Although this is a straight forward concept, I have seen many people have
misunderstanding here.
Please note that you may or may not see a direct question on these topics on
the exam, but having a better understanding about the EEF and OPA will
certainly help you on your PMP Exam.
The environment can be defined as something related to the natural world and
the impact of human activity on its condition, or the culture that an individual
lives in, and the people and institutions with whom they interact (Wikipedia).
Government regulation
Market conditions
Infrastructure 400 PMP Exam Sample Questions Try It Out
Organizational culture
Type of organizational structure
Internal political conditions
Available resources
Simply put, assets are something that you can own, keep, and make use of.
For example, you can have a car which helps you move around, you can have
a house to live in, a computer to work on, etc. This list is endless. These
things are called assets.
In the same way, organizations also have assets which help them in achieving
their objectives. Here these assets are called organizational process assets
(OPA). These organizational process assets are kept in some central
repository so that they can be used whenever required.
The first category is for processes and procedures for conducting work, which
includes the following:
Policies 400 PMP Exam Sample Questions Try It Out
Procedures
Standard template
General guidelines
The second category includes corporate knowledge base for storing and
retrieving information. For example:
Risk register
Lessons learned
Stakeholder register
Past project files
Historical information
These organizational process assets influence the project success, and they
keep growing as the organization becomes larger.
For example, lets say that youre in the identify risks process and are
identifying the risks. You decide to start identifying risks by using a check list.
Are you going to create this checklist from scratch or will you look in any
similar past project records to find it out?
Of course, you will go for the second option and find a risk checklist from
previous records and customize it as per your project requirements. This will
save you a lot of time.
On the other hand, enterprise environmental factors may or may not help your
organizations. These are the conditions in which your organization has to
work. These do not fall under the control of the project management team.
For example, if the government increases taxes, it will hurt your profit;
however, if they decrease taxes, it will increase your profit.
The key point is that organizational process assets always support the project
team, while enterprise environmental factors can sometimes help the project
and other times may hurt it as well.
j 53 f 34 h 3 s
400 PMP Exam Sample Questions Try It Out
Comments
Andre says
July 29, 2012 at 7:44 PM
Reply
Reply
Reply
Reply
Alejandro says
November 16, 2017 at 9:53 PM
Great explanation!, thank you!
400 PMP Exam Sample Questions Try It Out
Reply
Reply
gianlucadamico says
August 5, 2012 at 11:44 PM
Reply
kp says
September 19, 2012 at 11:44 AM
Good job .. Well explained.. I have abt 2 weeks to go for my exam. Its great to read
and understand the concepts..
Reply
Olga says
December 26, 2016 at 1:58 PM
Thank you for the information. I have a question. Does EEF include
OPA? According to PMBOK organizational culture is one of the
internal EEF. And organizational culture includes policies, process,
procedures, etc. I mean Organizational culture includes Organizational
process assets. Does it mean that OPA is a part of EEF?
Reply
Reply
Our study group has a long debate regarding the difference between EEF and OAP.
Your article made it clear.
Reply
Reply
Vandemataram says
December 5, 2012 at 11:00 AM
You simplify things very well. Wish I knew about this site earlier..
Thank you VERY much. Keep up the good work, I am sure its going to help others
as well.
Reply
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Kupa says
January 10, 2013 at 6:16 PM
Reply
Reply
Janaka says
January 19, 2013 at 9:29 AM
Fahad, How do I categorize following items whether they are belong to EEF/ OPA
Reply
Reply
Arturo says
February 7, 2013 at 6:43 PM
Hello Usmani,
but
Thanks
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Naveen says
January 28, 2013 at 1:41 AM
Hi
Can you please exlain PMIS Project Management Information Systems in detail?
Appreciate your helpon this?
Thanks!
Reply
Hello Naveen,
Reply
Maha says
February 4, 2013 at 11:25 PM
Hi Fahad,
Reply
Reply
Jim says
April 4, 2017 at 2:40 PM
Hello Fahad,
thanks in advance.
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Maha says
February 5, 2013 at 7:48 PM
Can you please explain what a project life cycle is and how it related to the 5 process
groups.
Does each project phase ave 5 process groups ?
Thank u again
Reply
Hello Maha,
You can say that product life cycle is the stages through which the product
passes. Beginning from its idea, design, development, marketing and then
selling to the market.
Project life cycle is a part of the product life cycle. For example, you can say
that design and development of any machine is a project. Once you develop
the machine, project finishes. Now, the rest product cycle starts; i.e.
marketing, selling and customer service etc.
