Sie sind auf Seite 1von 177

Tribhuwan University

Institute of Engineering
Pulchowk Campus
DEPARTMENT OF CIVIL ENGINEERING

FINAL REPORT ON
DESIGN OF BRIDGE OVER KERUNGA KHOLA,
CHITWAN

Supervisor
Asso. Prof. Nabin Chandra Sharma
Department of Civil Engineering

Prepared By
ANJAN LUITEL (069/BCE/012)
BIBEK KUMAR KHATRI (069/BCE/031)
BIGYA GYAWALI (069/BCE/034)
BIKAL SHAKYA (069/BCE/035)
BIKESH LAGE (069/BCE/037)
BUDDHIMAN TAMANG (069/BCE/047)

October, 2016
Tribhuwan University

Institute of Engineering
Pulchowk Campus

Department of Civil Engineering


Lalitpur, Nepal

Certificate
This is to certify that the final year project entitled DESIGN OF BRIDGE OVER
KERUNGA KHOLA, CHITWAN was submitted by the students to the DEPARTMENT
OF CIVIL ENGINEERING in partial fulfillment of requirement for the degree of Bachelor of
Engineering in Civil Engineering. The project was carried out under special supervision and
within the time frame prescribed by the syllabus.

Asso. Prof. Nabin Chandra Sharma

Project Supervisor

. .

Mr. Dinesh Gupta Mr. Rajan Suwal

Internal Examiner External Examiner

Dr. Kamal Bahadur Thapa

Head of Department

Department of Civil Engineering


Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ACKNOWLEDGEMENT
Were grateful to our Department of Civil Engineering, Pulchowk Campus for providing us
with this project to further enhance our knowledge in the field of civil engineering and its
application.

Bridge construction has been a predominant feature of human progress and evolution. It
has always been a symbol of peace and development. Hence, in the context of our country
which has more than 6000 rivers and rivulets, construction of bridge plays a very important
role in development and making it an undoubted reason for choosing this project.

Were indebted to our advisor and supervisor Assoc. Prof. Dr. Nabin Chandra Sharma for his
valuable time, instructions and guidance throughout the project.

Were heartily thankful to Mr. Chuman Babu Shrestha, capacity building specialist, LRBSU
for arranging us the field visit and providing the design data. Were so deeply obliged to site
engineer of both bridge sites for their supervision during our site visit.

i
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ABSTRACT
We aim to analysis and design a combination of T-Girder and Truss Bridge by
using the different theories of civil engineering. The combination of structural mechanics and
foundation engineering forms the base of our design.
The knowledge of influence line diagram, shear force diagram and bending moment
diagram are the essentials of this project. IRC codes were used as the guidelines in the design
of the bridge.
The superstructure components for truss (slab, stringer, crossbeam and truss girder)
and t-girder (slab, t-girder, cross beam) have been designed under class AA and class A
loading as prescribed by IRC. Pigeauds method was used in analysis of the slab and Hendry-
Jaeger method in the analysis of t-girders.
The substructure components include bearing, abutments, piers and foundation.
Considering the various forces acting on the substructure, spread foundation is provided and
the abutment is gravity type.
Hence with the help of our supervisor and the available materials and data, we have
made an effort to analyse and design The Bridge.

Salient Features

Particulars Required Information/ Range/ Values


Name of the Project Design of Bridge over Kerunga Khola
Location
Zone Narayani
District Chitwan
Village/ Town Kalyanpur V.D.C.
Name of Road -
Chainage of the Bridge Site -
Geographical Location
Easting 531972.828 (Longitude 841926)
Northing 3050960.78 (Latitude 273434)
Classification of Road Local Road
Type of the Road Surface Gravel
Terrain/ Geology Plain
Information on the Structure
Total Length of the Bridge 60 m
Span Arrangement 12 + 36 + 12 m
Total Width of the Bridge 7.2 m
No. of Lanes Two
Width of:
Carriageway 6m
Footpaths Not provided
Kerbs 0.6 m

ii
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Particulars Required Information/ Range/ Values


