Beruflich Dokumente
Kultur Dokumente
Prepared by:
2. Esther Andere
Approved by:
Project Location L.R. NO. 209/7139, Off Likoni Road in Industrial Area,
Nairobi
Document Number
520452
Page 2
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
E-mail administrator@total.co.ke
Website www.total.co.ke
PIN No.
2. Esther A Kabaka
E-mail Philip.abuor@sgs.com/isaiah_kegora@sgs.com
Website www.ke.sgs.com
Page 3
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CERTIFICATION
The preparation of this EIA Study Report was commissioned by the management of Total
Kenya Limited in fulfillment of requirements of the EIA/EA Regulations and Environment
Management and Coordination Act, 1999.
..
Submitted by:
Official Stamp
Approved by:
.. ..
Signature Date
.. ..
Signature Date
Page 4
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
ACKNOWLEDGEMENT
We extend our special thanks to the management of Total (K) Ltd (the Proponent) for
contracting SGS (K) Limited (the Firm of Experts) to prepare this E.I.A study Report for their
proposed installation of their Liquefied Petroleum Gas tank and cylinder filling station at BAT
Kenya, Likoni Road.
We further register our gratitude to the various stakeholders consulted during public
stakeholder consultation for their invaluable contribution, support and cooperation. Their input
contributed enormously towards successful completion of this E.I.A study report.
Page 5
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
ACRONYMS
Acronym Description
BS British Standard
EA Environment Audit
Page 6
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
EXECUTIVE SUMMARY
Introduction
Total Kenya limited (proponent) proposes to construct a 2ton LPG storage tank and filling
point on plot L.R. No. 209/7139, which is owned by British American Tobacco Ltd. The facility
will be operated by BAT (K) Ltd, Likoni Road; with the main purpose of providing more LPG
stock at the factory for refilling the forklifts cylinders.
The E.I.A for the project is being coordinated by SGS (K) ltd (NEMA registered firm of
experts). The firm has been appointed by the proponent to complete the EIA study in
accordance with Legal Notice (L.N.) 101: Environment (Impact Assessment and Audit)
Regulations 2003 promulgated under the Environment Management and Coordination Act,
1999.The proposed project is also expected to comply with the energy act and its subsidiary
legislation.
The proposed development activities will mainly involve civil, mechanical and electrical works
associated with the installation of the LPG tank and filling point and thereafter operations of
the facilities. The main activities to be carried out in the development of the proposed project
include excavations or earth works, installation of the tank and pump and pipe works.
The proposed project is expected to start immediately this Study Report is approved by
NEMA and EIA Licence is issued to the Proponent. It is estimated that the project will cost
approximately two million and seven hundred thousand Kenyan Shillings (Kshs 2,700,000.)
to complete.
The project site is located in an industrial set up. The neighborhood is characterized by
light industries such as printing firms, beverage manufacturing, motor vehicles parts
manufacturing plant and warehouses. The project area is served by two main roads;
Likoni Road and Enterprise Road.
Project Objectives
The proposed project aims to increase the availability of LPG at the Nairobi BAT Factory to be
used for powering the forklifts. BAT (K) is in the process of phasing out forklifts which use
diesel in a bid to support Government and their Companies corporate efforts to promote the
use of clean fuels.
The proponent has undertaken a preliminary estimate of the total project cost using
experienced consultants. The estimated total project cost is approximately Kshs 2,700,000.
Page 7
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
On the basis of the above project cost estimate, the proponent is paying Kshs. Kshs. 10 000
to NEMA as EIA license fee.
Project Description
Technical Description
Installation of a 2ton LPG Tank, with a diameter of 1.5m and a length of 3.03 m
Construction of a cylinder filling station;
Pipe works
Paint works
Water Sprinkler system
Construction of a Perimeter fence and gate
The proposed project will be designed, constructed, and operated in conformance with
applicable national and international EHS guidelines and standards. Regarding safety at the
facility the proponent will put in place all mechanisms, processes and procedures to eliminate
mitigate or control identified risks and promotes continuous improvement. Further to this the
proponent will apply HSEQ considerations in all planning, decision making, processes and
practices. Various measures have also been put in place to prevent leakages which include
an electronic check scale and manual leak detector. An emergency shutdown system will also
be installed to improve the safety situation at the facility. A hazardous operability study
(HAZOP) will be carried out during the design phase of the facility to incorporate health,
safety and environmental considerations.
An environmental management plan has been prepared which describes the environmental
protection strategies that will be employed at the site. The EMP contains the management
programmes and plans for handling the adverse environmental impacts.
Construction Phase
The LPG Tank will be transported from Mombasa to BAT Premises at Likoni Road in Nairobi.
Most raw materials and fittings required for the LPG facility will be sourced locally. Heavy duty
machinery including cranes, bulldozers, excavators, front-end loaders and electric welding
machines will be used during construction.
Construction activities are expected to generate noise levels to a limit of 85 decibels and
other safety hazards.
Page 8
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Operational Phase
A fire protection system will be provided. It will by means of two 9Kg Dry powder
extinguishers and a water sprinkler system. The sprinkler system will comprise of 1 1/2" main
water line to tank and filling station, 1" and 3/4" cooling rings to storage tank complete with
thermospray sprinkler nozzles.
The facility will be hooked to the existing electricity supply line of KP&LC while Sewerage and
waste will be managed in accordance with the existing waste management procedures of
BAT Kenya limited and Environmental Management and Coordination (Waste Management)
Regulations of 2006.
Approximately 5 long term job opportunities will be generated through the operation of the
LPG station. Skilled and unskilled labor will be required in technical fields as in operations and
management. Local people will be employed wherever possible.
Noise levels will be kept to a minimum by designing the facility according to the requirements
of Kenyan legislation - The Environmental Management And Coordination (Noise And
Excessive Vibration Pollution) (Control) Regulations, 2009 and ISO: 15664:2001.Noise
impacts shall not exceed the standards [Threshold Limit Values (TLV),] adopted by
International Labor Organization (ILO), World Health Organization (WHO) and American
Conference of Industrial Hygienist (ACGIH) 1989-guideline document.
Approximately 5 long term job opportunities will be generated through the operation of the
LPG station. Skilled and unskilled labor will be required in technical fields as in operations and
management. Local people will be employed wherever possible.
The site enjoys temperate tropical climate with two rainy seasons. The mean annual rainfall
ranges between 850-1050mm (Lakin undated). The mean daily temperature ranges between
12 and 26C. The mean monthly relative humidity varies between 36 and 55 per cent.
The site is underlain by ancient core of crystalline rocks of the Basement Complex. The
prominent rock type in the project area is welded tuffs at shallower depths followed by
fractured phonolite. The soils are black cotton soil, which are inorganic clays of medium to
high compressibility and form a major soil group in Nairobi.
The ambient noise level at site is typical of the industrial setting. Existing noise data indicates
that noise levels range between 51.5 dB (A) and 62.5 dB (A). The ambient noise at the site is
mainly influenced by noise from neighboring industrial facilities and traffic on the nearby
Likoni Road.
Page 9
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The ambient air quality is also typical of industrial setting. Available data on air quality of the
site indicate that the concentration of particulate matter, sulphur dioxide and nitrogen dioxide
in air are generally within guideline limits stipulated under the Draft EMC (Air Quality
Standards) Regulations, 2008.
During construction phase, waste will be generated from construction activities, domestic
waste from construction team, sewage, waste oil, treated timber, polythene and plastics
packing material and lubricants, containers of used construction materials and wastewater
from hydrostatic testing.
During operation phase, waste to be generated include domestic waste generated by the
operation staff, components/parts of the facilitys infrastructure been removed during
replacement; and redundant electronic equipment.
Whereas during decommissioning phase, the main waste generated will be demolished parts
of the facility which include; concrete boulders, scrap metals, plastics and rubber among
others. The contractor should develop an integrated solid waste management system for the
site.
During the construction phase the proposed project will utilize machineries such as hydraulic
excavator, mobile service crane, dump trucks and tipper Lorries which are likely to generate
noise. The contractor at site will be expected to provide proper protective equipment and well
planned programs for equipment usage.
During operation phase noise generation will be from the generator, compressor and the
pumps. The amount of noise will depend on the size and the model of the pump to be used.
As will be the case with the construction phase, the sources of noise during decommissioning
phase, will be mainly machinery and vehicles used in demolition of the facility and removing
the materials from the site. The construction activities will be limited to daytime and the
workers will be provided with personal protective equipment.
The potential health and safety impacts of the proposed project include the occupational
health and safety risks related to the project activities; risks to the public as a result of events
of major disasters such as fire outbreaks and explosions.
A number of activities undertaken during development of the proposed project have potential
risks to health and safety of the workers. During the construction phase, the potential H&S
risks the workers are likely to be exposed to include: Injuries resulting from falling from LPG
Page 10
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
tanks installation; Injuries resulting from operation of machinery, equipment, tools and
construction vehicle, Exposure to diseases, including, typhoid etc. and road accidents.
The potential occupational health and safety impacts during operation phase include injuries
to workers from, routine monitoring and maintenance and deaths and injuries from major
disasters e.g. explosions and fire outbreaks. During the operation phase, the workers may
come in contact with liquid LPG and suffer from severe cold burns whereas during
decommissioning, the potential H&S risks include injuries occasioned by dismantling of the
facility. The proposed project could be of great public concern especially in the event of a
major disaster such as explosions and fire outbreaks. Liquefied Petroleum Gas is a highly
flammable product and can be detrimental to the public safety if measures are not put in
place. The impact significance related to public safety is likely to be high during operation
phase of the project.
This report presents an environmental management plan which covers on the measures for
mitigating the adverse potential environmental impacts of the proposed project. The EMP
includes programmes and plans for addressing the adverse environmental impacts. The
proposed management programmes includes:
The proposed programs and plans will be subjected to monitoring. Monitoring will have two
elements: routine monitoring against standards or performance criteria; and periodic review or
evaluation. Monitoring will often focus on the effectiveness and impact of the programme or
plan as a whole.
Analysis of alternatives
Several alternatives for the proposed project were evaluated. The alternatives considered
include: Location, process/activity/operation, layout, input, and no-go option. On the basis of
these considerations, the proposed project satisfies the overall economic, technical,
environmental and safety criteria used.
Page 11
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Public Consultation
Public stakeholder consultation was undertaken in order to obtain the views and concerns of
the stakeholders regarding the proposed project. The stakeholders perceived that the project
will not generate adverse environmental impacts. Some of the pertinent issues which were
raised have been addressed in the environmental management plan.
Conclusion
The project, including the construction and operation of the LPG tank and cylinder filling
station is anticipated to provide sufficient stock of LPG at the factory and also lower CO 2
emissions to the atmosphere. The potential adverse impacts associated with the proposed
project are possible to mitigate successfully. The impacts before implementation of
mitigation measures are assessed as very low to medium low and the ratings are
expected to improve further with the implementation of the proposed mitigation
measures. In particular, the LPG facility will be designed, constructed and operated
according to the latest industry norms and standards. Programs and plans developed and
implemented through the EMP will be monitored and audited to ensure compliance.
Recommendation
The mitigation measures proposed in this report should be included in the tender contract
and tender documents so that the contractor who will be selected for the project will be
bound to implement them.
