Sie sind auf Seite 1von 19

SUMMARY REPORT

July 2014

TORM REPUBLICAN
Occupational accident on 3 December 2013
The Danish Maritime Accident Investigation Board
Carl Jacobsens Vej 29
DK-2500 Valby
Tel. +45 91 37 63 00

E-mail: dmaib@dmaib.dk
Website: www.dmaib.com

Outside office hours, the Danish Maritime Accident Investigation Board can be reached on +45 23 34 23 01.

This marine accident summary report is issued on 10 July 2014

Case number: 2013026421

Front page: TORM REPUBLICAN, mooring lines. Source: DMAIB

The marine accident report is available from the webpage of the Danish Maritime Accident Investi-
gation Board www.dmaib.com.

The Danish Maritime Accident Investigation Board


The Danish Maritime Accident Investigation Board is an independent unit under the Ministry of
Business and Growth that carries out investigations with a view to preventing accidents and pro-
moting initiatives that will enhance safety at sea.

The Danish Maritime Accident Investigation Board is an impartial unit which is, organizationally and
legally, independent of other parties

Purpose
The purpose of the Danish Maritime Accident Investigation Board is to investigate maritime acci-
dents and to make recommendations for improving safety, and it forms part of a collaboration with
similar investigation bodies in other countries. The Danish Maritime Accident Investigation Board
investigates maritime accidents and accidents to seafarers on Danish and Greenlandic merchant
and fishing ships as well as accidents on foreign merchant ships in Danish and Greenlandic wa-
ters.

The investigations of the Danish Maritime Accident Investigation Board procure information about
the actual circumstances of accidents and clarify the sequence of events and reasons leading to
these accidents.

The investigations are carried out separate from the criminal investigation. The criminal and/or lia-
bility aspects of accidents are not considered.

Marine accident reports and summary reports


The Danish Maritime Accident Investigation Board investigates about 140 accidents annually. In
case of very serious accidents, such as deaths and losses, or in case of other special circum-
stances, either a marine accident report or a summary report is published depending on the extent
and complexity of the events.

Page 2 of 19
Contents
1. PREFACE ................................................................................................................................ 4
2. FACTUAL INFORMATION....................................................................................................... 5
2.1 Photo of the ship ............................................................................................................... 5
2.2 Ship particulars ................................................................................................................. 6
2.3 Voyage particulars ............................................................................................................ 6
2.4 Weather data .................................................................................................................... 6
2.5 Marine casualty or incident information ............................................................................. 6
2.6 Shore authority involvement and emergency response ..................................................... 7
2.7 Scene of the accident ....................................................................................................... 8
3. NARRATIVE ............................................................................................................................ 8
3.1 Background ...................................................................................................................... 8
3.2 Sequence of events .......................................................................................................... 8
3.3 Mooring arrangement...................................................................................................... 12
3.3.1 Mooring setup .......................................................................................................... 12

3.3.2 Snap back zones ..................................................................................................... 13

3.3.3 Procedures and risk assessments ........................................................................... 15

3.3.4 The parted mooring rope ......................................................................................... 15

4. ANALYSIS ............................................................................................................................. 17
4.1 Parting of the mooring line .............................................................................................. 17
4.2 Mooring arrangement and operations ............................................................................. 17
5. CONCLUSIONS .................................................................................................................... 19
6. PREVENTIVE MEASURES TAKEN....................................................................................... 19

Page 3 of 19
1. PREFACE
On 3 December 2013 there was a serious oc- their everyday work as well as the interrela-
cupational accident on board the Danish tank- tions between regulations, procedures, crews
er TORM REPUBLICAN in Bilbao, Spain. perception of risk and the reality they meet.
DMAIBs main focus areas in the investigation This safety report is a summary of these find-
of the accident have been the conflicting goals ings.
that ship crews encounter and negotiate in

