Beruflich Dokumente
Kultur Dokumente
Appid=1493&Progid=547
SIDDHARTHINSTITUTEOFENGG&TECHNOLOGY
CivilEngg.
PartA:InstitutionalInformation
1NameandAddressoftheInstitution
SIDDHARTHINSTITUTEOFENGINEERING&TECHNOLOGY
SiddharthNagar,NarayanavanamRoad,Puttur
Chittoor(Dt),AndhraPradesh,Pin:517583
Website:www.sietk.org
2NameandAddressofAffiliatingUniversity
JAWAHARLALNEHRUTECHNOLOGICALUNIVERSITY,ANANTAPUR
SaradhaNagar,Ananthapuramu,AndhraPradesh
Pin:515002
Website:jntua.ac.in
3YearofestablishmentoftheInstitution:
2001
4TypeoftheInstitution:
University Autonomous
DeemedUniversity Affiliated
GovernmentAided
5OwnershipStatus:
CentralGovernment Trust
StateGovernment Society
GovernmentAided Section25Company
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 1/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Selffinancing AnyOther(PleaseSpecify)
6OtherAcademicInstitutionsoftheTrust/Society/Companyetc.,ifany:
7Detailsofalltheprogramsbeingofferedbytheinstitutionunderconsideration:
Electronics & Communication Granted provisional accreditation for two years for the period(specify
4 2001 60 300 2013 2001 20132015
Engineering period)
8ProgramstobeconsideredforAccreditationvidethisapplication:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 2/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5 UnderGraduate Engineering&Technology MechanicalEngg.
9Totalnumberofemployeesintheinstitution:
Note
Fulltimeonrollwithprescribedpayscale.AnemployeeoncontractforaperiodofnotlessthantwoyearsANDdrawingconsolidatedsalarynotlessthanapplicablegrosssalaryshallonlybecountedasaregularemployee.
PrescribedpayscalesmeanspayscalesnotifiedbytheAICTE/CentralGovernment andimplementationasprescribedbytheStateGovernment.IncaseStateGovernmentprescribeslesserconsolidatedsalaryforaparticularcadrethen
samewillbeconsideredasreferencewhilecountingfacultyasaregularfaculty.
CAY CurrentAssessmentYear
CAYm1 CurrentAssessmentYearminus1
CAYm2 CurrentAssessmentYearminus2
A.Regular*Employees(FacultyandStaff):
FacultyinEngineering(Female) 39 46 33 36 26 33
FacultyinMaths,Science&Humanities(Male) 33 33 29 29 25 25
FacultyinMaths,Science&Humanities(FeMale) 23 23 19 19 15 15
Nonteachingstaff(Male) 63 63 73 73 90 99
Nonteachingstaff(FeMale) 14 14 16 16 15 17
B.Contractual*Employees(FacultyandStaff):
20142015 20132014 20122013
Items
MIN MAX MIN MAX MIN MAX
FacultyinEngineering(Male)
FacultyinEngineering(Female)
FacultyinMaths,Science&Humanities(Male)
FacultyinMaths,Science&Humanities(FeMale)
Nonteachingstaff(Male)
Nonteachingstaff(FeMale)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 3/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
10TotalnumberofEngineeringStudents:
EngineeringandTechnologyUG
Shift1 Shift2
EngineeringandTechnologyPG
Shift1 Shift2
Engineering and Technology
Shift1 Shift2
Polytechnic
Shift1 Shift2
MBA
Shift1 Shift2
MCA
Instructions
(Thedatamaybecategorizedintabularformseparatelyforundergraduate,postgraduateengineering,otherprogram,ifapplicable)Note:IncasetheInstitutionisrunningAICTEapprovedadditionalcoursessuchasMBA,MCAinthefirst
shift,engineeringcoursesinthesecondshift,PolytechnicinSecondshiftetc.,separatetableswiththerelevantheadingshallbeprepared.
PleasechecktheShiftfromtheabovechecklisttofillthedetails.ClickthebuttontocreatetableinwhichyouhavetofillthenumberofstudentsindifferentDisciplineandShifts.
EngineeringandTechnologyUGShift1
EngineeringandTechnologyPGShift1
Totalno.ofBoys 86 110 88
Totalno.ofGirls 48 61 61
EngineeringandTechnologyPolytechnicShift2
Totalno.ofGirls 33 36 26
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 4/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
EngineeringandTechnologyMBAShift1
Totalno.ofGirls 38 57 54
EngineeringandTechnologyMCAShift1
Totalno.ofBoys 55 76 89
Totalno.ofGirls 23 40 44
11VisionoftheInstitution:
Tobeoneamongthepremierinstitutionsofthecountryinproducingethicallystrongandtechnicallysoundengineersandmanagerstoservethenation.
12MissionoftheInstitution:
Tocreatesacredenvironmentforthestudentstoacquireknowledgethroughinnovativeandprofessionalapproachandutilizeitforthewelfareofthemankind.
13ContactInformationoftheHeadoftheInstitutionandNBAcoordinator,ifdesignated:
HeadoftheInstitution
Designation Principal
MobileNo. 9396932888
EmailID principal.f6@jntua.ac.in
NBACoordinator,IfDesignated
Name V.Viswanadha,M.Tech.,(Ph.D)
Designation AssociateProfessor
MobileNo. 9966984105
EmailID vissuvnl@gmail.com
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 5/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PARTB:CriteriaSummary
1 VISION,MISSIONANDPROGRAMEDUCATIONALOBJECTIVES 60 60.00
6 FACILITIESANDTECHNICALSUPPORT 80 80.00
7 CONTINUOUSIMPROVEMENT 50 50.00
8 FIRSTYEARACADEMICS 50 43.84
9 STUDENTSUPPORTSYSTEMS 50 50.00
PartB
1VISION,MISSIONANDPROGRAMEDUCATIONALOBJECTIVES(60) TotalMarks60.00
1.1StatetheVisionandMissionoftheDepartmentandInstitute(5) TotalMarks
InstituteMarks
(VisionstatementtypicallyindicatesaspirationsandMissionstatementstatesthebroadapproachtoachieveaspirations)
(HereInstituteVisionandMissionstatementshavebeenaskedtoensureconsistencywiththedepartmentVisionandMissionstatementstheassessmentoftheInstituteVisionandMissionwillbetakenupinCriterion10)
Tobeoneamongthepremierinstitutionsofthecountryinproducingethicallystrongandtechnicallysoundengineersandmanagersto
Visionoftheinstitute servethenation.
Tocreatesacredenvironmentforthestudentstoacquireknowledgethroughinnovativeandprofessionalapproachandutilizeitforthe
Missionoftheinstitute welfareofthemankind.
Throughtheexcellenceofitspeople,theDepartmentofCivilEngineeringwillberecognizedasaleaderofitsdisciplineina
VisionoftheDepartment
mannerthatexemplifiesthetraditionsoflearning,inventionandengagement.
M1:ThemissionoftheDepartmentofCivilEngineeringhasthreetenetsthatcenterontheprincipleofimprovinglivesand
livelihoods.M2:TocreateknowledgethroughresearchinthescienceandtechnologyofCivilEngineering.M3:Toshare
MissionoftheDepartment
knowledgethrougheducationalprogramsandthedisseminationofournewinventionsandtodeveloptheprofessional
potentialoffaculty,staffandstudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 6/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1.2StatetheProgramEducationalObjectives(PEOs)(5) TotalMarks
InstituteMarks
(StatethePEOs(3to5)ofprogramseekingaccreditation)
TheProgramEducationalObjectivesofthedepartmentofCivilEngineeringare:
PEO1:CivilEngineeringGraduatesunderstandtheorigin,workingprinciplesandoutcomesofCivilEngineeringandalliedprojectsfrompartstowhole,interms
oftechnology,economy,socialandenvironmentalaspects.
PEO2:GraduatestakeuphighereducationandR&DinCivilEngineeringandalliedareasofscienceandtechnologyforthebenefitofindustryandsociety.
PEO3:Graduatesutilizeformalandinformallearningopportunitiestomaintainandenhancetechnical,personalandprofessionalgrowth,communicate
effectively,exhibitprofessionalleadership,teamworkandethicalvalues.
1.3IndicatewheretheVision,MissionandPEOsarepublishedanddisseminatedamongstakeholders(10) TotalMarks
InstituteMarks
(Describewhere(websites,curriculam,postersetc.)theVision,MissionandPEOsarepublishedanddetailtheprocesswhichensuresawarenessamonginternalandexternalstakeholderswitheffectiveprocessimplementation)
(InternalstakeholdersmayincludeManagement,GoverningBoardMembers,faculty,supportstaff,studentsetc.andexternalstakeholdersmayincludeemployers,industry,alumni,fundingagencies,etc.)
Thevariousinternalstakeholdersare
Students
Management
MembersoftheGoverningBody
Faculty
Supportingstaffetc.,
Theexternalstakeholdersare
Parents
Alumni
University
Employers
Industry
Fundingagenciesetc.
Vision,MissionandPEOsarecommunicatedtothestakeholdersbythefollowingways:
Totheinternalstakeholders:
TheVision,MissionandObjectivesaredisplayedatallprominentplacesinthecampussuchasPrincipaloffice,Administrativeoffice,HODoffices,allnoticeboards,ExaminationSection,PlacementCell,Library,Laboratories,Canteen,Hostelsetc.,
Printedinallmanuals(institutionalacademiccalendar,labmanuals,labobservations,labrecords,coursefilesetc.)andprojectbooks.
Thestatementsaredisplayedintheinstitutewebsite(www.sietk.org/siddharth_civil.html)
Thesestatementsarealsocommunicatedthroughprospectus,newsletters,institutemagazines,souvenirs,bannersetc.
Totheexternalstakeholders:
Thestatementsarecommunicatedthroughtheprospectus,newsletters,institutemagazines,souvenirs,postersetc.
Thestatementsaredisplayedintheinstitutewebsite(www.sietk.org/siddharth_civil.html)
Communicatedthroughelectronicandprintmedia,andmeetings.
1.4StatetheprocessfordefiningtheVisionandMissionoftheDepartment,andPEOsoftheprogram(25) TotalMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 7/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1.4StatetheprocessfordefiningtheVisionandMissionoftheDepartment,andPEOsoftheprogram(25) TotalMarks
InstituteMarks
(ArticulatetheprocessfordefiningtheVisionandMissionofthedepartmentandPEOsoftheprogram)
ProcessofdefiningVisionandMissionoftheDepartment:
STEP1:Departmentcommittee(HODandseniorfaculties)collectstheinformationfromthestakeholdersregardingtheirdesiresandexpectationswhicharedireneedtothenationandsociety.
STEP2:Consideringtheaboveinformation,theroughdraftofVisionandMissionstatementshavebeenframedbythedepartmentcommitteeandthencirculatedamongthedepartmentfacultymembersforfurthersuggestions.
STEP3:TheVisionandMissionstatementsarefinalizedbythedepartmentcommitteeaftergettingapprovaloftheacademicadvisorycommittee.
ProcessofdefiningPEOsoftheprogram:
TheProgramEducationalObjectives(PEOs)areactuallythebroadstatementsoftheobjectivesforwhichtheProgramisbeingrun.Primarily,theseobjectivesshouldhelpinfulfillingthemissionofthedepartment.Secondly,thestudentswhoaregraduatingfromtheprogramareexpectedtoleadafruitfulandmeaningfullifeinthesocietyby
beingusefulinitsprogressivedevelopment.Thus,itisnecessarythattheseobjectivesshouldbeinconsonance,totheextentpossible,withthecurrentresearchscenariointherelevantfieldofengineeringandwiththeneedsoftherelevantindustry.Theresearchscenarioisjudgedbythefacultymembersthroughtheresearchpublications.
Theindustryneedsaregaugedthroughthefeedback,mostlyverbal,receivedintheTrainingandPlacementcellwheneverthecompaniescomeforcampusplacements.Inaddition,theindustryscenariohasaspecificrelationshipwiththeresearchhencefacultyiscompetenttoassesstheneedsofindustry.Moreover,thealumniwhohave
gonetotheindustryorhigherstudiesareabletoreflecttheobjectivesareadequate.
Fig1:THEFLOWCHARTOFPROCESSFORDEFININGTHEPEOs
1.5EstablishconsistencyofPEOswithMissionoftheDepartment(15) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 8/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(Generatea"MissionoftheDepartmentPEOsmatrix"withjustificationandrationaleofthemapping)
Note:M1,M2,..MnaredistinctelementsofMissionstatement.
Entercorrelationlevels1,2or3asdefinedbelow:
1:Slight(Low)2:Moderate(Medium)3:Substantial(High)Ifthereisnocorrelation,put
Note:InthisdocumentwhereverthetermProcesshasbeenuseditsmeaningisprocessformulation,notificationandimplementation.
PEO1:CivilEngineeringGraduatesunderstandtheorigin,
workingprinciplesandoutcomesofCivilEngineeringand
3 1
alliedprojectsfrompartstowhole,intermsoftechnology,
economy,socialandenvironmentalaspects.
PEO2:GraduatestakeuphighereducationandR&DinCivil
Engineeringandalliedareasofscienceandtechnologyforthe 1 3
benefitofindustryandsociety.
PEO3:Graduatesutilizeformalandinformallearning
opportunitiestomaintainandenhancetechnical,personaland
1 3
professionalgrowth,communicateeffectively,exhibit
professionalleadership,teamworkandethicalvalues.
Note:M1,M2andM3aredistinctelementsofDepartmentmissionstatement.
Correlationlevels1,2or3aredefinedas
1:Slight(Low)
2:Moderate(Medium)
3:Substantial(High)
2PROGRAMCURRICULUMANDTEACHINGLEARNINGPROCESSES(120) TotalMarks120.00
2.1ProgramCurriculum(20) TotalMarks
2.1.1StatetheprocessusedtoidentifyextentofcomplianceoftheUniversitycurriculumforattainingtheProgramOutcomesandProgramSpecificOutcomesasmentionedinAnnexureI.Alsomentiontheidentified
InstituteMarks
curriculargaps,ifany(10)
(Statetheprocessdetailsalsomentionidentifiedcurriculargaps).
Note:IncaseallPOsarebeingdemonstrablymetthroughUniversityCurriculumthen2.1.2willnotbeapplicableandtheweightageof2.1.1willbe20.
Theinstitutionadheresthesyllabusdesignedbytheaffiliatinguniversity(JNTUAnantapur).Asmandatedbytheuniversity,theinstitutionissupposedtodeliverspecifictopics/unitsofthesyllabuswithinthespecifictimeframessoastoconductmidterm(Internal)examsandexternalexamsaspertheacademicschedulegivenbythe
university.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 9/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
TheAcademicSchedulepublishedbytheUniversityformsthebasisforplanningandimplementationofthecurriculum.
Theinterest,strengthandexpertiseofthefacultyaretakenintotheaccountwhilechoosing/assigningthesubjectsby/tothefaculty,wellinbeforethecommencementofthesemester.
Afterallotmentofthesubjects,thefacultypreparestheImplementationPlan/LessonPlan,CourseMaterialandTutorialQuestions.
ThesuitabilityoftheImplementationPlanandtheCourseMaterialagainstthesyllabusisverifiedbyIQACmembers(seniorfacultyand/orHOD)beforethecommencementofthesemester.
Dependingonthenumberoftutorial/practicalhoursrequiredforeachcourse,eachdepartmentpreparesthetimetableforeffectiveimplementationofthecurriculum.
TheImplementationPlan,CourseMaterial,etc.arereviewed,revisedeveryyearandwhenevernecessary.
IfthereisanyrevisioninthecurriculumprescribedbytheuniversityorwhilepreparingtheCourseinformationsheet,facultywillperformtheanalysisandidentifythegapstoattainthecourseoutcomesandprogramoutcomes.
Basedonthegapsidentified,appropriateactivitieslikefieldtrip,workshops,miniprojects,assignments,classroomteaching,guestlectures,andlabexperimentsareplanned.
Thefollowingtrainingprogramsareoffered,bytheTraining&Placementcell,tohelpthestudentstofacecompetitiveexaminationsaswellasplacementsconfidently:
QuantitativeAptitude&LogicalReasoning
FunctionalEnglish
GroupDiscussions
Interviewskills
Computerlanguages
Structureofthecoursefile
S.No. CONTENT
1 ProgramEducationObjectives(PEOs)
2 ProgramOutcomes(POs)
3 ProgramSpecificOutcomes(PSOs)
4 Syllabuscopy
5 MappingofPOsandPSOs
6 Academiccalendar
7 Coursetimetable
8 Lecturenotes
9 CopiesofPPTslides,ifany
Questionpapersoftutorials,Unittests,InternalExaminations(IE),UniversityExaminationsand
10
Assignments
11 SchemeofevaluationofIEandadditionaltests
12 KeyofIEquestionpaper
13 TwosampleanswerscriptseachofIE,assignmentsandunittests
14 Attendanceregister(s)
15 Resultsanalysis(aspergivenproforma)
Summaryofassessmentofcourseoutcomesthrough
a)Contentdelivery
16
b)Examinations,tests,assignments,etc.
c)Studentsfeedback
Curriculum:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 10/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
B.TechIYEAR(R13)
S.No Coursecode Subject Th Tu/Drg/Lab Credits
1. 13A52101 CommunicativeEnglish 2 3
2. 13A56101 EngineeringPhysics 2 3
3. 13A51101 EngineeringChemistry 2 3
4. 13A54101 MathematicsI 3 1 5
5. 13A12101 ProgramminginC&DataStructures 3 1 5
6. 13A01101 EngineeringMechanics 3 1 5
7. 13A03101 EngineeringDrawing 1 5 5
8. 13A12102 ProgramminginC&DataStructuresLab 3 4
EngineeringPhysics&EngineeringChemistry
9. 13A99102 3 4
Lab
TotalCredits 45
Note:Th=TheoryTu=Tutorial,Drg=Drawing&Lab=Laboratory.
IIB.TechISemester(R13)
S.No. Coursecode Subject Theory Tu/Lab Credits
1. 13A54301 MathematicsII 3 1 3
2. 13A99301 Electrical&MechanicalTechnology 3 1 3
3. 13A01301 StrengthofMaterialsI 3 1 3
4. 13A01302 SurveyingI 3 1 3
5. 13A01303 FluidMechanics 3 1 3
6. 13A01304 BuildingMaterials&Construction 3 1 3
7. 13A01305 SurveyingLabI 3 2
8. 13A01306 StrengthofMaterialsLab 3 2
TotalCredits 22
IIB.TechIISemester(R13)
S.No. Coursecode Subject Theory Tu/Lab Credits
1. 13A54303 Probability&Statistics 3 1 3
2. 13A01401 StrengthofMaterialsII 3 1 3
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 11/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3. 13A01402 Hydraulics&HydraulicMachinery 3 1 3
4. 13A01403 EnvironmentalScience 3 1 3
5. 13A01404 StructuralAnalysisI 3 1 3
6. 13A01405 SurveyingII 3 1 3
7. 13A01406 FluidMechanics&HydraulicMachineryLab 3 2
8. 13A01407 SurveyingLabII 3 2
TotalCredits 22
IIIB.TechISemester(R09)
S.No. Coursecode Subject Theory Lab Credits
1. 9AHS401 ManagerialEconomics&FinancialAnalysis 4 4
Design&Drawingofreinforcedconcrete
2. 9A01501 4 4
structures
3. 9A01502 ConcreteTechnology 4 4
4. 9A01503 WaterresourcesEngineeringI 4 4
5. 9A01504 StructuralAnalysisII 4 4
6. 9A01505 EngineeringGeology 4 4
7. 9A01506 EngineeringGeologyLab 3 2
8. 9AHS601 AdvanceEnglishcommunicationSkillsLab 3 2
TotalCredits 28
IIIB.TechIISemester(R09)
1. 9A01601 DesignandDrawingofSteelStructures 4 4
2. 9A01602 GeotechnicalEngineeringI 4 4
3. 9A01603 EnvironmentalEngineeringI 4 4
4. 9A01604 WaterResourcesEngineeringII 4 4
5. 9A01605 Estimation,CostingandValuation 4 4
6. 9A01606 TransportationEngineering 4 4
7. 9A01607 GeotechnicalEngineeringLab 3 2
8. 9A01608 EnvironmentalEngineeringLab 3 2
TotalCredits 28
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 12/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
IVB.TechISemester(R09)
1. 9A01701 FiniteElementMethodsinCivilEngg. 4 4
2. 9A01702 BridgeEngineering 4 4
3. 9A01703 GeotechnicalEngineeringII 4 4
4. 9A01704 EnvironmentalEngineeringII 4 4
ElectiveI
9A01705
1.EarthquakeResistantDesign
5. 9A01706 4 4
2.AirPollution&Control
9A01707
3.Railways,DocksandHarborEngineering
ElectiveII
9A01708
1.WaterresourcesSystemPlanning&
Management
6. 4 4
9A01709 2.AdvancedStructuralAnalysis
3.ConstructionTechnologyandProject
Management
9A01710
7. 9A01711 CADLab 3 2
8. 9A01712 Concrete&HighwayMaterialsLab 3 2
TotalCredits 28
IVB.TechIISemester(R09)
S.No. Coursecode Subject Theory Lab Credits
1. 9A01801 AdvancedStructuralEngineering 4 4
2. 9A01802 DesignandDrawingofIrrigationStructures 4 4
ElectiveIII
9A01803 AdvancedFoundationEngineering
3. 4 4
9A01804 GroundImprovementTechniques
9A01805 RemoteSensing&GIS
ElectiveIV
9A01806
ExperimentalStressAnalysis
9A01807
4. Prestressedconcrete 4 4
9A01808
EnvironmentalImpact
AssessmentandManagement
5. 9A01809 Seminar 2 2
6. 9A01810 Project 10
TotalCredits 28
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 13/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
TotalCredits(R13regulation):180
TotalCredits(R09regulation):220
GapsIdentifiedinProgrammeCurriculumandCourse:
Theinstitutioninvitesrepresentativesoftheindustrytointeractwiththestudentsonaregularbasis.Requirementsoftheindustryareascertainedfromtherepresentativesoftheindustry,gapsareidentifiedandtheteaching&trainingstrategiesareformulatedaccordinglytofillthegaps.
Bycollectingfeedbacksfromthealumnistudents.
Thefacultyregularlyattendsforseminars,workshops,conferences,etc.organizedbyotherinstitutionsandresearchorganizations.Thathelpsthemtoidentifythetrendsinrespectiveareasandaccordinglyoperationalizethecurriculum.
i.)GapsinProgrammeCurriculum
S.No. IdentifiedGapsinProgramme
1 AutoCADD
2 PrinciplesofTownPlanning
3 ComputerProgrammingSkills(C++)
4 SoftSkills
5 QuantitativeAptitude
6 TechnicalDevelopments&CareerOpportunitiesTraining
DeliveryDetailsofGapsbasedonProgramme:
ResourcePerson Relevanceto
S.No. Gap Action YearSem %of
withdesignation POs,PSOs
Taken students
IIII, P.Jyothi
2 PrinciplesofTownPlanning GuestLecture 89 PO6
IVI Asst.ExecutiveEngineer
IIII, B.SreeramBabu,Chief
3 SoftSkills GuestLecture 94 PO10,PO12
IVI TrainingOfficer
ii.)GapsinCourse
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 14/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
S.No. Yearand CourseName GapsIdentified
Semester
1 CommunicativeEnglish AdvancedSkills,VerbalEnglish
2 EngineeringMechanics AnalysisofTruss
IYear
3 EnvironmentalStudies ISO14000standards
4 EngineeringDrawing AuxiliaryProjections
Studythestressstraincharacteristicsofmildsteelrod
5 III StrengthofMaterialsLab
usingUTM
Design&DrawingofReinforced
ConcreteStructures
Designofmultistoriedbuilding
7 IIII
RejuvenationofGroundWaterTableThroughRain
WaterResourcesEngineeringI
WaterHarvesting
2.1.2StatethedeliverydetailsofthecontentbeyondthesyllabusfortheattainmentofPOsandPSOs(10) InstituteMarks
(Providedetailsoftheadditionalcourse/learningmaterial/content/laboratoryexperiments/projectsetc.,arisingfromthegapsidentifiedin2.1.1inatabularformintheformatgivenbelow)
Note:PleasementionindetailwhethertheInstitutionhasgivensuchinputsandsuggestionstotheAffiliatingUniversityregardingcurriculargapsandpossibleadditionofnewcontent/addoncoursesinthecurriculum,tobridgethegapandtobetterattain
programoutcome(s).
20142015
Theory
1 Design&DrawingofSteelStructures:Designofoverheadtank 11/03/2015 B.MuraliKrishnaAsst.Prof. 85 PO3,PO6,PSO3
Classes
Theory
6 StructuralAnalysisI:Analysisoffixedarches 29/09/2014 N.KrishnaMurthyAsst.Prof. 92 PO2,PSO3
Classes
RejunevationofGroundWaterTableThroughRainwaterHarvestingin SriP.V.SubbaRao,M.Tech.,SuperintendingEngineerDesign&controlNTRTeluguGanga
8 Guestlecture 14/08/2014 90 PO3,PO6,PSO3
Chittoor.Dist.,A.P. ProjectTirupati
Design&DrawingofReinforcedConcreteStructures:Designofmultistoried Theory
9 22/07/2014 C.PrabhakarReddyAsst.Prof 95 PO3,PO5,PO12
building Classes
20132014
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 15/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3DStructure&DesigningusingSTAADPRO:NationallevelworkshoponTechnochamp2014ALCHERINGIIT
1 Workshop 12/03/2014 MandeepSingh,MahendraPalSinghIITGUWAHATI 80 PO3,PO5,PSO3
Guwahati
Theory
2 Design&DrawingofReinforcedConcreteStructures:Designofslabsinworkingstressmethod 21/02/2014 C.PrabhakarReddyAsst.Prof 85 PO2,PO3,PSO3
Classes
Theory
3 StrengthofMaterials:Elongationofbarsduetoownweight&elongationoftaperedsection 07/10/2013 K.P.VenugopalAsst.Prof 92 PO2
Classes
Theory
4 FiniteElementMethods:Analysisof3dimensionalproblemsinfiniteelementsanalysis 10/09/2013 B.MuraliKrishnaAsst.Prof 88 PO3,PO5,PSO3
Classes
Theory C.VenumadhavProf.&HODAudishankaracollege,
5 GreenBuildings 26/02/2013 90 PO2,PO6,PO7
Classes Gudur.
Theory
6 TrafficImpactStudies 22/07/2013 BalajiAssoc.ProfNBKR,VAKKADU 85 PO5,PO7,PO10
Classes
20122013
ConstructionTechnologyandProjectManagement:Cementand Mr.VasudevaMurthy,GCILUKFounder&MDofBuildBizzonlinePrivateltdToolsAcademyforcareer
1 Workshop 11/03/2013 97 PO5,PO6,PSO1
ConcreteTechnology excellence,Bengaluru
WREI:RejuvenationofGroundWaterTableThroughRainWater Guest
2 04/02/2013 P.V.SubbaRaoSuperintendingEngineer,Designs&QualityControl,NTRTeluguGangaProject,Tirupati 98 PO6,PO7
Harvesting lecture
Guest Dr.K.N.SatyanarayanaProfessor,BuildingTechnology&ConstructionmanagementDiv.,Dept.ofcivil
3 OpportunitiesinConstruction&InfrastructureinIndia 08/10/2012 100 PO5,PO6,PSO1
lecture engineeringIITMadras
Guest
4 AdvancesinFoundationEngineering 08/09/2012 SrinivasuluAsst.prof. 90 PO2,PO4,PSO1
lecture
Guest
5 AwarenessonGate,IES,PSUs 31/08/2012 P.JagadishDirector,JHAcademy 80 PO1,PO2,PO6
lecture
2.2TeachingLearningProcesses(100) TotalMarks
2.2.1DescribeprocessesfollowedtoimprovequalityofTeaching&Learning(25) InstituteMarks
(Processesmayincludeadherencetoacademiccalendarandimprovinginstructionmethodsusingpedagogicalinitiativessuchasrealworldexamples,collaborativelearning,qualityoflaboratoryexperiencewithregardtoconductingexperiments,
recordingobservations,analysisofdataetc.encouragingbrightstudents,assistingweakstudentsetc.Theimplementationdetailsandimpactanalysisneedtobedocumented)
Everyyear,theacademiccalendarisscheduledbytheJNTUA.Basedontheuniversitycalendar,theinstitutionpreparesitsownacademiccalendarandteachingplanandalsofollowsvariousinstructionalmethods.
i.Institutionalacademiccalendar
Theinstitutionfollowstheuniversitycalendar,whichconsistsofdetailssuchas(1)durationofinstruction(2)scheduleofinternalexaminations(3)scheduleofexternalexaminations(4)holidays.
ThescheduleofUnitTestsispreparedbytheinstitution,isappendedtotheAcademicCalendarissuedbytheUniversity.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 16/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Variousdepartmentalactivitiesareplannedtobeorganizedbytherespectivedepartments,areincludedintheAcademicCalendarwellinbeforecommunicatingtothestudents.
ii)TeachingPlan
Theteachingplanispreparedtakingintotheaccountofthefollowingaspects:
Incaseoftheorysubjects,thesyllabusisprescribedbytheuniversityandadditionaltopicstobediscussedbasedonthespecificrequirements.
Incaseofpracticalsubjects,thenumberofexperimentsisprescribedbytheuniversityandtheadditionalexperimentsanddesignexperimentsaretobeconductedbasedonthespecificrequirements.
Prescribedsyllabushastobecompletedbeforeconductingtheunit,InternalandExternalexaminations.
Thenumberofinstructionalandtutorialhourswhichisrequiredforcompletingthesyllabusofeachsubjectbasedonthepreviousexperienceofthefaculty.
DiverseAssignments,forencouragingbrightstudents,advancedtopicassignmentsareimposed,givingawardstotoppersineachclassduringannualcelebrations.
Awards&Rewards,basedontheperformance,toppersareappreciatedduringannualcelebrations.
Counseling,intheviewofthestudentcareer,counselorsguideandmotivatethemtowardstheirsuccess.
TheImplementationPlan,Coursematerial,Assignments,Counsellingrecords,Attendanceregistersetc.arereviewed/revisedregularlyandwhenevernecessary.
Forassistingtheweakstudents,remedialclassesareconducedbasedontheirperformanceininternalandexternalexaminations,specialclassesarealsoconductedtoenhancetheperformancebygivingmorepracticeonimportantconcepts.
ClassTimeTable
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 17/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
RemedialClassTimeTable
Classificationofbrightstudentsandweakstudentsaredoneaftercompletionof1st midtermexaminations.Thestudentswhosecuredlessthan50%oftotalmarksandthestudentswithbacklogsaregroupedasweakstudentsandtherestofthestudentsaregroupedasbrightstudents.Fortheweakstudents,remedialclassesareplanned
accordingly.Thedetailedscheduleisasgivenbelow.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 18/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
iii)LearningProcess:Theinstitutionencouragesthefacultytoinvolvethestudentsactivelyintheprocessoflearning.Followingsupportstructuresareavailableforthefacultytodevelopvariouslearningskillsamongthestudents:
InteractiveLearning:
Besidestraditionalclassroomswithablackboard,everydepartmentisequippedwithanEclassroomwithLCDprojectorandinternetconnectivity.
