is
clear path
3. Always wear mandatory ppes
4. Inspection to ensure cleanup
is complete.