2
2 First Stage Tender Process 15w 4d 23 May 16 13 Sep 16
3 ABP Appoint Multiplex as FSA Contractor 23 May 16 23 May 16 3
8
8 70% Works Package Pricing 15w 2h 27 May 16 13 Sep 16
9 UXO Survey 6w 1d 27 May 16 11 Jul 16 9
23
23 FSA Schedule 2 Pre-Construction Period Services 30w 4d 20 May 16 23 Dec 16
24 Part 1 - Management / Pricing 30w 4d 20 May 16 23 Dec 16 24
26 Assist the Cost Consultant to produce a revised Cost Plan 14w 2d 23 May 16 01 Sep 16 26
27 Investigation into Precasting/Preforming and off-site construction techniques 11w 1s 10 Jun 16 26 Aug 16 27
28 Milestone 2:- Examine the Cost Plan in detail and be satisfied that it represents a reasonably sufficient estimate 6w 13 Jun 16 25 Jul 16 28
29 Assist the Employer and Contractor in obtaining any further consents approvals licences agreements or other matters 11w 3d 08 Jun 16 26 Aug 16 29
30 Participate in the BIM modelling in accordance with the BIM execution plan 12w 2d 02 Jun 16 26 Aug 16 30
31 Assist the Employer and Contractor in initiating, managing and coordinating all liaison with Third Parties 11w 3d 08 Jun 16 26 Aug 16 31
32 Inspect the site and research the likelihood of impact on or interest by Third Parties 12w 1d 08 Jun 16 01 Sep 16 32
33 Prepare a Strategy for management of these Third Party issues 8w 3d 04 Jul 16 01 Sep 16 33
35 Initiate regular neighbouring meetings in conjunction with the Employer and Contractor 3w 08 Jul 16 29 Jul 16 35
Carry out a pre-construction survey of buildings, highways and the like that may be affected by the Project and agree with the Contractor. 36
36 1w 19 Dec 16 23 Dec 16
Provide a report on the same.
37 Milestone 9:- Prepare project specific policy for safety and agree with the Contractor 5w 11 Jul 16 15 Aug 16 37
38 Milestone 9:- Prepare project specific policy for training and agree with the Contractor 5w 11 Jul 16 15 Aug 16 38
39 Milestone 9:- Prepare project specific policy for sustainabilty and agree with the Contractor 5w 11 Jul 16 15 Aug 16 39
40 Milestone 9:- Prepare project specific policy for Industrial Relations and agree with the Contractor 5w 11 Jul 16 15 Aug 16 40
Milestone 9:- Prepare and agree KPIs with the Contractor and report regularly on compliance against them including statistical 41
41 5w 11 Jul 16 15 Aug 16
records
Milestone 10:- Provide logistics advice to the Contractor. Prepare logistics statement and method statement for execution of the 42
42 9w 20 May 16 25 Jul 16
project as part of the Construction Management Plan
43 Milestone 10:- Produce a Project Specific Fire Safety Manual 5w 1d 22 Jul 16 26 Aug 16 43
45 Milestone 12:- Prepare material component flows and identify those that need advance ordering and processing 4w 1d 23 May 16 22 Jun 16 45
Provide advice to the Contractor on the consequences of the design on; Packaging of the work; Interface management; ease of 46
46 11w 3d 08 Jun 16 26 Aug 16
construction; sequencing; availability of materials and labour; durability and maintenance; programme and costs
47 Manage the progress of the design 13w 4d 23 May 16 26 Aug 16 47
48 Advise the Contractor on Information Release Dates and Approval Periods 10w 20 Jun 16 26 Aug 16 48
50 Notify the contractor of the failure of any Named Specialist to perform their services. 13w 4d 23 May 16 26 Aug 16 50
51 Milestone 16:- Prepare and agree with the Contractor a Package Procurement Programme 1w 23 May 16 31 May 16 51
Milestone 17:- Investigate and report on the capability and financial standing of the proposed Work Sub-Contractors - organise 52
52 3w 31 May 16 21 Jun 16
and attend selection interviews
Milestone 18:- Recommend the most effective bidding procedures; propose and discuss with the Contractor the most appropriate 53
53 3w 31 May 16 21 Jun 16
procurement route for individual packages
Agree with the Contractor and his legal advisors any requirement for Third Party Rights, collateral warranties and/or assignments to Third 54
54 11w 3d 13 Jun 16 01 Sep 16
Parties and/or product or professional indemnity insurances and incorporate these into the Work Sub-Contracts.
55 Advise and agree with the Contractor and his legal advisors any requirements for bonds, parent company guarantees or legal opinion letters 14w 2d 23 May 16 01 Sep 16 55
56 Prepare for the placing of work sub-contracts so that they can be placed once the Sub Building Contract is entered into 8w 1d 01 Jul 16 26 Aug 16 56
Milestone 22:- Institute a system of documentation and records for reporting upon the performance of all the work sub contractos 57
57 3w 1d 31 May 16 22 Jun 16
in a form acceptable to the agreement of the Contractor
58 Verify on site the survey control and setting out information. Bring to the attention of the Contractor any discrepancies. 9w 2d 28 Jun 16 20 Sep 16 58
Milestone 24:- Verify the content of any site investigation and existing underground utility services information provided by the
59 Contractor. Verify the location of all logged underground utilities adjacent to or crossing the site. Bring any discrepancies or 3w 29 Jun 16 20 Jul 16 59
clashes with the Project or Temporary Works to the attention of the Contractor
Milestone 25:- Prepare the Proposals with the Pre-appointed Consultants designs, all design information developed by the 60
60 10w 2d 10 Jun 16 23 Aug 16
Principal Sub-Contractor, and any necessary input from the Work Sub-Contractors
61 Provide information to the Contractor for the purposes of claimimg capital allowances on plant and machinery expenditure 8w 4d 01 Jul 16 01 Sep 16 61
Milestone 27:- Assist the Contractor's discussions on crane oversailing licenses with adjoining freeholders, City Airport and 62
62 7w 1d 01 Jun 16 21 Jul 16
tenants as required. Provide the Employer and Contractor with confirmation of any agreements reached
63 Liaise as necessary with Third Party Stakeholders to include: LBN; CLA; UEL; DLR; RoDMA; London Regatta Centre; TfL; GVA etc 13w 4d 23 May 16 26 Aug 16 63
Provide assistance to and provide and maintain appropriate resources to assist the Employer in complying with its responsibilities under 64
64 13w 4d 23 May 16 26 Aug 16
Clause 5.5A of the GLA Development Agreement.
Provide assistance to the Employer in complying with its responsibilities under Clause 43.6 of the GLA Development Agreement, in respect 65
65 13w 4d 23 May 16 26 Aug 16
of the FoI Act 2004 and the EIR 2004
66
66 Part 2 : Design Services 22w 3d 23 May 16 31 Oct 16
Carry out or procure the carrying out of all of the services contained in all the forms of appointment of all the Named Specialists appended 67
67 13w 4d 23 May 16 26 Aug 16
in Schedule 11 up to the execution of the Sub Building Contract.
68 Appointment of Pre-appointed Consultants 31 Oct 16 31 Oct 16 68
78 Finalise PSC Second Stage Appointment and Mezzanine Funding in Place 3w 26 Sep 16 09 Nov 16 78
85 ABP / WTP to instruct provision of Early Production Design Information 06 Sep 16 06 Sep 16 85
90 ABP/WTP to place orders for necessary consultants to satisfy Planning Conditions CCRs 007, 010 & 012 22 Jul 16 22 Jul 16 90
91 ABP/WTP instruct Placing of contract for Site Accommodation CCR TBC 13 Dec 16 13 Dec 16 91
92 ABP/WTP instruct Placing of contract for Water testing CCR014 01 Aug 16 01 Aug 16 92
93 ABP/WTP instruct Placing of contract for Hoardings CCR TBC 13 Dec 16 13 Dec 16 93
94 ABP/WTP instruct Placing of contract with Bactec for UXO survey CCR018 13 Dec 16 13 Dec 16 94
96 ABP/WTP Instruct placing of contract with Pre-cast cladding sub-contractor for design of the works and production of Mock-ups CCR016 05 Sep 16 05 Sep 16 96
97 ABP/WTP Instruct placing of contract with Window sub-contractor for design of the works and production of Mock-ups CCR023 03 Oct 16 03 Oct 16 97
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
98 ABP/WTP instruct Placing of contract with Groundworker 13 Dec 16 13 Dec 16 98
99 ABP/WTP instruct Placing of contract with Dewatering Sub-contractor CCR TBC 13 Dec 16 13 Dec 16 99
100 ABP/WTP instruct Placing of contract with Windows Sub-contractor for Bulk material purchase and production slot CCR023a 13 Dec 16 13 Dec 16 100
101 ABP/WTP instruct fees for additional planning discharge C11 CCR 024 20 Sep 16 20 Sep 16 101
102 ABP/WTP instruct fees for additional planning discharge C08 CCR 025 28 Sep 16 28 Sep 16 102
103 ABP/WTP instruct fees for additional planning discharge Tecnical Safeguarding of Cranes C11 CCR 026 03 Oct 16 03 Oct 16 103
104 ABP/WTP instruct design change to Lift core size CCR027 03 Oct 16 03 Oct 16 104
105 ABP/WTP instruct Placing of contract with Site Setting Out Sub-contractor CCR TBC 07 Oct 16 07 Oct 16 105
106 ABP/WTP instruct design change to Ground slab edge design CCR TBC 03 Oct 16 03 Oct 16 106
107 BP/WTP instruct Placing of contract with Surface Geophysics Sub-contractor CCR TBC 03 Oct 16 03 Oct 16 107
108 ABP/WTP instruct design change to Windows to Fixed Lights CCR TBC 12 Oct 16 12 Oct 16 108
109 ABP/WTP instruct design change to Cladding for Soldier Course and Granite Plinth CCR TBC 12 Oct 16 12 Oct 16 109
110 ABP/WTP instruct design change for Brick Slip Alternatives CCR TBC 07 Oct 16 07 Oct 16 110
111 ABP/WTP instruct design change for slab edge extension CCR 003 03 Oct 16 03 Oct 16 111
112 ABP/WTP instruct design change for PCC columns, stairs and twinwall cores CCR 005 03 Oct 16 03 Oct 16 112
113 ABP/WTP instruct design change for PCC cladding to be 'stacked' not hung CCR 021 03 Oct 16 03 Oct 16 113
114 ABP/WTP instruct placing or order for site temporary services feeds CCR TBC 13 Dec 16 13 Dec 16 114
115 ABP/WTP instruct design change for CFA Piling CCR 022 03 Oct 16 03 Oct 16 115
116 ABP / WTP Place Minor Works Contract with MPX 14w 2d 01 Aug 16 13 Dec 16 116
117 ABP Pay for works to Water Main 02 Aug 17 02 Aug 17 117
121 ABP instruction to Redesign TEC Stage F (Instruction C17) 19 Jun 17 19 Jun 17 121
122 Instruction to proceed with temporary external works design & Procurement 13 Jul 17 13 Jul 17 122
123 Expenditure of Provisional Sums (Some are undefined provisional sums and will result in pre-agreed instructions) 111w 28 Nov 16 06 Mar 19 123
124 Defined Provisional Sums - issue of instruction to expend and Stage E design 46w 28 Nov 16 06 Nov 17 124
135 Undefined Provisional Sums - Issue of instruction to expend and provision of Stage E design 43w 3d 26 Apr 17 12 Mar 18 135
136 Signage - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the base scheme) 22 Jan 18 22 Jan 18 136
Information Light Wall - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the
137 12 Feb 18 12 Feb 18 137
base scheme)
138 External Lighting - Fixtures 09 Aug 17 09 Aug 17 138
External Lighting - Distribution - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed
139 09 Aug 17 09 Aug 17 139
in the base scheme)
140 Incoming Utilities 11 Dec 17 11 Dec 17 140
Fixed Fibre Telecommunications - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been
141 11 Dec 17 11 Dec 17 141
designed in the base scheme)
142 Temporary External Works - Temporary Carpark 13 Jul 17 13 Jul 17 142
143 Temporary External works 12 Feb 18 12 Feb 18 143
Security - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the base scheme.
144 Also assumes that all necessary wireways in all internal and external doors are already coordinated with the design team to facilitate design 09 Aug 17 09 Aug 17 144
and procurement)
145 Asbestos Removal to Listed Buildings 26 Apr 17 26 Apr 17 145
Type B Lobby Fitout - (Note this is for the fixed installation only - assumes that infrastructure necessary has already been designed in the
146 06 Nov 17 06 Nov 17 146
base scheme and that any infrastructure necessary has been coordinated already with the base build design)
147 Temporary Car Park 12 Mar 18 12 Mar 18 147
148
148 Work to Listed Buildings 10A and 10B (Based on minimal structural alterations to the buildings) 100w 27 Feb 17 06 Mar 19
ABP/WTP provide a detailed brief showing the proposed use for the buildings, a scope for the works and request price and programme for 149
149 27 Feb 17 27 Feb 17
the design works
150 CITIC/MPX respond with price and programme for the design 1w 27 Feb 17 03 Mar 17 150
151 MPX to submit CCR for Asbestos Survey, Asbestos removal & Pigeon guano removal 2w 31 Mar 17 13 Apr 17 151
152 CI for Asbestos Survey, Asbestos removal & Pigeon guano removal 1w 11 May 17 17 May 17 152
153 Carry out Asbestos Survey & Pigeon guano removal 4w 2d 17 May 17 16 Jun 17 153
161 Procure Fabric Survey Including trial pits to foundations 10w 15 May 17 16 Oct 17 161
162 Procure Drainage & Incoming services surveys 10w 15 May 17 16 Oct 17 162
164 MPX review survey tenders and produce tender reports 4d 17 Oct 17 20 Oct 17 164
165 MPX to Submit tender reports & Recommendation for Carrying out surveys to ABP 16 Oct 17 16 Oct 17 165
167 WI to issue CI to carry out Surveys and Obtain reports 06 Nov 17 06 Nov 17 167
168 Carry Out Archaeological survey(MoLA) & issue reports to WTP/ABP 5w 06 Nov 17 08 Dec 17 168
169 Carry out remaining surveys, Obtain reports & and issue reports to WTP/ABP 6w 06 Nov 17 15 Dec 17 169
170 MPX to Prepare and submit survey report 2w 18 Dec 17 09 Jan 18 170
171 ABP/WT Review and instruct design of Listed building works 1w 10 Jan 18 16 Jan 18 171
172 Obtain prices from Design team to carry out design 2w 17 Jan 18 30 Jan 18 172
174 WTP instruct design for listed buildings 2w 07 Feb 18 20 Feb 18 174
175 Prepare Stage C design for listed buildings 5w 21 Feb 18 27 Mar 18 175
176 Prepare cost plan for the Stage C design 2w 28 Mar 18 12 Apr 18 176
177 Submit Stage C design, programme and costplan for client review 13 Apr 18 13 Apr 18 177
178 ABP/WTP Review Stage C Design, Programme and Cost plan and provide comments 2w 13 Apr 18 26 Apr 18 178
180 Submit design for listed building approval 15 May 18 15 May 18 180
183 Go to supply chain to obtain tenders for works 8w 15 May 18 10 Jul 18 183
185 ABP/WTP Review, approve and instruct the works 3w 25 Jul 18 14 Aug 18 185
188
188 Shell & Core Works 20w 06 Sep 18 06 Feb 19
189 Cut back and disposal of bushes and shrubs surrounding the listed buildings and gardens 2w 06 Sep 18 19 Sep 18 189
190 Devegetate facade and treat affected areas, clean facade, windows and doors prior to decoration 2w 18 Sep 18 01 Oct 18 190
192 Temporary measures to ensure building security and water tightness 4w 13 Sep 18 10 Oct 18 192
193 Repair defects in the precast concrete components 4w 13 Sep 18 10 Oct 18 193
Remove falling historical repairs, defective precast concrete panels and mouldings, and treat cast in reinforcement or replace with s/s bars 194
194 10w 17 Sep 18 23 Nov 18
and reinstate.
195 Repair or Replace any barge boards, fascia boards and any other external woodwork 3w 12 Oct 18 01 Nov 18 195
196 Repair or replace broken tiles including special tiles to encure water tightening incl. repair of lead flashings 10w 27 Sep 18 05 Dec 18 196
197 Replace missing or defective rainwater goods 10w 25 Sep 18 03 Dec 18 197
Removal of loose defective paint, filling hairline cracks, rubbing down, preparation and decoration to all window, doors, woodwork, metal 198
198 12w 18 Sep 18 10 Dec 18
work, stonework, pebble dashing and render
199 Strip out existing reduntant services, cap and make safe 8w 03 Oct 18 27 Nov 18 199
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
201 Replacement of Existing defective structural elements 12w 20 Sep 18 12 Dec 18 201
202 Structural Improvements, alterations and internal adaptions 12w 20 Sep 18 12 Dec 18 202
204 Linings to existing structural internal and external walls incl. ceilings 8w 18 Oct 18 12 Dec 18 204
206 Internal Frames and fire doors, ironmongery to maintian fire intergrity 8w 18 Oct 18 12 Dec 18 206
208 Overhaul existing staircases, balustrades and handrails to ensure safe access 4w 26 Nov 18 21 Dec 18 208
209 Connection to DH/DC network, LV Connections, Main water connection, Open reach & Telecoms connections 4w 26 Nov 18 21 Dec 18 209
211 Emergency, Temporary lighting, Smoke detectors, fire alarms as required to maintain fire integrity 8w 29 Nov 18 06 Feb 19 211
213 Listed Buildings Heating/Cooling, Water and Electrical Connections 66w 05 Dec 16 13 Apr 18 213
214 Sizing of the Deep level connections to District Heating and Cooling ring mains 05 Dec 16 05 Dec 16 214
217 CITIC/BM Prepare cost plan for the design 2w 21 Feb 18 06 Mar 18 217
218 Submit design, programme and costplan for client review 07 Mar 18 07 Mar 18 218
219 ABP Review Design, Programme and Cost plan and provide comments 2w 07 Mar 18 20 Mar 18 219
224
224 Planning Consent 29w 03 Jun 16 23 Dec 16
225 Planning Conditions Precedent to Start on Site Cleared 21w 3d 03 Jun 16 23 Dec 16 225
227 AKT II provide structural design for temporary energy centre 6w 23 Jan 17 03 Mar 17 227
229 Slab Edge Extension to accommodate 'Stacked' Facade 10w 1d 08 Sep 16 20 Dec 16 229
230 Reduced Lift shaft sizing impact on structure 10w 2d 04 Oct 16 20 Dec 16 230
231 Facade Design Freeze on elevations to Buildings 5A and B 03 Oct 16 03 Oct 16 231
232 Facade Design Freeze on elevations to Buildings 8A, 8B and 9A 30 Aug 16 30 Aug 16 232
233
233 Revised Stage E Piling Design for CFA piling 21w 18 Jul 16 13 Dec 16
234 ABP/WTP instruction to produce revised Stage E piling design for CFA and to provide Test Pile 18 Jul 16 18 Jul 16 234
236 Building 9A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 236
237 Building 8B Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 237
238 Building 8A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 238
239 Building 5B Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 239
240 Building 5A Piling layout and loads P1 issue 21 Oct 16 21 Oct 16 240
251
251 Piling 23w 2d 26 Aug 16 21 Feb 17
252 Piling Design 6w 23 Nov 16 21 Feb 17 252
253 Building 9A Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 253
254 Building 8B Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 254
255 Building 8A Piling layout and loads C1 issue 31 Jan 17 31 Jan 17 255
256 Building 5B Piling layout and loads C1 issue 21 Feb 17 21 Feb 17 256
257 Building 5A Piling layout and loads C1 issue 21 Feb 17 21 Feb 17 257
258 Keltbray issue typical piling details and layouts 26 Aug 16 26 Aug 16 258
259
259 Substructure and Under Slab Drainage 32w 4d 06 Sep 16 11 May 17
260 ABP review Keltbray proposed pile design 1w 1d 06 Sep 16 13 Sep 16 260
261 AKT2 issue typical pilecap details to Farrells 14 Sep 16 14 Sep 16 261
262 Stage F Lift pit and shaft design 9w 1d 26 Sep 16 28 Nov 16 262
264 Buildings 8A, 8B and 9A Pilecap and ground floor slab design including under slab services 08 Dec 16 08 Dec 16 264
265 C1 Design Information for Buildings 9A, 8A & 8B 31 Jan 17 31 Jan 17 265
266 Building 9A & 8B Substructure Rebar Design Intent 31 Jan 17 31 Jan 17 266
267 Buildings 5A & 5B Pilecap and ground floor slab design including under slab services 24 Feb 17 24 Feb 17 267
270 Building 5A & 5B Substructure Rebar Design Intent 11 May 17 11 May 17 270
274 Building 8A, 8B and 9A Facade Design - C1 issue 7w 05 Sep 16 21 Oct 16 274
276
276 Superstructure Design 44w 3d 15 Sep 16 14 Aug 17
277 Stage F Structural Design 23w 08 Dec 16 07 Jun 17 277
279 P1 Issue of Construction Information for Buildings 9A, 8A & 8B 22 Dec 16 22 Dec 16 279
280 Provide Reinforcement Intent for Core Walls and Columns - Building 8A, 8B and 9A 20 Jan 17 20 Jan 17 280
281 Provide Post Tension Slab Loading and deflection design - Building 9A and 8B 20 Jan 17 20 Jan 17 281
282 P1 Issue of Construction Information for Buildings 5A & 5B 10 Apr 17 10 Apr 17 282
283 C1 Issue of Construction Information for Buildings 9A, 8A & 8B 24 Feb 17 24 Feb 17 283
284 Building 9A Ground & First Floor GAs 18 Apr 17 18 Apr 17 284
285 Building 8B Ground & First Floor GAs 01 Mar 17 01 Mar 17 285
286 Provide Reinforcement Intent for Core Walls and Columns - Building 5A and 5B 25 Apr 17 25 Apr 17 286
287 Provide Post Tension Slab Loading and deflection design - Building 8A 25 Apr 17 25 Apr 17 287
288 C1 Issue of Construction Information for Buildings 5A & 5B 04 May 17 04 May 17 288
289 Building 8A Ground & First Floor GAs 05 May 17 05 May 17 289
290 Provide Post Tension Slab Loading and deflection design - Buildings 5A and 5B 11 May 17 11 May 17 290
291 Building 5A and 5B ground & First Floor GAs 07 Jun 17 07 Jun 17 291
301 Provide full GAs for all 2nd floor and above - Building 8A & 8B 06 Mar 17 06 Mar 17 301
302 Provide full GAs for all 2nd floor and above - Building 9A 06 Mar 17 06 Mar 17 302
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