Facultyregularlyusespresentationsandvideosasteachingtoolsandencouragesinteractivelearningamongthestudents.
Respectivedepartmentsorganizeguestlecturesandseminarsregularly.
CollaborativeLearning:
Facultiesfacilitatediscussionsonimportantconceptswithintheclassroomtoencouragecombinedlearning.
Departmentalassociationsarehighlyactiveintheinstitution.
Theseassociationsregularlyorganizeseminars,discussionsandcompetitionstoencouragecollaborativelearningamongthestudents.
IndependentLearning
TheCentralLibraryhasavastcollectionofbooks,journals&projectreports,etc.
Alibraryhourismadecompulsoryforallthestudentstoencouragethestudentstolearnindependently.
Internetfacilityisavailabletothestudentstolearnontheirown.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 19/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Further,theassignmentsalsoencouragethestudentstolearnontheirown.
AssociationActivities:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 20/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
2.2.2QualityofinternalsemesterQuestionpapers,AssignmentsandEvaluation(20) InstituteMarks
(Mentiontheinitiatives,implementationdetailsandanalysisoflearninglevelsrelatedtoqualityofsemesterquestionpapers,assignmentsandevaluation)
i)InternalsemesterQuestionPapers:
Forinternalexaminations,4setsofquestionpaperswithbothobjectiveanddescriptivearepreparedbyfacultyconcernedbasedonthepreviousuniversityquestionpapersamongtheseoneisselectedbythechiefsuperintendentbefore1hourcommencementoftheexamination.
Eachsetofdescriptivequestionpapercontains5questionsamongthese3shouldbeanswered,1st questioniscompulsorywhichhas5shortanswerquestions(each2marks)coveringentiresyllabusoftheinternalexaminationandlonganswerquestions(each10marks)givingimportancetoeveryunit.
EachquestionintheinternalpapersisdesignedbasedontheBloomstaxonomylevels(L1L6).
L1:Knowledge
L2:Comprehension
L3:Application
L4:Analysis
L5:Synthesis
L6:Evaluation
Eachquestionintheinternalpapersismarkedwiththecourseoutcomes.
EachsetofobjectivetypequestionsispreparedbygivingimportancetofundamentalsandonparwithcompetitiveexamslikeGATE/IES/UPSC/APPSCetc.
Additionalreviewsoninternalquestionpapersaredonebyseniorfacultymembers(subjectexperts).
Assignments
Afterthecompletionofeveryunitassignmentsaregiventothestudents.
Simpleassignmentsforweakstudents.
Diverseassignmentsforbrightstudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 21/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 22/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
EvaluationProcess:
Evaluationisentirelydonebasedonthestudentsperformanceintheinternalexaminationandassignments.
Evaluationprocessconsistsof
Conductingexamsandgivingassignments.
Evaluatingpapersbasedonstandardkey(schemeofevaluation).
Distributingtheanswersheetstothestudents.
Ifanydiscrepancyisfoundbythestudents,thennecessarycorrectionsaretobetakenbythefaculty.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 23/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Therefore,transparencyofevaluationisachieved.
2.2.3Qualityofstudentprojects(25) InstituteMarks
(Qualityoftheprojectismeasuredintermsofconsiderationtofactorsincluding,butnotlimitedto,environment,safety,ethics,cost,type(application,product,research,reviewetc.)andstandards.Processesrelatedtoprojectidentification,allotment,
continuousmonitoring,evaluationincludingdemonstrationofworkingprototypesandenhancingtherelevanceofprojects.MentionImplementationdetailsincludingdetailsofPOsandPSOsaddressedthroughtheprojectswithjustification)
ThequalityofprojectsismonitoredbytheInternalDepartmentCommittee(IDC)whichhasHOD,Projectcoordinator,seniorfacultiesinthedepartment.Ittakesresponsibilityofcomingoutwithinnovativeideasoftheprojectsandalsoensuresthatthereisnorepetitionofprojects.Italsoensures,projectsarecarefullydesignedsuchthat
theyencouragethestudentstogainexpertiseontechnologieswhichhavethedemandintheemploymentmarket.
ThecommitteeselectsthetopicsthatcancoverallCourseOutcomesaswellascertainexternalfactorssuchasenvironment,diverseapplications,safety,cost,andstandards.
ProjectProcess:
Step1:Projectbatchesareformedbasedonacademicpercentage(5studentsineachbatch).
Step2:Guideswillbeallocatedbasedonstudentsinterestandguidesareaofexpertise.
Step3:Theprojectareasareselectedbasedonstudentsareaofinterest.
Step4:TheProjecttopicsarecoveredwithmaximumcourseoutcomesintheircoursedurationaswellasvariousfactorssuchasenvironment,safety,ethics,cost,application,standards,etc.
Step5:Thestudentswilldotheprojectworkregularlywiththehelpofguides.
Step6:ThereviewswillfrequentlybeconductedwithIDCandguides.
Step7:Thestudentsareencouragedtodeveloptheprototypes.
Step8:Thestudentsalsoareencouragedtoparticipateinvariousnationallevelfestsandprojectexhibitions.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 24/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Step9:TopthreeprojectswillbeselectedbyIDCandawardedbytheDepartment.
Step10:MajorityoftheseprojectworksarecarriedthroughResearch&Developmentcell.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 25/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Processofprojectguideallotment&selection:
Projectreviewdetails:
SomeoftheProjectsarelistedbelow:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 26/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Project Matching Measured
Areasof Matchingwith
NameoftheStudents ProjectTitle Mappedcourses withthe
Specialization Supervisor(s) thestatedPOs aspects
statedPSOs
CAY(20142015)
N.VenkatNaveen
DesignandEstimationofRoofTop
P.BalaSubramanyam WaterHarvestingforGroundWater WaterResources EstimationCostingandValuation PO7,PO8,
Dr.S.SiddiRaju PSO2
B.PrathapKumar Recharge(AtSiddharthagroupof Engineering ,WaterResourceEngineering PO9
Institutes) Environmental
K.Nagarjuna Safety
S.MaheshBabu
Dr.K.Chandrasekhar PO3,
P.Ashok DesignandDrawingofReinforced Environmental
Environmental Reddy
IntegratedDesignofSmartVillage concreteStructures,Environmental PO6,PO7, PSO2
C.CharanKumarReddy Engineering Safety
Engineering
PO9
N.ShanmugaSundhar
P.Harijyothi
DesignandDrawingofReinforced Economical,
P.Deepkiran Environmental PO6,
InterlinkingofTanks Dr.S.SiddiRaju concreteStructures,Environmental PSO2 Environmental,
G.Suhasini Engineering PO7,PO9
Engineering,ConcreteTechnology Safety
D.AnishKumar
CAYm1(20132014)
C.Sasidhar
Mounika.A PlanningandDesignofearthdam
acrossKushasthaliandBuggaVagu WaterResources EstimationCostingandValuation,Geo PO1,PO7, Environmental,
C.Kesavulu Dr.S.SiddiRaju PSO2.
nearErramarajupalemvillagein Engineering TechnicalEngineering PO8,PO9 Safety
KasiNiraanjan KarvetinagaramMandal
Y.S.BhanuChandra
R.S.Surekha
Bharathi.D Economical,
DesignandEstimationofdrinking Environmental Dr.K.Chandrasekhar EstimationCostingandValuation PO3,
M.Harish PSO2 Environmental,
waterdistributionsystem,Nagaripeta Engineering Reddy EnvironmentalEngineering PO6,PO7
G.Jayaprasanth Safety
P.Venkateswarlu
A.Brahmini
G.Suresh EnvironmentalEngineering,
Alignmentandformationofouter Transportation Dr.K.Chandrasekhar PO6,PO7,
Balaji.M Transportation PSO2 Safety
ringroadatTirumala Engineering Reddy PO9
T.K.Manikanta Engineering
P.Renuka
CAYm2(20122013)
J.Rajeshwari
EstimationCostingandValuation,
S.KhajaNayabRasool Identification&EffectiveUseof PO7,
WaterResources WaterResourcesEngineering,RS&GIS
GroundWaterTableInTirupati Dr.S.SiddiRaju PSO2 Safety,
A.Chendu Engineering PO8,PO9
UrbanAreaUsingGISApplications
Economical
M.SarathKumar
N.Nirupa
PO3,
G.Saravana DesignandDrawingofReinforced Environmental,
DesignOfSuperPassageWithRCC WaterResources
S.AnandKumarVarma concreteStructures,Environmental PO6,PO7, PSO2
M.Dorababu Pier&PierCap Engineering Safety
Engineering,ConcreteTechnology
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 27/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
P.Gowtham PO9
D.Anusha DesignandDrawingofReinforced
concreteStructures,
N.V.Pragna StudyOfFlexuralEffectOnLaterally PO1,PO6, Environmental,
Dr.K.Chandrasekhar
UnsupportedBeams(AsPerIsCode StructuralEngineering DesignandDrawingofSteel PSO2
K.Y.Babitha Reddy PO7,PO9 Safety
800:2007) Structures,
P.ChandraKumar ConcreteTechnology
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 28/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
2.2.4Initiativerelatedtoindustryinteraction(15) InstituteMarks
(Givedetailsoftheindustryinvolvementintheprogramsuchasindustryattachedlaboratories,partialdeliveryofappropriatecoursesbyindustryexpertsetc.Mentiontheinitiatives,implementationdetailsandimpactanalysis)
Theinstitutionhasverygoodinteractionwiththevariousindustries.
ThevariousinnovativecentresareestablishedlikeMicrosoftinnovationcentre,IBMcentreofexcellence,IEGJKC,startupincubationcentre,skilldevelopmentcentreetc.
i)HSSBIMSolutionsPrivateLimited:
ForstudentscareerdevelopmenttheinstitutionundersignedMoUwithHSSBIMsolutionprivatelimited.
TheobjectiveoftheMoUistotrainthestudentonAutodeskcertificationprograms(AutoCAD,Autodesk@SimulationCFDMotion,etc.)tomeettheindustrialneedsforthecareerdevelopmentofthestudents.
TheyareprovidinglatestsoftwareversionofAutodeskEducationMasterSuite125licensesatfeeofcost
Throughitseducationcommunityportaladdresstechnologyaccessisprovidedforfacultiesandstudentswithfreestudentdemoversionlicense.
ii)MoUwithUnitechtransfer
UnitechtransferGmbHGermanCentreforAutomationandRobotics:
ForstudentscareerdevelopmenttheinstitutionundersignedanMoUwithUnitechtransferGmbHGermanCentreforAutomationandRobotics.
CompanyresponsibleforfollowingactivitiesinorganisationofInternship/ProjectandPlacementexecutionandallrelatedmatters.
ThemainactivityincludesremotetheoreticalandpracticaltrainingfromGermanandremotestudentassistance.
DesigningthetasksaccordingtothecurrentIndustryneedsforIndianstudentswhichcanbeexecutablewithin23monthsaccordingtothecurrentIndustryneedsforIndianstudents.
Providingthetechnicalinfrastructureattheinstitute:SoftwaretooperatefromIndia.
GermanexpertstosupporttheIndianuniversitiesduringthecompleteperiodoftaskexecution.
iii)MicrosoftInnovationCentre:
Ourinstitutionisoneamong45institutionsinIndiatohaveMicrosoftEdvantagePlatinumlevelstatusandalsotheMicrosoftInnovationCentre(MIC).
Thisinitiativehashelpedmorethan500studentstogetcertifiedonMicrosofttechnologies.
ManystudentsarehoningtheirskillsonMicrosofttechnologiesinMIC.
StudentsareevendevelopingprojectsandappsformobiledevicesinMIC.
Thisinitiativehascreatedavastawarenessoflatesttechnologiesamongthestudentsandthestaff.
TheinstitutionhasMicrosoftInnovationCentreestablishedwithinthecampustofostercriticalthinkingandinnovationamongthestudents.
StudentsareencouragedtoworkonMicrosofttechnologiesandcreatenewproductsandservicesusingthesame.
Hackathonprogramconductedon31st Jan2015bytheinstitutionandmorethan500appsareuploadedinonline.
MICistrainsourstudentsasperrequirementsofMNCs.
Thebenefitsofthecollaborationare:
Opportunitytoemergeasoneofthecompetententitiesintheacademiccirclesinvariousareasofinformationtechnologies.
Opportunitytoberecognizedbytheindustryandacademiccirclesasoneofthepreferredlocation/institutionforacquiringtrainingandskillslatesttechnologyandsoftwares.
OpportunitytostudentsandfacultymemberstoincreasetheirknowledgeandacquireskillsonbestinclauseIBMsoftware.
Opportunitytodesigninnovativecurriculumandonvariousindustryspecializationus9ingrelevantIBMsoftware
OpportunitytolearnfromthepractitionersintheindustryfromIBMorbusinesspartners.
OpportunityforstudentsandfacultymemberstoavailprofessionalandglobalcertificationonIBMsoftware
OpportunitytosetupajointandcobrandedLabonthecampuswithIBM,focusedonvariousspecialityareaslikeBigData,Analytics,Mobility,Security,SWEngg.etc.,
OpportunitytoconductindependentnoncommercialresearchbyfacultymembersasperguidelinesfromIBMtimetotime.
OpportunitytoreceivecoursewarefromIBMdesignedbyprofessionalsinIBMsoftwareLabs.
OpportunitytoconductvariousseminarandworkshopswithIBMintheinstitution
OpportunitytocomarketwithIBMtopromotePrograms.
iv)IEGJawaharKnowledgeCentre(IEGJKC):
JawaharknowledgecentreisaCareerDevelopmentandjoborientedprogramorganizedbyInstitutionofElectronicGovernance(IEG),Govt.ofA.P.ThemainobjectiveoftheJKCistoensurethecareeropportunitiesforstudents.
JKCisoneofthejobsourcesforthestudents,havingcollaborationwithourinstitution.MostofthetopleadingRecruitersarevisitingtheinstitutionforonCampusdrivesthroughJKC.
OurinstitutionhasthehighestnumberofregisteredstudentsinJKCinthedistrict,withStarcategoryStatus.
v)StartupIncubationcentre:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 29/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
TheStartupIncubationCentretoourinstitutionhasbeensanctionedbytheA.P.StateGovernment,asapartofSunriseStartupprogramsforstudentsonJan2015.
A.P.Stategovernmenthassanctionedtotal38incubationcentresinstate(5forChittoordistrict)throughthis.Amongthoseoneisourinstitution.
ItisaprivilegetoourinstitutiontorunincubationfunctionalityforthedevelopmentofstudentEntrepreneurs.
Studentcommitteehasbeenformedandapprovedbystartupvillage,Visakhapatnam.ThiscommitteeisworkingonincubatorfunctionalitiesundertheguidanceofCoordinatorandHeadoftheInstitution.
vi)SkillDevelopmentCentre:
Aimingtopromoteinnovationamongstudents,theAndhraPradeshgovernmentlaunched17skilldevelopmentcentresacrossthestatewherestudentsfromcollegesanduniversitieswouldtakepartindevelopingmobileappsandotherskills.
Itisproudthatamongthoseoneisourinstitutionthroughoutthestate.
Itisstartedwithabatchof48studentsinPhaseI.
Theydeveloped52AndroidAppsinthedurationof2weeks(512015to1712015).
TwostudentsofphaseIwereawardedtwoandroidmobilesbyourhonourableChiefMinisterfortheirappsdevelopment.
4studentshadgotplacementsinLogicshore,Vizag.
PhaseIIstartedinthesameyearwith50students,dividedinto10batcheswith150numbersofsessions.
InPhaseII,10projectshavebeendevelopedandthesamesubmittedasFinalyearprojects.
Amongthese10projects7aremobileapplicationsand3arewebapps.
Interactionwithindustry:
1.ThecollegehasenteredintoMoUswithleadingindustries,whicharebeingpursuedactively.
2.AnactiveEntrepreneurshipDevelopmentCellisheadedbyaseniorProfessortomouldthestudentstobecomeEntrepreneurs.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 30/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
ConductedProgramsbytheInnovativeCentres:
Resourceperson
S.No. Nameofthecentre Program Date(s) No.ofstudents/facultybenefited
(Mr/Dr/Mrs/Ms)
Twodayworkshopon3Dstudent 09102014to
1 HSSBIMSOLUTIONS DibyenduBiswas,Vetrivel 45
designchallenge 11102014
AwarenessofAutomationand GouthamM
2 Unitechtransfer 05012016to06012016 200
Robotics MD,Unitechtransfer.
AbdulFirozekhan,RameezAhmad
3 MicrosoftInnovationCentre HackathonProgram 31012015 40
Microsoftassociatepartners
Awarenesscamponstartupboot
4 K.AshokRaju,Chairman,SGEI 10022015 180
camp
AwarenesssessiononTechnology Ektachowdary,consultant,ISB,
5 05052015 50
StartupIncubationcentre entrepreneurprogram Akshyjalan,consultant,ISB
RipulKumar,CEO,KernCommunication/Anchalsood, 24082015to
Twodayworkshopondesign
6 StrategicDesigner&Analyst,ISB/Roliagarwal, 38
thinking 25082015
StrategicDesigner
05012015to
7 PhaseI Abrar,Trainer(throughvideoconference) 48
17012015
APSkillDevelopmentcentre
09022015to
8 PhaseII Abrar,Trainer(throughvideoconference) 50
04042015
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 31/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 32/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 33/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
SomeoftheIndustrialvisits:
20152016
STUDENTSDETAILS
DATEOF
S. NAMEOFTHE
INDUSTRY TOPIC TOTALNO. FACULTYNAMES
No. INDUSTRY
VISITED YEAR OF
STUDENTS
Dr.S.SiddiRaju
Professor,
1 13102015 SomasilaProject III 65
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 34/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
WaterSupply, Y.MuraliKrishna
Power&Irrigation
AssosiateProfessor
WaterSupply, Mr.M.Pavankumar
2 28092015 AraniarDam II 36
Power&Irrigation Assistantprofessor
Assistantprofessor
AnnamacharyaProject
(Cheyyeru)
Dept.OfGeology
Dr.S.SiddiRaju
Professor,
HistoricalFort&
4 12082015 III 75
Hydrology Mr.S.ArifHussain
Chandragiri Assistantprofessor
Fort
Kalyandam
20142015
Srisailam
Yaganti Y.MuraliKrishna
2 21082014 Spillways III 45
Mahanandhi AssosiateProfessor
Ballumcaves
20132014
Dept.OfGeology
Srisailam
HistoricalFort& S.AnandKumarVarma
1 12072013 Yaganti III 59
Hydrology AssistantProfessor
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 35/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Mahanandhi
BallumCaves
20122013
ChandragiriFort
K.P.Venugopal
1 13082012 Dept.OfGeology HistoricalFort III 55
AssistantProfessor
Kalyandam
IndustrialVisitsphotographs:
2.2.5Initiativerelatedtoindustryinternship/summertraining(15) InstituteMarks
(Mentiontheinitiatives,implementationdetailsandimpactanalysis)
Theprimarygoaloftheinternshipistoallowstudentstoincorporateandemphasizethelessonslearnedintheclassroomsintoarealworldexperiencesetinaprofessionalpracticeorientedenvironment.
TheinternshipprogramisanexcellentcomplementstotheDepartmentsprogramforcontinuousimprovement.Thefacultyadvisorswillbenefitbydevelopingrelationswithemployersthatparticipateinprogram.
Inadditiontoofferingstudentstoopportunitytodemonstrateanddeveloptheirtechnicalskills,participationintheprogramallowsstudentstodevelopprofessionalskillssuchasteamwork,effectivecommunications,socialinteractionsandprofessionalnetworking,anunderstandingofbusinessprocedures,leadership,andcritical
thinking.
ThestudentsaremotivatedtoparticipateinthetrainingprogramssuchasInternships/SummerTrainingcoursesbyprovidingattendance.Thenthetrainedstudentswillgiveorientationprogramstootherstudents.
Theseinitiativeswillbenefitotherstudentswhodidntattendthecourse,togaintheknowledgeinthatcourse.
Intelligentstudentswillcomeforwardtoparticipateontheirowninterest.Theyareencouragedtoparticipateintheintercollegetechnicalsymposiums.
ISB(IndianSchoolofBusiness)InternshipProgram.AndstudentscangettheengineeringdegreeplusTEPcertificationfromISBaswell.
OurInstitutionissupportingtheB.TechstudentstojointheTechnologyEntrepreneurshipPrograminIndianSchoolofBusiness(ISB),Hyderabad.
TheTEPhasdevelopedatwoyearsemivirtualprogram,acombinationofonlineandofflinemodules.ForEngineeringCollegesISBwiththehelpofGlobalfacultyhasdesignedtheProgram.ISBpartnerswiththeselectedcollegestoenrollstudentsintotheTEP.Theengineeringcollegesareselectedbasedontheirinterest
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 36/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
tosupporttheprogram.
SomeoftheIndustryVisitsandinternships:
Studentscanvisittheindustriestogainpracticalknowledgeonadvancedtrendsintheindustry.Everyyear,studentsareencouragedtoparticipateintheindustrialvisitsandinternship.
Someoftheindustrialvisits/internships
Someoftheinternshipprograms
Nameofthe
S.No. Nameofthestudent Areaofthework Internshipduration
industry
HighwayDept.,
2Months
T.SREEKANTH BSCPL planningDept.,
1 (01062015to
B.Tech,IIIYear Infrastructurelimited SurveyDept.,
29072015)
Testingofmaterials.
Someofthesummertrainingprograms:
Year No.of
Academicyear Resourceperson(s)/Industry Date Topic
Sem students
RipulKumar,CEO,Kern
Communication/Anchalsood,Strategic 24082015to Designthinkingfor
201516 IVI Designer&Analyst,ISB/Roliagarwal, 40
25082015 Entrepreneurship
StrategicDesigner,ISB(IndianSchoolof
Business)
Listoftrainedstudents:
AcademicYear201415:
AutoCAD,
3 12F61A0143 M,SaiSrinivas
STAADPro 9weeks
4 12F61A0145 R.Sheshadri
CADDCENTRE RevitArchitecture
CHENNAI AutoCAD,
5 12F61A0155 TVenkataKesava. 6weeks
STAADPro
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 37/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
AutoCAD,
7 12F61A0147 V.S.Sireesha 6weeks
ECADTIRUPATI RevitArchitecture
AutoCAD,
CADDCENTRE
9 13F65A0106 B.ThulasiRam STAADPro 9weeks
CHENNAI
RevitArchitecture
CADDUNIVERSE AutoCAD,
10 12F61A0160 B.VishnuVardhan 9weeks
ANANTHAPUR STAADPro
AcademicYear201314:
AcademicYear201213:
Internshipcertificate:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 38/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3COURSEOUTCOMESANDPROGRAMOUTCOMES(120) TotalMarks120.00
DefinetheProgramspecificoutcomes
PSO1 BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
PSO2 ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteel
PSO3
structures.
3.1EstablishthecorrelationbetweenthecoursesandtheProgramOutcomes(POs)andProgramSpecificOutcomes(PSOs)(20) TotalMarks
ProgramOutcomesasmentionedinAnnexureIandProgramSpecificOutcomesasdefinedbytheProgram
3.1.1CourseOutcomes(COs)(SARshouldincludecourseoutcomesofonecoursefromeachsemesterofstudy,however,shouldbepreparedforallcoursesandmadeavailableasevidence,ifasked)(5) InstituteMarks
Note:NumberofOutcomesforaCourseisexpectedtobearound6.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 39/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Items 20142015
Abletoknowtheconceptofstressandstrainandtheir
C2 13.1
relationship(L1)
Abletodrawshearforceandbendingmomentdiagramsfor
C2 13.2
differenttypesofbeams(L2)
Abletocalculatethebendingandshearstressesofthebeam
C2 13.3
(L4)
C2 13.4 Abletocalculatethedeflectionofbeam(L4)
AbletoCalculatethedirectandbendingstressesoftthe
C2 13.5
structures(L4)
Items 20142015
C2 23.1 Abletoanalyseandsolvepipeflowproblem(L4)
Abletodesignsubmergedbodiesbasedondragandlift
C2 23.2
characteristics(L6)
Toknowclearlyaboutpumps,characteristiccurvesand
C2 23.3
hydropowerplants(L1)
Toselectthesuitablepumpsandturbinesbasedonthe
C2 23.4
requirements(L2)
Toknowaboutcentrifugalpump,specificspeed,
C2 23.5 characteristics,geometicsimilarityandcavitationofturbines
(L1)
Items 20142015
Abletoknowtheconstituentsofconcreteanddifferent
C3 12.1
methodsofdesign(L1)
Abletoanalysesinglyreinforced,doublyreinforcedT,Lbeams
C3 12.2
(L4)
Abletoknowthedesignproceduresforshear,torsion,bond
C3 12.3
andanchorage(L1)
Toanalysethecolumns,footingsandslabsbylimitstate
C3 12.4
method(L4)
Abilitytoanalysethebeamsforserviceabilitylimitsaccording
C3 12.5
tocodalprovisions(L4)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 40/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Items 20142015
Abilitytoanalyzetensionmembers,compressionmembers
C3 21.1 andabilitytodesignofsimpleboltedandweldedconnections
(L4)
Abilitytodesignsteelframesandconnectionsofbuildingina
C3 21.2
teamsetting(L6)
Familiaritywithprofessionalandethicalissuesandthe
C3 21.3
importanceoflifelonglearninginStructuralEngineering(L1)
Abilitytodesigngantrygirder,detailingofsimplebeams,
C3 21.4
compoundbeams,columnsincludinglacingandbattens(L6)
Abilitytodesignrooftrusses,plategirders,curtailmentof
C3 21.5
flangeplates,stiffeners,splicingandconnections(L6)
Items 20142015
Abletoknowthebasicconceptsofhighwaybridgeloadings
C4 12.1
standards(L4)
C4 12.2 Abilitytodesignbridgebearings(L4)
C4 12.3 Toknowtheclearideaaboutpiersandabutments(L1)
Abilitytodesigndecktypeweldedplategirder,bridgeofsingle
C4 12.4
lineB.G.(L6)
AbilitytodesigncompositebridgesconsistingofRCCslabs
C4 12.5
oversteelgirders(L6)
Items 20142015
Abletodesigntheadvancedstructureslikeflat,slab,intzwater
C4 21.1 tank,circularandrectangularwatertankrestingontheground
(L6)
Abletoanalyzethecantileverretainingwallwithhorizontal
C4 21.2
backfill(L4)
Abilitytodesignthegridfloor,waistslabanddifferenttypesof
C4 21.3
staircases,cinemabalcony(L6)
Tounderstandthedesignconceptsofsimpledoglegged
C4 21.4
staircase(L1)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 41/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C4 21.5 AbletodrawRCCdetailingforadvancedstructures(L2)
3.1.2COPOmatricesofcoursesselectedin3.1.1(Sixmatricestobementionedonepersemesterfrom3rdto8thsemester)(5) InstituteMarks
Note:Entercorrelationlevels1,2or3asdefinedbelow:
1:Slight(Low)2:Moderate(Medium)3:Substantial(High)Ifthereisnocorrelation,put
1.coursename:C213
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C213.1 2 2 3
C213.2 3 3 3 3
C213.3 2 2 3 2 3
C213.4 3 2
C213.5 3 3 3
Average 2 2 1 0 0 0 1 0 0 0 0 3
2.coursename:C223
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C223.1 3 3 2 3 3
C223.2 3 3 2 3
C223.3 3 3
C223.4 3 2
C223.5 2 2 3
Average 2 2 1 0 1 0 0 1 0 0 1 2
3.coursename:C312
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C312.1 2 2 3 1
C312.2 2 2 3 1 1
C312.3 2 2 3 1
C312.4 2 2 3 1
C312.5 2 2 2 1 1
Average 2 2 3 0 0 0 0 0 0 0 0 1
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 42/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4.coursename:C321
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C321.1 3 3 3 2
C321.2 3 3 3
C321.3 2 3
C321.4 3 3 3
C321.5 3 3 3 2
Average 2 2 2 0 0 0 0 0 0 0 0 1
5.coursename:C412
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C412.1 3 3 3 2
C412.2 3 2
C412.3 2 2 2 2
C412.4 3 3 3 3
C412.5 2 2 3 3
Average 2 2 3 0 0 0 0 0 0 0 0 2
6.coursename:C421
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C421.1 2 2 3 2
C421.2 3 3 3 3
C421.3 3 3 3 2
C421.4 2 2 2 2
C421.5 2 2 2 3
Average 2 2 3 0 0 0 0 0 0 0 0 2
1.CourseName:C213
C213.1
C213.2 2 2
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 43/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C213.3 2 2
C213.4 2 2
C213.5 2 3
Average 0 1 1
2.CourseName:C223
C223.1
C223.2
C223.3
C223.4
C223.5
Average 0 0 0
3.CourseName:C312
C312.1
C312.2 2 2
C312.3 2 2
C312.4 2 2
C312.5 2 2
Average 0 1 1
4.CourseName:C321
C321.1 2
C321.2 2
C321.3 2
C321.4 2
C321.5 2
Average 0 0 2
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 44/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5.CourseName:C412
C412.1 3
C412.2 3
C412.3 3
C412.4 3
C412.5 3
Average 3 0 0
6.CourseName:C421
C421.1 2
C421.2 3
C421.3 2
C421.4 2
C421.5 2
Average 0 0 2
3.1.3AProgramlevelCoursePOmatrixofallcoursesINCLUDINGfirstyearcourses(10) InstituteMarks
BeforeproceedingpleaseclickonEdittofetchthedata.Note:Entercorrelationlevels1,2or3asdefinedbelow:
1:Slight(Low)2:Moderate(Medium)3:Substantial(High)Ifthereisnocorrelation,put
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C101 1 2 1 2 2 2 2
C102 2 1 3 3 1 2 3
C103 2 2 2 3 1
C104 2 2 1
C105 2 2 3 2 2 2
C106 2 3 2 2 2 2 2
C107 2 3 2 2 2
C108 2 2 3 2 2 2
C109 2 2 2 2 2 3 2
C110 1 2 2 2 2 2
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 45/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C111 2 2 2 2
C211 2 2 2 2 2
C212 2 2 1
C213 3 3 3 3 3 3
C214 2 2 2 2 2
C215 2 3 2 1 2 2 1
C216 1 2 2 2 2
C217 3 2 3 2 2 3
C218 3 2 3 3 3 3
C221 1 2 2 1
C222 2 2 2 2 1 2
C223 3 3 3 2 3 3 3 3
C224 2 2 1 2 2
C225 2 3 2 1 1 2 2
C226 2 2 2 2 1 2
C227 3 3 2 3 3 3
C228 3 2 2 2 3 3
C311 3 3
C312 1 2 3 1 1 1
C313 2 2 3 3 2 2 2
C314 2 2 2 2 2 2 2 2
C315 2 3 2 2 2 3
C316 2 2 2 2 2 2 2
C317 3 2 3 3 3 2
C318 2 3 2
C321 1 2 3 1 1 1
C322 2 3 2 2 2 2
C323 2 2 3 2 2 2 3 2
C324 3 2 3 2 2 1 1 2
C325 2 2 2 2 2 1 2 2
C326 2 2 3 2 2 2
C327 2 3 2 3 3 3
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 46/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C328 3 2 2 3 3 2
C411 2 3 3 2 2 2
C412 2 3 3 2
C413 2 2 2 1 2 2 2
C414 2 2 3 1 2 2 2 2 2
C415 2 2 3 2 2 1 2
C416 2 2 2 1 2 2 1
C417 2 2 2 3 3 3
C418 3 3 3 3 3 3
C421 2 2 3 2
C422 2 2 3 2 2
C423 3 2 2 3 2 2 3 2
C424 3 3 2 1 2 1 2
C425 3 3 3 3 3 3 1
C426 3 3 3 3 2 3 1 1 1
3.1.3BProgramlevelCoursePSOmatrixofallcoursesINCLUDINGfirstyearcourses
C101
C102
C103
C104
C105
C106
C107
C108
C109
C110
C111
C211
C212
C213 2
C214
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 47/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C215
C216 2
C217
C218
C221
C222
C223 1
C224
C225
C226
C227
C228
C311
C312 2 2
C313 3
C314
C315
C316 1
C317 2
C318
C321 2 2
C322
C323
C324 1
C325
C326 1
C327
C328
C411
C412 3
C413
C414
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 48/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C415
C416
C417 3
C418 2
C421 2
C422 3
C423
C424
C425 3 3 3
C426 3 3 3
3.2AttainmentofCourseOutcomes(50) TotalMarks
3.2.1DescribetheassessmentprocessesusedtogatherthedatauponwhichtheevaluationofCourseOutcomeisbased(10) InstituteMarks
(Examplesofdatacollectionprocessesmayinclude,butarenotlimitedto,specificexam/tutorialquestions,assignments,laboratorytests,projectevaluation,studentportfolios(Aportfolioisacollectionofartifactsthatdemonstrateskills,personal
characteristicsandaccomplishmentscreatedbythestudentduringstudyperiod),internallydevelopedassessmentexams,projectpresentations,oralexamsetc.)
