Sie sind auf Seite 1von 14

Information Management

40

Variations in government contract


in Malaysia

&#'()*(+,"-./0,1(20(3(4#KT40@*65010#D:045#G:.:250:L
&# 567+, 8-8,97))-.,#KT40@*65010#D:045#G:.:250:L
&#Abdelnaser Omran#KT40@*65010#D:045#G:.:250:L

!"#$ %#&# ()*# +!,-.*/012# !3# +!45167+10!4# 8!695# ,*:45# 1):1# 01# 05# ):6;.2# -!550<.*# 1!# +!,-.*1*#
:#-6!=*+1#801)!71#+):4>*5#1!#1)*#-.:45#!6#1)*#+!45167+10!4#-6!+*55#015*.3"#()*6*#+:4#!4.2#<*#:#,04!6012#!3#
+!416:+15#!3#:42#50?*#04#8)0+)#1)*#57<=*+1#,:11*6#8)*4#+!,-.*1*;#05#0;*410+:.#04#*@*62#6*5-*+1#801)#8):1#
8:5#+!41*,-.:1*;#:1#1)*#!715*1"#A5#57+)B#@:60:10!45#:6*#04*@01:<.*#04#*@*4#1)*#<*51C-.:44*;#+!416:+15"#()05#
517;2#05#:11*,-1*;#1!#*/:,04*#1)*#8:25#:#@:60:10!4#8:5#3!6,*;#04#.:8#:4;#-6!=*+1B#04#304;04>#!71#8)*1)*6#
1)*#D1:4;:6;#E!6,#!3#F!416:+1#75*;#04#G:.:250:#-:610+7.:6.2#1)*#>!@*64,*41#H7<.0+#I!695#J*-:61,*41#
KHIJL#3!6,#):5#<**4#710.0?*;#1!#1)*#<*51#.*@*.#04#@:60:10!4#+:5*5"#A;;010!4:..2B#1)05#517;2#*/:,04*;#1)*#
<*4*3015#!3#@:60:10!45#1!#-:610*5#04#+!416:+1#:4;#:.5!#-6!@0;*5#57>>*510!45#:4;#:557,-10!45#04#:4#*33!61#1!#
+!4160<71*#5!.710!45#1!#0557*5#:4;#-6!<.*,#;*1*+1*;"#()*#6*5*:6+)#,*1)!;!.!>2#75*;#04#1)05#517;2#8:5#:4#
*/1*450@*#6*@0*8#!3#6*.*@:41#.01*6:176*B#+:5*#517;2B#*,-060+:.#M7*510!44:06*5#:4;#5167+176*;#041*6@0*85#:4;#
>*4*6:.#!<5*6@:10!45#<:5*;#!4#*/-*60*4+*#:4;#5766!74;04>5"#()*#:+:;*,0+#517;2#:--6!:+)#04+!6-!6:1*;#
51:>*5#57+)#:5#04010:.#74;*651:4;04>B#;:1:#:4;#043!6,:10!4#>:1)*604>B#:4:.2505#!3#;:1:B#304;04>5#:4;#+!4C
+.750!4#:4;#>*4*6:.#57>>*510!45#04#1)*#517;2"#()*#,:=!6#304;04>5#!3#1)05#517;2B#:,!4>#!1)*65B#6*@*:.*;#1):1#
1)*#*/051*4+*5#!3#@:60:10!45#:6*#+!,,!4#04#-6!=*+15"#()*#,:04#+:75*#!3#@:60:10!45#8:5#;7*#1!#+.0*41#6*M7*51#
<*+:75*#!3#04:;*M7:1*#-6!=*+1#!<=*+10@*5#3!6#1)*#;*50>4*6#1!#;*@*.!-#+!,-6*)*450@*#;*50>4"#N*50;*5B#1)*#:4:.C
2505#-!041*;#!71#1):1#1)*#>!@*64,*41#3!6,#!3#+!416:+1#1)*#H7<.0+#I!695#J*-:61,*41#KHIJL#%'OP%'OA#+:4#
)*.-#04#!@*6+!,04>#-6!=*+15#801)#@:60:10!4#<*+:75*#!3#1)*#+.*:6#;*304*;#-6!+*;76*"#()05#517;2#:.5!#3!74;#
1):1#-6!-*6#-.:4404>#:4;#+!!6;04:10!4#:1#1*4;*6#51:>*#+:4#,040,0?*#1)*#6059#!3#Q748:41*;R#@:60:10!45"#S4#
+!4+.750!4B#1)05#517;2#6*+!,,*4;*;#1):1#37176*#6*5*:6+)#5)!7.;#<*#;!4*#04#;*50>4#:4;#<70.;#<:5*;#+!416:+1#
:5#57+)#4*8#043!6,:10!4#5):604>#+:4#.*:;#1!#:4#*/-:450!4#1!#1)*#<!;2#!3#94!8.*;>*#!3#1)*#+!45167+10!4#04C
;75162#04#G:.:250:"#
Keywords: Variation, government contract, variation order, Penang, Malaysia.