Type of Superstructure RCC T-Girder + Steel Truss
Type of Bearings Elastomeric Pad Bearings
Type of Abutments RCC rectangular abutment
Type of Piers RCC Solid Piers
Type and Depth of Foundation Spread Footing for Abutments
Well Foundation for Piers

Design Data
Live Load IRC Class AA (Wheeled and Tracked)
IRC Class A
Net Bearing Capacity of Soil 300 kN/m2
Design Discharge 95.54 m3/sec
Linear Waterway 46.43 m

SUMMARY OF QUANTITIES
Grade and Quantity of Concrete
In Superstructure M25 154.4 m3
In Substructure M20 548.136 m3
Grade and Quantity of Reinforced Steel
In Superstructure Fe415 12.12 MT
In Substructure Fe415 64.328 MT
Grade and Quantity of Structural Steel
In Superstructure E250 76.066 MT
In Substructure -
In Foundation -
Quantities of other materials
Brick Masonry -
Gabion Masonry -
Formworks 411.018 m2
Timber -
Stone Masonry -

SUMMARY OF COST
Superstructure Rs. 1,30,22,728 /-
Substructure Rs. 1,26,88,792 /-
Foundation Works -
Approach Road -
River Training Works -
Miscellaneous Works -
Grand Total Rs. 2,57,11,520 /-
Cost per m run (Truss) Rs. 3,05,578/-
(T-Girder) Rs. 84,248 /-

iii
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

NOTATION
Diameter of Bar
uv Shear Stress
m Partial Safety Factor
Ag Gross Area
Ah Horizontal Seismic Coefficient
Ast Area of Steel in Tension
Asv Area of Stirrups
bf Flange width
bw Web width
d Effective depth
d Effective Cover
D Overall Depth
E Youngs modulus of Elasticity
fck Characteristic Strength of Concrete
fy Characteristic Strength of Steel
I Importance Factor
Ip Polar Moment of Inertia
Ld Development Length
pc Percentage of Steel in Compression
pt Percentage of Steel in Tension
R Response Reduction Factor
Sa/g Average Response Acceleration Coefficient
Sv Spacing of Stirrups
Xu Actual depth of Neutral Axis
Xul Ultimate depth of Neutral Axis
Z Zone Factor

iv
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

TABLE OF CONTENTS

INTRODUCTION ....................................................................................................................................... 1
1.1 Introduction ............................................................................................................................ 1
1.2 Title of project work................................................................................................................ 1
1.3 Project assignment.................................................................................................................. 1
1.4 Objectives................................................................................................................................ 2
1.5 Client Requirements ............................................................................................................... 2
METHODOLOGY ...................................................................................................................................... 3
2.1. Acquisition of Data .................................................................................................................. 3
2.2. Structural Planning and Preliminary Design ........................................................................... 7
2.3. Idealization and Analysis of bridge structure........................................................................ 13
ACQUISITION OF DATA FOR DESIGN ..................................................................................................... 17
3.1 Topographical Survey............................................................................................................ 17
3.2 Geology and Topography ...................................................................................................... 17
3.3 Hydrology .............................................................................................................................. 18
3.4 Observation visit and Verification of data ............................................................................ 21
SELECTION OF BRIDGE TYPE ................................................................................................................. 24
STRUCTURAL PLANNING AND PRELIMINARY DESIGN .......................................................................... 25
T-Beam Bridge ................................................................................................................................... 25
Truss Bridge....................................................................................................................................... 27
ABUTMENT/PIER HEIGHT CALCULATION: ......................................................................................... 28
STRUCTURAL ANALYSIS AND DESIGN OF BRIDGE COMPONENTS ........................................................ 29
A. Design of RCC T-Girder (12 m span) bridge .............................................................................. 29
1. Analysis and design of Deck slab .......................................................................................... 29
2. Analysis and Design of Main Girder ..................................................................................... 44
III. Analysis of Cross Beam ..................................................................................................... 65
IV. Design of Elastomeric bearing .......................................................................................... 68
B. Design of Steel Truss (36 m span) bridge .................................................................................. 75
1. Design of Deck Slab .............................................................................................................. 75
2. Design of stringer beam ....................................................................................................... 76
III. Design of cross girders ...................................................................................................... 78

v
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

IV. Design of Steel Trusses ..................................................................................................... 80


