Bill of Quantities: Group - A, Civil Works (Structural Works including Tank), Group - B, Civil Works (Pre - Engineered Steel

Building).

Item Group Item Description Unit Quantity


No Code
1 A N/A Erection and maintenance of site office and removal the same after completion of work in accordance with the LS 1.00
conditions of contract. In addition to the office required for his own use, the Contractor shall provide and maintain
furnished field office for the use of the Engineer and his staff. The field office is to have a concrete floor, adequate
foundation, brick walls, false ceiling of hard board with seasoned Garjan wood frame and painted, and all windows
are to be glazed and provided with steel grill. Outside and inside wall surface are to be painted on plaster
acceptable to the Engineer. The field office shall be maintained in a secure and watertight condition by the
Contractor until the completion of the contract and shall be provided with electricity, running water and sewerage.
All doors shall be fitted with approved locks and windows shall be provided with screen/blinds. Before construction
the Contractor shall submit plans and drawings showing proposed details and location for the field office, including
foundations, access roads, shades, layout of electrical and water supply and hard standings thereto for the
approval of the engineer. The Engineer may require revision of the plans prior to giving approval for construction.
The Contractor shall also submit details proposed furniture, fittings and other items of equipment and plant to the
engineer for approval. These items shall be of the standard quality suitable for site. The office, complete with
furnishings, fittings, access roads and hard standings shall be ready for occupation by the Engineer within 28 days
of the date when the Contractor first occupies the site. The Contractor will provide day and night guards and a tea
boy for the field office. At the end of the project all materials, equipment and plant, furniture, fittings recovered
from dismantling the office and removing access road will be the property of the Contractor. No interim payment
shall be certified unless Engineer's office with required facilities are constructed and accepted by the Engineer.
(This is a time related item. Proportionate payment for this item shall be made distributing in each bill on the basis
of percentage progress of the whole works under contract) Engineers site office of minimum 15 sqm plinth area
with providing furniture, first aid-box, safety helmet, level / theodolite, consumables, stationeries etc.
2 A N/A Providing and maintenance window type 1800 BTU AC (Air-Cooler) for Engineers office and remove after Each 1.00
completion of contract.
3 A N/A Providing and maintenance one project profile signboards of the size not exceeding 1 m x 2 m, to be placed at a Sqm 2.00
suitable place of the site including submission of proposals for the materials of the signboards and text layout to
the Engineer for approval which will be positioned as directed by the Engineer and removing the same on
completion of the Works or as instructed by the Engineer.
4 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local sqm 1088.67
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under the
contract. Layout and marking for earthwork in excavation in foundation accepted by the Engineer. [Plinth area of
the structure shall be considered for measurement]
5 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 1311.99
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineers approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in very
stiff (hard) clayey soil/ rubbish etc.
6 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 349.49
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches (1.5-2.00) m depth and maximum 10 m lead: in very
stiff (hard) clayey soil/ rubbish etc.
7 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 278.5
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineers approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches (2.0-2.50) m depth and maximum 10 m lead: in very
stiff (hard) clayey soil/ rubbish etc.
8 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 278.5
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches (2.5-3.00) m depth and maximum 10 m lead: in very
stiff (hard) clayey soil/ rubbish etc.
9 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 278.5
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches (3-3.50) m depth and maximum 10 m lead: in very stiff
(hard) clayey soil/ rubbish etc.
10 A N/A Earth work in excavation in all kinds of soil for foundation trenches including. layout, providing center lines, local cum 278.5
bench-mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk
powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning
the excavated earth at a safe distance out of the area enclosed by the layout etc. all complete and accepted by the
Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval.
However, Engineers approval shall not relieve the contractor of his responsibilities and obligations under the
contract. i) Earthwork in excavation in foundation trenches (3.5-4.0) m depth and maximum 10 m lead: in very stiff
(hard) clayey soil/ rubbish etc.
