Bhilai Steel Plant
(Known as Construction Department also)
1. Background
Steel Industry with its vital and forward linkage has a critical role to play
in the planned economic development of the country. Steel is one of the critical
materials required for sustaining the growth of countries economy.
While the steel industry has phases of conscious success in the past, it is
presently beset with the problem of lower capacity utilization, high-energy
consumption, lower productivity, high cost and Technological obsolescence. These
problems are being tackled through comprehensive planned corporate strategies
for greater satisfaction to the customers & meeting the global demand of steel.
2. Importance of Projects
A Project in a steel plant involves number of activities right from
Conceptualization, Planning, finalization of Consultant, Feasibility report, seeking
approval, Tendering, Ordering, Execution & Commissioning of units to achieve the
desired results.
3. Need of Projects
• INSTALLATION OF NEW UNITS
• MODIFCATION OF EXISTING UNITS
• SUBSTITUTION OF AGED UNITS (REPLACEMENT)
• INTRODUCTION OF AUTOMATION SYSTEMS.
• INTRODUCTION OF STATE OF THE ART TECHNOLOGY
14
The work of 1 MT was started in 1955-56 and completed progressively by 1956-61
at a cost of
Rs. 202 Crs.
Unit Features
Coke Ovens 3 Batteries, 65 Ovens
Sinter Plant 2 Machines - 50 M2
Blast Furnace 3 B.F. -1033 M3
Steel Melting Shop 5 OHF (250 T)
Power Plant - I 2 Nos. 12 MW TG
Oxygen Plant – I 3 units
RMP - I 1 No. Dolomite Kiln & 2 Nos. Lime Kiln
Mills
Blooming Mill 1150 mm, 2 High Reversing
Billet Mill 700 / 500 mm
R&SM 950 / 800 mm
Merchant Mill 350 mm
Unit Features
Coke Ovens 3 Batteries, 65 Ovens, 21.7 M3
Sinter Plant 1 Machine – 50 M2
Blast Furnace 3 B.F. – 1719 M3
Steel Melting Shop 5 OHF (500 T)
Slag Processing Plant Crushing & Screening of Aggregates
Power Plant - I 1 No. 12 MW TG
Oxygen Plant - I 1 Unit
RMP - I 1 No. Dolomite Kiln & 3 Nos. Lime Kiln
Mills
Blooming Mill 8 Groups of Soaking Pits
R&SM Finishing groups – 3, 4, 5 & 6
Billet Mill 1000 mm
Wire Rod Mill 250 mm
Note: -Coke Oven Batteries No. 7 & 8 and Sinter M/c No. 4 were added
beyond 2.5 MT Stage.
Unit Features
Coke Ovens 1 Battery 67 Ovens, 7 Meter Tall (COB –9)
Sinter Plant 4 Machines - 75 M2
Blast Furnace 2000 M3 with BLT (BF-7)
Steel Melting Shop 4 Twin Hearth Furnaces (500 T)
3 Nos. 100 / 130 T Convertor
Continuous Casting Shop 4 Nos. Single Strand Slab Caster
1 No. 4 Strand Bloom Caster
Oxygen Plant II 3 Nos. Air Separation Units
RMP II 1 No. Dolomite Kiln, 2 Nos. Lime Kiln & Brick
shop
Power Plant II 2 Nos. 30 MW TG & 1 No. 14 MW TG
OHP & CRMBSY
15
Mills
Plate Mill 3600 MM – 4 High Reversing and 4 High
Finishing
IV. Other AMR Schemes & De-bottlenecking Schemes & Capital
Schemes & Township
Number of AMR Schemes & De-bottlenecking schemes & Capital schemes,
Pollution control schemes & work on Township were also executed from time to
time.
