Sie sind auf Seite 1von 3

Name : Favi Ainin Fitria

NRP : 4211440000011
Class : LNG

Scenario : PLTU Gresik blok 1, 2 dan 3 akan dikonversi menjadi


pembangkit listrik LNG, maka perhitungan konversi daya
menjadi kebutuhan bahan bakar adalah sebagai berikut :

Power Plant LNG Sup


Power Generated = 400 MW Distance to Sourc
= 80 mmSCFD
Total Power / Day = 74880 mmBTU
LNG Needed = 1440 Ton/Day Load-unload spee
2880 M^3/Day Time Load-Unloa
120.000 M^3/Hour

So, the storage unit total capacity is 57600 m^3 built at jetty area. If
using more than 1 storaging tank, there must be clearance 1 meter to
distributing the pipes.

Price Factor
Land Preparation = 150 $ / m^2
Plate = 65 $ / m^2
Construction Cost Addition = 400 $ / 2 M height
Worker = 100 $ / m^2

Constraints Dim
Diameter Max = 20 m
Length Max = 390 m
Volume Needed = 57600 m^3
Height Max = 30

Calculations Cost E
Total Volume = 57600.00 m^3
Land area used = 676 m^2
Plate Area = 17200.00 m^2
Total Length = 146 m
LNG Supply Vessel
Distance to Source = 881.6 km (From Bontang to Paiton)
Ship Speed = 10 knot
Total Capacity = 20000 m^3
Load-unload speed = 750 m^3/hr
Time Load-Unload = 12.00 hours
Trip Time = 47.603 hours
Total time = 119.205 hours
Ships Needed = 0.8 ships

Dimension
Diameter = 20 m 2
Height = 29.09 m
Volume = 8228.57 m^3 / unit
Circle Area = 314.29 m^2
Storage Qty. = 7 Unit

Cost Estimated
land Preparation = 101400 $
Stiffener = 39200 $
Worker + Plate = 2838000 $
Total Cost = 2.979 Million $
2