11 A N/A Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150mm layers including leveling, cum 1165
watering and compaction to achieve minimum dry density of 90% with optimum moisture content (Modified
proctor test) by ramming each layer up to finished level as per design supplied by the design office only etc. all
complete and accepted by the Engineer.
12 A N/A One layer of brick flat soling in foundation or in floor with first class or picked jhama bricks including preparation sqm 1206.3
of bed and filling the interstices with local sand, leveling etc. complete and accepted by the Engineer
13 A N/A Earth filling in foundation trenches and plinth in 150 mm layer with earth available within 90 m of the building site cum 68.16
to achieve minimum dry density of 90% with optimum moisture content (Modified proctor test) including carrying
watering, leveling, dressing and compacting to a specified percentage each layer up to finished level etc. all
complete and accepted by the Engineer.
14 A N/A Boring/drilling for cast in situ pile up to the required depth and diameter with minimum 6 m long temporary steel Rm 226.67
casing, true to vertical, providing bentonite slurry and maintaining water level in the hole, washing the hole for at
least 30 minutes, clean the bore-hole and make the bore- hole ready for placing steel cage and concreting including
hire charge of rig set with winch machine, tripod stand, trimie pipe, cost of fuel, lubricant, mobilization,
demobilization, maintenance, spares, stand-byes, insurance coverage, water, electricity and other charges all
compete approved and accepted by the Engineer. Before commencing boring operation Contractor shall submit
the method statement of cast-in-situ pile work including sequence of boring and casting, disposal of spoils, test
result of materials to the Engineer for approval. However, Engineer's approval shall not relieve the Contractor of
his responsibilities and obligations under contract.450mm dia.
15 A N/A Removing of spoils / mud accumulated during boring for cast in situ pile by wash boring from working site to a safe cum 36.12
distance by contractors own arrangement i.e. with container set in truck or on cart including loading, unloading
everything complete as per standard practice. (Quantity should be given three times of solid volume of boring)
16 A N/A Providing and making point welding at contact point of the spiral binders at reasonable intervals with the main Point 552.00
reinforcements by electric arc welding for construction of cast in situ bored pile carefully with highly oxidized
electrodes making the points prominent and accepted by the Engineer (rate is inclusive of all materials labour,
tools and plants, electricity and all equipment).
17 A N/A Cast in situ pile with reinforced cement concrete works with minimum cement content relates to mix ratio 1 : 1.5 cum 23.81
: 3 having minimum f'cr = 26 Mpa, and satisfying a specified compressive strength f'c = 21 Mpa at 28 days on
standard cylinders as per standard practice of Code ACI/BNBC/ASTM & cement conforming to BDS EN-197-1- CEM
-1 ( 52.5 N) / ASTM-C 150 Type ? I, best quality coarse sand [Sylhet sand or coarse sand of equivalent F.M.2.2], 20
mm down well graded crushed stone chips conforming to ASTM C-33, including breaking chips, screening through
proper sieves, making, placing re-bar cage in position, placing and removing tri-pod as per requirement, pouring
the concrete in bore-hole with the help of a trimie pipe, maintaining the trimie pipe immersed in concrete by at
least 1 meter throughout the period of concreting, maintaining required slump, etc. mixing the aggregates with
standard mixer machine with hoper, casting in forms, all complete including water, electricity, testing of materials
and concrete etc and other charges as per design, drawing etc all complete approved and accepted by the
Engineer.(Rate is excluding the cost of reinforcement and its fabrication, binding, welding and placing)
18 A N/A Labour for breaking head of hardened cast in situ bored pile/pre-cast pile up to a required length by any means cum 1.83
but without damaging the rest and removing the dismantled materials such as concrete to a safe distance including
scraps and cleaning concrete from steel/M.S. rods, straightening and bending of pile bars, preparation and making
platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and
dressing the situ and clearing the bed etc. complete in all respects and accepted by the Engineer.
19 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 270.51
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone
chips conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms,
compacting by vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges
of materials and cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of
admixture in the mix to be fixed by mix design, mix design test done by contractor). Including PVC water stopper
in 250mm wide horizontal construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber.