Theinstitutefollowstheassessmentprocessfortheevolutionofcourseoutcome.
EvaluationProcess:
Theevaluationprocessincludes
(a)InternalExams
(b)UniversityExams
TheinstitutefollowstheevaluationprocessprescribedbytheUniversityforInternalandExternalExams.
InternalExamination:
AspertheUniversityexaminationpattern,twomidtermtestsareconductedforeachsubject.
TheInternalExaminationfor30marksincludesbothobjectivequestionsfor10marksandDescriptivequestionsfor20marks.
Responsible
S.No. Activity Remarks
person
1.Willbecompletedwithin3daysoftheexamcompletion.
EvaluationofInternal Individual
1 2.Distributetheanswersheetsinclassandclarifies,incaseof
Examination faculty
grievances
Submissionofmarks
Individual
2 foreachquestion& Withinaweekfromthedateoflastexam.
faculty
totaltoHOD
Consolidationofallsubjects
Studentswillverifytheirmarksandreportanygrievanceswithin3
3 marks&displayonthenotice Coordinator
daysfromthedateofdisplay.
board
1.Ensurethemarksenteredinregisterandsubmittedaresame.
Verification&
4 HOD
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 49/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Analysis 2.AnalyzetheCOattainmentsandidentifythemeasuresfor
improvement
SubmitSemestercoursesmarks
5 HOD Consolidateallcoursesandsubmitsonesetforeachclass
toPrincipal
Principalverifythemarksof
6 studentsandsubmittedtoExam Principal SubmissionofInternalmarkstotheExaminationbranch
branch
Chiefof
Communicatemarks Asperuniversityscheduledtheinternalmarksarepostedto
7 Examination
toUniversity controllerofexaminationbranch
Evaluations
SampleCopyofQuestionWiseMarkSplitSheet
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 50/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Sampleinternalmarkspage:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 51/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 52/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
ExternalExamination:
TheExternalExaminationofeachcourseisfor70marks.
ScheduleofExaminations
ThescheduleofinternalandexternalexaminationsisclearlymentionedintheacademicschedulepublishedbytheUniversity/institutionandthesameiscommunicatedtoallthestudentsandthefacultyatthebeginningofeachsemester.
MandatoryAssessment:
Universitypostsresultsontheuniversitywebsite.ResultsAnalysisisreviewedbyheadofthedepartmentandPrincipalimmediatelyafterresultsaredeclaredandareasforimprovementareidentified.
Counselorsadvisethestudentsbasedonindividualperformance.
Sampleuniversityresultpage:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 53/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3.2.2RecordtheattainmentofCourseOutcomeofallcourseswithrespecttosetattainmentlevels(40) InstituteMarks
ProgramshallhavesetCourseOutcomeattainmentlevelsforallcourses.
(Theattainmentlevelsshallbesetconsideringaverageperformancelevelsintheuniversityexaminationoranyhighervaluesetastargetfortheassessmentyears.Attainmentlevelistobemeasuredintermsofstudentperformanceininternal
assessmentswithrespecttotheCourseOutcomesofacourseinadditiontotheperformanceintheUniversityexamination)
EvaluationofinternalandexternalexaminationmarksforsettingCourseattainmentlevelsforallcourses:
Evaluationofmarksfrombothinternalandexternalexaminations
SemesterI 30 70 100
AcademicYear
SemesterII 30 70 100
MeasurementofCourseattainmentlevelsforUniversityExaminations:
AttainmentLevel1:50%ofstudentsscoring60%marksintheUniversityfinalexamination.
AttainmentLevel2:60%ofstudentsscoring60%marksintheUniversityfinalexamination.
AttainmentLevel3:70%ofstudentsscoring60%marksintheUniversityfinalexamination.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 54/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
CourseattainmentlevelsforIIYearISemesterUniversityExamination:201415
%ofStudentsScoredmorethan
COURSE Attainmentlevel
60%
C211 53.1 1
C212 53.1 1
C213 53.1 1
C214 56.3 1
C215 43.8 0
C216 51.6 1
C217 100 3
C218 100 3
MeasurementofCourseattainmentlevelsforInternalExaminations:
AttainmentLevel1:50%studentsscoringmorethan60%marksoutofthemaximummarks.
AttainmentLevel2:60%studentsscoringmorethan60%marksoutofthemaximummarks.
AttainmentLevel3:70%studentsscoringmorethan60%marksoutofthemaximummarks.
CourseattainmentlevelsforIIYearISemesterInternalExamination:201415
%ofStudentsScoredmore
COURSE Attainmentlevel
than60%
C211 57.2 1
C212 66.5 2
C213 65.5 2
C214 61.8 2
C215 61.8 2
C216 60.9 2
C217 100 3
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 55/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C218 100 3
Overallcourseattainmentforallcourses:
ACADEMICYEAR:201415
C211 1 1 1
C212 2 1 1.3
C213 2 1 1.3
C214 2 1 1.3
C215 2 0 0.6
C216 2 1 1.3
C217 3 3 3
C218 3 3 3
C221 1 0 0.3
C222 2 2 2
C223 0 1 0.7
C224 1 1 1
C225 1 0 0.3
C226 2 1 1.3
C227 3 3 3
C228 3 3 3
C311 2 1 1.3
C312 2 2 2
C313 2 0 0.6
C314 3 2 2.3
C315 2 1 1.3
C316 2 2 2
C317 3 3 3
C318 3 3 3
C321 1 1 1
C322 2 0 0.6
C323 3 1 1.6
C324 0 0 0
C325 2 1 1.3
C326 2 1 1.3
C327 3 3 3
C328 3 3 3
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 56/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C411 3 1 1.6
C412 3 3 3
C413 2 0 0.6
C414 3 2 2.3
C415 3 2 2.3
C416 3 1 1.6
C417 3 3 3
C418 3 3 3
C421 3 1 1.6
C422 1 2 1.7
C423 3 0 0.9
C424 3 1 1.6
C425 3 3 3
C426 3 3 3
COattainment
2.26 1.54 1.75
average
CourseAttainment:
Forexample:WaterResourcesEngineeringI(C314)
AttainmentthroughUniversityExamination:Moderatei.e.2
AttainmentthroughInternalAssessment:Substantiali.e.3
Considering70%weightagetoUniversityexaminationand30%weightagetoInternalassessment,theattainmentcalculationswillbe(70%ofUniversitylevel)+(30%ofInternallevel)
i.e.70%of2+30%of3=1.4+0.9=2.3
3.3AttainmentofProgramOutcomesandProgramSpecificOutcomes(50) TotalMarks
3.3.1DescribetheassessmenttoolsandprocessesusedformeasuringtheattainmentofeachoftheProgramOutcomesandProgramSpecificOutcomes(10) InstituteMarks
(DescribetheassessmenttoolsandprocessesusedtogetherthedatauponwhichtheevaluationofeachoftheProgramOutcomesandProgramSpecificOutcomesisbasedindicatingthefrequencywithwhichtheseprocessesarecarriedout.Describe
theassessmentprocessesthatdemonstratethedegreetowhichtheProgramOutcomesandProgramSpecificOutcomesareattainedanddocumenttheattainmentlevels)
ThedepartmentassesstheprogramtomeetalltheProgramOutcomesandProgramSpecificOutcomesthroughwellqualifiedandexperiencefaculty,bytheoryclasseswithaddontopics,labexperiments,assignments,unittests,miniprojects,mainprojects,seminarsandfeedbackofStudentatthetimeofexit.
Assessmenttooldescription Frequencyofassessment
Internalexaminations Twiceinasemester
Universityexaminations Onceinasemester
Studentexitfeedback
Onceinayear
(IndirectAttainment)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 57/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3.3.2ProvideresultsofevaluationofPO&PSO(40) InstituteMarks
ProgramshallsetProgramOutcomeattainmentlevelsforallPOs&PSOs.
(Theattainmentlevelsbydirect(studentperformance)andindirect(surveys)aretobepresentedthroughProgramlevelCoursePO&PSOmatrixasindicated).
POAttainment
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C211 2 2 1 1 2 2
C212 2 2 2 2 1
C213 2 2 2 1 1 2
C214 2 3 2 1 1 1
C215 2 2 1 2 2 2
C216 2 2 2 2 2
C217 3 3 3 3 3 3
C218 3 3 3 3 3 3
C221 2 2 2 3
C222 2 2 3 3 2 2
C223 1 1 1 2 1 1 1
C224 2 1 1 2 1
C225 1 1 1 2
C226 2 2 1 2 2 2
C227 3 3 3 3 3 3
C228 3 3 3 3 3 3
C311 3 2
C312 2 2 3 2 2 2
C313 2 2 2 2 1 1 2
C314 3 2 3 3 3 2 3 3
C315 1 2 3 2 2
C316 2 1 2 2 2 2 3
C317 3 3 3 3 3 3
C318 2 3 2
C321 1 2 2 1 1
C322 1 1
C323 2 2 3 2 1 2 2 2
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 58/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C324 2
C325 2 1 2 3 2 2 1 2
C326 2 2 2 2 1 2
C327 3 3 3 3 3 3
C328 3 3 3 3 3 3
C411 2 2 2 2 2 3
C412 3 3 3 3
C413 2 2 3 2 2 1 2
C414 3 2 3 2 2 3 3 2 3
C415 3 3 2 3 3 3 3
C416 2 3 3 2 3 3
C417 3 3 3 3 3 3
C418 3 3 3 3 3 3
C421 3 2 2 2
C422 2 2 2 2 2
C423 2 2 2 2 2 2 2
C424 3 3 2 1 3 2 2
C425 3 3 3 3 3 3 3 3
C426 3 3 3 3 3 3 3 3 1 3 3
COAttainmentLevel
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
COAttainment 2.12 1.98 1.46 1.54 1.76 1.54 0.90 0.23 0.49 0.52 0.52 2.19
DirectAttainment 2.15 1.98 1.33 1.43 1.70 1.43 0.63 0.04 0.11 0.15 0.15 2.24
InDirectAttainment 2 2 2 2 2 2 2 1 2 2 2 2
PSOAttainment
Course PSO1 PSO2 PSO3
C211
C212
C213
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 59/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C214
C215
C216 2
C217 2
C218 3
C221
C222
C223
C224
C225
C226
C227
C228
C311
C312 2 2
C313 1
C314
C315
C316
C317 2
C318
C321 2 2
C322
C323
C324 1
C325
C326
C327 3
C328 3
C411 1
C412 3
C413
C414
C415
C416
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 60/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C417 3
C418 3
C421 2
C422
C423
C424
C425 3 3 3
C426 3 3 3
COAttainmentLevel
InDirectAttainment 2 2 2
4STUDENTSPERFORMANCE(150) TotalMarks120.61
InstituteMarks
Table4.1
Sanctionedintakeoftheprogram(N) 120 60 60 60 60 60
Totalnumberofstudentsadmittedinfirstyearminusnumberofstudentsmigratedtootherprograms/institutionsplusNo.ofstudentsmigratedtothisprogram(N1) 90 59 60 56 58 49
Numberofstudentsadmittedin2ndyearinthesamebatchvialateralentry(N2) 6 12 12 13 12 6
Separatedivisionstudents,Ifapplicable(N3) 0 0 0 0 0 0
Totalnumberofstudentsadmittedintheprogramme(N1+N2+N3) 96 71 72 69 70 55
Table4.2
Numberofstudentswhohavesuccessfullygraduatedwithoutbacklogsinanysemester/yearofstudy(WithoutBacklogmeansnocompartmentorfailuresin
TotalNoofstudentsadmittedintheprogram(N1+ anysemester/yearofstudy)
Yearofentry
N2+N3)
Iyear IIyear IIIyear IVyear
20142015 96 43 0 0 0
20132014 71 35 41 0 0
20122013 72 34 42 41 0
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 61/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
20112012(LYG) 69 38 47 44 44
20102011(LYGm1) 70 36 44 41 40
20092010(LYGm2) 55 36 38 36 35
Table4.3
Numberofstudentswhohavesuccessfullygraduated
Yearofentry TotalNoofstudentsadmittedintheprogram(N1+N2+N3)
Iyear IIyear IIIyear IVyear
20142015 96 88 0 0 0
20132014 71 59 65 0 0
20122013 72 58 62 59 0
20112012(LYG) 69 54 67 66 55
20102011(LYGm1) 70 57 65 65 54
20092010(LYGm2) 55 48 54 54 46
4.1EnrolmentRatio(20) TotalMarks
InstituteMarks
20132014 60 59 98.33
20122013 60 60 100.00
Average[(ER1+ER2+ER3)/3]:91.11
Assessment:18.00
4.2SuccessRateinthestipulatedperiodoftheprogram(40) TotalMarks
4.2.1Successratewithoutbacklogsinanysemester/yearofstudy(25) InstituteMarks
SI=(Numberofstudentswhohavegraduatedfromtheprogramwithoutbacklog)/(Numberofstudentsadmittedinthefirstyearofthatbatchandadmittedin2ndyearvialateralentryandseparatedivision,ifapplicable)
AverageSI=MeanofSuccessIndex(SI)forpastthreebatches
Successratewithoutbacklogsinanyyearofstudy=25AverageSI
X
NumberofstudentsadmittedinthecorrespondingFirstyear+admittedin2ndyearvialateralentryand 69.00 70.00 55.00
seperateddivision,ifapplicable
AverageSI[(SI1+SI2+SI3)/3]:0.62
Assessment[25*AverageSI]:15.50
4.2.2Sucessrateinstipulatedperiod(15) InstituteMarks
SI=(Numberofstudentswhograduatedfromtheprograminthestipulatedperiodofcourseduration)/(Numberofstudentsadmittedinthefirstyearofthatbatchandadmittedin2ndyearvialateralentryandseparateddivision,ifapplicable)
AverageSI=meanofSuccessIndex(SI)forpastthreebatches
Successrate=15AverageSI
X
NumberofstudentsadmittedinthecorrespondingFirstyear+admittedin2ndyearvialateralentryand 69.00 70.00 55.00
seperateddivision,ifapplicable
Y
55.00 54.00 46.00
Numberofstudentswhohavegraduatedinthestipulatedperiod
AverageSI[(SI1+SI2+SI3)/3]:0.80
Assessment[15*AverageSI]:12.05
4.3AcademicPerformanceinThirdYear(15) TotalMarks
InstituteMarks
AcademicPerformance=1.5*AverageAPI(AcademicPerformanceIndex)
API=((Meanof3rdYearGradePointAverageofallsuccessfulStudentsona10pointscale)or(MeanofthepercentageofmarksofallsuccessfulstudentsinThirdYear/10))x(numberofsuccessfulstudents/numberofstudentsappearedinthe
examination)
Successfulstudentsarethosewhoarepermittedtoproceedtothefinalyear.
AverageAPI[(AP1+AP2+AP3)/3]:6.93
Assessment[1.5*AverageAPI]:10.40
4.4AcademicPerformanceinSecondYear(15) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 63/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
AcademicPerformanceLevel=1.5*AverageAPI(AcademicPerformanceIndex)
API=((Meanof2ndYearGradePointAverageofallsuccessfulStudentsona10pointscale)or(MeanofthepercentageofmarksofallsuccessfulstudentsinSecondYear/10))x(numberofsuccessfulstudents/numberofstudentsappearedinthe
examination)
SuccessfulstudentsarethosewhoarepermittedtoproceedtotheThirdyear.
AverageAPI[(AP1+AP2+AP3)/3]:6.57
Assessment[1.5*AverageAPI]:9.86
4.5Placement,HigherStudiesandEntrepreneurship(40) TotalMarks
InstituteMarks
AveragePlacement[(P1+P2+P3)/3]:0.87
Assessment[40*AveragePlacement]:34.80
4.6ProfessionalActivities(20) TotalMarks
4.6.1Professionalsocities/chaptersandorganizingengineeringevents(5) InstituteMarks
(TheDepartmentshallproviderelevantdetails)
WehaveISTEStudents/FacultychapterandmembershipinvariousotherprofessionalsocietieslikeIEEE,IRED,IAENG,ISOC,IAHS,IAH,IWWA,IWRS...etc.
1 ISTE(Students) 86 June2018
2 ISTE(Faculty) 4 LifeTime
3 IEEE(Faculty) 1 Dec2016
4 IRED(Faculty) 14 LifeTime
5 IAENG(Faculty) 15 LifeTime
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 64/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
6 ISOC (Faculty) 15 LifeTime
Dr.T.Harinarayana(GERMI
2 EnergySecurityThroughRenewableSources 28th Feb2015
Director),Dr.SagarAgrwat
Mr.DibyenduBiswas,
3 201415 3DStudentDesignChallenge 09th Oct2014
Mr.Vetrivel
Sustainablewaterresourcesdevelopmentindrought
4 Mr.Kamalnathsetty 15th Sep2014
proneareas
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 65/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 66/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4.6.2Publicationoftechnicalmagazines,newsletters,etc.(5) InstituteMarks
(TheDepartmentshalllistthepublicationsmentionedearlieralongwiththenamesoftheeditors,publishers,etc.)
WepublishNewsletterquarterlyandmagazinetwiceinayear.
Nameofthe Nameofthe
S. TechnicalMagazine/ Technical
IssueNo.&Month Name(s)oftheEditor(s) Publisher
No. NewsLetter Magazine/News
Letter (s)
AY(201516)
1.Y.MuraliKrishna
SIET/Civil/TM001/Oct
2 TechnicalMagazine CIVILINFOSIET 2.G.ShanmukhaSrinivas SIETK
2015
3.V.S.Meganathan
CAY(201415)
1.Y.MuraliKrishna
SIET/Civil/TM001/Oct
5 TechnicalMagazine CIVILINFOSIET 2.G.ShanmukhaSrinivas SIETK
2014
3.V.S.Meganathan
1.Y.MuraliKrishna
SIET/Civil/TM
6 TechnicalMagazine CIVILINFOSIET 2.G.ShanmukhaSrinivas SIETK
002/March2015
3.V.S.Meganathan
CAYm1(201314)
1.J.SathyanarayanaReddy
SIET/Civil/TM001/Oct
4 TechnicalMagazine CIVILINFOSIET 2.C.PrabhakarReddy SIETK
2013
3.K.P.Venugopal
SIET/Civil/TM002/March 1.Y.MuraliKrishna
2014
5 TechnicalMagazine CIVILINFOSIET 2.G.ShanmukhaSrinivas SIETK
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 67/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3.V.S.Meganathan
CAYm2(201213)
1.S.AnandKumarVarma CivilEngineering
1 NewsLetter DISHA Issue1&Aug2012
2.N.KrishnaMurthy Dept.
2 1.J.SathyanarayanaReddy CivilEngineering
NewsLetter DISHA Issue2&Nov2012
Dept.
2.K.PrakashChandra
1.J.SathyanarayanaReddy CivilEngineering
3 NewsLetter DISHA Issue3&May2013
2.K.PrakashChandra Dept.
1.Dr.S.SiddiRaju
SIET/Civil/TM001/Oct
4 TechnicalMagazine CIVILINFOSIET 2.N.KrishnaMurthy SIETK
2012
3.K.PrakashChandra
SIET/Civil/TM 1.Y.MuraliKrishna
5 TechnicalMagazine CIVILINFOSIET SIETK
002/March2013 2.S.AnandKumarVarma
AsamplecopyofNewsLetter(Aug2014):
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 68/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4.6.3Participationininterinstituteeventsbystudentsoftheprogramofstudy(10) InstituteMarks
(TheDepartmentshallprovideatableindicatingthosepublications,whichreceivedawardsintheevents/conferencesorganizedbyotherinstitutes.)
UniversityRanks&GoldMedals:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 69/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Mr.C.SasidharreceivinggoldmedalfromHonorablevicechancellor
PrathibhaAwardsbyAPstateGovt.:
S.No. Regd.No. NameoftheStudents AcademicYear Branch/Specialization %ofMarks
M.Tech.
1 13F61A0212 D.Sukanya 20132015 81.78
(StructuralEngineering)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 70/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
StudentsreceivingPrathibhaAwardsfromHonbleChiefMinister,A.P.
10outof48underJNTUAin201415
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 71/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Participationininterinstituteeventsbystudentsoftheprogramofstudy:
Events/Conferences CAY(201415) CAYm1(201314) CAYm2(201213) Total
Workshops 02 03 19 24
Symposium 10 15 22 47
S.
NameoftheStudent Event Date OrganizedBy Prizes(I/II/III)/Awards
No.
CAY:201415
T.VenkataKesava
1 Symposium 30th ,31st&1st Nov2014 SreeVidhyanekethanCollege,Tirupathi 1st Prize
(12F61A0155)
G.Nandini
2 TechnoHunt 18th&19th Apr2014 SVU,Tirupathi 1st Prize
(12F61A0134)
G.Nandini
3 Quiz 15th Mar2014 JNTUA,Anantapur 2nd Prize
(12F61A0134)
U.Manjunath
4 Symposium 13th Mar2014 RGMCollege,Nandhyala 1st Prize
(12F61A0127)
G.Mounika
5 Quiz 30th ,31st&1st Nov2014 SreeVidhyanekethanCollege,Tirupathi 2nd Prize
(12F61A0131)
G.Nandini
6 Symposium 18th&19th Apr2014 SVU,Tirupathi 2nd Prize
(12F61A0134)
G.Nandini
7 Quiz 15th Mar2014 JNTUA,Anantapur CertificateAwarded
(12F61A0134)
G.Nandini
8 Symposium 18th&19th Apr2014 SVU,Tirupati CertificateAwarded
(12F61A0134)
G.Nandini
9 Symposium 15th Mar2014 JNTUA,Anantapur CertificateAwarded
(12F61A0134)
B.VishnuVardhanaNaidu
10 Quiz 30th ,31st&1st Nov2014 SVCE,Tirupati CertificateAwarded
(12F61A0160)
D.PradeepNaidu
11 Quiz 30th ,31st&1st Nov2014 SVCE,Tirupati CertificateAwarded
(12F61A0135)
M.MukeshNaik
12 Quiz 30th ,31st&1st Nov2014 SVCE,Tirupati CertificateAwarded
(12F61A0132)
M.SaiSrinivas
13 Quiz 30th ,31st&1st Nov2014 SVCE,Tirupati CertificateAwarded
(12F61A0143)
U.Manjunath
14 Workshop 30th ,31st&1st Nov2014 SreeVidhyanekethanCollege,Tirupathi CertificateAwarded
(12F61A0127)
U.Manjunath
th th
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 72/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
15 Symposium 18th&19th Apr2014 SVU,Tirupathi CertificateAwarded
(12F61A0127)
G.Nandini
16 Quiz 30th ,31st&1st Nov2014 SreeVidhyanekethanCollege,Tirupathi CertificateAwarded
(12F61A0134)
G.Nandini
17 Symposium 30th ,31st&1st Nov2014 SreeVidhyanekethanCollege,Tirupathi CertificateAwarded
(12F61A0134)
CAYm1:201314
A.Brahmini
1 Symposium 8th&9th Mar2013 GoldenValley 1st Prize
(10F61A0105)
D.Bharathi
2 Symposium 8th&9th Mar2013 GoldenValley 1st Prize
(11F65A0104)
M.Harish
3 Symposium 10th Apr2013 SVCET,Chittoor 1st Prize
(10F61A0113)
S.Kartheek
4 Symposium 10th Apr2013 SVCET,Chittoor 1st Prize
(10F61A0117)
S.Kavitha
6 Symposium 11th May2013 SVCET,Chittoor 2nd Prize
(10F61A0119)
S.Dhanya
7 Symposium 11th May2013 SVCET,Chittoor 2nd Prize
(10F61A0110)
U.Manjunath
8 Symposium 2nd Mar2013 N.B.K.R. 3rd Prize
(12F61A0127)
U.Manjunath
9 Symposium 16th Feb2013 N.B.K.R. 3rd Prize
(12F61A0127)
B.Kavitha
10 Workshop 19th Mar2013 IITMadras CertificateAwarded
(10F61A0118)
M.Harish
11 Symposium 8th&9th Mar2013 SVCET,Chittoor CertificateAwarded
(10F61A0113)
P.DevendraNaidu
12 Symposium 8th&9th Mar2013 SVCET,Chittoor CertificateAwarded
(10F61A0109)
P.Mounika
13 Symposium 8th&9th Mar2013 SVCET,Chittoor CertificateAwarded
(11F61A0108)
P.Mounika
14 Symposium 8th&9th Mar2013 SVCET,Chittoor CertificateAwarded
(11F61A0108)
D.Bharathi
15 Workshop 4th&5th Feb2013 SVCE,Tirupathi CertificateAwarded
(11F65A0104)
Ch.Praveen
16 Workshop 9th&10th Dec2013 SVCE,Tirupathi CertificateAwarded
(10F61A0130)
U.Manjunath
17 Symposium 15th Mar2014 JNTU,Anantapur CertificateAwarded
(12F61A0127)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 73/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
U.Manjunath
18 Symposium 13th Mar2014 RGM,Kurnool CertificateAwarded
(12F61A0127)
K.Lavanya
19 Symposium 26thFeb2013 SIST,Puttur CertificateAwarded
(11F61A0122)
CAYm2:201213
S.KhajaNayabRasool
1 Symposium 20th Mar2012 SVIST,Madanapalle 1st Prize
(09F61A0134)
S.KhajaNayabRasool
2 Symposium 11th Mar2012 AITS,Tirupathi 2nd Prize
(09F61A0134)
S.KhajaNayabRasool
3 Symposium 22ndMar2012 SVNE,Tirupathi 1st Prize
(09F61A0134)
N.SarathKumar
4 Symposium 20th Mar2012 SVIST,Madanapalle 1st Prize
(09F61A0130)
M.P.Rajan
5 Symposium 22th Mar2012 AITS,Tirupathi 2nd Prize
(09F61A0125)
M.P.Rajan
6 Symposium 21st Mar2012 KKC,Puttur 1st Prize
(09F61A0125)
S.KhajaNayabRasool
7 Symposium 29thJan2012 SVIST,Madanapalle 1st Prize
(09F61A0134)
M.P.Rajan
8 Symposium 09th&10th Mar2012 SVU,Tirupathi 1st Prize
(09F61A0125)
CSasidhar
9 Symposium 10th Mar2012 SIST,Puttur 1st Prize
(10F61A0137)
KYBabhitha
10 Symposium 25th Jan2012 KMM,Tirupathi 2nd Prize
(10F65A0103)
T.UmaMaheshwari
11 Symposium 25th Jan2012 KMM,Tirupathi 1st Prize
(09F61A0142)
K.Kavya
12 Symposium 21st&22nd 2011 VishvodayaTechnicalAcademy 2nd Prize
(08F61A0116)
KSailaja
13 PosterPresentation 28th Sep2011 SVCET,Tirupathi 3rd Prize
(09F61A0129)
YNimeelika
14 Symposium 28th Sep2011 SVCET,Tirupathi CertificateAwarded
(08F61A0130)
YNimeelika
15 Symposium 21st&22nd 2011 VishvodayaTechnicalAcademy 2nd Prize
(08F61A0130)
YNimeelika
16 Symposium 21st&22nd 2011 VishvodayaTechnicalAcademy CertificateAwarded
(08F61A0130)
U.Manjunath
17 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 74/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(11F61A0130)
K.Lavanya
18 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0122)
N.Bhargavi
19 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0108)
G.MaheshKumar
20 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0127)
G.MaheshKumar
21 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0127)
B.Madhu
22 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0125)
L.Mallikarjuna
23 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0128)
P.DilipKumar
24 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0113)
N.Bhargavi
25 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0108)
V.Madhupriya
26 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0124)
K.Lavanya
27 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0122)
S.MaheshBabu
28 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0126)
T.Reddaiah
29 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0142)
S.MukeshKumar
30 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0132)
PBalasubramanyam
31 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0105)
BAvinash
32 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0103)
PHarijyothi
33 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0117)
UManjunath
34 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0130)
PAshok
35 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0102)
KKavya
36 Symposium 9th&10th Jan2012 KSRM,Kadapa CertificateAwarded
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 75/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(08F61A0116)
YNimeelika
37 Symposium 9th&10th Jan2012 KSRM,Kadapa CertificateAwarded
(08F61A0130)
PSKarthik
38 Symposium 18th&19th Feb2012 SVNE,Tirupathi CertificateAwarded
(10F61A0117)
PSKarthik
40 Symposium 9th&10th Mar2012 SVU,Tirupathi CertificateAwarded
(10F61A0117)
C.H.Praveen
41 Symposium 10th Mar2012 SIST,Puttur CertificateAwarded
(10F61A0130)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 76/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5FACULTYINFORMATIONANDCONTRIBUTIONS(200) TotalMarks186.29
InstituteMarks
Note:PleaseprovidecumulativeinformationforalltheshiftsforthreeassessmentyearsinbelowformatinAnnexureII.