!"#$%#&#%'$'
Information Management
41
1. Introduction that continues to challenge stakeholders of
projects to this day. This happens against a
Use of the word variations in build- background that over years, experience has
ing contracts usually refers to a change in the been gained to handle variations in form of
works instructed by the architect, contract ad- contract clauses and procedures, which de-
ministrator or the employer as the case may- fine what constitutes a variation and how to
be. Most standard forms of contract include a manage them. They continue to cause un-
clause under which the employer or his rep- due uneasiness to the stakeholders because
resentative is able to issue an instruction to of their effect on the successful delivery of
the contractor to vary the works which are projects in terms of cost, time, quality and
described in the contract. A change in shape utility. Disputes and misunderstandings are
of the scheme, the introduction of different still encountered when variations arise, often
materials, revised timing and sequence are causing disruptions to the smooth running of
all usually provided for by the variations projects. This study is attempted to examine
clause. It will also usually include a mecha- the ways a variation was formed in law and
nism for evaluating the financial effect of the project, in finding out whether the Standard
variation and there is normally provision for Form of Contract used in Malaysia particu-
adjusting the completion date. In the absence larly the government PWD form has been
of such a clause the employer could be in a utilized to the best level in variation cases.
difficulty should a variation to the works Additionally, this study examined the ben-
be required and the contractor could not be efits of variations to parties in contract and
compelled to vary the works and he could in- also provides suggestions and assumptions
sist upon completing precisely the work and in an effort to contribute solutions to issues
supplying precisely the material for which he and problem detected.
has contracted. No power to order variations
would be implied in such situation. 2. Variation in Government Contract
The complexity of construction works
means that it is hardly possible to complete There is no single definition of what
a project without changes to the plans or constitutes a variation. In general, the ever
the construction process itself. Construction famous guru of construction industry Prof.
plans exists in form of designs, drawings, Vincent Powell-Smith ascribes the followings
quantities and specifications earmarked for meaning to the term variation:
a specific construction site. Changes to the
plans are effected by means of a variation A42#+):4>*#1!#1)*#8!695#:5#;*1:0.*;#!6#;*C
order initiated by a consultant on behalf of 5+60<*;#04#1)*#+!416:+1#;!+7,*415U"
the client or as raised by the contractor. Legal
precedents, illustrate that variations date On a broad-brush approach, follow-
back to time in memorial. While their occur- ing the above mentioned definition, there is,
rence is no longer an inconceivable issue, it prima facie, a variation every time there is
is their effect and subsequent management a departure from the work stipulated in the