Page 4 of 19
2. FACTUAL INFORMATION
2.1 Photo of the ship

Figure 1: TORM REPUBLICAN


Photo: Ria Maat/Shipspotting.com

Page 5 of 19
2.2 Ship particulars
Name of vessel: TORM REPUBLICAN
Type of vessel: Chemical/product tanker
Nationality/flag: Danish
Port of registry: Copenhagen
IMO number: 9290658
Call sign: OYNE2
DOC company: Torm A/S
IMO company no. (DOC): 0310062
Year built: 2006
Shipyard/yard number: Hyundai Mipo Dockyard Company Ltd. Ulsan, Korea/0240
Classification society: American Bureau of Shipping
Length overall: 183.2 m
Breadth overall: 32.47 m
Gross tonnage: 29,242
Deadweight: 46,955 t
Draught max.: 12.216 m
Engine rating: 8,580 kW
Service speed: 14.5 knots
Hull material: Steel
Hull design: Double hull

2.3 Voyage particulars


Port of departure: Anchorage off Bilbao, Spain
Port of call: Bilbao, Spain
Type of voyage: Merchant shipping, international
Cargo information: Discharging, Naphtha
Manning: 21
Pilot on board: No
Number of passengers: 0

2.4 Weather data


Wind direction and speed: Southerly, 6 m/s
Wave height: 1.4 m
Visibility: 10 nm
Light/dark: Dark
Current: Unknown

2.5 Marine casualty or incident information


Type of marine casualty/incident: Occupational accident
IMO classification: Serious
Date, time: 3 December 2013 at 0254 LMT
Location: Petronor Terminal Berth 1, Bilbao, Spain
Position: 4322.20 N 00305.67 E
Ships operation, voyage segment: Alongside
Place on board: Main deck
Human factor data: Yes
Consequences: One seafarer injured

Page 6 of 19
2.6 Shore authority involvement and emergency response
Involved parties: Terminal, ambulance/paramedics/doctor, police
Resources used: 2 ambulances, paramedics, doctor, police
Speed of response: 12 minutes (from emergency call to arrival of ambu-
lance)
Actions taken: Injured person brought ashore
Results achieved: Injured person hospitalized for treatment

Page 7 of 19
2.7 Scene of the accident

JETTY NO. 1

LOCATION OF ACCIDENT. ALONGSIDE


PETRONOR TERMINAL, BILBAO, SPAIN

Figure 2: Scene of the accident. Insert: Close-up of terminal


Source: Google Earth

3. NARRATIVE
3.1 Background At the time of the accident, the crew consisted
of the master, seven officers, one electrician,
The Danish products/chemical tanker TORM one chief cook, one mess man, eight ratings,
REPUBLICAN was operating in world-wide one cadet and one ordinary seaman trainee,
tramp trade, i.e. trading on the spot market 21 persons in total.
without a fixed schedule or ports of call. Dur-
ing the previous year, the ship had called at
3.2 Sequence of events
33 ports in USA, South and Central America,
the Far East, Europe and Africa. On 25 No- TORM REPUBLICAN took pilot on 1 Decmber
vember 2013 the ship anchored off Bilbao, 2013 at 0136 hrs. and entered the port of
Spain, arriving from Galveston, USA with a Bilbao. The ship was moored at Petronor
cargo of naphtha. After six days awaiting ac- Terminal, Jetty No. 1 with port side alongside
cess to the terminal, she weighed anchor on 1 with a total of 12 mooring lines (figure 3).
December to approach the port of Bilbao. The
berth was designed for tankers with a The crew received advice on tides, mooring,
displacement of 25,000-500,000 tonnes and a swell etc. from the pilot. At the time there was
LOA 1 of 150-400 m. For vessels of 50,000 a wave height of 2.4 metres and the area
DWT 2 and above a minimum of eight mooring generally had significant tides. In addition, the
lines at each end was a requirement from the location of the jetty, on the outermost end of
terminal. the breakwater, meant that swell and surges
from passing vessels should be expected, and
as a result extra tension on the mooring lines.
Because of these circumstances, the master
1
LOA: Length overall.
2
DWT: Deadweight tonnage.

Page 8 of 19
had ordered frequent, at least hourly, tending
to the mooring lines.