20122013
Distributionofteachingload(%) AcademicResearch
Qualification
Allthe Faculty
Degree Dateof UG Sponsored
Designations receiving Consultancy
Nameofthefaculty (starting Current joining Fromother Fromthis Research Research
Yearof sincejoining 1st Serving Ph.Dduring Ph.D andProduct Specialization
member offrom University Designation the programme programme PG Paper (Funded
Graduation the Year 100%in the Guidance Development
highest Institution tothis toother Publications Research)
Instituition programme assessment
degree) programme programme
year
GeoHydrology
Dr.S.SiddiRaju PhD S.V.University 1994 Professor Professor 27/06/2011 0.00 100 0.00 0.00 0.00 No 0 8 0 0 andWater
Resources
Water
Dr.K.Chandrasekhar
PhD S.V.University 2011 Professor Professor 01/07/2011 0.00 100 0.00 0.00 0.00 No 0 2 0 0 Resource
Reddy
Engineering
TNTech
ME/M Univ., Assistant Assistant Transportation
Y.MuraliKrishna 2005 18/06/2012 0.00 100 0.00 0.00 0.00 No 0 0 0 0
Tech Cookeville, Professor Professor Engineering
USA
Water
ME/M NIT Assistant Assistant
N.Cheeralaiah 2003 04/07/2012 0.00 100 0.00 0.00 0.00 No 0 0 0 0 Resource
Tech Warangal Professor Professor
Engineering
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 77/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Assistant Assistant
R.Nagarjuna M.Sc. S.V.University 2008 04/07/2011 0.00 0 50.00 0.00 0.00 No 0 0 0 0 Mathematics
Professor Professor
Dr.P.Subramanyachari PhD S.V.University 2007 Professor Professor 30/08/2009 0.00 0 50.00 0.00 0.00 No 0 0 0 0 MBA
Assistant Assistant
S.Kishore M.Sc. S.V.University 2007 29/06/2009 0.00 0 50.00 0.00 0.00 No 0 0 0 0 English
Professor Professor
20132014
Distributionofteachingload(%) AcademicResearch
Qualification
Allthe Faculty
Degree Dateof UG Sponsored
Designations receiving Consultancy
Nameofthe (starting Current joining Fromother Fromthis Research Research
Yearof sincejoining 1st Serving Ph.Dduring Ph.D andProduct Specialization
facultymember offrom University Designation the programme programme PG Paper (Funded
Graduation the Year 100%in the Guidance Development
highest Institution tothis toother Publications Research)
Instituition programme assessment
degree) programme programme
year
GeoHydrology
Dr.S.SiddiRaju PhD S.V.University 1994 Professor Professor 27/06/2011 0.00 100 0.00 0.00 0.00 No 0 0 0 0 andWater
Resources
Water
Dr.K.Chandrasekhar
PhD S.V.University 2011 Professor Professor 01/07/2011 0.00 100 0.00 0.00 0.00 No 0 8 0 0 Resource
Reddy
Engineering
Assistant
ME/M Associate Professor, Geotechnical
K.PrakashChandra S.V.University 2005 01/07/2011 0.00 100 0.00 0.00 0.00 No 0 0 0 0
Tech Professor Associate Engineering
Professor
TNTech Assistant
ME/M Univ., Associate Professor, Transportation
Y.MuraliKrishna 2005 18/06/2012 0.00 100 0.00 0.00 0.00 No 0 0 0 0
Tech Cookeville, Professor Associate Engineering
USA Professor
Water
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 78/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
N.Cheeralaiah ME/M NIT 2003 Assistant Assistant 04/07/2012 0.00 100 0.00 0.00 0.00 No 0 0 0 0 Resource
Tech Warangal Professor Professor Engineering
Assistant Assistant
S.Kishore M.Sc. S.V.University 2007 29/06/2009 0.00 0 50.00 0.00 0.00 No 0 0 0 0 English
Professor Professor
Assistant Assistant
R.JyothsnaDevi Other JNTUA 2008 29/06/2009 0.00 0 50.00 0.00 0.00 No 0 0 0 0 MBA
Professor Professor
20142015
Distributionofteachingload(%) AcademicResearch
Qualification
Allthe Faculty
Degree Dateof UG Sponsored
Designations receiving Consultancy
Nameofthefaculty (starting Current joining Fromother Fromthis Research Research
Yearof sincejoining 1st Serving Ph.Dduring Ph.D andProduct Specialization
member offrom University Designation the programme programme PG Paper (Funded
Graduation the Year 100%in the Guidance Development
highest Institution tothis toother Publications Research)
Instituition programme assessment
degree) programme programme
year
Geo
Hydrologyand
Dr.S.SiddiRaju PhD S.V.University 1994 Professor Professor 27/06/2011 0.00 100 0.00 0.00 0.00 No 0 13 0 0
Water
Resources
Water
Dr.K.Chandrasekhar
PhD S.V.University 2011 Professor Professor 01/07/2011 0.00 100 0.00 0.00 0.00 No 0 13 0 0 Resource
Reddy
Engineering
ME/M Bharathiyar
2000 Associate Associate Structural
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 79/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C.PrabhakarReddy Tech University Professor Professor 06/07/2011 0.00 100 0.00 0.00 25.00 No 0 0 0 0 Engineering
Assistant
ME/M Associate Professor, Geotechnical
K.PrakashChandra S.V.University 2005 01/07/2011 0.00 100 0.00 0.00 0.00 No 0 0 0 0
Tech Professor Associate Engineering
Professor
TNTech Assistant
ME/M Univ., Associate Professor, Transportation
Y.MuraliKrishna 2005 18/06/2012 0.00 100 0.00 0.00 0.00 No 0 0 0 0
Tech Cookeville, Professor Associate Engineering
USA Professor
Water
ME/M NIT Assistant Assistant
N.Cheeralaiah 2003 04/07/2012 0.00 100 0.00 30.00 0.00 No 0 0 0 0 Resource
Tech Warangal Professor Professor
Engineering
Water
G.Shanmukha ME/M Assistant Assistant
S.V.University 2014 01/07/2014 0.00 100 0.00 0.00 0.00 No 0 0 0 0 Resource
Srinivas Tech Professor Professor
Engineering
Associate Associate
Dr.S.Kishore PhD S.V.University 2013 01/10/2013 0.00 0 50.00 0.00 0.00 No 0 0 0 0 MBA
Professor Professor
Assistant Assistant
S.Kishore M.Sc. S.V.University 2007 29/06/2009 0.00 0 50.00 0.00 0.00 No 0 0 0 0 English
Professor Professor
5.1StudentFacultyRatio(20) TotalMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 80/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
InstituteMarks
S:Fratio=N/FN=No.ofstudents=3*Xwherexis(approvedintake+20%lateralentryintake+separatedivision,ifany)
F=No.offaculty=(a+bc)foreveryassessmentyear
a:TotalnumberoffulltimeregularFacultyservingfullyto2nd,3rdand4thyearofthethisprogram
b:TotalnumberoffulltimeequivalentregularFaculty(consideringfractionalload)servingthisprogramfromotherProgram(s)
c:TotalnumberoffulltimeequivalentregularFaculty(consideringfractionalload)ofthisprogramservingotherprogram(s)
RegularFacultymeans:
Fulltimeonrollwithprescribedpayscale.AnemployeeoncontractforaperiodofmorethantwoyearsANDdrawingconsolidatedsalarymorethanapplicablegrosssalaryshallonlybecountedasaregularemployee.
PrescribedpayscalesmeanspayscalesnotifiedbytheAICTE/CentralGovernmentandimplementationasprescribedbytheStateGovernment.IncaseStateGovernmentprescribeslesserconsolidatedsalaryforaparticularcadrethensamewillbe
consideredasreferencewhilecountingfacultyasaregularfaculty.
Markstobegivenproportionallyfromamaximumof20toaminimumof10foraverageSFRbetween15:1to20:1,andzeroforaverageSFRhigherthan20:1.
AverageSFRforthreeassessmentyears:14.65
AssessmentSFR:20.00
5.2FacultyCadreProportion(25) TotalMarks
InstituteMarks
ThereferenceFacultycadreproportionis1(F1):2(F2):6(F3)
F1:NumberofProfessorsrequired=1/9xNumberofFacultyrequiredtocomplywith15:1StudentFacultyratiobasedonno.ofstudents(N)asper5.1
F2:NumberofAssociateProfessorsrequired=2/9xNumberofFacultyrequiredtocomplywith15:1StudentFacultyratiobasedonno.ofstudents(N)asper5.1
F3:NumberofAssistantProfessorsrequired=6/9xNumberofFacultyrequiredtocomplywith15:1StudentFacultyratiobasedonno.ofstudents(N)asper5.1
CadreRatioMarks[(AF1/RF1)+[(AF2/RF2)*0.6]+[(AF3/RF3)*0.4]]*12.5:35.55
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 81/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5.3FacultyQualification(25) TotalMarks
InstituteMarks
FQ=2.5x[(10X+6Y)/F)]
whereXisno.ofregularfacultywithPh.D.,
Yisno.ofregularfacultywithM.Tech.,
Fisno.ofregularfacultyrequiredtocomply1:15FacultyStudentratio(no.offacultyandno.ofstudentsrequiredaretobecalculatedasper5.1)
X Y F FQ=2.5x[(10X+6Y)/F)]
AverageAssessment:18.29
5.4FacultyRetention(25) TotalMarks
InstituteMarks
NoofFacultyRetained 10 14 15
TotalNoOfFaculty 15 17 19
%ofFacultyRetained 67 82 79
Average:75.99
AssessmentMarks:20.00
5.5InnovationsbytheFacultyinTeachingandLearning(20) TotalMarks
InstituteMarks
InnovationsbytheFacultyinteachingandlearningarefollows:
a.InstructiondeliveryandInstructionalmethods:
Thefacultyusesthechalkandboardtoteachthecurriculumintheclassroom.
ThecoursesalsoaredeliveredusingtheLCDProjectors.
ThemembersoftheFacultyusetheelearningresourcesfromNationalProgrammeonTechnologyEnhanced(NPTEL).
Demonstrationwiththeworkingmodels,charts,componentsetc.,intheclassroomforbetterunderstanding.
Opencourseware,webinarsfromnationalandinternationalorganizationsarepresentedtothestudents.
AnimationvideoswhichexplainintheEclassroomfortheeffectiveteaching.
Conductingtheseminars,groupdiscussions,quizetc.,intheclassrooms.
Eachfacultyteachesthecontentbeyondthesyllabusonadvancedtopicsofthesubject.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 82/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Guestlecturers,workshops,seminarsbytheeminentpeoplefromIndustry,AcademicandResearchInstitutionsarearrangedbytheDepartment.
Symposiumsandconferencesareorganizedtosharetheirinnovativeideaswithothers.
b.PrintedLabmanualsandlabobservationbooks:
Labmanualswithsamplereadingsareavailableinthelaboratoriesforthestudentsreference.
Allthelabmanualsarerevisedandupdatedeveryyearandwheneversyllabusisrevised.
Theprintedobservationsareprovidedtothestudentswithalltheexperiments.
Conducting2or3design/additionalexperimentsinadditiontotheuniversitycurriculumtofillthegapandimprovetheirpracticalknowledge.
Thestudentsareencouragedtodotheminiprojectsinthelaboratory.
Charts,labinformationpostersareplacedineachlabforreference.
c.LecturenotesandQuestionbank:
Thelecturenotesandpowerpointpresentationsofeachcoursearepreparedbythefaculty.
Theprintedobjectiveanddescriptivequestionsarecirculatedtothestudents.
LecturenotesandQuestionbankofeachcourseareavailableinthecollegewebsiteforpeerreviewofstudentsaswellasthefacultywhoishandlingthenewcourse.
d.IndustrialVisits:
Industrialvisitsarefrequentlyconductedtoenhancerealtimeexposureoftechnology.
OurstudentshaverecentlyvisitedKalyaniDamTirupathi,CheyyurDam,AraniarprojectinPichatur,RayalaseemaThermalPowerPlant(RTPP)Kadapa,MangampetaMining,SrisailamDam(Leftbank)etc.
e.Assessment:
MandatoryAssessment
AspertheUniversityexaminationpattern,twomidtermtestandonefinalexaminationareconductedforeachsubject.
MidtermtestsareevaluatedbytheinternalfacultyandfinalexaminationisevaluatedbytheUniversity.
Inthecaseofapracticalcourse,studentsareevaluatedonanongoingbasisinternallyandthenafinalexternalexamination.
AdditionalAssessment
Informalquiz,assignments,seminarsetc.,attheendofeachunittoensureproperunderstandingoftheconceptsbythestudents.
Additionalunittests,sliptestsareconductedaftercompletionofeachunit.
f.Evaluation:
FormativeEvaluation
Inthecaseoftheorysubjects,cumulativeevaluationisbasedontheclasstests,unittests,assignmentsandseminarsthatareconductedsoonaftercompletionofspecificnumberofunitsofthesyllabus.
Inthecaseofpracticalsubjects,thestudentsarecontinuouslyevaluated.Soonafterperforminganexperiment,thestudentshavetopreparetherecordofobservationsandsubmitthesameforreviewbyconcernedfaculty,beforeattendingthenextlaboratorysession.
Internalevaluationofprojectworkisdoneperiodicallybyconductingreviews.
SummativeEvaluation
Theinstitutionhasapolicyofannouncingtheresultsofmidtermexaminationswithintwodaysafterthelastexam.
AllthefacultiesstrictlyadheretothispolicyandthesameisensuredbytheHODsandthePrincipalbyconductingperiodicalreviews.
Evaluationofendsemesterexaminations(theoryandpracticalsubjects)isconductedbytheUniversity.
Evaluationofprojectworkisalsodonebytheuniversity.
5.6FacultyasparticipantsinFacultydevelopment/trainingactivities/STTPs(15) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 83/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Max5PerFaculty
Nameofthefaculty
20142015 20132014 20122013
RF=NumberofFacultyrequiredtocomplywith15:1Student
14.40 14.40 14.40
FacultyRatioasper5.1
Averageassessmentover3years:15.42
5.7ResearchandDevelopment(30) TotalMarks
5.7.1AcademicResearch(10) InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 84/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Academicresearchincludesresearchpaperpublications,Ph.D.guidance,andfacultyreceivingPh.D.duringtheassessmentperiod.
Numberofqualitypublicationsinrefereed/SCIJournals,citations,Books/BookChaptersetc.(6)
Ph.D.guided/Ph.D.awardedduringtheassessmentperiodwhileworkingintheinstitute(4)
Allrelevantdetailsshallbementioned.
a.No.ofQualityPublications:
InstitutionR&Distakingcareofthepublicationofqualitypapersinreferredjournals.Itprovidesthefacilitieslikeinternet,computing,informationregardingInternationalconferencesandjournalpublications.Institutionprovidesthepublicationfees,travellingallowancesandOD.
Thepublicationofourfacultyinpeerreviewedjournals.
AcademicYear
NameoftheFaculty
201415 201314 201213
Dr.S.SiddiRaju 13 8
Dr.K.ChandrasekharReddy 13 8 2
Dr.N.KrishnaMurthy 1 4
S.AnandKumarVarma 4
M.PavanKumar 1
b.BooksPublished:
Detailsof
S.No. NameoftheFaculty Year TitleofBook ISBNNumber
publishers
WaterResourcesAssessment CreativeSpace
1 Dr.S.SiddiRaju 201314 139781494480448
andManagement Publications
HydroGeologyand
Geochemicalaspectsof LambertAcademic
2 Dr.S.SiddiRaju 201213 9783659464171
Pullampeta,kadapaDist., Publications
A.P.
PerformanceofHighSchool Discovery
3 Dr.S.SiddiRaju 201112 9789350561126
ChildreninPhysicalSciences PublishingHouse
c.Ph.D.awardedduringassessmentperiodwhileworkingintheinstitute:
5.7.2SponsoredResearch(5) InstituteMarks
20142015
TotalAmount(X):2900000.00
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 85/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
20132014
0.00
TotalAmount(Y):0.00
20122013
0.00
TotalAmount(Z):0.00
CumulativeAmount(X+Y+Z)=2900000.00
5.7.3DevelopmentActivities(10) InstituteMarks
Providedetails:
ProductDevelopment
Researchlaboratories
Instructionalmaterials
Workingmodels/charts/monogramsetc.
ProductDevelopment:
Thedepartmentencouragesstudentsandstafftodeveloptheproducts.
Researchlaboratories:
ThereisaseparateR&DCellwhichcaterstheneedsofthestudentsandfacultyintermsofresourcesandcomputingfacilities.
R&Dcellconsistsofworkingmodels,projectmodulesandprojectbooks.
Facilitieslikeprintingreprography,scanningetc.,areavailable.
MicrosoftandIBMinnovationcentersareestablishedintheinstitutiontodevelopsoftwareapplications.
Instructionalmaterials:
Alllabmanualsaredevelopedbyourfaculty.
Booksandprintedmaterialrelatedtoadvancedtopicsmadeavailable.
InformationregardingtheConstructionTechnology,MSProjectandAutoCADsoftwareusageisavailableinhardandsoftcopyform.
Workingmodels/charts/monogramsetc.:
Alltheprojectworkingmodelspreservedforreferenceinprojectlab.
Ineverylabthetechnicalinformationchartsandmodelsaredisplayedwhicharepreparedbyourstaffandstudents.
Subjectrelatedinformationchartsareplacedonwalls.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 86/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5.7.4Consultancy(fromIndustry)(5) InstituteMarks
(ProvidealistwithProjectTitle,FundingAgency,AmountandDuration)Fundingamount(Cumulativeduringassessmentyears)
20142015
20132014
20122013
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 87/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
CumulativeAmount(X+Y+Z)=
5.8FacultyPerformanceAppraisalandDevelopmentSystem(FPADS)(30) TotalMarks
InstituteMarks
Awelldefinedsystemforfacultyappraisalforalltheassessmentyears(10):
Wehavewelldefinedsystemforfacultyappraisalswiththepersonal,academic,experience,trainingandevaluation,andresearchetc.
Itsimplementationandeffectiveness(20):
AttheendofeachacademicyearfacultyappraisalisassessedbytheHODandforwardedtotheprincipal.Theprincipalfurtherassesthedetailsandrecommendthefacultybasedontheirperformancetothemanagement.
SIDDHARTHINSTITUTEOFENGINEERING&TECHNOLOGY
AnnualSelfAssessmentforthePerformanceBasedAppraisalSystems(PBAS)
AcademicYear___________________________
PARTAGENERALINFORMATION
1.Name(inblockletters):
2.Department:
3.CurrentDesignation&GradePay:
4.DateoflastPromotion:
5.Whetheracquiredanydegreeorfreshacademicqualificationsduringtheyear:
PARTBACADEMICPERFORMANCEINDICATORS
CATEGORY:I.TEACHINGLEARNINGANDEVALUATIONACTIVITIES
(i)Lectures,Seminars,Practicals,ContactHours
Noofclasses %ofclasses/practicalstaken
S.No Course Level(UG/PG) Noofclassespercourseallotted
attended asperdocumentedrecord
ClassesTaken(Max250for100%performance&proportionatescoreupto80%performance,bellowwhichnoscoremaybegiven)
(Markslimitedto250)
(ii)Reading/Instructionalmaterialconsultedandadditionalknowledgeresourcesprovidedtostudents
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 88/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
APIscoreonpreparationandimpartingofknowledge/instructionaspercurriculum&syllabusenrichmentbyprovidingadditional
resourcetostudents(maxscore:50)
(Markslimitedto50)
(iii)UseofparticipatoryandinnovativeteachingLearningmethodologies,Updatingofsubjectcontent,courseimprovementetc.
SNo ShortDescription
UseofparticipatoryandinnovativeteachingLearningmethodologies,Updatingofsubjectcontent,courseimprovementetc.
(Markslimitedto100)
(iv)ExamDutiesAssignedandPerformed
Extenttowhichcarried
S.No TypeOfExaminationDuties DutiesAssigned
out(%)
Examinationduties(Invigilationquestionpapersetting,evaluation/assessmentofanswerscripts)asperallotment
(Markslimitedto100)
CATEGORY:IICOCURRICULAR,EXTENSION,PROFESSIONALDEVELOPMENTRELATEDACTIVITIES
Pleasementionyourcontributiontoanyofthefollowing:
(i)Extension,Cocurricular&fieldbasedActivities
Studentrelatedcocurricular,extensionandfieldbasedactivities
TotalAPI
Score Byfaculty Byscreeningcommittee
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 89/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(Marks
limited
to100)
Yearly/Semesterwise
(ii)Contributiontocorporatelifeandmanagementoftheinstitution
responsibilities
Contributiontocorporatelifeandmanagementofthedepartment&institutethroughparticipationinacademicand
administrativecommitteesandresponsibilities
TotalAPI
Byfaculty Byscreeningcommittee
Score
(Marks
limitedto
100)
(iii)ProfessionalDevelopmentActivities
Participationinseminars,conferences,shorttermtrainingcoursesetc.
TotalAPI
Byfaculty Byscreeningcommittee
Score
(Marks
limitedto
50)
TotalAPIscoreforCATEGORY:II
TotalAPI
Score Byfaculty Byscreeningcommittee
(Marks
limitedto
250)
CATEGORY:III.RESEARCH,PUBLICATIONSANDACADEMICCONTRIBUTIONS
A)Publishedpapersinjournals
Byscreening
TotalAPIScore Byfaculty
committee
(Markslimitedto50)
B(i))Articles/chapters/labmanuals/bookspublished
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 90/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Tilewithpage BookTitle, Whetherpeer
S.No editor& ISSN/ISBNNo Noofcoauthors
nos. reviewed.
publisher
(Markslimitedto30)
(ii))paperinconferenceproceedings
(Markslimitedto20)
IIIC)OngoingandcompletedResearchProjectsandconsultancies
(C)projects/Consultancies
Grant/Amount
S.No Tile Agency Period Status
Mobilized(Rslakh)
(Markslimitedto50)
(D)ProjectGuidance
UG
PG
Ph.D
(Markslimitedto50)
(E)(i)Trainingcourses,TeachingLearningEvaluationtechnologyprogrammes,FacultyDevelopmentProgrammes
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 91/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(Markslimitedto10)
(ii)Paperspresentedinconferences,Seminars,Workshops,Symposia
Titleof Whetherinternational
S.No Tileofthepaperpresented conference/ Organizedby /national/state/regional/college/university
Seminar level
(Markslimitedto20)
(iii)Invitedlecturesandchairmanshipsatnational/internationalconference/seminaretc.
Titleof Whether
Tileoflecture/Academic conference/
S.No Organizedby international
session
Seminaretc /national
(Markslimitedto10)
TotalAPIScore
Byscreening
TotalAPIScore Byfaculty
committee
(Markslimitedto50)
IV.SUMMARYOFAPISCORES
Teaching,Learningand
I
Evaluationrelatedactivities
Cocurricular,Extension,
II
Professionaldevelopmentetc
ResearchandAcademic
III
Contribution
PARTCOTHERRELEVANTINFORMATION
Pleasegivethedetailsofanyothercredentials,significantcontributions,awardsreceivedetc.notmentionedearlier
SNo Details(MentionYear,valueetc.,whererelevant)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 92/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
LISTOFENCLOSUERS:(Pleaseattach,copiesofcertificates,sanctionorders,papersetc)
14
25
36
Icertifythattheinformationprovidediscorrectasperrecordsavailablewiththecollegeand/ordocumentsenclosedalongwiththedulyfilledPBASproforma.
Signatureofthefaculty
HODcomments
Principalcomments
SignatureoftheHODSignatureofthePRINCIPAL
5.9Visiting/Adjunct/EmeritusFacultyetc.(10) TotalMarks
InstituteMarks
Wehavetheprovisionofinvitingtheexpertsfromindustry,academicinstitutions,scientistandeminentpersonalitiesinthefieldoftechnologytoimprovetechnicalknowledgeonadvancedtopics,teachingskills,researchandpersonalitydevelopmentofourfacultyandstudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 93/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Thefollowingthelectures/interactionsareorganizedbythedepartment.
No.ofHours TotalNo.ofHours
NameoftheAdjunctFaculty Designation Organization TopicGiven Date(s)
Organized OrganizedperYear
AY:20152016
OpportunitiesinConstruction&
Dr.K.N.Satyanarayana Professor IITMadras 4 07102015
InfrastructureinIndia
RejunevationofGroundWaterTable
NTRTeluguGanga
Sri.P.V.SubhaRao SuperintendingEngineer 5 throughRainwaterHarvestingin 14082015
Project,Tirupati
ChittoorDist.,A.P.
PullaReddyEngineering 50
Dr.T.ChandraSekharReddy Professor 5 ConstructionTechniques 02082015
College,Kurnool
ToolsAcademyfor
Founder&MDofBuild
Mr.P.VasudevaMurthy CareerExcellence, 10 Cement&ConcreteTechnology 23&24092015
Bizzonlinepvtltd.
Bengaluru
CAY:20142015
ExecutiveEngineer SustainableWaterResources
Mr.KamalnathanShetty I&CADDept.Tirupati 5 15092014
(Retted.) DevelopmentinDroughtProneAreas
HSSBIMSolutions ApplicationsofRevitArchitecture,
Mr.VetrivelShanmugam Manager 5 09012015
Pvt.Ltd.,Chennai ArchiCAD,inCivilEngineering
HSSBIMSolutions 27,28&2901
Mr.DibyenduBiswas DesignEngineer 10 RevitArchitecture
Pvt.Ltd.,Chennai 2015
I&CAD,Govt.ofA.P.,
Mr.Elumalai Asst.Exe.Engineer 4 InterlinkingofTanks 22082014
Puttur
CivilEngineeringPracticesforCivil
Dr.V.RangaRao Professor&Principal CheeralaEngg.College 5 30072014
Engineers
CAYm1:20132014
AudishankaraCollege,
Prof.C.Venumadhav Professor&HOD 5 GreenBuildings 26022014
Gudur
DevelopmentinRoadTransportation
Mr.ChengalReddy DVM APSRTC,Tirupathi 5 07022014
inIndia
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 94/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
AssociateProfessor& Analysis&StabilityofReinforced
Mr.O.EswarReddy SVEC,Rangampet 5 29012014
HOD EarthStructures 52
GlobalEngineering ApplicationsofRS&GISinCivil
Mr.MaruthiMohanReddy AssociateProfessor 5 19082013
College,Kadapa Engineering
CAYm2:20122013
ToolsAcademyfor Cement&ConcreteTechnology
Founder&MDofBuild
Mr.P.VasudevaMurthy CareerExcellence, 10 (Constructionsite&Industry 10&11032013
Bizzonlinepvtltd.
Bengaluru Oriented)
RejunevationofGroundWaterTable
NTRTeluguGanga
Sri.P.V.SubhaRao SuperintendingEngineer 5 throughRainwaterHarvestingin 04022013
Project,Tirupati
ChittoorDist.,A.P.
OpportunitiesinConstruction&
Dr.K.N.Satyanarayana Professor IITMadras 4 08102012
InfrastructureinIndia
RoleofMineralAdmixtureson
Mr.VijayaSekharReddy HOD SKIT,Srikalahasthi 5 10012013
Concrete
I&CAD,Govt.ofA.P.,
Mr.Elumalai Asst.Exe.Engineer 5 InterlinkingofTanks 14022013
Puttur
Professor, DesignofReinforcedConcrete
Dr.I.V.RamanaReddy S.V.University 5 28022013
Dept.ofCivilEngineering Structures
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 95/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
6FACILITIESANDTECHNICALSUPPORT(80) TotalMarks80.00
6.1Adequateandwellequippedlaboratories,andtechnicalmanpower(30) TotalMarks
InstituteMarks
Weekly TechnicalManpowerSupport
Numberof
utilization
students Nameof
Sr. Nameofthe status(allthe
perset NameoftheImportantEquipment the
No Laboratory coursesfor Designation Qualification
up(Batch Technical
whichthelabis
Size) staff
utilized)
SurveyingLab
I& K. Lab Diploma
1 3 1.Theodolite2.Totalstation 4sessions
SurveyingLab Murugesan Technician (Civil)
II
1.TorsionTestApparatus2.UniversalTesting
Strengthof Lab
2 3 Machine3.SpringTestingMachine4.Impact 8Sessions C.Rajesh ITI
MaterialLab Technician
TestingMachine5.Hardnesstestingmachine
Fluid 1.Venturimeter2.OrificeMeter3.Centrifugal
Mechanics Pump4.MultiStageCentrifugalPump5.
Lab
3 AndHydraulic 3 ReciprocatingPump6.PipeFriction 12Sessions M.Lokaiah ITI
Technician
Machinery Apparatus7.ImpactofJetOnVanes
Lab Apparatus
Concrete
Technology& 1.Aggregatecrushingtest2.Losangles Lab B.Tech
5 4 4sessions S.Sameer
Highway Abrasiontest3.Reboundhammer Technician (Civil)
MaterialsLab
Geotechnical 1.Casagrandesapparatusforliquidlimit,
C. Lab
6 Engineering 3 plasticlimit.2.Corecutter3.Sand 2sessions B.Tech(Civil)
JyothiBabu Technician
Lab Replacement
Environmental
Lab B.Tech
7 Engineering 1 1.pHmeter2.Turbiditymeter 2sessions A.Naresh
Technician (Civil)
Lab
1.EquippedWith36I32GProcessorMake
SystemsInstalledWithWindowsXP,Modeling
J.Suresh& Lab
8 CADLab 1 AndAnalysis2.Softwares,WithDVDWriter 8Sessions B.Tech
V.Mamatha Technician
anUSBDrivePeripherals,Printer,Scanner,
Internet,etc.
6.2Additionalfacilitiescreatedforimprovingthequalityoflearningexperienceinlaboratories(25) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 96/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
No FacilityName Details Reason(s)forcreatingfacility Utilization enhancedlearning POs/PSOs
Tostudythecompressivestrengthofcubes 69StudentsfromIII
1 Compressivetesting(ConcreteTechnologyLab) CTMCapacity20Tones ConcreteTechnology PO2,PO3&PSO2
byusingFlyAsh B.Tech
Tostudythedesign&analysisofdifferent 61StudentsfromIV
3 Designofstructures(CADLab) STAADPROV8i CAD PO3,PO2&PSO3
structures B.Tech
6.3Laboratories:Maintenanceandoverallambiance(10) TotalMarks
InstituteMarks
Themaintenanceandambiancemeasuresinthelaboratoriesare:
Calibrationofequipmentatthebeginningofeverysemester.
Alllaboratoryequipmentarekeptinconditionbeforethecommencementofthesemester.