Measurement: Casted Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment:
Bill will be provided in total hardened concrete volume unit. A. Footing/pile cap a) Concrete
20 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 210.72
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone
chips conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms,
compacting by vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges
of materials and cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of
admixture in the mix to be fixed by mix design, mix design test done by contractor). Including PVC water stopper
in 250mm wide horizontal construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber.
Measurement: Casted Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment:
Bill will be provided in total hardened concrete volume unit. A. Footing/pile cap b) Formwork/shuttering, prop and
necessary supports etc. (steel)
21 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 278.21
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone
chips conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms,
compacting by vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges
of materials and cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of
admixture in the mix to be fixed by mix design, mix design test done by contractor). Including PVC water stopper
in 250mm wide horizontal construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber.
Measurement: Casted Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment:
Bill will be provided in total hardened concrete volume unit. B. Padestals, column, column capitals, lift walls and
walls i) Ground floor a) Concrete.
22 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 1592.46
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone
chips conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms,
compacting by vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges
of materials and cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of
admixture in the mix to be fixed by mix design, mix design test done by contractor). Including PVC water stopper
in 250mm wide horizontal construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber.
Measurement: Casted Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment:
Bill will be provided in total hardened concrete volume unit. B. Padestals, column, column capitals, lift walls and
walls i) Ground floor b) Formwork/shuttering, prop and necessary supports etc. (steel).
23 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 49.13
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment: Bill will be provided in
total hardened concrete volume unit. C) Foundation beam a) Concrete.
24 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 327.58
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done).Mode of payment: Bill will be provided in
total hardened concrete volume unit. C)Foundation beam b)Formwork/shuttering, prop and necessary supports etc.
(steel)
25 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 82.77
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit. Floor slab(Plinth Level) a) Concrete
26 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 22.77
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit. Floor slab(Plinth Level) b) Formwork/shuttering, prop and necessary supports
etc. (steel)
27 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 74.91
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit. Floor and roof slab : Ground Floor a) Concrete
28 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 45.89
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit. Floor and roof slab : Ground Floor b) Formwork/shuttering, prop and necessary
supports etc. (steel)
29 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum cum 2.76
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit.1st Floor a) Concrete
30 A N/A Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.25:2.5 having minimum sqm 29.78
f'cr=40 Mpa, and satisfying a specified compressive strength f'c = 32 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI/BNBC/ASTM & Cement conforming to BDS EN-197-1-CEM -1 ( 52.5 N) / ASTM-C 150
Type ? I, with approved high range admixture, plasticizer or else (complying specific type under ASTM-C 494), best
quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.2], 20 mm down well graded crushed stone chips
conforming to ASTM C-33, W/C ratio not more than 0.42, Slump 50-60mm, providing casting in forms, compacting by
vibrator machine and curing at least for 28 days, including cost of water, electricity, testing charges of materials and
cylinders, other charges etc. all complete approved and accepted by the ENGINEER.(Dose of admixture in the mix to
be fixed by mix design, mix design test done by contractor). Including PVC water stopper in 250mm wide horizontal
construction joint of RCC basement slab / wall/ reserviour with 9mm thick PVC rubber. Measurement: Casted
Concrete volume will be measured (Deduction of rebar will not be done). Mode of payment: Bill will be provided in
total hardened concrete volume unit. 1st Floor b) Formwork/shuttering, prop and necessary supports etc. (steel)
31 A N/A Brick works of width one brick or one and a half brick length with first class bricks in cement sand (F.M. 1.2) mortar Cum 98.93
(1:6) in superstructure including raking out joints, filling the interstices with mortar, cleaning and soaking the bricks
at least for 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete
(measurement to given as 250 mm width for one brick length and 375 mm for one brick and a half brick length) and
accepted by the Engineer.(Cement: CEM-II/A-M). i) Ground floor
32 A N/A Brick works of width one brick or one and a half brick length with first class bricks in cement sand (F.M. 1.2) mortar Cum 45.95
(1:6) in superstructure including raking out joints, filling the interstices with mortar, cleaning and soaking the bricks
at least for 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete
(measurement to given as 250 mm width for one brick length and 375 mm for one brick and a half brick length) and
accepted by the Engineer.(Cement: CEM-II/A-M). 1St Floor
33 A N/A 125 mm brick works with first class bricks in cement sand (F.M. 1.2) mortar (1:4) and making bond with connected sqm 318.02
walls including necessary scaffolding, raking out joints, cleaning and soaking the bricks for at least 24 hours before
use and washing of sand curing at least for 7 days in all floors including cost of water, electricity and other charges
etc. all complete and accepted by the Engineer. (Cement: CEM-II/A-M) In Ground floor.