Every project phase has starting and finish; therefore, yes every project phase
has all five process groups.
Reply
400 PMP Exam Sample Questions Try It Out
Gaurav D Purkayastha says
March 4, 2013 at 6:03 AM
Hello Mr Usmani
I intend to take PMP on PMBOK 4 later this year, and stumbled upon your website,
which has been extremely helpful. I wish I had known about this earlier.
A BIG Thank you for all the material your colleagues and you have put up, and I wish
you the very best.
Reply
Youre welcome Gaurav, and thanks for visiting & liking my blog.
Reply
JP says
March 18, 2013 at 6:56 PM
I understand the PMI calls PMIS and QCS Enterprise Environmental Factors but from
a financial accounting definition perspective An asset is a resource controlled by the
enterprise as a result of past events and from which future economic benefits are
expected to flow to the enterprise.
Thus, some PMIS and QCS and Infractructure can be considered assets. For
instance, customized software for Accounting/Auditing Information System.
Reply 400 PMP Exam Sample Questions Try It Out
Thank you Mr JP for stopping by and providing the feedback on EEF from a
financial accounting perspective.
Reply
Raul.
Reply
Reply
Nasim says
April 5, 2013 at 8:03 PM
Thank you so much for sharing. I referSample
400 PMP Exam to your blog so often
Questions for a better
Try It Out
understanding of any PMP subjects.
Reply
Reply
Matt says
May 17, 2013 at 12:52 AM
Thank you. You have made it very clear to understand. And you are right, sometimes
the best way to understand it is going back to its original definition. Thank you again!!
Reply
Reply
Nandhini says
December 13, 2013 at 12:35 PM
Hi,
I am going through the EEF and OPA concepts. Why do we categorize productivity
metrics and duration of estimating databases as EEF and not OPA?
Reply 400 PMP Exam Sample Questions Try It Out
Hello Nandini,
Reply
Your explanation is verify clear, thanks you and keep posting this blog.
Reply
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Fahad Usmani says
April 30, 2014 at 1:55 PM
Reply
Abhishek says
May 11, 2014 at 9:25 PM
Reply
Reply
Ashraf says
July 8, 2014 at 7:27 PM
Reply
400 PMP Exam Sample Questions Try It Out
Fahad Usmani says
July 9, 2014 at 10:45 PM
Reply
Reply
Reply
Niq says
October 21, 2014 at 10:47 PM
Reply
Rajashekhar says
November 4, 2014 at 4:12 AM
Reply
Reply
Amya says
November 7, 2014 at 7:32 AM
Reply
Youre welcome.
Reply
400 PMP Exam Sample Questions Try It Out
Masoumeh nafar says
November 18, 2014 at 9:23 AM
Reply
Ryan says
November 23, 2014 at 7:03 PM
Excellent
Reply
Thanks Ryan.
Reply
Bonosus says
December 2, 2014 at 6:33 PM
Reply
Reply
400 PMP Exam Sample Questions Try It Out
precious says
January 30, 2015 at 5:09 PM
This blog is so perfect. Thanks for your aid through this medium.
Reply
Reply
Chris says
February 10, 2015 at 3:37 AM
Thank you so much! Exactly what I needed to finally understand the difference
between EEFs and OPAs!
Reply
Reply
Mohammed says
March 11, 2015 at 7:05 PM
400 PMP Exam Sample Questions Try It Out
Thank you so very much for the simple yet very clear way of explaining the concepts
of EEF and OPAs.
Excellent job
Reply
Reply
M Sood says
April 23, 2015 at 10:22 AM
Why Project Management Information Systems are considered as EEF as these are
more of organization specific and should be considered as OPA?
Reply
Reply
Cj says
May 24, 2015 at 6:29 AM
apt and perfect , I understood and
400 PMP really
Exam helped
Sample me . Thanks
Questions !!
Try It Out
Reply
Reply
Anton says
June 3, 2015 at 1:10 PM
Reply
Hello Anton,
I have already given answer for this question in this blog post. Please read it
again.
Reply
Helli Fahad
First of all i just want to share that
400 PMP your
Exam articles
Sample are reallyTryvery
Questions It Outsimple to unserstand
Can you please help me in understanding commercial databases &PMIS and why
these are EEF instead of OPA
Reply
Because these are not always helpful, and you have work within their boundaries.
Reply
Aleem says
July 7, 2015 at 6:53 PM
Reply
You are welcome Aleem, and thanks for your million likes.
Reply
Hello Fahad,
I am thinking of giving the
400PMP
PMP exam. I yet to
Exam Sample begin. could
Questions Try Ityou
Out please help me how
should i proceed ?