Page 12
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
TABLE OF CONTENTS
CERTIFICATION .................................................................................................................................... 4
ACKNOWLEDGEMENT ......................................................................................................................... 5
ACRONYMS ........................................................................................................................................... 6
1 INTRODUCTION ........................................................................................................................ 19
1.1 Project Background ............................................................................................................. 19
1.2 Project Objectives ............................................................................................................... 19
1.3 Data Collection .................................................................................................................... 19
1.3.1 Review of secondary data ............................................................................................... 19
1.3.2 Interviews ........................................................................................................................ 19
1.3.3 Baseline environmental survey ....................................................................................... 19
1.3.4 Noise quality .................................................................................................................... 20
1.3.5 Air Quality Measurement ................................................................................................. 20
1.3.6 Assessing significance of Impacts................................................................................... 20
1.4 Purpose of this Report ........................................................................................................ 23
Page 13
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 14
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 15
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 16
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 17
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
List of Figures
FIGURE 1: SATELLITE IMAGE SHOWING THE LOCATION OF THE PROPOSED PROJECT SITE ................................ 24
FIGURE 2: TYPICAL MOUNDED BULLET................................................................................................................. 74
FIGURE 3: AN IMAGE OF LPG SPHERE ................................................................................................................ 75
FIGURE 4: PROPOSED ENVIRONMENTAL MANAGEMENT STRUCTURE ................................................................ 80
List of Tables
TABLE 1: CRITERIA FOR ASSESSING SIGNIFICANCE OF IMPACTS ........................................................................ 21
TABLE 2 : SIGNIFICANCE RATING MATRIX ........................................................................................................... 22
TABLE 3: POSITIVE/NEGATIVE MITIGATION RATINGS AND ASSOCIATED COLOR CODES ..................................... 23
TABLE 4: STANDARDS TO BE USED FOR THE PROPOSED LPG FACILITY ............................................................ 26
TABLE 5: SUMMARY OF LEGISLATIONS APPLICABLE TO THE PROPOSED PROJECT ............................................. 38
TABLE 6: SUMMARY OF IDENTIFIED IMPACTS ...................................................................................................... 71
TABLE 7: LIST OF STAKEHOLDERS CONSULTED DURING PROJECT REPORT PREPARATION ............................. 77
TABLE 8: ADDITIONAL STAKEHOLDERS CONSULTED DURING PREPARATION OF EIA STUDY REPORT .............. 77
TABLE 9: APPROACH USED TO MANAGE POTENTIAL IMPACTS ........................................................................... 79
TABLE 10: FUNCTIONS OF STAFF IN IMPLEMENTATION OF EMP ........................................................................ 81
TABLE 11: MITIGATION AND MANAGEMENT MEASURES FOR THE IDENTIFIED IMPACTS ...................................... 91
Page 18
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER ONE
1 INTRODUCTION
Total Kenya Limited, one of the leading oil marketers in Kenya, which is hereinafter referred
to as Proponent, is proposing to install a 2ton petroleum storage tank and a cylinder filling
station at British American Tobacco Kenya premises, located along the Likoni Road in
Industrial area of Nairobi.
The Legal Notice No. 101 of 2003 (EIA/EA Regulations, 2003) requires the Proponent to
prepare EIA Study Report for approval by National Environment Management Authority
(NEMA) prior to commencement of a new development. As such, Total Kenya Limited
engaged SGS Kenya Limited to undertake environmental impact assessment for the
proposed project.
The Proponent is seeking to have sufficient stock of LPG for powering the forklifts used in
their operations. There is an underway plan of phasing out the forklifts that use diesel and
replacing them with those that utilize LPG. The Proponent intents to increase the number of
forklifts that uses LPG gas from 15 to 30. The proposed 2tone tank will ensure the availability
and accessibility of the gas.
The Firm of Experts employed various approaches in collecting data and information for
assessing the impacts of the proposed project. The following techniques were used:
A wide range of environmental and socio-economic data were sought to describe the baseline
conditions at the project area. These included socio-economic, physical and environmental
data and reports from government departments and on-line sources.
1.3.2 Interviews
Interviews were conducted during public stakeholder consultation in order to obtain the views
and concerns of the interested parties as regard to the proposed project. A semi structured
interview checklist was used to capture the responses of the stakeholders.
Page 19
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The ambient noise level at the proposed site was measured using precision type 1 accuracy
Integrating Sound Level Meter accuracy Integrating Sound Level Meter. The instrument was
calibrated using sound level calibrator at 94 dB (A) and 1000 Hz. The calibration was used to
check the sensitivity of the instrument immediately before and after the measurement period.
The meter was set to measure the A-weighted noise level, which varies with the frequency
and intensity like the sensitivity of the human ear.
The sound level meter was held at 1 metre from the ground and the L eq, (the continuous
equivalent sound pressure level) and an indicative of the average noise level over a given
period), sample measurements were taken at various locations in the proposed site.
Air quality measurement was done to determine the levels of air contaminants of concern
associated with the operations at the project area. The measurements were done using
Minivol air samplers were used at the selected locations for fine particulate monitoring. The
Minivol portable air sampler is an ambient air sampler for particulate matter. The sampler is
positioned with the intake upward in an unobstructed area, free from any obstruction to
airflow. The sampler is fitted with a PM10 inlet, which only allows for particles of an
aerodynamic diameter of less than 10 m (PM10) to pass through it. The sample is drawn
through the unit at a predetermined flow rate and collected onto filter papers over typically 24-
hr sampling periods.
The first stage of impact assessment is identification of environmental activities, aspects and
impacts. The significance of the impacts is then assessed by rating each variable numerically
according to defined criteria as outlined in Table 1.
The purpose of the rating is to develop a clear understanding of influences and processes
associated with each impact. The severity, spatial scope and duration of the impact together
comprise the consequence of the impact and when summed can obtain a maximum value of
15. The frequency of the activity and the frequency of the impact together comprise the
likelihood of the impact occurring and can obtain a maximum value of 10. The values for
likelihood and consequence of the impact are then read off a significance rating matrix (Table
2), and it is determined whether mitigation is necessary using Table 3.
Page 20
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Receptors can comprise, but are not limited to, people or human-made structures or systems,
such as local residents, communities and social infrastructure, as well as components of the
biophysical environment such as aquifers, flora and palaeontology. In the case where the
impact is on human health or wellbeing, this should be stated. Similarly, where the receptor is
not anthropogenic, then it should, where possible, be stipulated what the receptor is.
Consequences
Magnitude of Impact Rating
Negligible 1
Minor 2
Marginal 3
Significant 4
Catastrophic 5
Page 21
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Regional 4
National 5
Likelihood
Frequency/duration of activity Rating
Annually or less 1
6 monthly/temporary 2
Monthly/infrequent 3
Weekly/life of operation 4
Daily/permanent 5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Likelihood (Frequency of Activity Frequency of Impact
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45
4 8 12 16 20 24 28 32 36 40 44 48 52 56 60
5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
6 12 18 24 30 36 42 48 54 60 66 72 78 84 90
7 14 21 28 35 42 49 56 63 70 77 84 91 98 105
Page 22
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
This report addresses the requirement for preparation of EIA Study Report in accordance with
EIA/EA Regulations, 2003.
The report presents an overview of the proposed project and the environmental regulatory
framework from which it operates. It identifies and assesses the significance of the impacts of
the project as well as mitigation measures necessary to reduce or prevent impacts from
occurring.
Page 23
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER TWO
The proposed project will be developed on Plot No L.R. No. 209/7139 which is along Londiani
Road, off Likoni Road in Industrial Area, Nairobi City. The owner of the land is BAT (K), Likoni
0 0
Road. Geographically, the site is located on Longitude 036 51 19.22 East and Latitude 01
18 17.10 South.
Copy of certificate of title of the land is appended at the end of this report (Appendices 1).
Figure 1 below is a satellite image showing the location of the project site
Londiani Rd
Likoni Rd
Figure 1: Satellite Image showing the location of the proposed project site
The site is bound by Modular Products Ltd to the West, Vas Auto Center Ltd to the North and
Agro Manufacturing Co. Ltd and Blue Waves. Across the Likoni Road which is on the West, is
the BAT factory.
Page 24
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The proposed project will have a 2ton Liquefied Petroleum Gas aboveground tank, a filling
station and perimeter fencing. The project will occupy an area of approximately (17*8.05)
square meters. LPG cylinders from the forklifts will be brought at the site for refilling.
2.3 Technology
The primary technologies used for the design, construction and operation of the LPG facility
include various international codes of practice, Standards, Government Acts and Local
Authority Regulations.
In Kenya there are a limited number of regulations covering the technology to be used in the
design, construction and operation of LPG station. Subsequently the country relies on
international codes of practice, standards and guidelines for the design, construction and
operation of such facilities.
The proposed project will be designed and constructed in alignment with the standards
quoted in table 4 below.
Page 25
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Mechanical Works
Steel Wedge Gate Valves for the Petroleum, Petrochemical and Allied
BS 1414
Industries
Steel Check Valves (Flanged and Butt-Welding Ends) for the Petroleum,
BS 1868
Petrochemical and allied Industries
Steel Wedge Gate, Globe and Check Valves 50mm and smaller for the
BS 5352
Petroleum, Petrochemical and Allied Industries.
ASME B 16.9 Factory Made Wrought Steel Butt Welding Fittings
1P part 2 Marketing Safety Code (for all works)
Electrical Works
BS 5467 Specification for XLPE Insulated Cables
BS 5486 Low Voltage Switchgear and Control Gear Assemblies
BS 5501 Electrical Apparatus for Potentially Explosive Atmospheres
BS 7430 Code of Practice for Earthing
BS 7671 Requirements for electrical Installations
IP Part 1 Electrical Safety Code
IEC 502 Specification for XLPE insulated Power Cables
Instrumentation and Control
BS 381 C Colors for Identification, Coding and special Purposes
BS 1363 1 3A plugs, socket-outlets and adapters
BS 4196 Sound Power Levels of Noise Sources
BS 5308 Instrument Cables
Code of Practice for Instrumentation in process Control Code of Practice for
BS 6739
Earthing
Code of Practice for the Instrumentation of in Process Control Systems: socket
BS 6739
outlets and couplers for industrial purposes
P Part 15 Area Classification code for Petroleum Installations
Civil and Structural Standards
BS 8110 Structural use of concrete
BS 8004 Code of practice for foundations
Page 26
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
It is approximated that the construction of the proposed project will cost Kshs 2,700,000. This
cost will be shared between the Proponent and BAT (K) Ltd. Therefore, the Proponent will
pay Kshs. 10 000 to NEMA as EIA licence fee.
The 2 ton storage tank will be transported from Mombasa. It will have a diameter of 1.5m and a
length of 3.03 m. It will be put on a Tank foundation pad u/g measuring 4m long by 2m wide by
0.5m deep, the design is as per BS 8110 Standard. The tank will be located 9m from the filling
point. During construction, the contractor will adhere to international and local standards including
NFPA 28, API 25, API 2510A and KS 1938.
The filling station will be supplied with a fire extinguisher to be used in case of fire emergencies.
The cylinder filling area will be reinforced with a thick concrete slab for the LPG Pump. The
pump will be installed 3m from the LPG cylinder and 6m from the filling shed. The shed will
measure 1.2m by 1.2m by 2m high, with a cast slab beneath of measuring 1.2m by 1.2m by
100mm thick.
The filling process will take place in the cylinder filling area. The Plants filling stock
management system will be fully computerized. This will ensure that every single cylinder will
be filled thoroughly and that instances such as over-filling, under-filling, and leakages do not
occur.
Before the LPG cylinders are filled, a pre-fill inspection of the cylinders will be undertaken to
ensure that the cylinders are safe to fill. The cylinders that are found to be in good condition
will be filled, sealed, weighed and taken back to the factory.
The project will have a perimeter fence of 7.5m, 17m and 3m high. This will be reinforced by
3m long 3" by 3" by 6mm Angle Iron fence supports. Chain links will be bound on the iron
bars and a steel gate of size 1.5m wide by 2.0 m high, will be fabricated and installed.
Page 27
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The facility will have a comprehensive fire fighting system covering all hazardous areas and
the other areas of the facility. This ensures that any fire within the depot is quickly surpassed
and extinguished. It includes fire water sprinkler systems for the LPG tank, and also two 9Kg
dry powder extinguishers will be mounted at the facility.