Figure 3: Sketch of mooring setup at the time of the accident. The broken spring line is no. 6
Source: DMAIB

Page 9 of 19
At 0254 hrs. on 3 December 2013, the ship deck, thus having to pass the forward spring
was discharging a cargo of naphtha from two line and one of the head lines which both led
cargo tanks in the forward part of the ship. from the forward starboard mooring winch to
the fairleads at the side. The trainee passed
Two crewmembers, an able seaman and an first underneath both lines, pushing the bucket
ordinary seaman trainee, were doing a regular in front of him. When he had passed the lines,
inspection round on deck checking moorings, he heard some noise, looked back and found
gangway etc. During the round, they took the his colleague lying injured on the deck and the
opportunity to finish an earlier task of moving mooring line broken. The able seaman was
a paint drum from the deck store at the severely injured, but conscious. The parted
manifold to the paint store under the mooring rope was located some 3 metres
forecastle deck (figure 4). After picking up the from the railing at the side.
drum, they walked on the port side of the

LINE PARTED HERE WALKING ROUTE

SPRING LINES

APPROX. POSITION
WHERE INJURED
CREWMEMBER WAS
FOUND

Figure 4: Bottom: Sketch of main deck seen from above. Crewmembers walking route marked in dashed red
Top: Photo from scene of accident
Source: DMAIB

Page 10 of 19
The duty officer was notified of the accident by An ambulance with paramedics arrived at
another deck rating who came running to the 0312 and a second ambulance with a doctor
cargo control room. The master was informed arrived at 0330. At 0354 the patient was trans-
and the remaining crew were called for assis- ferred to the jetty and at 0420 the ambulance
tance. At 0300 the terminal was informed of left for the hospital.
the accident and was requested to call ambu-
lance assistance. A few minutes later the The local police were on board to inspect the
charterer and the owner were informed. Dis- scene of the accident, and at 0430 the cargo
charge operations were stopped and the in- discharge operation was resumed.
jured man was placed on a stretcher and
moved from the scene of the accident.

Page 11 of 19
3.3 Mooring arrangement
3.3.1 Mooring setup
The mooring setup of TORM REPUBLICAN terminal requirements, often in a configuration
was typical for this type of vessel. On the called 2+2+2. This configuration, which was
raised forecastle deck, there were two also used on the day of the accident, meant
combined anchor and mooring winches, one that two head lines, two spring lines and two
in each side. On the aft deck, there were two breast lines at each end were used.
mooring winches of the split winch type, and
on the starboard side of the cargo deck there The spring mooring lines shown in figure 3
were two split winches placed just forward of above (nos. 5 and 6) were led from the
the accommodation and between the cargo mooring winch placed on the starboard side of
manifold and the forecastle, respectively. All the cargo deck, forward of the manifold area.
winches were hydraulically powered. In Because of the inexpedient match between
addition to the winches, a number of bollards, the particular jetty and the ship, the forward
bitts and rollers were installed to spring lines had a very short lead and a steep
accommodate various mooring scenarios. angle which is not desireable as it has a
Generally the ship moored according to negative effect on the strength and flexibility of
the mooring line (figure 5).

FORWARD SPRING LINE


FROM MAIN DECK

Figure 5: Spring line similar to the parted one. Photo taken on the night of the accident
Source: TORM

The vessel was berthed at the outermost end from passing vessels. During the ships stay at
of the breakwater with very little protection Bilbao, the tide varied approximately 3.5 me-
from the sea and some effect of the waves tres. The combination of these factors meant
was expected, as well as occasional surges that the crew needed to attend to mooring

Page 12 of 19
lines regularly, and thus the master had is- When the ship was moored with the port side
sued standing orders to this effect. alongside, as it was in this case, the lines
At the time of the accident, the ship was dis- were led across the cargo deck to the port
charging from two forward cargo oil tanks. The side fairleads (figure 6). The spring lines
combined effect of the rising tide and the ves- consisted of a 220 metre mooring wire and an
sels bow rising due to the discharge caused 11 metre rope tail attached to it. Normally the
increased tension on the spring lines. wire part of the line would rest in the fairlead,
but in cases like the present with very short
moorings the rope part was in the fairlead.