Sanctione
S d
PROJECT
N Cost
(Rs. Crs)
1 Re-building of Coke Oven Battery # 5 219.04
8 Repl. of existing MG sets for Roughing & Finishing stand drive 48.31
Motors at Plate Mill by digital Thyristor Convertors
9 Instln. of 700 TPD ASU-4 with Associated facilities at OP-II 212.44
Total 1339.4
Estimate
SN PROJECT cost
(Rs. Crs)
1 Installation of End Forging Plant for thick web rails 53.92
16
The Consultancy for various schemes is being provided by MECON & CET. The
Major Schemes are as follows:
SN Description of schemes
1. Modernization of BF-6 : Package-I (BF proper & CH)
2. Modernization of BF-6 : Package-II (GCP)
3. Installation of 2nd Sinter M/c in SP-3
4. Installation of 4060 M3 BF Complex
5. BOF Shop Technological Package
6. Installation of Continuous Casting Plant Complex
7. Installation of Universal Beam Mill
8. Installation of Bar & Rod Mill
9. Installation of new Normalizing Furnace under Plate Mill Modernization &
Augmentation
10. Augmentation of Plate Mill capacity: Instln. Of Cooling Beds, Pilers & Other
Equipment (Package –III)
11. Reheating Furnace for UBM, B&RM & URM
12. Installation of Secondary Refining Unit for SMS-III
13. Augmentation of OHP Part-A
14. Installation of Universal Rail Mill
15. Installation of New Coal Handling Plant
16. Installation of Hot Metal De-sulphurisation Unit for SMS-III
17. Replacement of Combi-caster with Bloom cum Beam blank caster in SMS-II
18. Installation of Compressed Air Station No. 4
19. Installation of Turbo-blower Station
20. Modernization of BF-6: Package-III (TB-9 revamping)
21. Modernization of BF-6: Package-IV (INBA SGP)
22. Aug. of Plate Mill capacity: Installation of Plate Edge Marking M/c & Automatic
Length Measuring System (Package –IV)
23. Aug. of Plate Mill capacity: Installation of 40 T EOT Crane & 17 T Semi-portal
Crane (Package –V)
24. Aug. of Plate Mill capacity: Installation of CNC Roll Grinding M/c
(Package –VI)
25. Aug. of Plate Mill capacity: Supply & Installation of GUILLOTINE Shear (Package
–VII)
26. Aug. of Plate Mill capacity: Civil & Strl. Works (Package –II)
27. Aug. of Plate Mill capacity: Installation of 140 TPH Walking Beam Type Furnace
(Package-I)
28. Augmentation of MSDSs & Installation of MSDS-VII
29. Boilers at P&BS
30. New OHP Part-B & Base blending facility for SP-3
31. COB-11 : 7 m tall coke oven battery No. 11 with 67 ovens
32. COB-11 : Installation of BPP with H2S recovery unit
33. COB-11 : Coke dry quenching facilities with coke sorting plant
34. Civil and Strl works for BOF, CCP shop
35. Civil & Structural Universal Rail Mill
36. Civil & Structural works for BOF & CCS, Universal Beam Mill and Bar & Rod Mill
37. Installation of 2 X 1250 TPD Oxygen Plant on BOO basis
17
Road Work
11 M Wide 3 KM
7 M Wide 8 KM
4 M Wide 5 KM
Laying & Linking of Railway Track 35 KM
Dismantling of Existing Railway Track 15 KM
VIII. Project organization
2. The zonal concept is functioning in the Project Deptt. and headed by senior
DGMs.
18
g. Seeking approval of management for release of tender enquiry for publication in
open tender / limited tender.
h. Release of publication matter for publication in newspapers & on sail website.
i. Issue of tender enquiry in case of limited tender.
j. Sale of tender document.
k. Extension if required for submission & opening of offers.
l. Opening of earnest money deposit / BG.
m. Opening of tender / techno-commercial offers.
n. Process for bid evaluation techno-commercial & commercial.
o. Recommendation for placement of ordering.
p. Award of contract.
q. Extension of time, clarification, settlement of rates of extra items & interim
deviations.
9.3 Site Execution zone
a. Detail study of contract, scope, terms & conditions.
b. Planning & execution for enabling works.
c. Providing utilities & services to the executing agency within the boundary limits.
d. Interaction with the executing agency for opening site office, gate passes for
workers & receipt of various policies from the party.
e. Study of L-1 network submitted by the party.
f. Finalization of implementation plan based on contractual commitments.
g. Follow-up with the party for completion of design engineering, equipment ordering,
manufacturing and erection.
h. Execution of civil work, dismantling if any and trench work.
i. Fabrication & erection of building structures.
j. Follow-up with the party for manufacturing & supply of equipment.
k. Erection of equipment (Mechanical, Electrical, Instrumentation & Automation).
l. Erection of refractory, sheeting etc.
m. No-load testing & trial run of equipment.
n. Load trial run of equipment.
o. Defect elimination.
p. Issue of PAT.
q. Commissioning of equipment.
r. Establishing performance guarantee.
s. Closure of contract.
t. Feed back.
X. Capital Expenditure
19
As on 31.03.07 around Rs. 6642 Crores Capital Investment has been made by
Bhilai Steel Plant. The Details are as follows: -.
20