Sie sind auf Seite 1von 6

RELIABILITY AND ASSET MANAGEMENT

The case for optimising


shutdown preparations
A risk-based approach to optimising inspection activities, eliminating unnecessary
work and controlling engineering standards, in addition to aligning contractor
objectives with those of the client, contributes to efficient shutdown preparation
Kevin McQuillan and Kenny McGeachie
Huntsman Petrochemicals (UK) Ltd

P
lanned shutdowns are an accepted identify the work required to allow the same levels as achieved in previous shut-
feature in the operation of almost plant to run reliably over the three-year downs. In order to understand this it is
all large chemical plants. They pro- period between shutdowns. However, useful to divide the work done during
vide engineers with the opportunity to the introduction of the Pressure Systems the shutdown into repair of defects,
inspect, clean, repair and modify equip- Regulations in 1994 provided flexibility, equipment inspection and testing,
ment that is otherwise in continuous where technically justified, to vary the equipment cleaning and modifications.
operation. The impact of shutdowns on shutdown interval, thus exposing the Analysis of the 1993 and 1997 shut-
the overall plant reliability can be organisation to the full complexity of downs shows that modifications are a
expressed in the equation: the optimisation process. relatively small part of the total work-
Plant unavailability = A number of other issues have caused load (Table 1). It is reasonable to expect
breakdown outage + shutdown duration most chemical plant operators to simplify that the workload associated with
shutdown interval the optimisation process by looking to repairing defects and cleaning equip-
From this equation it can be seen that extend shutdown intervals as far as prac- ment will generally be proportional to
there is a benefit from optimising the tical while trying to minimise the the chosen shutdown interval, so in
work done during a shutdown to: increase in the per shutdown workload. order to achieve the aim of delivering a
Reduce the probability of breakdowns Among the key factors driving this six-year interval without increasing the
between shutdowns. trend are the minimum fixed duration overall shutdown workscope, it would
Protect future process performance at and cost associated with all shutdowns, be necessary to reduce the amount of
design throughput/energy efficiency and the times taken to de-inventory and inspection work in order to compensate
(the equation is written on the assump- subsequently recommission the plant. for the increase in defect repair and
tion that the plant can run at full rate Also, the period of plant operation cleaning. Alternatively, it would be nec-
during an operational campaign). immediately after a shutdown is often essary to find more effective ways of
Increase the interval between shut- characterised by unsteady plant condi- making repairs or cleaning equipment.
downs. tions and high levels of equipment
Reduce the duration of each shut- breakdown. Inspection during shutdowns
down. Since the introduction of the Pressure Historically, shutdown intervals and
There is a clear conflict in these Systems Regulations, the No. 6 olefins workscope have been dominated by the
issues. It might reasonably be expected plant at Wilton has moved away from statutory and company requirements for
that efforts to reduce breakdowns, pro- the fixed three-year shutdown interval, routine inspection and testing of key
tect throughput and energy efficiency, with subsequent shutdowns in 1997 and items of equipment, primarily pressure
or to increase shutdown intervals would 2002. The aim of the 2002 shutdown vessels and heat exchangers. These
tend to put more work into each shut- has been to prepare the plant for reliable inspections have mainly been delivered
down, thus tending to increase the dura- high rate operation for a period of six by visual internal inspection of the
tion of the shutdown. This conflict years until the next planned shutdown equipment, which coincidentally
makes the overall optimisation of in 2008. requires an amount of cleaning in order
workscope a complex issue. to provide access to the equipment.
The Huntsman No. 6 olefins plant at Worklist preparation Items of equipment covered by legisla-
Wilton International, in the UK, is one The stated aim of the 2002 olefins shut- tion were required to be inspected at
of the largest ethylene crackers in the down was to specify and deliver the each shutdown, but for other items the
world, with an annual throughput of work required to support reliable high- inspection interval could be extended
approximately 2.5 million tonnes of rate operation of
hydrocarbons. The plant is shut down the plant until the Analysis of work for 1993 and 1997 shutdowns
periodically for maintenance work, and 2008 shutdown.
until 1994 the task of optimising the An unwritten fur- Work type 1993 shutdown 1997 shutdown
work done during shutdowns was sim- ther aim was to Hours Percentage Hours Percentage
plified by manipulating one of the vari- ensure that the
Repair 5 6520 36 9 1 000 49
ables in the equation above. duration of the
Inspect and test 8 0070 51 56 000 31
National legislation required that the shutdown, and Cleaning 7850 05 2 2 000 12
plant shut down every three years to therefore the total Modification 12 560 08 15 000 08
provide for inspection of the steam sys- work undertaken, Total 15 7000 100 184 000 100
tems. Thus, the task facing the engineers could be held at
in preparation for each shutdown was to approximately the Table 1