34 A N/A 125 mm brick works with first class bricks in cement sand (F.M. 1.2) mortar (1:4) and making bond with connected sqm 154.33
walls including necessary scaffolding, raking out joints, cleaning and soaking the bricks for at least 24 hours before
use and washing of sand curing at least for 7 days in all floors including cost of water, electricity and other charges
etc. all complete and accepted by the Engineer. (Cement: CEM-II/A-M) 1St Floor
35 A N/A 125 mm brick works with first class bricks in cement sand (F.M. 1.2) mortar (1:4) and making bond with connected sqm 5.00
walls including necessary scaffolding, raking out joints, cleaning and soaking the bricks for at least 24 hours before
use and washing of sand curing at least for 7 days in all floors including cost of water, electricity and other charges
etc. all complete and accepted by the Engineer. (Cement: CEM-II/A-M) 2nd Floor
36 A N/A Providing 125 mm thick (Partition walls) brick work in superstructure brick work (1:4) in cement sand (F.M. 1.2) mortar sqm 21.95
with 10 hole machine made ceramic bricks of approved size having uniform colour, carefully laid in cement mortar
and depth joints true to vertical and horizontal lines including. racking out joints, filling the interstices with same
mortar, making bond with connected walls, cleaning, soaking brick at least 24 hours and washing of sand, curing 7
days in all floors, including cost of water, electricity and other charges accepted by the Engineer. (Cement:CEM-II/A-
M). In ground floor
37 A N/A Providing 125 mm thick (Partition walls) brick work in superstructure brick work (1:4) in cement sand (F.M. 1.2) mortar Sqm 21.95
with 10 hole machine made ceramic bricks of approved size having uniform colour, carefully laid in cement mortar
and depth joints true to vertical and horizontal lines including. racking out joints, filling the interstices with same
mortar, making bond with connected walls, cleaning, soaking brick at least 24 hours and washing of sand, curing 7
days in all floors, including cost of water, electricity and other charges accepted by the Engineer. (Cement:CEM-II/A-
M). In 1St Floor
38 A N/A Rule pointing to brick wall with cement sand (F.M. 1.2) mortar (1:2) with fresh cement and raking out the joints, Sqm 21.95
scaffolding, curing at least for 7 days, cost of water, electricity and other charges etc. all complete in all respect as per
drawing and accepted by the Engineer. (Cement: CEM-II/A-M).Ground floor.
39 A N/A Rule pointing to brick wall with cement sand (F.M. 1.2) mortar (1:2) with fresh cement and raking out the joints, Sqm 21.95
scaffolding, curing at least for 7 days, cost of water, electricity and other charges etc. all complete in all respect as per
drawing and accepted by the Engineer. (Cement: CEM-II/A-M).1St Floor
40 A N/A Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to wall both inner-and outer surface, sqm 608.94
finishing the corner and edges including washing of sand cleaning the surface, scaffolding and curing at least for 7
days, cost of water, electricity and other charges etc. all complete in all respect as per drawing and accepted by the
Engineer. (Cement: CEM-II/A-M). Ground Floor.