!"#$%#&#%'$'
Information Management
42
contract. Whether such a variation is in law 3. Variations and variation orders
strictly a variation with its attendant legal
consequences has to be established in relation Any deviation from an agreed well-
to the particular contract involved. Usually, defined scope and schedule can be called as
each standard forms of building contract will variations. Stated in a different way, this is
contain a definition of a variation in terms of a change in any modification to the contrac-
specific actions and activities. As for the PWD tual guidance provided to the contractor by
203/203A (Rev. 2007) Condition of Contract, the owner or owners representative. This in-
Clause 24.2 defines and stipulates that: cludes changes to plans, specifications or any
other contract documents. A variation order
%V"%# ()*# 1*6,# QW:60:10!4R# ,*:45# :# +):4>*# is the formal document that is used to mod-
04#1)*#F!416:+1#J!+7,*41#8)0+)#4*+*5501:1*5#1)*# ify the original contractual agreement and
:.1*6:10!4# !6# ,!;030+:10!4# !3# 1)*# ;*50>4B# M7:.012# becomes part of projects documents (Fisk,
!6# M7:41012# !3# 1)*# I!695# :5# ;*5+60<*;# <2# !6# 6*C 1997; OBrien, 1998). Furthermore, a varia-
ferred to therein and affects the Contract Sum, tion order is written order issued to the con-
04+.7;04>X tractor after execution of the contract by the
:L# 1)*#:;;010!4B#!,0550!4#!6#57<5101710!4#!3# owner, which authorize a change in the work
any work; or an adjustment in the contract sum or even
<L#1)*# :.1*6:10!4# !3# 1)*# 904;# !6# 51:4;:6;# the contract time (Clough and Sears, 1994).
!3# :42# !3# 1)*# ,:1*60:.5B# >!!;5# 1!# <*# 75*;# 04# 1)*# For a variation to be tenable at law, it must be
Works; or valid in the first place. Unless such a change
+L# 1)*#6*,!@:.#36!,#1)*#D01*#!3#:42#8!69#*/C meets the validity test, the contractual conse-
*+71*;# !6# ,:1*60:.5#!6# >!!;5# <6!7>)1# 1)*6*!4# <2# quences ensuing thereof cannot arise and ac-
the Contractor for the purposes of the Works other cordingly cannot be enforced. Therefore, the
1):4#8!69B#,:1*60:.5#!6#>!!;5#8)0+)#:6*#4!1#04#:+C contractor cannot be compelled to comply
cordance with this Contract. with any variation order issued and he on his
part may not be able to recover his contrac-
Fong (2004) defines Clause 24.2 by ex- tual entitlements as to additional costs and/
plaining that the meaning of variation for or time, for instance. It is hence apparent that
the purpose of the Contract as the alteration the central issue of validity forms the essence
or modification of the design, quality and of a contractually tenable and therefore en-
quantity of Works shown upon the Contract forceable variation; a matter that continues
Drawings, Bills of Quantities and/or the to generate disputes in many a contract in
Specification. It also includes the addition, the engineering and construction industry.
omission or substitution of any work, altera- According to Harbans Singh (2002), when
tion of the kind or standard or any of the ma- one classifies a variation as valid, the fun-
terials or goods to be used for the Works and damental reference is in terms of posing the
the removal off the Site of any work, material question: whether the change has been car-
or goods executed or brought to the site ex- ried out in compliance with a valid variation
pect if the work, material or goods are not in order or not? The term variation order in turn
accordance with the Contract. has no magical meaning but its precise ambit
!"#$%#&#%'$'
Information Management
43
must be appreciated to ensure that the ele- with this term. Should there be no such term
ments of validity are not compromised. Prof or that the provisions of an existing term be
Vincent Powell-Smith in relation to engineer- not complied with, any variation order there-
ing contracts which holds a variation order upon issued may, for all intents and purpos-
to be: es, be invalid and therefore unenforceable.
To cater for the eventuality of permitting
A4# 045167+10!4# !3# 1)*# *4>04**6# 1!# *33*+1# :# such variations to be effected, most if not, all
+):4>*# 1!# 1)*# 8!695# :5# ;*304*;# 04# 1)*# +!416:+1## the standard forms of conditions of contract
documents, it is commonplace for a variation simC have incorporated express stipulations in the
-.2#1!#<*#0557*;#:5#:4#*4>04**6R5#045167+10!4Y#01#<*C conditions of contract. In the rare situation of
04>#*@0;*41#36!,#1)*#+!41*41#1):1#01#05#:#@:60:10!4"# the absence of such an express stipulation in
Alternatively, variations are issued separately on the contractor it being rendered invalid/un-
variation orders. enforceable, the parties have only a number
of alternatives available to them; one of these
being to enter into a supplementary agree-
The principal elements of a valid varia-
ment to enable the varied work as envisaged
tion order outlined by Harbans Singh (2002)
to be carried out. To preclude such a situa-
are, a variation must be in the form of an in-
tion from arising and to obviate its attendant
struction in the formal/contractual sense.
complications, it is necessary for the parties
Secondly, the person issuing the instruction
to ensure that not only the relevant express
must be the contract administrator or the per-
provisions are included in their contract from
son empowered under the contract to issue
the very outset but these are religiously ad-
such instruction. Third principle is the in-
hered to in the implementation stage. Under
struction must effect a change to the works the second factor of determining validity of
and forth is the works being changed or var- a variation order, Fong (2000) explains, for a
ied must be spelt out or defined in the con- variation order to be upheld as contractually
tract documents. Fong (2000) in Law and valid, one of the main requirements is that