The site preparation work will consist of the following; site clearing (relocation of pallets and
boxes), excavation followed by backfilling and compaction. The waste generated from site
clearing will be transported and dumped by the waste handlers. The Contractor will be in
charge for the transport of raw materials to site during construction process. Some of the
materials to be delivered to the site include aggregates, masonry stones, cement, iron sheets
and other construction materials.
2.4.2 Materials
The exact quantities of materials required for the construction of the proposed project are not
known at this stage of the project. The Proponent will utilize several materials in the
construction of the project. Some of the materials have been sourced locally whereas others
have been obtained from sources outside Nairobi City.
The materials to be used in the construction of the projects consist of the following:
a) Concrete
b) Sandstone
c) Sand
d) Steel rods
e) PVC pipes
f) Water
g) Paint
h) corrugated preprinted roofing
i) energy Diesel and electricity
Page 28
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
2.4.3 Product
The final product after construction phase is LPG storage facility which will comprise
of a 2 ton Aboveground Storage Tank and associated Pipe work and a Gas filling
area.
2.4.3.1 By-products
The Proposed project will generate several byproducts during both construction and operation
phases.
During the construction phase of the project it is envisaged that the by-products might include:
Metal cuttings generated from the construction activities
Any excess construction materials brought to the project site by the contractor which can
be reused later
Excavated material
2.4.3.2 Waste
During construction the proposed project is anticipated to generate different waste which shall
include:
The workers will not be supplied with any forms of foodstuffs. They are expected to buy or
carry their own food. Plastic bags and containers which the workers will use to carry their food
are expected to increase within the site and in the immediate vicinity.
Other forms of waste include sanitary waste and therefore the provision of sanitary facilities
will need to be considered both for the site construction workers and the visiting population.
The project will generate waste from the site construction activities which includes:
Excavated soils and vegetation;
Construction equipment and maintenance wastes;
Dust and fumes;
Scrap metals;
Packaging materials, etc.
The wastes will be segregated in accordance with Legal Notice 121: Waste Regulation, 2006
with recyclable material collected and transported to a recycling facility. An effort will be
made to minimize the amount of waste generated by application of 4-R principles (reduce,
reuse, recycle, recover) to the extent practical. Non-recyclable wastes should be
transported offsite to a permitted landfill. A Waste Management Plan (WMP) will be
Page 29
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
developed for all phases of the Project. The objective of this plan is to minimize waste
discharges and emissions and identify appropriate waste reduction and other mitigative
measures.
Air quality impacts associated with construction activities are generally related to the
generation of dust especially during dry weather conditions and exhaust emissions
from the operation of construction equipment. Control measures, such as use of
dust suppression techniques, will be used in construction zones as required to
minimize the impacts from fugitive dust. The air emissions from the construction
equipment will be localized and temporary, lasting the duration of construction
activities. Routine inspection and maintenance of construction equipment will
minimize exhaust fumes.
The target noise levels during construction are set at 75dB (A) (BS 5228, 1997) during the
day and 70 during the night.
2.4.5 Commissioning
The final stage of construction is the start-up and commissioning of the facility. During the
commissioning stage, air will be purged from the tank and pipelines.
Once commissioned, the tank will be filled with LPG. The gas will be brought in by Total trucks.
The proposed LPG will only serve BAT Kenya, and will be used for refilling the cylinders used
by their forklifts.
Page 30
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
2.4.6.1 Products
The primary product of the proposed project during the operational phase will be Liquid
Petroleum Gas.
2.4.6.2 By-products
During the operational phase of the project it is not expected that there will be any by-
products generated.
2.4.6.3 Waste
Effluent Waste
The above effluent water will be discharged offsite through the BAT drainage system.
Domestic Waste
Some of the domestic waste to be generated at the facility will include office waste such as
paper, empty cans among others.
Sewage Waste
The employees of the Proponent who will be based within the project area are expected to
generate sewage waste which will be channeled to the conservancy tank.
Upon decommissioning of the proposed LPG tank, rehabilitation of the project site will be
carried out to restore the site to its original status or a better status than it was originally. This
Page 31
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
will include replacement of top soil and re-vegetation which will lead to improved visual quality
of the area.
During the decommissioning phase it is expected that there will be no product. However the
by-products during decommissioning phase will include:
2.4.7.2 Waste
During the Decommissioning phase of the proposed project, several waste products are
expected to be generated. These shall include:
The demolition activities that will occur particularly during the demolition process will generate
a considerable amount of dust and other particulates that will be released into the
atmosphere.
The demolition machinery, equipment and trucks brought in by the Contractor are expected to
generate smoke emissions. The concentration of emissions will depend on the maintenance
levels of the equipment, machinery and trucks used by the Contractor.
The potential health and safety impacts of the proposed project include the occupational
health safety risks related to the project activities; risks to the public as a result of events of
major disasters such as fire outbreaks and explosions.
The potential occupational health and safety impacts during construction phase will include
injuries through the construction activities whilst during the operation phase they will include
injuries to workers from, routine monitoring and maintenance and deaths and injuries from
major disasters e.g. explosions and fire outbreaks . Whereas during decommissioning; the
potential H&S risks include injuries occasioned by dismantling of the facility.
Page 32
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
2.6 Employment
The proposed project is expected to create employment in both the construction and
operation phases of the project.
Page 33
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER THREE
The baseline environmental condition of the proposed project is described in terms of the
existing physical, biological, and social environment.
The physical characteristics of the proposed project site is described in terms of soils,
geology, topography, drainage, climate, ambient noise levels and non ionizing radiation
levels.
The proposed project site is overlain by ancient core of crystalline rocks of the Basement
Complex which underlies the greater part of the plateau areas of Africa which have been
affected by the extensive faulting, displacement and volcanic activity associated with the
Rift Valley System (Ministry of Water and Irrigation 2011). The prominent rock type in the
project area welded tuffs at shallower depths followed by fractured phonolite while the
soils are black cotton soil, which are inorganic clays of medium to high compressibility
and form a major soil group in Nairobi (Ministry of Roads, 2012). They are characterized
by high shrinkage and swelling properties. Because of its high swelling and shrinkage
characteristics, the black cotton soil has been a challenge to the construction engineers.
The soil is very hard when dry, but loses its strength completely when in wet condition.
3.1.3 Climate
The project area and the entire Nairobi City has a temperate tropical climate with two
rainy seasons. The area receives high rainfall between March and April and experiences
short rainy season between November and December. The mean annual rainfall ranges
between 850-1050mm (Lakin undated). The mean daily temperature ranges between 12
and 26C. It is usually dry and cold between July and August, but hot and dry in January
and February (CBS 2003). The mean monthly relative humidity varies between 36 and 55
per cent. The mean daily sunshine hours varies between 3.4 and 9.5 hours (CBS 2003a).
The ambient noise levels of the proposed site influenced by noise from the neighbouring
industrial facilities and traffic on the nearby Likoni Road.
The data of noise measurement undertaken at the project site in 2012 indicates that
ambient noise levels at the site range between 51.5 dB (A) and 62.5 dB (A). The levels
Page 34
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The data of ambient air quality measures undertaken at the project site in 2012
indicates that the concentration of particulate matter, sulphur dioxide (SO2) and Nitrogen
dioxide (NO2) in the air are within the 120 g/m3 recommended by the draft EMC (Air
Quality Standard) Regulation, 2008 for an industrial area. The concentrations were: NO2
(32.8 g/m3), SO2 (14.1 g/m3) and particulate matter (15 g/m3). The air quality is
expected to be impacted by construction and demolition activities; however,
implementation of the proposed recommended measures will keep the levels within the
acceptable limits.
The project site is mainly covered by buildings and paved surface. There are ornamental
trees on the fence and along the nearby road. A huge acacia tree on the neighbouring
plot to south east has branches hanging over the boundary of the proposed site. The
trees on fence will be removed and a boundary wall erected. A flower garden has been
included in proposed the design of the gym.
Water
Ground and surface water both play an important role in water supply for Nairobi. The
principal source of water for Nairobi is surface water from the Tana River drainage basin
(Foster and Tuinhof 2005). Freshwater is also found in the three main rivers that flow
through Nairobi, but quality is a problem.
As regards to the project site, the Proponent has two onsite boreholes which supplies
water for general use while drinking water is supplied by a contractor in bottles. Water is
used for flowering, cooking, general cleaning and in sanitary conveniences. The water to
be used in contraction work will supplied from the same sources.
Land use
The Proposed project site is located in an industrial set up. The neighborhood is
characterised by light industries such as printing firms, beverage manufacturing, motor
vehicles parts manufacturing plant and warehouses.
Population
Nairobi has eight per cent of the countrys total population and 25 per cent of Kenyas
urban population (KNBS 2009). The growth of population of Nairobi is partly explained
by net migration into the city. The net immigration flow into the city between 1979 and
Page 35
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
1989 was 772,624 (NEMA, 2003). The forces motivating rural-urban migration to Nairobi
include better economic prospects, opportunities for higher education and higher wage
employment, and the attraction of Nairobi as a market for goods and services (UNEP,
2007). But there is also the phenomenon of diurnal migration of people from the environs
who commute daily into Nairobi for purposes of employment, education or trade.
Projections are that diurnal migration will continue unless deliberate efforts are made to
develop satellite towns and employ strategies to reduce the daily influx of people to the
city.
Infrastructure
The project area is served by two roads; Likoni Road and Enterprise Road. The roads
are normally characterised by heavy traffic congestions partly caused by heavy
commercial vehicles. Other infrastructural facilities available in the project area are:
sewer lines; water reticulation system, telecommunication facilities and electricity.
Page 36
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER FOUR
This section of the report discusses the policy, applicable EHS legislations and institutional
framework.
4.1 Policy
The execution of the proposed project will be done in accordance with all applicable
legislation, regulations, approvals and relevant guidelines. Table 5 provides legislations that
are applicable to the proposed project.
Page 37
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The EMCA, 1999 NEMA A framework legislation that Requires the Proponent to:
addresses major issues concerning submit EIA Study Report to NEMA before commencing
any new project.
the environment. The purpose of
engage NEMA approved expert/firm of experts in
the Act is to provide for sustainable conducting EIA studies
management of the environment.
Environment Impact NEMA Provides for the framework for Requires the Proponent to:
Assessment /Environmental carrying out environmental impact
prepare EIA Study report in accordance with the format
Audit Regulations, 2003 assessment in Kenya specified in Regulations and pay attention to issues
specified in the second schedule of the Regulations
carry out corrective measures in the improvement order
from NEMA
carry out corrective measures in the improvement order
from NEMA
allow a NEMA inspector to enter the facility for the
monitoring the effects of its activities on the
environment
mitigate trans-boundary impacts taking into account
regional and international treaties
L.N. 121: Environmental NEMA Formulated for managing various The Regulations requires the Proponent to:
Management and Coordination kinds of waste in Kenya
Acquire valid EIA licence from NEMA prior to engaging
(Waste Management) in an activity that can generate hazardous substance
Regulations, 2006 Segregates their waste (hazardous and non-
hazardous) by type and then disposes the wastes in an
Page 38
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
L.N. 120: Environmental NEMA Formulated for sustainable The Regulation requires the Proponent to:
Management and Coordination management of water used for
Refrain from any activity which might cause water
(Water Quality) Regulations, various purposes in Kenya pollution.
2006 Not to discharge any liquid, gaseous or solid into water
resource as to cause pollution.
Acquire a valid effluent discharge license to discharge
effluent into the environment.
acquire EIA licence prior to abstracting ground water or
any activity that is likely to have any adverse impact on
the quantity and quality of the water
follow the monitoring guide set out in the Third
Schedule to the regulation when discharging effluent
into the environment
Legal Notice No.61 of 2009: NEMA Promulgated for control of Noise The regulations:
The Environment Management and excessive vibration pollution
Prohibits the Proponent from making or causing to be
Page 39
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 40
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 41
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Hazardous Substances Rules, DOSHS Protection of employees from This legislation requires the Proponent to:
2007 exposure to hazardous substances
Ensure that where chemicals come into contact with
in the workplace employees, the exposure limits set out in the First
Schedule of the Regulations are not exceeded.