303 Provide full GAs for all 2nd floor and above - Building 5A & 5B 06 Mar 17 06 Mar 17 303
304 Stage F Mechanical and Electrical Design 22w 22 Sep 16 08 Mar 17 304
317 Fire Alarms and Detection including Disabled Refuges 19 Jun 17 19 Jun 17 317
340 Vital Energy Design of Systems (defined provisional Sum) 65w 09 May 16 30 Aug 17340
341 Vital Energy produce Stage D design 7w 4d 09 May 16 01 Jul 16 341
342 Consultants review Vital Energy Stage D design and comment 2w 04 Jul 16 15 Jul 16 342
343 Vital Energy Produce Stage E design and coordinate with remainder of Infrastructure design 8w 18 Jul 16 12 Sep 16 343
344 ABP decision and order to Vital Enegi to proceed 4w 21 Nov 16 16 Dec 16 344
347 Fabrication and delivery of pipework and valves 20w 30 Jan 17 22 Jun 17 347
348 Temporary Energy Centre Design (Undefined provisional Sum) 57w 2d 01 Jul 16 30 Aug 17 348
349 Temporary Energy Centre excluding Anxillary Buildings 57w 2d 01 Jul 16 30 Aug 17 349
350 Vital Energi provide Stage C design for temporary energy centre 01 Jul 16 01 Jul 16 350
352 Farrells prepare and submit Temporary energy centre for planning 1w 13 Jul 16 19 Jul 16 352
355 Temporary Energy Centre ABP/WTP Review and accept Stage D design 1w 08 Sep 16 14 Sep 16 355
357 ABP/WTP Acceptance of Vital Energi design of Temporary Energy Centre 1w 13 Mar 17 17 Mar 17 357
358 Stage F Temporary Energy Centre (Undefined provisional Sum) 10w 2d 20 Mar 17 05 Jun 17 358
359 MPX instruction to Consultant inorder to redesign Stage F 19 Jun 17 19 Jun 17 359
360 Detailed design development by Architect and Structural Engineer for VE 5w 27 Jun 17 31 Jul 17 360
361 Farrells design Freeze date for VE 01 Aug 17 01 Aug 17 361
362 Planning Submission 1w 01 Aug 17 07 Aug 17 362
363 Consultant review of design (other consultants) for VE 4w 01 Aug 17 29 Aug 17 363
Release of final Stage F design (Information regarding the additional steel member for the landscape store released earlier due to 8
364 30 Aug 17 30 Aug 17 364
weeks lead time)
365 Statutory Authorities and Third Party Interfaces 91w 2d 31 May 16 04 Apr 18 365
367 Prepare & Submit Construction Environmental Management & Logistics Plan 4w 19 Jul 16 15 Aug 16 367
370 Site Investigation and Sampling for Soil Contamination 8w 31 Oct 16 23 Dec 16 370
373 Application To EA For Working Near a Watercourse 17w 31 May 16 23 Dec 16 373
374 Prepare Scheme For Monitoring Magnetic Interference & Submit To LBN For Approval 17w 1d 05 Aug 16 20 Mar 17 374
375 Complete negotiations with Thames Water and agree price for connections and manholes 10w 3d 23 Aug 16 09 Dec 16 375
376 Enter into contract with Thames Water for Connection works 12w 12 Dec 16 01 Aug 17 376
377 Thames Water / DLR lead-in (assumed) 24w 02 Aug 17 09 Feb 18 377
378 Prepare Application To LBN For Working Above Designated Maximum Height and approval of same 16w 01 Aug 16 09 Dec 16 378
379 Prepare Water Discharge License Applications To LBN, RoDMA & Thames Water 4w 19 Dec 16 27 Jan 17 379
382 Pre-construction Condition A06 - Physical Facade Mock Up 77w 4d 05 Sep 16 04 Apr 18 382
383 CITIC/MPX Place orders for precast, windows and metalwork 4w 05 Sep 16 30 Sep 16 383
384 Prepare Brick Sample panels and submit 4w 13 Sep 16 10 Oct 16 384
385 LBN approval period for brick samples 3w 05 Dec 16 07 Apr 17 385
388 Detailed design development of Precast Concrete Panels 14w 2d 12 Sep 16 20 Dec 16 388
389 Outline design of mock up windows and other components 3w 10 Oct 16 28 Oct 16 389
390 Detailed Design of windows, shopfronts, balconies etc 7w 2d 31 Oct 16 20 Dec 16 390
391 Provide samples and Specifications of all materials 26 Sep 16 26 Sep 16 391
392 Details of the typical ground floor facade treatment 03 Oct 16 03 Oct 16 392
393 Details of the typical facade treatments for the elevations facing any courtyard or square 10 Oct 16 10 Oct 16 393
394 Details of the top floor facade treatments 31 Oct 16 31 Oct 16 394
395 Details of windows, doors, entrances, reveals and sills, balconies, canopies, balustrades and material junctions 19 Dec 16 19 Dec 16 395
397 Manufacture of moulds, casting and delivery of Installation of Physical Facade Mock Up 4w 20 Feb 17 17 Mar 17 397
399 Production of Physical Facade Mock Up (PC Concrete Panels) 2w 13 Apr 17 28 Apr 17 399
401 LBN Inspection and Comment on Physical Mock ups for Type and Type B buildings 1w 28 Apr 17 05 May 17 401
402 Carry out any necessary alterations to design, moulds etc 2w 08 May 17 19 May 17 402
403 Produce revised physical mockups and install on site 4w 19 May 17 16 Jun 17 403
407 Install windows to precast units (assumed off site) 27w 01 Sep 17 04 Apr 18 407
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
408 Start installation of precast units 06 Nov 17 06 Nov 17 408
409
409 Pre-construction Condition C01 - UXO Site Safety & Emergency Procedures 10w 12 Jul 16 21 Sep 16
410 Provide an UXO site safety and emergency procedures plan for submission to LBN 1w 12 Jul 16 18 Jul 16 410
411 Review and submit UXO site safety and emergency procedures plan 1w 19 Jul 16 25 Jul 16 411
412 LBN consider UXO site safety and emergency procedures plan 8w 26 Jul 16 20 Sep 16 412
413 LBN approve site safety and emergency procedures plan 21 Sep 16 21 Sep 16 413
414 Pre-construction Condition C09 - Monitoring of Magnetic Interference during Construction 30w 05 Aug 16 20 Mar 17 414
415 Produce a scheme for monitoring magnetic interference during construction 4w 05 Aug 16 02 Sep 16 415
416 Submit a scheme for monitoring magnetic interference during construction 05 Sep 16 05 Sep 16 416
417 LBN consider scheme for monitoring magnetic interference during construction 8w 31 Oct 16 23 Dec 16 417
418 LBN approve scheme for monitoring magnetic interference during construction 20 Mar 17 20 Mar 17 418
419
419 Pre-construction Condition C12 - Signage prohibiting feeding of wildlife and waterfowl. 16w 05 Aug 16 28 Nov 16
420 Produce details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 4w 05 Aug 16 02 Sep 16 420
421 Submit details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 05 Sep 16 05 Sep 16 421
422 LBN consider details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 8w 05 Sep 16 25 Nov 16 422
423 LBN approve details of the number and location of signs prohibiting the feeding of wildlife and waterfowl 28 Nov 16 28 Nov 16 423
424 Pre-construction Condition C36 - EA approval for working adjacent to Watercourse 22w 4d 14 Dec 16 09 Jun 17 424
425 Carry out water sampling and testing and report 1w 14 Dec 16 20 Dec 16 425
426 Produce plan for dealing with water run-off from site 2d 25 Apr 17 26 Apr 17 426
427 EA approval of plan for control of water from site 6w 27 Apr 17 09 Jun 17 427
428 Complete liaison with Utilities Providers 16w 4d 13 Jun 16 07 Oct 16 428
429
429 Sub-Sub-Contract Package Procurement 134w 17 Jun 16 07 Mar 19
430 Prelim Packages Lead-ins 27w 17 Jun 16 09 Jan 17 430
434 Submit RAMS, Specification and drawings showing hoardings etc. 11 Jul 16 11 Jul 16 434
442 Place order for Site Setting out 2w 07 Oct 16 20 Oct 16 442
443 Works Package Orders and Lead-in 128w 4d 25 Jul 16 07 Mar 19 443
444
444 Prelims and Early Works 76w 2d 25 Jul 16 12 Feb 18
445 Site Setting out and Survey - SES - A17.2 5w 12 Sep 16 05 Dec 16 445
446 Hoarding and Site Set Up - Pacific - A1201 7w 2d 12 Sep 16 05 Dec 16 446
447 Site Security Early Works - Phoenix - A22 8w 4d 25 Jul 16 07 Nov 16 447
448 Site Security Main Works - Phoenix - A22 7w 4d 01 Nov 16 09 Jan 17 448
450 Test Pile and Temporary Access Bridge Piles - Keltbray 9w 09 Sep 16 18 Jan 17 450
451 Site Welfare and Accommodation - Premier Modular 12w 30 Aug 16 23 Jan 17 451
456
456 Provisional Sums 127w 05 Aug 16 07 Mar 19
457 Raised Access Floors 41w 1d 16 May 17 08 Oct 18 457
460 Windows Package - Canopies Fabrication & Install 27w 25 Jan 17 07 Feb 18 460
480 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 480
498 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 498
516 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 516
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
523 Complete Pre-Qualification 02 May 17 02 May 17 523
524 Tender Design complete 02 May 17 02 May 17 524
525 Prepare Tender Documents 1w 02 May 17 08 May 17 525
526 Out to Tender 09 May 17 09 May 17 526
527 Tender Period 1w 09 May 17 15 May 17 527
528 Tender Return Date 2w 16 May 17 18 Aug 17 528
529 Tender reconciliation 2w 21 Aug 17 22 Sep 17 529
530 Recommended sub-contractor (PAM 16) 25 Sep 17 25 Sep 17 530
534 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 534
552 Agree Ts and Cs and execute Sub-contract (PAM 20) 1w 17 Oct 17 23 Oct 17 552
564 Ground works Package - E4 dockside coping stone 26w 2d 06 Nov 17 22 May 18 564
565 Dewatering Package - Discharge into Docks 30w 05 Aug 16 22 May 17 565
566 Extra Low Voltage (ELV) Package 40w 31 Mar 17 07 Feb 18 566
568 Dock Wall Repairs & Alteration works 22w 12 Sep 17 08 Mar 18 568
577 Water Mains and Building connections 28w 1d 02 Mar 17 25 Sep 17 577
578 Thames Water sewer connection 33w 2d 09 Oct 17 29 Jun 18 578
579 Medium pressure gas connection 35w 2d 06 Nov 17 27 Jul 18 579
580 LV Switchgear and distribution 34w 06 Nov 17 18 Jul 18 580
581 VDV - Fibre Network 39w 09 Oct 17 08 Aug 18 581
583 Groundworks, Infrastructure and Dewatering - Galldris 14w 12 Sep 16 09 Jan 17 583
585 Pre-Cast Concrete Cladding - Thorp - D713 53w 2d 22 Aug 16 20 Feb 18 585
587 Windows/ Curtain Walling - Prater - D802 30w 17 Nov 16 17 Jan 18 587
588 Roofing and Waterproofing - Prater - D802 24w 4d 17 Nov 16 12 Jan 18 588
589 Lifts / Vertical Transportation - Schindler - F601 36w 4d 11 Jan 17 14 Mar 18 589
601
601 Issue final design information and re-price 2w 30 Jun 17 13 Jul 17
604 Agree Ts and Cs and execute Sub-contract (PAM 20) 2w 28 Jul 17 10 Aug 17 604
607
607 Sub-contractor fabrication, procurement and mobilisation 10w 11 Oct 17 11 Jan 18
609 Dry lining, Ceilings & associated works 37w 4d 06 Apr 17 26 Jan 18 609
610 Metalwork - Architectural and General - GK Engineering - E101 19w 3d 22 Dec 16 23 Aug 17 610
611 Doors and Joinery - Doug Phillips - E1001 36w 2d 17 Jan 17 22 Feb 18 611
612 Mechanical & Electrical Services and Plumbing - Mercury 26w 06 Feb 17 05 Dec 17 612
613 Dry Risers and Sprinklers - Argus Fire 30w 4d 24 Jan 17 04 Sep 17 613
614 External & Hard Landscaping Works 25w 2d 23 Jan 17 18 May 18 614
629 Agree Ts and Cs and execute Sub-contract (PAM 20) 2w 04 Jul 17 17 Jul 17 629
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
633 Start on Site 20 Nov 17 20 Nov 17 633
634 Floor and Wall Tiling, and Stone Flooring 25w 09 Oct 17 30 Apr 18 634
637 Carpet Tiling and Soft Flooring 37w 26 Jan 18 22 Oct 18 637
643 CPD Piling design and approval by AKT II 5w 21 Nov 16 23 Dec 16 643
645
645 Temporary Works Design 26w 05 Sep 16 17 Mar 17
646 Site Access Bridge 12w 05 Sep 16 25 Nov 16 646
647 Site access bridge temporary works design 6w 05 Sep 16 09 Nov 16 647
651
651 Groundworks and Infrastructure 14w 28 Nov 16 17 Mar 17
652 Temporary Works Excavation design for trenching 3w 31 Jan 17 10 Mar 17 652
666
666 Superstructure Reinforcement detailing 13w 1d 27 Feb 17 02 Jun 17
667 Superstructure Post tensioned concrete design and detailing 13w 27 Feb 17 02 Jun 17 667
668 Superstructure Precast / RC design and/or detailing 11w 13 Mar 17 02 Jun 17 668
670 Precast concrete design and fixing to structure 4w 01 Aug 16 26 Aug 16 670
671 Precast concrete cladding Subcontractor to advise stacking loads and eccentricity 15 Aug 16 15 Aug 16 671
673 Structural steelwork fabrication drawings for TEC 6w 19 Jun 17 28 Jul 17 673
677 Windows and associated doors, copings, screens and flashings 6w 03 Oct 16 02 Jun 17 677
681 Movement joints, acoustic and fireproofing of joints to masonry and dry-lining 5w 21 Nov 16 23 Dec 16 681
691 Vertical Transportation (VT) (Lifts) incl intercom and CCTV 13w 22 Aug 16 31 Aug 17 691
698 Materials Order, Manufacture, Transport and Delivery 15w 1d 17 Nov 17 13 Mar 18 698
699
699 Type A Building Lifts 28w 1d 19 May 17 05 Dec 17
700 Drawing 2w 19 May 17 02 Jun 17 700
704 Materials Order, Manufacture, Transport and Delivery 10w 07 Aug 17 05 Dec 17 704
705
705 Construction Works 129w 3d 18 Jul 16 06 Mar 19
706 Early Works and Phase 1 Enabling works 50w 4d 21 Sep 16 02 Oct 17 706
707 Establish primary settting out stations and grids on site 1w 21 Oct 16 27 Oct 16 707
708 Potential Early Start for Site Hoardings 2w 3d 21 Sep 16 10 Oct 16 708
709 MPX submit information for GLA Licence 3d 21 Sep 16 23 Sep 16 709
710 ABP to apply for GLA Licence for use of Site Areas outwith Phase 1 26 Sep 16 26 Sep 16 710
712 GLA Grant Licence for use of Site Areas Outwith Phase 1 10 Oct 16 10 Oct 16 712
713 ABP/WTP Instruct CITIC/MPX to proceed with Hoardings 10 Oct 16 10 Oct 16 713
715
715 Hoarding To Site 14w 3d 10 Nov 16 06 Mar 17
716 Place order with S/C 10 Nov 16 10 Nov 16 716
719 Start installing posts in soft ground to NW corner of site adjacent to 1000 - (360 metres) 2w 09 Feb 17 06 Mar 17 719
721 Erect hoarding to Dock side and decorate / brand (740 metres) 3w 13 Jan 17 02 Feb 17 721
722 Erect hoarding to remainder of site up to Becton Park Station from West to East (510 m) 1w 23 Jan 17 27 Jan 17 722
723 Erect remainder of hoarding to East end of site (500m) 1w 24 Jan 17 30 Jan 17 723
726 Piling contractor lead in / mobilisation for rig 4w 08 Dec 16 18 Jan 17 726
731 Excavate (assume U/S) and cart to tip for piling platform 1d 12 Jan 17 12 Jan 17 731
732 Form piling platform and get approval to use. 1d 13 Jan 17 13 Jan 17 732
733 Install test pile and anchor piles 2d 19 Jan 17 20 Jan 17 733
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
736 Provide test pile report 2w 06 Feb 17 17 Feb 17 736
737
737 Dock Wall survey 19w 4d 15 May 17 02 Oct 17
738 MPX Issue Tender report intrusive survey for ABP/WTP approval 2w 15 May 17 26 May 17 738
739 ABP/WTP to review and instruct Intrusive survey 2w 30 May 17 12 Jun 17 739
740 MPX Proceed with Survey and issue Reports 15w 24 May 17 02 Oct 17 740
741
741 Entrance Access Bridge 5w 16 Jan 17 17 Feb 17
742 Install mini piles for entrance bridge slab 3d 16 Jan 17 18 Jan 17 742
744 Dig down, expose and cap off existing drainage from the apron into the dock where shown on the drawings or visible. 4w 10 Apr 17 10 May 17 744
746 UXO Survey including drilling through hardstandings 8w 12 Dec 16 17 Feb 17 746
747 Carry out soil investigation to identify areas and extent of contamination and report on remediation necessary 3w 23 Jan 17 10 Feb 17 747
750 Install below ground drainage and temporary services to site accommodation area 2w 30 Jan 17 10 Feb 17 750
756 Base Slab & Ducts for Substation (by others direct) 3w 30 Jan 17 17 Feb 17 756
757 Install temporary feeds for power, lighting, water and telecomms 3w 02 Feb 17 04 May 17 757
760 Phase 1 Ground and Infrastructure Works 78w 08 Mar 17 28 Sep 18 760
769 Reduced level dig throughout and cart to tip as necessary 10w 08 Mar 17 19 May 17 769
770 Generate phasing and alignment of temp roads 5w 12 Apr 17 19 May 17 770
771 Carry out any remediation of soils that may be necessary (Variation) 5w 12 Apr 17 19 May 17 771
773 Retaining wall between Buildings 9A & 10A 5w 18 May 17 22 Jun 17 773
774
774 Drainage & Services Between Manholes SM11/FM11 to SM9/FM9 & FM11/SM11 to FM31 and SM38(Stage 1) 59w 4d 03 Apr 17 18 Jun 18
775 Stage 1 Deep level infrastructure 55w 3d 03 Apr 17 17 May 18 775
778 Build Manhole FM11 & SM11 (including rocker pipes towards Sewer connections) 2w 19 Apr 17 03 May 17 778
780 Lay Foul & Surface Water drainage Pipes FM 11/SM11 To FM9/SM9 1w 1d 04 May 17 11 May 17 780
782 Lay Foul & Surface Water drainage Pipes SM38 & FM31 To FM11 & SM11 2w 1d 24 Apr 17 09 May 17 782
784 Connection into Main Sewer in Royal Albert Way 13w 12 Feb 18 17 May 18 784
786 Excavate & Construct Service Ducts for Electric cables 2w 04 Apr 18 17 Apr 18 786
790 Excavate Trenches & Lay Ducts for data and Telecoms 2w 09 May 18 22 May 18 790
791 Excavate For District Heating and Cooling Pipes 1w 23 May 18 30 May 18 791
792 Install District Heating and Cooling Pipes for Building 10A 1w 31 May 18 06 Jun 18 792
793 Backfill District Heating and Cooling Pipes 1w 2d 08 Jun 18 18 Jun 18 793
795
795 Drainage & Services Between Manholes SM30/FM24 to SM7/FM7 (Stage 1A) 2w 1d 05 May 17 19 May 17
796 Stage 1A Deep level services 2w 1d 05 May 17 19 May 17 796
797 Excavation & Temporary Propping For Drainage 2w 08 May 17 19 May 17 797
799 Lay Foul & Surface Water drainage Pipes FM 25 To FM7 2w 1d 05 May 17 19 May 17 799
801
801 Dockside Mews Buried Services 58w 4d 19 Jun 17 21 Aug 18
802 Prater clear of Mews on 8A side 12 Mar 18 12 Mar 18 802
804 Prater clear of Mews on 5A side, East Elevation 24 Apr 18 24 Apr 18 804
805 Prater clear of Mews on 5A side, South Elevation 09 May 18 09 May 18 805
848 Excavate for and install electric, data and telecoms ducts 1w 21 May 18 25 May 18 848
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
850 Ready to start flushing TEC to Buildings 8A and 8B 05 Jul 18 05 Jul 18 850
885
885 Stage 1B services 57w 4d 12 Jul 17 07 Sep 18
886 Deep Services 4d 12 Jul 17 17 Jul 17 886
887 SM4 to SM 18 3d 12 Jul 17 14 Jul 17 887
888 Build SM18 1d 17 Jul 17 17 Jul 17 888
889 FM4 to FM17 3d 12 Jul 17 14 Jul 17 889
890 Build FM 17 1d 14 Jul 17 14 Jul 17 890
892 Drainage & Services Between Manholes FM26 to FM17/FM4 (Stage 1B) 7w 23 May 18 11 Jul 18 892
897 Install Water Pipes in Trenches and all connections between main runs and buildings including heating and cooling pipework 6w 23 May 18 04 Jul 18 897
903 Excavation & Temporary Propping For Drainage 2w 11 Jul 18 24 Jul 18 903
905 Build Manhole FM22,FM23 & SM25, SM26, SM27, SM28 4w 27 Jul 18 23 Aug 18 905
907 Lay Foul & Surface Water drainage Pipes FM 26 To FM 22 3w 1d 13 Aug 18 04 Sep 18 907
909 Drainage & Services Between Manholes SM9/FM9 to SM7/FM7 (Stage 2) 62w 3d 28 Apr 17 31 Jul 18 909
914 Lay Foul & Surface Water drainage Pipes FM/SM 9 To FM/SM 8 1w 4d 16 May 17 16 Jun 17 914
917 Lay Foul & Surface Water drainage Pipes FM/SM 8 To FM/SM 7 1w 2d 17 May 17 16 Jun 17 917
922 Install District Heating Cooling connections to buildings 1w 10 Apr 18 16 Apr 18 922
939 Drainage & Services Between Manholes SM7/FM7 to SM3/FM3 (Stage 3) 67w 3d 09 May 17 13 Sep 18 939
944 Lay Foul & Surface Water drainage Pipes FM 7 To FM 6 1w 3d 16 May 17 16 Jun 17 944
947 Lay Foul & Surface Water drainage Pipes FM 6 To FM5 2w 15 May 17 11 Jul 17 947
960 Install 450 dia Flow and return DH Main 1w 4d 12 Jun 18 22 Jun 18 960
961 Install 600 dia Flow and return DC Main 1w 2d 12 Jun 18 20 Jun 18 961
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
969 Excavate for District Heating and Cooling 1w 12 Jun 18 18 Jun 18 969
970 Install DH/DC 1w 3d 25 Jun 18 04 Jul 18 970
971 Backfill 2d 05 Jul 18 06 Jul 18 971
972 Water Main 4w 05 Jul 18 01 Aug 18 972
973 Excavate for Sprinkler and Water main 1w 05 Jul 18 11 Jul 18 973
974 Install Spinkler Main 3d 12 Jul 18 16 Jul 18 974
975 Install Thames Water Pipes in Trench 1w 24 Jul 18 30 Jul 18 975
976 Backfill 2d 31 Jul 18 01 Aug 18 976
977 Combined Service Trench 2w 2d 02 Aug 18 17 Aug 18 977
987 Drainage & Services Between Manholes SM3/FM3 to SM1/FM1 (Stage 4) 12w 3d 14 Jun 17 11 Sep 17 987
1007 Drainage & Services Between Manholes FM29 to FM27 (Stage 5) 24w 3d 22 May 17 10 Nov 17 1007
1011 Build Manhole FM29, 28 & 27 & SM34, 35, 36 2w 1d 21 Jun 17 05 Jul 17 1011
1012 Lay Foul & Surface Water drainage Pipes FM 10 To FM 27 and attenuation tanks 3w 22 May 17 12 Jun 17 1012
1015 Lay Foul & Surface Water drainage Pipes FM 2 To FM1 2w 17 Jul 17 28 Jul 17 1015
1022 Install Water Pipes in Trenches and all connections between main runs and buildings including heating and cooling pipework 1w 25 Sep 17 29 Sep 17 1022
1025 Drainage & Services Between Manholes FM17 to FM12 (Stage 1C) 53w 2d 05 Jul 17 31 Jul 18 1025
1045 Pull HV/LV Cables Through Ducts & Terminate 10w 22 May 18 31 Jul 18 1045
1046 Drainage Connections to existing Thames Water Sewers 57w 3d 03 Aug 17 28 Sep 18 1046
1047 Thames Water construct manhole on existing sewer, and new manholes FM30 and SM13 10w 29 Jun 18 07 Sep 18 1047
1048 Thames Water lay drains and backfill 3w 10 Sep 18 28 Sep 18 1048
1049 Complete drainage between FM30 & FM11, SM12 and SM11 4w 03 Aug 17 12 Sep 17 1049
1050 Main Utility Services Onto Site 78w 4d 07 Mar 17 03 Oct 18 1050
1051 Water Main From Royal Albert Way To Site Ring Main 14w 30 Jun 17 06 Oct 17 1051