41 A N/A Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to wall both inner-and outer surface, sqm 459.38
finishing the corner and edges including washing of sand cleaning the surface, scaffolding and curing at least for 7
days, cost of water, electricity and other charges etc. all complete in all respect as per drawing and accepted by the
Engineer. (Cement: CEM-II/A-M). 1St Floor
42 A N/A Supplying, fitting and fixing of ceiling with 12 mm thick melamine board laminated by mechanical hot press with a Sqm 69.24
milk white PVC membrane in aluminum frame suspended from ceiling.
43 A N/A Supplying, fitting and fixing of 9 mm thick perforated gypsum board false ceiling with aluminum T bar frame in natural sqm 355.02
anodized frame at 600 mm x 600 mm grid suspended from ceiling by 12 SWG double ply G.I. Wire
44 A N/A Supplying, fitting and fixing of door frame for single leaf in all floors with 38 x 38 x 6 mm M.S. angle, fixing 130 mm rm 9.92
long 6 Nos. of iron clamps of same size (with one end bifurcated) with the vertical members of the frame, fixing the
frame in wall with cement concrete (1:2:4), mending good the damages, fixing 4 Nos. of 100 mm size iron hinges with
the vertical members of the frame all complete including cutting, sizing, welding, fabricating, carriage from workshop
to site including local carriage, curing etc. as per plan and drawing etc. all complete and accepted by the Engineer.
(Running meter of the doorframe will be considered towards measurement).
45 A N/A Supplying, fitting and fixing 36 mm thick and having density 400 kg/cum solid particle board single leaf flush door for sqm 3.20
all floors for internal use made of well matured mechanical seasoned Rubber (Malaysian timber) or other approved
wooden frame having finished size 35 x 50 mm around upon which 1.2 mm thick veneer (total two Nos. of veneers
one of 0.7 mm horizontally made of gorjon and another of 0.5 mm vertically made of Burma Teak or Champa or
Chapalish or Garjan wood) with necessary screws are pested on each side by mechanized process and provided with
best quality 4 Nos. 100 mm iron hinges, 2 Nos. best quality 12 mm iron dia 300 mm and 225 mm long iron tower and
socket bolts, 2 (two) Nos. heavy type nickel plated handles, hinged cleats, buffer blocks etc. complete and accepted
by the Engineer. Garjon Veneered
46 A N/A Supplying, fitting and fixing 38mm thick RFL Cosmic Door shutter with frame as per E/C(Size2'-6''x6'10'' Nos 4.00
47 A N/A Supplying, fitting and fixing 38mm thick RFL Cosmic Door shutter with frame as per E/C(Size3'-0''x6'10'') each 2.00
48 A N/A Supplying, fitting and fixing country made GP(Gress Porcellanato) - glazed homogeneous floor tiles irrespective of sqm 177.8
color &/or design, with on 20mm thick cement sand (F.M. 1.2) mortar (1:4) base and raking out the joints with white
cement including cutting and laying the tiles in proper way and finishing with care etc. all complete and accepted by
the Engineer. (Cement: CEM-II/A-M) In floor Ground Floor. GP (homogeneous) 400 x 400 mm floor tiles
49 A N/A Supplying, fitting and fixing country made GP(Gress Porcellanato) - glazed homogeneous floor tiles irrespective of sqm 188.60
color &/or design, with on 20mm thick cement sand (F.M. 1.2) mortar (1:4) base and raking out the joints with white
cement including cutting and laying the tiles in proper way and finishing with care etc. all complete and accepted by
the Engineer. (Cement: CEM-II/A-M) In floor 1St Floor. GP (homogeneous) 400 x 400 mm floor tiles
50 A N/A Supplying, fitting and fixing country made glazed wall tiles ,irrespective of color &/or design, with on 20 mm thick Sqm 137.80
cement sand (F.M. 1.2) mortar (1:3) base and raking out the joints with repective joint filler & binder including cutting,
laying and hire charge of machine and finishing with care etc. including water, electricity and other charges complete
all respect accepted by the Engineer. (Cement: CEM-II/A-M) In Ground Floor. Wall tiles more 250x400mm in sizes or
equivalent
51 A N/A Supplying, fitting and fixing country made glazed wall tiles ,irrespective of color &/or design, with on 20 mm thick sqm 126.92
cement sand (F.M. 1.2) mortar (1:3) base and raking out the joints with repective joint filler & binder including cutting,
laying and hire charge of machine and finishing with care etc. including water, electricity and other charges complete
all respect accepted by the Engineer. (Cement: CEM-II/A-M) In 1St Floor. Wall tiles more 250x400mm in sizes or
equivalent
52 A N/A Painting to door and window frames and shutters in two coats with approved best quality and colour of synthetic sqm 60.00
enamel paint delivered from authorized local agent of the manufacturer in a sealed container, having highly water
resistant, high bondibilty, flexible, using specific brand thinner applied by brush/roller/spray over a coat of priming
elapsing time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and polishing with
sand paper and necessary tools, scaffolding, testing charges etc. all complete in all floors approved and accepted by
the Engineer.