129
P T Q WINTER 2002/03
w w w. e p t q . c o m
RELIABILITY AND ASSET MANAGEMENT

subject to the equipment remaining in of failure, and an evalua-


good condition. tion of the associated risk. Impact of risk-based inspection on
By 1993, the inspection intervals for Inspection should be shutdown workload
the equipment on No. 6 olefins were: focussed on high-risk
Interval (years) % of items items, and be geared to Year 1997 2002
4 17 detection and quantifica-
Number of items due for inspection 157 232
6 10 tion of deterioration aris-
Number of items studied 157 232
9 23 ing from the predicted Number of non-invasive inspections 080 188
12 50 failure mechanism and Number of SD inspections 081 047
This situation allowed the inspection vulnerable areas. Number or repair requirements
workload to be spread out between shut- For example, if the like- identified prior to shutdown 018 017
downs, but clearly any move to increase ly deterioration is external Number of repair requirements
the interval between shutdowns would corrosion under insula- identified during shutdown 006 002
cause a proportionate increase in the tion, then inspecting the
inspection workload at each shutdown. equipment internally is Table 2
The introduction of the Pressure Sys- not the most appropriate
tems Regulations increased the atten- method to use. This aspect of RBI (some- RBI/ focussed scheme process is to opti-
tion given to the effectiveness of the times known as focussed schemes) is mise the inspection content of the shut-
traditional inspection processes often given less attention by some expo- down by eliminating unnecessary
reliance on visual internal inspection nents of the RBI process, but in many inspection activity, exploiting the use of
and it was noted that most visual inter- ways is more important and a funda- online non-invasive inspection, thereby
nal inspections served merely to con- mental pre-requisite of the assessment reducing shutdown inspection work,
firm the good condition of the of risk (if it is not known how the ensuring that most likely deterioration
equipment. Repairs had been necessary equipment is likely to fail, how can the is identified prior to the shutdown so
in 5% of cases, and many of these were failure consequences be established?). that appropriate repair or replacement
as a result of damage caused during 3. The RBI process should be multi- work can be built into the shutdown
inspection. disciplinary, using a mixture of process, plan, and ensuring that inspection is a
In many cases the most significant plant design, materials and inspection value adding part of maintenance.
deterioration mechanism was external expertise. The RBI review explores the
corrosion, and yet all inspections duty and condition of the equipment, Repairs and cleaning
depended mainly on visual internal establishing what can happen and why. The two main remaining categories of
inspection. The process can identify opportunities work are repairs and modifications in
The environment within most pres- for improvements in process control support of repair work, and cleaning. In
sure vessels is hazardous for the inspec- and design or material selection since it both cases, it might be expected that the
tor, with significant cleaning and will establish proximate cause of an workload would increase in proportion
preparation required to provide access. experienced or predicted failure. to the shutdown interval.
Despite the general good condition of The Huntsman approach to RBI was Repair work during shutdowns is