1052 Hydrant Main From Royal Albert Way To Site Ring Main 12w 14 Jul 17 06 Oct 17 1052
1053 Gas Main From Royal Albert Way To Site Ring Main 10w 28 Jul 17 06 Oct 17 1053
1055 HV Electrical Supply Cable From Albert Way To Temporary Site Sub Station 12w 07 Mar 17 02 Jun 17 1055
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1087 Ground Floor 9w 05 Sep 17 06 Nov 17 1087
1088 Pour 1 1w 05 Sep 17 11 Sep 17 1088
1089 Pour 2 2w 1d 07 Sep 17 21 Sep 17 1089
1090 Pour 3 1w 3d 25 Sep 17 04 Oct 17 1090
1091 Pour 4 1w 1d 02 Oct 17 18 Oct 17 1091
1092 Pour 5 2w 17 Oct 17 06 Nov 17 1092
Install ducts to take incoming electricity cables, DH/DC flow and return pipework and Sprinkler main to Building 9A and surround in
1093 2w 22 Sep 17 27 Oct 17 1093
concrete if necessary
1094 Superstructure 27w 1d 05 Sep 17 22 Mar 18 1094
1095 FRC 500mm high core wall from 4.500m and set platform to take slipform 1w 4d 05 Sep 17 15 Sep 17 1095
1096 SET UP SLIP FORM TO CORE WALLS 3w 18 Sep 17 06 Oct 17 1096
1097 SLIP 1ST LIFT 2d 09 Oct 17 10 Oct 17 1097
1098 INSTALL FOLLOW UP PLATFORMS 4d 16 Oct 17 19 Oct 17 1098
1099 SLIP CORE TO ROOF 4w 2d 20 Oct 17 20 Nov 17 1099
1100 DISMANTLE SLIP 1w 21 Nov 17 27 Nov 17 1100
1129 Shopfronts, windows External Doors & Louvres at Ground and First floors 7w 4d 10 Apr 18 06 Jun 18 1129
1130 Shopfronts, windows External Doors & Louvres at Ground and First floors - West 4w 10 Apr 18 09 May 18 1130
1131 Shopfronts, windows External Doors & Louvres at Ground and First floors - South 4w 18 Apr 18 17 May 18 1131
1132 Shopfronts, windows External Doors & Louvres at Ground and First floors - East 4w 30 Apr 18 29 May 18 1132
1133 Shopfronts, windows External Doors & Louvres at Ground and First floors - North 4w 09 May 18 06 Jun 18 1133
1142 Install Roof Louvres and Mansafe Latchways 5w 02 May 18 07 Jun 18 1142
1148 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 9A 08 Aug 17 08 Aug 17 1148
1158 Window for Cantidecks t load out upper floors - levels 5 - Roof (Level 9) 2w 1d 05 Mar 18 19 Mar 18 1158
1159 Construct hoist base 1 (North) 4d 19 Apr 18 24 Apr 18 1159
1163 Lift /Toilet Core Fit Out 56w 2d 23 Oct 17 07 Dec 18 1163
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1206 Perimeter drylining walls 3d 24 Apr 18 26 Apr 18 1206
1207 Screed 3d 30 Apr 18 02 May 18 1207
1208 High level domestic pipework 3d 03 May 18 08 May 18 1208
1209 Low level mechanical pipework 3d 09 May 18 11 May 18 1209
1210 High level LV electrical containment 3d 14 May 18 16 May 18 1210
1211 Wire and terminate to Distribution Boards 3d 17 May 18 21 May 18 1211
1212 Lighting, Fire Alarms, BMS, Control Wiring 3d 22 May 18 24 May 18 1212
1213 High level mechanical 1st Fix 3d 25 May 18 30 May 18 1213
1214 Wall Partition incl. Noggins and Vanity Frames 3d 31 May 18 04 Jun 18 1214
1222 2nd fix light fittings and electrical to ceilings 3d 09 Jul 18 11 Jul 18 1222
1232 Lighting, Fire Alarms, BMS, Control Wiring 3d 30 May 18 01 Jun 18 1232
1282 2nd fix light fittings and electrical to ceilings 3d 30 Jul 18 01 Aug 18 1282
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1336 Plasterboard Ceiling 3d 17 Jul 18 19 Jul 18 1336
1337 Floor tiling 3d 20 Jul 18 24 Jul 18 1337
1338 Joinery and doors 3d 25 Jul 18 27 Jul 18 1338
1339 Sanitaryware and Vanity units 1w 3d 30 Jul 18 08 Aug 18 1339
1340 Mist and one coat 3d 09 Aug 18 13 Aug 18 1340
1341 2nd Fix Mechanical to ceilings 4d 14 Aug 18 17 Aug 18 1341
1342 2nd fix light fittings and electrical to ceilings 3d 20 Aug 18 22 Aug 18 1342
1343 Partition system walls - Cubicles 1w 23 Aug 18 30 Aug 18 1343
1344 Final decorations 3d 31 Aug 18 04 Sep 18 1344
1366 Gnd Floor Lift Lobby Fit Out 6w 1d 16 Aug 18 28 Sep 18 1366
1379 1st Floor Lift Lobby Fit Out 6w 1d 21 Aug 18 03 Oct 18 1379
1381 High level mechanical 1st Fix incl. Duct works 2d 29 Aug 18 30 Aug 18 1381
1384 Lighting, Fire Alarms, BMS, Control Wiring 2d 06 Sep 18 07 Sep 18 1384
1392 2nd Floor Lift Lobby Fit Out 6w 1d 24 Aug 18 08 Oct 18 1392
1394 High level mechanical 1st Fix incl. Duct works 2d 03 Sep 18 04 Sep 18 1394
1397 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Sep 18 12 Sep 18 1397
1405 3rd Floor Lift Lobby Fit Out 6w 1d 30 Aug 18 11 Oct 18 1405
1407 High level mechanical 1st Fix incl. Duct works 2d 03 Sep 18 04 Sep 18 1407
1410 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Sep 18 12 Sep 18 1410
1419 4th Floor Lift Lobby Fit Out 6w 1d 04 Sep 18 16 Oct 18 1419
1421 High level mechanical 1st Fix incl. Duct works 2d 06 Sep 18 07 Sep 18 1421
1424 Lighting, Fire Alarms, BMS, Control Wiring 2d 14 Sep 18 17 Sep 18 1424
1433 5th Floor Lift Lobby Fit Out 6w 1d 07 Sep 18 19 Oct 18 1433
1435 High level mechanical 1st Fix incl. Duct works 2d 11 Sep 18 12 Sep 18 1435
1438 Lighting, Fire Alarms, BMS, Control Wiring 2d 19 Sep 18 20 Sep 18 1438
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1446 Final Ceiling Final MEP fixtures 3d 17 Oct 18 19 Oct 18 1446
1447 6th Floor Lift Lobby Fit Out 6w 1d 12 Sep 18 24 Oct 18 1447
1449 High level mechanical 1st Fix incl. Duct works 2d 14 Sep 18 17 Sep 18 1449
1452 Lighting, Fire Alarms, BMS, Control Wiring 2d 24 Sep 18 25 Sep 18 1452
1461 7th Floor Lift Lobby Fit Out 6w 1d 17 Sep 18 29 Oct 18 1461
1463 High level mechanical 1st Fix incl. Duct works 2d 19 Sep 18 20 Sep 18 1463
1466 Lighting, Fire Alarms, BMS, Control Wiring 2d 27 Sep 18 28 Sep 18 1466
1475 8th Floor Lift Lobby Fit Out 6w 1d 20 Sep 18 01 Nov 18 1475
1477 High level mechanical 1st Fix incl. Duct works 2d 24 Sep 18 25 Sep 18 1477
1480 Lighting, Fire Alarms, BMS, Control Wiring 2d 02 Oct 18 03 Oct 18 1480
1492 Lighting, Fire Alarms, BMS, Control Wiring 2d 28 Aug 18 29 Aug 18 1492
1502 Lighting, Fire Alarms, BMS, Control Wiring 2d 29 Aug 18 31 Aug 18 1502
1512 Lighting, Fire Alarms, BMS, Control Wiring 2d 31 Aug 18 04 Sep 18 1512
1522 Lighting, Fire Alarms, BMS, Control Wiring 2d 04 Sep 18 06 Sep 18 1522
1532 Lighting, Fire Alarms, BMS, Control Wiring 2d 06 Sep 18 10 Sep 18 1532
1542 Lighting, Fire Alarms, BMS, Control Wiring 2d 10 Sep 18 12 Sep 18 1542
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1548 Final Coat on ceiling 2d 26 Sep 18 28 Sep 18 1548
1552 Lighting, Fire Alarms, BMS, Control Wiring 2d 12 Sep 18 14 Sep 18 1552
1562 Lighting, Fire Alarms, BMS, Control Wiring 2d 14 Sep 18 18 Sep 18 1562
1572 Lighting, Fire Alarms, BMS, Control Wiring 2d 21 Sep 18 24 Sep 18 1572
1582 Lighting, Fire Alarms, BMS, Control Wiring 2d 25 Sep 18 26 Sep 18 1582
1592 Lighting, Fire Alarms, BMS, Control Wiring 2d 27 Sep 18 28 Sep 18 1592
1602 Lighting, Fire Alarms, BMS, Control Wiring 2d 01 Oct 18 02 Oct 18 1602
1612 Lighting, Fire Alarms, BMS, Control Wiring 2d 03 Oct 18 04 Oct 18 1612
1622 Lighting, Fire Alarms, BMS, Control Wiring 2d 05 Oct 18 08 Oct 18 1622
1632 Lighting, Fire Alarms, BMS, Control Wiring 2d 09 Oct 18 10 Oct 18 1632
1642 Lighting, Fire Alarms, BMS, Control Wiring 2d 11 Oct 18 12 Oct 18 1642
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1650 Staircase Flooring incl. Nosing 4w 26 Oct 18 22 Nov 18 1650
1654 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 9A 13 Dec 17 13 Dec 17 1654
1659
1659 Install conduit to cleaners sockets to core walls 1w 18 May 18 24 May 18
1660 Boarding and Insulation to external and core walls 2w 18 May 18 01 Jun 18 1660
1661
1661 Taping and Joining to Walls 1w 30 May 18 05 Jun 18
1662 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 30 May 18 12 Jun 18 1662
1663
1663 Install Joinery incl Doors 2w 13 Jun 18 26 Jun 18
1664 Decoration 2w 20 Jun 18 03 Jul 18 1664
1666 Install conduit to cleaners sockets to core walls 1w 25 May 18 01 Jun 18 1666
1667
1667 Boarding and Insulation to external and core walls 2w 25 May 18 08 Jun 18
1668 Taping and Joining to Walls 1w 06 Jun 18 12 Jun 18 1668
1669 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 06 Jun 18 19 Jun 18 1669
1675 Install conduit to cleaners sockets to core walls 1w 04 Jun 18 08 Jun 18 1675
1676
1676 Boarding and Insulation to external and core walls 2w 04 Jun 18 15 Jun 18
1677 Taping and Joining to Walls 1w 13 Jun 18 19 Jun 18 1677
1678
1678 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 13 Jun 18 26 Jun 18
1679 Install Joinery incl Doors 2w 27 Jun 18 10 Jul 18 1679
1680
1680 Decoration 2w 03 Jul 18 16 Jul 18
1681 Install Sprinkler Pipes to 2nd Floor 1w 03 May 18 10 May 18 1681
1682
1682 High Level Services Second Floor 8w 22 Feb 18 20 Apr 18
1683 Fit out Third Floor 19w 4d 01 Mar 18 24 Jul 18 1683
1684
1684 Install conduit to cleaners sockets to core walls 1w 11 Jun 18 15 Jun 18
1685 Boarding and Insulation to external and core walls 2w 11 Jun 18 22 Jun 18 1685
1686
1686 Taping and Joining to Walls 1w 20 Jun 18 26 Jun 18
1687 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 20 Jun 18 03 Jul 18 1687
1688
1688 Install Joinery incl Doors 2w 04 Jul 18 17 Jul 18
1689 Decoration 2w 11 Jul 18 24 Jul 18 1689
1693 Install conduit to cleaners sockets to core walls 1w 18 Jun 18 22 Jun 18 1693
1694
1694 Boarding and Insulation to external and core walls 2w 18 Jun 18 29 Jun 18
1695 Taping and Joining to Walls 1w 27 Jun 18 03 Jul 18 1695
1696
1696 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 27 Jun 18 10 Jul 18
1697 Install Joinery incl Doors 2w 11 Jul 18 24 Jul 18 1697
1698
1698 Decoration 2w 18 Jul 18 31 Jul 18
1699 Install Sprinkler Pipes to 4th Floor 1w 18 May 18 24 May 18 1699
1700
1700 High Level Services Fourth Floor 8w 08 Mar 18 08 May 18
1701 Fit out Fifth Floor 19w 4d 15 Mar 18 07 Aug 18 1701
1702
1702 Install conduit to cleaners sockets to core walls 1w 25 Jun 18 29 Jun 18
1703 Boarding and Insulation to external and core walls 2w 25 Jun 18 06 Jul 18 1703
1704
1704 Taping and Joining to Walls 1w 04 Jul 18 10 Jul 18
1705 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 04 Jul 18 17 Jul 18 1705
1707
1707 Decoration 2w 25 Jul 18 07 Aug 18
1708 Install Sprinkler Pipes to 5th Floor 1w 25 May 18 01 Jun 18 1708
1709
1709 High Level Services Fifth Floor 8w 15 Mar 18 15 May 18
1710 Fit out Sixth Floor 19w 4d 22 Mar 18 14 Aug 18 1710
1711
1711 Install conduit to cleaners sockets to core walls 1w 02 Jul 18 06 Jul 18
1712 Boarding and Insulation to external and core walls 2w 02 Jul 18 13 Jul 18 1712
1713
1713 Taping and Joining to Walls 1w 11 Jul 18 17 Jul 18
1714 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 11 Jul 18 24 Jul 18 1714
1715
1715 Install Joinery incl Doors 2w 25 Jul 18 07 Aug 18
1716 Decoration 2w 01 Aug 18 14 Aug 18 1716
1720 Install conduit to cleaners sockets to core walls 1w 09 Jul 18 13 Jul 18 1720
1721
1721 Boarding and Insulation to external and core walls 2w 09 Jul 18 20 Jul 18
1722 Taping and Joining to Walls 1w 18 Jul 18 24 Jul 18 1722
1723
1723 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 18 Jul 18 31 Jul 18
1724 Install Joinery incl Doors 2w 01 Aug 18 14 Aug 18 1724
1725
1725 Decoration 2w 08 Aug 18 21 Aug 18
1726 Install Sprinkler Pipes to 7th Floor 1w 11 Jun 18 15 Jun 18 1726
1727
1727 High Level Services Seventh Floor 8w 29 Mar 18 30 May 18
1728 Fit out Eighth Floor 18w 2d 25 Apr 18 05 Sep 18 1728
1729
1729 Install conduit to cleaners sockets to core walls 1w 23 Jul 18 27 Jul 18
1730 Boarding and Insulation to external and core walls 2w 23 Jul 18 03 Aug 18 1730
1731
1731 Taping and Joining to Walls 1w 01 Aug 18 07 Aug 18
1732 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 2w 01 Aug 18 14 Aug 18 1732
1733
1733 Install Joinery incl Doors 2w 15 Aug 18 29 Aug 18
1734 Decoration 2w 22 Aug 18 05 Sep 18 1734
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1753 Partition closure 2d 07 Sep 18 10 Sep 18 1753
1756
1756 Complete Ceiling Tiles 1w 01 Oct 18 05 Oct 18
1757 Install Raised Access Floor incl Below Floor Barriers 2w 08 Oct 18 19 Oct 18 1757
1758
1758 Soft Floor Coverings 1w 22 Oct 18 26 Oct 18
1759 Prepare 1st Floor for Handover 4w 03 Oct 18 30 Oct 18 1759
1760
1760 Complete Ceiling Tiles 1w 03 Oct 18 09 Oct 18
1761 Install Raised Access Floor incl Below Floor Barriers 2w 10 Oct 18 23 Oct 18 1761
1762
1762 Soft Floor Coverings 1w 24 Oct 18 30 Oct 18
1763 Prepare 2nd Floor for Handover 4w 08 Oct 18 02 Nov 18 1763
1764
1764 Complete Ceiling Tiles 1w 08 Oct 18 12 Oct 18
1765 Install Raised Access Floor incl Below Floor Barriers 2w 15 Oct 18 26 Oct 18 1765
1766
1766 Soft Floor Coverings 1w 29 Oct 18 02 Nov 18
1767 Prepare 3rd Floor for Handover 4w 11 Oct 18 07 Nov 18 1767
1768
1768 Complete Ceiling Tiles 1w 11 Oct 18 17 Oct 18
1769 Install Raised Access Floor incl Below Floor Barriers 2w 18 Oct 18 31 Oct 18 1769
1770
1770 Soft Floor Coverings 1w 01 Nov 18 07 Nov 18
1771 Prepare 4th Floor for Handover 4w 16 Oct 18 12 Nov 18 1771
1772
1772 Complete Ceiling Tiles 1w 16 Oct 18 22 Oct 18
1773 Install Raised Access Floor incl Below Floor Barriers 2w 23 Oct 18 05 Nov 18 1773
1774
1774 Soft Floor Coverings 1w 06 Nov 18 12 Nov 18
1775 Prepare 5th Floor for handover 4w 19 Oct 18 15 Nov 18 1775
1777
1777 Install Raised Access Floor incl Below Floor Barriers 2w 26 Oct 18 08 Nov 18
1778 Soft Floor Coverings 1w 09 Nov 18 15 Nov 18 1778
1781
1781 Install Raised Access Floor incl Below Floor Barriers 2w 31 Oct 18 13 Nov 18
1782 Soft Floor Coverings 1w 14 Nov 18 20 Nov 18 1782
1785
1785 Install Raised Access Floor incl Below Floor Barriers 2w 05 Nov 18 16 Nov 18
1786 Soft Floor Coverings 1w 19 Nov 18 23 Nov 18 1786
1789
1789 Install Raised Access Floor incl Below Floor Barriers 2w 05 Nov 18 16 Nov 18
1790 Soft Floor Coverings 1w 19 Nov 18 23 Nov 18 1790
1792 External Roads & Landscaping to Building 9A 35w 4d 18 May 18 08 Feb 19 1792
1844 STAND PRECAST CORE WALLS GND - 1ST FLOOR 4d 11 Sep 17 27 Sep 17 1844
1845 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 2w 13 Sep 17 26 Sep 17 1845
1846 FRC 1ST FLOOR SLAB 2w 2d 27 Sep 17 12 Oct 17 1846
1847 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 4d 06 Oct 17 16 Oct 17 1847
1848 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 1w 4d 09 Oct 17 19 Oct 17 1848
1849 FRC 2ND FLOOR SLAB 1w 3d 10 Oct 17 25 Oct 17 1849
1850 STAND PRECAST WALLS 2ND - 3RD FLOOR 4d 24 Oct 17 27 Oct 17 1850
1851 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 1w 2d 19 Oct 17 27 Oct 17 1851
1852 FRC 3RD FLOOR SLAB 2w 25 Oct 17 07 Nov 17 1852
1853 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 4d 02 Nov 17 09 Nov 17 1853
1854 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 1w 2d 02 Nov 17 10 Nov 17 1854
1855 FRC 4TH FLOOR SLAB 2w 02 Nov 17 15 Nov 17 1855
1856 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 4d 09 Nov 17 17 Nov 17 1856
1857 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 1w 3d 10 Nov 17 21 Nov 17 1857
1858 FRC 5TH FLOOR SLAB 2w 14 Nov 17 27 Nov 17 1858
1859 STAND PRECAST WALLS 5TH - 6TH FLOOR 4d 21 Nov 17 29 Nov 17 1859
1860 STAND PRECAST COLUMNS 5TH - 6TH FLOOR 1w 3d 21 Nov 17 30 Nov 17 1860
1861 FRC 6TH FLOOR SLAB 2w 2d 24 Nov 17 11 Dec 17 1861
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1870 Facades 35w 4d 15 Jan 18 28 Sep 18 1870
1879 Install SFS, Windows and Cladding Level 6 South elevation 7w 22 Jan 18 09 Mar 18 1879
1880 Install SFS, Windows and Cladding Level 6 North East and West Elevation 5w 12 Feb 18 16 Mar 18 1880
1881 Install ribbon window curtain walling to North Elevation 5w 12 Feb 18 16 Mar 18 1881
1885 Complete ribbon windows after hoists removed 3w 04 Jun 18 22 Jun 18 1885
1886 Canopies 31w 16 Feb 18 28 Sep 18 1886
1887 Install Frame for the Canopies 1w 16 Feb 18 22 Feb 18 1887
1888 Complete cantilevered frame & glazing for Canopies 1w 24 Sep 18 28 Sep 18 1888
1895 Install Stair Core Roofing and cladding 4w 19 Feb 18 16 Mar 18 1895
1896 Roof Finishes to roof and terrace incl. Aluminum copings 4w 19 Feb 18 16 Mar 18 1896
1899 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 8A 25 Jul 17 25 Jul 17 1899
1924 Window for Cantidecks to load out upper floors 4w 4d 15 Jan 18 15 Feb 18 1924
1928 Lift /Toilet Core Fit Out 63w 05 Sep 17 06 Dec 18 1928
1939 Hand back Lift 2 after builders beneficial use 16 Nov 18 16 Nov 18 1939
1940 Recommission Lift 2 2w 16 Nov 18 29 Nov 18 1940
1949 Hand back Lift 4 after builders beneficial use 23 Nov 18 23 Nov 18 1949
1965 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Apr 18 20 Apr 18 1965
1966 Mark and Cut openings for MEP on walls including Ceiling 2d 23 Apr 18 24 Apr 18 1966
1972 1st Fix Wall with Head tracks 1w 15 Feb 18 21 Feb 18 1972
1973 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Feb 18 21 Mar 18 1973
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
1987 Final Coat Paint on walls & Ceilings 2d 23 Mar 18 26 Mar 18 1987
1988 Level 02 - CORE 01 12w 22 Feb 18 22 May 18 1988
1989 Toilet 12w 22 Feb 18 22 May 18 1989
1990 1st Fix Wall with Head tracks 1w 22 Feb 18 28 Feb 18 1990
1991 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Mar 18 28 Mar 18 1991
1992 Fix Pocket Doors 1w 01 Mar 18 07 Mar 18 1992
1993 Inspection and Ceiling Grid Clearance 29 Mar 18 29 Mar 18 1993
1994 2nd Fix wall 1w 29 Mar 18 06 Apr 18 1994
1995 IPS Frame (Box Out only) incl. Backing ply 3d 09 Apr 18 11 Apr 18 1995
1999 Wall Tiling works incl. IPS Panels 3d 24 Apr 18 26 Apr 18 1999
2000 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 Apr 18 08 May 18 2000
2001 Mark and Cut openings for MEP on walls including Ceiling 2d 09 May 18 10 May 18 2001
2003 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 May 18 16 May 18 2003
2004 Fix MEP Final Fixtures 3d 16 May 18 18 May 18 2004
2005 Final Coat Paint on Ceiling 2d 21 May 18 22 May 18 2005
2006 Lobby 8w 3d 01 Mar 18 03 May 18 2006
2007 1st Fix Wall with Head tracks 1w 01 Mar 18 07 Mar 18 2007
2008 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Mar 18 06 Apr 18 2008
2009 Fix Ceiling Grid 3d 09 Apr 18 11 Apr 18 2009
2010 Paint 1st Coat 2d 12 Apr 18 13 Apr 18 2010
2011 Fix doors incl. Ironmongery 2d 16 Apr 18 17 Apr 18 2011
2012 Mark and Cut openings for MEP on walls 2d 18 Apr 18 19 Apr 18 2012
2013 Install Ceiling Tiles 3d 20 Apr 18 24 Apr 18 2013
2014 Fix MEP Final Fixtures 3d 25 Apr 18 30 Apr 18 2014
2015 Final Coat Paint on walls and ceiling 3d 01 May 18 03 May 18 2015
2016 Staircase Level 02 - CORE 01 2w 1d 19 Mar 18 04 Apr 18 2016
2017 H/L Electrical Containment & Conduits - 1st Fix 2d 19 Mar 18 20 Mar 18 2017
2018 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 21 Mar 18 22 Mar 18 2018
2019 Ceiling Rose fixing 1d 23 Mar 18 23 Mar 18 2019
2020 First Coat Paint on Walls & Ceiliings 2d 26 Mar 18 27 Mar 18 2020
2021 MEP Final Fixtures on Wall & Ceilings 2d 28 Mar 18 29 Mar 18 2021
2022 Final Coat Paint on walls & Ceilings 2d 03 Apr 18 04 Apr 18 2022
2026 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Mar 18 13 Apr 18 2026
2027 Fix Pocket Doors 1w 15 Mar 18 21 Mar 18 2027
2028 Inspection and Ceiling Grid Clearance 16 Apr 18 16 Apr 18 2028
2029 2nd Fix wall 1w 16 Apr 18 20 Apr 18 2029
2030 IPS Frame (Box Out only) incl. Backing ply 3d 23 Apr 18 25 Apr 18 2030
2031 Screed 2d 26 Apr 18 30 Apr 18 2031
2032 Fix Ceiling Grid Works 3d 01 May 18 03 May 18 2032
2033 Floor Tiling Works 3d 04 May 18 09 May 18 2033
2034 Wall Tiling works incl. IPS Panels 3d 10 May 18 14 May 18 2034
2035 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 15 May 18 22 May 18 2035
2036 Mark and Cut openings for MEP on walls including Ceiling 2d 23 May 18 24 May 18 2036
2037 Install Vanity Tops 4d 23 May 18 29 May 18 2037
2038 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 May 18 31 May 18 2038
2039 Fix MEP Final Fixtures 3d 31 May 18 04 Jun 18 2039
2040 Final Coat Paint on Ceiling 2d 05 Jun 18 06 Jun 18 2040
2041 Lobby 8w 3d 15 Mar 18 18 May 18 2041
2042 1st Fix Wall with Head tracks 1w 15 Mar 18 21 Mar 18 2042
2043 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Mar 18 20 Apr 18 2043
2044 Fix Ceiling Grid 3d 23 Apr 18 25 Apr 18 2044
2052 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Apr 18 12 Apr 18 2052
2053 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Apr 18 16 Apr 18 2053
2055 First Coat Paint on Walls & Ceiliings 2d 18 Apr 18 19 Apr 18 2055
2056 MEP Final Fixtures on Wall & Ceilings 2d 20 Apr 18 23 Apr 18 2056
2057 Final Coat Paint on walls & Ceilings 2d 24 Apr 18 25 Apr 18 2057
2058 Level 04 - CORE 01 12w 22 Mar 18 20 Jun 18 2058
2059 Toilet 12w 22 Mar 18 20 Jun 18 2059
2060 1st Fix Wall with Head tracks 1w 22 Mar 18 28 Mar 18 2060
2061 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 29 Mar 18 30 Apr 18 2061
2062 Fix Pocket Doors 1w 29 Mar 18 06 Apr 18 2062
2063 Inspection and Ceiling Grid Clearance 01 May 18 01 May 18 2063
2064 2nd Fix wall 1w 01 May 18 08 May 18 2064