FAIRLEADS
PARTED ROPE

ROLLERS

FORWARD SPRING
WINCH

Figure 6: Sketch of forward spring mooring arrangement


Source: DMAIB

The mooring setup on TORM REPUBLICAN To avoid chafing it was normal procedure to
was such that the weakest link in case of apply grease to the fairleads. This practice
overload should be the winch brake (set at resulted in the mooring wires and ropes being
30.6 t) followed by the wire (nominal breaking soiled.
strength 55.8 t), the rope tail (nominal
breaking strength 73.5 t) and lastly the fixed 3.3.2 Snap back zones
structures such as the winch foundation and When mooring lines break, they will snap back
the fairleads. This setup is the standard and is to the point to which they are fixed, i.e.
intended to minimize the consequences in winches, bollards, rollers or bitts. Snap back
case of overload. Contrary to the intended zones 3 are the areas which constitute the
functionality, on the day of the accident the most likely and therefore dangerous locations
winch brake was not released and the rope for a person to be in if a mooring line breaks.
burst. Snap back zones are usually painted on the
deck describing an angle, indicating the area
The brake holding power of the winches was to avoid (figure 7).
checked on a regular basis. For the particular
winch the latest test was carried out on 18
September 2013, confirming the setting of the
brake force at 30.6 tonnes. There were no
company requirements for calibrating the
3
equipment used for the winch brake holding For detailed information on snap back zones,
rd
tests. refer to OCIMF Mooring Equipment Guidelines, 3
Edition and www.seahealth.dk.

Page 13 of 19
Figure 7: Example of snap back zones
Source: Seahealth.dk

The snap back zones are generally defined the further it travels from the point of
considering the elasticity of the lines used, the breakage. The end of the broken rope may
angles and leads which are commonly used also recoil past the point to which it is secured
on board and the predominant expected to a distance almost equal to the remaining
behaviour of a parting mooring line. The length. A mooring line which is leading around
possible area of the snap back zone of the a pedestal roller will whip back in a wide arc
rope when it recoils will increase in breadth as it returns to the point to which it is secured.

Page 14 of 19
TORM REPUBLICAN had snap back zones the deck. Figure 8 shows the snap back zones
marked on the deck. In the area where the at the similar position in the starboard side.
accident happened, no zones were marked on

Figure 8: Snap back zones at starboard side forward, TORM REPUBLICAN


Source: DMAIB

3.3.3 Procedures and risk assessments


Among the tools available to the ships crew rope tail had been brought into service on 24
was a shipboard manual which contained a August 2012 and thus was due for replace-
section on safe mooring operations. The ship- ment in approximately 3 months.
board manual is a generic document and is
not made specifically for the individual vessel. 3.3.4 The parted mooring rope
The main areas that the manual describes are The parted rope tail was an 8-strand nylon
types of mooring operations, familiarization, rope, 64 mm in diameter and 11 metres long,
lists of factors to consider, the use of shack- with covered (chafe protected) eye splices at
les, mooring management and general safety both ends. When new, the rope had a
reminders. Examples of the latter include: minimum breaking strength of 162,000 lbs
Always stand well clear of a mooring line un- (approx. 73.5 tonnes).
der load., ... synthetic fibre ropes give little or
no warning when it is about to break ... This type of rope has an indicator strand
woven into it over the full length of the rope.
A risk assessment was also available on The indicator strand will break when the rope
board, containing a selection of identified risks is subjected to elongation in excess of 30%.
and their countermeasures which were to be
considered in connection with mooring opera- Examination of the parted rope tail revealed
tions. Among the items dealt with in the risk the following:
assessments were: Fatigue, lack of compe-
tency, running of wires, rotating machinery, - The rope tail burst as a result of over-
manual handling and poor communication. load. Most cords showed signs of
breaking due to overload (figure 9).
As per company procedures, mooring lines
were used for a maximum of 18 months after - The breaking strength of the rope may
which they were replaced. The parted mooring have been reduced by as much as