Practice of Construction Contract Claims it must be issued by the person empowered
identifies two main factors determining the under the contract to effect the same. Such a
validity of a variation order. First, the le- body or person might be:
gal nature of the proposed change, i.e. con-
a) The employer himself; or
tract conditions governing variations and b) The contract administrator; or
the common law rules governing the scope c) Any other body or person designated
of change. Second the formalities governing in the contract or authorized expressly under
the change, e.g. issue of the variation order the contract.
by the designated person and the applicable The body or person so designated can
procedural requirements. Fong (2000) ex- be either named in the contract or empow-
plains further that under contract conditions ered through a formal letter of delegation of
governing variations, it is settled law that a power issued after award of the contract dur-
contractually valid variation order can only ing the currency of the contract. The above
be issued if there is a term in the contract per- requirement is neatly summed up in the fol-
mitting the same and strictly in accordance lowing words by Robinson and Lavers:
!"#$%#&#%'$'
Information Management
44
()*#*,-.!2*6B#74;*6#:..#51:4;:6;#3!6,5B#05# The following characteristics and/or
6*M706*;#1!#*/*6+05*#)05#60>)1#1!#+):4>*##1)*#+!4C features of the power of the contract admin-
16:+1!6R5# !<.0>:10!45B# 1)6!7>)# 1)*# :>*4+2# !3# 1)*# istrator to vary works should also be consid-
:6+)01*+1# K!6# *4>04**6# !6# 57-*6@050!4# # !330+*6L"# ered according to Harbans Singh (2002). The
()*# +!416:+1!6# 05# >*4*6:..2# 74;*6# 4!# !<.0>:10!4# characteristic are, the employer may (either
to accept instructions direct from the employer in the contract or the letter of delegation of
*/+*-1# 74;*6# 5!,*# >!@*64,*41:.# 3!6,5# 8)*6*# powers) subject the exercise of the said pow-
57+)#:#60>)1#!3#;06*+1#+!,,740+:10!4#05#6*1:04*;# er to certain procedural and/or financial lim-
3!6# 6*:5!45# !3# 4:10!4:.# 5*+76012"# ()*# 75*# !3# 1)*# itations, e.g. in Public Works Contracts, the
:6+)01*+1#:5#:>*41#04#1)05#+!41*/1#05#4*+*55:62#!3# prior consent of the employer may be a pre-
+!765*#1!#*4576*#+!!6;04:10!4#!3#1)*#;*50>4B#1!#*4C requisite to the contract administrators issu-
576*#51:4;:6;0?*;#:;,040516:10@*#-6!+*;76*5#:4;# ing any variation orders. Where the contract
<*+:75*B#04#,!51#+:5*5B#1)*#04010:1!6#!3#1)*#+):4>*5# administrator is empowered under the con-
05#1)*#:6+)01*+1#)0,5*.3#:5#)05#;*1:0.*;#;*50>4#8!69# tract to vary the works, his use of such power
-6!>6*55*5" as the employers agent is for the purpose of
the contract purely discretionary:# *!;!/#Z1;#
As can be distilled from the above ex- @#()*#N!6!7>)#!3#D8041!4#[#H*4;.*<762" Second
tract, in most contracts, this power is del- characteristics will be a person who is desig-
egated to the contract administrator, i.e. the nated as the party empowered to issue varia-
Architect in the PAM Forms, Engineer in tion orders is not obliged to exercise the said
the IEM Forms, Employers Representatives power fairly as the said power is normally
in the Putrajaya Forms, etc. It is pertinent to only for the benefit of the employer and the
note that once the contract designates a spe- person exercising such power is acting as the
cific person as the official who is empowered latters agent: J:@2# \335)!6*# @# ],*6:.;# E0*.;#
to vary the works or a specific person is del- F!416:+104>. As an overview, the contract ad-
egated this duty, a variation order issued by ministrator must be mindful not to exceed his
any other person will not be contractually real or ostensible authority or act beyond the
valid. Furthermore according to Robinson & powers vested in him under the contract or in
Lavers (1988), in exercising this power, the his professional services agreement. Should
contract administrator must ensure that the such an eventuality occasion, he may be cul-
said power meets the following criteria: pable of acting ultra vires with such possible
consequences of rendering any variation or-
It covers the nature of the variation or
der issued invalid and/or exposing himself to
change ordered;
claims of breach of contract or negligence by
Covers the extent of the variation or
the employer. According to Fish (1997), there
change envisaged; and
are two basic types of variations: directed and
It meets any express time limit pre- constructive changes, which are discussed in
scribed for exercising such powers, e.g. detail below:
whether the contract permits variation or- :;,<-4=23=6,%0(./=),
ders to be issued after practical completion of Directed changes are easy to identify. A
work, etc. directed change occurs when the client directs
!"#$%#&#%'$'
Information Management
45
the contractor to perform works that are dif- 4. For administrative purpose, to es-
ferent from the specified in the contract or tablish the method of extra work payment
an addition to the original scope of work. A and funds for work already stipulates in the
directed change can also be deductive in na- contract.
ture, that is, it may reduce the scope of work 5. For administrative purposes, to au-
called for in the contract. Disagreements tend thorize an increase in extra work funds nec-
to center on questions of financial compensa- essary to complete previously authorized
tion and the effect of the change on the con- change.
struction schedule for directed changes. 6. To cover adjustments to contract unit
::;,%>.)34723-?=,%0(./=), prices for overruns and under runs, when re-
A constructive change is an informal act quired by the specifications.
authorizing or directing a modification to the 7. To effect cost reduction incentive pro-