Laboratoryequipmentareservicedandmaintainedeveryweek.
Maintenancebookisavailableineachlaboratory
Readinessoflaboratorymanuals&plans.
Maintainingthestudentslogbooks.
Listofexperiments,equipmentdetailsandsafetymeasuresaredisplayedineachLaboratory.
LaboratoryEquipmentsareverifiedasinStockRegisterswithLabIncharge,HODeveryacademicyear.
Computersystemsaredailycleanedandareservicedasandwhenrequired.
Maintaininglicenseisverifiedandupdated.
Faultyequipmentisrepairedbytheserviceagents.
Laboratoriesareregularlycleaned.
Alllaboratoriesarehavinggoodventilation.
Alllaboratoriesarefurnishedwithfurniture.
Alllaboratoriesarespaciousandtidy.
Alllaboratoriesarehavingluminouslighting.
Alltheequipmentsarewellorganizedineachandeverylaboratory.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 97/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 98/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
6.4Projectlaboratories(5) TotalMarks
InstituteMarks
Mentionfacilities&Utilization
TheDepartmenthasseparateprojectlaboratorywiththelatestequipmentandsystems,somanylivemodelswhicharedonebythestudents.Italsocontainsotherfacilitiessuchasinternet,reprographic,scanning,printer,stationaryetc.Allthepreviousprojectreportsareavailableforreadyreference.TheProjecthoursareallocatedinthe
regulartimetable.Thestudentsarealsoallowedtodotheirprojectsbeyondtheworkinghours.
Theprojectcoordinatorconductsasessionduringtheirthirdyearintheprojectlaboratoryandexplainsabouttheprojectworkwhichtheywilldointheirfinalyear.Duringthesessiontheygettheguidelinestogroupformationwithidealsizeandcomplementarypersonalcapabilitiesasgroupmembers.Thevariousareasoftheproject,
technology,recenttrends,andpossiblesampleproblemstatementsperprojectarenarratedtothestudents.
Facilitiesandtheirutilizationintheprojectlaboratory
2 STAADpro V8i Todesignandanalysisofbuildingstructures
3 Curingtank 3.6x1x0.6m Curingofconcretecubesandbeams
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 99/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
HPLaserJet
4 Printer&Scanner, Toprintandscanningofprojectdocuments
M126
PROJECTLAB
6.5Safetymeasuresinlaboratories(10) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 100/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5 ConcreteTechnology&HighwayMaterialsLab Apron Shoes Handglosses Safetyinstructionsare
displayed Fireextinguishers FirstAidBox Sufficient
widthofexit TwoNumberofexits
7CONTINUOUSIMPROVEMENT(50) TotalMarks50.00
7.1ActionstakenbasedontheresultsofevaluationofeachofthePOs&PSOs(20) TotalMarks
InstituteMarks
IdentifytheareasofweaknessesintheprogrambasedontheanalysisofevaluationofPOs&PSOsattainmentlevels.MeasuresidentifiedandimplementedtoimprovePOs&PSOsattainmentlevelsfortheassessmentyears
POsAttainmentLevelsandActionsforImprovement(20142015)
PO1:EngineeringKnowledge
1.ET&MT:LackinginDCMotors.2.BMC:Unabletounderstandthemanufacturingprocessesofmaterialslike
bricks,limeandcementetc.3.H&HM:Lackofknowledgeonfunctioningofventurimeterandorificemeter.4.
WREII:Lackofknowledgeondrainagegalleries5.CT:Studentsarelackingknowledgeonpretensioningand
PO1 3 2.20
posttensioningofconcrete.6.SAII:Studentsarelackingaboutredundantforcesanddeflectionwherethey
occurandhowtheywilloccur.7.SAI:Unabletounderstandtheconceptsofinfluencelines.8.DDSS:Lackof
knowledgeonbeamdesignrequirementsasperI.S.coderecommendations.
Action1:WorkshopsonoperationofDCMotors.Action2:Industrialvisitstothemanufacturingunitsofcement,limeandbricks.Action3:NPTELvideosonfunctioningofVenturimeterandorificemeter.Action4:Visitingdamstoshowdrainagegalleries.
Action5:Workshopsbyexpertsfromindustryonpretensioningandposttensioningofconcrete.Action6:Demonstrationwithmodelsandfieldtrips.Action7:Guestlecturesoninfluencelines.Action8:Morepracticingsessionsondesignanddrawingof
steelstructuresasperIScoderecommendations.
PO2:ProblemAnalysis
1.H&HM:Lackofknowledgeonfunctioningofpeltonwheelturbine.2.SAI:Lackofknowledgeonfixedbeams.
PO2 3 2.20 3.EG:Unabletounderstandthescienceofminerals.4.WREII:Lackofknowledgeonogeespillway.5.ECV:
Lackofknowledgeontendersandcontracts.
Action1:NPTELvideosonfunctioningofPeltonwheelturbine.Action2:SeminarsonfixedbeamsAction3:Fieldvisitstoseemineralsoccurnaturallyandunderstandpracticallyaboutmineralogy.Action4:Visitingtodamsandshowingdirectlyallthe
featuresofOgeespillway.Action5:Seminarsontendersandcontractstopicbyasiteengineer.
PO3:Design/developmentofSolutions
1.MII:Laplace&Ztransformaredistincttothedesignofexperiment,notinterpretationofdataandno
synthesisofinformationtogivevalidproblems,Butitisusedasabasicsubjectforknowledgebasedresearch.
PO3 3 2.08 2.FM:Unabletounderstandweirsandnotches.3.H&HM:LackofknowledgeonfunctioningofVenturimeter
andorificemeter.4.SAII:Studentsarelackingabouttypesofframes,jointsandlackoffundamentalsin
structures.5.WREII:Lackofknowledgeondiversionheadworks.
Action1:GuestlecturesonLaplace&ztransformtopic.Action2:NPTELvideosonweirsandnotches.Action3:NPTELvideosonfunctioningVenturimeterandorificemeter.Action4:Demowithmodelsandfieldtrips.Action5:Fieldtripstodamsand
canals.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 101/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PO4:ConductInvestigationsofComplexProblems
1.MII:Unabletounderstandmatrices.2.FM:Unabletounderstandweirsandnotches.3.H&HM:Lackof
PO4 3 2.08 knowledgeonfunctioningofventurimeterandorificemeter.4.SURVEYINGII:Lackofknowledgeinoperating
totalstation.5.GTEI:Unabletounderstandtheconsolidationprocedure.
Action1:Guestlecturesonfundamentalprocedureonmatrices.Action2:NPTELvideosonweirsandnotches.Action3:NPTELvideosonfunctioningventurimeterandorificemeter.Action4:Workshopsonoperatingtotalstation.Action5:Guestlectureson
consolidationprocedure.
PO5:ModernToolUsage
1.SurveyingI:Lackingknowledgeontheodolitesurveying.2.ES:Lackofknowledgeonindustrialairpollution.
PO5 3 2.18 3.CT:Lackofknowledgeonthemanufacturingprocessofcement.4.GTEI:Unabletounderstandpermeability.
5.WREII:Lackofknowledgeoncrossdrainageworks.
Action1:WorkshopsonRepetitionandReiterationmethodsofTheodolitesurveying.Action2:Visitstolocalpollutedindustrialsite.Action3:Visitstothecementmanufacturingunit.Action4:Guestlecturesonpermeabilitybyexperts.Action5:Sitevisitsto
drainageworksanddemonstratepractically.
PO6:TheEngineerandSociety
1.SURVEYINGI:Unabletounderstandtheconceptsofsimplecurvesandcompoundcurves.2.ES:Unableto
understandthesoilerosionanddeforestation.3.CT:Lackofknowledgeinworkabilityofconcrete.4.DDSS:
PO6 3 2.10
LackofknowledgeinbeamdesignrequirementsasperI.S.coderecommendations.5.TE:Lackofknowledge
onhighwaygeometricdesign.
Action1:Guestlecturesonsettingsimplecurvesandcompoundcurves.Action2:Seminarsonsoilerosionanddeforestation.Action3:Workshopsonworkabilityofconcrete.Action4:MorelecturesondesignanddrawingofsteelstructuresasperIScode
recommendations.Action5:Workshopsonhighwaygeometricdesign.
PO7:EnvironmentandSustainability
1.SM1:Lackofknowledgeondeflectionofbeams.2.WREII:Lackofknowledgeontypesofdams.3.DDSS:
PO7 3 2.33
Unabletounderstandthedesignofplategirder.
Action1:Guestlecturesondeflectionofbeamsbyexpert.Action2:Fieldvisitstovariousdamlocations.Action3:Guestlecturesandseminarsonplategirder.
PO8:Ethics
1.SMI:Unabletounderstandstressandstraintopic.2.HHM:Lackofknowledgeinturbines.3.SAI:Lackof
PO8 1.50 1.00
knowledgeinmomentdistributionmethod.
Action1:Guestlecturesforsorting,mergingandstrings.Action2:Workshopsonhydraulicturbines.Action3:Remedialclassesonmomentdistributionmethod.
PO9:IndividualandTeamWork
Action:Individual&GroupAssignments.
PO10:Communication
Action1:GroupDiscussions,DebatesandSeminars.
PO11:ProjectManagementandFinance
Action1:Guestlecturesonchannelflow.Action2:Seminarsonseepage.
PO12:LifelongLearning
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 102/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Action1:Visitstopowerstations.Action2:Guestlecturesonplanetablesurveying.Action3:PPTonecosystems.Action4:MorelecturesondesignanddrawingofsteelstructuresasperIScoderecommendations.Action5:Workshopsoncompaction.
POsAttainmentLevelsandActionsforImprovement(20132014)
PO1:EngineeringKnowledge
1.ET&MT:LackinginDCMotors.2.FM:Unabletounderstandweirsandnotches.3.ES:Lackofknowledgeon
PO1 2.5 2.10 industrialairpollution.4.CT:Studentsarelackingknowledgeonpretensioningandposttensioningofconcrete.
5.GTEI:Unabletounderstandcompactionprocess.
Action1:WorkshopsonoperationofDCMotors.Action2:NPTELvideosonweirsandnotches.Action3:Visitingtolocalpollutedindustrialsite.Action4:Workshopsbyexpertsfromindustryonpretensioningandposttensioningofconcrete.Action5:
Workshopsoncompaction.
PO2:ProblemAnalysis
1.SURVEYING:Lackofknowledgeinoperatingtotalstation.2.P&S:Lackofstatisticsfundamentals.3.SAII:
PO2 2.5 2.08 Studentsarelackingaboutredundantforcesanddeflectionwheretheyoccurandhowtheywilloccur.4.WREII:
Lackofknowledgeonogeespillway.5:AP&C:Lackofknowledgeinpollutants.
Action1:Workshopsonoperatingtotalstation.Action2:RemedialclassesinstatisticsfundamentalsAction3:Demonstrationmodelstoovercometheproblemsandgoingtofieldtripsshowingtheproblemspractically.Action4:Visitingdamsandshowing
directlyallthefeaturesofOgeespillway.Action5:Seminarsonairpollutants
PO3:Design/developmentofSolutions
1.FM:Unabletounderstandweirsandnotches.2.H&HM:Lackofknowledgeonfunctioningofventurimeter
andorificemeter.3.SAI:Unabletounderstandtheconceptsofinfluencelines.4.SAII:Studentsarelacking
PO3 2.5 2.00
abouttypesofframes,jointsandlackoffundamentalsinstructures.5.WREII:Lackofknowledgeondiversion
headworks
Action1:NPTELvideosonweirsandnotches.Action2:NPTELvideosonfunctioningventurimeterandorificemeter.Action3:Guestlecturesoninfluencelinesbyexperts.Action4:Demomodelstoovercometheproblemandgoingfieldtripsshowing
practically.Action5:Fieldtripstodamsandcanals.
PO4:ConductInvestigationsofComplexProblems
1.BMC:Unabletounderstandthemanufacturingprocessesofmaterialslikebricks,limeandcementetc.2.
HHM:Lackofknowledgeinchannelflow3.DDSS:LackofknowledgeonbeamdesignrequirementsasperI.S.
PO4 2.5 2.03
coderecommendations.4.GTEI:Unabletounderstandtheconsolidationprocedure.5.EEII:Lackof
knowledgeinsolidwastemanagement.
Action1:Industrialvisitstothemanufacturingunitsofcement,limeandbricks.Action2:Guestlecturesonchannelflow.Action3:MorelecturesondesignanddrawingofsteelstructuresasperIScoderecommendations.Action4:Guestlectureson
consolidationprocedure.Action5:Guestlecturesonsolidwastemanagement.
PO5:ModernToolUsage
1.BPD:Lackofknowledgeincommercialbuildingdrawing.2.EG:Unabletounderstandthescienceof
PO5 2.50 2.08 minerals.3.WREII:Lackofknowledgeondrainagegalleries.4.EEI:Lackofknowledgeinsewage.5.GTEII:
Unabletounderstandshallowfoundations.
Action1:MorePracticingofDrawingsclearlyusingAutoCADD,tellingdrawingineasyprocedure.Action2:Fieldvisitstoseemineralsoccurnaturallyandunderstandpracticallyaboutmineralogy.Action3:Visitingdamsbyshowingdrainagegalleries.
Action4:Seminarsonsewage.Action5:Seminarsonfoundations.
PO6:TheEngineerandSociety
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 103/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1.DDRCS:Unabletounderstandlimitstatedesignofconcretestructureforshear,torsion.2.WRE1:Lackof
PO6 2.50 2.05 knowledgeinhydrology.3.GTEI:Unabletounderstandcompactionprocess.4.WREII:Lackofknowledgeon
diversionheadworks.5.TE:Lackofknowledgeonhighwaygeometricdesign.
Action1:LecturesonlimitstatedesignofconcretestructuresforshearandtorsionusingI.S.codalprovision.Action2:Guestlecturesonhydrology.Action3:Workshopsoncompaction.Action4:Fieldtripstodamsandcanals.Action5:Workshopson
highwaygeometricdesign.
PO7:EnvironmentandSustainability
1.SMI:Lackofknowledgeondeflectionofbeams.2.ECV:Unabletounderstandrateanalysis.3.GIS:Lackof
PO7 2.50 2.25
knowledgeinphotogrammetry.
Action1:Guestlecturesondeflectionofbeamsbyexpert.Action2:Guestlecturesonrateanalysisthroughexperts.Action3:Guestlecturesonphotogrammetry.
PO8:Ethics
1.SMI:Unabletounderstandstressandstraintopics.2.HHM:Lackofknowledgeinturbines.3.SAI:Lackof
PO8 1.50 1.00
knowledgeinmomentdistributionmethod.
Action1:Guestlecturesforsorting,mergingandstrings.Action2:Workshopsonhydraulicturbines.Action3:Remedialclassonmomentdistributionmethod.
PO9:IndividualandTeamWork
Action:Individual&GroupAssignments.
PO10:Communication
Action1:Seminarsondisposalofsolid.
PO11:ProjectManagementandFinance
Action1:Guestlecturesonchannelflow.
PO12:LifelongLearning
1.ETMT:Lackofknowledgeonsinglephasetransformers.2.SAI:Unabletounderstandtheconceptsof
influencelines.3.SAII:Studentsarelackingabouttypesofframes,jointsandlackoffundamentalsin
PO12 2.5 2.12 structures.4.DDSS:LackofknowledgeonbeamdesignrequirementsasperI.S.coderecommendations.5.
WREII:Lackofknowledgeondiversionheadworks.6.SurveyingI:Unabletounderstandplanetable
surveying.7.ES:Lackofknowledgeinecosystems.8.GTEI:Unabletounderstandcompactionprocess.
Action1:Visitstopowerstation.Action2:Guestlecturesoninfluencelinesbyexperts.Action3:Demowithmodelstoovercometheproblemandgoingfieldtrips.Action4:Morepracticingondesignanddrawingofsteelstructures.Action5:Fieldtripsto
damsandcanals.Action6:Guestlecturesonplanetablesurveying.Action7:PPTonecosystems.Action8:Workshopsoncompaction.
POsAttainmentLevelsandActionsforImprovement(20122013)
PO1:EngineeringKnowledge
1.SMI:Unabletounderstandstressandstraintopic.2.BMC:Unabletounderstandthemanufacturing
processesofmaterialslikebrickslimeandcementetc.3.ES:Lackofknowledgeonindustrialairpollution.4.
PO1 2.30 2.05
GTEI:Unabletounderstandtheconsolidationprocedure.5.TE:Lackofknowledgeonhighwaygeometric
design.6.EEII:Lackofknowledgeindisposalofsolid.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 104/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Action1:Guestlecturesondeflectionofbeamsbyexpert.Action2:Industrialvisitstothemanufacturingunitsofcement,limeandbricks.Action3:Visitstolocalpollutedindustrialsite.Action4:Guestlecturesonconsolidationprocedure.Action5:
Workshopsonhighwaygeometricdesign.Action6:Seminarsondisposalofsolid.
PO2:ProblemAnalysis
1.SURVEYING:Lackofknowledgeinoperatingtotalstation.2.SAI:Lackofknowledgeonfixedbeams.3.
PO2 2.30 2.08
WREII:LackofknowledgeonOgeespillway.4..GTEII:Unabletounderstandshallowfoundations.
Action1:Organizingworkshopsonoperatingtotalstation.Action2:Seminarsonfixedbeams.Action3:VisitingdamsandshowingdirectlyallthefeaturesofOgeespillway.Action4:Seminarsonfoundations.
PO3:Design/developmentofSolutions
1.FM:Unabletounderstandweirsandnotches.2.H&HM:Lackofknowledgeonfunctioningofventurimeter
PO3 2.30 2.00 andorificemeter3.SAII:Studentsarelackingaboutredundantforcesanddeflectionwheretheyoccurandhow
theywilloccur.4.WREII:LackofknowledgeonOgeespillway.
Action1:NPTELvideosonweirsandnotchesAction2:NPTELvideosonfunctioningventurimeterandorificemeter.Action3:Demonstrationmodelstoovercometheproblemsandgoingtofieldtripsshowingtheproblemspractically.Action4:Visitingdam
andshowingdirectlyallthefeaturesofOgeespillway.
PO4:ConductInvestigationsofComplexProblems
1.MII:Unabletounderstandmatrices.2.ET&MT:LackinginDCMotors.3.SURVEYING:Lackofknowledgein
operatingtheodolite.4.H&HM:Lackofknowledgeonfunctioningofpeltonwheelturbine.5.CT:Studentsare
PO4 2.30 2.00
lackingknowledgeonpretensioningandposttensioningofconcrete.6.EG:Unabletounderstandthescience
ofminerals.7.DDSS:LackofknowledgeonbeamdesignrequirementsasperI.S.coderecommendations.
Action1:Guestlecturesonfundamentalprocedureonmatrices.Action2:WorkshopsonoperationofDCMotors.Action3:Workshopsonoperatingtheodolite.Action4:NPTELvideosonfunctioningofpeltonwheelturbine.Action5:Workshopsconducted
byexpertsfromindustrytoimproveonpretensioningandposttensioningofconcrete.Action6:Fieldvisitstoseemineralsoccurnaturallyandunderstandpracticallyaboutmineralogy.Action7:Morelecturesondesignanddrawingofsteelstructures.
PO5:ModernToolUsage
1.SAII:Studentsarelackingaboutredundantforcesanddeflectionwheretheyoccurandhowtheywilloccur.
PO5 2.30 2.03
2.GTEI:Unabletounderstandpermeability.
Action1:Demonstrationwithmodelstoovercometheproblemsandgoingtofieldtripsshowingtheproblemspractically.Action2:Guestlecturesonpermeabilitybyexperts.
PO6:TheEngineerandSociety
1.BM&C:Unabletounderstandthemanufacturingprocessesofmaterialslikebricks,limeandcementetc.2.
PO6 2.30 2.00
EEI:Lackofknowledgeinsewage.3.GTEII:Unabletounderstandshallowfoundations.
Action1:Industrialvisitstothemanufacturingunitsofcement,limeandbricks.Action2:Seminarsonsewage.Action3:Seminarsonfoundations.
PO7:EnvironmentandSustainability
Action1:Seminarsonsoilerosionanddeforestation.Action2:Guestlecturesonrateanalysisbyexperts.
PO8:Ethics
Action1:Guestlecturesforsorting,mergingandstrings.
PO9:IndividualandTeamWork
Action1:Individual&GroupAssignments.
PO10:Communication
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 105/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PO10 2.30 1.75 1.ECV:Unabletounderstandrateanalysis.
Action1:Guestlecturesonrateanalysisbyexperts.
PO11:ProjectManagementandFinance
Action1:Seminarsonseepage.
PO12:LifelongLearning
1.SMI:Unabletounderstandstressandstraintopic.2.ES:Lackofknowledgeinecosystems.3.GTEI:Unable
PO12 2.30 2.08
tounderstandcompactionprocess.4.TE:Lackofknowledgeonhighwaygeometricdesign.
Action1:Guestlecturesforsorting,mergingandstrings.Action2:PPTonecosystems.Action3:OrganizingworkshopsoncompactionAction4:Workshopsonhighwaygeometricdesign.
PSOsAttainmentLevelsandActionsforImprovement(20142015)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
Action:Seminarsoncanalregulatorsdesign.
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
Action:Morepracticingondesignanddrawingofreinforcedstructures.
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
Action:GuestlecturesgivenbytheExperts&Morepracticingondesignanddrawingofsteelstructures.
PSOsAttainmentLevelsandActionsforImprovement(20132014)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
Action:Seminarsondiversionheadtanks.
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
Action:Morelecturesondesignanddrawingofreinforcedstructures.
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
Action:GuestlecturesonPERT&CPM.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 106/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PSOsAttainmentLevelsandActionsforImprovement(20122013)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
Action:Seminarsonseepage.
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
Action:Seminarsongrouting.
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
Action:Organizingworkshopsonrateanalysisforvariousmaterials.
7.2AcademicAuditandactionstakenthereofduringtheperiodofAssessment(10) TotalMarks
InstituteMarks
TheprogressofacademicactivitiesismonitoredandauditedcontinuouslybytheHODandprincipal.Thenecessarysuggestionsandmeasuresaregivenforthebetterprogressandimprovement.
ExternalAudits
1.JNTUaffiliationinspection
2.NAACinspection
FREQUENCY/ MENTIONFORMNUMBEROR
S.NO. ITEMTOBEAUDITED BYWHOM
DURINGYEAR NAME
JNTUAaffiliation
1. JNTUAcoordinators Onceinayear PermanentAffiliation
inspection
AdvicesfromJNTUACoordinators:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 107/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Correctivemeasures:
1.Additionalfacultyrecruited,atpresentfacultystudentratioismaintainedas1:15.
2.Atpresentmorethan50%offacultiesareratifiedbytheUniversity(JNTUA).
3.Correctivemeasuresaretakenoninstructedfacultytoevaluateinternalmarksstrictly.
4.SalariesofstaffarebeingpaidthroughUnionbankofIndia,PuttursinceDecember2013.
5.AtpresentallthestaffmembersarehavingAadharandPANnumbers.
AdvicesfromNAACCommittee:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 108/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Correctivemeasures:
1.Collegeisgivingtrainingonsoftskillsforthestudentsfromfirstyearonwards.Sincemostofthestudentsareruralbackground.
2.CollegestrivingmobilizethefundsfromvariousagencieslikeAICTE,DST&UGC.
3.ThedepartmentishavingMOUwithcontrolconceptsandtogivetrainingandcarryoutprojectsonPLC&Automation.
InternalAudits
1.Coursefiles,laboratorymanualsandlessonplans.
2.Attendanceregisters.
3.Curriculumdeliveryprogress.
4.Internalexams.
5.Universityresults.
6.Seminars,workshops,andindustrialvisits.
7.Studentscounseling.
8.LaboratoryAudit
9.LibraryAudit
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 109/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Coursefiles,laboratory
Departmental
1. manualsandlesson Onceinasemester AuditForm1
coordinators,HOD
plans
Curriculumdelivery
3. HOD monthly AuditForm3
progress
Resultcoordinator,
5. Universityresults OnceinaSemester AuditForm5
HOD&Principal
Activities,seminars,
coordinator,HOD&
6. workshopsand Monthlyonce AuditForm6
Principal
industrialvisits
Staff,coordinator&
7. Studentscounseling Twiceinamonth AuditForm7
HOD
Departmentalcommittee
9. LibraryAudit Yearlyonce AuditForm9
membersandHOD
1.Verificationofcoursefiles,laboratorymanualsandlessonplans:
Audit:
Allthecoursefiles,laboratorymanualsandlessonplansarepreparedbeforecommencementofthesemesterbyrespectivesubjectfaculty.
AllthesefilesareverifiedandapprovedbytheHOD.
Action:
Ifanyofthefacultymembersareunabletocompletethefiles,thenecessaryactionistakenandreauditingwillbedone.
Samplecopyoflaboratorymanual
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 110/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Samplecopyoflessonplan
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 111/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
2.VerificationofStudentsattendanceregisters:
Audit:
StudentsattendanceregistersareverifiedweeklybytheHODandmonthlybytheprincipal.
Action:
Studentswhogotlessthan75%attendancearecounseledandinformedtotheparentsthroughletters.
Studentswithpoor(<65%)attendancearecounseledandinformedtotheparentsthroughletterandphone.
Inspecialcases,theparentsarecalledandintimatedpersonallyabouttheirwardattendance.
SamplecopyofPostalletters
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 112/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3.Monitoringofthecurriculumdeliveryprogress:
Audit:
ThecurriculumdeliveryprogressismonitoredbytheHODeverymonth.
Action:
Ifanysubjectislagginginthecoverageofsyllabusasperthelessonplan,therespectivefacultywillbepersonallycalledandgivensuggestionsbytheHOD.Theyarealsoadvisedtotakeextraclassestocompletethesyllabuswithinthetime.
Samplecopyofcurriculumdeliveryprogress
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 113/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 114/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4.Reviewofinternalmarks:
Audit:
AftertheIst internalexaminations,theanswerssheetsareevaluatedaccordingtotheschemeofevaluation.
TherespectivesubjectfacultywillsubmitthemarkstotheHODandalsosortoutthestudentswhogotlessthan50%ofmarks.
Action:
Basedonthestudentsperformance,thestudentsaredividedintotwocategories:SMALLperformersandHIGHperformers.FortheSMALLperformers,remedialclassesareconductedandsimpleassignmentsaregiven.FortheHIGHperformers,areencouragedwithseminarsanddiverseassignments.
Theremedialclassesareconductedbeyondtheregulartimingsbypreparingspecialtimetable,forthestudentswhohaveperformedpoorintheIst midexaminations.
Ithelpstoenhancetheknowledgeofpoorperformedstudents.
Samplecopyofinternalmarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 115/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 116/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
RemedialclassesTimetable
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 117/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5.Reviewofuniversityresults:
Audit:
Aftertheannouncementofuniversityresults,arereviewedbytheHODandprincipal.
Action:
Inanysubject,ifthepasspercentageispoor,theHODpersonallydiscusseswithfacultyconcernedandtakesnecessaryaction.
TheInstitutiontopperisencouragedbygivinglaptopsandthedepartmenttoppersareencouragedbygivingprizes.
Thesemestertoppersareencouragedbygivingmeritcertificates.
Samplecopyofuniversityresults
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 118/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
6.Monitoringthedepartmentalactivities,seminars,workshopsandindustrialvisits:
Audit:
ThedataoftheStudentswhohaveparticipatedinseminars,workshops,symposiumsinsideandoutsidethecampus,isrecorded.
Theindustrialvisitsareplannedinordertoprovideexposureonrealtimeindustryworkingenvironment.
Action:
InactiveStudentsaremotivatedbyexplainingtheimportanceoftheprogramsandprovidedwithnecessarysuggestionsandguidelines.
Samplecopyofactives
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 119/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 120/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 121/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 122/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
7.StudentsCounseling:
Audit:
Everystudentiscounseledbytherespectivecounselors.
Thefacultymembersarethecounselorswhoconstantlymonitoralltheactivitiesandacademicsofthestudents.
Action:
ThecounselingbooksareverifiedbycounselingcoordinatorandtheHOD.
Samplecopyofcounselingbook
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 123/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 124/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
IncludeExternalauditslikeAFRC,NBA,NAAC,andJNTU.
8.LaboratoryAudit
Audit:
LaboratoryauditonceinasemesterbythelabInchargesandHOD.
TheLabinchargesandLabassistantsarecheckstheequipmentandcomponentsattheendingofthesemester.
Action:
Ifanyequipmentorcomponentsareinshortageinthelab,thecommitteechecksthelistandrecommendspurchasingthecomponentsandequipment.
Ifanyequipmentisdamagedornotworkingproperlythatsystemmustbeservicedbythelabassistantsorserviceagencies.
SamplecopyofLaboratoryAudit
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 125/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
9.LibraryAudit
Audit:
LibraryauditcanbedoneonceinayearbythedepartmentalcommitteemembersandHOD.
Thedepartmentalcommitteemembersarechecksthebooksandstudentratio.
Action:
Ifanybookislessthanthestudentratiothenthedepartmentalcommitteeisrecommendtopurchasethatbook.
Anystaffmembersarerecommendedfornewauthorbooks,thedepartmentcommitteeandHODcheckthelist,ifitisnecessarythentheyrecommendstopurchase.
SamplecopyofLibraryAudit
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 126/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
7.3ImprovementinPlacement,HigherStudiesandEntrepreneurship(10) TotalMarks
InstituteMarks
Assessmentisbasedonimprovementin:
Placement:number,qualityplacement,coreindustry,paypackagesetc.
Higherstudies:performanceinGATE,GRE,GMAT,CATetc.,andadmissionsinpremierinstitutions
Entrepreneurs
PLACEMENT
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 127/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Theinstitutionhas100%careerandplacementassistance,highlyqualifiedandexperiencedfacultyandtrainers,verygoodinfrastructureforcareerguidance,trainingandplacement.TheinstitutionhasaseparateTrainingandPlacement(T&P)Cellwithqualifiedtrainersfromvariousfieldsofexpertise.Departmenthasaplacement
coordinatortoassistT&PCell.TheT&PCellhasConferencehall,GDrooms,interviewcabins,Panelcubicles,SkillDevelopmentCentre,SeminarHalls,ClassroomsequippedwithLCDProjectorsandAudioSystems.TheT&PCellfocusesonSoftSkills,FunctionalEnglish,Quantitative,aptitude,LogicalReasoningGroupdiscussion,
JAM,PersonalEffectiveness,Interviewfacingskills,ComputerlanguagesC,C++,JavaandDotNet.
CONSOLIDATEDDATA
Batch Averagesalary
TotalNo.of TotalNo.of %ofstudents
S.NO. perannum
(YearofAdmission) students studentsplaced placed
(INR)
HIGHERSTUDIES
Theinfrastructuralfacilitiesandtrainingofferedbytheinstitutionishighlyusefultothestudentsinpertaininghigherstudies,withregardtomouldtheircareer.OurstudentsareencouragedtoattemptGATE,GRE,TOFEL,CATandPGCETthatmakesthemtogetadmissionsinvariousprestigiousinstitutions.
