Beruflich Dokumente
Kultur Dokumente
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 1
Traditional Project Management Life Cycle
Defining
Planning
Executing
Controlling
Closing
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 2
Defining
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 3
Planning
What is to be done?
Why it is being done?
Who will do it?
When it will be done?
What resources will be needed?
What criteria must be met in order for the project to be
declared complete and successful?
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 4
Planning - continued
Planning reduces uncertainty
Allows us to consider likely outcomes and put corrective
measures in place
Planning improves efficiency
By recognizing dependencies and resource relationships
in advance, can optimize tasks and shorten total duration
Planning increases understanding
Act of planning gives insight into goals and objectives
A basis for measuring:
Planning provides a basis for measuring work planned
against work performed
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 5
Executing
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 6
Controlling
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 7
Closing
There are several questions that should answered as part of
any closing:
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 8
Causes of Project Failure:
Projects that have failed generally display several of the
following characteristics:
The customers conditions of satisfaction have not been
negotiated.
The project no longer has a high priority
No one seems to be in charge
The schedule is too optimistic
The project plan is not used to manage the project
Sufficient resources have not been committed
Project status is not monitored against plan
No formal communications plan is in place
The project has lost sight of its original goals
There is no change management process in place
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 9
Levels of Project Management:
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 10
Project Management Life Cycle:
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 11
Scope the Project
Begins with an exchange of info between requestor and
project manager
Goal is bound by a number of objective statements that
clarify goal statement
Documented in form of Project Overview Statement (POS)
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 12
POS (Project Overview Statement)
Brief document (usually one page) that describes, in the
language of business:
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 15
The Project Management Pain Curve
Proper Planning is painful but pays off in less pain later in the project
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 16
Launch the Plan
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 17
Monitor/Control Project Progress
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 18
Close Out the Project
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 19
Project Management Life Cycle:
1. Scope the project. 4. Monitor/control project progress
State the problem/opportunity. Establish progress reporting system.
Establish the project goal. Install change control tools/process
Define the project objectives. Define problem-escalation process.
Identify the success criteria Monitor project progress versus plan.
list assumptions, risks, and obstacles. Revise project plans
2. Develop the project plan. 5. Close out the project.
Identify the project activities. Obtain client acceptance
Estimate activity duration. Install project deliverables.
Construct/analyze the project network Complete project documentation
Prepare the project proposal. Complete post implementation audit
3. Launch the plan Issue final project report
Recruit and organize the project team.
Establish team operating roles.
level project resources.
Schedule work packages.
Document work packages.
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 20
Project Management Life Cycle:
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 21
Defining the Project
The top 10 reasons why projects succeed are these:
Executive management support
User involvement
Experienced project manager
Clear business objectives
Standard infrastructure
Firm basic requirements
Formal methodology
Reliable estimates
Skilled staff
Communication is the key!
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 22
Managing Client Expectations
How often do you find yourself thinking about what you are
going to say while the other party is talking?
An essential skill that project managers need to cultivate is
good listening
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 24
Establishing Clarity of Purpose
The COS process is to negotiate to closure on exactly what
will be done to meet the request
This process repeats itself until there is an agreed-to request
that is satisfied by an agreed-to response
As part of this agreement there will be a statement, called
success criteria, in the POS that specifies when and how the
request will be satisfied
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 25
Conducting Milestone Reviews
The COS is a dynamic agreement that becomes part of the
continual project monitoring process
Situations change throughout the project life cycle and so will
the needs of the customer and that means that COS will
change
At every major project status review and project milestone,
review the COS
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 26
Creating the Project Overview Statement
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 28
Stating the Problem or Opportunity
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 29
Establishing the Project Goal
The second section of the POS states the goal of the project:
What you intend to do to address the problem or opportunity
identified in the problem/opportunity section
The purpose of the goal statement is to get senior
management to value the idea enough to read on
A project has one goal
The goal statement will be used as a continual point of
reference for any questions that arise regarding scope or
purpose
The goal statement should not include a specific completion
date (If you expect management to ask for a date, estimate the
date to the nearest quarter, month, or week as Appropriate)
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 30
S.M.A.R.T. Characteristics of Goal Statement
Dorans S.M.A.R.T. characteristics provide the criteria for a
goal statement:
Specific
Be specific in targeting an objective
Measurable
Establish measurable indicators of progress
Assignable
Make the object assignable to one person for completion
Realistic
State what can realistically be done with available
resources
Time-related
State when the objective can be achieved
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 31
Defining the Project Objectives
The third section of the POS is the project objectives
Objective statements as a more detailed version of the goal
statements
The purpose of objective statements is to clarify the exact
boundaries of the goal statement and define the boundaries or
the scope of your project
Every objective must be accomplished in order to reach the
goal
No objective is superfluous
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 32
An objective statement should contain
An outcome
A statement of what is to be accomplished
A time frame
The expected completion date
A measure
Metrics that will measure success
An action
How the objective will be met
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 33
Identifying Success Criteria
The fourth section of the POS answers the question, Why do
we want to do this project?
Represents the measurable business value that will result
from doing this project and sells the project to senior
management
Must answer the question, What must happen for us and the
customer to say the project was a success?
State the business value to be achieved, and therefore,
provide a basis for senior management to authorize the
resources to do detailed planning
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 34
Types of Success Criteria
Success criteria all reduce to one of three types:
Increased revenue
Reduced costs
Improved service
Alternatively, consider quantifiable statements
about the impact your project will have on:
Efficiency and effectiveness
Error rates
Reduced turnaround time
Reduced cost of providing service
Quality
Improved customer satisfaction
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 35
Assumptions, Risks, and Obstacles
The fifth section of the POS identifies any factors that can
affect the outcome of the project that you want to bring to the
attention of senior management
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 36
Examples of Risk Factors
Technological
New technology
Rapidly changing
Environmental
Changing management structure
Skill level required
Interpersonal
Poor working relationships between teammates or
stakeholders
Cultural
Project inconsistent with existing corporate culture
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 37
Submitting a POS for Approval
Once POS is complete, it is submitted to management for
approval
As part of the approval process, senior management asks
several questions regarding the information presented
Expect several iterations
Approval of the POS commits the resources required to
complete a detailed plan for the project
Rough estimates of time or cost variables are often
requested from the project manager and the project team
It is not unusual to have the project manager return to the
drawing board several times for more analysis and thought as
a prerequisite to management approval
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 38
Participants in the Approval Process
Core project team
May have been identified at the early stages of the project
Will be the managers, professionals, and perhaps the customer who will
remain on the project team from the beginning to the very end of the project.
May participate in developing the POS and reach consensus on what it
contains
Project team
Some potential members of the project team are usually known beforehand
Their subject matter expertise and ideas should be considered as the POS is
developed
Project manager
Ideally, the project manager will have been identified at the start and can participate in
drafting the POS
Should have a major role to play in its definition and its approval
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 39
Participants in the Approval Process continued
Resource managers
Those who will be asked to provide the skills needed at the times when they
will be needed are certainly important
Little point in proposing a project if the resources are not or cannot be made
available to the project
Function/process managers
Several units will provide input to or receive output from the project products or
services and their advice should be sought
Customer
PM-methodology includes a significant role for the customer
Discussed the COS
Senior Management
Their support is a critical factor in successful projects
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 40
Using the JPP Session to Develop the POS
The Joint Project Planning (JPP) session is the tool text recommends for
developing the project plan.
This session will involve the customer or his or her representative, the project
manager, and, if they have been identified, key members of the project team
Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering 2017/2018 41