Reply
Buy some good PMP exam reference books, study them, then read the
PMBOK Guide. After that get your 35 contact hours training program. Practice
some questions, and attempt the exam.
Reply
Kiran says
September 20, 2015 at 3:40 AM
Reply
Reply
Reply
Reply
Recommendation: You need a search bar for terms that direct one to your
explanations. Love the site need more versatility to locate the words I need quickly
defined.
Reply
I had the search bar but no body was using it there it was removed. Now, as
per your suggestion, I have added it again, let us see the result.
Reply
Reply
Thanks Femi.
Reply
Amit says
November 17, 2015 at 1:23 PM
Why human resource policies is OPA? We cannot change it, it should be EEF.
Reply
Reply
Amit says
November 17, 2015 at 1:26 PM
Reply
400 PMP Exam Sample Questions Try It Out
Fahad Usmani says
November 17, 2015 at 5:49 PM
Reply
Thanks so much Fahad for this explanation. Very helpful and your examples really
helped me clear majority of my confusions regarding OPA and EEF. However couple
of them still remains, respecting all your efforts and knowledge.
For the purpose of clarification please bear with me.
1. You have mentioned that OPA can be customized according to the suitability,
and they make the project management teams life much easier. Policies,
procedures, plans and knowledge bases are OPAs. Here I am little bit confused, my
understanding of policies and procedures is that they are assets owned by the
organization and applied across all project and operational activities, which are not
individually customized for a particular project activity. For example, my current
project follows the Health and Safety Policy (OPA) of our organization which cannot
be customized for my project and hence a constraint, rather than a support.
2. Organization structure I really need some help here how would the org.
structure an EEF? Please help.
Reply
If you find any new best practice, procedure can be update. Likewise policy
can also be changed.
Organizational structure is environment
400 PMP Exam Sample in which youTryhave
Questions It Outwork. For example
if you working in weak matrix organization, you may have to approach the
functional manager for you needs.
Reply
ahmed says
January 21, 2016 at 10:19 PM
Reply
Reply
Hello
Very nice and interesting blogs. many thanks Fahad Usmani..
Could we say that, organization structure is an EEF. ok, but the documents that
describe the framework of organizaton is an OPA?
Reply
Reply
Hi Fahad,
Thanks for explaining such complex terms so simple and convincing way.
I felt like I am in a classroom
Thanks again,
Mahesh
Reply
No problem Mahesh, you can post your doubt at anytime, I will try my best to
answer you.
Reply
Mike says
March 10, 2016 at 11:19 PM
400 PMP Exam Sample Questions Try It Out
Wow this really helped me.
Reply
Reply
Salahuddin says
May 6, 2016 at 6:42 PM
Hi Fahad,
Thanks for the clarification
Reply
Reply
Christy says
May 8, 2016 at 12:15 PM
Hi,
I have confusion between
400OPA
PMP and
ExamEEF andQuestions
Sample found yourTrywebsite.
It Out Looking at the
comments and I see your categorization of these examples below. I dont understand
the rationale even though I feel I know what you mean by the article. Can you please
elaborate more or relate it to the article definition for my better understanding?
Thanks lot!
Reply
sanjay says
June 13, 2016 at 2:14 PM
excellent Stuff, first time I have understood. Thanks keep sharing your thoughts and
Experience.
Reply
Reply
G-money says
July 6, 2016 at 10:53 AM
Please oblige my question. I know
400 PMP it has
Exam been
Sample asked before,
Questions but Im still struggling to
Try It Out
understand the distinctions:
My understanding:
EEF Condition (internal and external) under which you have to work. You have not
choice. You cannot change it, it affects everybody (Cold weather, the law, harsh
governmental policies, high altitude, unfriendly co-worker/work culture, functional
matrix org, projectized org, etc)
OPA (Internal only) Tools, techniques, information or knowledge that affect the
actual doing of the work they can help or guide you do your work (guidelines,
procedures, historical information from past projects, lessons learned).
Reply
Policies are OPA as they are designed by your organization to help you
successfully complete the project.
Reply
Manoj k says
July 21, 2016 at 4:11 PM
Hi Fahad, thanks for your patience to answer all questions. Here i have a confusion
and seek your help.
While the project is still running
400 PMP where is all project
Exam Sample dataTry
Questions stored?
It Out data like PM plan,
Project documents, Work performance data, Work performance reports.
If this data is stored through PMIS (EEF) as a front end, is it stored in some
knowledge base like Corporate Knowledge base (OPA) as a backend?