V. Design of Truss Joints ........................................................................................................ 90
VI. Consideration of Wind Load on Member Stresses ........................................................... 91
VII. Consideration of Seismic Force ......................................................................................... 94
VIII. Design of Bracings ............................................................................................................. 95
IX. Design of Connections .................................................................................................... 100
X. Design of Elastomeric bearing for truss .......................................................................... 107
C. Design of RCC Abutment ......................................................................................................... 116
1. Planning and Preliminary Design........................................................................................ 116
2. Analysis and Design of Abutment Cap ............................................................................... 118
III. Analysis and Design of Abutment Stem .......................................................................... 119
IV. Design of Dirt Wall .......................................................................................................... 126
V. Analysis and Design of Spread Footing ........................................................................... 130
D. Design of RCC Solid Pier .......................................................................................................... 134
1. Planning and preliminary design ........................................................................................ 134
2. Load Calculation ................................................................................................................. 135
III. Analysis and Design of Pier Cap ...................................................................................... 139
IV. Analysis and Design of Pier Stem .................................................................................... 140
DRAWINGS .......................................................................................................................................... 150
APPROXIMATE ESTIMATES ................................................................................................................. 151
CONCLUSION AND RECOMMENDATIONS........................................................................................... 155
BIBLIOGRAPHY .................................................................................................................................... 156
ANNEXES ............................................................................................................................................. 157
Detail Design of Connections at Truss Joints .................................................................................. 157

vi
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

INTRODUCTION
1.1 Introduction
Bridges has been a predominant feature of human progress and evolution. Bridges
are used by people and vehicles for crossing rivers, lakes, ravines, canyons, railroads and
highways. Bridges must be strong enough to safely support their weight as well as the
weight of the vehicle that pass over it.
As Nepal is a mountainous country with a lot of river and rivulets, we need a lot of
bridges just to join one part of the country to another. So we need to construct a lot of
bridges to ease the extension of road network as well as to carry out other development
works in an efficient way. So there is a huge potential of bridge engineering in Nepal.
In this project we are assigned to design a bridge over Kerunga Khola joining Devi
Mandir Chowk of Madhi V.D.C. to Kerunga Chowk of Kalyanpur V.D.C. of Chitwan
district. As it is a local road so a single lane bridge shall suffice. But as per the provisions
in Nepal Road Standards (a minimum of 6 m carriageway for bridges longer than 50 m),
the bridge will be designed as a two-lane bridge. We are supposed to design the most
economic bridge for this section based of the various data provided by LRBSU. This
report is also prepared as a part of project work for the fulfilment of the Project-II as per
the syllabus of Bachelor of Civil Engineering fourth year second part.
In Nepal, mostly RCC T-beam superstructure is preferred as the resources to design
and construct are readily available in Nepal. But for understanding of various other
superstructures, we chose to use a Steel Truss bridge along with the T-girder over the
river. The variation in design procedures for the two types and a need to accommodate
these superstructures over the pier has helped to enhance our understanding of the
essentials of Bridge Engineering.

1.2 Title of project work


The main objective of this project is to design a bridge over Kerunga Khola by using
the Limit State approach of design. So this project is entitled as Design of Bridge over
Kerunga Khola, Chitwan.

1.3 Project assignment


Following assignments were completed during the completion of the project:
1.1.1. Study of topographic, geological, hydrological, geotechnical and traffic
condition of bridge site from previous reports.
1.1.2. Visit of bridge site and preparation of site observation report including
verification of data required.
1.1.3. Finding the different alternate span arrangements of bridge for the site and
comparing them.
1.1.4. Carryout design and detailing of selected bridge type.
1.1.5. Design of bearing.
1.1.6. Design of abutment and pier.
1.1.7. Design of foundation.

1
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

1.1.8. Preparation of detail drawing of bridge superstructures with its all


components, abutments, pier, bearing and footing required for the construction
of selected bridge type.