Ensure that all employees exposed to chemicals in the
workplace are protected adequately from exposure to
hazardous substances that may be present in them
using the hierarchy of hazard control methods
Have a Hazard Communication program implemented
at their workplace.
Maintain an inventory of all MSDSs for the chemicals
stored in their workplace
Dispose of all unused, obsolete or expired chemicals in
an environmentally sound manner.
Label appropriately all containers containing chemicals
as indicated in the MSDS for that chemical.
Page 42
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Environmental Management NEMA Formulated to provide for The proposed project has potential to impact on air quality.
and Coordination ( Air Quality prevention, control and abatement Dust and fugitive emissions from transport vehicles during
Standards) Regulations, 2008 - of air pollution to ensure clean and construction and decommissioning phases and petroleum
Draft healthy ambient air fumes during operation phase could impact on air quality.
Building Code Ministry of Local Formulated to provide rules, The Proponent is required to adhere to the rules, guidelines
Government guidelines and standards to be and standards stipulated in the Code during development of
observed during construction. the proposed project
Page 43
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Public Health Act Cap 242 Ministry of Public The Act regulates activities The Act prohibits the Proponent from engaging in activities
Health detrimental to human and that cause environmental nuisance or those that cause
environmental health and safety danger, discomfort or annoyance to inhabitants or is
hazardous to human and environmental health and safety.
The Local Government Act Ministry of Local The Act requires the Proponent to grant the Officers and
(Cap. 265) Government servants of Local Authority access to their premises to
inspect, maintain, alter or repair sewers, drains, pipes,
ventilating shafts or other
The Penal Code (Cap. 63) Judiciary Formulated to define the penal The Code Prohibits the Proponent from:
system in Kenya. It outlines criminal
Voluntarily corrupting or fouling water for public springs
offences and prescribes penalties to or reservoirs, rendering it less fit for its ordinary use
them Making or vitiating the atmosphere in any place to
make it noxious to health of persons/institution in
dwellings or business premises in the neighbourhood
or those passing along public way.
The Occupier Liability Act (Cap The Act Requires the Proponent to ensure that visitors to
34) his premises will be reasonably safe in using the premises
for the purposes for which he is invited or permitted by the
Proponent to be there
Page 44
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Occupational Health and Safety DOSHS Enacted to provide for the health, It requires the Proponent to:
Act, 2007 safety and welfare of persons
undertaking S&H risk assessments,
employed in workplaces, and for
provide notification of accidents, injuries and dangerous
matters incidental thereto and occurrences, etc
connected therewith. Provide first aid facilities at the workplace
provide PPEs to the employees
Legal Notice No. 25: Noise DOSHS Promulgated for work related noise It requires the Proponent to:
Prevention and Control Rules exposures
Comply with the following permissible noise levels :
a. Workplace Noise- 90 dB (A) over an 8-hour TWA
period over 24-hours; and 140 dB (A) peak sound
level at any given time.
b. Community noise level emanating from a
workplace -50 dB(A) during the day; and 45
dB(A) at night.
ensure that any equipment brought to a site in Kenya
for use shall be designed or have built in noise
reduction devices that do not exceed 90 dB(A).
Medically examine those employees that may be
exposed to continuous noise levels of 85 dB (A) as
indicated in Regulation 16. If found unfit, the
Page 45
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Liquefied Petroleum Gas ERC Promulgated for Management of The Regulations requires the Proponent to:
(LPG) Regulations, 2009 LPG Business in Kenya. It covers
Apply for/obtain licence from ERC prior to operating bulk
on import, export, transport,
LPG storage facility. Application for the licence should be
storage, wholesale and retail of
accompanied by the follow:
LPG
EIA Licence issued in accordance with EMCA, 1999
Page 46
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
KS 1938:2006 KEBS/ERC Code of practice for handling, The Standard provides guidelines for:
storage and distribution of LPG in
Design pressure
domestic, commercial and industrial
Fire protection
installations
Construction and initial (production) testing of storage
Part 3: LPG installation involving
vessel
storage vessels of individual water
storage capacity exceeding 500L Filling ratio and volumes of storage vessel
Page 47
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Installation of vaporizers
Page 48
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
NEMA - the principal government authority established under MENR to exercise general
supervision and coordination over all matters relating to the environment in Kenya.
NEC- The apex body under the Act charged with the responsibility of developing the
national environmental policy in Kenya as well as to set annual environmental goals and
objectives.
PCC - formed to investigate environmental complaints against any person, submit their
findings/recommendations to the NEC and to submit periodic reports of its activities to the
NEC.
SERC- established to advise the NEMA on the criteria and procedures for the
measurement of environmental quality in Kenya. Environmental quality relates to air
quality, wastewater quality, waste quality, noise quality, land use quality, etc. Additionally
the SERC is required to recommend to the NEMA minimum environmental quality
standards for all environmental parameters for which subsidiary legislation is or has been
promulgated.
Page 49
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 50
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER FIVE
Several environmental impacts (positive and negative) associated with the proposed project
were identified through the use of experts judgment method. The following section highlights
the impacts anticipated throughout the lifecycle of the proposed project. The associated
impact assessment tables for each impact will be categorized according to project phases,
prior to and post mitigation. Effects of activities are categorized as negative impact and or
positive impact.
Section one of this report presents the methodology used in assessing the potential impacts
of the proposed project. The key impacts identified for the proposed project are highlighted
according to the relevant project phases.
The Firm of Experts utilized precautionary principles to establish the significance of impacts
and their management and mitigation.
The proposed project is anticipated to generate the following impacts, however the
significance of the impacts will range between low to moderate before mitigation and will
further reduce with mitigation measures:
a) soil and Geology Impacts
e) Socioeconomic impacts
During operation phase soil contamination is not anticipated because of the presence of the
concrete paved surface which will prevent any potential contaminant from reaching the
subsurface layers and is thus not assessed. During decommissioning phase, soil
contamination could occur especially with the use of machinery in demolition of the facility.
Page 51
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Construction Phase
Likelihood Consequence Rating
Frequency Frequency Severity of Spatial scope/ Duration
of Activity of Impact Impact Geographical
extent
5 4 1 1 1 Low
Daily likely insignificant site specific One day to negative
one month impact
score 9 3 27
The Contractor shall prepare a hazardous materials and waste management plan. The plan
shall include, but not limited to, measures to prevent: (a) contamination of soils; (b) pollution
of water; (c) and safe siting and storage.
Decommissioning Phase
Mitigation Measures
The Proponent and contractor engaged in the demolition of the facility shall ensure machinery
and vehicles used during demolition are adequately serviced to prevent any oil leakages.
Page 52
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Additionally, the Proponent shall undertake a further survey to identify any contaminated areas
and remediate them accordingly.
During operation phase, soil erosion is not anticipated at the project site because the concrete
surface to be constructed will protect the soil from agents of erosion.
During decommissioning phase, removal of concrete surface will expose the soil to the above
erosion agents.
5 5 Daily 3 1 1 Low
negative
Daily marginal site specific One day to
impact
one month
score 10 5 50
The Proponent and Contractor shall implement soil conservation program described in
section 8.5.1 of this report.
Page 53
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
5 2 Negligible 1 1 Low
negative
Daily Very 1 site specific One day to
impact
seldom one month
score 7 3 21
4 5 Negligible 1 1 Low
negative
Daily Daily 1 site specific One day to
impact
one month
score 10 3 30
Mitigation Measures
The Proponent shall ensure that the site is restored as much as possible to original state. This
shall be accomplished through surfacing of denuded areas and planting of vegetation.
5 2 Negligible 1 1 Low
negative
Daily Very seldom 1 site specific One day to
impact
one month
score 7 3 21
Page 54
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
anticipated as the site will be covered by the proposed project. While during
decommissioning phase, dust emission would be generated from debris and soil resulting
from demolition process.
5 5 1 1 1 Low
negative
Daily Daily insignificant site specific One day to
impact
one month
score 10 3 30
The Proponent and Contractor shall implement dust abatement measures which shall include:
Sprinkling stockpile with water regularly or cover with a membrane to prevent them from
being blown away and keep them for the shortest time possible;
Page 55
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Decommissioning Phase
5 5 1 1 1 Low
negative
Daily Daily insignificant site specific One day to
impact
one month
score 10 3 30
4 3 4 2 4 Medium
low
Life of unlikely harmful site specific Life of
operation operation
score 7 10 70
The Proponent need to develop, implement and monitor environment, health and safety
measures and procedures, including an emergency preparedness and response plan.
4 3 1 2 4 Low
negative
Life of unlikely Non harmful site specific Life of
impact
operation operation
score 7 7 49
Page 56
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
During operation phase exhaust emission from trucks entering and exiting the site will be
source of gaseous pollutants.
5 5 2 1 1 Low
negative
Daily Daily Minor site specific One day
impact
to one
month
score 10 4 40
5 5 1 1 1 Low
negative
Daily Daily Negligible site specific One day
impact
to one
month
score 10 3 30
Page 57
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The construction machinery and vehicles will generate noise of varying magnitude. The
proposed project will utilize machineries such as wheel loading shovel; 30 to 40 Ton tracked
Excavator, Mobile service crane, Dump Truck and Tipper lorry
From the predictions of the specialist study on ambient noise quality measurements it can be
seen that all the above activities are predicted to be largely within the target noise levels,
although highest levels are expected when using pneumatic drills to break hard rock for
foundation when the noise levels would peak at about 68dB (A)
Page 58
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
As will be the case with the construction phase, the sources of noise during decommissioning
phase, will be mainly machinery and vehicles used in demolition of the facility and removing
the materials from the site.
Consequence
Magnitude 2
Geographic extent 1
Duration of impact 1
Total 4
Likelihood
Duration of activity 1
Frequency of impact 1
Total 2
Comment/mitigation:
1. Follow the rules sand regulations set out in the relevant codes of practice and instructions
contained in the Environmental Management Plan (EMP) and construction Environmental
Plan(CEP)
2. Use protective equipment
3. Site the noisy equipment and plant away from occupied building.
4. Maintain equipment and plant.
Mitigated Impact: Noise above 75
dB (A)
Consequence
Magnitude 1
Geographic extent 1
Duration of impact 1
Total 3
Likelihood
Duration of activity 1
Frequency of impact 1
Total 2
Results (Consequence * - 6 (Very low)
Page 59
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Likelihood)
Comment/mitigation
1. Site the power generator away from the occupied building.
2. Maintenance personnel to use ear defenders.
3. Maintain equipment and plant.
Operation phase and decommissioning
Unmitigated Impact: Noise above 85 Significance
dB(A)
Consequence
Magnitude 2
Geographic extent 1
Duration of impact 1
Total 4
Likelihood
Duration of activity 1
Frequency of impact 1
Total 2
Results (Consequence * Likelihood) - 8(very low)
Comment/mitigation:
The Proponent to ensure that the booster pumps to be used during operation phase complies with
national and international noise quality standards. Noise abatement measures will be covered in
the EMP.
Impact with mitigation : Noise
above 85 dB(A)
Consequence
Magnitude 2
Geographic extent 1
Duration of impact 1
Total 4
Likelihood
Duration of activity 1
Frequency of impact 1
Total 2
Results (Consequence * Likelihood) - 8 (very low)
Page 60
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Decommissioning Phase
Consequence
Magnitude 1
Geographic extent 1
Duration of impact 1
Total 3
Likelihood
Duration of activity 2
Frequency of impact 1
Total 3
Comment/mitigation:
The Proponent to ensure that the machinery and vehicles used during demolition comply
with Noise Quality Standards. Noise abetment measures will be included in construction
management programme.