53 A N/A On exterior surface applying as per manufacturer instructions 3 coat of weather coat of approved quality and colour sqm 436.32
delivered from authorized local agent of the manufacturer in a sealed container complete in all respect in all floors
and accepted by the Engineer.
54 A N/A Approved best quality and colour synthetic polyvinyl distemper delivered from authorized local agent of the sqm 528.31
manufacturer in a sealed container, applying to wall and ceiling in 2 coats over a coat of brand specified primer or
sealer elapsing specified time for drying/ recoating matt finish including cleaning and sand papering making the
surface free from loose and flaky materials, dirt, grease, wax, polish, scraping all chalked and scaled materials,
applying the paint by brush/roller and necessary scaffolding etc. all complete in all floors accepted by the Engineer.
55 A N/A French polishing to door and window frames and shutters three coats over a coat of priming including putty, cleaning sqm 8.40
finishing and polishing with sand paper etc. all complete in all floors accepted by the Engineer.
56 A N/A Supplying, fitting and fixing of Aluminum composite swing doors with fixed partition as per the U. S. Architectural sqm 16.80
Aluminum Manufacturer's Association (AAMA) standard specification having 1.5 mm thick wall frame (size101.60,
44.45 mm), 1.8 mm thick shutter side (size 54 mm, 46 mm ), 1 mm thick door glass bit (size 16.54 mm, 14. 49 mm),
1.8 mm thick closure section (size 101.54 mm, 42.93 mm), 1.5 thick closure cover (101.60 mm), 4 mm thick floor
bottom (size 101.60 mm, 12.70 mm), 1.8 mm thick shutter bottom (size 86.60 mm, 43.99 mm), 1.8 mm thick shutter
top (size 51 mm, 43.99 m) 2.3mm to 4.01mm thick handle (short) (size 101.60 mm, 38.10 mm, 25.40 mm), 1.5 mm
thick top and side (size 101.60 mm, 44.45 mm), 1.50 mm thick bottom (size 101.35 mm, 44.45 mm), 1.50 mm thick
bottom cover (44.32 mm, 19.61mm), 1.50 mm thick grouve cover size 83.21 mm, 16.00 mm), 0.99 mm thick fixed
glass protector (size 39.09 mm, 14.81 mm), 0.99 mm thick fixed glass protector bit (size 15.75 mm, 14.81 mm) section
of all aluminum members will be anodized to aluminum bronze/silver colour with a coat not less 15 microns in
thickness and density of 4 mg per square cm etc. keeping provision for 5mm of glass panes with cost including all
accessories like swing door clouser, swing door lock , swing door mohair, flush bolt , bolts and nuts including sealants,
labour charge for fitting , fixing by angles, screws, mohiar, washer, machinery, cost of fabrication, making the grooves,
mending good the damages, electricity etc. complete in all respect as per drawing and accepted by the Enginee. S.S
colour
57 A N/A Supplying, fitting and fixing Rim/ round door lock approved and accepted by the Engineer. nos 2.00
58 A N/A Supplying, fitting and fixing best quality heavy type 19 mm dia and to 300 mm long brass hasp bolt including cutting nos 3.00
grooves in door shutter and frames, screws etc. all complete approved and accepted by the Engineer.