1.4 Objectives
As the title suggests the main objective of this project is to analyse and design the
Steel Truss Bridge by Limit State Method. In addition to this following objectives were
set while fulfilling the above maintained assignments:
a. To be familiar with the bridge and its design.
b. To recognize various types of bridges.
c. To know about various type of loading and their forms of application.
d. To understand various methods used in the design of the structural component of
loading of bridge and their limitations.
e. To be familiar with the standard specification regarding the design of bridge.
Thus the objective of this project is to obtain the basic ideas of bridge building.

1.5 Client Requirements


The bridge was designed for LRBSU as per their requirement based on the present
need of the site and possible future need. The requirements of the bridge to be
designed are as follows:
Type of Road Local Road
Footway No
Wearing surface Asphalt Concrete
Bridge type Permanent

2
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

METHODOLOGY
2.1. Acquisition of Data

2.1.1. Preliminary Data


For the design of our bridge the preliminary data needed was acquired from the report prepared by
consultancy but in actual practice it is done by following methods.
Site selection survey
Site selection survey is done by a team of bridge engineer, geotechnical engineer, surveyor and hydrologist.
After consultation with local residents, technical personnel of Divisional Road Office of the site, proposed
bridge alignment is fixed.
Topographical survey
Tachometric survey is carried for detailed engineering survey of the proposed bridge site. Theodolites, level
machines, staffs and measuring tape are usually used for detailed survey.
After consultation with the technical personnel and the local villagers and as directed by the river morphology;
an axis joining line joining left bank and right bank is fixed. Temporary Benchmark is also fixed.
The bridge site detailing area covers a suitable region along the length of river both upstream and
downstream. It also covers left and right banks along the existing approach roads. L-section of approach road
and river measured and also the benchmarks and bridge points are shown in contour maps.
Geotechnical Investigation
Geotechnical investigation is one of the major parts of the project work for the design of the proposed bridge
at Kerunga Khola in Chitwan district. Geotechnical investigation works includes core drilling, test pitting, visual
investigation at site. Detail report and test results with bore logs are included in the actual project report.
For our project the site and its contour map, hydrological data and geotechnical data were provided by LRBP
(Local Road and Bridge Programme).
2.1.2. Hydrology
Methods
The maximum discharge which a bridge across a natural stream is to be designed to pass can be estimated by
the following methods:
a) By using one of the empirical formulae applicable to the region;
b) By using the rational method involving the rainfall and other characteristics for the area;
c) By the area velocity method, using the hydraulic characteristics of the stream such as cross sectional
area, and the slope of the stream;
d) From any available records of the flood discharges observed at the or at any other site at the vicinity.
It is desirable to estimate the flood discharge by all or at least two of the above methods. These methods are
briefly discussed here.

A. Empirical formulae
Empirical formulae for flood discharge from a catchment have been proposed of the form:
Q=CAn
Where, Q=maximum flood discharge in m3 per second.
A= catchment area in Km2.
C= constant depending on the nature of the catchment and the location.
n= constant.
A popular empirical formulae of the above type is Ryves formulae given by equation
Q=CA2/3

3
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

The value of C is taken as 6.5 for the tracts near the coast, 8.5 for the areas between 25 and 50 km of
the coast and 10 for the limited areas near hills.
B. Rational formulae
A rational formula for the flood discharge should take into account the intensity, distribution and
duration of rainfall as well as the area, shape, slope, permeability and initial wetness of catchment.
Many complicated formulae are available in treatises on hydrology. A typical rational formula is:
Q=AIo
Where, Q= maximum flood discharge in m3 per second
A= catchment area in Km2.
Io= peak intensity of rainfall in mm per hour.
= a function depending upon characteristics of catchment in producing the peak run-off.
=0.56Pf/ (to+Io)

to= concentration time in hours.


to= (0.88 L3/H)0.35
L= distance from the critical point to the bridge site in kilometres.
H= difference in elevation between the critical point and the bridge site in meters.
P= percentage coefficient of run-off for the catchment characteristics.
F= a factor to correct for the variation of intensity of rainfall I o over the area of the catchment.