contract caused by an act or failure to act. In posal (value engineering proposals).
contrast to the mutually recognized need for
8. To effect payment after settlement of
change, certain acts or failure to act by the cli-
claims.
ent that increases the contractors cost and/or
time of performance may also be considered
A variation order is used in most in-
grounds for a variation order. This is termed
stances when a written agreement by both
as a constructive change and must be claimed
parties to the contract is either necessary or
in writing by the contractor within the time
desirable. Such use further serves the pur-
specified in the contract documents in order
pose of notifying a contractor of its right to
to be considered.
file a protest if it fails to execute a variation
@;A?(+7(3-./, 30=, .==6, >B, ?(4-(3->., order (Fisk, 1997). The absence of a varia-
orders tions clause undoubtedly makes it difficult
to vary the terms of the contract but it is at
least possible that the courts would imply a
The usage of a variation order is to ef-
term allowing minor variations to be made.
fect a change in the contract. As mentioned
In any event, it would of course be most un-
previously, such changes should always be
usual for a contractor to attempt to refuse to
in writing to avoid unnecessary disputes
carry out small changes and even less likely
among the owners and the contractors. The
following are some of the purpose served by that the contractor would go to court over an
variation orders (Fisk, 1997): attempt to impose them. By inserting a clause
1. To change contract plans or to spec- which allows for changes to be made to the
ify the method and amount of payment and works as they are being built, the employer,
changes in contract time there from. through the contract administrator, can al-
2. To change contract specifications, ter the works as and when necessary. The
including changes in payment and contract purpose of the variation clauses is to allow
time that may result from such changes. such changes to be made, and also to per-
3. To effect agreements concerning the mit any consequential changes to be made
order of the work, including any payment or to the contract sum. Furthermore according
changes in contract that may result. to Murdoch & Hughes (1996), it is always
!"#$%#&#%'$'
Information Management
46
possible for a contract to include a clause that plaintiffs entered into a sub-contract for the
fixes express limits on the amount of varia- construction of part of the weather deck of a
tions. In any event, it must be borne in mind North Sea drilling platform. The documents
that the existence of a variation clause does on which the plaintiffs tendered include 22
not entitle the employer to make large scale engineers drawings. However, when work
and significant changes to the nature of the began, a stream of design changes trans-
works, as these are defined in the recitals to formed the contract into one based on 161
the contract. In particular, variations which drawings. The trial judge ruled that these
go to the root of the contract are not permissi- changes were so significant as to amount to
ble. If the recitals state that 8 dwelling houses a new contract, but the Court of Appeal held
are to be built, then a variation altering this to that they could all be accommodated within
12 would possibly be constructed as going to the contractual variation clause.
the root of the contract. However, if the recit-
5.0 Potential Effects of Variation
als state that the contract is for 1008 houses,
Orders
then a variation changing this to 1012 would
Research on the effects of variation or-
not go to the root of the contract, because it
ders were done by many researchers (Clough
would be a minor change in quantity. If the
and Sears, 1994; Thomas and Napolitan,
quantity of work is not indicated in the re-
1995; Fisk, 1997; Ibbs, 1997; Veenendaal,
cital, then the question does not arise in the
1998; Reichard and Norwood, 2001; Arain
same way. What is probably more important
and Low, 2005; Moselhi et al., 2005). Changes
is that if the contract is for the erection of a
that occur during construction will affect any
swimming pool, a variation which attempts
project (Reichard and Norwood, 2001). Lewis
to change it to a house would clearly be be- (1991) indicated that change orders have its
yond the scope of the contract. There are two ripple effects as a contractor does not work
classic cases to explain the above statement. in a vacuum; rather must properly allocate
The first case is in Blue Circle Industries Plc his limited resources within projects and be-
v Holland Dredging Company (UK) Ltd the tween actual and potential projects. Thus,
parties entered into a contract under which whenever a change occurs, a contractor must
the defendants were to dredge a channel make adjustments to work under the contract
which served the plaintiffs dicks in Lough and reallocate time, material and labour re-
Larne, Eire. The dredged material was to be sources. Arain and Low (2005) identified 16
deposited in areas of Lough Larne to be noti- potential effects of variation orders on insti-
fied by the local authority. When the plain- tutional building from the research they did
tiffs instructed the defendants instead to use in Singapore. The effects that were deter-
the dredged material so as to construct an mined are discussed further below.
artificial island, it was held that this could
not be regarded as a variation. It was beyond C;D, E4>/4=)), -), BB=23=6, 573, F-30>73,
the scope of the original contract altogether, any Delay
and thus had to form a separate contract. In Project progress and quality may be af-
McAlpine Humberoak Ltd v Mc Dermott fected by variations (Arain and Low, 2005).
International Inc, on the other hand, the During construction, time is of the essence.