Page 15 of 19
30% due to wear (chafing). Many - The indicator string was broken and
strands and cords showed general fragmented along the full length of the
signs of wear and chafing, especially rope, indicating that at some point in
around the location of the break (figure time the rope had been subjected to
10). elongation in excess of 30%. In its
original, undamaged condition this
- While the use of grease on ropes in it- type of rope can withstand elongation
self probably did not reduce the of approximately 50% before breaking.
strength, the grease did make it diffi- It was not possible to establish wheth-
cult to establish the condition of the er the elongation happened just prior
mooring ropes. to the rope parting or on an earlier oc-
casion.

SOME STRANDS SHOW


SIGNS OF BREAKING DUE TO
WEAR. BROKEN STRANDS HAVE VARYING
LENGTH. FIBRES SHOW SIGNS OF
BREAKING DUE TO OVERLOAD.

Figure 9: Details of the parted rope end


Source: DMAIB

Page 16 of 19
BROKEN OUTER STRANDS AND SIGNS OF INTERNAL WEAR: SOME
FIBRES. SEVERE ABRASIONS FIBRES/YARNS WERE MELTED OR
PROBABLY RESULT OF CHAFING. APPEAR FLUFFY.

Figure10: Details of parted rope. Both pictures show discolouration from grease
Source: DMAIB

4. ANALYSIS
The accident occurred when a crewmember - A combination of both.
passed beneath a mooring line just as it
broke. In analysing the accident, focus will be - Also contributing to the parting of the
on two main items; the parting of the rope and rope was the tide, the cargo discharge
the general mooring operation and the proce- from the forward tanks and the inex-
dures leading up to the occurrence. pedient short lead and steep angle of
the spring line.
4.1 Parting of the mooring line
It was established that the rope end parted as
4.2 Mooring arrangement and
a result of overload and that the winch brake
did not release before the rope broke. The operations
possible explanations for this are: When analyzing the accidental events on
TORM REPUBLICAN, it can in hindsight be
- The brake setting may have deviated argued that the crewmembers should have
from the expected. The brake holding recognized the danger of passing underneath
power of the winch was tested and a mooring line under tension. The question of
adjusted using an uncalibrated why they chose to pass the mooring line must
instrument. be understood with the crewmembers
viewpoint in mind.
- The breaking strength of the rope was
reduced due to abrasions from chafing On the day of the accident, they had the task
and a previous elongation which had of doing an hourly round to inspect and tend
caused permanent deformation. to the moorings, and the job of moving a paint
drum forward. In an optimization process
these two tasks were not seperated and the