C. Area-velocity method
The area-velocity method based on the hydraulic characteristics of the stream is probably the most
reliable among the methods of determining the flood discharge. The velocity obtaining in the stream
under the flood conditions is calculated by Mannings or similar formula: Mannings formula is used
here. The discharge is given by equation:
Q= AV
Where, Q= discharge in m3 per second.
A= wetted area in m2.
V= velocity of flow in m/s
= (1/n) R2/3S1/2
n= coefficient of roughness.
S= slope of stream.
R= hydraulic mean radius in m.
= wetted area in m2/wetted area in meters.
The wetted area and wetted perimeter are obtained from the cross-section of the stream at site
drawn to scale with the floods levels marks therein. The quantity S in equation denotes the slope of
stream.
D. Estimation from flood marks
If flood marks can be observed on an existing bridge structure near the proposed site, the flood
discharge passed by the structure can be estimated reasonably well, by applying appropriate
formulae available in treatises on hydraulics. It is possible by inspection to ascertain the flood levels
soon after a flood. Sometimes, these flood marks can be identified even years after a flood, but it is
desirable to locate these as soon after the flood as possible.
Design discharge
The design discharge may be taken as the maximum values obtained from the least two method
mentioned. If the values obtained by two methods differ by 50%, then the maximum design discharge
is limited to 1.5 times the lower estimate. Freak discharge of high intensity due to failure of dam or
tank constructed upstream of the bridge site need not to be catered for. From consideration of

4
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

economy, it is not desirable to aim to provide for the passage of the very extraordinary flood that may
ever happen at a particular site. It may be adequate to design for a flood occurring once in a 20 years
in case of culverts and once in 100 years for bridges and to ensure that the rarer floods be passed
without excessive damage to structure.
Linear waterway
When the watercourse to be crossed in an artificial channel for irrigation or navigation, or when the
banks are well defined for artificial streams, the linear waterway should be full width of channel or
stream.
For large alluvial stream with undefined banks, the required linear waterway should be
determined using Laceys formula given by equation
L = CQ
Where, L= the linear waterway in m.
Q= the designed maximum discharge in m3 per second.
C= a constant, usually taken as 4.8 for regime channels, but may vary from 4.5 to 6.3
according to local conditions.
It is not desirable to reduce the linear waterway below that for regime condition. If a
reduction is affected, special attention should be given to afflux and velocity of water under the
bridge. With reduced waterway, velocity would increase and greater scour depth would be involved,
requiring deeper foundations. Thus, any possible saving from a smaller linear waterway will be offset
by extra expenditure on deeper foundations and protective works.
Afflux is the heading up of water over the flood level caused by the constriction of waterway
bridge site.it can be computed from equation
X = (v2/2g) ((L2/c2.L12)-1)
Where, X= afflux
V= velocity of normal flow in stream
g= acceleration due to gravity
L= width of stream in at H.F.L
L1= linear waterway under the bridge
c= coefficient of discharge through the bridge, taken as 0.7 for sharp entry and 0.9 for bell
mouth entry.
The afflux should be kept minimum and limited to 300mm. afflux causes increase in velocity in
downstream side, leading to greater scour depth and requiring deeper foundations. The road
formation level and the top level of the guide bunds are dependent on the maximum water level on
upstream side including afflux.

Economical span
Considering only the variable items for the given linear waterway, the total cost of the
superstructure increases with the increase or decrease in span length. The most economical span is
that for which the cost of superstructure equals the cost of sub-structure. This condition may be
derived as below:
Let,
A= cost of approaches
B= cost of two abutments including foundations
L= total linear waterway
l= length of one span
n= number of spans
P= cost of one pier, including foundation
C= total cost of bridge.
Assuming that the cost of superstructure of one span is proportional to the square of the span length,
total cost of superstructure equals n.kl2, where k Is a constant.