!"#$%#&#%'$'
Information Management
47
However, according to Arain and Low 1998). Because of this, the overhead expense
(2005), only major variations during the proj- for all the parties involved will increase as
ect may affect the project completion time there is a lot of work and paperwork need to
because the contractor would usually try be done. However, normally these overhead
to accommodate the variations by utilizing charges are provided for from the contingen-
the free floats in the construction schedules. cy fund allocated for the construction proj-
Therefore, variations will affect the project ects (Arain and Low, 2005).
progress but without any delay in the project
completion date. 5.5 Delays in Payment
Delay in payment occurred frequent-
5.2 Increases in Project Cost ly due to variations in construction project
During the construction phase, the most (CII, 1990). CII (1995), variations may hin-
common effect of variations is the increase der the project progress as mentioned before
in project cost (CII, 1990). The increase in the thus leading to delays in the construction
project cost is caused by any major additions works done which will eventually affect-
or modifications to the design (Clough and ing payments to the contractors. If the main
Sears, 1994). Therefore, contingency sum will contractor does not have enough funds to
usually be allocated in every construction pay the subcontractors then this may cause
project to cater for any possible variations in severe problem to both the main contrac-
the project, while keeping the overall project tor and the subcontractor as well. This can
cost intact. happen because some main contractor de-
pends on the payment from client to pay the
5.3 Hiring New Professionals subcontractors.
CII (1995), variations often occur in
complex technologies projects, this may be 5.6 Quality Degradation
caused by something was overlooked by Frequent variations may affect the qual-
the architect/engineer during the design ity of work adversely (Fisk, 1997). This may-
stage. Complex technologies projects need be because of frequent variations may cause
specialists to get the job done (Fisk, 1997). the contractors to compensate their losses by
Depending on the nature, occasionally, new cutting corners.
professional need to be hired or the entire
project team is replaced to execute the varia- 5.7 Productivity Degradation
tions (Arain and Low, 2005). Hiring the new Variation orders often associated with
professionals takes time and thus affecting interruption, delays and modification of
the project progress. work do have a negative impact on labor
productivity. Hester et al., (1991) feel that the
C;@,:.24=()=),-.,G?=40=(6,AH*=.)=, productivity of workers was expected to be
Variations need to go through a few seriously affected in cases where they were
stages of processing procedures as men- required to work overtime for prolonged
tioned earlier and require to be evaluated be- periods to compensate for schedule delays.
fore they can even be implemented (OBrien, Thomas and Napolitan (1995) concluded
!"#$%#&#%'$'
Information Management
48
from their research that variations normal- from references books, newspaper, journals
ly led to disruptions and these disruptions and other printed materials. This is impor-
were reasonable for labor productivity deg- tant since appropriate and relevant data and
radation and on average, there is a 30 percent information related to the study is necessary
loss of efficiency when changes are being per- prior to a detailed analysis. For the purpose
formed. Thomas and Napolitan (1995) also of this study, the researcher developed a
feel that the most significant types of disrup- structured interview-based questionnaire.
tions were due to the shortage of materials The purpose of such method was primarily
and lack of information as well as the work to gather data relating to the research objec-
out of sequence and these disruptions result tives in this study. Among the relevant ques-
in daily loss of efficiency in the range of 25 tions asked include the cause of variations in
to 50 percent. Reichard and Norwood (2001) a project, the forms of contract involved and
found out from their research that if varia- procedures or steps undertaken when there
tions reach 10 to 15 percent of the originally is a variation.
planned labor hours, productivity of the re-
maining unchanged work will decreased due 6.2 Questionnaire Design
to the extra labor hours spent on executing The questionnaire in this study con-
the variations. According to Moselhi et al., sisted of two segments; basically Segment A
(2005) the few factors that were found to in- and Segment B. Segment A consisted of in-
fluence the impact of variation orders on la- formation related to the demographic data
bor productivity are as follows: of the respondents. Among the variables in
this section include, age, gender, years of ex-
,I;J,$=)=(420,K=30>6>+>/L perience and profession of the respondent.
Systematic research method is impor- In Segment B, questions posed were related
tant to get good research result. Research sys- to the research paper, and included items on
tem that is reliable has to be used so that the awareness in construction contract variation,
objectives that were lineout above will bare the frequency of such variations, the cause of
result. variations in a project and the procedures tak-
en when there is a variation in a project. The
6.1 Data Collection questionnaire items, particularly related to
Data collection was carried out through the area of study, were formulated based on
primary and secondary sources. As for pri- an extensive literature review and frequent
mary data, the data shall be acquired through discussions with the supervisor of the study.
case study, questioners, observation, struc- After some review and amendments, a final
tured interviews (both contractor and clients). copy of the questionnaire was produced.
The scope of case study and questioners dis-
tribution shall be confined to Penang. The sec- 6.3 Questionnaire Distribution
ondary data shall be acquired from library, A total of 50 questionnaire forms were
resource center, Government Departments, distributed to selected respondents in the
lectures, Internet and other sources. As an il- construction industry mainly operating in
lustration, secondary data shall be obtained the northern state of Malaysia, Penang. The
!"#$%#&#%'$'
Information Management
49
method used by the researcher in the distri- responders answered yes. This study con-
bution was on a personal contract-basis. In firms that the reasons of variation offered by
this method, the researcher himself went to respondents were in lined and seems to fit the
meet the respondents and provided them literature review. From the many reasons or
with a copy of the questionnaire. The tech- causes of variation the single most frequent
nique used in data collection was a drop cause of variation was client request (21%).
and pick-up technique. In this technique, Results from the questionnaire study seem to
respondents were given the questionnaire support the case study findings in the sense
and told that the completed questionnaire that the second highest contributor of varia-
shall be picked up the next day. The ques- tion for Balai Bomba Kepala Batas, Penang
tionnaires in this study were distributed on was due to client request. Example of varia-
28th December 2009 to 28th January 2010. 15 tion due to client request is change of plan
of the respondents returned the completed or scope of project, inadequate project objec-
questionnaire on the same day. There were a tives and many more. Under the case study
few cases when the researcher was informed of this research the reason of variation is due
that the completed questionnaire shall be re- to inadequate project objectives that result in
turned the next day. However, this did not the designer unable to develop a comprehen-
happen. Although the initial plan, as stat-
sive design which leads to numerous varia-
ed earlier, was to collect the questionnaires
tions during the project construction phase.
from the respondents the next day; however
With reference to the procedures be taken
it was different in practice. Some 10 respon-
when there is a variation in a project, it was
dents took more than one day to send in
observed among the procedures followed
their responses and another 5 respondents
were checking with the relevant contract and
took 14 days to reply. Although the respon-
drawings to establish and valid variation and
dents were reminded via a telephone call
then gather information to produce an esti-
and through personal contact, the researcher
mate and brief clients on the financial impact
did not receive the completed questionnaire.
of the variation, issue SO instruction to con-
Thus, most probably, either the respondent
tractor for changes, verify estimated cost and
would had misplaced the questionnaire, or
whether cost is treated as variation (addition/
changed his (her) mind about participating
omission) and finally owners approval for
in the study.
variation to be carried out. Basically, the pro-
7. Results Analysis cedures taken when there is a variation are
relatively same in process. These procedures
In analyzing the detailed information are affirmed in the researcher literature re-
based on questionnaire in this study, it fur- view by Harbans Singh (2002) explaining
ther reinforces the existences of variation as that most of the standard forms of construc-
a common occurrence in a typical project. tion contract provide some basis procedures
When the respondents in this study were or rule for variation works. The rules are
asked if variation were common in projects often similar in principle. Either its private
thru their working experience, 97% of the sector of government sector standard form