Page 17 of 19
tasks were completed in what was thought of rested and what they should do if they do not
as a meaningful and low risk manner. They feel up for the task?
could have chosen an alternative route from
the deck store to the paint store which would Snap back zones might offer some valuable
not bring them close to the line, but then they assistance in establishing safe and unsafe
needed to go back to tend to the mooring areas on deck. However, unless a vessel has
lines. As the deck hands were handling a very fixed system of mooring, for instance
mooring lines on a daily basis, it was not ships repeatedly calling at the same ports all
considered dangerous to be near them. the time, the establishment and marking of
Further, the mooring rope spanned from one possible snap back zones can easily lead to
side of the ship to the other offering little room more confusion than clarification. Another
for the crew to pass them without being in a problem with marking unsafe areas is the risk
snap back zone depending on where the rope that all other areas are then considered safe,
would break. which is not necessarily the case. When
mooring lines break, it is not possible to pre-
The shipboard manual and risk assessments dict exactly which way they will travel and thus
did list a number of factors and risks to con- no area near moorings can be considered
sider in connection with mooring operations, completely safe.
but the task of tending and checking moorings
was not dealt with in detail. For instance, nei- Another factor that may contribute to this type
ther the manual nor the risk assessments of accident is the rather strict mooring re-
suggest how to tend to moorings without posi- quirements and guidelines set by terminals.
tioning oneself in a dangerous situation or ar- This could create a tendency to weigh compli-
ea. A number of normative terms are used, ance higher than safety issues when selecting
such as always stand well clear of a mooring the mooring setup. In this instance the re-
wire under load, proper and correct mainte- quirement from the terminal was to deploy six
nance and good, seamanlike line tending. mooring lines at each end. This may have re-
The practical use of such terms is probably sulted in the decision to use the two forward
limited in an everyday working situation. spring lines despite the fact that it was known
they would have short leads and steep angles.
Common to many such procedures is that, While, on the one hand, the ports require-
although taken individually they offer sound ments and guidelines can be both reasonable
advice, procedures cannot cover every possi- and helpful, on the other hand, they could also
ble situation and are often contradictory, for restrict the master and crew in their decision
example, the combination of crewmembers making. One example is the prohibition of us-
being told to a) Always stay clear of lines un- ing constant tension winches which is wide-
der tension and b) Tend to all mooring lines at spread in oil terminals. Although not neces-
least once an hour. sarily the solution to all mooring problems,
constant tension winches may have been able
The other identified hazards listed in the risk to prevent some accidents in the past. These
assessments such as fatigue, lack of compe- are general issues and not particular to this
tence, poor communication etc. are real haz- accident.
ards to be dealt with. However, the control
measures to be implemented do not neces-
sarily address the underlying problems. For
example, in the risk assessment the control
measure to counter fatigue is: Officers to en-
sure that they are as well rested as possible
prior to port operations. Chief Officer to en-
sure that crew members are likewise rested. 4
Issues that are not addressed in detail are
how the crew should ensure that they are well

4
Quote from Risk Assessment MEG3 Effective
Mooring

Page 18 of 19
5. CONCLUSIONS
The accident on TORM REPUBLICAN Mooring arrangements are sometimes
occurred as a result of multiple coinciding designed in such a way that they become
factors:The layout of terminal/jetty vs ship size inherently dangerous, which will challenge the
and layout, a mooring line which had a way crews operate despite the efforts made to
reduced breaking strength, and the develop safe mooring practices. Great forces
unfortunate coincidence that the rope parted are present: Winches, mooring lines and wires
just as the crewmembers were passing under tension, people physically operating
beneath while doing normal maintenence very close to these forces with limited visibility,
work. time constraints and very little room to
operate. Because of the complexity of
Common to many mooring accidents is that mooring arrangements and operations and
they happen under normal circumstances and due to the designs that are sometimes
are not exclusively due to some extraordinary inherently dangerous, it is difficult for the
outside influence or human action or crewmembers to predict where the safe areas
omission. Mooring operations are routine jobs are, if there are indeed any safe areas. The
which are carried out by the crew on a regular design of the mooring arrangements makes it
basis and are therefore not considered to very difficult for crews to operate safely as
expose them to an immediate hazard. Since they have no other option than to be
all work contains an element of risk, it will physically very close to the equipment, thus
always be carried out as a result of a repeatedly putting themselves in danger.
negotiation of two different goals: Getting the
job done, and being safe. Understanding this
negotiation is essential for creating safety.

6. PREVENTIVE MEASURES
TAKEN
Following the accident the company carried
out an internal investigation. Among the pre-
ventive measures taken are:

- A detailed Safety Flash and safe - Ships mooring winch brakes to be re-
mooring guidelines were sent to all tested to check if settings are correct.
fleet vessels.
- Incident findings to be shared with en-
- On-board debriefing on safety proce- tire fleet.
dures and awareness carried out by
Safety superintendent and Head of - Safe mooring procedures in QMS to
SQE. be amended to highlight risks associ-
ated with short mooring lines, unsuita-
- The vessel was to conduct an extraor- bly placed bollards and movement of
dinary safety meeting regarding the in- vessel causing chafing of mooring
cident, with emphasis on mooring pro- lines.
cedures and safety.

- A follow-up extraordinary internal ISM


audit to be carried out on the vessel to
review safety procedures and aware-
ness.

Page 19 of 19

Das könnte Ihnen auch gefallen