5
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

The cost of railing, flooring, etc., is proportional to the total length of bridge and can be taken as kL.
C= A + B + (n-1) P + nkl2 +KL
For minimum cost, dC/dL should be zero, we get
P= k.l2
Therefore, for an economic span, the cost of superstructure of one span is equal to the cost of
substructure of same span.
The economical span (le) can then be computed from the equation
Le= (P/k)
P and k are to be evaluated as average over a range of possible span lengths.
Location of pier and abutments
Pier and abutments should be as to make the use of best the foundation conditions
available. As far as possible the most economical span as above should be adopted. If navigational or
aesthetic requirements are to be considered, the span may be suitably modified. As a rule, the
number of span should be kept low, as pier obstructed water flow. If pier are necessary, odd number
of span should be preferred.
For small bridges with open foundations and solid masonry piers and abutments, the
economical span is approximately 1.5 times the height of pier or abutments, while that for masonry
arch bridges it is about 2 times the height of keystone above the foundation, the question has to be
examined in detail.
The alignment of pier and abutments should be, as far as possible, parallel to the mean
direction of flow in the stream. If any temporary variation in the direction and velocity of stream
current is anticipated, suitable protective works should be provided to protect the sub-structure
against the harmful effects on stability of the bridge structure.
Vertical clearance above H.F.L
For the high level bridges, a vertical clearance should be allowed between the H.F.L, and the
lowest point of the superstructure. This is required to allow for any possible error in the estimation of
the H.F.L., and the design discharge. It also allows floating debris to pass under the bridge without
damaging the structure.
The difference between the vertical clearance and the free-board is sometimes not clearly
understood. While vertical clearance is the difference in level between H.F.L. and the lowest point of
the superstructure, freeboard is associated with the approaches and guides bunds. The freeboard at
any point is the difference between the highest flood level after allowing afflux, if any, and the
formation level of the embankment on the approaches or the top level of guide bunds at that point,
for high level bridges, the freeboard should not be less than 600 mm.
Scour Depth
Scour of stream bed occurs during the passage of a flood discharge, when the velocity of
stream exceeds the limiting velocity that can be withstand by the particles of the bed material. The
scour should be measured with reference to existing structures near the proposed bridge site, if this is
possible. Due allowance should be made in the observed value for additional scour that may occur
due to the designed discharge being greater than the flood discharge for which the scour was
observed, and also due to increased velocity due to obstruction to flow caused by the construction of
bridge.
Where the above practical method is not possible, the normal depth of scour may be
computed by equation for natural streams in alluvial beds.
d=0.473(Q/f).33
Where,
d= normal depth of scour below H.F.L. for regime conditions in a stable
channel in meters.
Q=designed discharge in m3 per second
f=Laceys silt factor for a representative sample of bed material
The minimum depth of foundation below H.F.L. is kept at 1.33d for erodible strata

6
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

2.2. Structural Planning and Preliminary Design


Considering the fact that we had very little background in the field of bridge design, this project
turned out to be more strenuous than we had ever imagined. The fine guidance from our supervisor and
the books recommended by him combined with immense hard work from each one of us are the reasons
for the successful completion of this project. The books available in the library were also of great help.
Although they were few in number, the old reports on steel truss bridges and R.C bridges facilitated us
with plenty of necessary materials. Finally, the internet served us with the resources required for the final
touch up of this report.

a. Types of bridge
i. According to Function
Aqueduct
Viaduct
Highway
Railway
Road-cum-rail or Pipeline Bridge
ii. According to the material of construction
Timber
Masonry
Iron
Steel
Reinforced concrete
Prestressed concrete
Composite
iii. According to the type of superstructure
Slab
Beam
Truss
Arch
Suspension
iv. According to the position of bridge floor relative to superstructure
Deck
Through
Half through
Suspended
v. According to the inter-span relations
Simple
Continuous
Cantilever
vi. According to the method of connection of different parts of superstructure
Pin connected
Welded
Riveted
vii. According to the road level relative to the high flood level of the river
High-level
Submersible
viii. According to the method of clearance for navigation
High-level
Movable-Bascule
Movable-swing
ix. According to anticipated type of service and duration of use
Permanent