!"#$%#&#%'$'
Information Management
50
of contract the producers on how to iden- valuation and also payment of varied work
tify a variation, measurement of variation, are outlined in detail in these forms.

Figure 1: What are causes of variations in a project?


35%
29%
30%
25% 21%
20% 15% 14%
15%
9%
10% 7%
5%
5%
0%

s
st

es
s

gn

er
ie

ts

ee
ue

iti

th
in

si
rit

es
q

gu

de

O
tra
ho
re

or
bi

te
ut

ns
nt

nf
am

ua
A
lie

co

eq
C

&
te

ad
si

es

in
to

ci
an

&
ue

ep

e
td

et
cr
en

pl
is

m
tm

co
us

In
dj
A

With reference to the second objective to the case study, the form of contract used for
of this study, majority (87%) of respondents the project was PWD 203A. Based on the re-
agreed that PWD standard form of contract searcher findings, the form of contract helped
can help them in overcoming a project that and gave an explicit guide to the contract ad-
has variations. Some of the reasons outlined ministrator in deciding, valuating, issuing
by respondents on how the standard form of and even in rejecting some variation claimed
contract helps in variation were, the varia- by the project contractor. Undoubtedly PWD
tion clause clearly defines what variation form of contract and it clauses has the clarity
is. Some respondents agreed that the PWD in dealing with variation procedures and this
form provides a framework and spells out is an integral part of effective management
the necessary steps/ procedures needed for of variation. The procedures in this form are
both parties (client and contractor) in terms clear to all parties and would help in reducing
of responsibilities, scope, obligations of the variations. Furthermore the comprehensive
parties concerned. On the other hand, some and balanced variation clauses in PWD form
respondents (13%) did not agree that PWD would help in improving coordination and
form of contract could help them in overcom- reduce conflicts that can result in problems
ing a project with variations. Among reasons and misinterpretation. Generally, supported
given were, conditions are vague, incomplete with the outcome and result of the study and
and difficult to implement effectively. Some observation by the researcher it can be con-
even argued that it does not overcome proj- cluded that PWD form can and does help in
ects with variation but only provides good overcoming projects with variations. In dis-
procedures and fair to both parties. Referring cussing the ways towards, minimizing the

!"#$%#&#%'$'
Information Management
51
risk of unwanted variations, the soundest are the main source of reference and informa-
proposal in this study is to have proper plan- tion, good coordination and involvement of
ning and coordination at tender stage. It is all professional parties and even the client is
in tandem with the Japanese policy that 80% important in developing creative and practi-
of effort and time should be in the planning cal ideas that minimize discrepancies and re-
stage and the other 20% in implementation sulting in reduced variation.
stage. As contract documents and drawings

Figure 2: !"#"$"%& '(& )"*+ ,- ./#01#'&23 415"1'",#*6

18% 15% Firm project brief

Planning & coordination


at tender stage
Others
67%

The involvement of the owner in the or not from variation. With 37% respondents
design phase would assist in clarifying the agreeing it benefited them, where else 47%
project objectives and in identifying the disagree variations can benefit and the bal-
noncompliance with their requirements at ance 16% both agree and disagree depending
an early stage. The controls for the errors on situation. In my observation, the question
and omissions in design, design discrepan- of benefit or not depends on what type of
cies and frequent change in design, would scenario does a variation incurred. Most con-
be through detailing of design. Thorough tractors and consultants response was if it is
detailing of design was perceived as one of an additional variation than it benefited them
the most effective controls for variation. This in terms of increase in contract sum and high-
process would assist in identifying the errors er profits (for contractor) and higher percent-
and ambiguities in design and help in elevat- age of fees for consultants but not beneficial
ing variations. Involvement of professionals if a variation resulted in an omission. In the
at initial stage can assist in developing better researchers own point of view, variation is an
and practical designs. Another suggestion in instrument to facilitate change in a contract
minimizing the risk of unwanted variation and it is not for any parties to misuse or make
is to have clear and complete project brief. It profits or even lose profits from it. Some of
helps in controlling variations as it helps in the views or comments expressed by respon-
clarifying the project objectives to all parties. dents among others were, there is no such
In my own view, variations must be kept to a thing as a variation free contract and any at-
minimum so that it is possible for all works to tempt towards this phenomena is an exercise
be completed by the original stipulated com- in complete futility. We all know variations
pletion date. The study recorded a mixture are the necessary evil in the construction in-
of responses whether organization benefited dustry that cannot be avoided but should be
!"#$%#&#%'$'
Information Management
52
managed or maybe minimized thus there is supported by literature review. The primary
no such thing as a complete and perfect con- reason for such a case study is to provide a
tract. Analysis of detailed information in the practical and workable scenario closely re-
case study revealed that there were variation lated to variation. It can be concluded that
with additional cost and some variation with the case study is in tandem and supports the
omission (reduction in cost). It was observed literature review and questionnaire analysis
that variation is a normal and common sce- done in this study.
nario in any typical construction project as

Figure 3: Do you think your organization Get some benefits from variations?