the equipment at inspection, occasional initially developed and applied as a pilot dominated by activity to rectify defects
surprise/unforeseen deterioration had project during the 1997 No. 6 olefins identified during plant operation. Sig-
been recorded. In these cases remedial plant shutdown, and the results of this nificant types of activity include the
work often causes significant delays to process are evident in Table 1, which replacement of defective valves, repack-
the shutdown. Little use was being made shows a clear reduction in inspection ing of valve glands and the replacement
of advanced technology in support of workload and an increase in cleaning of corroded pipework. Most defects arise
equipment inspection. workload in the 1997 shutdown com- as a result of normal plant operation,
Driven by these issues, and by the pared to that in 1993. and it would be expected that the total
overriding need to support shutdown Since then, the process has been fur- workload would increase in proportion
interval extension by reducing inspec- ther refined in partnership with ABB to shutdown interval.
tion workload, a process was developed Eutech. ABB has similar experience with Generally, it is not possible or cost
and applied during the 1997 plant shut- other clients in the process industry sec- effective to do the work online, so in an
down preparations. This process has tor. The process has been applied in effort to control shutdown workload it
since been further developed both many situations, both in ordinary main- is useful to look for more effective ways
inside and outside Huntsman, and has tenance and in support of shutdown of delivering the work, or technical solu-
become characterised as risk-based inspection optimisation. tions to avoid or reduce the defect rate
inspection (RBI). There are three key fea- The impact of the process on the on future shutdowns. The most signifi-
tures of the process: shutdown inspection workload is signif- cant saving of this type, achieved during
1. The amount of effort invested in icant, in that a number of inspections the 2002 shutdown, was a result of the
inspecting equipment should be in pro- can be carried out with the plant online use of axial swage pipe connection tech-
portion to the risk associated with fail- by using non-invasive external inspec- nology. This technology uses a fitting
ure of the equipment, where the risk is tion as the means of certifying the con- that, with the use of hydraulic equip-
the product of the probability and con- dition of the equipment. Additionally, ment, establishes a metal to metal inter-
sequence of failure. This aspect of RBI the process allows equipment that is ference fit and thus avoids the need for
has been well recognised by most stud- likely to have suffered deterioration to welding and associated costs.
ies, and software packages are now avail- be identified so that repair or replace- Figure 1 shows a sectioned fitting and
able to help in the quantification of risk ment requirements can be planned into Figure 2 shows the assembly equipment.
2. The inspection of equipment the shutdown, thus reducing the likeli- The fittings can only be used if the
should be knowledge-based, under- hood of surprise deterioration and parent pipework is in good condition,
pinned by a clear understanding of the unplanned additions to the shutdown and use in the 2002 shutdown was lim-
behaviour of the item, the potential fail- workscope. The situation is summarised ited to service duties only. The fittings
ure mechanisms and the consequences in Table 2. The overall impact of the were installed by technicians from the