Consequence
Magnitude 1
Geographic extent 1
Duration of impact 1
Total 3
Likelihood
Duration of activity 1
Frequency of impact 1
Total 2
Page 61
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Several wastes are anticipated to be generated throughout the project cycle (Section 2 of this
report provides a description of the waste to be generated). During construction phase,
wastes anticipated from demolition and construction activities will: concrete waste, asbestos
sheets from the existing buildings, excavated soil, metal and timber cuttings among others.
These wastes have potential to cause adverse impacts; for example asbestos materials are
known to cause asbestosis, a chronic inflammatory and fibrotic medical condition affecting the
tissue of the lungs caused by the inhalation and retention of asbestos fibers.
During operation phase, the expected waste from the project will include domestic and
medical waste from the clinic. Medical wastes are potentially dangerous and present a high
risk of infection to the general population and to the staff.
Whereas during decommissioning phase, demolition waste generated will be mainly concrete
boulders, and scrap metals.
Mitigation Measures
The Contractor in collaboration with the Proponent will prepare and maintain site waste
management plan which estimate the quantity of each type of waste expected to be produced
and track their recovery and destination throughout the construction phase of the project.
Waste streams could be recovered, segregated and either re-used on site (e.g. crushed
concrete aggregate) or disposed offsite in line with the Proponents Go Green Initiative.
Page 62
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
one month
score 9 5 45
Operation phase
Likelihood Consequence Rating
Frequency Frequency of Benefit/Severity of Spatial Duration
of Activity Impact Impact scope/Geographical
extent
4 4 2 2 4 Medium
Life Life Minor site specific Life of low
operation operation operation
score 8 8 64
Mitigation Measures
The Proponent will manage waste in accordance with the existing procedures and relevant
legislations. Waste streams could be recovered, segregated and either re-used on site (e.g.
crushed concrete aggregate) or disposed offsite in line with the Proponents Go Green
Initiative. Medical waste will be collected disposed offsite by NEMA approved waste handler.
Mitigation Measures
The Contractor selected for undertake demolition work will in collaboration with the Proponent
will prepare and maintain site waste management plan which estimate the quantity of each
type of waste expected to be produced and track their recovery and destination throughout
the decommissioning phase of the project. Waste streams could be recovered, segregated
Page 63
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
and either re-used on site (e.g. crushed concrete aggregate) or disposed offsite in line with
the Proponents Go Green Initiative.
The potential occupational health and safety impacts anticipated for operation phase include:
injuries to workers from preventive and corrective maintenance especially of electrical
equipment, work at height especially renewing coat of paint on the roofs and walls and
handling of medical wastes.
During decommissioning phase, the potential H&S risks include hazards of falling objects;
work at height hazards, injuries from operating tools and equipment.
score 10 6 60
Page 64
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Mitigation Measures
The Proponent is recommended to enforce the existing H&S operation procedures for
minimizing potential health and safety impacts. During construction phase, the Proponent is
recommended to ensure that tool box talks are done every day. Toolbox talks address actual
and anticipated safety concerns for scheduled project work. The talks provide an opportunity
to relate specific safety concerns with the jobs to be performed.
Page 65
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
4 5 1 1 4 Medium-low
score 9 6 54
The proposed project could be of great public concern especially in the event of major
disaster such as major fire outbreak and explosion caused by third parties. The product to be
stored is highly flammable hence incidents fire or explosions can be detrimental to the public.
The impact significance related to public safety is likely to be low during the rehabilitation and
closure of the facility.
Construction phase
Likelihood
Duration of activity 4
Page 66
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Frequency of impact 4
Total 8
Comment/mitigation:
Mitigation measures for the potential Occupational Health and Safety impacts will be
covered in the construction Safety Management Plan. The implementation of the
proposed project to be done in accordance to the OSHA 2007 and any other relevant H&S
legislation
Consequence
Magnitude 1
Geographic extent 1
Duration of impact 2
Total 4
Likelihood
Duration of activity 2
Frequency of impact 1
Total 3
Operation Phase
Impact without mitigation: Risk of large Significance
scale incident
Consequence
Magnitude 5
Geographic extent 4
Duration of impact 4
Total 13
Likelihood
Duration of activity 4
Frequency of impact 3
Total 7
Results (Consequence * Likelihood) - 91( medium high)
Comment/mitigation:
Page 67
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Mitigation measures for impacts resulting from public safety is covered in the emergency
management and response plan presented in the EMP.
5.2.6 Socioeconomic
The proposed project site area consists mainly of light industries. The proposed project is
therefore compatible to the existing as well as future land-uses. Since the proposed project
will not conflict with the existing and perhaps future developments, impacts were therefore not
assessed.
The proposed project will generate job opportunities (skilled and unskilled Labour) during
construction and operation phases.
It is anticipated that proposed project will provide opportunities for local employment and
service provision, such as the use of local transport companies and sourcing of some
construction materials locally. There also likely to be trickledown effect results from the
employment opportunities as well as services provided by the facility.
Constructions, Operations
Page 68
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
3 3 4 4 4
Results: MEDIUM HIGH (+ 80)
Mitigation/Comments: Communication and information programs should be used to manage
expectations and target local service providers including those registered through the Public
Participation process. Management and enhancement measures for local employment to be included
in Labour and human resources plan. Local authorities and employment hubs should be consulted
when recruiting local workers and service providers.
The proposed project is expected to improve the security situation in the area in that the
project will employ security guards, install security lights and installing alarm systems.
Due to the proposed project there will be an influx of people searching for jobs. An increase in
economic activities will increase the demand for housing, communication transport and
financial services will significantly increase and thus present a likelihood of increasing the
land values.
Page 69
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
In the operational phase, the BAT K ltd perceived that there will be increased LPG supply.
Operations Phase
Benefits without enhancement: LPG Provision
Severity Spatial Duration of Duration of Frequency of
scope impact activity impact
2 5 4 4 4
Result: MEDIUM HIGH (+ 88 )
Benefits with enhancements
Severity Spatial Duration of Duration of Frequency of
scope impact activity impact
3 4 4 5 4
Results: MEDIUM- HIGH(+ 99 )
Mitigation/Comments: The proposed project will ensure that there is plenty of LPG which
will meet the increasing demand for LPG at the factory.
5.2.7 Cumulative impacts
Cumulative impacts are impacts of an activity that in themselves may not become significant
but may become significant when added to the existing and potential impacts eventuating
from similar or diverse activities or undertakings in the area.
The concrete paving will affect permeability of storm water into the subsurface and
underground water.
The soil once excavated and moved within the site loses its original physical and chemical
composition, structure, arrangement of soil horizons and the transition between those
horizons. These changes cumulatively alter the biological, physical and chemical properties
of the soil and consequently the reaction patterns with pollutants.
Page 70
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Without With mitigation Without mitigation With mitigation Without mitigation With mitigation
mitigation
Air Quality
negative impact negative impact Not anticipated Not anticipated negative impact negative impact
Fugitive Emission Very low Very low Low Low Very low Very low
negative impact Negative impact Negative impact Negative impact Negative impact Negative impact
Occupational Health Low medium Very low Very low Very low Very low Very low
and Safety negative impact negative impact negative impact negative impact negative impact negative impact
Risk of large incident low medium Very low low medium Low
fire explosion and fire negative impact negative impact negative impact Negative impact Not anticipated Not anticipated
outbreak
Very low Very low Low Low Very low Very low
negative impact Negative impact Negative impact Negative impact Negative impact Negative impact
Page 71
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Socioeconomic
Employment low Medium High low Medium High Very low High
Positive impact Positive impact Positive impact Positive impact Positive impact Positive impact
Page 72
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
CHAPTER SIX
6 ANALYSIS OF ALTERNATIVES
The following alternative aspects were considered for the proposed project: No Project
Scenario, design and site alternative. Evaluation of the alternatives is governed by a rule of
reason, which requires the evaluation of alternatives necessary to permit a reasoned
choice.
The no Project Scenario is where the proposed project should not be undertaken at all. The
site will remain as it is; covered by grass and few ornamental trees and it will imply that
anticipated benefits from the project would not be realized and similarly the potential adverse
impacts associated with the project will not be experienced. The Project is part of the BAT
Kenya Limited Green Initiative which is geared towards reducing impacts of their operations
on the environment. By implementing the project, the Proponent will enable BAT Kenya
limited to phase out diesel powered forklifts and replace them with LPG powered ones which
are environmentally friendly. Propane-powered forklifts produce significantly less emissions in
the way of carbon monoxide, nitrogen oxide, hydrocarbon, and particulate matter than
comparable gasoline- or diesel-powered forklifts. The No Project Scenario is therefore not
considered as a viable option.
The Proponent has only one proposed site for the storage and distribution of Liquefied
Petroleum Gas. The site is located at Premises of BAT, who are the sole users of the product.
This will also go further in reducing logistical constraints of transporting LPG cylinders to the
site on a daily basis.
Additionally, the proposed site is ideal because it is located away from the factory where the
main manufacturing operations occur and hence would not compromise the safety of the
factory.
The Proponent has proposed to install a 5 ton above ground LPG tank to substitute the
current practice of daily supply of gas in small cylinders.
The proposed design will largely improve the safety of storage and handling of LPG at the
factory and will create a steady supply/stock of LPG gas to BAT. In comparison to mounded
LPG storage tanks described under section 6.3.2 below, the proposed option has smaller
footprint.
Page 73
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
LPG can also be stored in a Mounded pressurised bullet which offer a safer option and
eliminates the possibility of BLEVE. The cover of the mound protects the vessel from fire
engulfment, radiation from a fire in close proximity and acts of sabotage, terrorism or
vandalism. The catastrophic failure mode of a cylindrical vessel is also such that it can be
directed away from any processing or occupied areas. Mounded bullet type storage is also
used where visual impact is important. A typical mounded bullet is depicted in Figure 2.
The disadvantage of mounded bullet storage over spheres is the plot space required. The
bullets themselves have a larger footprint and the space required for mounding adds
additional cost. GLT occupies an area of approximately 11.89 hectares. The buildings
including access roads onsite occupy an area of approximately 7.16 hectares while
undeveloped area and foot ball pitch are 2.05 and 1.68 hectares, respectively. Opting for
mounded bullets storage will drastically diminish the available undeveloped space for future
development including expansion of the existing operations.
LPG can also be stored in LPG sphere tank, shown by figure 3. The sphere offers the
maximum volume for the least surface area and the required thickness of a sphere is one-half
the thickness of a cylinder of the same diameter. However, they are less safer since it weight
is not distributed evenly on a larger area thus increasing chances of collapse as compared to
LPG tanks described in the previous sections, especially in areas prone to earth quakes.
Page 74
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
The proposed facility will handle Liquefied Petroleum Gas. The amount of LPG stored will be
dependent on the requirements of BAT (K) Ltd. The input alternatives are thus dictated by the
forklift operations at BAT (K). The design does not allow storage of other products other than
Liquefied Petroleum Gas.
6.5 Conclusion
On the basis of the above considerations, the Firm of Experts concludes that the proposed
project satisfies the overall economic, technical, environmental considerations. BAT K Ltd will
have adequate stock of LPG; will not incur extra cost of land acquisition and will reduce the
cost of daily transportation of LPG to the site.
Finally, the Firm of Experts believes that the No-go option does not compete with the
benefits of proceeding with the project.
Page 75
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
CHAPTER SEVEN
The objectives of public participation in an EIA are to provide sufficient and accessible
information to Interested and Affected Parties (I&APs) in an objective manner to assist them
to identify issues of concern, and provide suggestions for enhanced benefits and alternatives.