Or does it data remain in EEF till the project completes and then is submitted to OPA
through lessons learned?
Reply
Reply
Manoj says
July 22, 2016 at 9:50 PM
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Thank you so much for your insight into PMBOK. Its helping my lightbulbs turn on.
Reply
Reply
Hi Fahad,
Thanks a lot for the detailed explanation and also crystal clear clarity on some of the
topics mentioned.
Reply
400 PMP Exam Sample Questions Try It Out
Fahad Usmani says
October 9, 2016 at 8:42 AM
Since these are not mandatory, during fast tracking you look on these
dependencies to cut the time.
Reply
Jasmeen says
October 11, 2016 at 9:31 PM
Hi,
I have one confusion. I came across 1 question which is on kick off meeting.
Question: if you are pm and you need clarification on business needs then who will
present in kick off meeting
Will it be pm or sponsor.
Because i know pm always represents kick off meetings. But confusion here is if pm
need clarification then who will present?
Please if you help me with this question
Thanks
Reply
If the project manager needs clarification on business need he can refer to the
project charter or project statement of work which has detailed information on
business need of the project.
Reply 400 PMP Exam Sample Questions Try It Out
Punit says
January 3, 2017 at 11:26 PM
I am beginner and learning the things from basics. Can you please guide me how can
I find good examples and tutorials like you explained this topic in a pretty good
manner.
Thanks,
Reply
Read all blog posts published on this blog and FAQs, you will get all info you
need to prepare and pass the PMP exam.
Reply
Dear Fahad!
I really love your style of explanation. Very helpful for beginners.
Pl keep it up
Reply
Reply
katy says
February 11, 2017 at 9:49 PM
I like your writing style. Writing in short, simple sentences that each focus on a
concept makes the info easy to understand. I recommend you place this box at the
top of the comments instead of the very bottom and youll get even more positive
feedback.
Reply
Thanks Katy for your comment. Which box are you talking about?
Reply
Carmen says
March 19, 2017 at 12:25 AM
Reply
Reply
Raymund says
May 16, 2017 at 12:40 PM
Reply
Reply
Reddy says
May 23, 2017 at 4:55 PM
It was good information, most of the time was confusing these terms. Much helpful.
Reply
Reply
400 PMP Exam Sample Questions Try It Out
Chi Ho says
May 28, 2017 at 5:25 PM
PMBOK Guide Fifth Edition, page 75 says The organizational process assets
include : standardized guidelines, work instructions, proposal evaluation criteria,
change control procedures, project files from previous projects, configuration
management knowledge base, etc. PMBOK Guide Fifth Edition, page 75
For me, change control procedures is nothing related to lesson learned, historical
data or knowledge base. Therefore, it it better in EEF. What do you think Fahad?
Reply
Chi Ho says
May 28, 2017 at 6:08 PM
To make more confusion, in Rita Mulcahy 8th page128, the definition of Change
Control System is Many organizations have a change control system as part of their
PMIS. This system includes procedures and software to track control changes. It is
part of an organizations EEF.
Look, according to Rita, the Change Control Procedures is included in the PMIS, and
PMIS is part of EEF. Hence the change control procedures must be part of EEF. But
PMBOK page 147 defines that OPA includes Change Control Procedures.
Reply
This is a great article that simply explains EEF and OPA and points at the
differencies.
Reply
Reply
really it is the best explanation I have seen to define the EEF & OPA. but I have a
little confuse regarding to the quality control system that you specified as EEF
but I can see it as company can change the system if their is another better
practice will improve the projects- so it should be under OPA.can you please
explain me why it goes under EEF and not under OPA?
your time and help is really appreciated and thanks in advance.
Reply
Reply
ellie na says
November 12, 2017 at 1:58 AM
Thanks for the helpful info! I understand the difference between OPAs and EEFs but
since they are an input to or output of most of the processes, is there a handy list of
processes where OPAs and/or EEFs are NOT an input or output? This would just
make it easier in terms of trying to manage all the ITTOs and focus one the ones that
are process or knowledge area specific,
Thanks!
Reply
You can assume it is input to always all processes. Cannot think of any
process which will have them as an input.
Reply
400 PMP Exam Sample Questions Try It Out
Leave a Reply
Your email address will not be published. Required fields are marked *
Comment
Name *
Email *
8 + four =
Post Comment
Submit Query
400 PMP Exam Sample Questions Try It Out
RECENT COMMENTS
Fahad Usmani on What is the PMP Exam Fee Refund Policy of PMI?