131
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT

Figure 1 Sectioned swaged fitting

shutdown mechanical contractor, and


the technicians were trained in the
installation process by the supplier of
the fittings.
A total of 454 swage fittings were used
during the shutdown. Of these, five
leaked when the plant was recommis-
sioned. In each case the leak was a result
of using the fitting on pipework that
was in poor condition. The technology
provided a significant reduction in the
shutdown workload, both by removing
the requirement for welding and also by
removing the requirement for fire tents
and post-weld non-destructive testing. Figure 2 Assembly of swaged fitting
The savings are estimated at 6500
main trade manhours, plus additional chemical cleaning (or simply to provide involved the use of the quick shot tube
savings in support trade hours. Addition- a safer environment for high-pressure cleaning system (Figure 4). A powerful air
ally, the use of the swage fitting technol- water jetting) and the use of hydrokinet- and water stream shoots reusable scrub-
ogy provides a significant reduction in ic cleaning on suitable duties (Figure 3). bers through the tubes to remove mud,
hot work, thus reducing the risk of fire, The hydrokinetic process uses acous- sludge, algae, and other deposits. The
and in the requirements for planning tic resonance established in a water col- tube scrubbers are loaded into the con-
and interface management (fire tents, umn within the fouled tube to break the denser tubes and propelled through by a
standby men and NDT technicians). bond between the tube wall and the stream of air and water via a hand held
The impact of the inspection study fouling material. The fouling material is cleaning gun. Scrubbers consist of a core
process already described was to remove then ejected from the tube by a combi- body and seven scraping discs, which are
many internal inspection requirements nation of the water pressure in the col- self-adjusting to the diameter of the tube.
from the shutdown. Coincidentally, this umn and a plug inserted into the tube as Openings at the base of the tips allow
also removed the requirement to clean part of the cleaning process. Hydroki- passage of water to agitate and advance
items in preparation for inspection. In netic cleaning is not suitable for all loosened deposits while maintaining
most pressure vessels this is not a prob- cleaning applications, but can deliver differential pressure to force the scrub-
lem, but for heat exchangers and distilla- large cost and duration savings on cer- ber completely through the tube. The
tion columns, lack of cleaning could tain duties. Other improvements scrubber construction ensures excellent
easily lead to efficiency losses or even
rate reductions, especially over a planned
six-year run at potentially high rates.
The problem was further compound-
ed by the lack of accurate heat balance
data from previous pre- and post- clean-
ing heat exchanger operations. It was
therefore decided to include identifica-
tion of cleaning requirements as part of
the inspection study, and also to under-
take supplementary inspections of items
required to be cleaned in order to vali-
date the conclusions of the inspection
study. This process generated a list of
heat exchangers and columns that were
required to be cleaned during the shut-
down, together with some pipework that
was known to be fouled with polymer.
The traditionally favoured method
for heat exchanger cleaning is to blast
the tubes with high-pressure water. This
technique was used on most of the
cleaning tasks undertaken during the
shutdown; however, some improve-
ments were achieved, notably the
removal of some bundles from site for Figure 3 Hydrokinetic cleaning

132
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT

shutdown of the No. 6 olefins plant,


there were major problems with leaks
from gasketed joints; approximately
1000 joints had to be retightened and
200 joints were required to be remade.
This caused approximately five days
delay in bringing the plant back online,
and the investigation after the shut-
down concluded that the leaks were
mainly caused by poor joint-making
standards.
For the 1993 and 1997 shutdowns a
Figure 4 Quick Shot tube cleaning system traceability system was introduced and
all technicians were trained in the
wear characteristics of the edges with- examination and pressure testing importance of high standards and the
out harmful wear to the interior wall of Instrument and electrical work is need to identify problems during the
the tube. checked by loop checking and trip/ maintenance period in order that re-
alarm testing machining, etc, could be used in a
Engineering standards Gasketed joint-making, following planned way to minimise leaks during
In most chemical plant shutdowns it is reassembly of components, is checked testing. This process was extremely
necessary to supplement local resource by pressure testing and/or leak testing effective, reducing the number of leaks
by the use of contractors. In these cir- on most systems. to less than 50, and the number of
cumstances, control of engineering So it could be argued that testing pro- remakes to less than 10.
standards becomes a key issue, particu- tects against poor standards. However, Traceability was also used during the
larly where inadequate standards could in the case of gasketed joint-making, 2002 shutdown, and as in previous
lead directly to plant integrity problems most shutdowns involve many techni- shutdowns the technicians were
during testing or start up. Looking at cians in making hundreds of joints, required to undertake detailed training
maintenance work during shutdowns, there is often no traceability of a partic- and validation. The training did not
and in particular those aspects that ular joint to the technicians involved in cover the fundamentals of joint-mak-
might impact on plant integrity: its assembly, and leaks discovered dur- ing, but focussed on:
Weld quality is ensured by good prac- ing leak testing can cause significant The importance of high standards in
tice; qualified welders, approved proce- and costly delays to the startup. joint making
dures and post weld non-destructive During leak testing after the 1990 The benefits of identifying defects in