The Firm of Expert consulted the neighbors of the Proponent. The responses from the
stakeholders were captured using the public stakeholder checklist while others were recorded
in the field note book.
Copies of completed checklists are appended at the end of this report (Appendix 6)
Generally, all the stakeholders consulted at the project site have no objection to the
establishment of proposed projects. They observed that the proposed project will not
generate any adverse environmental impacts. The responses for concerns raised by the
respondents are provided in Table 7 below.
Page 76
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Vas Auto Centre Ltd 020 650283/4 Neighbor -Vas Auto Centre Ltd
No Name Contacts
1
Martin Kamau Tel.02002561
2
Jackson Mwangi Irungu P.O. Box 78449-00507, Nairobi
3
Mathew Kariuki Tel.0724423593
4
Ahmed A Tel. 0720585801
5
Jackline Tel. 0713133162
Socio-economic issues
Page 77
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Environmental impacts
All the respondents were of the opinion that the project will have minimal or rather no impacts
on air, noise levels, flora and fauna, water and soil.
The respondents were of the opinion that during the construction phase workers will be at risk
of
Working at heights
Falling objects;
Exposure to dust and fuel fumes;
Fire risks
Noise
Ergonomic issues
Air pollution in the event of leakage of LPG
Members interviewed were asked to propose mitigations measures for the mentioned EHS
Issues. They proposed the following to be undertaken during the construction and operation
phases:
Continuous risk assessments;
Inducting employees on safety and environment before commencing work;
Use of permit to work systems;
Use of appropriate and inspected tools,
Barricading the area and use of warning signs;
Control of access of the project site;
Operations to be conducted by approved operators;
Have a preventive maintenance programme of the LPG Tank.
Page 78
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
CHAPTER EIGHT
This section presents the environmental management plan (EMP) for the proposed project.
The EMP specifies the mitigation and management measures which the Proponent will
undertake and shows how the Project will mobilize organizational capacity and resources to
implement these measures.
The EMP covers information on the management and/or mitigation measures that will be
taken into consideration to address impacts in respect of the following project phases: design,
construction, operation and decommissioning.
The proposed EMP will be the responsibility of the HSE department of the BAT Kenya
Limited; however, it will have links with other departments such as operation and
maintenance. Table 9 presents the range of approaches that will be used to manage potential
impacts of the proposed project.
The environment, health and safety management cycle has five broad components:
Planning and design
Project implementation (covering the construction and operation phases);
Checking and corrective action; and
Management review
Page 79
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
The Proponent and BAT Kenya Limited will utilize the existing arrangements in the
implementation of the EMP during planning and design, construction, operation and
decommissioning/closure. The Proponent is accountable for ensuring that resources are made
available to effectively implement the EMP and necessary environmental management
measures arising from the project. Figure 4 shows the proposed organizational structure for
the proposed Project, showing the reporting lines of staff to be involved in environmental
management of the project. The Project Manager will take responsibility for the day to day
running of the project and will oversee the detail of implementation of the EMP during
construction phase while during operational and decommissioning phases, will be managed by
the Factory Manager. The two managers will collaborate with the QEHS Manager of TKL and
HSE Manager of BAT Kenya Limited in implementation of the EMP.
TKL BAT
Construction Phase
HSE Manager
Project Manager QHSE Manager
HSE Executive
Contractor EIA/EA Expert
Construction Manager
HSE Manager
HSE Executive
Decommissioning
Project Manager BAT
Phase
Page 80
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Table 10 provides details on the functions of each staff member. The environmental, health
and safety management of the project will be the responsibility of the Health, Safety and
Environment (HSE) Manager who reports directly to the East and Central Africa Operations
Manager. The HSE Manager will be supported by EHS Executive.
Environmental monitoring will be undertaken by the EHS Executive, and independent audits
of environmental performance will be conducted from time to time by independent NEMA
approved environmental expert.
Position Responsibility
Page 81
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Carry out statutory health and safety audit of the GLT including the
DOSHS Approved H&S
Advisor LPG facility
Carry out statutory Fire safety audit of the GLT including the LPG
DOSHS Approved Fire
Auditor facility
The Proponent will commit contractors to meeting the relevant responsibilities by means of
specific conditions in the contracts of appointment. Where there is concern over the capacity
of contractors to undertake specific activities according to the system stated here, the
Proponent will provide additional training to improve the capacity of the contractors.
Activities of contractors will be overseen by the Project Manager and staff as appropriate.
The Proponent will put in place the following construction phase contractor arrangements to
support EMP implementation:
Contractors will have certain key environmental line functions included in their job
descriptions and performance criteria. Critical among these is the Construction Manager.
Page 82
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Regular (at least monthly) liaison between the Construction Manager, the Project
Manager and the HSE Manager and his/her team must be carried out. At the
commencement of the construction phase, weekly meetings should occur. Meetings
should review implementation of EMP requirements, highlight issues of concern, identify
required interventions and prescribe corrective actions and schedule, and allocate budget
and appoint responsible parties. The Factory Manager should receive minutes of
meetings and should be invited to attend meetings at least once in a month.
A code of practice for construction teams will be prepared and implemented. This code
will guide the management and behaviour of construction teams. The code will include
items relating to health safety and community relations.
Contracts will be key tools in managing many potential negative impacts such as transport
related incidents. They will specify required environmental and social practices.
To determine the effectiveness of the EMP, the Proponent will use a series of internal
and external inspections and audits:
Internal environmental, health and safety inspections will be carried out once every week
by EHS Executive;
Page 83
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
incident and will be subject to the Proponents existing incident reporting and handling
procedures
EHS Manager, will arrange for initial and subsequent environmental audits and will
provide relevant information required by relevant authorities including NEMA. The audit
will be carried out in accordance with EMCA, 1999 and its subsidiary legislation, EIA/EA
Regulations, 2003. Any negative findings arising from the audits will be addressed
accordingly.
Accidents or near misses that did or could result in injury to staff, visitors to site or the
surrounding communities
All incidents will be formally recorded and noted in the General Register in accordance with
requirements of OSHA 2007.
Checking and if necessary implementing corrective action, to ensure that required EMP
management activities are being implemented and desired outcomes are achieved. As
such this component includes four key activities namely:
Monitoring selected environmental quality variables as defined in the objectives and
targets.
Ongoing inspections of the operational controls and general state of the operations.
Internal audits to assess the robustness of the EMP or to focus on a particular
performance issue.
External audits to provide independent verification of the efficacy of the EMP.
There are several mechanisms for implementing corrective action, both during the
construction and operational phases. The main mechanisms to address transgressions
include verbal instruction (in the event of minor transgressions from established
procedure, usually following a site inspection); written instruction (identifying source(s) of
problems, usually following an audit) and contract notice (following possible breach of
contract).
Page 84
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
8.2.8 Reporting
The findings of all of the above will be structured into instructive reporting that provides
information to all required parties on EHS performance, together with clearly defined
corrective action where this is seen to be required. Both the monitoring and inspections
are to be reported continuously.
The Proponent will organize for formal management review at defined intervals both
during the construction and operational phases. The purpose of the management review
is for senior project management to review the environmental management performance
during the preceding period and to propose measures for improving that performance in
the spirit of continuous improvement.
8.2.10 Liaison
Throughout the project cycle, the Proponent will liaise with authorities especially NEMA
Kenya to ensure ongoing feedback on the environment performance of the project.
The EMP addresses the planning and design, pre-construction and construction,
operational and closure phases of the proposed project.
In the case of the proposed Project the environmental aspects and potential impacts will
mainly emanate from the site preparation and construction activities.
The proposed project will comprise of 2 ton LPG tank and filling station. Detail description of
the project is provided in Chapter 2 of this report.
Page 85
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Impacts have been described and rated in terms of their potential significance. The
management measures presented in this EMP have been developed in response to these
impacts. Anticipated positive impacts/benefits from the preconstruction and construction,
operation and closure of the proposed projects include the following: creation of employment
creation of market for supply of goods and services and contribute to BATs green initiative as
LPG propelled forklifts are more eco-friendly than the diesel propelled ones.
The anticipated negative impacts which could arise with mitigation during preconstruction
and construction, operation and closure of the proposed facility include the following:
Impact on air quality emanating from decreased air quality due to dust emission; fugitive
emissions and air pollution from incidents
Health and safety impacts; occupational health and safety and public safety
This study identified potential impacts of the proposed project. The subsequent sections
provide description of the management plans and programmes within which
management and mitigation measures will be implemented. The actions and activities for
decommissioning phase are dealt with in the rehabilitation and closure plan which also
addresses the mitigation measures that will be ongoing once operations have ceased.
Table 11 presents the EMP for the proposed project. It covers on the proposed
management and mitigation measures for the identified impacts. The information
presented addresses the dual objective of the EMP, namely to fully disclose the
Page 86
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
The EMP will put in place measures to avoid and mitigate impacts and optimize benefits
arising from activities during construction phase of the project. The principal focus of project
management for construction phase will include:
Personnel and contractor management
Conduct and site management
Landowner relations
Maintenance of complaints register
Emergency preparedness; and
Management and mitigation of impacts such as noise, dust, safety and pollution.
The operation phase of the proposed project will be mainly receipt, storage and delivery of
LPG to the customers.
For the purpose of the EMP there are three principal mechanisms for the implementation of
management and mitigation measures:
Facilities these can be either specific facilities that have a dedicated HSE management
functions or additions to facilities that are central to the proposed project activity.
Page 87
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
The mechanisms for effecting the EMP requirements are collectively called operational
controls. Such operational controls require that a responsible party, a budget and in
implementation schedule are specified and allocated, to further enable and facilitate
implementation. In addition, roles and responsibilities need to be defined for the EMP. These
roles include dedicated HSE management roles as well as the HSE responsibilities of other
company personnel (ultimately all personnel will have an HSE role). To facilitate coordinated
and purposeful implementation, the EMP management and mitigation measures are grouped
in programmes and plans.
Checking and if necessary implementing corrective action, form the fourth component of the
EMP management cycle. They ensure that:
Ongoing inspections of the operational controls and general state of the operations.
8.4.5 Monitoring
The environmental variables that are to be monitored are described in the description of the
baseline environment. Monitoring results must be structured and presented for review on an
ongoing basis so that if objectives and targets are not met, corrective action can be taken.
An ongoing but pragmatic inspections regime will be developed that allows for potential HSE
transgressions to be identified proactively, so that mitigation can be quickly and effectively
implemented.
Where the monitoring data and the inspection reports highlights problems, an internal audit
can be used to ascertain the source of the problem and to define action to prevent its
recurrence. The three key areas for audit are facilities (are they operating properly?), project
procedures (are they properly designed and implemented?) and finally, and perhaps most
importantly Contractors HSE performance.
Page 88
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
There are several mechanisms for implementing corrective action, both during the
construction and operational phases. The main mechanisms to address transgressions
include verbal instruction (in the event of minor transgressions from established procedure,
usually following a site inspection); written instruction (identifying source/s of problems,
usually following an audit) and contract notice (following possible breach of contract).
8.4.9 Reporting
The findings of all of the above will be structured into instructive reporting that provides
information to all required parties on HSE performance, together with clearly defined
corrective action where this seen to be required. Both the monitoring and inspections are
reported on continuously. Within the reporting structure it is necessary to create a review
function that continuously assesses the reporting and prescribes any necessary corrective
action. Reporting will include the provision of information on the HSE performance to external
stakeholders and surrounding communities.
The final component of the EMP management cycle is a formal management review that
takes place at defined intervals both during the construction and operational phases. The
purpose of the management review is for senior project management to review the
environmental management performance during the preceding period and to propose
measures for improving that performance in the spirit of continuous improvement.