HIGHERSTUDIESDATA
Batch
S.NO. (Yearof No.ofstudentsforHigherEducation
Admission)
1 20122013 10
2 20112012 19
3 20102011 17
ENTREPRENEURS
EntrepreneurshipDevelopmentCellaimstoimproveandgenerateacultureofinnovationanddevelopmentofentrepreneurialspiritamongstthestudentsandbuddingentrepreneurstostarttheirownenterprise.Ithastrainingandincubationcenter,SDCactivities,seminars,workshops,guestlecturersetc.Tomakeentrepreneurs,the
resourcespersonsfromindustriesandbankingareinvitedtoconductworkshopsonentrepreneurship.
ENTREPRENEURSDATA
S. BATCH No.ofStudent
1 20122013 7
2 20112012 6
3 20102011 5
7.4Improvementinthequalityofstudentsadmittedtotheprogram(10) TotalMarks
InstituteMarks
Assessmentisbasedonimprovementintermsofranks/scoreinqualifyingstatelevel/nationallevelentrancestests,percentagemarksinPhysics,ChemistryandMathematicsin12thStandardandpercentagemarksofthelateralentrystudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 128/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Item CAY CAYm1 CAYm2
Noofstudentsadmitted 0 0 0
NationalLevelEntranceExamination
OpeningScore/Rank 0 0 0
ClosingScore/Rank 0 0 0
State/University/LevelEntranceExamination/Others Noofstudentsadmitted 90 59 60
NameoftheEntranceExaminationforLateralEntryorlateral Noofstudentsadmitted 12 12 13
entrydetails 415 1115 286
OpeningScore/Rank
AverageCBSE/Anyotherboardresultofadmitted 75 74 72
students(Physics,Chemistry&Maths)
8FIRSTYEARACADEMICS(50) TotalMarks43.84
8.1FirstYearStudentFacultyRatio(FYSFR)(5) TotalMarks
InstituteMarks
FacultyRatio(FYSFR)(5)Assessment=(515)/AverageFYSFR(LimitedtoMax.5)
DataforfirstyearcoursestocalculatetheFYSFR
NumberofFacultymembers(consideringfractionalload)
Year NumberOfStudents(approvedintakestrength)N FYSFR(N/F)
F
20122013 600 40 15
20132014 720 48 15
20142015 840 56 15
AverageFYSFR:15.00
Assessment[(5*15)/AverageFYSFR]:5.00
8.2QualificationofFacultyTeachingFirstYearCommonCourses(5) TotalMarks
InstituteMarks
Assessmentofqualification=(5x+3y)/RF
x=NumberofRegularFacultywithPh.D,
y=NumberofRegularFacultywithPostgraduatequalification
RF=NumberoffacultymembersrequiredasperSFRof15:1,Facultydefinitionasdefinedin5.1
20122013 6 34 40 3.00
20132014 10 38 48 3.00
20142015 12 44 56 3.00
AverageAssessment:3.00
8.3FirstYearAcademicPerformance(10) TotalMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 129/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
8.3FirstYearAcademicPerformance(10) TotalMarks
InstituteMarks
AcademicPerformance=((Meanof1stYearGradePointAverageofallsuccessfulStudentsona10pointscale)or(MeanofthepercentageofmarksinFirstYearofallsuccessfulstudents/10))x(numberofsuccessfulstudents/numberofstudents
appearedintheexamination)
Successfulstudentsarethosewhoarepermittedtoproceedtothesecondyear.
AcademicPerformance
AverageAPI[(AP1+AP2+AP3)/3]:5.84
Assessment[1.5*AverageAPI]:5.84
8.4AttainmentofCourseOutcomesoffirstyearcourses(10) TotalMarks
8.4.1DescribetheassessmentprocessesusedtogatherthedatauponwhichtheevaluationofCourseOutcomesoffirstyearisdone(5) InstituteMarks
(Examplesofdatacollectionprocessesmayinclude,butarenotlimitedto,specificexamquestions,laboratorytests,internallydevelopedassessmentexams,oralexamsassignments,presentations,tutorialsheetsetc.)
TheinstitutefollowstheassessmentprocessfortheevaluationofCourseOutcomes
EvaluationProcess:
Theevaluationprocessincludes:
(a)InternalExams
(b)UniversityExams
TheinstitutefollowstheevaluationprocessprescribedbytheUniversityforInternalandExternalExams.
InternalExamination:
AspertheUniversityexaminationpattern,threemidtermtestsareconductedforeachsubject.
TheInternalExaminationfor30marksincludesbothobjectiveexaminationfor10marksandDescriptiveexaminationfor20marks.
1.Willbecompletedwithin3daysoftheexamcompletion.
Evaluationof
1 Individualfaculty 2.Distributetheanswersheetsinclassandclarifies,incase
InternalExamination
ofgrievances.
Submissionofmarks
totaltoHOD
Consolidationofallsubjectsmarks& Studentswillverifythemarksandreportanygrievances
3 Coordinator
displayonthenoticeboard within3daysfromthedateofdisplay.
1Ensurethemarksenteredinregisterandsubmittedare
Verification& same.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 130/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4 Analysis HOD 2.AnalyzetheCOattainmentsandidentifythemeasures
forimprovement.
SubmitSemester
Principal
Principalreviews
anddisplaythe
6 Principal Submissionofinternalmarkstotheexaminationbranch.
markstostudentsat
Exambranch
Chiefof
Communicatemarks Aspertheuniversityscheduletheinternalmarksareposted
7 Examination
toUniversity tothechiefofexaminationbranch.
Evaluations
SampleInternalMarksPage
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 131/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 132/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
ExternalExamination:
TheExternalExaminationofeachcourseisfor70marks.
ScheduleofExaminations
ThescheduleofinternalandexternalexaminationsisclearlymentionedintheacademicschedulepublishedbytheUniversity/institutionandthesameiscommunicatedtoallthestudentsandthefacultyatthebeginningofeachsemester.
MandatoryAssessment:
Universitypostsresultsontheuniversitywebsite.ResultsAnalysisisreviewedbyHOD&Principalimmediatelyafterresultsaredeclaredandareasforimprovementareidentified.
Counselorsadvisethestudentsbasedonindividualperformance.
Resultsarecommunicatedtoparentsbypost.
Sampleuniversityresultpage:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 133/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
8.4.2RecordtheattainmentofCourseOutcomesofallfirstyearcourses(5) InstituteMarks
Programshallhavesetattainmentlevelsforallfirstyearcourses.
(Theattainmentlevelsshallbesetconsideringaverageperformancelevelsintheuniversityexaminationoranyhighervaluesetastargetfortheassessmentyears.Attainmentlevelistobemeasuredintermsofstudentperformanceininternal
assessmentswithrespecttheCOsofasubjectplustheperformanceintheUniversityexamination)
EvaluationofinternalandexternalexaminationmarksforsettingCourseattainmentlevelsforallcourses:
Evaluationofmarksfrombothinternalandexternalexaminations
MeasurementofCourseattainmentlevelsforUniversityExaminations:
AttainmentLevel1:50%ofstudentsscoringpassmarksintheUniversityfinalexamination.
AttainmentLevel2:60%ofstudentsscoringpassmarksintheUniversityfinalexamination.
AttainmentLevel3:70%ofstudentsscoringpassmarksintheUniversityfinalexamination.
COURSETITLES:FollowingarethecoursetitlesalongwithcoursecodeusedinPOs
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 134/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Note:1.C101,C102indicativeCoursesforfirstyear.Firstnumericdigitindicatesyearofstudyandremainingtwodigitsindicatecoursenumbers.
1 C101 CommunicativeEnglish
2 C102 Engineering.Physics
3 C103 Engineering.Chemistry
4 C104 MathematicsI
5 C105 ProgramminginC&DataStructures
6 C106 EngineeringMechanics
7 C107 EngineeringDrawing
8 C108 ComputerProgramminglab
9 C109 Engineeringphysics&chemistryLab
10 C110 Engineering&ITworkshop
11 C111 EnglishLanguageCommunicationSkillsLab
CourseattainmentlevelsforIYearUniversityExamination:201415
PercentageofStudentsScoredmore
COURSE Attainmentlevel
than60%
C101 62.5 2
C102 53.4 1
C103 52.3 1
C104 51.1 1
C105 52.9 1
C106 51.1 1
C107 51.1 1
C108 100 3
C109 100 3
C110 100 3
C111 100 3
MeasurementofCourseattainmentlevelsforInternalExaminations:
AttainmentLevel1:50%studentsscoringmorethan60%marksoutofthemaximummarks.
AttainmentLevel2:60%studentsscoringmorethan60%marksoutofthemaximummarks.
AttainmentLevel3:70%studentsscoringmorethan60%marksoutofthemaximummarks.
CourseattainmentlevelsforIYearInternalExamination:201415
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 135/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PercentageofStudents
COURSE Attainmentlevel
Scoredmorethan60%
C101 63.3 2
C102 52.7 1
C103 51.5 1
C104 51.1 1
C105 56.7 1
C106 51.5 1
C107 51.6 1
C108 100 3
C109 100 3
C110 100 3
C111 100 3
Overallcourseattainmentforallfirstyearcourses:
ACADEMICYEAR:201415
C101 2 2 2
C102 1 1 1
C103 1 1 1
C104 1 1 1
C105 1 1 1
C106 1 1 1
C107 1 1 1
C108 3 3 3
C109 3 3 3
C110 3 3 3
C111 3 3 3
CourseAttainment:
Forexample:MathematicsI(C104)
AttainmentthroughUniversityExamination:Moderatei.e.2
AttainmentthroughInternalAssessment:Substantiali.e.3
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 136/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Considering70%weightagetoUniversityexaminationand30%weightagetoInternalassessment,theattainmentcalculationswillbe(70%ofUniversitylevel)+(30%ofInternallevel)i.e.70%of2+30%of3=1.4+0.9=2.3
8.5AttainmentofProgramOutcomesfromfirstyearcourses(20) TotalMarks
8.5.1IndicateresultsofevaluationofezchrelevantPOand/orPSO,ifapplicable(15) InstituteMarks
(DescribetheassessmentprocessesthatdemonstratethedegreetowhichtheProgramOutcomesareattainedthroughfirstyearcoursesanddocumenttheattainmentlevels.Alsoincludeinformationonassessmentprocessesusedtogatherthedata
uponwhichtheevaluationofeachProgramOutcomeisbasedindicatingthefrequencywithwhichtheseprocessesarecarriedout)
POsAttainment:
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
C101 3 3 2 3 3 3 2
C102 1 1 2 2 1 1 2
C103 1 1 2 2 2
C104 1 1 1
C105 2 2 2 1 2 2
C106 1 1 1 1
C107 2 2 2 2 2
C108 3 3 3 3 3 3
C109 3 3 3 3 3 3 3
C110 3 3 3 3 3 3
C111 3 3 3 3
COAttainmentLevel
Course PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 PO10 PO11 PO12
DirectAttainment 1.82 2.09 0.91 1.27 0.91 0.91 0.82 0.27 1 0.55 0 1.64
InDirectAttainment 2 2 2 2 2 2 2 1 2 1 0 2
COAttainment 1.86 2.07 1.13 1.42 1.13 1.13 1.06 0.42 1.2 0.64 0 1.71
PSOsAttainment:
8.5.2ActionstakenbasedontheresultsofevaluationofrelevantPOs(5) InstituteMarks
(Theattainmentlevelsbydirect(studentperformance)aretobepresentedthroughProgramlevelCoursePOmatrixasindicated)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 137/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
POsAttainmentLevelsandActionsforImprovement(20142015)
PO1:EngineeringKnowledge
1.AttainedlowachievementinEngineeringPhysics,EngineeringChemistry,Engineeringmechanics.2.Attained
PO1 3 2
lowachievementinMathematicsI.
Action1:Conductingseminarsoncomplextopicswithstudents.Action2:MorepracticingsessionsonMathematicsI.
PO2:ProblemAnalysis
Action1:Givingareviewonthebasicsofengineeringsciences.Action2:Givingassignmentsonapplicationsoftheconcepttopic.
PO3:Design/developmentofSolutions
Action1:Conductingworkshops.Action2:Preparingtheprojectworkbystudents.
PO4:ConductInvestigationsofComplexProblems
Action1:Morepracticingsessions.Action2:Givingprojectstoapplythetheoreticalknowledge.
PO5:ModernToolUsage
PO5 3 2 AttainedlowachievementinEngineeringPhysics&EngineeringMechanics.
Action1:Conductingnewexperimentsinphysicsrelatedtotheoreticalknowledge.
PO6:TheEngineerandSociety
PO6 3 2 AttainedlowachievementinEngineeringphysics.
Action1:Explainingtomorepracticalexamples.
PO7:EnvironmentandSustainability
Action1:GivinglecturesonhowEngineeringMechanicshelpsondevelopingtheenvironment.
PO8:Ethics
PO8 3 3 Attainedthetargetlevel.
Action:MoreseminarsandworkshopsonEthicalvalues.
PO9:IndividualandTeamWork
Action1:GivingteamworktowriteCprogrammes.
PO10:Communication
PO10 3 3 Attainedthetargetlevel.
Action:Morepracticeonlistening,speaking,readingandwriting.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 138/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PO11:ProjectManagementandFinance
PO11 0 0 ThisPOisnotapplicableforfirstyearcourses.
Action:
PO12:LifelongLearning
Action1:GivingseminarsontheimportanceonClanguage,communicativeEnglish,engineeringphysics.
POsAttainmentLevelsandActionsforImprovement(20132014)
PO1:EngineeringKnowledge
Action1:Conductingseminarsoncomplextopicswithstudents.Action2:MorepracticingsessionsonMathematicsI.
PO2:ProblemAnalysis
Action1:Givingareviewonthebasicsofengineeringsciences.Action2:Givingassignmentsonapplicationsoftheconcepttopic.
PO3:Design/developmentofSolutions
Action1:Conductingworkshopsonengineeringmechanics.Action2:Preparetheprojectworkbystudents.
PO4:ConductInvestigationsofComplexProblems
Action1:Morepracticingsessions.Action2:Givingprojectstoapplythetheoreticalknowledge.
PO5:ModernToolUsage
Action1:UsageofICTtoolsandgivingseminartopicsonengineeringphysics.
PO6:TheEngineerandSociety
Action1:MorepracticingsessionsandExplainingtomorepracticalexamples.
PO7:EnvironmentandSustainability
Action1:Givingseminarsonengineeringmechanics.
PO8:Ethics
Action1:Bygivinglecturesonethicalvalues.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 139/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PO9:IndividualandTeamWork
Action:
PO10:Communication
Action1:GroupdiscussionsoncommunicativeEnglish.
PO11:ProjectManagementandFinance
PO11 0 0 Notapplicable.
Action:
PO12:LifelongLearning
Action1:GivingseminarsontheimportanceofEngineeringPhysics.
POsAttainmentLevelsandActionsforImprovement(20122013)
PO1:EngineeringKnowledge
Action1:Conductingseminarsoncomplextopicswithstudents.Action2:MorepracticingsessionsonMathematicsI.
PO2:ProblemAnalysis
1.AttainedlowachievementinEngineeringPhysics,EngineeringChemistry,Engineeringmechanics.2.Attained
PO2 2 1.9
lowachievementinMathematicsI.
Action1:Givingareviewonthebasicsofengineeringsciences.Action2:Givingassignmentsonapplicationsoftheconcepttopic.
PO3:Design/developmentofSolutions
Action1:Preparingtheprojectworkbythestudents.
PO4:ConductInvestigationsofComplexProblems
Action1:ConductingmathematicalQuizforrememberingformulae.Action1:Practicingmoreexercises.
PO5:ModernToolUsage
Action1:ConductingworkshopsandseminarsonICTtoolsusage.
PO6:TheEngineerandSociety
PO6 2 2 AttainedlowachievementinEngineeringMechanics,EngineeringChemistry.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 140/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Action1:Involvingthestudentsinseminarsandworkshops.
PO7:EnvironmentandSustainability
Action1:Givingseminarsonengineeringmechanics.Action2:Givingseminaronsustainabledevelopment.
PO8:Ethics
PO8 2 2 Attainedthetargetlevel.
Action1:Bygivinglecturesonethicalvalues.
PO9:IndividualandTeamWork
PO9 2 2 Attainedthetargetlevel.
Action1:ConductingGroupdiscussionsonvariousEngineeringsciences.
PO10:Communication
PO10 2 2 Attainedthetargetlevel.
Action1:Groupdiscussions,DebatesandOralpresentations.
PO11:ProjectManagementandFinance
PO11 0 0 NotApplicable.
Action:
PO12:LifelongLearning
Action1:Givingmoreseminars.
PSOsAttainmentLevelsandActionsforImprovement(20142015)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
PSO1
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
PSO2
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
PSO3
PSOsAttainmentLevelsandActionsforImprovement(20132014)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 141/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PSOsAttainmentLevelsandActionsforImprovement(20132014)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
PSO1
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
PSO2
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
PSO3
PSOsAttainmentLevelsandActionsforImprovement(20122013)
PSO1:BridgeDesign:Abletodesignandvalidatethevariousstructuralelementsofbridgesofdifferentdimensions.
PSO1
PSO2:ApplicationofConcreteTechnology:Analyzethecauses,preventiveandcorrectivemeasuresofcracksinbuildings.
PSO2
PSO3:STAADPro.andRivetingsoftwareusage:ExpertiseinSTAADProandRevitsoftwareforthedesignofconcreteandsteelstructures.
PSO3
9STUDENTSUPPORTSYSTEMS(50) TotalMarks50.00
9.1Mentoringsystemtohelpatindividuallevel(5) TotalMarks
InstituteMarks
Typeofmentoring:Professionalguidance/careeradvancement/courseworkspecific/laboratoryspecific/allrounddevelopment.Numberoffacultymentors:Numberofstudentspermentor:Frequencyofmeeting:
(Theinstitutionmayreportthedetailsofthementoringsystemthathasbeendevelopedforthestudentsforvariouspurposesandalsostatetheefficacyofsuchsystem)
StudentsMentoringSystem
TheprincipalobjectiveofintroducingtheStudentMentoringSystemistoguidetheacademic,careeradvancement,cocurricularandextracurricularperformancesofthestudentandaccordinglymouldthestudentstoutilizealltheresourcesavailableintheinstitutionforholisticdevelopmentofthestudents.
Thesystemencompassescontinuousmonitoringthestudentsperformance,identifyingthestrengths,shortcomings,behaviorandattitude,andofferingamiablesupportandspecificsuggestionstodevelopthestudentsinallaspects.Thesystemalsoaimsatimplantinggoodhabits,behaviorandhumanvaluesamongthestudents.
Themembersincounselingcommitteefromeachdepartmentarelistedbelow.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 142/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
CounselingCommittee:
Sr.No. NameoftheFaculty Designation Department
Table9.1:CounselingCommittee
Mentoring(counseling)systemconsistsof:
Everyclasshasonecounselinghourperweektofacilitateaquick1:1interactionbetweenthefacultyandthestudent.
Therearearound200counselorsintheinstitution.
Thereisonecounselorforevery20students.
Everyweekduringthecounselinghour/whenevernecessarythestudentsgetcounseled.
Priorto1:1sessionwiththestudent,thefacultyascertainsthedetailsofattendance,performanceinexaminations/tests.
Detailsofattendanceandperformancearediscussedduringthe1:1interaction,suggestions/comments,ifany,arenotedintheStudentRecordbookandfirstweekofeverymonthattendancereportissenttotheparentswhosewardshavelessthan75%attendance.
Thosewhogotbelow65%attendance,counselorsintimatetoparentsthroughphonealso.
Thestudentsalsoarecounseledoncareerguidance,higherstudiesandentrepreneurship.
Goodandtopperformersarefurtherencouragedtoaimatuniversityranks,higherstudiesandjobsatmultinationalcompanies.
Ifsomestudentsareidentifiedasslowlearners,remedialclassesarearrangedfortheminconsultationwiththeHeadoftheDepartment.
Thestudentsareencouragedtoparticipateinvariouscocurricularandextracurricularactivitiesorganizedbytheindividualdepartmentsandinstitution.Theimportanceofparticipatinginsuchactivitiesforpersonalandprofessionaldevelopmentisemphasizedduringthecounselingsessions.
Inaddition,thetraining&placementcellconductscareercounselingsessionsforthestudentsaspartofthetrainingprogrammers.
SamplestudentsallotmentperCounselor(IIB.TechCIVIL):
TotalNo.of
Sr.No. CounselorName StudentRollNos.
Students
1 G.ShanmukhaSrinivas 13F61A010113F61A0120 20
2 Y.MuraliKrishna 13F61A012113F61A0140 20
3 M.PavanKumar 13F61A014114F65A0101 20
4 S.ArifHussain 14F65A010214F65A0112 11
Table9.2:Studentsallotmentpercounselor
SamplestudentcounsellingbookforProfessionalguidance/careeradvancement/courseworkspecific/laboratorySpecific:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 143/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.1:Samplestudentcounsellingbook(IICIVIL)
Fig9.2:PointsofCounselling&Mentoring
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 144/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.3:StudentsAwards,Results,Attedancedetails,Professionalguidance
Mentoringthestudentbycounselors:
Fig9.4:CounselingtheStudents
Sampleattendancelettersendingtotheparents:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 145/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.5:AttendanceLetter
EvidenceofSuccess
Asthestudentsprogressintheiracademics,thementorshavealwaysobservedtheimprovementintermsoftheirattitude,personaldisposition,academicperformance,andlanguageandcommunicationskills.
Manystudentsareimprovedintheirperformanceconsistentlyasaresultofmentoring.Morespecifically,manystudentshavebeenimprovedverywellintheirthirdandfinalyearsofstudy.Theinstitutionspasspercentagehasalwaysbeenmorethantheuniversityaverageandhigherthanthatofotherinstitutionsinandaroundthetown.
ThetoppersintherespectiveclasseshavealwaysbeenencouragedtosetuptheirpreparationwhichresultsinconsistentlygettinguniversityranksandrecentlywegotGoldmedalsfortheacademicyears201112&20132014.
Inspiteofdifficultemploymentinmarketconditions,thestudentsoftheinstitutiongotanumberofjobopportunitiesinplacements.
Samplelistofstudentswhoareimprovedintheiracademicperformanceduetoeffectivecounselingmechanism:
PassPercentage
1 13F61A0120 D.Mahesh 61 62 62
2 13F61A0157 D.Vijay 76 77 78
3 13F61A0123 K.Mounica 75 76 72
4 13F61A0129 I.Pravallika 70 70 69
Table9.3:AnalysisofIIB.TechCivilPasspercentages
Samplelistofstudentswhoareimprovedattendanceinclassworkduetoeffectivecounselingmechanism:
AttendancePercentage
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 146/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
I II I II
1 12F61A0101 M.Amulu 97 79 92 86
2 12F61A0131 G.Mounika 89 69 79 79
3 12F61A0140 D.RenukaDevi 99 79 89 90
4 12F61A0155 T.VenkataKesava 89 84 90 87
5 13F65A0108(LE) P.PadmaPriya 94 85 81 85
Table9.4:AnalysisofIIIB.TechCivilAttendancepercentage
9.2Feedbackanalysisandreward/correctivemeasurestaken,ifany(10) TotalMarks
InstituteMarks
Feedbackcollectedforallcourses:YES/NOSpecifythefeedbackcollectionprocessAveragePercentageofstudentswhoparticipateSpecifythefeedbackanalysisprocessBasisofreward/correctivemeasures,ifanyIndicesusedformeasuringquality
ofteaching&learningandsummaryoftheindexvaluesforallcourses/teachersNumberofcorrectiveactionstaken.
A)Feedbackcollectedforallcourses:YES
B)FeedbackCollectionProcess:
ThefeedbackiscollectedbytheInternalQualityAssuranceCell(IQAC).
Theinstitutionhasestablishedasystemofcollectingfeedbackfromthestudentsinallcoursestwiceinasemester.Generally,after10daysofthebeginningandattheendofeverysemester.
Thefeedbackhasbeencollectedthroughtheonlinesystembyadefinedinbuiltfeedbacksoftwarewherestudentscanrespondtowardsthestructuredquestionnaireregardingthekeyelementsi.e.communication,numberofexamplesquoted,behaviourinclass,teachingmethodologyandsoon.
Maximumnumberofstudentsisparticipatedingivingfeedback(98%to100%).
ThemembersinIQACcommitteefromeachdepartmentarelistedbelow.
IQACCommittee:
Table9.5:IQACCommittee
OnlineFeedbackformatonFaculty:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 147/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.6:Onlinefeedbackformat
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 148/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
C)Feedbackanalysis:
Oncefeedbackiscollecteditwillbeundertheprocessofthefacultyperformancethroughsomestandardstatisticaltoolapplications.
ThecollectedfeedbackisanalysedbytheIQACandadetailedreportissubmittedtotheprincipal.
Analysisofonlinefeedbackformat:
Fig9.7:Onlinefeedbackanalysisreport
Rewards/CorrectiveMeasures:
ThefacultyiscalledtohaveadiscussionaboutfeedbackwiththeHODandPrincipalforthebettermentintheirperformance.
Thebestperformedfacultymembersareencouragedwithappreciation.
Membersofthefaculty,whoseperformanceispoor,areadvisedbasedontheirweakareasbyHODandPrincipal.
ThefacultymembersareencouragedtoparticipateinvariousWorkshops/Seminars/Conferences/TrainingPrograms/FDPstoenhancetheirskills.
Theinstitutionorganizesfacultydevelopmentprogrammesregularlyforimprovingtheirknowledgeandteachingskills.
ThefacultywhoperformsextremelywellisrequestedtoconductFacultyDevelopmentProgrammesandparticipateinResearch&Developmentwork.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 149/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Feedbacksummarysheet:
Fig9.8:FeedbackSummarySheet
9.3Feedbackonfacilities(5) TotalMarks
InstituteMarks
Assessmentisbasedonstudentfeedbackcollection,analysisandcorrectiveactiontaken.
A)Feedbackcollectionprocess:
TheinstitutionhasaseparatesystemcalledIQACtocollectfeedbackfromthestudentsonvariousfacilitiesavailableintheinstitution.
Feedbackiscollectedinthemiddleoftheacademicyear.
ThestudentsareencouragedtogivefeedbackonfacilitiessuchasCollegeInfrastructure,Departmentsresources,Laboratories,Library,ComputingandInternet,Sports,Placement&Training,Hostels,Transport,Canteen,safety,medicalandsoon.
Thefollowingformatisusedtocollectfeedbackfromthestudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 150/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Feedbackformatonfacilities:
Fig9.9:Feedbackformatonfacilities
OnlineFeedbackformatonLaboratory:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 151/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.10:OnlineFeedbackformatonLaboratory
B).Feedbackanalysis:
Aftercollectingthefeedback,percentageoffeedbackoneachfacilityiscalculated.
Primarilythefacilitieswhichhasgotpoorfeedbackareidentified(i.e.percentageoffairismore).
Subsequentlyotherfacilitieswhichalsoneedimprovementareidentified.
Feedbackanalysisformat:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 152/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.11:Feedbackanalysisformat
OnlineFeedbackanalysisformat:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 153/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig9.12:SampleanalysisFeedbackformatforLaboratory
C)Correctiveactions:
Afteranalysingthefeedback,thefirstpriorityisgiventoimprovethefacilitywhichhasgotpoorfeedback.
Allthereliablesuggestionsareconsideredforimplementation.
Subsequentlycorrectivemeasuresforotherfacilitiesarealsotaken.
Someofthecorrectiveactionstakenare:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 154/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1.Additionalcanteenisconstructed.
2.A/Cbuseswithaudio&videosystemsareprovidedforalltheroutes.
3.Additionalseminarhallisestablished.
1 201516 4.Additionalplayground(volleyball,Basketballcourts)isprovided.
5.CCTVcamerasareextendedtoalltheareas.
6.ATMfacilityisprovided.
7.A/Cauditoriumwithaudio&videosystemisconstructed.
1.Busfacilitiesareextendedtonewroutes.
2.Dinningseatsofthecanteenarereplacedwithchairs.
2 201415 3.Vehicleparkingfacilityisprovided.
4.Someofthelaboratoriesaremodernized.
5.No.ofvolumesareincreasedinthelibraryandNPTELvideosareaddedintheDigitallibrary.
1.Starteddigitallibrary.
3 201314 2.EclassroomsareprovidedforeachDepartment.
3.ROsystemisestablishedforpurificationofdrinkingwater.
1.Placementcellismodernized.
4 201213 2.Someofthelaboratoriesareenhancedwithadditionalequipments.
3.Additionalroomsareconstructedforthehostels.
Table9.6:CorrectiveactionsonFacility
Samplecorrectivemeasurestakentoimprovethelaboratoriesare:
1.GeotechnicalEngineeringLaboratoryisequippedwithCBR,ConsolidationandTri
AxialSheartest.
2.IntroducedTotalStationinSurveyingIILab.
1 201516 3.Revisedlabmanualsareprovidedforeachstudentinadvance.
4.Additionalexperimentsarealsoconductedinlabsessions.
5.CCTVcamerasareextendedtoallthelaboratories.
6.Laboratoryrevisionsessionsareplannedtoconductforstudentabsentees.
1.CT&Highwaylabismoderated.
2.ThenumberofexperimentstobeconductedinthelaboratorymeetstheJNTUA
2 201415 curriculum.
3.Impartingguidelinesforimplementinginnovativeideas.
4.Thesafetymeasurestobetakenforthestudentsduringlabsessionsareinstructed.
1.Dresscodeforsafetymeasuresisimplementedforallstudentsduringlabhours.
2.Reducedthesizeofstudentsperbatchtofour.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 155/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
3 201314 3.Laboratoryexperimentsaredemonstratedbythefacultycompletelybeforethe
commencementoflab.
1.Alllaboratoriesbeinginstalled.
4 201213 2.Regularlyconductingvivavoceinthelaboratorysessions.
3.Thelabexperimentsareplannedtocompletewithinthestipulatedtime.
Table9.7:CorrectivemeasurestakentoimproveLaboratories
9.4SelfLearning(5) TotalMarks
InstituteMarks
(Theinstitutionneedstospecifythefacilities,materialsandscopeforselflearning/learningbeyondsyllabus,Webinars,Podcast,MOOCsetc.andevaluatetheireffectiveness)
Theinstitutionencouragesthestudentsinvariouswaysofselflearningtomakethemgainknowledgeinandoutofthecurriculum.
Thefollowingresourcesareavailableintheinstitution.
A).GeneralFacilities:
Digitallibraryfacility(NPTEL,EBooks,National&InternationalJournals).
Availabilityofcoursematerialinlibrary.
Languagelabfacility.