133
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT

invasive inspection. There has been an


Worklist analysis including 2002 shutdowns increase in the cleaning workload, part-
ly due to increases in the shutdown
interval and partly due to re-categorisa-
Work type 1993 shutdown 1997 shutdown 2002 shutdown
tion of work previously undertaken dur-
Repair 56 520 36 91 000 49 62 320 38
ing inspections.
Inspect and test 80 070 51 56 000 31 44 280 27
The modification workload has
Cleaning 7850 5 22 000 12 39 360 24
stayed reasonably constant and the
Modification 12 560 8 15 000 08 18 040 11
Total 157 000 100 184 000 100 164 000 100 repair workload has risen (the high fig-
SD interval 4 year 5 year 6 year ure in 1997 being due in part to a major
Per-year hours 39 250 36 800 27333 planned refurbishment of the main
cracked gas header), but the use of novel
Table 3 techniques has a considerable impact in
controlling the increase. The workload,
flange faces or flange misalignment dur- bolts <1in diameter) to be tightened measured in main trade manhours per
ing the maintenance period rather than using hand spanners. year of plant operation, has shown a
during leak testing Guidelines on acceptable levels of steady reduction as the shutdown inter-
The olefins joint-making procedure, flange alignment were also issued, based val has increased.
and the use of prescribed torque settings on the findings of laboratory and site Table 3 demonstrates that it is possi-
and tightening sequence testing work undertaken in cooperation ble to achieve increases in shutdown
The requirement for traceability by with the gasket supplier. It was estab- interval without incurring similar
tagging and the means of achieving this lished that for spiral wound gaskets mis- increases in the workload and hence the
Safety issues and other mandatory alignment of up to 1mm was usually duration of each event. As the table
requirements (the use of new gaskets on acceptable and this figure was incorpo- shows, reductions can be achieved in
all joints). rated into the joint making procedure. manhours per operational year, and in
The training was delivered using a The revision of the joint making pro- total event manhours. This has the
purpose-made video, which included cedure, and the calculation of torque added benefit of reducing a number of
statement and demonstration of best settings, was undertaken in partnership other risks (safety performance and
practices in mechanical joint integrity. with ABB Eutech, Hedley Purvis, and industrial relations risk, associated with
Trainees were required to take a written Klinger UK Ltd. large events).
validation test on completion of the Torque settings for piping flanges
training, and technicians who failed the were calculated using the Hedley Purvis Contractor management
test were required to repeat the training. Infomate Bolting Software System, and Once the shutdown workload is estab-
The majority of the questions asked in torque settings for heat exchanger and lished and the planning is complete, it is
the validation test were covered directly vessel flanges were calculated using BS necessary to deliver the work. The final
in the training video, but a small num- EN 1591 Part 1 flanges and their joints aspect in preparing and delivering a cost-
ber of other relevant questions were also design rules for gasketed circular effective shutdown is to examine the
included. flange connections. work done in the 2002 shutdown, and to
The overall pass rate for the valida- A total of 400 technicians and supervi- attempt to engage the contractors used
tion test was very high, but it was inter- sors were trained and validated in the in support of delivering the shutdown,
esting to note that although most joint-making procedure, and the applica- into the overall objectives of minimising
candidates could answer correctly the tion of the procedure was audited during the shutdowns cost and duration.
questions covered by the video, there the shutdown. Approximately 7300 The plan for the 2002 shutdown
were fewer correct answers to those flanged joints were made during the shut- showed an overall duration (product- to-
questions that relied on the technicians down, and any flange defects were identi- product) of 47 days, with a 28 day main-
general knowledge of joint-making. fied and repaired during the maintenance tenance window. The 19-day period of
In order to further improve control of period. During leak testing and plant shutting down the plant and prepara-
joint making, the requirement to use commissioning a small number of joints tion for maintenance, followed at the
controlled tightening of all joints was were required to be re-torqued, but no end of maintenance by leak testing and
introduced during the 2002 shutdown. joints that had been worked on during commissioning, is effectively fixed by
HSE Offshore Safety Notice 2/2000, Bolt- the shutdown were required to be remade. plant design and process conditions and
ing of Flanged Joints for Pressurised Sys- This was an excellent performance, is independent of the shutdown work-
tems, was issued to highlight poor and a clear demonstration of the bene- load. The main scope is to deliver
practice in joint-making and provide fits of high standards in gasketed joint- improvements in duration and cost,
guidance of safe practice in assembly, making supported by the use of provided by optimising the activities
tightening and inspection. The docu- controlled tightening and early identifi- undertaken during the 28-day mainte-
ment emphasises the importance of cation of flange defects. nance period.
controlled tightening of gasketed joints. The key shutdown objectives for the
The olefins plant joint-making proce- Worklist analysis delivery of the specified work were iden-
dure was revised prior to the 2002 shut- The final worklist for the 2002 shut- tified as cost control, EHS performance,
down to include the following down is summarised, in comparison programme achievement and quality of
requirement for controlled tightening: with previous events, in Table 3. work completed. Two main contracts
All joints with bolts above 1in diame- The table shows that the RBI process were let for the delivery of the event,
ter to be tightened to specified torques has delivered a significant reduction in and in both cases the contracts were
using hydraulic torque equipment the total workload associated with designed to focus the efforts of the con-
All other joints on hydrocarbon duty equipment inspection, despite the tractors in supporting the achievement
to be tightened to specified torques increase in SD interval. This is due to the of these objectives, thus aligning the
using calibrated hand torque wrenches elimination of unnecessary inspection objectives of the contractors with those
All other joints (service duties with and the extensive use of online non- of the client organisation, which were

