Beruflich Dokumente
Kultur Dokumente
Project Schedule
Name
Institution
Authors Note
PROJECT SCHEDULE 2
Introduction
The paper is written basing on the project schedule created in the first section of the
assignment. From the beginning while the project schedule was developed it was considered that
the work in the entire project will be done on the normal working days which falls within the
week under normal working condition and a single working day will compose of a maximum of
8 hours. While developing the schedule of the project all the holidays that are applicable have
Project Analysis
From the plan, it can be clearly seen that the project is scheduled to begin on 11th
September 2017 and end on 15th October 2017. Furthermore, the critical path is the time as well
as the cluster of activities to be carried out from the begging to the end of the scheduled project.
Normally, there is always one significant path but basing on the nature of this project there is a
likelihood of having more than one path for this specific project (Flyvbjerg, 2013). Similarly,
basing on the nature of the projects as well as all other dependencies the calculated crucial path
Recommendations
Various factors were considered to influence the project negatively as a result affecting
the date of completion. Three primary activities were identified, and they could affect the project
in a negative way. The activities included the unforeseen delays, lack of funds, and unavailability
of the necessary resources. However, the most recommended way of eradicating the negative
impact to the project schedule is to try to eliminate all the activities, which have adverse effects
to the project (Flyvbjerg, 2013). The manager has to consider some additional activities. First of
PROJECT SCHEDULE 5
all, the manager will have to consider the extra time that is required for the completion of the
project activities to avoid unpredictable delays. Secondly, the funds that are required for the
project should be approved in advance and finally it will be better to hire additional resources in
case of a shortage.
PROJECT SCHEDULE 6
Reference
Flyvbjerg, B. (2013). Quality control and due diligence in project management: Getting