8.4.11 Liaison
Throughout the project, ongoing liaison will be maintained with authorities and communities
alike to ensure the following:
Advance warning of any project activities that may have some adverse impact on
surrounding communities, e.g. clearing of construction site, installation of storage tanks;
and
This section presents mitigation and management measures for the identified potential
impacts of the proposed project. The section also provides description of the management
plans and programmes within which management and mitigation measures will be
implemented. The actions and activities for decommissioning phase are dealt with in the
rehabilitation and closure plan which also addresses the mitigation measures that will be
ongoing once operations have ceased.
Page 89
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Table 11 presents the EMP for the proposed project. It covers on the proposed management
and mitigation measures for the identified impacts. This information presented addresses the
dual objective of the EMP, namely to fully disclose the commitments to be undertaken by the
Proponent to provide managers and staff with a clear framework for EMP implementation.
Page 90
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Table 11: Mitigation and Management measures for the identified Impacts
Aspect Impact Mitigation Objective Performance Monitoring Timing of Cost Responsibility
Measure/Enhancement Indicators or Mitigation/ Estimate
measures Acceptance Criteria Enhancement
Measures
Air Degradation of Relevant legislative and To achieve air No receipt of air Non-compliance Throughout project No Proponent,
Quality Air Quality Kenya Standard design quality quality-related and incident cycle significant Contractor and
material User (BAT
requirements will be objectives of complaints from reporting will be additional Kenya Limited)
adhered to where the Draft Air neighbouring closed out t to cost
Page 91
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Audit of vehicle
servicing records.
Noise Noise Pollution Construction activities To minimise the No noise related Landholder Construction, 100,000 Proponent and
Quality from Incidents Operation and monitoring User
Page 92
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Page 93
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Documentation
of consultation
and planning for
atypically noisy
events.
Waste Pollution Develop strategies To minimise No evidence of Housekeeping Construction, No material Proponent,
additional
from waste (waste management any negative uncontrolled checks to ensure operation and Contractor and
costs
generation Decommissioning are User
plan) for management of impacts waste (i.e., not in waste is being phases anticipated
specific waste streams associated with appropriate stored correctly and above
general
prior to construction waste containers) at no litter is budgets for
responsibiliti
phase. generation above ground occurring.
es of EHS
through facilities during Manager for
Stockpile and salvage Regular audits and the
adoption of the inspections. implementati
reusable and recyclable reviews will be
on of the
waste
wastes, such as timber Record of undertaken, and plan.
Page 94
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Page 95
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Page 96
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Soil Degradation of Minimising the areas to To avoid or Documentation Non-compliance Construction phase No material Proponent and
additional
Quality soil be excavated of regular and incident Contractor
minimise soil costs
are
disturbance/conta servicing/mainte reporting will be
Re-vegetating disturbed anticipated
mination. nance of all closed out by senior above
areas once construction general
vehicles and management to budgets for
and demolition works are
responsibiliti
plant ensure prompt
completed; during es of EHS
components. rectification and Manager for
construction and
change the
decommissioning The extend of implementati
management as on of the
phases respectively; excavated area
required. plan.
Ensuring that
Neighbours
vehicles/equipment used
complaints will be
during construction and
recorded and
decommissioning
closed out.
phases are serviced
regularly. Regular reporting
and inspections will
Page 97
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Audit of vehicle
servicing records.
Water Degradation Develop strategies for To minimise any No evidence of Housekeeping Construction, No material Proponent,
Quality of water negative impacts operation and additional Contractor and
management of water uncontrolled checks to ensure
quality costs
on water decommissioning are User
resources. waste (i.e., not in waste is being
resources during anticipated
construction, appropriate stored correctly and
Regular checking and above
operation and containers) at no litter is general
maintenance of all plant budgets for
decommissionin above ground occurring.
and machinery to g phases. responsibili
facilities during ties of EHS
minimize the risk of fuel Regular audits and
inspections. Manager
or lubricant leakages reviews will be for the
Record of undertaken, and implementa
Storing hydrocarbons,
regulated waste recommendations tion of the
fuels, lubricants and plan.
disposal. and corrective
chemicals to be used in
actions shall be
bunded and lockable oil Number of
implemented.
storage tanks, with Waste Spill
hoses and gauges kept Reports. Waste will be
within the bund. tracked and
appropriately
Leaving vegetation in
Page 98
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Stockpiles to be kept
away from watercourses
Health Occupational Development and To minimise Occupational Workplace - Construction, No material - Proponent and
additional
and health and implementation of impacts on health injury and illness inspection to operation and Contractor
costs
Safety safety impacts decommissioning are
occupational health and and safety during incidents. ensure phases anticipated
safety plan. The Plan will construction, above
Page 99
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Socio- Creation of During construction Maximize impacts Construction, No additional- Proponent, and
Kenya Labour Laws Compliance with-
economic employment phase, the Contractor on local economy operation and cost is Contractor
Page 100
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Page 101
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
Page 102
ENVIRONMENTAL IMPACT ASSESSMENT PROJECT REPORT 2013
This section presents the programmes for managing the identified impacts. It is worth noting
that the use of management programmes to manage the impacts is necessitated by the fact
that most of the mitigation measures cannot be implemented as discrete, isolated actions
because there are spatial, temporal and casual interactions among impacts. The programmes
recommended for managing the potential impacts of the proposed project include:
The aim of this programme is to ensure that air quality is maintained through construction, as
well as operation phases. The air quality management programme includes the following:
Dust management
Emissions
The Contractor shall ensure that the construction machinery and equipment are
appropriate and fit to prevent fugitive emissions, as per national standards or international
practices. The Proponent shall ensure the regular maintenance of this equipment.
A maintenance plan for the construction machinery and vehicles shall be implemented to
prevent excessive emissions during the construction phase of the project.
Page 103
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
This programme aims to ensure that noise generated by construction and operation
activities is kept to a minimum and adheres to relevant noise standards. The noise
management programme includes the following:
The Contractor shall ensure that construction activities are limited to working hours (i.e.
between 06h 00 and me 9h 00 daily) from Monday to Saturday, or as required in terms of
legislation and/or negotiated with local landowners.
Noise generating equipment will be designed to control and dampen noise emissions,
and will be located at a distance far enough from the nearest noise sensitive
development, to ensure that the increase in ambient noise level will comply with ISO
standards.
Landowners, residents and public shall be able to register their complaints and concerns
about noise through complaints register set up prior to the commencement of construction
activities. These public complaints should be responded to as a matter of urgency and
where possible measures must be taken to minimize the noise
The aim of this programme is to ensure that the Safety and Health of the employees quality is
maintained through construction, as well as operation phases. The OHS management
programme includes the following: Undertaking S&H risk assessments, S&H audits, Provision
of adequate and appropriate firefighting equipment, Provision of Personal Protective
Equipment to the workers and Issuing of work permit systems for hot jobs at the site.
8.7.1 Overview
The following management plans will be implemented during construction, operation, and
decommissioning phase of the proposed project:
The construction management plan for the proposed project shall include the following:
Page 104
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Contractor shall comply with all applicable laws, regulations, permit and approval
conditions and requirements relevant to the storage, use, and proper disposal of
hazardous materials.
The Contractor shall manage all hazardous materials and waste in a safe and responsible
manner, and shall prevent contamination of soils, pollution of water and/ or harm to
people or animals as a result of the use of these materials.
The Contractor shall prepare a hazardous materials and waste management plan for
inclusion in the site specific environmental plan to be submitted to the Proponent prior to
establishment on site. The plan shall include, but not limited to, measures to prevent: (a)
safe siting and storage;
The contractor shall place on-site tools and equipment, such as generators, compressors
on bermed impermeable sheeting to prevent oil spills/leaks from causing subsurface
contamination.
The contractor shall ensure oil spills/leaks are prevented or minimized. This can be
achieved through: instructing employees not to overfill diesel bowsers and equipment
tanks; regular auditing to verify that no leaking or defective equipment is brought/used
onsite; any oils or lubricants discharged during servicing of the machinery or vehicles are
contained in dry trays or other appropriate containment measures.
The Contractor shall ensure that fueling and repairs are carried out by trained personnel
familiar with spill containment and clean-up procedures.
The Contractor shall ensure that all the employees working onsite are trained on good
housekeeping practices.
The contractor shall prevent littering and the random discard of any solid waste on or
around the construction site
The Contractor to determine safe traveling speeds for the construction site and ensure
that restrictions are enforced.
Emergency Preparedness
The Contractor shall develop an emergency plan that will enable rapid and effective
response to all types of environmental emergencies in accordance with recognized
national and international standards. The emergency plan shall include establishment of a
network of communication between the Contractor and emergency services including
police, ambulance services, and fire brigades among others.
Page 105
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Contractor shall test emergency preparedness with drill operations and shall review
drills, conduct mock emergencies and remedy shortcomings to ensure a high level of
emergency readiness to deal with environmental and third party incidents.
The Contractor shall take all necessary precautions to prevent fires caused either
deliberately or accidentally during construction process.
The Contractor shall prepare a fire prevention and fire emergency plan as a part of the
Environmental Plan to be submitted to BAT Kenya Ltd.
The Contractor shall provide adequate fire fighting appliances at specified localities on
the worksite to meet any emergency resulting from ignition of a fire.
The Contractor shall ensure that hot work is prohibited under specified meteorological
conditions with high fire risks and that appropriate and adequate firefighting equipment
would be required to be on standby at all times where hot work is being carried out.
The Contractor shall institute appropriate measures to minimize or avoid air quality
impacts. This can be achieved through formulation of air quality management plan.
The Contractor to minimize/control emission of dust due to traffic movement and wind
erosion of stockpile material and exposed soil.
The Contractor to mitigate emissions of gases vapours and odours by conducting initial
risk assessment and the installation of procedures to control the risk.
The Contractor to ensure that all equipment used and all facilities erected on site are
designed and operated to control the emission of smoke, dust, fumes and any other air
impurity into the atmosphere.
The noise management programme is geared towards minimizing the amount of noise
generated by the construction and operation activities as well ensure adherence to the
relevant noise standards. The noise management programme includes the following:
The Contractor shall comply with the legal requirements for the management of noise
impact specified in the recently promulgated noise quality regulations.
The Contractor shall formulate noise management plan for minimizing the generation of
noise and vibration from construction activities occurring on site and its impact on
surrounding residents, businesses and workers.
Page 106
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Contractor shall respect the property and rights of neighboring landowners and
occupiers at all times and shall treat all persons with deliberate courtesy.
The Contractor shall respect any special agreements between the Proponent and the
neighbors
Complaints register
The Contractor shall establish and maintain a register for periodic review by the Proponent
that logs all the complaints raised by the neighbors or the general public about construction
activities. The register shall be regularly updated and records maintained including the name
of the complainant, his/her domicile and contact details, the nature of the complaint and any
action taken to rectify the problem.
Health management
The Contractor shall comply with all relevant legislative requirements governing worker
health and safety (e.g. OSHA 2007 and its subsidiary legislations).
The Contractor shall prepare and implement a programme to minimize diseases likely to
be contracted by the construction workers as a result of the proposed project such as HIV
Aids.
The CCP for the proposed project shall cover on the following:
Control of access
The contractor shall ensure that the construction is not accessed by authorized persons.
The contractor shall store topsoil excavated from the site in a wind row or stockpile which
shall be discernibly separate from wind rows or stockpiles of any other excavated
materials.
Top soil shall be protected from any contaminant that might impact on vegetation.
The Contractor shall temporarily stockpile topsoil in a location that will minimize any loss
due to erosion or mixing with other material.
The Contractor shall ensure that topsoil is stockpiled in a manner and for a period of time
that does not result in deterioration in its plant support capacity.
The Contractor shall, as far as possible, source all material needed to construct the
proposed project from the licensed mines
Page 107
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
In instances where materials are to be obtained from a new borrow area; the Contractor
shall comply with relevant legislations.
The Contractor shall prepare a method statement including plans, detailing the expected
quantity of excavation, temporary and permanent drainage control, the final contouring of
the borrow pit and the proposed method of rehabilitation.