134
P T Q WINTER 2002/03
RELIABILITY AND ASSET MANAGEMENT

achieved by establishment of a target manage, and although the contractors defect rectification, to reach the position
cost for each contract. The contracts were efficient at identifying variations where shutdown intervals are dictated
were written so that the contractors and that tended to increase cost, it was more by unavoidable cleaning requirements,
the client organisations would share difficult to identify or record variations rather than by mechanical deterioration
deviations from the agreed targets. that tended to reduce cost. Ultimately, that triggers the need to inspect equip-
Thus, if the total cost were within the use of target manhours in incentive- ment. This requires an optimisation of
budget there would be a gainshare, based contracts will only drive the con- equipment design, focussing on ele-
and if the total cost was above budget tractors to control and reduce cost if it ments in the process chain that suffer
there would be a painshare. can be established that the targets are from time dependent deterioration that
Fixed bonuses were agreed for achieve- not to be subject to variation after they influence the outage frequency. The cost
ment of plan and for achievement of have been agreed. benefits of improvements in engineering
specified EHS targets. Payment of these design can be optimised to whatever is
bonuses would be independent of shut- Conclusion the desired goal.
down cost performance (although in The foregoing discussion has noted that
reality there are strong links between cost for large petrochemical plants, there are This article is based on a paper presented at
and programme performance). In addi- benefits to be gained from increasing the ERTC Reliability Conference, Prague,
tion, establishment of contractor selec- the interval between plant shutdowns, 2325 September 2002.
tion and technician training in support but that these benefits depend on the
of quality objectives also helped in ability to control shutdown workload
achieving contract objectives. and duration. The aim is a strategy, Kevin McQuillan is olefins engineering
The application of these two con- which embodies the best combination manager for the Huntsman Petrochemicals
tracts was analysed after the event, and of low cost and acceptable business risk. olefins manufacturing site at Wilton, UK. He
the key learning is that the use of fixed A number of techniques for control- is responsible for engineering standards, and
bonuses for programme and EHS perfor- ling shutdown workload have been project and maintenance activities, and has
mance worked very well. In particular, described, and the benefits of these led the development of the Huntsman
on EHS performance, achievement of techniques have been demonstrated by method for the application of RBI.
the bonus was dependent on both input examining the history of plant shut- Kenny McGeachie is an olefins technical
measures, eg auditing compliance, and downs on the Huntsman No. 6 olefins engineer at the Huntsman ICI manufactur-
output measures, eg accident statistics. plant at Wilton. ing site at Wilton, with responsibilities for
The use of a target cost was less suc- On a given plant, it should be possi- engineering standards, asset life planning
cessful, primarily because the targets ble, by judicious application of RBI and and technical support to asset
were subject to variation as a result of techniques to improve reliability or to management and project personnel. He is
emergent work. This was difficult to reduce the work content of cleaning and a graduate in mechanical engineering.

135
P T Q WINTER 2002/03

Das könnte Ihnen auch gefallen