Daily Activity Report

BLCP Outage 2017 Unit#1 Shutdown Project


Date of Daily Activty Report : 13/11/2017
08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00 18:00-19:00 19:00-20:00
Weather Report C S S S S S S S C C C
Remarks: Sunny : S Clouded : C Rainy :R Heavy Rains : HR

Item Last day Item Today Item Next day

Piping Activity
1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint 1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint 1 Continues tube RH fit up & weld inside boiler (LHS top) 12 joint

2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint 2 Continues Tube Instaiiation fit up and weld (RHS top) 12 joint
3 Continues tube RH fit up & weld inside boiler (Front top) 12 joint. 3 Continues tube RH fit up & weld inside boiler (Front top) 12 joint. 3 Continues tube RH fit up & weld inside boiler (Front top) 12 joint.
4 Continues machine beveling tube RHS/LHS & Front side top. 4 Continues machine beveling tube RHS/LHS & Front side top. 4 Continues machine beveling tube RHS/LHS & Front side top.
(And outside Beveling LHS bottom for preparation fit up gride support.) (And outside Beveling LHS/RHS bottom for preparation fit up gride support.) (And outside Beveling LHS/RHS bottom for preparation fit up gride support.)
5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top) 5 Continues spare part tube laydown area & Stock tube (for fit up Tube RH LHS top)
6 Continues First fit up gride support LHS No.A06-14700-1101A (68 - 71) & weld. 4 6 Continues fit up gride support LHS bottom & weld. 4 joint 6 Continues fit up gride support LHS bottom & weld. 4 joint
4 Joint

Item Position Day Night Today Piping Activity Photo


MANPOWER
1 Site Engineer 1 0 1
2 QA Engineer 2 1 3
3 Safety 2 1 3
4 QA,QC Superviser 2 0 2
5 Superviser 5 3 8
6 Admin Staff 1 0 1
7 Welder 13 7 20
8 Fitter A,B 30 11 41
9 Electricain 1 2 3
10 Fire Watch 5 2 7
11 Store/General 3 0 3
12 Rigger 6 2 8
71 29 100
Piping Activity Photo
Total (Man-Day)
The TJEL manpower combine foe SPC Sub-Contact

Note : Progress Erection Top


No. Description Fit up Weld RT Acc
1 RHS top (145 joints) 100 100 93 92
2 LHS top (145 joints) 102 102 92 80
3 Front side (297 joints) 26 26 19 18

Total 228 228 204 190

Note : Progress Erection Bottom


No. Description Fit up Weld RT Acc
1 RHS bottom (145 joints) 0 0 0 0
2 LHS bottom (145 joints) 4 4 4 2
3 Front side bottom (297 joints) 0 0 0 0

Total 4 4 4 2