59 A N/A Supplying, fitting and fixing of Aluminum sliding window as per the U.S. Architectural Aluminum Manufacturer's sqm 32.62
Association (AAMA) standard specification having 1.2 mm thick outer bottom (size 75.50 mm, 32mm), 1.2 mm thick
outer top (size 75.50 mm, 16.80 mm), 1.2 mm thick shutter top (size 33 mm.26.80, 22 mm), 1.2 mm thick shutter
bottom (size 60mm, 24.40 mm), 1.2 mm thick outer side (size 75.50 mm,19.90 mm), 1.2 mm thick sliding fixed side
(size 31 mm, 26 mm),1.2 mm thick shutter lock (size 49.20 mm 26.20 mm) and 1.2 mm thick inter lock (size 34.40 mm,
32.10 mm) sections all aluminum members (total weight kg/sqm) will be anodized to aluminum bronze/silver colour
with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories like
sliding door key lock, sliding door wheel, sliding door mohiar, sliding door neoprene, bolts and nuts including sealants,
keeping provision for fitting 5 mm thick glass including labour charge for fitting of accessories, making grooves and
mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer.
Size up to 1500mmx1400mm. S.S colour
60 A N/A Supplying, fitting and fixing window grills of any design made with 20 x 5 mm F.I. bar including fabricating, welding sqm 32.62
cost of electricity and tools and plants etc. complete for all floors accepted by the Engineer. (Total weight per sqm
should be min 12 kg. and add or deduct. @ Tk.136.00 for each kg. excess or less respectively).
61 A N/A Supplying, fitting and fixing 10mm glass outer Wall necessary screws etc. Frame will be 50x25mm outer frame fixed sqm 106.44
with floor /ceiling using SS screw, complete in all respect accepted by the Engineer.
62 A N/A Supplying, fitting and fixing 10mm thick clear tempered glass door including all accessories 1 set maintenance auto sqm 15.61
closed special quality 2 nos clamping device, 1 set locking device, top hinge and handle etc. complete in all respect as
per drawing and direction of the Engineer in Charge.
63 A N/A Supplying and providing Floor hardener paint of approved best quality and colour delivered from authorized local sqm 529.32
agent of the manufacturer in a sealed container, applying to wall in two coats over a coat of brand specified primer
or sealer elapsing specified time for drying or recoating including cleaning drying, making free from dirt, grease, wax,
removing all chalked and scaled materials, fungus, mending good the surface defects, sand papering the surface and
necessary scaffolding, spreading by brush/ roller/spray etc. all complete in all floors accepted by the Engineer.
64 A N/A Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall (1:4) with cement up sqm 1877.33
to 150 mm below ground level with neat cement finishing including washing of sand, finishing the edges and corners
and curing at least for 7 days, cost of water, electricity and other charges etc. all complete in all respect as per drawing
and accepted by the Engineer.(Cement: CEM-II/A-M) Ground floor.
65 A N/A Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to ceiling R.C.C. columns, beams, surface sqm 35.00
of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing the corners and edges including
washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of water, electricity and other
charges etc. all complete in all respect as per drawing and accepted by the Engineer.(Cement: CEM-II/A-M) Ground
floor.