AvailabilityofvideolecturesinCDform.LCDprojectorsforpresentation.
SkillDevelopmentCentre(SDC).
MicrosoftInnovationCentre(MIC).
IBMCentreofExcellency.
ListofNPTELvideos:
1 CIVIL 640
2 ME 599
3 EEE 822
4 ECE 816
5 CSE 635
TOTAL 3512
Table9.8:NPTELvideos
ListofNational&InternationalJournals:
1 CIVIL 8 9
2 ME 7 13
3 EEE 7 14
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 156/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4 ECE 11 23
5 CSE 11 10
Table9.9:National&InternationalJournals
FacilitiesforSelfLearning:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 157/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
B)Webbasedlearningfacilities:
Theinternetisanopeninformationsysteminwhichvarioussourcesofinformationandmaterialsareavailablesuchastexts,images,audios,videosandsoon.
Thesequencesoftheinformationcanbelinkedtogetherthatleadstotheselflearning.
Theinternetoffersnewpossibilitiestostructure,represent,adaptandintegratevariouslearningcontentsandmaterials.
Thestudentscanutilizetheinternetfacilitiesinthecollegehours&beyondthecollegehours.
WiFiisenabledinthecampus.
Eclassroomisavailableforeverydepartment.
StudentscollectedthematerialsthroughtheEMail.
FacilitiesforWebbasedLearning
C)Motivation:
Thecounsellorguidesthestudentstocoverthegapbetweentheuniversitycurriculumandindustryrequirementsbyutilizingtheavailableresources.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 158/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Thestudentsaremotivatedtocomeupwithinnovativeideastoinventnewproducts.
Thecounsellorguidesthestudentstobecomefamiliarwithadvancedlevelcoursesandselflearningmethodsthatmakethemboosttheirconfidencelevelsthroughthefollowingsteps.
Thestudentsareencouragedtoparticipateinseminars/workshops/conferences.
SampleStudentProjectsPrototypeModel:
9.5CareerGuidance,Training,Placement(10) TotalMarks
InstituteMarks
(Theinstitutionmayspecifythefacility,itsmanagementanditseffectivenessforcareerguidanceincludingcounselingforhigherstudies,campusplacementsupport,industryinteractionfortraining/internship/placement,etc.)
Theinstitutionhas100%careerguidanceandplacementassistancewithhighlyqualifiedandexperiencedfacultyandtrainers.
TheinstitutionhasaseparateTrainingandPlacement(T&P)Cellwithqualifiedtrainersfromvariousfieldsofexpertise.
Theyalsoemphasizeonacademicexcellence,softskillsandpersonalitydevelopmentsothatthestudentsareabletobecomeleaderstohandleanytoughsituationsoftheircareer.
TheinstitutionhascounsellorstogivetheguidanceoncareerwiththehelpofT&PCell.
EachdepartmenthasaplacementcoordinatortoassistT&PCell.
TheT&PCellhasConferencehall,GDrooms,interviewcabins,Panelcubicles,SkillDevelopmentCentre,SeminarHalls,ClassroomsequippedwithLCDProjectorsandAudioSystems.
Thestudentsareencouragedtotakeinternshipsandvisitvariousindustries.
TheinstitutionguidesonGATE,PGECET,GRE,TOEFL,etc.forgettingadmissionintohigherstudies.
T&PCommittee:
FacilitiesforTraining&Placements:
1 SeminarHalls 2
2 Conferencehall 2
3 Interviewcabins 4
4 Panelcubicles 4
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 159/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5 SkillDevelopmentCentre 1
6 EClassroomswithLCDProjectorsandAudioSystems. 7
7 GDrooms 1
Table9.10:No.offacilitiesinTraining&Placements
T&PCellInternalTrainersandSkillareas:
1 G.Pushpadrisekhar .Net
2 V.Mohanapriya C,C++,Java
3 S.Venkatesh Softskills
4 K.Vasundhara English
5 P.Lakshmikeerthi Softskills
6 A.Suresh Java,Oracle
7 T.Ashok English
8 K.Lokesh Aptitude
9 D.Harssan English
10 Dr.E.Sudhakar Aptitude
11 Dr.C.SureshBabu Aptitude
12 E.KarthikeyanSharma English
Table9.11:InternalTrainers
T&PCellExternalTrainersandSkillareas:
Table9.12:ExternalTrainers
TheT&PCellfocusesonthefollowingareas
SoftSkills
FunctionalEnglish
Quantitativeaptitude
LogicalReasoning
Groupdiscussion
JAM
PersonalEffectiveness
Interviewfacingskills
ComputerlanguagesC,C++,Java,DotNetforECE,CSE,EEE&MCAstudents
CAD/CAMforCivilandMechanicalEngineeringstudents
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 160/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
PlacementcommitteeandInternalTrainersforHigherstudies:
Table9.13:InternalTrainersforhigherstudies
i)Listofsuccessfulstudentsinhigherstudies:
StudentsQualified
Department Batch
GATE GRE/TOFEL PGECET
201216 10
Civil 201115 19
201014 1 16
201216 3 8
MECH 201115 2 10
201014 1 2 9
201216 1 5
EEE 201115 1 6
201014 1 1 1
201216 2 10 8
ECE 201115 1 5 4
201014 1 11 8
201216 10 15
CSE 201115 6 14
201014 1 13
Table9.14:Successfulstudentsinhigherstudies
ii)Studentsplaceddetails.
Batch
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 161/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Sr.No Department 201216 201115 201014
2 CSE 78 82 91
3 EEE 35 42 48
4 MECH 85 45 47
5 CIVIL 38 33 30
Table9.15:Studentsplacementdetails
PlacedStudents&ExternalTrainer:
iii)Listofindustriesvisited:
Nameoftheindustryfor
Academicyear Year Date(s) Areasofexposure
visit/Internship
CIVIL
1.Mangampetmines
III 07815 Geologyandwaterresources
2.Annamacharyaproject(cheyyeru)
201516
1.Dept.ofGeology
Geology,structuralandwater
III 2.Chandragirifort 12815
resourcesengineering
3.Kalyanidam
1.Srisailam
2.Yaganti Structuralandwaterresources
III 21812
3.Mahanandhi engineering
201213
4.Ballumcaves
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 162/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1.Chandragirifort Geologyandstructural
III 01912
engineering
2.S.V.Geologydept.
Table9.16:Listofindustriesvisited
9.6EntrepreneurshipCell(5) TotalMarks
InstituteMarks
(Theinstitutionmaydescribethefacility,itsmanagementanditseffectivenessinencouragingentrepreneurshipandincubation)(Successstoriesforeachoftheassessmentyearsaretobementioned)
TheinstitutionhasestablishedEntrepreneurshipDevelopmentCell(EDC)toencouragethestudentstobecomeentrepreneurs.TheEDCprovidesthefollowingsupporttothestudentcommunity:
TheEDCorganisestheprojectexhibition,creationofnewideas,tocopeupbusinesscompetition,industrialvisit,awarenesscamp,seminarsandworkshops,etc.,whichhelpthestudentstobecomeentrepreneurs.
TheEDCguidesandassiststheprospectiveentrepreneursonvariousaspectssuchaspreparingprojectproposals,obtainingprojectapprovals,gettingloansandfacilitiesfromagenciesofsupportsystem,acquiringinformationaboutrecenttechnology,etc.
TheEDCinspiresthestudentsbymakingthemawareoftopentrepreneursandtheirachievements.
TheEDCorganizescontinuousinteractionwithindustrypeopleinordertoacquiretheknowledgeofestablishingthenewcompany.
TheinstitutioninculcatesEntrepreneurskillsamongthestudentsbyhostingTechnologyEntrepreneurProgrammeoncampusincollaborationwithISB,Hyderabad.
ThestartupIncubationCentretoourinstitutionhasbeensanctionedbytheA.P.Stategovernment,asapartofSunriseStartupprogramsforstudentsonJan2015.ItisaprivilegetoourinstitutiontorunincubationfunctionalityforthedevelopmentofstudentEntrepreneurs.Studentcommitteehasbeenformedandapprovedby
startupvillage,Visakhapatnam.ThiscommitteeisworkingonincubatorfunctionalitiesundertheguidanceofCoordinatorandtheHeadoftheInstitution.
ThemembersinEDCcommitteefromeachdepartmentarelistedbelow.
EntrepreneurshipDevelopmentCellCommittee
Table9.17:EDCCommittee
EDCCommitteeroom:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 163/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 164/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
EntrepreneurshipFacilities:
i)ListofActivitiesOrganized
1.Mrs.AnchalSood,StrategicDesigner&Analyst,ISB,Hyderabad
24082015&
1 TwodayworkshoponDesignThinking 2.Mr.RipulKumar,CEO,KernCommunication ISB,Hyderabad
25082015
3.Mrs.RoliAgarwal,Freelancer,ISB,Hyderabad
1.EktaChowdhary,Consultant,ISB
2 OnedayAwarenesssessiononTechnologyEntrepreneurshipProgramme 05052015 ISB,Hyderabad
2.Mr.AkshayJalan,ISB.
Smt.K.RamaDevi
3 OnedayworkshoponWomenEntrepreneurs:ChallengesandStrategies 07032015 EDC,SIETK,Puttur
PresidentofALEAP.
05122014
SponsoredbyEntrepreneurshipDevelopmentInstituteof
4 3DayEntrepreneurshipAwarenessCamp(EAC) to Dr.K.Lakshminarayna,Director,ASSSDC.
India,Ahmedabad,Gujarat,India
07122014
5 GuestLectureonTechnologyandManagementforEntrepreneurshipDevelopment 19102012 Mr.K.Kandaswami,MD,M/s.AnandhaFabrication(Cbe)Pvt.Ltd.,
EDC,SIETK,Puttur
Table9.18:EDCOrganizedEvents
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 165/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
EDCProgrammes:
9.7CocurricularandExtracurricularActivities(10) TotalMarks
InstituteMarks
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 166/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(Theinstitutionmayspecifythecocurricularandextracurricularactivities)(QuantifyactivitiessuchasNCC,NSSetc.)
Cocurricularandextracurricularactivitiesaredulyimplementedforthestudents.Theinstitutionhastheauditorium,seminarhalls,eclassrooms,skilldevelopmentcentre,MIC,IBM,Incubationcentre,R&D,library,spaciousplaygroundwithallfacilities,culturalclubs,Enviroclub,NSSunitetc.,inordertomakethestudentsperfectin
cocurricular&extracurricularactivities.
ThemembersofCoCurricular&ExtraCurricularcommitteefromeachdepartmentarelistedbelow.
CoCurricular&ExtraCurricularCommittee:
Sr.No. Nameofthefaculty Designation Nameofthestudent Department
4 M.RajeswaraRao Member
C.V.Jaswanth ECE
5 T.Manivannan Member
6 R.G.Kumar Member
B.AnilKumarReddy CSE
7 B.Ravindranaik Member
Table9.19:Cocurricular&ExtracurricularCommittee
Cocurricular&ExtraCurricularFacility:
Sports,Seminarhalls,NSS,EnviroClub,Auditorium,WomanEmpowermentCell,CulturalClubetc.
A)CocurricularActivities:
TheSIDDHARTHQUESTisconductedtoencouragethestudentstoparticipateinPaperpresentation,TechnicalQuiz,etc.
Thestudentsareencouragedtogiveseminarsonlatesttrendsbeyondthesyllabus.
TheWorkshopsareorganizedontheemergingtechnologies.
Encouragethestudenttodevelopminiprojectsontheemergingtechnologiesandmakethempreparesomeprototypemodels.
ThetrainingisprovidedonSoftSkills,Technicalskills&Verbal&NonVerbalreasoning.
TheEDCbeingpartofthecocurricularactivitiesencouragesthestudentstobecomeemployers.
Encouragestudentstodevelopthecreativity,lateralthinkingandcommunication/peoplemanagementskillsthroughgoalsettingexercises,groupdiscussions,mockinterviewsandpresentations.
CocurricularAchievements:
No.ofParticipants
Sr.No. Branch CocurricularActivities
201415 201314 201213
1 CIVIL Paperpresentation 17 19 41
Technicalposter
2 MECHANICAL 82 16 11
Presentation
3 EEE Puzzles 40 29 18
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 167/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4 ECE Technicalquiz 99 41 26
Projectexpo
5 CSE Shortfilm 124 90 102
Table9.20:CoCurricularAchievements
SamplecopyofCoCurricularAchievements:
Prizes(I/II/III)/
Sr.No. NameoftheStudent Event Date OrganizedBy
Awards
AY:201415
T.VenkataKesava SreeVidhyanekethanCollege,
1 Symposium 30th ,31st &1st Nov2014 1st Prize
(12F61A0155) Tirupathi
G.Nandini
2 TechnoHunt 18th &19th Apr2014 SVU,Tirupathi 1st Prize
(12F61A0134)
G.Nandini
3 Quiz 15th Mar2014 JNTUA,Anantapur 2nd Prize
(12F61A0134)
U.Manjunath
4 Symposium 13th Mar2014 RGMCollege,Nandhyala 1st Prize
(12F61A0127)
G.Nandini
6 Symposium 18th &19th Apr2014 SVU,Tirupathi 2nd Prize
(12F61A0134)
G.Nandini
7 Quiz 15th Mar2014 JNTUA,Anantapur CertificateAwarded
(12F61A0134)
G.Nandini
8 Symposium 18th &19th Apr2014 SVU,Tirupati CertificateAwarded
(12F61A0134)
G.Nandini
9 Symposium 15th Mar2014 JNTUA,Anantapur CertificateAwarded
(12F61A0134)
U.Manjunath
15 Symposium 18th &19th Apr2014 SVU,Tirupathi CertificateAwarded
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 168/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(12F61A0127)
AY:201314
A.Brahmini
1 Symposium 8th &9th Mar2013 GoldenValley 1st Prize
(10F61A0105)
D.Bharathi
2 Symposium 8th &9th Mar2013 GoldenValley 1st Prize
(11F65A0104)
M.Harish
3 Symposium 10th Apr2013 SVCET,Chittoor 1st Prize
(10F61A0113)
S.Kartheek
4 Symposium 10th Apr2013 SVCET,Chittoor 1st Prize
(10F61A0117)
S.Kavitha
6 Symposium 11th May2013 SVCET,Chittoor 2nd Prize
(10F61A0119)
S.Dhanya
7 Symposium 11th May2013 SVCET,Chittoor 2nd Prize
(10F61A0110)
U.Manjunath
8 Symposium 2nd Mar2013 N.B.K.R. 3rd Prize
(12F61A0127)
U.Manjunath
9 Symposium 16th Feb2013 N.B.K.R. 3rd Prize
(12F61A0127)
B.Kavitha
10 Workshop 19th Mar2013 IITMadras CertificateAwarded
(10F61A0118)
M.Harish
11 Symposium 8th &9th Mar2013 SVCET,Chittoor CertificateAwarded
(10F61A0113)
P.DevendraNaidu
12 Symposium 8th &9th Mar2013 SVCET,Chittoor CertificateAwarded
(10F61A0109)
P.Mounika
13 Symposium 8th &9th Mar2013 SVCET,Chittoor CertificateAwarded
(11F61A0108)
P.Mounika
14 Symposium 8th &9th Mar2013 SVCET,Chittoor CertificateAwarded
(11F61A0108)
D.Bharathi
15 Workshop 4th &5th Feb2013 SVCE,Tirupathi CertificateAwarded
(11F65A0104)
Ch.Praveen
16 Workshop 9th &10th Dec2013 SVCE,Tirupathi CertificateAwarded
(10F61A0130)
U.Manjunath
17 Symposium 15th Mar2014 JNTU,Anantapur CertificateAwarded
(12F61A0127)
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 169/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
U.Manjunath
18 Symposium 13th Mar2014 RGM,Kurnool CertificateAwarded
(12F61A0127)
K.Lavanya
19 Symposium 26thFeb2013 SIST,Puttur CertificateAwarded
(11F61A0122)
AY:201213
S.KhajaNayabRasool
1 Symposium 20th Mar2012 SVIST,Madanapalle 1st Prize
(09F61A0134)
S.KhajaNayabRasool
2 Symposium 11th Mar2012 AITS,Tirupathi 2nd Prize
(09F61A0134)
S.KhajaNayabRasool
3 Symposium 22nd Mar2012 SVNE,Tirupathi 1st Prize
(09F61A0134)
N.SarathKumar
4 Symposium 20th Mar2012 SVIST,Madanapalle 1st Prize
(09F61A0130)
M.P.Rajan
5 Symposium 22th Mar2012 AITS,Tirupathi 2nd Prize
(09F61A0125)
M.P.Rajan
6 Symposium 21st Mar2012 KKC,Puttur 1st Prize
(09F61A0125)
S.KhajaNayabRasool
7 Symposium 29thJan2012 SVIST,Madanapalle 1st Prize
(09F61A0134)
M.P.Rajan
8 Symposium 09th &10th Mar2012 SVU,Tirupathi 1st Prize
(09F61A0125)
C.Sasidhar
9 Symposium 10th Mar2012 SIST,Puttur 1st Prize
(10F61A0137)
KYBabhitha
10 Symposium 25th Jan2012 KMM,Tirupathi 2nd Prize
(10F65A0103)
T.UmaMaheshwari
11 Symposium 25th Jan2012 KMM,Tirupathi 1st Prize
(09F61A0142)
K.Kavya
12 Symposium 21st &22nd 2011 VishvodayaTechnicalAcademy 2ndPrize
(08F61A0116)
K.Sailaja
13 PosterPresentation 28th Sep2011 SVCET,Tirupathi 3rd Prize
(09F61A0129)
Y.Nimeelika
14 Symposium 28th Sep2011 SVCET,Tirupathi CertificateAwarded
(08F61A0130)
Y.Nimeelika
15 Symposium 21st &22nd 2011 VishvodayaTechnicalAcademy 2nd Prize
(08F61A0130)
Y.Nimeelika
16 Symposium 21st &22nd 2011 VishvodayaTechnicalAcademy CertificateAwarded
(08F61A0130)
U.Manjunath
17 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 170/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(11F61A0130)
K.Lavanya
18 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0122)
N.Bhargavi
19 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0108)
G.MaheshKumar
20 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0127)
G.MaheshKumar
21 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0127)
B.Madhu
22 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0125)
L.Mallikarjuna
23 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0128)
P.DilipKumar
24 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0113)
N.Bhargavi
25 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0108)
V.Madhupriya
26 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0124)
K.Lavanya
27 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0122)
S.MaheshBabu
28 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0126)
T.Reddaiah
29 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0142)
S.MukeshKumar
30 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0132)
P.Balasubramanyam
31 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0105)
B.Avinash
32 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0103)
P.Harijyothi
33 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0117)
U.Manjunath
34 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0130)
P.Ashok
35 Workshop 7th Sep2012 VisvodayaCollege,Kavali CertificateAwarded
(11F61A0102)
K.Kavya
36 Symposium 9th &10th Jan2012 KSRM,Kadapa CertificateAwarded
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 171/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
(08F61A0116)
YNimeelika
37 Symposium 9th &10th Jan2012 KSRM,Kadapa CertificateAwarded
(08F61A0130)
PSKarthik
38 Symposium 18th &19thFeb2012 SVNE,Tirupathi CertificateAwarded
(10F61A0117)
PSKarthik
40 Symposium 9th &10th Mar2012 SVU,Tirupathi CertificateAwarded
(10F61A0117)
C.H.Praveen
41 Symposium 10th Mar2012 SIST,Puttur CertificateAwarded
(10F61A0130)
Table9.21:CoCurricularAchievements
CoCurricularActivities:
Extracurricularactivities:
TheinstitutionhasseparateNSSunitwith100studentvolunteers,sanctionedbyJNTUA.
TheNSSunitisheadedbyprogrammeofficer(facultyincharge)andChairman(Principal).
ThevariousactivitiesconductedthroughtheNSSunitareblooddonation,
Globalhandwashingday,SwatchBharathAbhiyan,GoodGovernanceday,Nationalunityday,Nationalyouthfestivalcelebration,Nationalvotersday,Republicdaycelebration,Massplantationprogramme,Roadsafetyawarenessprogramme,Internationalwomensday,etc.
Industrialvisitisorganizedeverymonthtoprovideexposureonrealtimeindustry&technologies.
Studentsaremotivatedtoparticipateinintercollegeeventsforpaperpresentationandprojectexhibitions.
Studentsareallowedtoparticipateinworkshop,technicalsymposium&eventswhichareconductedinothercolleges.
Intercollegecompetitionsforvariousindoorandoutdoorgamesareconducted.
ThestudentsareallowedtoparticipateinCulturaleventsduringvariouscollegefunctions.
ExtracurricularAchievementsinSports:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 172/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
No.ofparticipants
Sr.No. Events Levels
201415 201413 201312
1 National 4
2 HandBall State 1 1
VolleyBall
ShuttleBadminton
Cricket
3 Kabaddi University 16 3 1
ThrowBall
Tennikoit
BasketBall
Taekwondoselectiontrails
4 Zone 1
Chess
ShuttleBadminton
5 Intercollegiate 6
Table9.22:ExtraCurricularAchievements
SamplecopyofExtraCurricularAchievements:
Department:CivilEngineering
YEAR201415
YEAR201314
YEAR201213
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 173/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Table9.23:ExtraCurricularAchievements
ExtraCurricularActivities:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 174/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 175/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
NSSactivities:
No.of
Sr.No. Date Nameofactivity Place
volunteers
Year:201415
Headquarters,
5 25012015 Nationalvotersday. 80
Narayanavam(M).
Jogalaindlu,
8 17112014 Swatchbharathabhiyan. 100
RajivNagar.
Year:201314
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 176/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
5 26012014 Republicdaycelebration College. 75
Year:201213
VeerappareddyPalemVillage,
1 25012013 Notionalvotersday 80
Puttur
18022013
VeerappareddyPalemVillage,
2 to SpecialcampProgramme 51
Puttur
24022013
Table9.24:NSSActivities
10GOVERNANCE,INSTITUTIONALSUPPORTANDFINANCIALRESOURCES(120) TotalMarks120.00
10.1Organization,GovernanceandTransparency(40) TotalMarks
10.1.1StatetheVisionandMissionoftheInstitute(5) InstituteMarks
(VisionstatementtypicallyindicatesaspirationsandMissionstatementstatesthebroadapproachtoachieveaspirations)
Vision:
Tobeoneamongthepremierinstitutionsofthecountryinproducingethicallystrongandtechnicallysoundengineersandmanagerstoservethenation.
Mission:
Tocreatesacredenvironmentforthestudentstoacquireknowledgethroughinnovativeandprofessionalapproachandutilizeitforthewelfareofthemankind.
10.1.2Governingbody,administrativesetup,functionsofvariousbodies,servicerules,procedures,recruitmentandpromotionalpolicies(10) InstituteMarks
Listthegoverning,senate,andallotheracademicandadministrativebodiestheirmemberships,functions,andresponsibilitiesfrequencyofthemeetingsandattendancetherein,inatabularform.Afewsampleminutesofthemeetingsandactiontaken
reportsshouldbeannexed.
Thepublishedrulesincludingservicerules,policiesandproceduresyearofpublicationshallbelisted.Alsostatetheextentofawarenessamongtheemployees/students.
TheInstitutionhasbeenestablishedin2001underJayaEducationalSociety.IthasaGoverningbodytomonitorandachievingthevisionandmissionoftheinstitution.Ithasaneffectiveorganizationalstructurewhichmonitorsandimprovestheinstitution.Theorganizationalstructureoftheinstitutionisgivenbelow.
OrganizationalStructure:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 177/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig10.1Organizationalstructureoftheinstitution
A.GoverningBody
TheInstitutionhasaGoverningBody.ItisaPolicymakingbodyoftheInstitutionandmeetsfrequentlyanddiscussestheagendapreparedbythePrincipal.Itreviewstheperformanceoftheinstitutionanddecisionstakeninthepreviousmeetingandalsoapprovesthepolicydecisions.Thebudgetofthecurrentacademicyearisfinalized.All
newproposalsarediscussedanddecisionstaken.
Qualificationsandpositioninthecurrent
Sr.No. NameoftheMemberofBoG PositioninBoG Nominatedby
engagements
Chairperson
MembersoftheTrust/Society/Management
B.Tech.(IIT,Gowhathi)
VIVUTechnologies(P)LTD.,USA
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 178/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
FacultymembersoftheInstitution
M.E.,Ph.D.
6 Dr.M.JanardhanRaju Member Principal
Prof.&HOD,ECE
EducationistsorIndustrialists
M.Tech.,CMD,
8 Mr.D.JaiRamesh Member Society
VijayElectricalsLimited,Hyderabad
M.S.,VicePresident,
9 Mr.GaddeSridhar Member Society
ICOMLimited,Hyderabad
OnenomineeoftheAICTE/UGC.
UnderProcessRequestedAICTEfor
10 Tobenominated Member AICTE
nominationofaMember
OnenomineeoftheStateGovernment
OnenomineeoftheUniversitytowhichtheInstitutionisaffiliated.
M.Tech.,Ph.D.(NominatedbyJNTUA, JNTUA,
12 Dr.V.Sankar Member
Ananthapuramu) Ananthapuramu
HeadoftheInstitution,Exofficio
M.Tech.,Ph.D., Member
13 Dr.K.ChandrasekharReddy ExOfficio
Principal Secretary
Table10.1ListoftheGoverningBody(BoG)members
1.TheSampleminutesofmeetingoftheGoverningbodyminutesofmeetingandWebsite/ICT/InternetCommitteeareannexedin10.1.
2.Rulesofannualleaves,casualleaves,studyandspecialleavesandincentivesareannexedin10.2.
B.VariousCommitteesoftheInstitution
TheInstitutionhas31committeesfortheeffectivefunctioningoftheorganization.Theobjectivesandfunctionsofthecommitteesareorganizedaspertheguidelinesoftheheadoftheinstitution.
Thelistandfrequencyofthemeetingsarementionedinthebelowtable.
1 AcademicAdvisoryCommittee Onceinthesemester,asandwhenrequired
2 CollegeAcademicCommittee Monthlyonce,asandwhenrequired
3 GrievanceRedressalCell Monthlyonce,asandwhenrequired
4 StudentCounselingCommittee onceinthesemester,asandwhenrequired
5 Purchase/StoresCommittee onceinsemester,asandwhenrequired
6 PublicRelations&PublicationsCommittee Monthlyonceinthesemesterwheneverrequired
7 R&DandConsultancyCommittee Monthlyonceinthewheneverrequired
8 Training&PlacementCommittee Onceineveryfortnight,asandwhenrequired
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 179/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
9 HostelCommittee Onceineveryfortnight,asandwhenrequired
10 CollegeMaintenanceCommittee Monthlyonce,asandwhenrequired
11 NSSCommittee Monthlyonce,asandwhenrequired
12 SocialWelfare(BC/SC/ST)Committee Onceineveryfortnight,asandwhenrequired
13 Sports&GamesCommittee Monthlyonce,asandwhenrequired
14 TransportationCommittee Monthlyonce,asandwhenrequired
15 Arts/CulturalCommittee Onceineveryfortnight,asandwhenrequired
16 DepartmentAssociationsCommittee Onceineveryfortnight,asandwhenrequired
17 Examinations/TimeTable/AdmissionsCommittee Monthlyonce,asandwhenrequired
18 LibraryCommittee Onceineveryfortnight,asandwhenrequired
19 IndustryInstitutePartnershipCell Monthlyonce,asandwhenrequired
20 EntrepreneurshipDevelopmentCell Monthlyonce,asandwhenrequired
21 Website/ICT/InternetCommittee Onceineveryfortnight,asandwhenrequired
22 AlumniCoordinationCommittee onceinthesemester,asandwhenrequired
23 InternalQualityAssuranceCell onceinthesemester,asandwhenrequired
24 InternalComplaintsCommittee Monthlyonce,asandwhenrequired
25 RTICell Monthlyonce,asandwhenrequired
26 ProfessionalSocieties&ActivitiesCommittee Onceineveryfortnight,wheneverrequired
27 GenderChampionshipCommittee Monthlyonce,asandwhenrequired
28 AntiRaggingCommittee Monthlyonce,asandwhenrequired
29 ResultAnalysisCommittee Onceinthesemester
30 WomenEmpowermentCell Monthlyonce,asandwhenrequired
Onceinbeginningoftheacademicyear,asandwhen
31 JNTUA,AICTE,NAAC,NBA&ISOCommittee
required
Table10.2Listofvariouscommitteesoftheinstitution
C.ConstructionandMaintenanceWing:
ItworksundercontroloftheSecretarywiththeassistanceofChiefOperatingOfficer,MaterialsManager,ConstructionManager,MaintenanceManageretc.
TheBuildingInchargemaintainsthebuildingsandfacilitieswiththehelpofACmechanic,Electrician,PlumberandCarpenter.TheMaintenanceManagerwillkeeptheinstitutewithefficientmaintenancewiththehelpofhousekeeping,gardenersandSecurity.
OrganizationalsetupoftheConstructionandMaintenanceWing:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 180/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Fig.10.2OrganizationalsetupoftheConstructionandMaintenanceWing
D.Servicerules,policiesandprocedures
Theinstitutionhasitsownservicerules,policiesandproceduresforeffectivefunctioningoftheinstitution.Itispublishedin2002andrevisedin2015
AlltheseareavailableatPrincipalsoffice,HODschamber,library,Examinationcell,placementcelletc.,anddistributedamongalltheemployees.Itisalsodisplayedininstitutionalwebsite.
HRManualCoverpage
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 181/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
HRManualContents
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 182/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 183/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
TheinstitutionhasitsownHRpoliciesforthesmoothorganization.ThecontentsoftheHRmanualaregivenabove.TheseHRpolicieshelpsinachievingtheinstitutionvisionandmissioneffectively.
E.RecruitmentandPromotionalPolicies
RecruitmentofFaculty/SupportingStaff
Itisoneofthefirstinstitutionsintheregiontoadvertiseforfacultytoattractthebesttalent.
Advertisementsarepublishedinthestateandnationallevelnewspapers.
Interviewsareconductedbyapanelconsistingofseniorfaculty,HeadoftheDepartment,Externalsubjectexpert,PrincipalandChairman.
Preferenceisgiventorelevantqualifications,teaching,researchandindustrialexperience.
Ademonstrationistakenfromeachpersontounderstandtheteachingcapabilitiesandcompetency.
TheguidelinesoftheuniversityandAICTEarefollowedduringtherecruitmentofthefaculty.
Theselectedcandidatesarerequiredtoattendtheuniversityratificationprocess.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 184/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
SupportingstaffarerecruitedbythepanelconsistsofHODs,PrincipalandChairman.
PromotionalPolicies
Basedonthestaffperformanceappraisal,theyarepromotedtohigherlevels.
