Beruflich Dokumente
Kultur Dokumente
P
lanned shutdowns are an accepted identify the work required to allow the same levels as achieved in previous shut-
feature in the operation of almost plant to run reliably over the three-year downs. In order to understand this it is
all large chemical plants. They pro- period between shutdowns. However, useful to divide the work done during
vide engineers with the opportunity to the introduction of the Pressure Systems the shutdown into repair of defects,
inspect, clean, repair and modify equip- Regulations in 1994 provided flexibility, equipment inspection and testing,
ment that is otherwise in continuous where technically justified, to vary the equipment cleaning and modifications.
operation. The impact of shutdowns on shutdown interval, thus exposing the Analysis of the 1993 and 1997 shut-
the overall plant reliability can be organisation to the full complexity of downs shows that modifications are a
expressed in the equation: the optimisation process. relatively small part of the total work-
Plant unavailability = A number of other issues have caused load (Table 1). It is reasonable to expect
breakdown outage + shutdown duration most chemical plant operators to simplify that the workload associated with
shutdown interval the optimisation process by looking to repairing defects and cleaning equip-
From this equation it can be seen that extend shutdown intervals as far as prac- ment will generally be proportional to
there is a benefit from optimising the tical while trying to minimise the the chosen shutdown interval, so in
work done during a shutdown to: increase in the per shutdown workload. order to achieve the aim of delivering a
Reduce the probability of breakdowns Among the key factors driving this six-year interval without increasing the
between shutdowns. trend are the minimum fixed duration overall shutdown workscope, it would
Protect future process performance at and cost associated with all shutdowns, be necessary to reduce the amount of
design throughput/energy efficiency and the times taken to de-inventory and inspection work in order to compensate
(the equation is written on the assump- subsequently recommission the plant. for the increase in defect repair and
tion that the plant can run at full rate Also, the period of plant operation cleaning. Alternatively, it would be nec-
during an operational campaign). immediately after a shutdown is often essary to find more effective ways of
Increase the interval between shut- characterised by unsteady plant condi- making repairs or cleaning equipment.
downs. tions and high levels of equipment
Reduce the duration of each shut- breakdown. Inspection during shutdowns
down. Since the introduction of the Pressure Historically, shutdown intervals and
There is a clear conflict in these Systems Regulations, the No. 6 olefins workscope have been dominated by the
issues. It might reasonably be expected plant at Wilton has moved away from statutory and company requirements for
that efforts to reduce breakdowns, pro- the fixed three-year shutdown interval, routine inspection and testing of key
tect throughput and energy efficiency, with subsequent shutdowns in 1997 and items of equipment, primarily pressure
or to increase shutdown intervals would 2002. The aim of the 2002 shutdown vessels and heat exchangers. These
tend to put more work into each shut- has been to prepare the plant for reliable inspections have mainly been delivered
down, thus tending to increase the dura- high rate operation for a period of six by visual internal inspection of the
tion of the shutdown. This conflict years until the next planned shutdown equipment, which coincidentally
makes the overall optimisation of in 2008. requires an amount of cleaning in order
workscope a complex issue. to provide access to the equipment.
The Huntsman No. 6 olefins plant at Worklist preparation Items of equipment covered by legisla-
Wilton International, in the UK, is one The stated aim of the 2002 olefins shut- tion were required to be inspected at
of the largest ethylene crackers in the down was to specify and deliver the each shutdown, but for other items the
world, with an annual throughput of work required to support reliable high- inspection interval could be extended
approximately 2.5 million tonnes of rate operation of
hydrocarbons. The plant is shut down the plant until the Analysis of work for 1993 and 1997 shutdowns
periodically for maintenance work, and 2008 shutdown.
until 1994 the task of optimising the An unwritten fur- Work type 1993 shutdown 1997 shutdown
work done during shutdowns was sim- ther aim was to Hours Percentage Hours Percentage
plified by manipulating one of the vari- ensure that the
Repair 5 6520 36 9 1 000 49
ables in the equation above. duration of the
Inspect and test 8 0070 51 56 000 31
National legislation required that the shutdown, and Cleaning 7850 05 2 2 000 12
plant shut down every three years to therefore the total Modification 12 560 08 15 000 08
provide for inspection of the steam sys- work undertaken, Total 15 7000 100 184 000 100
tems. Thus, the task facing the engineers could be held at
in preparation for each shutdown was to approximately the Table 1
129
P T Q WINTER 2002/03
w w w. e p t q . c o m
RELIABILITY AND ASSET MANAGEMENT
131
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT
132
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT
133
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT
134
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT
achieved by establishment of a target manage, and although the contractors defect rectification, to reach the position
cost for each contract. The contracts were efficient at identifying variations where shutdown intervals are dictated
were written so that the contractors and that tended to increase cost, it was more by unavoidable cleaning requirements,
the client organisations would share difficult to identify or record variations rather than by mechanical deterioration
deviations from the agreed targets. that tended to reduce cost. Ultimately, that triggers the need to inspect equip-
Thus, if the total cost were within the use of target manhours in incentive- ment. This requires an optimisation of
budget there would be a gainshare, based contracts will only drive the con- equipment design, focussing on ele-
and if the total cost was above budget tractors to control and reduce cost if it ments in the process chain that suffer
there would be a painshare. can be established that the targets are from time dependent deterioration that
Fixed bonuses were agreed for achieve- not to be subject to variation after they influence the outage frequency. The cost
ment of plan and for achievement of have been agreed. benefits of improvements in engineering
specified EHS targets. Payment of these design can be optimised to whatever is
bonuses would be independent of shut- Conclusion the desired goal.
down cost performance (although in The foregoing discussion has noted that
reality there are strong links between cost for large petrochemical plants, there are This article is based on a paper presented at
and programme performance). In addi- benefits to be gained from increasing the ERTC Reliability Conference, Prague,
tion, establishment of contractor selec- the interval between plant shutdowns, 2325 September 2002.
tion and technician training in support but that these benefits depend on the
of quality objectives also helped in ability to control shutdown workload
achieving contract objectives. and duration. The aim is a strategy, Kevin McQuillan is olefins engineering
The application of these two con- which embodies the best combination manager for the Huntsman Petrochemicals
tracts was analysed after the event, and of low cost and acceptable business risk. olefins manufacturing site at Wilton, UK. He
the key learning is that the use of fixed A number of techniques for control- is responsible for engineering standards, and
bonuses for programme and EHS perfor- ling shutdown workload have been project and maintenance activities, and has
mance worked very well. In particular, described, and the benefits of these led the development of the Huntsman
on EHS performance, achievement of techniques have been demonstrated by method for the application of RBI.
the bonus was dependent on both input examining the history of plant shut- Kenny McGeachie is an olefins technical
measures, eg auditing compliance, and downs on the Huntsman No. 6 olefins engineer at the Huntsman ICI manufactur-
output measures, eg accident statistics. plant at Wilton. ing site at Wilton, with responsibilities for
The use of a target cost was less suc- On a given plant, it should be possi- engineering standards, asset life planning
cessful, primarily because the targets ble, by judicious application of RBI and and technical support to asset
were subject to variation as a result of techniques to improve reliability or to management and project personnel. He is
emergent work. This was difficult to reduce the work content of cleaning and a graduate in mechanical engineering.
135
P T Q WINTER 2002/03