66 A N/A Reinforcement: Supplying, fabrication, and fixing to details as per design : deformed bar reinforcement in concrete in kg 94512.97
accordance with BDS ISO 6935-2: 2009 under Ductility Class D only , including straightening and cleaning rust, if any,
bending and binding in position with supply of G.I. wires, splices (laps) etc. complete in all respects and accepted by
the Engineer ( Measurement shall be recorded only on Standard Mass per Unit length of Bars, while, dia of bars
exceeds its standard). 72.5-grade ribbed or deformed bar with minimum fy (ReH)= 500 MPa & ultimate strength(fu
or Rm) at least 575 Mpa, minimum elongation after fracture and total elongation at maximum force is 14% and 7%
respectively. Including Laps Measurement: Fabricated Rebar weight will be calculated excluding lapping, chair etc for
6mm ~ 32mm diameter rebar. Mode of payment: Bill will be provided in weight unit (Weight will be calculated by
multiplying standard mass per unit length and cross sectional area) i) Ground floor
67 A N/A Supplying and fitting fixing horizontal bracing in Palisading with split wooden ballah having an average diameter rm 60.00
not less than 150 mm with a minimum end diameter of 100 mm @ 450 mm including supply of iron nails, gazals etc.
complete approved and accepted by the Engineer.
68 A N/A Supplying wooden ballah having an average diameter not less than 150 mm (without barks) at one third distance rm 185.00
from larger end with a minimum end diameter of 100 mm for retaining purpose and driving to a depth as per design
and drawing by any method including all arrangement for staging, hoisting, carrying etc. complete and accepted by
the Engineer.
69 A N/A Labour charge for Cutting tree without making any damages to existing structure including tree root and return to each 10.00
any place within BUET campus
70 A N/A 38 mm thick artificial patent stone (1:2:4) flooring with cement, best quality coarse sand (50% quantity of Sylhet sand sqm 166.87
or coarse sand of equivalent F.M. 2.2 and 50% best local sand of FM 1.2) and 12 mm down well graded brick chips
including breaking chips, screening, laying the concrete in alternate panels, compacting and finishing the top with
neat cement and curing at least 7 days in all floors including cost of water, electricity and other charges etc. all
complete and accepted by the Engineer. (Cement: CEM-II/A-M) In ground floor.
72 A N/A Shifting of earth / rubbish (which will be treated as the properties of contractor after collection) from site to outside cum 50.00
of the BUET campus by any means including site improvement by leveling, watering and dressing etc all complete as
per direction of the engineer in charge. Measurement: Considered by measuring total compacted earth /rubbish
volume. Mode of payment: Volume unit. a) Rubbish
73 A N/A Shifting of earth / rubbish (which will be treated as the properties of contractor after collection) from site to outside cum 2775.47
of the BUET campus by any means including site improvement by leveling, watering and dressing etc all complete as
per direction of the engineer in charge. Measurement: Considered by measuring total compacted earth /rubbish
volume. Mode of payment: Volume unit. b) Earth
74 B N/A Pre-Engineered Steel building including doors, windows, grills, all panels, fittings and fixtures as per requirement of LS 1.00
Drawings (Sheet No. SS-00 to SS-31) and Specification (PS Clause 3.31, Section 8) and Drawings having same floor plan (complete
and facilities as given for Towing Tank, Office and Laboratory facilities (Section 9). The Contractor will have to submit as per
proposal with details credentials (experience and competence) of the steel fabricator with his tender. Prior to drawings :
execution, the Contractor shall submit details samples all items, test results, shop-drawings, working procedure for steel
approval from the Engineer. All materials and workmanship shall meet the stated requirements of the roofing
Specification/Drawings. The design detailing shall also meet the requirements of cyclonic wind. The cost shall be system
inclusive of preparing the detail shop-drawing, supply, installation and erection including transportation to site and with all
all other incidental expenses. The civil Works ( pedestal, brick walls, grade beam, floor including filling and base work, accessorie
all reinforcements as required in design, painting and finishing), sanitary and electrical works shall be the s)
responsibility of the Contractor and are catered for in the BoQ as separate item. The payment of these civil items shall
be made as per the Contractor's quoted rate for the relevant items. Note: The Tenderers are required to submit
detailed proposal including experience and competence of the proposed fabricator including quality specifications,
manufacturer's catalogue etc. for this item (steel fabricator's part only).