10.1.3Decentralizationinworkingandgrievanceredressalmechanism(10) InstituteMarks
Listthenamesofthefacultymemberswhohavebeendelegatedpowersfortakingadministrativedecisions.Mentiondetailsinrespectofdecentralizationinworking.SpecifythemechanismandcompositionofgrievanceredressalcellincludingAntiRagging
Committee&SexualHarassmentCommittee.
Theinstitutionhas31committees/cellstoensurethedecentralizationandefficientexecutionofadministrativeworks.Eachcommitteehasonecoordinatorandfacultymembersfromeverydepartment.Thesecommitteesaremonitoredbytheheadoftheinstitution.Allthesecommitteesareinvolvedindatacollection,organizingactivities,
periodicalreviewsandprovidingsuggestionsforfurtheractions.Theyfrequentlyconductmeetingsandmaintaintherecords.Inadditiontotheinvolvementinthesecommittees,therearesomeotherdepartmentalresponsibilitiesforthefacultysuchasClassincharge,Projectincharge,labincharge,attendanceinchargeetc.Theadministrative
setupofthedepartmentisgivenbelow.
OrganizationalSetupoftheDepartment
Fig10.3OrganizationalSetupoftheDepartment
Thenamesofthecoordinatorsofallcommitteesarementionedinthefollowingtables.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 185/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
CommitteesandCoordinators
1. AcademicAdvisoryCommittee Dr.K.ChandrasekharReddy(Principal)
2. CollegeAcademicCommittee Dr.K.ChandrasekharReddy(Principal)
3. GrievanceRedressalCell C.P.Gopi
4. StudentCounselingCommittee J.Suneetha
5. Purchase/StoresCommittee Dr.M.JanardhanaRaju
6. PublicRelations&PublicationsCommittee Dr.P.Subramanyachari
7. R&DandConsultancyCommittee P.RameshBabu
8. Training&PlacementCommittee G.PrasadBabu
9. HostelCommittee O.NarendraReddy
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 186/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
26. ProfessionalSocieties&ActivitiesCommittee C.Dhanalakshmi
Table10.3ListofCommitteecoordinatorsofvariouscommittee
AdministrationCoordinators:
1. HeadoftheInstitution(Principal) Dr.K.ChandraSekharReddy
2. ChiefOperatingOfficer M.B.AnilMenon
3. HeadoftheDepartmentCIVIL Dr.S.SiddiRaju
4. HeadoftheDepartmentEEE N.RameshRaju
5. HeadoftheDepartmentMECH Dr.S.SunilKumarReddy
6. HeadoftheDepartmentECE Dr.M.JanardhanRaju
7. HeadoftheDepartmentCSE P.Nirupama
8. HeadoftheDepartmentBS&H B.HariKrishna
9. HeadoftheDepartmentMBA C.P.Gopi
Table10.4Listofcoordinatorsforvariousadministrativecommittees
MechanismandCompositionofGrievanceRedressalCell,AntiraggingCommittee&SexualHarassmentCommittee
i)GrievanceRedressalCell
TheinstitutionhasaGrievanceRedressalCell(GRC)headedbyaseniorfacultyandsupportedbytheotherfacultymembersfromallthedepartments.ThecommitteeismaintainedaspertheAICTEguidelines.TheGRCtakescareofthegrievancesofstudents/staff.Theyeithercandroptheirgrievancesinthesuggestionboxorcandirectly
reporttotheGRC.Thestudentsareallowedtosharetheirgrievancesevenwiththeircounsellorsandclassteachers.NecessaryremedialmeasureswillbeinitiatedbytheGRC,ifitisnecessarythesamewillbebroughttothenoticeofPrincipal/Chairman.
FollowingistheconstitutionofGrievanceRedressalCell:
C.P.Gopi
1. MBA Coordinator
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 187/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Professor&HOD
S.Choudaiah
2. MCA Cocoordinator
Professor&HOD
Dr.S.SiddiRaju
3. CIVIL Member
Professor&HOD
N.RameshRaju
4. EEE Member
Professor&HOD
Dr.S.SunilKumarReddy
5. MECH Member
Professor&HOD
Dr.M.JanardhanRaju
6. ECE Member
Professor&HOD
P.Nirupama
7. CSE Member
Professor&HOD
B.HariKrishna
8. BS&H Member
Professor&HOD
P.ChandraSekhar
9. EEE Member
AssociateProfessor
B.Ganeshan
10. BS&H Member
AssistantProfessor
Table10.5ListofCommitteemembersoftheGrievanceRedressalCell
SomeoftheGrievancesreceivedandaddressedareasfollows:
Grievancesreceived
Suggestionboxesshouldbesetupinthemajorlocationsofthecampus.
Foodqualityinthecanteenshouldbeimproved
WiFifacilityshouldbeextendedforstudentsalso
Transportationfacilitiesshouldbeprovidedwhenadepartmentorganizesextracurricularactivitiesbeyondworkinghours
Transportationfacilitiesshouldbeprovidedtoadditionalroutes
Additionalparkingfacilitiesforbikes
Grievancesaddressed
Suggestionboxesweresetupinthemajorlocationsofthecampus.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 188/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Earlier,thecanteenwasoutsourced.Now,themanagementisrunningthecanteenandthequalityoffoodhasimprovedsignificantly.
WiFifacilityisprovidedforallfacultiesandstudents.
Withpriorintimationtobusinchargeandprincipal,eventorganizers/coordinatorscanarrangespecialbuses.
Transportationfacilitiesareextendedtoadditionalroutesaspertherequestsmadebythestudentsandthestaff.
Parkingplaceisprovidedoutsideofthecollegeforstudentsandinsideforfaculty.
ii)AntiRaggingCommittee
Theinstitutionhasconstitutedantiraggingcommitteetopreventragginginsidetheinstitutionpremisesandalsotocreateawarenessamongthestudentssoastopreventthesamefromhappeningoutsidethecampus.IthasthePrincipal,HODs,faculty,supportingstaffandseniorstudents.
FollowingarethemembersoftheAntiRaggingCommittee
Dr.K.ChandrasekharReddy
1. ADMIN Chairman
Principal
B.HariKrishna
2. BS&H Coordinator
Professor&Head
P.RameshBabu
3. CSE Cocoordinator
AssociateProfessor
C.P.Gopi
4. MBA Member
Professor&Head
S.Choudaiah
5. MCA Member
Professor&Head
Dr.S.SiddiRaju
6. CIVIL Member
Professor&Head
N.RameshRaju
7. EEE Member
Professor&Head
Dr.S.SunilKumarReddy
8. MECH Member
Professor&Head
Dr.M.JanardhanRaju
9. ECE Member
Professor&Head
P.Nirupama
10. CSE Member
Professor&Head
S.VamsiKrishna
11. ECE Member
AssociateProfessor
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 189/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
18. K.Pushparaj MCA StudentMember
Table10.6ListofthecommitteemembersoftheAntiraggingcommittee
Theinstitutionhastakenthefollowingmeasurestopreventragging.
AntiRaggingcommitteesinvolvingteaching,Nonteachingstaffandseniorstudentsareconstituted.
TheentirecampusisunderCCTVcamerasurveillance.
Bannersandpostersonantiraggingactaredisplayedatprominentplaces.
Complaintboxesatfirstyearclassroomsandatprominentplacesarearranged.
TheTelephonenumbersofthecollegeadministration,D.S.P.,C.I.,andS.I.ofpolicearedisplayedatprominentplaces.
AntiRagginghelplinenumberandwebsiteaddressaredisplayedinthecampusatprominentplaces,usingwhichstudentscanreceiveassistancewithin15minutes.
AwarenessonAntiRaggingactiscreatedtoallthestudentswiththeinvolvementofjudiciary,revenueandpolicedepartments.
AwarenessonAntiRaggingactiscreatedtoallthestudentsbytheprincipal,HODsandseniorfacultymembersineachclass.
ThedateofcommencementoffirstyearclassworkisinformedtothelocalpolicestationandalsointimatedtoC.I.,D.S.P.,Puttur.
Undertakingformsareobtainedfromthestudentsandtheirparentsstatingthatseniorstudentsdonotinvolveinraggingofanyform.
Separatebusesarearrangedforthefirstyearstudents.
Lunchtimingsandclasstimingsofthefirstyearstudentsaredifferentfromthatoftheseniorstudents.
Classroomsforfirstyearstudentsarearrangedinaseparateblock.
Freshersdayisconductedwithinonemonthfromthecommencementoffirstyearclasswork.
Thefacultymembersaredeputedashostelwardensinordertohavebettervigilance.
AllthestudentsareissuedIDcardsandnooutsidersareallowedintothehostel.
Theimplementationoftheabovemeasuresresultedin,noincidentofragginghasbeenhappenedtilldateinthecampus.Ourcampusisraggingfreecampus.
iii)SexualHarassmentCommittee(InternalComplaintsCommittee)
InpursuanceoftheSexualHarassmentofWomenatWorkplace(Prevention,ProhibitionandRedressal)Act2013andtheRulesframedthereunder,theInstituteherebyadoptsthefollowingprocedurefordeterminingcomplaintsfiledtotheInternalComplaintsCommittee(ICC)constitutedundertheAct.Theprocedurecomplieswiththe
basicprinciplesofnaturaljusticeandfairplayandhastobeadheredtoinallcomplaints,though,inindividualcomplaints.
FollowingarethemembersoftheInternalComplaintsCommittee:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 190/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Table10.7ListofcommitteemembersoftheInternalComplaintsCommittee
TheICCFunctioningprocedure
AnyaggrievedwomanmaycomplaintofsexualharassmentatworkplacetotheICC,withinaperiodofthreemonthsfromthedateofincidentandincaseofseriesofincidents,withinaperiodofthreemonthsfromthedateoflastincident.
AdditionaldocumentsandlistofwitnessescanbesubmittedtoICCatalaterstageduringtheproceeding.
AnycomplaintreceivedbythemembersshouldimmediatelybeforwardedtotheSecretaryoftheICC,andthismustbenotifiedtoothercommitteemembersattheearliestandameetingshouldbecalledfordiscussingthematter.
TheICCshalldiscussanddecideonitsjurisdictiontodealwiththecaseorrejectthecomplaintprimafacieandrecommendtotheheadoftheinstitutionforfurtheractions.
TheCommitteewillprovideassistancetotheaggrievedwoman,ifshesochooses,tofileapolicecomplaintinrelationtoanoffenceunderIndianPenalCode.
TheCommitteesuggeststheheadoftheinstitutiontoensurethesafetyandprotectionoftheaggrievedwomanasandwhenrequired.
TheinstitutionstrictlyimplementstherulesthataregivenbytheUGCtoavoidsexualharassmentatworkplace.
Duetotheseprecautionarymeasures,nosuchanincidentofwomanharassmenthasbeenhappenedtilldateinthecampus.
10.1.4Delegationoffinancialpowers(10) InstituteMarks
InstitutionshouldexplicitlymentionfinancialpowersdelegatedtothePrincipal,HeadsofDepartmentsandrelevantincharges.Demonstratetheutilizationoffinancialpowersforeachyearoftheassessmentyears
TheinstitutionismaintainingaseparateaccountinthenameofthePrincipal.Allthefinancialtransactionsarecarriedthroughthisaccount.TheHODsandInchargescansubmitthefinancialproposalstotheprincipalwellinbeforethecommencementoftheacademicyear.Thedepartmentheadshavethefinancialpowerthrough
theprincipalsaccount.Eachdepartmentutilizesthefinancialprovisionmaximumof1lakhthroughprincipalsaccountpermonth.Ifitismorethan1lakh,theletterhastobeforwardedtothechairmanoftheinstitutionfortheapproval.TheGoverningBodyreviewstheproposalsandmakesappropriatebudgetallocations.
10.1.5Transparencyandavailabilityofcorrect/unambiguousinformationinpublicdomain(5) InstituteMarks
(Informationonpolicies,rules,processesanddisseminationofthisinformationtostakeholdersistobemadeavailableonthewebsite)
TheinstitutionhasitsownHRpolicies,servicerulesandprocesseswhicharedisseminatedtothestakeholdersbydisplayingatPrincipalsoffice,HODschamber,library,Examinationcell,placementcelletc.,anddistributedamongalltheemployees.Itisalsomadeavailableintheinstitutionalwebsite(www.sietk.org).
Theparticularsrelatedtothestudents,facultyandsupportingstaffandotherinstitutionaldetailsaremadeavailableinthewebsite.
TheinstitutionHRManual(policies,rulesandprocesses)isavailableatPrincipal&HODoffices.
Theauditreportsareplacedintheinstitutionwebsite(www.sietk.org/audit.html(http://www.sietk.org/audit.html))andstudentandfacultyincentivesarealsoavailableintheinstitutionwebsite(www.sietk.org/incentives.(http://www.sietk.org/incentives.)html)
10.2BudgetAllocation,Utilization,andPublicAccountingatInstitutelevel(30) TotalMarks
Summaryofcurrentfinancialyearsbudgetandactualexpenditureincurred(fortheinstitutionexclusively)inthethreepreviousfinancialyears
TotalIncomeatInstitutelevel:ForCFY,CFYm1,CFYm2&CFYm3
CFY:(CurrentFinancialYear),
CFYm1:(CurrentFinancialYearminus1),
CFYm2:(CurrentFinancialYearminus2)and
CFYm3:(CurrentFinancialYearminus3)
Table1CFY20142015
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 191/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Table2CFYm120132014
Table3CFYm220122013
Table4CFYm320112012
Teachingandnonteaching
72022000 72020000 63421000 63421000 55300000 55300000 30700000 30700000
staffsalary
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 192/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
10.2.1Adequacyofbudgetallocation(10) InstituteMarks
(Theinstitutionneedstojustifythatthebudgetallocatedduringassessmentyearswasadequate)
Basedontherecommendationsofthevariouscommitteesbudgetisallocatedforvariousitemssuchasinfrastructure,library,laboratoryconsumables,teachingandnonteachingsalaries,maintenanceandspares,R&Detc.,aresatisfactory.ItisevidentfromtheaboveBudgettables.
10.2.2Utilizationofallocatedfunds(15) InstituteMarks
(Theinstitutionneedstostatehowthebudgetwasutilizedduringassessmentyears)
Fundprovidedtothealldepartmentsisproperlyusedtodeveloptheinfrastructureoftheofeachdepartmenttoachieveabetterprogrammeoutcome.
10.2.3Availabilityoftheauditedstatementsontheinstituteswebsite(5) InstituteMarks
(Theinstitutionneedstomakeauditedstatementsavailableonitswebsite)
TheaccountoftheInstituteisauditedbyateamofAuditors.AcopyoftheReportissubmittedtotheInstitute.ThisReportisplacedintheinstituteswebsiteeveryyearimmediatelyafterreceivingfromtheauditors.Thereportremainsconfidentialuntilitsconsiderationandfinalapproval.
10.3ProgramSpecificBudgetAllocation,Utilization(30) TotalMarks
InstituteMarks
TotalIncomeatInstitutelevel:ForCFY,CFYm1,CFYm2&CFYm3
CFY:(CurrentFinancialYear),
CFYm1:(CurrentFinancialYearminus1),
CFYm2:(CurrentFinancialYearminus2)and
CFYm3:(CurrentFinancialYearminus3)
Table1::CFY20142015
Table2::CFYm120132014
Table3::CFYm220122013
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 193/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Table4::CFYm320112012
Software 0 0 0 0 0 0 0 0
10.3.1Adequacyofbudgetallocation(10) InstituteMarks
(Programneedstojustifythatthebudgetallocatedovertheassessmentyearswasadequatefortheprogram)
Thebudgetallocatedwassufficientforthecivilengineeringdepartmentequipmentpurchase,maintenanceoflabs,conductingworkshopsetc.Themanagementisallottingrequiredbudgettodevelopthedepartmentinallaspects.Thebudgetisshowninabovetable.
10.3.2Utilizationofallocatedfunds(20) InstituteMarks
(Programneedstostatehowthebudgetwasutilizedduringthelastthreeassessmentyears)
Fundprovidedtothedepartmentisproperlyusedtodeveloptheinfrastructureoftheofthedepartmenttoachieveabetterprogrammeoutcome.
10.4LibraryandInternet(20) TotalMarks
(IndicatewhetherzerodeficiencyreportwasreceivedbytheInstitutionforalltheassessmentyears.Effectiveavailability/purchaserecordsandutilizationoffacilities/equipmentetc.tobedocumentedanddemonstrated)
TheInstitutionisreceivedthezerodeficiencyreportforallthethreeassessmentyears.Itishavingallthefacilitiesinthelibraryaspernorms.
Thelibraryishavingdedicatedstaff,thedetailsarementionedinbelowtable.
1 H.KasthuriM.A.,B.Ed.,M.LiSc.,M.Phil Librarian
2 P.SharadhaB.A.,M.LiSc AssistantLibrarian
3 T.MuralikrishnaM.A.,PGDCA DataEntryOperator
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 194/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
4 K.Sujatha DigitalLibraryIncharge
5 K.Praveena LibraryAssistant
6 K.Megavarnam Attendar
Table10.12ListofStaffMembersinthelibrary
ThelibraryhasanadvisorycommitteewiththeChiefLibrarianastheCoordinator&seniorfacultyandthestudentrepresentativesfromallthedepartmentsasmembers.TheCommitteetakescareofallthepurchasesandutilizationoffacilitiesinthelibrary.Thelistofcommitteemembersandtheirresponsibilitiesismentionedbelow.
MembersofLibraryCommittee
H.Kasthuri,
2. Library Cocoordinator
ChiefLibrarian
N.DeepakKumar,
3. CSE Member
AssociateProfessor
V.S.Meganathan
4. CIVIL Member
AssistantProfessor
K.Shruthi,
5. EEE Member
AssistantProfessor
B.A.Devan,
6. MECH Member
AssistantProfessor
R.P.V.G.AshokReddy,
7. ECE Member
AssistantProfessor
G.Yamuna,
8. MBA Member
AssistantProfessor
P.Karthikeyan,
9. MCA Member
AssistantProfessor
Table10.13ListofCommitteemembersofthelibrary
Responsibilitiesofthecommittee
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 195/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
TheCommitteefrequentlyconductsmeetingstodiscussindetail,theadditionalfacilitiesrequiredforthelibrary.
Itcollectstherequirementsofthelibraryfromthedepartmentsatthebeginningoftheacademicyear.
Itpreparesquotationsforpurchasingbooks,journals,magazinesetc.,
Itensurestheavailabilityofthelibraryresourceswellinbeforethecommencementoftheclasswork.
Itensuresthattheeresourcesareavailableinthedigitallibraryforselflearning.
Italsoemphasizesonsubscribingthemostreputedmagazinesandjournalsforthepurposeofresearch.
Itmaintainsthestockregistersofthelibrarybooks,journalsandmagazinesetc.,
Itpreparesthebudgetrequiredforlibraryinthebeginningofacademicyear.
TheinitiativesareimplementedbytheCommitteetorenderthelibrary,student/userfriendly.
TheinstitutionhastheWebsite/ICT/InternetCommitteewiththeChiefITManagerastheCoordinator&seniorfacultyandthestudentrepresentativesfromallthedepartmentsasmembers.TheCommitteetakescareofallthepurchasesandutilizationoffacilitiesofInternet.Thelistofcommitteemembersandtheirresponsibilitiesis
mentionedbelow.
MembersofWebsite/ICT/InternetCommittee
S.No. NameoftheMember Department Position
M.SatheeshBabu
1 IT Coordinator
ChiefITManager
A.Dhasaradhi
2 CSE Cocoordinator
AssociateProfessor
S.ArifHussian
3 CIVIL Member
AssistantProfessor
B.Srinivasulu
5 MECH Member
AssistantProfessor
M.Amarnadh
6 ECE Member
AssistantProfessor
V.Sreedhar
7 BS&H Member
AssistantProfessor
M.NareshBabu
8 MBA Member
AssistantProfessor
Table10.14ListofCommitteemembersoftheWebsite/ICT/InternetCommittee
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 196/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Responsibilitiesofthecommittee
TheCommitteefrequentlyconductsmeetingstodiscussindetailtheenhancementoftheWebsite/ICT/Internetfacilities.
Itdevelopstheinstitutionswebsitewithmoderntechnology,providestheappropriateandrelevantinformation.
ItprovidestheICTtoolsforallthedepartments.
IttakescareofadequateInternetfacilitythroughoutthecampus.
MaintenanceoftheLAN,routersthroughoutthecampus.
ProvidingthehighsecurityforinstitutionsdatafromtheHackers.
ItensuresthattheInternetresourcesareavailableforselflearning.
Italsoemphasizesonsufficientbandwidthtomeettherequirementsoftheinstitution.
ItpreparesthebudgetproposalrequiredforWebsite/ICT/Internetfacilitiesinthebeginningofacademicyear.
10.4.1Qualityoflearningresources(hard/soft)(10) InstituteMarks
Relevanceofavailablelearningresourcesincludingeresources
Accessibilitytostudents
Supporttostudentsforselflearningactivities
i)Relevanceofavailablelearningresourcesincludingeresources
Thelibraryhasvariouslearningresources,includingeresources.Thedetailsarementionedbelow:
Totalareaofthelibrary=720Sqm(areasplitforallsections)
LibraryAreadivisionandMeasurements
1 Textbook&Librarysection 250
2 ReadingandCirculation 200
3 Referencesection 55
4 Enrollmentsection 15
5 DigitalLibrary 70
6 NPTELvideosection 130
Table10.15ListofDifferentsectionsofthelibrary
Totalseatingcapacity=300persons
5024titles
26635volumes
5128referencebooks
1053ebooks
140journals/magazines
3164projectreports(hardandsoftcopies)
DigitalLibrarywith30computers
Internetfacility
NPTELVideolessonsareavailableforalltheprograms.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 197/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
1 CIVIL 640
2 ME 599
3 EEE 822
4 ECE 816
5 CSE 635
TOTAL 3512
Table10.16ListofNPTELVideos
IEEEInternationalJournals(hardandsoftcopies)
1 CIVIL 8 9
2 ME 7 13
3 EEE 7 14
4 ECE 11 23
5 CSE 11 10
Table10.17ListofJournals
JGateandDELNETEJournalresourcesusingusernameandpasswordprovidedbythedigitallibraryincharge.
SONETvideolecturesofallprograms.
VideolecturesonJNTUAcurriculumwhicharesuppliedbyPearsonEducare
Coursematerialisavailableforalltheprograms.
Booksareavailableforvariouscompetitiveexams.
Scanning,printingandreprographicfacilities.
Thefollowingpicturesshowtheresourcesavailableinthelibrary:
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 198/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
ii)Accessibilitytostudents
Alibraryhourisincludedinthetimetableandismandatoryforallclasses.Thestudentsareencouragedtoutilisetheresourcesavailableinthelibraryduringthehour.Theclassteacherconcernedaccompaniesthestudentstoproperutilizationoftheresources.
Thelibraryiskeptopenbeyondtheworkinghoursoftheinstitutionforthebenefitofstudentsandfaculty.Studentsareencouragedtopreparetheirownnotes/materialbyusingthevarietyofresourcesavailableinthelibrary.
Thestudentsandfacultyareissuedthelibrarycardsforborrowingthebooks.
TheBookbankfacilityisalsoavailable.
Forvisually/physicallychallengedstudentsbooksareissuedfortheentiresemesterandsuchstudentsneednotcometothelibraryforborrowingbooks.TheLibrarystaffmembersassistthem.
Eresourcesareaccessiblefromthedigitallibraryanddepartmentallibraryalso.
Studentcanaccessonlinejournalsavailableinthedigitallibraryanddepartmentlibrarywithusernameandpasswordprovidedbytheconcernedincharges.
Librarytimings:
Duration WorkingHours
WorkingDays 8a.m.6p.m.
Holidays 9a.m.4p.m.
BeforeExaminations 8a.m.8p.m.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 199/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
DuringExaminations 8a.m.8p.m.
DuringVacation 9a.m.4p.m.
Table10.18LibraryTimings
Samplecopyofclasstimetablewithlibraryhour
iii)Supporttostudentsforselflearningactivities
Theinstitutionsupportsvariousselflearningactivitiestothestudents.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 200/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
Thelibraryisthebestresourcesforselflearning.
Thelibrarycontainsvastcollectionoftitles,volumes,referencebooksandebooks.
IthasgoodnumberofpeerreviewedNationalandInternationaljournalsforalltheprograms.
Hardandsoftcopiesofprojectreportsaremadeavailablewiththelibrary.
IthasDigitallibrarywith30systemswithinternetconnectivity.
HardandsoftcopiesofIEEEJournalsareavailable.
NPTEL,SONETandPearsonEducarevideolecturesareavailable.
JGateandDELNETonlineresourcesareavailable.
Coursematerialsareavailableforalltheprograms.
Booksareavailableforvariouscompetitiveexams.
Studentsaremotivatedtoparticipateintechnicalseminarsandconferences.
Specialappreciationstothestudentswhopublishedpapersinreputedjournals.
10.4.2Internet(10) InstituteMarks
NameoftheInternetprovider BSNL,ExcellMediaPvt.Ltd
Availablebandwidth 10Mbps(BSNL),100Mbps(ExcellMediaPvt.Ltd)
WiFiavailability TheWiFifacilityisavailableintheinstitutionwith10Mbpsspeedand
thisfacilityisextendedtodifferentlocationsinandaroundthecampus.
Internetaccessinlabs,classrooms,library Internetisprovidedtoallthestudentsandfacultybyusernameand
TheInternetaccessisavailableintheCentralComputingCentre,
andofficesofallDepartments
passwordprovidedbythesystemadministrator.Description:1.UniFi
laboratories,classrooms,libraryandofficesofallthedepartments.
Securityarrangements APLR3Pack:Indoor2.4GHzAccesspoint.2.Metal2SHPnwith17
ThecampusalsoisWiFienabled.
Thecomputersaremaintainedwithhighsecurityantivirussoftwares.
dBiSectorAntenna:Outdoor2.4GHzAccessPointwith180Degrees
KasperskyAntivirus(client),QuickHealServerEdition. Firewalls
Sector.
andphishingconfiguredinserversfordatamanagement. User AnnexureI
authenticationisprovidedforallthestudentsandfaculty. Proxy
(A)PROGRAMOUTCOME(POs)
EngineeringGraduateswillbeableto: serverisrunningonFedoratotransfersecuredpackets. Server
roomisundersurveillance. TheStudentsareabletoaccessWiFi
connectivitywithusernameandpasswordmechanismprovidedbythe
1.EngineeringKnowledge:Applytheknowledgeofmathematics,science,engineeringfundamentals,andanengineeringspecializationtothesolutionofcomplexengineeringproblems.
Networkadministrator. AlltheWiFiuseractivities(browsinghistory)
2.ProblemAnalysis:Identify,formulate,reviewresearchliterature,andanalyzecomplexengineeringproblemsreachingsubstantiatedconclusionsusingfirstprinciplesofmathematics,naturalsciences,andengineeringsciences.
arestoredintheInternetServer.
3.Design/developmentofsolutions:Designsolutionsforcomplexengineeringproblemsanddesignsystemcomponentsorprocessesthatmeetthespecifiedneedswithappropriateconsiderationforthepublichealthandsafety,andthecultural,
societal,andenvironmentalconsiderations.
4.Conductinvestigationsofcomplexproblems:Useresearchbasedknowledgeandresearchmethodsincludingdesignofexperiments,analysisandinterpretationofdata,andsynthesisoftheinformationtoprovidevalidconclusions.
5.Moderntoolusage:Create,select,andapplyappropriatetechniques,resources,andmodernengineeringandITtoolsincludingpredictionandmodelingtocomplexengineeringactivitieswithanunderstandingofthelimitations.
6.Theengineerandsociety:Applyreasoninginformedbythecontextualknowledgetoassesssocietal,health,safety,legalandculturalissuesandtheconsequentresponsibilitiesrelevanttotheprofessionalengineeringpractice.
7.Environmentandsustainability:Understandtheimpactoftheprofessionalengineeringsolutionsinsocietalandenvironmentalcontexts,anddemonstratetheknowledgeof,andneedforsustainabledevelopment.
8.Ethics:Applyethicalprinciplesandcommittoprofessionalethicsandresponsibilitiesandnormsoftheengineeringpractice.
9.Individualandteamwork:Functioneffectivelyasanindividual,andasamemberorleaderindiverseteams,andinmultidisciplinarysettings.
10.Communication:Communicateeffectivelyoncomplexengineeringactivitieswiththeengineeringcommunityandwithsocietyatlarge,suchas,beingabletocomprehendandwriteeffectivereportsanddesigndocumentation,makeeffective
presentations,andgiveandreceiveclearinstructions.
11.Projectmanagementandfinance:Demonstrateknowledgeandunderstandingoftheengineeringandmanagementprinciplesandapplythesetoonesownwork,asamemberandleaderinateam,tomanageprojectsandinmultidisciplinary
environments.
12.Lifelonglearning:Recognizetheneedfor,andhavethepreparationandabilitytoengageinindependentandlifelonglearninginthebroadestcontextoftechnologicalchange.
(B)PROGRAMSPECIFICOUTCOME(PSOs)
Declaration
TheheadoftheinstitutionneedstomakeadeclarationaspertheformatgivenBelow:
ThisSelfAssessmentReport(SAR)ispreparedforthecurrentacademicyearandthecurrentfinancialyearonbehalfoftheinstitution.
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 201/202
5/16/2016 https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547
IcertifythattheinformationprovidedinthisSARisextractedfromtherecords,andtothebestofmyknowledge,iscorrectandcomplete.
Iunderstandthatanyfalsestatement/informationofconsequencemayleadtorejectionoftheapplicationfortheaccreditationforaperiodofthreeormoreyears.
IalsounderstandthattheNationalBoardofAccreditation(NBA)oritssubcommitteeswillhavetherighttodecideonthebasisofthesubmittedSARwhethertheinstitutionshouldbeconsideredforanaccreditationvisit.
IftheinformationprovidedintheSARisfoundtobewrongduringthevisitorsubsequenttograntofaccreditation,theNBAhastherighttowithdrawthegrantofaccreditationandnoaccreditationwillbeallowedforaperiodofnextthreeyearsormore
andthefeewillbeforfeited.
Iundertakethattheinstitutionshallcooperatethevisitingaccreditationteam,shallprovidealldesiredinformationduringthevisitandarrangeforthemeetingasrequiredforaccreditationaspertheNBAsprovision.
Iundertakethat,theinstitutioniswellawareabouttheprovisionsintheNBAsaccreditationmanualconcernedforthisapplication,rules,regulationsandnotificationsinforceasondateandtheinstituteshallfullyabidetothem.
ISolemnlyaffirmandagreetotheabovementionedinformation/facts.
HeadoftheDepartment HeadoftheInstitute
Name: Name:Dr.K.ChandrasekharReddy
Designation: Designation:Principal
Signature: Signature:
SealofTheInstitution:
Place:Puttur
Date:0605201616:05:38
https://enba.nbaind.org/SARTemplates/SARUGTireIITemplateRevisedPrint.aspx?Appid=1493&Progid=547 202/202