2065 IPS Frame (Box Out only) incl. Backing ply 3d 09 May 18 11 May 18 2065
2066 Screed 2d 14 May 18 15 May 18 2066
2067 Fix Ceiling Grid Works 3d 16 May 18 18 May 18 2067
2068 Floor Tiling Works 3d 21 May 18 23 May 18 2068
2069 Wall Tiling works incl. IPS Panels 3d 24 May 18 29 May 18 2069
2070 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 30 May 18 06 Jun 18 2070
2071 Mark and Cut openings for MEP on walls including Ceiling 2d 07 Jun 18 08 Jun 18 2071
2072 Install Vanity Tops 4d 07 Jun 18 12 Jun 18 2072
2073 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 Jun 18 14 Jun 18 2073
2074 Fix MEP Final Fixtures 3d 14 Jun 18 18 Jun 18 2074
2075 Final Coat Paint on Ceiling 2d 19 Jun 18 20 Jun 18 2075
2077 1st Fix Wall with Head tracks 1w 29 Mar 18 06 Apr 18 2077
2078 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 Apr 18 08 May 18 2078
2104 Wall Tiling works incl. IPS Panels 3d 08 Jun 18 12 Jun 18 2104
2105 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Jun 18 20 Jun 18 2105
2106 Mark and Cut openings for MEP on walls including Ceiling 2d 21 Jun 18 22 Jun 18 2106
2107 Install Vanity Tops 4d 21 Jun 18 26 Jun 18 2107
2108 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 2108
2109 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 2109
2110 Final Coat Paint on Ceiling 2d 03 Jul 18 04 Jul 18 2110
2111 Lobby 8w 3d 16 Apr 18 18 Jun 18 2111
2112 1st Fix Wall with Head tracks 1w 16 Apr 18 20 Apr 18 2112
2113 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 2113
2114 Fix Ceiling Grid 3d 23 May 18 25 May 18 2114
2115 Paint 1st Coat 2d 29 May 18 30 May 18 2115
2116 Fix doors incl. Ironmongery 2d 31 May 18 01 Jun 18 2116
2117 Mark and Cut openings for MEP on walls 2d 04 Jun 18 05 Jun 18 2117
2118 Install Ceiling Tiles 3d 06 Jun 18 08 Jun 18 2118
2122 H/L Electrical Containment & Conduits - 1st Fix 2d 11 May 18 14 May 18 2122
2123 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 15 May 18 16 May 18 2123
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2124 Ceiling Rose fixing 1d 17 May 18 17 May 18 2124
2125 First Coat Paint on Walls & Ceiliings 2d 18 May 18 21 May 18 2125
2126 MEP Final Fixtures on Wall & Ceilings 2d 22 May 18 23 May 18 2126
2127 Final Coat Paint on walls & Ceilings 2d 24 May 18 25 May 18 2127
2128 Level 06 - CORE 01 12w 23 Apr 18 18 Jul 18 2128
2129 Toilet 12w 23 Apr 18 18 Jul 18 2129
2130 1st Fix Wall with Head tracks 1w 23 Apr 18 30 Apr 18 2130
2131 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 2131
2132 Fix Pocket Doors 1w 01 May 18 08 May 18 2132
2139 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 2139
2140 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 2140
2141 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 2141
2142 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 2142
2143 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 2143
2144 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 2144
2145 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 2145
2146 Lobby 8w 3d 01 May 18 02 Jul 18 2146
2147 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 2147
2148 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 2148
2149 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 2149
2150 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 2150
2151 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 2151
2152 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 2152
2153 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 2153
2154 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 2154
2155 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 2155
2156 Staircase Level 06 - CORE 01 2w 1d 25 May 18 11 Jun 18 2156
2157 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 2157
2158 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 2158
2160 First Coat Paint on Walls & Ceiliings 2d 04 Jun 18 05 Jun 18 2160
2161 MEP Final Fixtures on Wall & Ceilings 2d 06 Jun 18 07 Jun 18 2161
2162 Final Coat Paint on walls & Ceilings 2d 08 Jun 18 11 Jun 18 2162
2166 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 2166
2167 Fix Pocket Doors 1w 16 May 18 22 May 18 2167
2182 1st Fix Wall with Head tracks 1w 16 May 18 22 May 18 2182
2183 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 2183
2190 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 2190
2191 Staircase Level GF - CORE 01 2w 1d 11 Jun 18 25 Jun 18 2191
2192 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 2192
2193 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 2193
2194 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 2194
2195 First Coat Paint on Walls & Ceiliings 2d 18 Jun 18 19 Jun 18 2195
2196 MEP Final Fixtures on Wall & Ceilings 2d 20 Jun 18 21 Jun 18 2196
2197 Final Coat Paint on walls & Ceilings 2d 22 Jun 18 25 Jun 18 2197
2212 Mark and Cut openings for MEP on walls including Ceiling 2d 09 May 18 10 May 18 2212
2214 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 11 May 18 16 May 18 2214
2233 Final Coat Paint on walls & Ceilings 2d 10 Apr 18 11 Apr 18 2233
2234 Level 02 - CORE 02 12w 08 Mar 18 06 Jun 18 2234
2237 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Mar 18 13 Apr 18 2237
2258 Mark and Cut openings for MEP on walls 2d 03 May 18 04 May 18 2258
2259 Install Ceiling Tiles 3d 08 May 18 10 May 18 2259
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2260 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 2260
2261 Final Coat Paint on walls and ceiling 3d 16 May 18 18 May 18 2261
2262 Staircase Level 02 - CORE 02 2w 1d 11 Apr 18 25 Apr 18 2262
2263 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Apr 18 12 Apr 18 2263
2264 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Apr 18 16 Apr 18 2264
2265 Ceiling Rose fixing 1d 17 Apr 18 17 Apr 18 2265
2266 First Coat Paint on Walls & Ceiliings 2d 18 Apr 18 19 Apr 18 2266
2267 MEP Final Fixtures on Wall & Ceilings 2d 20 Apr 18 23 Apr 18 2267
2268 Final Coat Paint on walls & Ceilings 2d 24 Apr 18 25 Apr 18 2268
2299 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 Apr 18 01 May 18 2299
2300 Ceiling Rose fixing 1d 02 May 18 02 May 18 2300
2301 First Coat Paint on Walls & Ceiliings 2d 03 May 18 04 May 18 2301
2302 MEP Final Fixtures on Wall & Ceilings 2d 08 May 18 09 May 18 2302
2303 Final Coat Paint on walls & Ceilings 2d 10 May 18 11 May 18 2303
2304 Level 04 - CORE 02 12w 09 Apr 18 04 Jul 18 2304
2305 Toilet 12w 09 Apr 18 04 Jul 18 2305
2306 1st Fix Wall with Head tracks 1w 09 Apr 18 13 Apr 18 2306
2307 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 Apr 18 15 May 18 2307
2308 Fix Pocket Doors 1w 16 Apr 18 20 Apr 18 2308
2309 Inspection and Ceiling Grid Clearance 16 May 18 16 May 18 2309
2310 2nd Fix wall 1w 16 May 18 22 May 18 2310
2311 IPS Frame (Box Out only) incl. Backing ply 3d 23 May 18 25 May 18 2311
2312 Screed 2d 29 May 18 30 May 18 2312
2313 Fix Ceiling Grid Works 3d 31 May 18 04 Jun 18 2313
2314 Floor Tiling Works 3d 05 Jun 18 07 Jun 18 2314
2315 Wall Tiling works incl. IPS Panels 3d 08 Jun 18 12 Jun 18 2315
2316 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 13 Jun 18 20 Jun 18 2316
2317 Mark and Cut openings for MEP on walls including Ceiling 2d 21 Jun 18 22 Jun 18 2317
2319 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 2319
2320 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 2320
2328 Mark and Cut openings for MEP on walls 2d 04 Jun 18 05 Jun 18 2328
2342 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 2342
2343 Fix Pocket Doors 1w 01 May 18 08 May 18 2343
2350 Wall Tiling works incl. IPS Panels 3d 22 Jun 18 26 Jun 18 2350
2351 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 27 Jun 18 04 Jul 18 2351
2352 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 2352
2353 Install Vanity Tops 4d 05 Jul 18 10 Jul 18 2353
2354 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 2354
2355 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 2355
2356 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 2356
2357 Lobby 8w 3d 01 May 18 02 Jul 18 2357
2358 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 2358
2359 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 2359
2360 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 2360
2361 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 2361
2362 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 2362
2363 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 2363
2364 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 2364
2365 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 2365
2366 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 2366
2372 MEP Final Fixtures on Wall & Ceilings 2d 06 Jun 18 07 Jun 18 2372
2373 Final Coat Paint on walls & Ceilings 2d 08 Jun 18 11 Jun 18 2373
2377 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 2377
2378 Fix Pocket Doors 1w 16 May 18 22 May 18 2378
2379 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 2379
2380 2nd Fix wall 1w 14 Jun 18 20 Jun 18 2380
2381 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 2381
2382 Screed 2d 26 Jun 18 27 Jun 18 2382
2383 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 2383
2384 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 2384
2385 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 2385
2386 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 2386
2387 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 2387
2388 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 2388
2389 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 2389
2390 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 2390
2391 Final Coat Paint on Ceiling 2d 31 Jul 18 01 Aug 18 2391
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2397 Fix doors incl. Ironmongery 2d 28 Jun 18 29 Jun 18 2397
2398 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 2398
2399 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 2399
2400 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 2400
2401 Final Coat Paint on walls and ceiling 3d 12 Jul 18 16 Jul 18 2401
2402 Staircase 5w 2d 11 Jun 18 17 Jul 18 2402
2403 H/L Electrical Containment & Conduits - 1st Fix 2d 11 Jun 18 12 Jun 18 2403
2404 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 13 Jun 18 14 Jun 18 2404
2405 Ceiling Rose fixing 1d 15 Jun 18 15 Jun 18 2405
2406 First Coat Paint on Walls & Ceiliings 2d 28 Jun 18 29 Jun 18 2406
2407 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 2407
2408 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 2408
2412 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 2412
2413 Fix Pocket Doors 1w 31 May 18 06 Jun 18 2413
2414 Inspection and Ceiling Grid Clearance 28 Jun 18 28 Jun 18 2414
2415 2nd Fix wall 1w 28 Jun 18 04 Jul 18 2415
2416 IPS Frame (Box Out only) incl. Backing ply 3d 05 Jul 18 09 Jul 18 2416
2417 Screed 2d 10 Jul 18 11 Jul 18 2417
2418 Fix Ceiling Grid Works 3d 12 Jul 18 16 Jul 18 2418
2419 Floor Tiling Works 3d 17 Jul 18 19 Jul 18 2419
2420 Wall Tiling works incl. IPS Panels 3d 20 Jul 18 24 Jul 18 2420
2421 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 25 Jul 18 01 Aug 18 2421
2422 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Aug 18 03 Aug 18 2422
2423 Install Vanity Tops 4d 02 Aug 18 07 Aug 18 2423
2424 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Aug 18 09 Aug 18 2424
2425 Fix MEP Final Fixtures 3d 09 Aug 18 13 Aug 18 2425
2426 Final Coat Paint on Ceiling 2d 14 Aug 18 15 Aug 18 2426
2427 Lobby 8w 3d 31 May 18 30 Jul 18 2427
2428 1st Fix Wall with Head tracks 1w 31 May 18 06 Jun 18 2428
2429 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 2429
2430 Fix Ceiling Grid 3d 05 Jul 18 09 Jul 18 2430
2431 Paint 1st Coat 2d 10 Jul 18 11 Jul 18 2431
2432 Fix doors incl. Ironmongery 2d 12 Jul 18 13 Jul 18 2432
2433 Mark and Cut openings for MEP on walls 2d 16 Jul 18 17 Jul 18 2433
2434 Install Ceiling Tiles 3d 18 Jul 18 20 Jul 18 2434
2435 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 2435
2436 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 2436
2437 Staircase 5w 2d 25 Jun 18 31 Jul 18 2437
2438 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 2438
2439 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 2439
2441 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 2441
2442 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 2442
2443 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 2443
2447 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 8A 28 Nov 17 28 Nov 17 2447
2450 Install conduit to cleaners sockets to core walls 3d 22 Mar 18 26 Mar 18 2450
2451 Boarding and Insulation to external and core walls 1w 27 Mar 18 04 Apr 18 2451
2454 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Apr 18 18 Apr 18 2454
2459 Install conduit to cleaners sockets to core walls 3d 05 Apr 18 09 Apr 18 2459
2463 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Apr 18 03 May 18 2463
2467 Install conduit to cleaners sockets to core walls 3d 17 Apr 18 19 Apr 18 2467
2468 Boarding and Insulation to external and core walls 1w 20 Apr 18 26 Apr 18 2468
2471 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 May 18 14 May 18 2471
2477 Install conduit to cleaners sockets to core walls 3d 19 Apr 18 23 Apr 18 2477
2478 Boarding and Insulation to external and core walls 1w 24 Apr 18 01 May 18 2478
2481 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 May 18 16 May 18 2481
2485 Install conduit to cleaners sockets to core walls 3d 02 May 18 04 May 18 2485
2486 Boarding and Insulation to external and core walls 1w 08 May 18 14 May 18 2486
2489 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 May 18 29 May 18 2489
2495 Install conduit to cleaners sockets to core walls 3d 04 May 18 09 May 18 2495
2496 Boarding and Insulation to external and core walls 1w 10 May 18 16 May 18 2496
2499 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 24 May 18 31 May 18 2499
2503 Install conduit to cleaners sockets to core walls 3d 17 May 18 21 May 18 2503
2504 Boarding and Insulation to external and core walls 1w 22 May 18 29 May 18 2504
2507 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Jun 18 12 Jun 18 2507
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2511 Fit-out Fourth Floor 6w 1d 21 May 18 03 Jul 18 2511
2513 Install conduit to cleaners sockets to core walls 3d 21 May 18 23 May 18 2513
2514 Boarding and Insulation to external and core walls 1w 24 May 18 31 May 18 2514
2517 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Jun 18 14 Jun 18 2517
2521 Install conduit to cleaners sockets to core walls 3d 01 Jun 18 05 Jun 18 2521
2522 Boarding and Insulation to external and core walls 1w 06 Jun 18 12 Jun 18 2522
2525 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 20 Jun 18 26 Jun 18 2525
2531 Install conduit to cleaners sockets to core walls 3d 05 Jun 18 07 Jun 18 2531
2532 Boarding and Insulation to external and core walls 1w 08 Jun 18 14 Jun 18 2532
2535 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Jun 18 28 Jun 18 2535
2539 Install conduit to cleaners sockets to core walls 3d 15 Jun 18 19 Jun 18 2539
2540 Boarding and Insulation to external and core walls 1w 20 Jun 18 26 Jun 18 2540
2543 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 04 Jul 18 10 Jul 18 2543
2549 Install conduit to cleaners sockets to core walls 3d 19 Jun 18 21 Jun 18 2549
2550 Boarding and Insulation to external and core walls 1w 22 Jun 18 28 Jun 18 2550
2553 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Jul 18 12 Jul 18 2553
2557 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18 2557
2558 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 2558
2561 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18 2561
2565 Temporary Access Closure - Cat A Fit Out 2w 2d 01 Aug 18 16 Aug 18 2565
2581 Install Raised Access Floor incl Below Floor Barriers 1w 10 Oct 18 16 Oct 18 2581
2585 Install Raised Access Floor incl Below Floor Barriers 1w 15 Oct 18 22 Oct 18 2585
2589 Install Raised Access Floor incl Below Floor Barriers 1w 18 Oct 18 25 Oct 18 2589
2593 Install Raised Access Floor incl Below Floor Barriers 1w 23 Oct 18 30 Oct 18 2593
2597 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 02 Nov 18 2597
2601 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 07 Nov 18 2601
2605 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 2605
2610 Install Raised Access Floor incl Below Floor Barriers 1w 17 Oct 18 23 Oct 18 2610
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2613 Complete Ceiling Tiles 1w 15 Oct 18 19 Oct 18 2613
2614 Install Raised Access Floor incl Below Floor Barriers 1w 22 Oct 18 26 Oct 18 2614
2618 Install Raised Access Floor incl Below Floor Barriers 1w 25 Oct 18 31 Oct 18 2618
2622 Install Raised Access Floor incl Below Floor Barriers 1w 30 Oct 18 05 Nov 18 2622
2626 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 2626
2630 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 2630
2634 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 2634
2641 Test and confirm Piling Mat Compliance with requirements 2d 11 May 17 12 May 17 2641
2642 Handover to Keltbray 1d 15 May 17 15 May 17 2642
2672 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 4w 2d 05 Sep 17 04 Oct 17 2672
2673 FRC 2ND FLOOR SLAB 4w 12 Sep 17 09 Oct 17 2673
2674 STAND PRECAST WALLS 2ND - 3RD FLOOR 1w 1d 20 Sep 17 17 Oct 17 2674
2675 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 3w 1d 21 Sep 17 17 Oct 17 2675
2676 FRC 3RD FLOOR SLAB 2w 4d 02 Oct 17 25 Oct 17 2676
2677 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 1w 1d 09 Oct 17 27 Oct 17 2677
2678 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 2w 2d 10 Oct 17 27 Oct 17 2678
2679 FRC 4TH FLOOR SLAB 3w 2d 05 Oct 17 03 Nov 17 2679
2680 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 1w 1d 24 Oct 17 07 Nov 17 2680
2681 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 1d 24 Oct 17 07 Nov 17 2681
2682 FRC 5TH FLOOR SLAB 3w 3d 26 Oct 17 20 Nov 17 2682
2683 STAND PRECAST WALLS 5TH - ROOF 1w 1d 06 Nov 17 22 Nov 17 2683
2684 STAND PRECAST COLUMNS 5TH - ROOF 2w 3d 06 Nov 17 22 Nov 17 2684
2685 FRC ROOF SLAB 3w 3d 06 Nov 17 29 Nov 17 2685
2686 STAND PRECAST CORE WALL OVERRUNS 1w 1d 15 Nov 17 01 Dec 17 2686
2693 Precast Cladding Panels North elevation Bay 1 3d 06 Dec 17 08 Dec 17 2693
2694 Precast Cladding Panels North elevation Bay 2 3d 11 Dec 17 13 Dec 17 2694
2695 Precast Cladding Panels North elevation Bay 3 3d 14 Dec 17 18 Dec 17 2695
2696 Precast Cladding Panels North elevation Bay 4 4d 19 Dec 17 22 Dec 17 2696
2699 Precast Cladding Panels South elevation Bay 1 3d 08 Jan 18 10 Jan 18 2699
2700 Precast Cladding Panels South elevation Bay 2 3d 11 Jan 18 15 Jan 18 2700
2701 Precast Cladding Panels South elevation Bay 3 3d 16 Jan 18 18 Jan 18 2701
2702 Precast Cladding Panels South elevation Bay 4 4d 19 Jan 18 24 Jan 18 2702
2708 Install SFS, Windows and Cladding Level 5 North 9w 08 Jan 18 09 Mar 18 2708
2709 Install ribbon window curtain walling to South Elevation 7w 19 Jan 18 08 Mar 18 2709
2710 Install SFS, Windows and Cladding Level 5 South East and West 6w 1d 25 Jan 18 08 Mar 18 2710
2711 Curtain Walling/ Doors Ground Floor 10w 08 Jan 18 16 Mar 18 2711
2714 Complete ribbon windows after hoists removed 3w 04 Jun 18 22 Jun 18 2714
2715 Canopies 31w 2d 07 Feb 18 21 Sep 18 2715
2716 Install Frame for the Canopies 1w 07 Feb 18 13 Feb 18 2716
2717 Complete Frame & glazing for Canopies 1w 17 Sep 18 21 Sep 18 2717
2723 Roof Finishes to roof and terrace incl. Aluminum copings 5w 2d 29 Jan 18 06 Mar 18 2723
2724 Install Stair Core Roofing and cladding 5w 2d 22 Jan 18 27 Feb 18 2724
2725 Building 8B Temporary Weatherproof 22 Jan 18 22 Jan 18 2725
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2727 Access ladders 2w 07 Mar 18 20 Mar 18 2727
2728 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 8B 28 Jul 17 28 Jul 17 2728
2736 Install roof plant and connect to risers 11w 02 Mar 18 23 May 18 2736
2752 Window for Cantidecks to load out upper floor 2w 03 Jan 18 16 Jan 18 2752
2753 Erect Hoist 2w 16 Jan 18 29 Jan 18 2753
2756 Lift /Toilet Core Fit Out 67w 2d 15 Aug 17 18 Dec 18 2756
2767 Hand back Lift 2 after builders beneficial use 21 Nov 18 21 Nov 18 2767
2768 Recommission Lift 2 2w 21 Nov 18 04 Dec 18 2768
2777 Hand back Lift 4 after builders beneficial use 28 Nov 18 28 Nov 18 2777
2778 Recommission Lift 4 2w 28 Nov 18 11 Dec 18 2778
2787 Hand back Lift 6 after builders beneficial use 05 Dec 18 05 Dec 18 2787
2793 1st Fix Wall with Head tracks 1w 16 Jan 18 22 Jan 18 2793