Rehabilitation
After completion of construction activities, the Contractor shall clear the site of
construction materials and dispose wastes in appropriate disposal sites.
The Contractor shall remove all temporary works on the construction site and grow grass
on the sloppy areas where retaining wall will not be constructed to control soil erosion
Wherever possible, give priority to qualified local people when hiring employees.
The workplace health and safety plan to be implemented by Total, BAT and Contractor shall
include the following key measures:
All relevant national legislation, including the OSHA 2007 and related regulations, shall be
adhered to ensure that health and safety of proximate communities and the public at
large are not threatened during construction and operational phases of the Project.
the Proponent shall ensure workplace health and safety during the operational phase of
the facility
Health and safety performance will be continuously monitored and procedures reviewed
with the aim of eliminating risk as far as reasonably practicable.
The community health and safety plan to be implemented by the Contractor, Total K Ltd and
BAT K Ltd shall include:
Adherence to OSHA 2007 Act and its subsidiary legislations to ensure that health and
safety of immediate neighbors and the public is not threatened.
The Contractor to ensure that construction work is undertaken in manner not likely to
pose risks to community health and safety.
Page 108
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Total (K) Ltd and BAT (K) Ltd to create awareness among the neighbors on the
community safety procedures.
The Proponent shall rollout and implement their documented emergency response plan at the
completed footprint. The EMRP shall include:
The Proponent shall implement a community health and safety plan which shall include the
following measures:
BAT Kenya Limited will compile a comprehensive safety emergency management plan
(SEMP) for the facility. The SEMP will cover the following aspects:
a) Kenyas Safety regulations
b) Scope of the SEMP
c) Notification of local authorities
d) Details of the facilitys system
e) Aim of the SEMP
f) Objectives of SEMP
g) Roles and responsibilities in the event of an emergency
h) Information requirements in the event of an emergency
i) Evacuation of people
j) The role of local communities
k) Regular testing of the SEMP
l) Planning for the eventuality of failure on the facility
m) Causes of the facilitys failure
Page 109
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Proponent shall develop rehabilitation and decommissioning plan in conjunction with
relevant stakeholders at least one year before the end of facilitys operations.
The Proponent shall investigate practical options for closure of the facility at least one
year before decommissioning and submit a report to relevant authorities NEMA included.
Decommissioning
The Proponent shall take into consideration the health and safety of personnel,
contractors, neighbors and the public during the planning and implementation of the
demolition process.
The Proponent shall undertake a further survey to identify any contaminated areas
remediate them accordingly.
Post Closure
The Proponent shall ensure that the facilitys site is free of impacts associated with the
abandonment/closure.
The Proponent shall develop, rollout and implement a monitoring plan that includes:
b) Outline of how land improvement and future land use will be affected by he past operation
and decommissioning of the LPG tank.
8.8 Monitoring
The proposed programmes and plans will be subjected to monitoring. Monitoring will have two
elements: routine monitoring against standards or performance criteria; and periodic review or
evaluation. Monitoring will often focus on the effectiveness and impact of the programme or
plan as a whole.
During construction phase, the Proponent shall monitor the contractors activities in order to
verify that the management measures/procedures/specifications are implemented as
Page 110
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
contained in the EMP. Compliance will mean that the Contractor is fulfilling their contractual
obligation.
During operation phase, the Proponent will monitor facilitys operations to ensure compliance
with management measures in the EMP and operation procedures. As part of this monitoring,
the Proponent will undertake statutory initial environmental audit as required by the EIA/EA
Regulations, 2003 and subsequent annual self environmental audits.
The Proponent shall regularly monitor programme implementation. The process will include
the regular monitoring of:
Erosion of soil resulting in the immediate surroundings of the facility caused by the
presence of facility or impacting on structures associated with the facility
Air quality and ambient emissions, including dust generated by construction activities
All of the management plans make provision for monitoring and evaluation. Special attention
should be given to the monitoring arrangements relating to biophysical impacts, occupational
health and safety, facility operational and emergency response.
During the construction phase of the project, the Contractors HSE Officer shall report all
environmental impacts as well as accidents and incidents to the Proponents HSE Officer.
The reported impacts and incidents will be captured on a database to ascertain trends and
track progress in the implementation of preventive and corrective actions, and benchmarking
against other, similar operations.
Depending on the level of severity, accidents and incidents will be investigated by the
Contractors HSE division, with key input from the line management to ensure accountability.
During operation, the Proponents HSE department will monitor the health and safety of
personnel and contractors, in compliance with legislative requirements. Emergency incidents
should be reported to the relevant authorities. The reported impacts and incidents will be
captured on a database to identify weakness in the emergency response plan and track
progress in the implementation of preventative and corrective and benchmarking against
other similar operations.
Page 111
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER NINE
The construction and operation activities of the proposed project might generate incidents and
hazards to the health and safety of the employees. It is therefore imperative that the project
is constructed and operated in a safe and incident free manner particularly in compliance with
Kenyan legislation on safety (e.g. Legal Notice No. 40 titled Building Operations and Works
of Engineering Construction Rules, 1984) and the Proponents HSE management system
requirements. This section recommends the incident prevention and hazard communication
actions that the Proponent should undertake in the construction and operations phase of the
project.
Contractor health and safety is an essential component of incident prevention during the
construction phase of the project. It is recommended that contractor health and safety rules
be implemented for the project containing the elements described below.
The responsibilities with regard to safety must be documented by the Proponent for all
contractors to follow while working at the project site. The Proponents responsibility is to
issue procedures, safety rules and safety induction training for all contractors working on site.
It is the responsibility of all contractors to strictly adhere to the Proponents HSE standards
and to ensure that every person in the contractors employment observes the requirements of
the Proponents regulations.
The contractor will be required to nominate a contractor supervisor for the project. This
person will be responsible for all HSE compliance requirements of subordinates and will issue
instructions regarding safety and health which have to be carried out by all contract
employees.
In accordance with the Legal Notice 160 of 1977 (First Aid Rules), the contractor shall ensure
that an adequate number of certified first aiders are available at the project site with properly
equipped first aid boxes. At least one first aider for every 50 employees is recommended.
Any contractor employee who observes or is involved in an accident will immediately report
such incident to the contractor supervisor who will record the details in a General Register as
stipulated under the Occupational Safety and Health Act, 2007. The Contractors Supervisor
on site shall fill out an Accident Report Form and submit it to the nearest provincial DOHSS
office within 24-hours of the accident.
Page 112
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
It will be the responsibility of the contractor to ensure that their employees do not engage in
any of the following practices during the construction phase of the project:
Smoking;
Personal business; and
Misconduct
Each contractor working at the project site shall ensure that all their employees are provided
with appropriate and adequate PPE. The contractor will be required to maintain a register
indicating the issuance, control and use of PPE which includes the following:
Safety shoes;
The contractor will be required to issue the Proponent with a comprehensive Safety Method
Statement for carrying out each phase of the construction works. The contractor will further
be required to comply with the safety procedures of the Proponent EHS Management
System.
The contractor and all the employees working for them shall be required to be familiar with the
Proponents fire and emergency procedures. The safety induction training to be provided by
the Proponents Consultant for all contractors working at the project site will include the
Proponents emergency and evacuation procedures.
The contractor will be required to familiarize themselves with the Proponents security
procedures and shall ensure that all employees comply with those security procedures.
The contractor will ensure that no unsafe tools are used at the project site. The contractor will
further ensure that all scaffolding and ladders, cranes, welding machines, compressors, etc.
are in good serviceable condition at all times during the construction phase of the project and
have been certified by DOHSS approved persons.
Page 113
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The Proponent will develop, rollout and implement a detailed HSE management system for
their project. It is expected that relevant parts of such an HSE management system will be
rolled out and implemented at the project site during the operational phase of the project.
In the event of an emergency at the project site the Proponents Emergency Response Plan
will be activated in accordance with the procedures laid out in it. It will therefore be necessary
for the Proponent to develop, rollout and implement their documented emergency response
plan prior to the construction phase.
The emergency response plan should as a minimum include the headings given below.
Introduction;
Purpose;
Scope;
Abbreviations;
Definitions;
Emergency response organization;
Emergency notification system;
Evacuation procedures;
Emergency response plan activation;
Contingency plans;
Emergency management resources and logistics;
Crisis control center;
Deactivation and recovery plan;
Training;
Emergency response plan maintenance; and
Emergency response plan distribution.
Page 114
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER TEN
10.1 Assumptions
The Firm of Experts made the following assumptions in preparing this E.I.A Study Report.
All the technical data and information provided by the Proponent and the specialists are
accurate and up-to-date
The public involvement process has been sufficiently effective in identifying the critical
issues that needed to be addressed
The Proponent and the Contractor will implement the measures in the proposed EMP
The Proponent will undertake monitoring to track the implementation of the EMP to
ensure that management measures are effective to avoid, minimize and mitigate impacts;
and that corrective action is being undertaken to address shortcomings and/or non-
performances.
Uncertainty arises from a variety of aspects in any development, and for this particular EIA
study has emanated from the following:
The changes that may occur in baseline conditions, due to external factors over the lifetime of
the project;
Uncertainty related to Proponents policy initiatives that might influence the assessment of
future baseline and post-development conditions;
Uncertainty in design information which should be dealt with by the definition of design
parameters for the development by the Contractor and Proponent; and
Uncertainty in relation to project planning and implementation as the detailed program and
means of construction may be influenced by the choice of Contractor and the detailed design
of the development.
The difficulties in compiling the information for this EIA study have related principally to the
above sources of uncertainty. To obviate these difficulties the Firm of Experts has used their
past experience wherever possible and consultation with Proponents having similar projects
to gauge and recommend appropriate mitigation measures in this EIA study.
Page 115
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
CHAPTER ELEVEN
From the findings of this EIA Study, the following conclusions and recommendations are
made:
(a) The proposed installation of LPG tank has the support of the stakeholders,
(b) The project will be designed, constructed, and operated according to the acceptable
industry norms and standards
(c) Though there are a number of potential adverse impacts associated with it, it is possible
to mitigate them successfully. Successful implementation of the proposed EMP will help
to minimize or reduce the environment impacts to the acceptable levels.
(d) The proposed project will generate socio-economic benefits which would not be realized if
the no development of option is considered.
Page 116
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
ATTACHMENTS
1. photographs
2. Site Layout
Checklists
Page 117
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The proposed place where the LPG Tank and filling facility Acacia tree at the neighbouring premises which was
are to be installed. The site was currently used as a leaning towards the poposed site. BAT (K) Ltd was to liaise
storage area for tobacco pallettes. with the occupier to prune the branches of the tree.
The building neighbouring the proposed project, currently The ground surface at the proposed site
being used as a warehouse.
Page 118
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
The main gate, which is off Londiani Road leading to the The main gate leading to the premise. The proposed
proposed site project will share the premise with BAT Gym, Clinic and
clinic.
Page 119
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Site Layout
Page 120
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 121
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
Page 122
ENVIRONMENTAL IMPACT ASSESSMENT STUDY REPORT 2014
REFERENCE
The following list of references was referred to in preparing this EIA Report:
5. Government of Kenya: Factories and Other Places of Work (Safety and Health
Committee) Rules 2004
10. Government of Kenya: The Safety and Health Committee Rules 2004
16. Government of Kenya: Factories and Other Places of Work (Noise Prevention and
Control) Rules 2005
17. British Standard (BS) 8233:1999: Sound Insulation and Noise Reduction for
Buildings
18. British Standard (BS) 5228 Part 1, 1997: Noise and Vibration Control on Construction
and Open Sites
19. British Standard (BS) 5228 Part 4, 1997: Noise Control on Construction and Open Sites:
Code of Practice for Noise and Vibration Control applicable to piling operations
Page 123