16%
37% Yes
No
Both
47%

8. Conclusions variation must begin from the planning stage


and continue through the end of the project.
As a conclusion, considering the fact Finally, the overall objectives of this study,
that variations are common in all types of as set out in above have been successfully
construction project, it is hoped that this achieved. It is most important to research
research can be used as a guide by profes- findings and information generated shared
sionals to reduce and control variations in among professionals in the construction in-
projects. Although variations are frequently dustry. Undoubtedly, such information shar-
unavoidable in the construction industry, ing leads to an expansion to the body of
unwanted or negative variations are unde- knowledge in dealing with both theoretical
sirable in projects as these would have an ad- and practical, the legal aspects and related
verse impact on time, cost and quality. The areas of variation.
study also suggests that the management of

REFERENCES:
!"Arian, F.M. and Low, S.P. (2005). !"#!$%&'()#*#%$)$*!(+,(-#"&#!&+*(+".$"/(,+"(&*/!&!0!&+*#1(20&1.&*%/3(4$-$"#%5
&*%(+*(&*,+")#!&+*(!$'6*+1+%7. Project Management Institute. 36 (4), 27-41.
!"CII. (1990). 86$(&)9#'!(+,('6#*%$/(+*('+*/!"0'!&+*('+/!(#*.(/'6$.01$, Construction Industry Institute, Univer-
sity of Texas, Austin, USA.
#!" !"#$%&'()*) and Sears, G.A. (1994). :+*/!"0'!&+*('+*!"#'!&*%;(<=!6($.&!&+*>, New York: John Wiley & Sons Inc.
$!"Fisk, E.R. (1997). :+*/!"0'!&+*(?"+@$'!(A.)&*&/!"#!&+*;(<B!6($.&!&+*>, New Jersey: Prentice Hall.
%!"Fong, C.K. (2000). 4#C(D(?"#'!&'$(+,(:+*/!"0'!&+*(:+*!"#'!(:1#&)/. Singapore: Longman.
&!"Fong, L.C. (2004). 86$(E#1#7/&#*(?FG(H+")(+,(:+*/!"0'!&+*(:+*!"#'!. Malaysia: Sweet & Maxwell Asia.

!"#$%#&#%'$'
Information Management
53
'!"*+,-+./'01.$%&'2)0) (2002). O*%&*$$"&*%(D(:+*/!"0'!&+*(:+*!"#'!/(E#*#%$)$*!(P(?+/!(:+))$*'$)$*!(?"#'5
tice. Malaysia: Lexis Nexis Asia.
(!"*3/43,&'5)&'2#6,3.+/&'7)8. and %+.$&'9) . (1991). :+*/!"0'!&+*('6#*%$/(#*.('6#*%$(+".$"/3(86$&"()#%*&5
tude and impact, University of California, Berkeley, CA.
)!":--/&' )5) (1997).(Q0#*!&!#!&-$(&)9#'!/(+,(9"+@$'!('6#*%$3(/&R$(&//0$/J Journal of Construction Management
and Engineering, 123, (3), 308-311.
*+!";"/3!%1&'<)&'8//3=&':. and El-Rayes, K. (2005). :6#*%$/(+".$"/(&)9#'!(+*(1#2+0"(9"+.0'!&-&!7J Journal of
Construction Engineering and Management, ACSE, 131, (3), 354-359.
**!";#,>"?%&'7. & *#$%3/&'5) (1996). :+*/!"0'!&+*(:+*!"#'!/(<4#C(D(E#*#%$)$*!>(L*.(O.&!&+*J London:
E & FN Spon.
* !"OBrien, J.J. (1998). :+*/!"0'!&+*('6#*%$(+".$"/J New York: McGraw- Hill.
*#!"Public Works Department (2007). PWD 203A/203 Standard Form of Contract.
*$!"Rajoo, S. (1999). 86$(E#1#7/&#*( !#*.#".(H+")(+,(S0&1.&*%(:+*!"#'!(<86$(?AE(KTTU(H+")>(L*.(O.&!&+*J(Ma-
laysia: Lexis Nexis.
*%!"(31?%+,>&' @)@)' and Norwood, C.L. (2001). A*#17R&*%( !6$( '0)01#!&-$( &)9#'!( +,( '6#*%$/J( AACE Interna-
tional Transactions.
*&!"Robinson, N. M., & Lavers, A.P. (1988). :+*/!"0'!&+*(1#C(&*( &*%#9+"$(D(E#1#7/&#J (Butterworth-1991).
Pg. 46-56, pg.86-102.
*'!"T%"=+/&'*)()&'and Napolitan, :J4J(Q0#*!&!#!&-$($,,$'!/(+,('+*/!"0'!&+*('6#*%$/(+*(1#2+0"(9"+.0'!&-&!7J(Jour-
nal of Construction Engineering and Management, 121, (3), 290-296, 1995.
*(!"Veenendaal, J.A. (1998). A*#17R&*%(!6$(&)9#'!(+,('6#*%$(+".$"/(+*(#(/'6$.01$J(Journal of Cost Engineering,
40, (9), 33-39.

I+J(KL(M(LNKN

Das könnte Ihnen auch gefallen