2794 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Jan 18 19 Feb 18 2794
2795 Fix Pocket Doors 1w 23 Jan 18 29 Jan 18 2795
2798 IPS Frame (Box Out only) incl. Backing ply 3d 27 Feb 18 01 Mar 18 2798
2803 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 19 Mar 18 26 Mar 18 2803
2804 Mark and Cut openings for MEP on walls including Ceiling 2d 27 Mar 18 28 Mar 18 2804
2805 Install Vanity Tops 4d 27 Mar 18 03 Apr 18 2805
2806 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 29 Mar 18 05 Apr 18 2806
2807 Fix MEP Final Fixtures 3d 05 Apr 18 09 Apr 18 2807
2808 Final Coat Paint on Ceiling 2d 10 Apr 18 11 Apr 18 2808
2809 Lobby 8w 3d 23 Jan 18 22 Mar 18 2809
2810 1st Fix Wall with Head tracks 1w 23 Jan 18 29 Jan 18 2810
2811 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 30 Jan 18 26 Feb 18 2811
2812 Fix Ceiling Grid 3d 27 Feb 18 01 Mar 18 2812
2813 Paint 1st Coat 2d 02 Mar 18 05 Mar 18 2813
2814 Fix doors incl. Ironmongery 2d 06 Mar 18 07 Mar 18 2814
2815 Mark and Cut openings for MEP on walls 2d 08 Mar 18 09 Mar 18 2815
2818 Final Coat Paint on walls and ceiling 3d 20 Mar 18 22 Mar 18 2818
2819 Staircase Level 01 - CORE 01 2w 1d 04 Apr 18 18 Apr 18 2819
2820 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Apr 18 05 Apr 18 2820
2821 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Apr 18 09 Apr 18 2821
2823 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 2823
2824 MEP Final Fixtures on Wall & Ceilings 2d 13 Apr 18 16 Apr 18 2824
2825 Final Coat Paint on walls & Ceilings 2d 17 Apr 18 18 Apr 18 2825
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2845 1st Fix Wall with Head tracks 1w 06 Feb 18 12 Feb 18 2845
2846 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 13 Feb 18 12 Mar 18 2846
2847 Fix Ceiling Grid 3d 13 Mar 18 15 Mar 18 2847
2848 Paint 1st Coat 2d 16 Mar 18 19 Mar 18 2848
2849 Fix doors incl. Ironmongery 2d 20 Mar 18 21 Mar 18 2849
2850 Mark and Cut openings for MEP on walls 2d 22 Mar 18 23 Mar 18 2850
2851 Install Ceiling Tiles 3d 26 Mar 18 28 Mar 18 2851
2852 Fix MEP Final Fixtures 3d 29 Mar 18 04 Apr 18 2852
2853 Final Coat Paint on walls and ceiling 3d 05 Apr 18 09 Apr 18 2853
2880 1st Fix Wall with Head tracks 1w 20 Feb 18 26 Feb 18 2880
2881 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 27 Feb 18 26 Mar 18 2881
2888 Final Coat Paint on walls and ceiling 3d 19 Apr 18 23 Apr 18 2888
2889 Staircase Level 03 - CORE 01 5w 2d 15 Mar 18 24 Apr 18 2889
2890 H/L Electrical Containment & Conduits - 1st Fix 2d 15 Mar 18 16 Mar 18 2890
2891 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 19 Mar 18 20 Mar 18 2891
2892 Ceiling Rose fixing 1d 21 Mar 18 21 Mar 18 2892
2893 First Coat Paint on Walls & Ceiliings 2d 05 Apr 18 06 Apr 18 2893
2894 MEP Final Fixtures on Wall & Ceilings 2d 19 Apr 18 20 Apr 18 2894
2895 Final Coat Paint on walls & Ceilings 2d 23 Apr 18 24 Apr 18 2895
2896 Level 04 - CORE 01 12w 27 Feb 18 25 May 18 2896
2897 Toilet 12w 27 Feb 18 25 May 18 2897
2898 1st Fix Wall with Head tracks 1w 27 Feb 18 05 Mar 18 2898
2899 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 06 Mar 18 04 Apr 18 2899
2900 Fix Pocket Doors 1w 06 Mar 18 12 Mar 18 2900
2901 Inspection and Ceiling Grid Clearance 05 Apr 18 05 Apr 18 2901
2902 2nd Fix wall 1w 05 Apr 18 11 Apr 18 2902
2903 IPS Frame (Box Out only) incl. Backing ply 3d 12 Apr 18 16 Apr 18 2903
2904 Screed 2d 17 Apr 18 18 Apr 18 2904
2905 Fix Ceiling Grid Works 3d 19 Apr 18 23 Apr 18 2905
2906 Floor Tiling Works 3d 24 Apr 18 26 Apr 18 2906
2907 Wall Tiling works incl. IPS Panels 3d 30 Apr 18 02 May 18 2907
2908 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 03 May 18 11 May 18 2908
2909 Mark and Cut openings for MEP on walls including Ceiling 2d 14 May 18 15 May 18 2909
2910 Install Vanity Tops 4d 14 May 18 17 May 18 2910
2911 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 May 18 21 May 18 2911
2912 Fix MEP Final Fixtures 3d 21 May 18 23 May 18 2912
2929 MEP Final Fixtures on Wall & Ceilings 2d 04 May 18 08 May 18 2929
2930 Final Coat Paint on walls & Ceilings 2d 09 May 18 10 May 18 2930
2931 Level 05 - CORE 01 12w 13 Mar 18 11 Jun 18 2931
2934 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 20 Mar 18 18 Apr 18 2934
2955 Mark and Cut openings for MEP on walls 2d 09 May 18 10 May 18 2955
2956 Install Ceiling Tiles 3d 11 May 18 15 May 18 2956
2977 Wall Tiling works incl. IPS Panels 3d 30 May 18 01 Jun 18 2977
2978 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jun 18 11 Jun 18 2978
2979 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jun 18 13 Jun 18 2979
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
2982 Fix MEP Final Fixtures 3d 19 Jun 18 21 Jun 18 2982
2983 Final Coat Paint on Ceiling 2d 22 Jun 18 25 Jun 18 2983
2984 Lobby 8w 3d 05 Apr 18 07 Jun 18 2984
2985 1st Fix Wall with Head tracks 1w 05 Apr 18 11 Apr 18 2985
2986 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Apr 18 11 May 18 2986
2987 Fix Ceiling Grid 3d 14 May 18 16 May 18 2987
2988 Paint 1st Coat 2d 17 May 18 18 May 18 2988
2989 Fix doors incl. Ironmongery 2d 21 May 18 22 May 18 2989
2990 Mark and Cut openings for MEP on walls 2d 23 May 18 24 May 18 2990
3013 Wall Tiling works incl. IPS Panels 3d 05 Apr 18 09 Apr 18 3013
3014 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 Apr 18 17 Apr 18 3014
3015 Mark and Cut openings for MEP on walls including Ceiling 2d 18 Apr 18 19 Apr 18 3015
3021 1st Fix Wall with Head tracks 1w 12 Feb 18 16 Feb 18 3021
3022 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Feb 18 16 Mar 18 3022
3040 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Feb 18 23 Mar 18 3040
3041 Fix Pocket Doors 1w 26 Feb 18 02 Mar 18 3041
3042 Inspection and Ceiling Grid Clearance 26 Mar 18 26 Mar 18 3042
3043 2nd Fix wall 1w 26 Mar 18 03 Apr 18 3043
3044 IPS Frame (Box Out only) incl. Backing ply 3d 04 Apr 18 06 Apr 18 3044
3045 Screed 2d 09 Apr 18 10 Apr 18 3045
3048 Wall Tiling works incl. IPS Panels 3d 19 Apr 18 23 Apr 18 3048
3049 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 Apr 18 02 May 18 3049
3050 Mark and Cut openings for MEP on walls including Ceiling 2d 03 May 18 04 May 18 3050
3051 Install Vanity Tops 4d 03 May 18 09 May 18 3051
3052 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 08 May 18 11 May 18 3052
3053 Fix MEP Final Fixtures 3d 11 May 18 15 May 18 3053
3054 Final Coat Paint on Ceiling 2d 16 May 18 17 May 18 3054
3055 Lobby 8w 3d 26 Feb 18 30 Apr 18 3055
3056 1st Fix Wall with Head tracks 1w 26 Feb 18 02 Mar 18 3056
3057 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 05 Mar 18 03 Apr 18 3057
3058 Fix Ceiling Grid 3d 04 Apr 18 06 Apr 18 3058
3059 Paint 1st Coat 2d 09 Apr 18 10 Apr 18 3059
3060 Fix doors incl. Ironmongery 2d 11 Apr 18 12 Apr 18 3060
3061 Mark and Cut openings for MEP on walls 2d 13 Apr 18 16 Apr 18 3061
3064 Final Coat Paint on walls and ceiling 3d 25 Apr 18 30 Apr 18 3064
3065 Staircase Level 02 - CORE 02 5w 2d 21 Mar 18 01 May 18 3065
3066 H/L Electrical Containment & Conduits - 1st Fix 2d 21 Mar 18 22 Mar 18 3066
3067 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 23 Mar 18 26 Mar 18 3067
3069 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 3069
3070 MEP Final Fixtures on Wall & Ceilings 2d 25 Apr 18 26 Apr 18 3070
3071 Final Coat Paint on walls & Ceilings 2d 30 Apr 18 01 May 18 3071
3072 Level 03 - CORE 02 12w 05 Mar 18 01 Jun 18 3072
3073 Toilet 12w 05 Mar 18 01 Jun 18 3073
3074 1st Fix Wall with Head tracks 1w 05 Mar 18 09 Mar 18 3074
3075 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Mar 18 10 Apr 18 3075
3076 Fix Pocket Doors 1w 12 Mar 18 16 Mar 18 3076
3077 Inspection and Ceiling Grid Clearance 11 Apr 18 11 Apr 18 3077
3078 2nd Fix wall 1w 11 Apr 18 17 Apr 18 3078
3079 IPS Frame (Box Out only) incl. Backing ply 3d 18 Apr 18 20 Apr 18 3079
3080 Screed 2d 23 Apr 18 24 Apr 18 3080
3081 Fix Ceiling Grid Works 3d 25 Apr 18 30 Apr 18 3081
3082 Floor Tiling Works 3d 01 May 18 03 May 18 3082
3083 Wall Tiling works incl. IPS Panels 3d 04 May 18 09 May 18 3083
3084 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 May 18 17 May 18 3084
3085 Mark and Cut openings for MEP on walls including Ceiling 2d 18 May 18 21 May 18 3085
3087 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 22 May 18 25 May 18 3087
3088 Fix MEP Final Fixtures 3d 25 May 18 30 May 18 3088
3091 1st Fix Wall with Head tracks 1w 12 Mar 18 16 Mar 18 3091
3092 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Mar 18 17 Apr 18 3092
3096 Mark and Cut openings for MEP on walls 2d 30 Apr 18 01 May 18 3096
3114 IPS Frame (Box Out only) incl. Backing ply 3d 03 May 18 08 May 18 3114
3115 Screed 2d 09 May 18 10 May 18 3115
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3116 Fix Ceiling Grid Works 3d 11 May 18 15 May 18 3116
3117 Floor Tiling Works 3d 16 May 18 18 May 18 3117
3118 Wall Tiling works incl. IPS Panels 3d 21 May 18 23 May 18 3118
3119 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 May 18 01 Jun 18 3119
3120 Mark and Cut openings for MEP on walls including Ceiling 2d 04 Jun 18 05 Jun 18 3120
3121 Install Vanity Tops 4d 04 Jun 18 07 Jun 18 3121
3122 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Jun 18 11 Jun 18 3122
3123 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 3123
3124 Final Coat Paint on Ceiling 2d 14 Jun 18 15 Jun 18 3124
3126 1st Fix Wall with Head tracks 1w 26 Mar 18 03 Apr 18 3126
3127 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 04 Apr 18 02 May 18 3127
3131 Mark and Cut openings for MEP on walls 2d 15 May 18 16 May 18 3131
3153 Wall Tiling works incl. IPS Panels 3d 05 Jun 18 07 Jun 18 3153
3154 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 08 Jun 18 15 Jun 18 3154
3155 Mark and Cut openings for MEP on walls including Ceiling 2d 18 Jun 18 19 Jun 18 3155
3156 Install Vanity Tops 4d 18 Jun 18 21 Jun 18 3156
3157 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Jun 18 25 Jun 18 3157
3174 First Coat Paint on Walls & Ceiliings 2d 25 May 18 29 May 18 3174
3175 MEP Final Fixtures on Wall & Ceilings 2d 11 Jun 18 12 Jun 18 3175
3176 Final Coat Paint on walls & Ceilings 2d 13 Jun 18 14 Jun 18 3176
3184 IPS Frame (Box Out only) incl. Backing ply 3d 04 Jun 18 06 Jun 18 3184
3185 Screed 2d 07 Jun 18 08 Jun 18 3185
3186 Fix Ceiling Grid Works 3d 11 Jun 18 13 Jun 18 3186
3187 Floor Tiling Works 3d 14 Jun 18 18 Jun 18 3187
3188 Wall Tiling works incl. IPS Panels 3d 19 Jun 18 21 Jun 18 3188
3189 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 22 Jun 18 29 Jun 18 3189
3190 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Jul 18 03 Jul 18 3190
3191 Install Vanity Tops 4d 02 Jul 18 05 Jul 18 3191
3192 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 04 Jul 18 09 Jul 18 3192
3193 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 3193
3194 Final Coat Paint on Ceiling 2d 12 Jul 18 13 Jul 18 3194
3195 Lobby 8w 3d 25 Apr 18 27 Jun 18 3195
3196 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 3196
3197 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 03 May 18 01 Jun 18 3197
3206 H/L Electrical Containment & Conduits - 1st Fix 2d 22 May 18 23 May 18 3206
3207 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 May 18 25 May 18 3207
3224 Wall Tiling works incl. IPS Panels 3d 19 Apr 18 23 Apr 18 3224
3225 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 Apr 18 02 May 18 3225
3226 Mark and Cut openings for MEP on walls including Ceiling 2d 03 May 18 04 May 18 3226
3227 Install Vanity Tops 4d 03 May 18 09 May 18 3227
3228 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 08 May 18 11 May 18 3228
3245 First Coat Paint on Walls & Ceiliings 2d 11 Apr 18 12 Apr 18 3245
3246 MEP Final Fixtures on Wall & Ceilings 2d 25 Apr 18 26 Apr 18 3246
3247 Final Coat Paint on walls & Ceilings 2d 30 Apr 18 01 May 18 3247
3248 Level 02 - CORE 03 12w 05 Mar 18 01 Jun 18 3248
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3251 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 12 Mar 18 10 Apr 18 3251
3252 Fix Pocket Doors 1w 12 Mar 18 16 Mar 18 3252
3253 Inspection and Ceiling Grid Clearance 11 Apr 18 11 Apr 18 3253
3254 2nd Fix wall 1w 11 Apr 18 17 Apr 18 3254
3255 IPS Frame (Box Out only) incl. Backing ply 3d 18 Apr 18 20 Apr 18 3255
3256 Screed 2d 23 Apr 18 24 Apr 18 3256
3257 Fix Ceiling Grid Works 3d 25 Apr 18 30 Apr 18 3257
3258 Floor Tiling Works 3d 01 May 18 03 May 18 3258
3259 Wall Tiling works incl. IPS Panels 3d 04 May 18 09 May 18 3259
3260 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 10 May 18 17 May 18 3260
3261 Mark and Cut openings for MEP on walls including Ceiling 2d 18 May 18 21 May 18 3261
3262 Install Vanity Tops 4d 18 May 18 23 May 18 3262
3263 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 22 May 18 25 May 18 3263
3267 1st Fix Wall with Head tracks 1w 12 Mar 18 16 Mar 18 3267
3268 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 19 Mar 18 17 Apr 18 3268
3269 Fix Ceiling Grid 3d 18 Apr 18 20 Apr 18 3269
3270 Paint 1st Coat 2d 23 Apr 18 24 Apr 18 3270
3271 Fix doors incl. Ironmongery 2d 25 Apr 18 26 Apr 18 3271
3272 Mark and Cut openings for MEP on walls 2d 30 Apr 18 01 May 18 3272
3273 Install Ceiling Tiles 3d 02 May 18 04 May 18 3273
3274 Fix MEP Final Fixtures 3d 08 May 18 10 May 18 3274
3275 Final Coat Paint on walls and ceiling 3d 11 May 18 15 May 18 3275
3276 Staircase 5w 2d 06 Apr 18 16 May 18 3276
3277 H/L Electrical Containment & Conduits - 1st Fix 2d 06 Apr 18 09 Apr 18 3277
3278 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 10 Apr 18 11 Apr 18 3278
3279 Ceiling Rose fixing 1d 12 Apr 18 12 Apr 18 3279
3280 First Coat Paint on Walls & Ceiliings 2d 25 Apr 18 26 Apr 18 3280
3281 MEP Final Fixtures on Wall & Ceilings 2d 11 May 18 14 May 18 3281
3282 Final Coat Paint on walls & Ceilings 2d 15 May 18 16 May 18 3282
3283 Level 03 - CORE 03 12w 19 Mar 18 15 Jun 18 3283
3284 Toilet 12w 19 Mar 18 15 Jun 18 3284
3285 1st Fix Wall with Head tracks 1w 19 Mar 18 23 Mar 18 3285
3286 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 26 Mar 18 24 Apr 18 3286
3290 IPS Frame (Box Out only) incl. Backing ply 3d 03 May 18 08 May 18 3290
3291 Screed 2d 09 May 18 10 May 18 3291
3294 Wall Tiling works incl. IPS Panels 3d 21 May 18 23 May 18 3294
3295 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 24 May 18 01 Jun 18 3295
3296 Mark and Cut openings for MEP on walls including Ceiling 2d 04 Jun 18 05 Jun 18 3296
3297 Install Vanity Tops 4d 04 Jun 18 07 Jun 18 3297
3298 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Jun 18 11 Jun 18 3298
3299 Fix MEP Final Fixtures 3d 11 Jun 18 13 Jun 18 3299
3300 Final Coat Paint on Ceiling 2d 14 Jun 18 15 Jun 18 3300
3301 Lobby 8w 3d 26 Mar 18 30 May 18 3301
3302 1st Fix Wall with Head tracks 1w 26 Mar 18 03 Apr 18 3302
3303 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 04 Apr 18 02 May 18 3303
3304 Fix Ceiling Grid 3d 03 May 18 08 May 18 3304
3305 Paint 1st Coat 2d 09 May 18 10 May 18 3305
3306 Fix doors incl. Ironmongery 2d 11 May 18 14 May 18 3306
3307 Mark and Cut openings for MEP on walls 2d 15 May 18 16 May 18 3307
3308 Install Ceiling Tiles 3d 17 May 18 21 May 18 3308
3310 Final Coat Paint on walls and ceiling 3d 25 May 18 30 May 18 3310
3312 H/L Electrical Containment & Conduits - 1st Fix 2d 20 Apr 18 23 Apr 18 3312
3313 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 Apr 18 25 Apr 18 3313
3315 First Coat Paint on Walls & Ceiliings 2d 11 May 18 14 May 18 3315
3316 MEP Final Fixtures on Wall & Ceilings 2d 25 May 18 29 May 18 3316
3317 Final Coat Paint on walls & Ceilings 2d 30 May 18 31 May 18 3317
3318 Level 04 - CORE 03 12w 04 Apr 18 29 Jun 18 3318
3333 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Jun 18 25 Jun 18 3333
3334 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 3334
3342 Mark and Cut openings for MEP on walls 2d 30 May 18 31 May 18 3342
3365 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 22 Jun 18 29 Jun 18 3365
3366 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Jul 18 03 Jul 18 3366
3367 Install Vanity Tops 4d 02 Jul 18 05 Jul 18 3367
3368 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 04 Jul 18 09 Jul 18 3368
3369 Fix MEP Final Fixtures 3d 09 Jul 18 11 Jul 18 3369
3370 Final Coat Paint on Ceiling 2d 12 Jul 18 13 Jul 18 3370
3371 Lobby 8w 3d 25 Apr 18 27 Jun 18 3371
3372 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 3372
3373 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 03 May 18 01 Jun 18 3373
3374 Fix Ceiling Grid 3d 04 Jun 18 06 Jun 18 3374
3375 Paint 1st Coat 2d 07 Jun 18 08 Jun 18 3375
3376 Fix doors incl. Ironmongery 2d 11 Jun 18 12 Jun 18 3376
3377 Mark and Cut openings for MEP on walls 2d 13 Jun 18 14 Jun 18 3377
3378 Install Ceiling Tiles 3d 15 Jun 18 19 Jun 18 3378
3379 Fix MEP Final Fixtures 3d 20 Jun 18 22 Jun 18 3379
3380 Final Coat Paint on walls and ceiling 3d 25 Jun 18 27 Jun 18 3380
3382 H/L Electrical Containment & Conduits - 1st Fix 2d 22 May 18 23 May 18 3382
3383 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 24 May 18 25 May 18 3383
3386 MEP Final Fixtures on Wall & Ceilings 2d 25 Jun 18 26 Jun 18 3386
3387 Final Coat Paint on walls & Ceilings 2d 27 Jun 18 28 Jun 18 3387
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3388 Level GF - CORE 03 12w 03 May 18 27 Jul 18 3388
3389 Toilet 12w 03 May 18 27 Jul 18 3389
3390 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 3390
3391 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 11 May 18 08 Jun 18 3391
3392 Fix Pocket Doors 1w 11 May 18 17 May 18 3392
3393 Inspection and Ceiling Grid Clearance 11 Jun 18 11 Jun 18 3393
3394 2nd Fix wall 1w 11 Jun 18 15 Jun 18 3394
3395 IPS Frame (Box Out only) incl. Backing ply 3d 18 Jun 18 20 Jun 18 3395
3396 Screed 2d 21 Jun 18 22 Jun 18 3396
3400 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 06 Jul 18 13 Jul 18 3400
3401 Mark and Cut openings for MEP on walls including Ceiling 2d 16 Jul 18 17 Jul 18 3401
3402 Install Vanity Tops 4d 16 Jul 18 19 Jul 18 3402
3403 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 18 Jul 18 23 Jul 18 3403
3426 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 8B 14 Nov 17 14 Nov 17 3426
3429 Fit out Ground Floor Unit 1 and 2 5w 2d 22 Jan 18 27 Feb 18 3429
3430
3430 Install conduit to cleaners sockets to core walls 3d 22 Jan 18 24 Jan 18
3431 Boarding and Insulation to external and core walls 1w 25 Jan 18 31 Jan 18 3431
3434
3434 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 14 Feb 18 20 Feb 18
3435 Install Joinery incl Doors 1w 21 Feb 18 27 Feb 18 3435
3436
3436 Decoration 1w 16 Feb 18 22 Feb 18
3437 Fit out Ground Floor Units 3 & 4 4w 3d 05 Feb 18 07 Mar 18 3437
3438
3438 Install conduit to cleaners sockets to core walls 3d 05 Feb 18 07 Feb 18
3439 Boarding and Insulation to external and core walls 1w 08 Feb 18 14 Feb 18 3439
3442
3442 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Feb 18 28 Feb 18
3443 Install Joinery incl Doors 1w 01 Mar 18 07 Mar 18 3443
3444
3444 Decoration 1w 26 Feb 18 02 Mar 18
3445 Fit Out Ground Floor Unit 5 and 6 4w 3d 15 Feb 18 19 Mar 18 3445
3446 Install conduit to cleaners sockets to core walls 3d 15 Feb 18 19 Feb 18 3446
3447 Boarding and Insulation to external and core walls 1w 20 Feb 18 26 Feb 18 3447
3449
3449 Taping and Joining to Walls 2d 27 Feb 18 28 Feb 18
3450 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 06 Mar 18 12 Mar 18 3450
3451
3451 Decoration 1w 07 Mar 18 13 Mar 18
3452 Install Joinery incl Doors 1w 13 Mar 18 19 Mar 18 3452
3455
3455 Install conduit to cleaners sockets to core walls 3d 30 Jan 18 01 Feb 18
3456 Boarding and Insulation to external and core walls 1w 02 Feb 18 08 Feb 18 3456
3459
3459 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 16 Feb 18 22 Feb 18
3460 Install Joinery incl Doors 1w 28 Feb 18 06 Mar 18 3460
3461
3461 Decoration 1w 20 Feb 18 26 Feb 18
3462 Units 3 and 4 5w 09 Feb 18 15 Mar 18 3462
3463
3463 Install conduit to cleaners sockets to core walls 3d 09 Feb 18 13 Feb 18
3464 Boarding and Insulation to external and core walls 1w 2d 14 Feb 18 22 Feb 18 3464
3467
3467 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 02 Mar 18 08 Mar 18
3468 Install Joinery incl Doors 1w 09 Mar 18 15 Mar 18 3468
3469
3469 Decoration 1w 06 Mar 18 12 Mar 18
3470 Units 5 and 6 4w 3d 23 Feb 18 27 Mar 18 3470
3471 Install conduit to cleaners sockets to core walls 3d 23 Feb 18 27 Feb 18 3471
3472 Boarding and Insulation to external and core walls 1w 28 Feb 18 06 Mar 18 3472
3475 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 14 Mar 18 20 Mar 18 3475
3481 Install conduit to cleaners sockets to core walls 3d 07 Feb 18 09 Feb 18 3481
3482 Boarding and Insulation to external and core walls 1w 12 Feb 18 16 Feb 18 3482
3485 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Feb 18 02 Mar 18 3485
3489 Install conduit to cleaners sockets to core walls 3d 19 Feb 18 21 Feb 18 3489
3490 Boarding and Insulation to external and core walls 1w 22 Feb 18 28 Feb 18 3490
3493 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Mar 18 14 Mar 18 3493
3497 Install conduit to cleaners sockets to core walls 3d 01 Mar 18 05 Mar 18 3497
3498 Boarding and Insulation to external and core walls 1w 06 Mar 18 12 Mar 18 3498
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3499 Install wiring to containment in ceilings 1w 13 Mar 18 19 Mar 18 3499
3501 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 20 Mar 18 26 Mar 18 3501
3507 Install conduit to cleaners sockets to core walls 3d 14 Feb 18 16 Feb 18 3507
3508 Boarding and Insulation to external and core walls 1w 19 Feb 18 23 Feb 18 3508
3511 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Mar 18 09 Mar 18 3511
3515 Install conduit to cleaners sockets to core walls 3d 26 Feb 18 28 Feb 18 3515
3516 Boarding and Insulation to external and core walls 1w 01 Mar 18 07 Mar 18 3516
3519 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 15 Mar 18 21 Mar 18 3519
3523 Install conduit to cleaners sockets to core walls 3d 08 Mar 18 12 Mar 18 3523
3524 Boarding and Insulation to external and core walls 1w 13 Mar 18 19 Mar 18 3524
3527 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 27 Mar 18 04 Apr 18 3527
3533 Install conduit to cleaners sockets to core walls 3d 21 Feb 18 23 Feb 18 3533
3534 Boarding and Insulation to external and core walls 1w 26 Feb 18 02 Mar 18 3534
3537 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Mar 18 16 Mar 18 3537
3541 Install conduit to cleaners sockets to core walls 3d 05 Mar 18 07 Mar 18 3541
3542 Boarding and Insulation to external and core walls 1w 08 Mar 18 14 Mar 18 3542
3545 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 22 Mar 18 28 Mar 18 3545
3549 Install conduit to cleaners sockets to core walls 3d 15 Mar 18 19 Mar 18 3549
3550 Boarding and Insulation to external and core walls 1w 20 Mar 18 26 Mar 18 3550
3553 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Apr 18 11 Apr 18 3553
3559 Install conduit to cleaners sockets to core walls 3d 28 Feb 18 02 Mar 18 3559
3560 Boarding and Insulation to external and core walls 1w 05 Mar 18 09 Mar 18 3560
3563 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 19 Mar 18 23 Mar 18 3563
3567 Install conduit to cleaners sockets to core walls 3d 12 Mar 18 14 Mar 18 3567
3568 Boarding and Insulation to external and core walls 1w 15 Mar 18 21 Mar 18 3568
3571 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 29 Mar 18 06 Apr 18 3571
3575 Install conduit to cleaners sockets to core walls 3d 22 Mar 18 26 Mar 18 3575
3576 Boarding and Insulation to external and core walls 1w 27 Mar 18 04 Apr 18 3576
3579 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 12 Apr 18 18 Apr 18 3579
3583 Temporary Hoist Access Closure - CAT A Fitout 2w 2d 04 Jun 18 19 Jun 18 3583
3597
3597 Complete Ceiling Tiles 1w 11 Oct 18 17 Oct 18
3598 Install Raised Access Floor incl Below Floor Barriers 1w 18 Oct 18 24 Oct 18 3598
3599
3599 Soft Floor Coverings 4d 25 Oct 18 30 Oct 18
3600 First floor 2w 4d 16 Oct 18 02 Nov 18 3600
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3601 Complete Ceiling Tiles 1w 16 Oct 18 22 Oct 18 3601
3602
3602 Install Raised Access Floor incl Below Floor Barriers 1w 23 Oct 18 29 Oct 18
3603 Soft Floor Coverings 4d 30 Oct 18 02 Nov 18 3603
3606 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 01 Nov 18 3606
3610 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 06 Nov 18 3610
3614 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 3614
3618 Install Raised Access Floor incl Below Floor Barriers 1w 08 Nov 18 14 Nov 18 3618
3622
3622 Complete Ceiling Tiles 1w 18 Oct 18 24 Oct 18
3623 Install Raised Access Floor incl Below Floor Barriers 1w 25 Oct 18 31 Oct 18 3623
3627
3627 Install Raised Access Floor incl Below Floor Barriers 1w 30 Oct 18 05 Nov 18
3628 Soft Floor Coverings 4d 06 Nov 18 09 Nov 18 3628
3631 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 3631
3635 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 3635
3639 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 3639
3643 Install Raised Access Floor incl Below Floor Barriers 1w 15 Nov 18 21 Nov 18 3643
3647
3647 Complete Ceiling Tiles 1w 25 Oct 18 31 Oct 18
3648 Install Raised Access Floor incl Below Floor Barriers 1w 01 Nov 18 07 Nov 18 3648
3649
3649 Soft Floor Coverings 4d 07 Nov 18 12 Nov 18
3650 First Floor 2w 4d 30 Oct 18 16 Nov 18 3650
3652 Install Raised Access Floor incl Below Floor Barriers 1w 06 Nov 18 12 Nov 18 3652
3656 Install Raised Access Floor incl Below Floor Barriers 1w 09 Nov 18 15 Nov 18 3656
3660 Install Raised Access Floor incl Below Floor Barriers 1w 14 Nov 18 20 Nov 18 3660
3664 Install Raised Access Floor incl Below Floor Barriers 1w 19 Nov 18 23 Nov 18 3664
3668 Install Raised Access Floor incl Below Floor Barriers 1w 22 Nov 18 28 Nov 18 3668
3671 Dock Wall Refurbishment (Undefined Provisional Sum) 55w 4d 19 Oct 17 30 Nov 18 3671
3672 Structural Repairs to Dock Wall (Undefined provisional Sum - indicative programme) 20w 08 Mar 18 01 Aug 18 3672
3686 External Works and Paving South of 8B 18w 4d 04 Jun 18 12 Oct 18 3686
3688 Install Coping stones to Dock Wall (78m) 3w 04 Jun 18 22 Jun 18 3688
3689 Install Hand Rail 1w 20 Jun 18 26 Jun 18 3689
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3713 Paving to Dockside (270m2) 4w 19 Oct 18 15 Nov 18 3713
3714 Tarmac Finishes to Muse Area 2w 12 Nov 18 23 Nov 18 3714
3715 Snag and Handover 1w 26 Nov 18 30 Nov 18 3715
3716 Progressively take down hoardings to Dock Edge and replace with heras fencing. 4w 19 Jun 17 14 Jul 17 3716
3717 Surface water drainage to 3B through the dock wall 2w 17 Jul 17 28 Jul 17 3717
3719 External Roads & Landscaping to Buildings 8A & 8B 25w 1d 26 Jun 18 19 Dec 18 3719
3742 Lay Granite Banding (60 linear meters) 3d 09 Jul 18 11 Jul 18 3742
3773 Construct slab for Estate Management Office 8w 14 Feb 18 12 Apr 18 3773
3774 Install Estates Management Office Modular Units 2w 13 Apr 18 26 Apr 18 3774
3775 Fit out Estates Management Office 16w 30 Apr 18 21 Aug 18 3775
3776 Construct Slab for Cycle Store and Refuse Store 8w 21 Feb 18 19 Apr 18 3776
3778 Fit out Cycle Store and Showers 15w 08 May 18 21 Aug 18 3778
3782 Drainage and Buried Services to roads and hardstandings for TEC area 10w 09 Oct 17 22 Dec 17 3782
3797 Complete Buildings 9A, 8A, 8B & Temporary Energy Centre 13 Feb 19 13 Feb 19 3797
3799
3799 Building 5A 77w 2d 26 Jun 17 21 Jan 19
3800 Piling 7w 26 Jun 17 11 Aug 17 3800
3828 STAND PRECAST CORE WALLS GND - 1ST FLOOR 1w 1d 26 Oct 17 14 Nov 17 3828
3829 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 2w 2d 25 Oct 17 16 Nov 17 3829
3831 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 1w 1d 09 Nov 17 24 Nov 17 3831
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3832 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 2w 4d 10 Nov 17 29 Nov 17 3832
3834 STAND PRECAST WALLS 2ND - 3RD FLOOR 1w 1d 22 Nov 17 08 Dec 17 3834
3835 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 2w 2d 23 Nov 17 08 Dec 17 3835
3837 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 1w 1d 05 Dec 17 21 Dec 17 3837
3838 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 2w 2d 06 Dec 17 21 Dec 17 3838
3840 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 1w 1d 19 Dec 17 15 Jan 18 3840
3841 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 2d 20 Dec 17 15 Jan 18 3841
3843 STAND PRECAST WALLS 5TH - 6TH FLOOR 1w 1d 09 Jan 18 25 Jan 18 3843
3844 STAND PRECAST COLUMNS 5TH - 6TH FLOOR 2w 2d 11 Jan 18 26 Jan 18 3844
3846 STAND PRECAST CORE WALLS 6TH - ROOF 1w 1d 24 Jan 18 08 Feb 18 3846
3866 Install SFS, Windows and cladding to Level 6 South elevation 8w 23 Mar 18 23 May 18 3866
3867 Install SFS, Windows and cladding to Level 6 North elevation 7w 06 Apr 18 29 May 18 3867
3868 Install ribbon window curtain walling to North Elevation 5w 3d 06 Apr 18 17 May 18 3868
3873 Complete ribbon windows after hoists removed 4w 23 Aug 18 20 Sep 18 3873
3874 Canopies 38w 3d 06 Apr 18 21 Jan 19 3874
3875 Install Frame for the Canopies 1w 06 Apr 18 12 Apr 18 3875
3876 Complete glazing for Canopies 1w 15 Jan 19 21 Jan 19 3876
3885 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 5A 30 Oct 17 30 Oct 17 3885
3910 Window for Cantidecks to load out upper floors 1w 21 Feb 18 27 Feb 18 3910
3914 Lift /Toilet Core Fit Out 57w 3d 30 Oct 17 07 Jan 19 3914
3925 Hand back Lift 2 after builders beneficial use 27 Nov 18 27 Nov 18 3925
3935 Hand back Lift 4 after builders beneficial use 04 Dec 18 04 Dec 18 3935
3936 Recommission Lift 4 2w 04 Dec 18 17 Dec 18 3936
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
3939 Lift 5 Car 1w 26 Jul 18 01 Aug 18 3939
3945 Hand back Lift 6 after builders beneficial use 11 Dec 18 11 Dec 18 3945
3946 Recommission Lift 6 2w 11 Dec 18 07 Jan 19 3946
3947 Toilet & Lobby 22w 29 Mar 18 06 Sep 18 3947
3951 1st Fix Wall with Head tracks 1w 29 Mar 18 06 Apr 18 3951
3952 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 Apr 18 08 May 18 3952
3999 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 25 Jun 18 28 Jun 18 3999
4000 Fix MEP Final Fixtures 3d 28 Jun 18 02 Jul 18 4000
4001 Final Coat Paint on Ceiling 2d 03 Jul 18 04 Jul 18 4001
4002 Lobby 9w 1d 11 Apr 18 18 Jun 18 4002
4003 1st Fix Wall with Head tracks 1w 11 Apr 18 17 Apr 18 4003
4004 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 Apr 18 22 May 18 4004
4030 Wall Tiling works incl. IPS Panels 3d 15 Jun 18 19 Jun 18 4030
4031 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 20 Jun 18 27 Jun 18 4031
4032 Mark and Cut openings for MEP on walls including Ceiling 2d 28 Jun 18 29 Jun 18 4032
4034 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 02 Jul 18 05 Jul 18 4034
4048 H/L Electrical Containment & Conduits - 1st Fix 2d 18 May 18 21 May 18 4048
4049 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 22 May 18 23 May 18 4049
4052 MEP Final Fixtures on Wall & Ceilings 2d 21 Jun 18 22 Jun 18 4052
4053 Final Coat Paint on walls & Ceilings 2d 25 Jun 18 26 Jun 18 4053
4054 Level 04 - CORE 01 12w 23 Apr 18 18 Jul 18 4054
4057 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4057
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4073 1st Fix Wall with Head tracks 1w 25 Apr 18 02 May 18 4073
4074 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4074
4075 Fix Ceiling Grid 3d 07 Jun 18 11 Jun 18 4075
4076 Paint 1st Coat 2d 12 Jun 18 13 Jun 18 4076
4077 Fix doors incl. Ironmongery 2d 14 Jun 18 15 Jun 18 4077
4078 Mark and Cut openings for MEP on walls 2d 18 Jun 18 19 Jun 18 4078
4079 Install Ceiling Tiles 3d 20 Jun 18 22 Jun 18 4079
4080 Fix MEP Final Fixtures 3d 25 Jun 18 27 Jun 18 4080
4081 Final Coat Paint on walls and ceiling 3d 28 Jun 18 02 Jul 18 4081
4083 H/L Electrical Containment & Conduits - 1st Fix 2d 25 May 18 29 May 18 4083
4084 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 30 May 18 31 May 18 4084
4086 First Coat Paint on Walls & Ceiliings 2d 14 Jun 18 15 Jun 18 4086
4087 MEP Final Fixtures on Wall & Ceilings 2d 28 Jun 18 29 Jun 18 4087
4088 Final Coat Paint on walls & Ceilings 2d 02 Jul 18 03 Jul 18 4088
4089 Level 05 - CORE 01 12w 01 May 18 25 Jul 18 4089
4108 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4108
4109 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4109
4116 Final Coat Paint on walls and ceiling 3d 05 Jul 18 09 Jul 18 4116
4118 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Jun 18 05 Jun 18 4118
4119 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Jun 18 07 Jun 18 4119
4120 Ceiling Rose fixing 1d 08 Jun 18 08 Jun 18 4120
4121 First Coat Paint on Walls & Ceiliings 2d 21 Jun 18 22 Jun 18 4121
4122 MEP Final Fixtures on Wall & Ceilings 2d 05 Jul 18 06 Jul 18 4122
4123 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4123
4124 Level 06 - CORE 01 12w 09 May 18 01 Aug 18 4124
4125 Toilet 12w 09 May 18 01 Aug 18 4125
4126 1st Fix Wall with Head tracks 1w 09 May 18 15 May 18 4126
4127 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4127
4128 Fix Pocket Doors 1w 16 May 18 22 May 18 4128
4129 Inspection and Ceiling Grid Clearance 14 Jun 18 14 Jun 18 4129
4130 2nd Fix wall 1w 14 Jun 18 20 Jun 18 4130
4131 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 4131
4132 Screed 2d 26 Jun 18 27 Jun 18 4132
4133 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 4133
4134 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 4134
4135 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 4135
4136 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 4136
4137 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 4137
4138 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 4138
4139 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 4139
4140 Fix MEP Final Fixtures 3d 26 Jul 18 30 Jul 18 4140
4157 MEP Final Fixtures on Wall & Ceilings 2d 12 Jul 18 13 Jul 18 4157
4158 Final Coat Paint on walls & Ceilings 2d 16 Jul 18 17 Jul 18 4158
4159 Level GF - CORE 01 12w 16 May 18 08 Aug 18 4159
4162 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4162
4183 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4183
4184 Install Ceiling Tiles 3d 11 Jul 18 13 Jul 18 4184
4188 H/L Electrical Containment & Conduits - 1st Fix 2d 18 Jun 18 19 Jun 18 4188
4189 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 20 Jun 18 21 Jun 18 4189
4191 First Coat Paint on Walls & Ceiliings 2d 05 Jul 18 06 Jul 18 4191
4192 MEP Final Fixtures on Wall & Ceilings 2d 19 Jul 18 20 Jul 18 4192
4193 Final Coat Paint on walls & Ceilings 2d 23 Jul 18 24 Jul 18 4193
4207 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 20 Jun 18 27 Jun 18 4207
4208 Mark and Cut openings for MEP on walls including Ceiling 2d 28 Jun 18 29 Jun 18 4208
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4209 Install Vanity Tops 4d 28 Jun 18 03 Jul 18 4209
4210 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 02 Jul 18 05 Jul 18 4210
4211 Fix MEP Final Fixtures 3d 05 Jul 18 09 Jul 18 4211
4212 Final Coat Paint on Ceiling 2d 10 Jul 18 11 Jul 18 4212
4213 Lobby 9w 1d 18 Apr 18 25 Jun 18 4213
4214 1st Fix Wall with Head tracks 1w 18 Apr 18 24 Apr 18 4214
4215 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 May 18 30 May 18 4215
4216 Fix Ceiling Grid 3d 31 May 18 04 Jun 18 4216
4217 Paint 1st Coat 2d 05 Jun 18 06 Jun 18 4217
4219 Mark and Cut openings for MEP on walls 2d 11 Jun 18 12 Jun 18 4219
4220 Install Ceiling Tiles 3d 13 Jun 18 15 Jun 18 4220
4222 Final Coat Paint on walls and ceiling 3d 21 Jun 18 25 Jun 18 4222
4224 H/L Electrical Containment & Conduits - 1st Fix 2d 18 May 18 21 May 18 4224
4225 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 22 May 18 23 May 18 4225
4243 Mark and Cut openings for MEP on walls including Ceiling 2d 05 Jul 18 06 Jul 18 4243
4245 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 09 Jul 18 12 Jul 18 4245
4246 Fix MEP Final Fixtures 3d 12 Jul 18 16 Jul 18 4246
4247 Final Coat Paint on Ceiling 2d 17 Jul 18 18 Jul 18 4247
4267 1st Fix Wall with Head tracks 1w 01 May 18 08 May 18 4267
4268 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 09 May 18 06 Jun 18 4268
4269 Fix Pocket Doors 1w 09 May 18 15 May 18 4269
4276 Wall Tiling works incl. IPS Panels 3d 29 Jun 18 03 Jul 18 4276
4277 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jul 18 11 Jul 18 4277
4278 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jul 18 13 Jul 18 4278
4279 Install Vanity Tops 4d 12 Jul 18 17 Jul 18 4279
4280 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 16 Jul 18 19 Jul 18 4280
4281 Fix MEP Final Fixtures 3d 19 Jul 18 23 Jul 18 4281
4282 Final Coat Paint on Ceiling 2d 24 Jul 18 25 Jul 18 4282
4283 Lobby 9w 1d 03 May 18 09 Jul 18 4283
4284 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4284
4285 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4285
4286 Fix Ceiling Grid 3d 14 Jun 18 18 Jun 18 4286
4287 Paint 1st Coat 2d 19 Jun 18 20 Jun 18 4287
4288 Fix doors incl. Ironmongery 2d 21 Jun 18 22 Jun 18 4288
4289 Mark and Cut openings for MEP on walls 2d 25 Jun 18 26 Jun 18 4289
4290 Install Ceiling Tiles 3d 27 Jun 18 29 Jun 18 4290
4292 Final Coat Paint on walls and ceiling 3d 05 Jul 18 09 Jul 18 4292
4294 H/L Electrical Containment & Conduits - 1st Fix 2d 04 Jun 18 05 Jun 18 4294
4295 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 06 Jun 18 07 Jun 18 4295
4298 MEP Final Fixtures on Wall & Ceilings 2d 05 Jul 18 06 Jul 18 4298
4299 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4299
4324 Mark and Cut openings for MEP on walls 2d 02 Jul 18 03 Jul 18 4324
4325 Install Ceiling Tiles 3d 04 Jul 18 06 Jul 18 4325
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4346 Wall Tiling works incl. IPS Panels 3d 13 Jul 18 17 Jul 18 4346
4347 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 18 Jul 18 25 Jul 18 4347
4348 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Jul 18 27 Jul 18 4348
4349 Install Vanity Tops 4d 26 Jul 18 31 Jul 18 4349
4350 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 30 Jul 18 02 Aug 18 4350
4351 Fix MEP Final Fixtures 3d 02 Aug 18 06 Aug 18 4351
4352 Final Coat Paint on Ceiling 2d 07 Aug 18 08 Aug 18 4352
4353 Lobby 9w 1d 18 May 18 23 Jul 18 4353
4354 1st Fix Wall with Head tracks 1w 18 May 18 24 May 18 4354
4355 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4355
4359 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4359
4362 Final Coat Paint on walls and ceiling 3d 19 Jul 18 23 Jul 18 4362
4381 Wall Tiling works incl. IPS Panels 3d 20 Jul 18 24 Jul 18 4381
4382 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 25 Jul 18 01 Aug 18 4382
4383 Mark and Cut openings for MEP on walls including Ceiling 2d 02 Aug 18 03 Aug 18 4383
4384 Install Vanity Tops 4d 02 Aug 18 07 Aug 18 4384
4385 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 06 Aug 18 09 Aug 18 4385
4386 Fix MEP Final Fixtures 3d 09 Aug 18 13 Aug 18 4386
4389 1st Fix Wall with Head tracks 1w 25 May 18 01 Jun 18 4389
4390 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4390
4391 Fix Ceiling Grid 3d 05 Jul 18 09 Jul 18 4391
4392 Paint 1st Coat 2d 10 Jul 18 11 Jul 18 4392
4393 Fix doors incl. Ironmongery 2d 12 Jul 18 13 Jul 18 4393
4394 Mark and Cut openings for MEP on walls 2d 16 Jul 18 17 Jul 18 4394
4395 Install Ceiling Tiles 3d 18 Jul 18 20 Jul 18 4395
4396 Fix MEP Final Fixtures 3d 23 Jul 18 25 Jul 18 4396
4397 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 4397
4398 Staircase 5w 2d 25 Jun 18 31 Jul 18 4398
4399 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 4399
4400 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 4400
4401 Ceiling Rose fixing 1d 29 Jun 18 29 Jun 18 4401
4402 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 4402
4403 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 4403
4404 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 4404
4435 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 04 Jul 18 05 Jul 18 4435
4437 First Coat Paint on Walls & Ceiliings 2d 19 Jul 18 20 Jul 18 4437
4438 MEP Final Fixtures on Wall & Ceilings 2d 02 Aug 18 03 Aug 18 4438
4439 Final Coat Paint on walls & Ceilings 2d 06 Aug 18 07 Aug 18 4439
4452 Wall Tiling works incl. IPS Panels 3d 29 Jun 18 03 Jul 18 4452
4453 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 04 Jul 18 11 Jul 18 4453
4454 Mark and Cut openings for MEP on walls including Ceiling 2d 12 Jul 18 13 Jul 18 4454
4460 1st Fix Wall with Head tracks 1w 03 May 18 10 May 18 4460
4461 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 16 May 18 13 Jun 18 4461
4475 Final Coat Paint on walls & Ceilings 2d 09 Jul 18 10 Jul 18 4475
4476 Level 02 - CORE 03 12w 09 May 18 01 Aug 18 4476
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4482 2nd Fix wall 1w 14 Jun 18 20 Jun 18 4482
4483 IPS Frame (Box Out only) incl. Backing ply 3d 21 Jun 18 25 Jun 18 4483
4484 Screed 2d 26 Jun 18 27 Jun 18 4484
4485 Fix Ceiling Grid Works 3d 28 Jun 18 02 Jul 18 4485
4486 Floor Tiling Works 3d 03 Jul 18 05 Jul 18 4486
4487 Wall Tiling works incl. IPS Panels 3d 06 Jul 18 10 Jul 18 4487
4488 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 11 Jul 18 18 Jul 18 4488
4489 Mark and Cut openings for MEP on walls including Ceiling 2d 19 Jul 18 20 Jul 18 4489
4490 Install Vanity Tops 4d 19 Jul 18 24 Jul 18 4490
4491 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 23 Jul 18 26 Jul 18 4491
4495 1st Fix Wall with Head tracks 1w 11 May 18 17 May 18 4495
4496 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 23 May 18 20 Jun 18 4496
4518 IPS Frame (Box Out only) incl. Backing ply 3d 28 Jun 18 02 Jul 18 4518
4519 Screed 2d 03 Jul 18 04 Jul 18 4519
4520 Fix Ceiling Grid Works 3d 05 Jul 18 09 Jul 18 4520
4524 Mark and Cut openings for MEP on walls including Ceiling 2d 26 Jul 18 27 Jul 18 4524
4525 Install Vanity Tops 4d 26 Jul 18 31 Jul 18 4525
4526 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 30 Jul 18 02 Aug 18 4526
4527 Fix MEP Final Fixtures 3d 02 Aug 18 06 Aug 18 4527
4528 Final Coat Paint on Ceiling 2d 07 Aug 18 08 Aug 18 4528
4529 Lobby 9w 1d 18 May 18 23 Jul 18 4529
4530 1st Fix Wall with Head tracks 1w 18 May 18 24 May 18 4530
4531 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4531
4532 Fix Ceiling Grid 3d 28 Jun 18 02 Jul 18 4532
4533 Paint 1st Coat 2d 03 Jul 18 04 Jul 18 4533
4534 Fix doors incl. Ironmongery 2d 05 Jul 18 06 Jul 18 4534
4535 Mark and Cut openings for MEP on walls 2d 09 Jul 18 10 Jul 18 4535
4536 Install Ceiling Tiles 3d 11 Jul 18 13 Jul 18 4536
4537 Fix MEP Final Fixtures 3d 16 Jul 18 18 Jul 18 4537
4538 Final Coat Paint on walls and ceiling 3d 19 Jul 18 23 Jul 18 4538
4539 Staircase 5w 2d 18 Jun 18 24 Jul 18 4539
4540 H/L Electrical Containment & Conduits - 1st Fix 2d 18 Jun 18 19 Jun 18 4540
4541 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 20 Jun 18 21 Jun 18 4541
4543 First Coat Paint on Walls & Ceiliings 2d 05 Jul 18 06 Jul 18 4543
4544 MEP Final Fixtures on Wall & Ceilings 2d 19 Jul 18 20 Jul 18 4544
4545 Final Coat Paint on walls & Ceilings 2d 23 Jul 18 24 Jul 18 4545
4549 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 31 May 18 27 Jun 18 4549
4565 1st Fix Wall with Head tracks 1w 25 May 18 01 Jun 18 4565
4566 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4566
4573 Final Coat Paint on walls and ceiling 3d 26 Jul 18 30 Jul 18 4573
4575 H/L Electrical Containment & Conduits - 1st Fix 2d 25 Jun 18 26 Jun 18 4575
4576 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 27 Jun 18 28 Jun 18 4576
4577 Ceiling Rose fixing 1d 29 Jun 18 29 Jun 18 4577
4578 First Coat Paint on Walls & Ceiliings 2d 12 Jul 18 13 Jul 18 4578
4579 MEP Final Fixtures on Wall & Ceilings 2d 26 Jul 18 27 Jul 18 4579
4580 Final Coat Paint on walls & Ceilings 2d 30 Jul 18 31 Jul 18 4580
4581 Level 05 - CORE 03 12w 31 May 18 22 Aug 18 4581
4582 Toilet 12w 31 May 18 22 Aug 18 4582
4583 1st Fix Wall with Head tracks 1w 31 May 18 06 Jun 18 4583
4584 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 07 Jun 18 04 Jul 18 4584
4585 Fix Pocket Doors 1w 07 Jun 18 13 Jun 18 4585
4586 Inspection and Ceiling Grid Clearance 05 Jul 18 05 Jul 18 4586
4587 2nd Fix wall 1w 05 Jul 18 11 Jul 18 4587
4588 IPS Frame (Box Out only) incl. Backing ply 3d 12 Jul 18 16 Jul 18 4588
4594 Mark and Cut openings for MEP on walls including Ceiling 2d 09 Aug 18 10 Aug 18 4594
4595 Install Vanity Tops 4d 09 Aug 18 14 Aug 18 4595
4596 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 13 Aug 18 16 Aug 18 4596
4614 MEP Final Fixtures on Wall & Ceilings 2d 02 Aug 18 03 Aug 18 4614
4615 Final Coat Paint on walls & Ceilings 2d 06 Aug 18 07 Aug 18 4615
4616 Level 06 - CORE 03 12w 07 Jun 18 30 Aug 18 4616
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4619 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 14 Jun 18 11 Jul 18 4619
4620 Fix Pocket Doors 1w 14 Jun 18 20 Jun 18 4620
4621 Inspection and Ceiling Grid Clearance 12 Jul 18 12 Jul 18 4621
4622 2nd Fix wall 1w 12 Jul 18 18 Jul 18 4622
4623 IPS Frame (Box Out only) incl. Backing ply 3d 19 Jul 18 23 Jul 18 4623
4624 Screed 2d 24 Jul 18 25 Jul 18 4624
4625 Fix Ceiling Grid Works 3d 26 Jul 18 30 Jul 18 4625
4626 Floor Tiling Works 3d 31 Jul 18 02 Aug 18 4626
4627 Wall Tiling works incl. IPS Panels 3d 03 Aug 18 07 Aug 18 4627
4628 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 08 Aug 18 15 Aug 18 4628
4629 Mark and Cut openings for MEP on walls including Ceiling 2d 16 Aug 18 17 Aug 18 4629
4630 Install Vanity Tops 4d 16 Aug 18 21 Aug 18 4630
4631 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 20 Aug 18 23 Aug 18 4631
4635 1st Fix Wall with Head tracks 1w 11 Jun 18 15 Jun 18 4635
4636 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 21 Jun 18 18 Jul 18 4636
4637 Fix Ceiling Grid 3d 19 Jul 18 23 Jul 18 4637
4638 Paint 1st Coat 2d 24 Jul 18 25 Jul 18 4638
4639 Fix doors incl. Ironmongery 2d 26 Jul 18 27 Jul 18 4639
4640 Mark and Cut openings for MEP on walls 2d 30 Jul 18 31 Jul 18 4640
4641 Install Ceiling Tiles 3d 01 Aug 18 03 Aug 18 4641
4642 Fix MEP Final Fixtures 3d 06 Aug 18 08 Aug 18 4642
4643 Final Coat Paint on walls and ceiling 3d 09 Aug 18 13 Aug 18 4643
4644 Staircase 5w 2d 09 Jul 18 14 Aug 18 4644
4645 H/L Electrical Containment & Conduits - 1st Fix 2d 09 Jul 18 10 Jul 18 4645
4646 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 11 Jul 18 12 Jul 18 4646
4647 Ceiling Rose fixing 1d 13 Jul 18 13 Jul 18 4647
4648 First Coat Paint on Walls & Ceiliings 2d 26 Jul 18 27 Jul 18 4648
4649 MEP Final Fixtures on Wall & Ceilings 2d 09 Aug 18 10 Aug 18 4649
4650 Final Coat Paint on walls & Ceilings 2d 13 Aug 18 14 Aug 18 4650
4651 Level GF - CORE 03 12w 14 Jun 18 06 Sep 18 4651
4652 Toilet 12w 14 Jun 18 06 Sep 18 4652
4653 1st Fix Wall with Head tracks 1w 14 Jun 18 20 Jun 18 4653
4654 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 21 Jun 18 18 Jul 18 4654
4658 IPS Frame (Box Out only) incl. Backing ply 3d 26 Jul 18 30 Jul 18 4658
4659 Screed 2d 31 Jul 18 01 Aug 18 4659
4662 Wall Tiling works incl. IPS Panels 3d 10 Aug 18 14 Aug 18 4662
4663 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 15 Aug 18 22 Aug 18 4663
4664 Mark and Cut openings for MEP on walls including Ceiling 2d 23 Aug 18 24 Aug 18 4664
4665 Install Vanity Tops 4d 23 Aug 18 29 Aug 18 4665
4666 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 28 Aug 18 31 Aug 18 4666
4667 Fix MEP Final Fixtures 3d 31 Aug 18 04 Sep 18 4667
4668 Final Coat Paint on Ceiling 2d 05 Sep 18 06 Sep 18 4668
4669 Lobby 9w 1d 18 Jun 18 20 Aug 18 4669
4670 1st Fix Wall with Head tracks 1w 18 Jun 18 22 Jun 18 4670
4671 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 28 Jun 18 25 Jul 18 4671
4672 Fix Ceiling Grid 3d 26 Jul 18 30 Jul 18 4672
4673 Paint 1st Coat 2d 31 Jul 18 01 Aug 18 4673
4674 Fix doors incl. Ironmongery 2d 02 Aug 18 03 Aug 18 4674
4675 Mark and Cut openings for MEP on walls 2d 06 Aug 18 07 Aug 18 4675
4678 Final Coat Paint on walls and ceiling 3d 16 Aug 18 20 Aug 18 4678
4680 H/L Electrical Containment & Conduits - 1st Fix 2d 16 Jul 18 17 Jul 18 4680
4681 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 18 Jul 18 19 Jul 18 4681
4683 First Coat Paint on Walls & Ceiliings 2d 02 Aug 18 03 Aug 18 4683
4684 MEP Final Fixtures on Wall & Ceilings 2d 16 Aug 18 17 Aug 18 4684
4685 Final Coat Paint on walls & Ceilings 2d 20 Aug 18 21 Aug 18 4685
4688 Latest Date for ABP/WTP to omit Cat A Shell and Core scope of works to Building 5A 01 Mar 18 01 Mar 18 4688
4691 Fit out Ground Floor Unit 2 and 3 5w 3d 21 Jun 18 30 Jul 18 4691
4692
4692 Install conduit to cleaners sockets to core walls 3d 21 Jun 18 25 Jun 18
4693 Boarding and Insulation to external and core walls 1w 26 Jun 18 02 Jul 18 4693
4696
4696 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 Jul 18 16 Jul 18
4697 Install Joinery incl Doors 1w 17 Jul 18 23 Jul 18 4697
4698
4698 Decoration 1w 24 Jul 18 30 Jul 18
4699 Fit Out Ground Floor Units 4 and 5 5w 3d 26 Jun 18 02 Aug 18 4699
4700
4700 Install conduit to cleaners sockets to core walls 3d 26 Jun 18 28 Jun 18
4701 Boarding and Insulation to external and core walls 1w 29 Jun 18 05 Jul 18 4701
4704
4704 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Jul 18 19 Jul 18
4705 Install Joinery incl Doors 1w 20 Jul 18 26 Jul 18 4705
4706
4706 Decoration 1w 27 Jul 18 02 Aug 18
4709 Install conduit to cleaners sockets to core walls 3d 26 Jun 18 28 Jun 18 4709
4710 Boarding and Insulation to external and core walls 1w 29 Jun 18 05 Jul 18 4710
4713 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Jul 18 19 Jul 18 4713
4717 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18 4717
4718 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 4718
4721 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18 4721
4725 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18 4725
4726 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18 4726
4729 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18 4729
4735
4735 Install conduit to cleaners sockets to core walls 3d 29 Jun 18 03 Jul 18
4736 Boarding and Insulation to external and core walls 1w 04 Jul 18 10 Jul 18 4736
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4738 Taping and Joining to Walls 2d 11 Jul 18 12 Jul 18 4738
4739
4739 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 18 Jul 18 24 Jul 18
4740 Install Joinery incl Doors 1w 25 Jul 18 31 Jul 18 4740
4741
4741 Decoration 1w 01 Aug 18 07 Aug 18
4742 Units 3 and 4 5w 3d 04 Jul 18 10 Aug 18 4742
4743
4743 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18
4744 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18 4744
4747
4747 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18
4748 Install Joinery incl Doors 1w 30 Jul 18 03 Aug 18 4748
4749
4749 Decoration 1w 06 Aug 18 10 Aug 18
4750 Units 5 and 6 6w 09 Jul 18 17 Aug 18 4750
4751
4751 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18
4752 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18 4752
4755
4755 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18
4756 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18 4756
4757
4757 Decoration 1w 13 Aug 18 17 Aug 18
4758 High Level Services Second Floor 8w 1d 20 Apr 18 20 Jun 18 4758
4761 Install conduit to cleaners sockets to core walls 3d 04 Jul 18 06 Jul 18 4761
4762
4762 Boarding and Insulation to external and core walls 1w 09 Jul 18 13 Jul 18
4763 Install wiring to containment in ceilings 1w 16 Jul 18 20 Jul 18 4763
4764
4764 Taping and Joining to Walls 2d 16 Jul 18 17 Jul 18
4765 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 23 Jul 18 27 Jul 18 4765
4766
4766 Install Joinery incl Doors 1w 30 Jul 18 03 Aug 18
4767 Decoration 1w 06 Aug 18 10 Aug 18 4767
4769 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18 4769
4770
4770 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18
4771 Install wiring to containment in ceilings 1w 19 Jul 18 25 Jul 18 4771
4772
4772 Taping and Joining to Walls 2d 19 Jul 18 20 Jul 18
4773 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18 4773
4774
4774 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18
4775 Decoration 1w 09 Aug 18 15 Aug 18 4775
4777 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18 4777
4778
4778 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18
4779 Install wiring to containment in ceilings 1w 24 Jul 18 30 Jul 18 4779
4780
4780 Taping and Joining to Walls 2d 24 Jul 18 25 Jul 18
4781 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18 4781
4782
4782 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18
4783 Decoration 1w 14 Aug 18 20 Aug 18 4783
4787 Install conduit to cleaners sockets to core walls 3d 09 Jul 18 11 Jul 18 4787
4788
4788 Boarding and Insulation to external and core walls 1w 12 Jul 18 18 Jul 18
4789 Install wiring to containment in ceilings 1w 19 Jul 18 25 Jul 18 4789
4790
4790 Taping and Joining to Walls 3d 19 Jul 18 23 Jul 18
4791 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 26 Jul 18 01 Aug 18 4791
4792
4792 Install Joinery incl Doors 1w 02 Aug 18 08 Aug 18
4793 Decoration 1w 09 Aug 18 15 Aug 18 4793
4795 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18 4795
4796 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18 4796
4799
4799 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18
4800 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18 4800
4801
4801 Decoration 1w 16 Aug 18 22 Aug 18
4802 Units 5 and 6 5w 3d 17 Jul 18 23 Aug 18 4802
4803
4803 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
4804 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4804
4807
4807 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4808 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4808
4809
4809 Decoration 1w 17 Aug 18 23 Aug 18
4810 High Level Services Fourth Floor 8w 22 May 18 17 Jul 18 4810
4813
4813 Install conduit to cleaners sockets to core walls 3d 12 Jul 18 16 Jul 18
4814 Boarding and Insulation to external and core walls 1w 17 Jul 18 23 Jul 18 4814
4817
4817 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 31 Jul 18 06 Aug 18
4818 Install Joinery incl Doors 1w 07 Aug 18 13 Aug 18 4818
4819
4819 Decoration 1w 14 Aug 18 20 Aug 18
4820 Units 3 and 4 5w 3d 17 Jul 18 23 Aug 18 4820
4821
4821 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
4822 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4822
4825
4825 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4826 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4826
4827
4827 Decoration 1w 17 Aug 18 23 Aug 18
4828 Units 5 and 6 6w 20 Jul 18 31 Aug 18 4828
4829
4829 Install conduit to cleaners sockets to core walls 3d 20 Jul 18 24 Jul 18
4830 Boarding and Insulation to external and core walls 1w 25 Jul 18 31 Jul 18 4830
4833 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Aug 18 14 Aug 18 4833
4834
4834 Install Joinery incl Doors 1w 15 Aug 18 21 Aug 18
4835 Decoration 1w 24 Aug 18 31 Aug 18 4835
4839 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18 4839
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4840 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 4840
4843
4843 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
4844 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 4844
4845
4845 Decoration 1w 17 Aug 18 23 Aug 18
4846 Units 3 and 4 6w 20 Jul 18 31 Aug 18 4846
4847
4847 Install conduit to cleaners sockets to core walls 3d 20 Jul 18 24 Jul 18
4848 Boarding and Insulation to external and core walls 1w 25 Jul 18 31 Jul 18 4848
4851
4851 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 08 Aug 18 14 Aug 18
4852 Install Joinery incl Doors 1w 15 Aug 18 21 Aug 18 4852
4853
4853 Decoration 1w 24 Aug 18 31 Aug 18
4854 Units 5 and 6 5w 3d 25 Jul 18 03 Sep 18 4854
4855
4855 Install conduit to cleaners sockets to core walls 3d 25 Jul 18 27 Jul 18
4856 Boarding and Insulation to external and core walls 1w 30 Jul 18 03 Aug 18 4856
4859
4859 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 13 Aug 18 17 Aug 18
4860 Install Joinery incl Doors 1w 20 Aug 18 24 Aug 18 4860
4861
4861 Decoration 1w 28 Aug 18 03 Sep 18
4862 High Level Services Sixth Floor 8w 20 Jun 18 14 Aug 18 4862
4880 Install Raised Access Floor incl Below Floor Barriers 1w 19 Oct 18 25 Oct 18 4880
4884 Install Raised Access Floor incl Below Floor Barriers 1w 24 Oct 18 30 Oct 18 4884
4888 Install Raised Access Floor incl Below Floor Barriers 1w 29 Oct 18 02 Nov 18 4888
4892 Install Raised Access Floor incl Below Floor Barriers 1w 01 Nov 18 07 Nov 18 4892
4896 Install Raised Access Floor incl Below Floor Barriers 1w 06 Nov 18 12 Nov 18 4896
4900 Install Raised Access Floor incl Below Floor Barriers 1w 09 Nov 18 15 Nov 18 4900
4904 Install Raised Access Floor incl Below Floor Barriers 1w 14 Nov 18 20 Nov 18 4904
4909 Install Raised Access Floor incl Below Floor Barriers 1w 26 Oct 18 01 Nov 18 4909
4913 Install Raised Access Floor incl Below Floor Barriers 1w 31 Oct 18 06 Nov 18 4913
4917 Install Raised Access Floor incl Below Floor Barriers 1w 05 Nov 18 09 Nov 18 4917
4921 Install Raised Access Floor incl Below Floor Barriers 1w 08 Nov 18 14 Nov 18 4921
4925 Install Raised Access Floor incl Below Floor Barriers 1w 13 Nov 18 19 Nov 18 4925
4929 Install Raised Access Floor incl Below Floor Barriers 1w 16 Nov 18 22 Nov 18 4929
4933 Install Raised Access Floor incl Below Floor Barriers 1w 21 Nov 18 27 Nov 18 4933
4938 Install Raised Access Floor incl Below Floor Barriers 1w 02 Nov 18 08 Nov 18 4938
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
4942 Install Raised Access Floor incl Below Floor Barriers 1w 07 Nov 18 13 Nov 18 4942
4946 Install Raised Access Floor incl Below Floor Barriers 1w 12 Nov 18 16 Nov 18 4946
4950 Install Raised Access Floor incl Below Floor Barriers 1w 15 Nov 18 21 Nov 18 4950
4954 Install Raised Access Floor incl Below Floor Barriers 1w 20 Nov 18 26 Nov 18 4954
4958 Install Raised Access Floor incl Below Floor Barriers 1w 23 Nov 18 29 Nov 18 4958
4962 Install Raised Access Floor incl Below Floor Barriers 1w 28 Nov 18 04 Dec 18 4962
4988 STAND PRECAST CORE WALLS GND - 1ST FLOOR 4d 22 Nov 17 05 Dec 17 4988
4989 STAND PRECAST COLUMNS GROUND - 1ST FLOOR 1w 3d 23 Nov 17 04 Dec 17 4989
4991 STAND PRECAST CORE WALLS 1ST - 2ND FLOOR 4d 07 Dec 17 15 Dec 17 4991
4992 STAND PRECAST COLUMNS 1ST - 2ND FLOOR 2w 08 Dec 17 21 Dec 17 4992
4994 STAND PRECAST WALLS 2ND - 3RD FLOOR 4d 20 Dec 17 08 Jan 18 4994
4995 STAND PRECAST COLUMNS 2ND - 3RD FLOOR 1w 4d 21 Dec 17 11 Jan 18 4995
4997 STAND PRECAST CORE WALLS 3RD - 4TH FLOOR 4d 11 Jan 18 19 Jan 18 4997
4998 STAND PRECAST COLUMNS 3RD - 4TH FLOOR 1w 4d 12 Jan 18 24 Jan 18 4998
5000 STAND PRECAST CORE WALLS 4TH - 5TH FLOOR 4d 24 Jan 18 01 Feb 18 5000
5001 STAND PRECAST COLUMNS 4TH - 5TH FLOOR 2w 25 Jan 18 07 Feb 18 5001
5014 Precast Cladding Panels South elevation Bay 1 3d 28 Mar 18 03 Apr 18 5014
5015 Precast Cladding Panels South elevation Bay 2 3d 04 Apr 18 06 Apr 18 5015
5016 Precast Cladding Panels South elevation Bay 3 3d 09 Apr 18 11 Apr 18 5016
5017 Precast Cladding Panels South elevation Bay 4 4d 12 Apr 18 17 Apr 18 5017
5022 Complete ribbon windows after hoists removed 4w 16 Jul 18 10 Aug 18 5022
5023 Install SFS, Windows & Cladding L05 9w 3d 26 Mar 18 06 Jun 18 5023
5024 Install SFS, Windows and cladding Level 5 North elevation 9w 3d 26 Mar 18 06 Jun 18 5024
5025 Install SFS, Windows and cladding Level 5 South, East and West Elevations 6w 13 Apr 18 29 May 18 5025
5026 Install ribbon window curtain walling to South Elevation 4w 3d 25 Apr 18 30 May 18 5026
5043 Latest Date for ABP/WTP to omit Cat A Shell and Core Services scope of works to Building 5B 14 Nov 17 14 Nov 17 5043
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5050 Ground Floor Plant Installation 5B 6w 09 Mar 18 23 Apr 18 5050
5058
5058 Blockwork Walls at L5 1w 28 Mar 18 05 Apr 18
5059 Revist 1w 1d 27 Jul 18 03 Aug 18 5059
5066 Window for Cantidecks to load out upper floor 2w 23 Feb 18 08 Mar 18 5066
5069 Lift /Toilet Core Fit Out 56w 2d 22 Nov 17 22 Jan 19 5069
5080 Hand back Lift 2 after builders beneficial use 21 Dec 18 21 Dec 18 5080
5081 Recommission Lift 2 2w 21 Dec 18 17 Jan 19 5081
5090 Hand back Lift 4 after builders beneficial use 09 Jan 19 09 Jan 19 5090
5105 Wall Tiling works incl. IPS Panels 3d 18 Jun 18 20 Jun 18 5105
5106 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 21 Jun 18 28 Jun 18 5106
5107 Mark and Cut openings for MEP on walls including Ceiling 2d 29 Jun 18 02 Jul 18 5107
5113 1st Fix Wall with Head tracks 1w 19 Apr 18 25 Apr 18 5113
5114 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 02 May 18 31 May 18 5114
5128 Final Coat Paint on walls & Ceilings 2d 26 Jun 18 27 Jun 18 5128
5131 1st Fix Wall with Head tracks 1w 24 Apr 18 01 May 18 5131
5132 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 02 May 18 31 May 18 5132
5133 Fix Pocket Doors 1w 02 May 18 09 May 18 5133
5136 IPS Frame (Box Out only) incl. Backing ply 3d 08 Jun 18 12 Jun 18 5136
5137 Screed 2d 13 Jun 18 14 Jun 18 5137
5138 Fix Ceiling Grid Works 3d 15 Jun 18 19 Jun 18 5138
5156 Final Coat Paint on walls and ceiling 3d 29 Jun 18 03 Jul 18 5156
5159 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 31 May 18 01 Jun 18 5159
5161 First Coat Paint on Walls & Ceiliings 2d 15 Jun 18 18 Jun 18 5161
5162 MEP Final Fixtures on Wall & Ceilings 2d 29 Jun 18 02 Jul 18 5162
5163 Final Coat Paint on walls & Ceilings 2d 03 Jul 18 04 Jul 18 5163
5164 Level 03 - CORE 01 12w 02 May 18 26 Jul 18 5164
5165 Toilet 12w 02 May 18 26 Jul 18 5165
5166 1st Fix Wall with Head tracks 1w 02 May 18 09 May 18 5166
5167 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 10 May 18 07 Jun 18 5167
5168 Fix Pocket Doors 1w 10 May 18 16 May 18 5168
5169 Inspection and Ceiling Grid Clearance 08 Jun 18 08 Jun 18 5169
5170 2nd Fix wall 1w 08 Jun 18 14 Jun 18 5170
5171 IPS Frame (Box Out only) incl. Backing ply 3d 15 Jun 18 19 Jun 18 5171
5172 Screed 2d 20 Jun 18 21 Jun 18 5172
5173 Fix Ceiling Grid Works 3d 22 Jun 18 26 Jun 18 5173
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5174 Floor Tiling Works 3d 27 Jun 18 29 Jun 18 5174
5175 Wall Tiling works incl. IPS Panels 3d 02 Jul 18 04 Jul 18 5175
5176 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 05 Jul 18 12 Jul 18 5176
5177 Mark and Cut openings for MEP on walls including Ceiling 2d 13 Jul 18 16 Jul 18 5177
5178 Install Vanity Tops 4d 13 Jul 18 18 Jul 18 5178
5179 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 17 Jul 18 20 Jul 18 5179
5180 Fix MEP Final Fixtures 3d 20 Jul 18 24 Jul 18 5180
5181 Final Coat Paint on Ceiling 2d 25 Jul 18 26 Jul 18 5181
5182 Lobby 9w 1d 04 May 18 10 Jul 18 5182
5183 1st Fix Wall with Head tracks 1w 04 May 18 11 May 18 5183
5184 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5184
5185 Fix Ceiling Grid 3d 15 Jun 18 19 Jun 18 5185
5188 Mark and Cut openings for MEP on walls 2d 26 Jun 18 27 Jun 18 5188
5191 Final Coat Paint on walls and ceiling 3d 06 Jul 18 10 Jul 18 5191
5192 Staircase 5w 2d 05 Jun 18 11 Jul 18 5192
5193 H/L Electrical Containment & Conduits - 1st Fix 2d 05 Jun 18 06 Jun 18 5193
5194 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 07 Jun 18 08 Jun 18 5194
5195 Ceiling Rose fixing 1d 11 Jun 18 11 Jun 18 5195
5196 First Coat Paint on Walls & Ceiliings 2d 22 Jun 18 25 Jun 18 5196
5197 MEP Final Fixtures on Wall & Ceilings 2d 06 Jul 18 09 Jul 18 5197
5198 Final Coat Paint on walls & Ceilings 2d 10 Jul 18 11 Jul 18 5198
5199 Level 04 - CORE 01 12w 10 May 18 02 Aug 18 5199
5200 Toilet 12w 10 May 18 02 Aug 18 5200
5201 1st Fix Wall with Head tracks 1w 10 May 18 16 May 18 5201
5202 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5202
5203 Fix Pocket Doors 1w 17 May 18 23 May 18 5203
5204 Inspection and Ceiling Grid Clearance 15 Jun 18 15 Jun 18 5204
5205 2nd Fix wall 1w 15 Jun 18 21 Jun 18 5205
5206 IPS Frame (Box Out only) incl. Backing ply 3d 22 Jun 18 26 Jun 18 5206
5207 Screed 2d 27 Jun 18 28 Jun 18 5207
5210 Wall Tiling works incl. IPS Panels 3d 09 Jul 18 11 Jul 18 5210
5211 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 12 Jul 18 19 Jul 18 5211
5212 Mark and Cut openings for MEP on walls including Ceiling 2d 20 Jul 18 23 Jul 18 5212
5218 1st Fix Wall with Head tracks 1w 14 May 18 18 May 18 5218
5219 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5219
5220 Fix Ceiling Grid 3d 22 Jun 18 26 Jun 18 5220
5221 Paint 1st Coat 2d 27 Jun 18 28 Jun 18 5221
5222 Fix doors incl. Ironmongery 2d 29 Jun 18 02 Jul 18 5222
5223 Mark and Cut openings for MEP on walls 2d 03 Jul 18 04 Jul 18 5223
5224 Install Ceiling Tiles 3d 05 Jul 18 09 Jul 18 5224
5225 Fix MEP Final Fixtures 3d 10 Jul 18 12 Jul 18 5225
5226 Final Coat Paint on walls and ceiling 3d 13 Jul 18 17 Jul 18 5226
5227 Staircase 5w 2d 12 Jun 18 18 Jul 18 5227
5228 H/L Electrical Containment & Conduits - 1st Fix 2d 12 Jun 18 13 Jun 18 5228
5229 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 14 Jun 18 15 Jun 18 5229
5230 Ceiling Rose fixing 1d 18 Jun 18 18 Jun 18 5230
5231 First Coat Paint on Walls & Ceiliings 2d 29 Jun 18 02 Jul 18 5231
5232 MEP Final Fixtures on Wall & Ceilings 2d 13 Jul 18 16 Jul 18 5232
5233 Final Coat Paint on walls & Ceilings 2d 17 Jul 18 18 Jul 18 5233
5234 Level 05 - CORE 01 12w 17 May 18 09 Aug 18 5234
5241 IPS Frame (Box Out only) incl. Backing ply 3d 29 Jun 18 03 Jul 18 5241
5258 Mark and Cut openings for MEP on walls 2d 10 Jul 18 11 Jul 18 5258
5261 Final Coat Paint on walls and ceiling 3d 20 Jul 18 24 Jul 18 5261
5262 Staircase 5w 2d 19 Jun 18 25 Jul 18 5262
5263 H/L Electrical Containment & Conduits - 1st Fix 2d 19 Jun 18 20 Jun 18 5263
5264 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 21 Jun 18 22 Jun 18 5264
5266 First Coat Paint on Walls & Ceiliings 2d 06 Jul 18 09 Jul 18 5266
5267 MEP Final Fixtures on Wall & Ceilings 2d 20 Jul 18 23 Jul 18 5267
5268 Final Coat Paint on walls & Ceilings 2d 24 Jul 18 25 Jul 18 5268
5269 Level GF- CORE 01 12w 24 May 18 16 Aug 18 5269
5270 Toilet 12w 24 May 18 16 Aug 18 5270
5271 1st Fix Wall with Head tracks 1w 24 May 18 31 May 18 5271
5272 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 01 Jun 18 28 Jun 18 5272
5273 Fix Pocket Doors 1w 01 Jun 18 07 Jun 18 5273
5274 Inspection and Ceiling Grid Clearance 29 Jun 18 29 Jun 18 5274
5275 2nd Fix wall 1w 29 Jun 18 05 Jul 18 5275
5276 IPS Frame (Box Out only) incl. Backing ply 3d 06 Jul 18 10 Jul 18 5276
5277 Screed 2d 11 Jul 18 12 Jul 18 5277
5278 Fix Ceiling Grid Works 3d 13 Jul 18 17 Jul 18 5278
5279 Floor Tiling Works 3d 18 Jul 18 20 Jul 18 5279
5280 Wall Tiling works incl. IPS Panels 3d 23 Jul 18 25 Jul 18 5280
5281 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 26 Jul 18 02 Aug 18 5281
5282 Mark and Cut openings for MEP on walls including Ceiling 2d 03 Aug 18 06 Aug 18 5282
5283 Install Vanity Tops 4d 03 Aug 18 08 Aug 18 5283
5284 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 07 Aug 18 10 Aug 18 5284
5285 Fix MEP Final Fixtures 3d 10 Aug 18 14 Aug 18 5285
5288 1st Fix Wall with Head tracks 1w 29 May 18 04 Jun 18 5288
5289 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Jun 18 05 Jul 18 5289
5290 Fix Ceiling Grid 3d 06 Jul 18 10 Jul 18 5290
5307 1st Fix Wall with Head tracks 1w 02 May 18 09 May 18 5307
5308 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 10 May 18 07 Jun 18 5308
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5309 Fix Pocket Doors 1w 10 May 18 16 May 18 5309
5310 Inspection and Ceiling Grid Clearance 08 Jun 18 08 Jun 18 5310
5311 2nd Fix wall 1w 08 Jun 18 14 Jun 18 5311
5312 IPS Frame (Box Out only) incl. Backing ply 3d 15 Jun 18 19 Jun 18 5312
5313 Screed 2d 20 Jun 18 21 Jun 18 5313
5314 Fix Ceiling Grid Works 3d 22 Jun 18 26 Jun 18 5314
5315 Floor Tiling Works 3d 27 Jun 18 29 Jun 18 5315
5316 Wall Tiling works incl. IPS Panels 3d 02 Jul 18 04 Jul 18 5316
5317 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 05 Jul 18 12 Jul 18 5317
5318 Mark and Cut openings for MEP on walls including Ceiling 2d 13 Jul 18 16 Jul 18 5318
5324 1st Fix Wall with Head tracks 1w 04 May 18 11 May 18 5324
5325 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5325
5343 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 17 May 18 14 Jun 18 5343
5351 Wall Tiling works incl. IPS Panels 3d 09 Jul 18 11 Jul 18 5351
5352 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 12 Jul 18 19 Jul 18 5352
5353 Mark and Cut openings for MEP on walls including Ceiling 2d 20 Jul 18 23 Jul 18 5353
5354 Install Vanity Tops 4d 20 Jul 18 25 Jul 18 5354
5355 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 24 Jul 18 27 Jul 18 5355
5356 Fix MEP Final Fixtures 3d 27 Jul 18 31 Jul 18 5356
5357 Final Coat Paint on Ceiling 2d 01 Aug 18 02 Aug 18 5357
5358 Lobby 9w 1d 14 May 18 17 Jul 18 5358
5359 1st Fix Wall with Head tracks 1w 14 May 18 18 May 18 5359
5360 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 24 May 18 21 Jun 18 5360
5361 Fix Ceiling Grid 3d 22 Jun 18 26 Jun 18 5361
5362 Paint 1st Coat 2d 27 Jun 18 28 Jun 18 5362
5363 Fix doors incl. Ironmongery 2d 29 Jun 18 02 Jul 18 5363
5364 Mark and Cut openings for MEP on walls 2d 03 Jul 18 04 Jul 18 5364
5365 Install Ceiling Tiles 3d 05 Jul 18 09 Jul 18 5365
5367 Final Coat Paint on walls and ceiling 3d 13 Jul 18 17 Jul 18 5367
5369 H/L Electrical Containment & Conduits - 1st Fix 2d 12 Jun 18 13 Jun 18 5369
5370 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 14 Jun 18 15 Jun 18 5370
5373 MEP Final Fixtures on Wall & Ceilings 2d 13 Jul 18 16 Jul 18 5373
5374 Final Coat Paint on walls & Ceilings 2d 17 Jul 18 18 Jul 18 5374
5421 Wall Tiling works incl. IPS Panels 3d 23 Jul 18 25 Jul 18 5421
5422 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 26 Jul 18 02 Aug 18 5422
5423 Mark and Cut openings for MEP on walls including Ceiling 2d 03 Aug 18 06 Aug 18 5423
5439 H/L Electrical Containment & Conduits - 1st Fix 2d 26 Jun 18 27 Jun 18 5439
5440 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 28 Jun 18 29 Jun 18 5440
5444 Final Coat Paint on walls & Ceilings 2d 31 Jul 18 01 Aug 18 5444
5445 Level 05 - CORE 02 12w 01 Jun 18 23 Aug 18 5445
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5446 Toilet 12w 01 Jun 18 23 Aug 18 5446
5447 1st Fix Wall with Head tracks 1w 01 Jun 18 07 Jun 18 5447
5448 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 08 Jun 18 05 Jul 18 5448
5449 Fix Pocket Doors 1w 08 Jun 18 14 Jun 18 5449
5450 Inspection and Ceiling Grid Clearance 06 Jul 18 06 Jul 18 5450
5451 2nd Fix wall 1w 06 Jul 18 12 Jul 18 5451
5452 IPS Frame (Box Out only) incl. Backing ply 3d 13 Jul 18 17 Jul 18 5452
5453 Screed 2d 18 Jul 18 19 Jul 18 5453
5454 Fix Ceiling Grid Works 3d 20 Jul 18 24 Jul 18 5454
5456 Wall Tiling works incl. IPS Panels 3d 30 Jul 18 01 Aug 18 5456
5457 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 02 Aug 18 09 Aug 18 5457
5458 Mark and Cut openings for MEP on walls including Ceiling 2d 10 Aug 18 13 Aug 18 5458
5460 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 14 Aug 18 17 Aug 18 5460
5482 1st Fix Wall with Head tracks 1w 08 Jun 18 14 Jun 18 5482
5483 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 15 Jun 18 12 Jul 18 5483
5484 Fix Pocket Doors 1w 15 Jun 18 21 Jun 18 5484
5487 IPS Frame (Box Out only) incl. Backing ply 3d 20 Jul 18 24 Jul 18 5487
5491 Wall Tiling works incl. IPS Panels 3d 06 Aug 18 08 Aug 18 5491
5492 Fix Ceiling Boarding including Taping & Jointing works incl. mist+1st coat 1w 1d 09 Aug 18 16 Aug 18 5492
5493 Mark and Cut openings for MEP on walls including Ceiling 2d 17 Aug 18 20 Aug 18 5493
5494 Install Vanity Tops 4d 17 Aug 18 22 Aug 18 5494
5495 Fix Sanitaryware and Wall Fixures incl. Connection & testing 4d 21 Aug 18 24 Aug 18 5495
5496 Fix MEP Final Fixtures 3d 24 Aug 18 29 Aug 18 5496
5497 Final Coat Paint on Ceiling 2d 30 Aug 18 31 Aug 18 5497
5498 Lobby 9w 1d 12 Jun 18 14 Aug 18 5498
5499 1st Fix Wall with Head tracks 1w 12 Jun 18 18 Jun 18 5499
5500 H/L services incl. Services within wall (Mechanical & Electrical Drop) 4w 22 Jun 18 19 Jul 18 5500
5501 Fix Ceiling Grid 3d 20 Jul 18 24 Jul 18 5501
5502 Paint 1st Coat 2d 25 Jul 18 26 Jul 18 5502
5503 Fix doors incl. Ironmongery 2d 27 Jul 18 30 Jul 18 5503
5504 Mark and Cut openings for MEP on walls 2d 31 Jul 18 01 Aug 18 5504
5507 Final Coat Paint on walls and ceiling 3d 10 Aug 18 14 Aug 18 5507
5509 H/L Electrical Containment & Conduits - 1st Fix 2d 10 Jul 18 11 Jul 18 5509
5510 Lighting/Power/BMS/FA & Emergency cable pulling Works 2d 12 Jul 18 13 Jul 18 5510
5512 First Coat Paint on Walls & Ceiliings 2d 27 Jul 18 30 Jul 18 5512
5513 MEP Final Fixtures on Wall & Ceilings 2d 10 Aug 18 13 Aug 18 5513
5514 Final Coat Paint on walls & Ceilings 2d 14 Aug 18 15 Aug 18 5514
5517 Latest Date for ABP/WTP to omit Cat A Shell and Core Fit-out scope of works to Building 5B 01 Mar 18 01 Mar 18 5517
5519 Fit out Ground Floor Unit 2 and 3 5w 1d 21 Jun 18 26 Jul 18 5519
5520 Install conduit to cleaners sockets to core walls 3d 21 Jun 18 25 Jun 18 5520
5521
5521 Boarding and Insulation to external and core walls 1w 26 Jun 18 02 Jul 18
5522 Install wiring to containment in ceilings 1w 03 Jul 18 09 Jul 18 5522
5523
5523 Taping and Joining to Walls 2d 03 Jul 18 04 Jul 18
5524 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 10 Jul 18 16 Jul 18 5524
5525
5525 Install Joinery incl Doors 1w 17 Jul 18 23 Jul 18
5526 Decoration 1w 20 Jul 18 26 Jul 18 5526
5529
5529 Install conduit to cleaners sockets to core walls 3d 05 Jul 18 09 Jul 18
5530 Boarding and Insulation to external and core walls 1w 10 Jul 18 16 Jul 18 5530
5533
5533 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 24 Jul 18 30 Jul 18
5534 Install Joinery incl Doors 1w 31 Jul 18 06 Aug 18 5534
5535
5535 Decoration 1w 03 Aug 18 09 Aug 18
5536 Units 3 and 4 5w 1d 17 Jul 18 21 Aug 18 5536
5537
5537 Install conduit to cleaners sockets to core walls 3d 17 Jul 18 19 Jul 18
5538 Boarding and Insulation to external and core walls 1w 20 Jul 18 26 Jul 18 5538
5541
5541 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Aug 18 09 Aug 18
5542 Install Joinery incl Doors 1w 10 Aug 18 16 Aug 18 5542
5543
5543 Decoration 1w 15 Aug 18 21 Aug 18
5544 High Level Services First Floor 8w 23 Apr 18 20 Jun 18 5544
5547
5547 Install conduit to cleaners sockets to core walls 3d 19 Jul 18 23 Jul 18
5548 Boarding and Insulation to external and core walls 1w 24 Jul 18 30 Jul 18 5548
5550
5550 Taping and Joining to Walls 2d 31 Jul 18 01 Aug 18
5551 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 07 Aug 18 13 Aug 18 5551
5552
5552 Install Joinery incl Doors 1w 14 Aug 18 20 Aug 18
5553 Decoration 1w 17 Aug 18 23 Aug 18 5553
5555 Install conduit to cleaners sockets to core walls 3d 31 Jul 18 02 Aug 18 5555
5556
5556 Boarding and Insulation to external and core walls 1w 03 Aug 18 09 Aug 18
5557 Install wiring to containment in ceilings 1w 10 Aug 18 16 Aug 18 5557
5558
5558 Taping and Joining to Walls 3d 10 Aug 18 14 Aug 18
5559 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 17 Aug 18 23 Aug 18 5559
5560
5560 Install Joinery incl Doors 1w 24 Aug 18 31 Aug 18
5561 Decoration 1w 30 Aug 18 05 Sep 18 5561
5565 Install conduit to cleaners sockets to core walls 3d 02 Aug 18 06 Aug 18 5565
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5566 Boarding and Insulation to external and core walls 1w 07 Aug 18 13 Aug 18 5566
5569
5569 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 21 Aug 18 28 Aug 18
5570 Install Joinery incl Doors 1w 29 Aug 18 04 Sep 18 5570
5571
5571 Decoration 1w 03 Sep 18 07 Sep 18
5572 Units 3 and 4 5w 1d 14 Aug 18 19 Sep 18 5572
5573
5573 Install conduit to cleaners sockets to core walls 3d 14 Aug 18 16 Aug 18
5574 Boarding and Insulation to external and core walls 1w 17 Aug 18 23 Aug 18 5574
5577
5577 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 03 Sep 18 07 Sep 18
5578 Install Joinery incl Doors 1w 10 Sep 18 14 Sep 18 5578
5579
5579 Decoration 1w 13 Sep 18 19 Sep 18
5580 High Level Services Third Floor 8w 23 May 18 18 Jul 18 5580
5583
5583 Install conduit to cleaners sockets to core walls 3d 16 Aug 18 20 Aug 18
5584 Boarding and Insulation to external and core walls 1w 21 Aug 18 28 Aug 18 5584
5587
5587 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 05 Sep 18 11 Sep 18
5588 Install Joinery incl Doors 1w 12 Sep 18 18 Sep 18 5588
5591 Install conduit to cleaners sockets to core walls 3d 29 Aug 18 31 Aug 18 5591
5592
5592 Boarding and Insulation to external and core walls 1w 03 Sep 18 07 Sep 18
5593 Install wiring to containment in ceilings 1w 10 Sep 18 14 Sep 18 5593
5594
5594 Taping and Joining to Walls 3d 10 Sep 18 12 Sep 18
5595 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 17 Sep 18 21 Sep 18 5595
5596
5596 Install Joinery incl Doors 1w 24 Sep 18 28 Sep 18
5597 Decoration 1w 27 Sep 18 03 Oct 18 5597
5601 Install conduit to cleaners sockets to core walls 3d 31 Aug 18 04 Sep 18 5601
5602
5602 Boarding and Insulation to external and core walls 1w 05 Sep 18 11 Sep 18
5603 Install wiring to containment in ceilings 1w 12 Sep 18 18 Sep 18 5603
5604
5604 Taping and Joining to Walls 2d 12 Sep 18 13 Sep 18
5605 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 19 Sep 18 25 Sep 18 5605
5606
5606 Install Joinery incl Doors 1w 26 Sep 18 02 Oct 18
5607 Decoration 1w 01 Oct 18 05 Oct 18 5607
5609 Install conduit to cleaners sockets to core walls 3d 12 Sep 18 14 Sep 18 5609
5610
5610 Boarding and Insulation to external and core walls 1w 17 Sep 18 21 Sep 18
5611 Install wiring to containment in ceilings 1w 24 Sep 18 28 Sep 18 5611
5612
5612 Taping and Joining to Walls 3d 24 Sep 18 26 Sep 18
5613 Install Suspended Ceiling including Ceiling Cavity Barriers and service tiles 1w 01 Oct 18 05 Oct 18 5613
5614
5614 Install Joinery incl Doors 1w 08 Oct 18 12 Oct 18
5615 Decoration 1w 11 Oct 18 17 Oct 18 5615
5632 Install Raised Access Floor incl Below Floor Barriers 1w 19 Nov 18 23 Nov 18 5632
5636 Install Raised Access Floor incl Below Floor Barriers 1w 22 Nov 18 28 Nov 18 5636
5640 Install Raised Access Floor incl Below Floor Barriers 1w 27 Nov 18 03 Dec 18 5640
5644 Install Raised Access Floor incl Below Floor Barriers 1w 30 Nov 18 06 Dec 18 5644
5648 Install Raised Access Floor incl Below Floor Barriers 1w 05 Dec 18 11 Dec 18 5648
5652 Install Raised Access Floor incl Below Floor Barriers 1w 10 Dec 18 14 Dec 18 5652
5657 Install Raised Access Floor incl Below Floor Barriers 1w 26 Nov 18 30 Nov 18 5657
5661 Install Raised Access Floor incl Below Floor Barriers 1w 29 Nov 18 05 Dec 18 5661
5665 Install Raised Access Floor incl Below Floor Barriers 1w 04 Dec 18 10 Dec 18 5665
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5668 Complete Ceiling Tiles 1w 30 Nov 18 06 Dec 18 5668
5669 Install Raised Access Floor incl Below Floor Barriers 1w 07 Dec 18 13 Dec 18 5669
5673 Install Raised Access Floor incl Below Floor Barriers 1w 12 Dec 18 18 Dec 18 5673
5677 Install Raised Access Floor incl Below Floor Barriers 1w 19 Dec 18 08 Jan 19 5677
5682 Lay Road Kerbs (250 linear meters ) 3w 14 Sep 18 04 Oct 18 5682
5683 Lay Channel Kerb 1w 3d 28 Sep 18 09 Oct 18 5683
5684 Lay Kerb To Foothpath 1w 05 Oct 18 11 Oct 18 5684
5685 Paving and Tarmac North of 5A 10w 2d 12 Oct 18 07 Jan 19 5685
5686 Sets to Footpath 4w 12 Oct 18 08 Nov 18 5686
5687 Flags to Footpath 2w 4d 09 Nov 18 28 Nov 18 5687
5688 Mistal Paving to west of 5A 2w 29 Nov 18 12 Dec 18 5688
5689 Regulate for Tarmac 3d 13 Dec 18 17 Dec 18 5689
5690 Tarmac 1w 18 Dec 18 07 Jan 19 5690
5691 Hard Landscaping Between 5A and 5B 13w 10 Sep 18 07 Dec 18 5691
5692 Prep Works 3w 10 Sep 18 28 Sep 18 5692
5693 Import work to Finish Level 1w 10 Sep 18 14 Sep 18 5693
5694 Install ten number tree pits 1w 17 Sep 18 21 Sep 18 5694
5695 Prep for Paving and Kerbs 1w 24 Sep 18 28 Sep 18 5695
5696 Kerbs and Stairs 2w 01 Oct 18 12 Oct 18 5696
5707
5707 TEC (Provisional Sum) 13w 1d 05 Jul 18 05 Oct 18
5708 Flush Water Primary Systems 7w 05 Jul 18 22 Aug 18 5708
5713
5713 Building 8A 16w 14 Aug 18 04 Dec 18
5714 Precommission M & E Plant 7w 14 Aug 18 02 Oct 18 5714
5722
5722 Building 5B 15w 01 Oct 18 25 Jan 19
5723 Precommission M & E Plant 6w 01 Oct 18 09 Nov 18 5723
5726
5726 Building 8B Snag and Handover to CITIC / ABP 11w 14 Nov 18 13 Feb 19
5727 Units 1 & 2 9w 14 Nov 18 30 Jan 19 5727
5757
5757 Building 8A Snag and Handover to CITIC / ABP 10w 09 Nov 18 01 Feb 19
5758 Units 1 & 2 9w 09 Nov 18 25 Jan 19 5758
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
2016 2017 2018 2019
Line Name Duration Start Finish
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
5776 Desnag ABP defects 2w 18 Jan 19 31 Jan 19 5776
5778 Building 9A Snag and Handover to CITIC / ABP 9w 4d 13 Nov 18 04 Feb 19 5778
5788 Building 5B Snag and Handover to CITIC / ABP 10w 2d 10 Dec 18 06 Mar 19 5788
5789
5789 Units 1 & 2 9w 4d 10 Dec 18 01 Mar 19
5790 Inspection and Snagging of Units 1 & 2 2w 10 Dec 18 21 Dec 18 5790
5809 Building 5A Snag and Handover to CITIC / ABP 11w 4d 14 Nov 18 19 Feb 19 5809
5810
5810 Units 1 & 2 9w 4d 14 Nov 18 05 Feb 19
5811 Inspection and Snagging of Units 1 & 2 2w 14 Nov 18 27 Nov 18 5811
5820
5820 Units 3 & 4 9w 4d 21 Nov 18 12 Feb 19
5821 Inspection and Snagging of Units 3 & 4 2w 21 Nov 18 04 Dec 18 5821
5830
5830 Units 5 & 6 9w 4d 28 Nov 18 19 Feb 19
5831 Inspection and Snagging of Units 5 & 6 2w 28 Nov 18 11 Dec 18 5831
-80 -76 -72 -68 -64 -60 -56 -52 -44 -40 -36 -32 -28 -24 -20 -16 -12 -8 -4 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65
Line Name Duration Start Finish
9 30 20 11 1 22 12 3 24 14 5 26 23 13 6 27 17 8 29 19 10 31 21 11 2 23 13 4 25 15 5 26 19 9 30 21 11 2 23 13 3 24 15 5 26 17 7 28 18
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F
2016 2017 2018 2019
Work Packages
MPX ABP/WTP Piling Pre-cast Cladding AKT Structural Design Hilson Moran MEP design Farrells Architectural Design Vital Energi UXO
Windows Hoarding Site Accommodation Canopies MEP Infrastructure/Groundworks Concrete Frame Architectural Metalwork Roofing & Waterproofing
Blockwork Lifts Logistics Repairs to Dock Wall Thames Water Sprinklers and Dry Risers Utilities Roof Louvres & Mansafe Dry Lining & Ceilings Hoist
Joinery and Doors SCreed Tiling Decorations Cubicles Flooring Raised Floors Soft Landscaping Hard Landscaping Commissioning
Baselines
RAD Phase 1 Revised Contract Programme Rev 06 161017