7
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Temporary
Military
b. Selection of Bridge Site
It may not be always possible to have a wide choice of sites for a bridge. This is particularly so in case of
bridges in urban areas and flyovers. For rivers bridges, in rural areas, usually a wider choice may be
available. The characteristics of an ideal site for a bridge across a river are:
A straight reach of river.
Steady river flow without whirls and across currents.
A narrow channel with firm banks.
Sustainable high banks above high flood level on each side.
Rock or other hard in-erodible strata close to the river bed level.
Proximity to a direct alignment of the road to be connected.
Absence of sharp curves in the approaches.
Absence of expensive river training works.
Avoidance of excessive underwater construction.
In selection a site a care should be taken to investigate a number of probable alternative sites and then
decide on the site which is likely to serve the needs of the bridges at the least cost.
c. Loading
IRC loads for the bridge design:
According to IRC: 6-2000, road bridges and culverts are classified on the basis of loadings that they are
designed to carry.

IRC class AA loading:


This loading is to be adopted within certain limits, in certain existing or contemplated industrial areas, and
along certain specified highways and areas. Bridges designed for class AA loading should be checked for
class A loading is considered in each lane.
IRC class A loading:
This loading is normally considered on all in which dominant bridges and culverts are constructed. One
train of class A loading is considered in each lane.
IRC class B loading:
This loading is normally considered when the structure is temporary and for bridges in specified area.
Structures with timber spans are to be regarded as temporary structures.
d. Superstructure
The basic function of bridge superstructure is to permit the uninterrupted smooth passage of traffic
over it and to transmit the loads and forces to the substructure safely through the bearings. Although it is
difficult to stipulate the aesthetic requirements, it should, however, be ensured that the type of
superstructure adopted is simple, pleasing to the eye, and blends with the environment.
The superstructure of any bridge must be designed such that it satisfies geometric and load carrying
requirements set forth by its owner. This geometric requirement depends upon the number and widths of
traffic lanes and footpaths that have to be carried across. They also depend on overall alignment and
various horizontal and vertical clearances required above and below the roadway. The superstructure
designed has to meet various structural design requirements such as strength, stiffness and stability.
The horizontal and vertical alignment of a bridge is governed by the geometrics of the highway,
roadway or channel, it is crossing. For girder type bridges, the girders may either be curved or straight,
and may be aligned on chords between supports with the deck slab built on the curve. The following
points require close examination when girders are aligned on a chord:
Non symmetric deck cross section
Deck finish of the warped surface
Vertical alignment of the curbs and railings, to preclude visible discontinuities
Proper development of super elevation
The components of superstructure are as follows:
Lighting

8
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

The lighting of the bridge is generally in accordance with the provisions of the authority having jurisdiction
on that area.
Drainage
The transverse drainage of the roadway is usually accomplished by providing suitable crown in the
roadway surface, and the longitudinal drainage is accomplished by camber or gradient.
Traffic lane
Roads designed for traffic flow can be single lane, double lane or more. Road width in meters should be
divided by 3.65 and the quotient approximated to the nearest whole number of design traffic lanes. We
have designed our bridge with two traffic lane.
Road width
Road width is the distance between the roadside faces of the kerbs which depends on the number and
width of traffic lanes and the width of the bounding hard shoulders. For our project we have designed
road width of 7.5 m.
Footpaths
Footpaths or walkways are generally provided where pedestrian traffic is anticipated, but not on major
arteries or in country sides. Its width is 1.5 m generally, but may be as narrow as 0.6 m and as wide as 2.5
m depending on the requirements. For our project we have designed footpath of 1 m wide and 300 mm
deep.
Road kerb
The road kerb is either surmountable type or insurmountable type. In the absence of walkways, a road
kerb is combined with parapet.
Parapets
Parapets can be of many shapes and of variable sturdiness. They are designed to prevent a fast moving
vehicle of a given mass from shooting off the roadway in the event of an accidental hit. Their height varies,
but it should be at least 700 mm. For our project we have designed parapet of 1000 mm depth and 150
mm width.

Handrails
The parapets are usually mounted by metal hand rail, about 350 mm high. Their roadside face is double
sloped. For our project we have designed handrail of size 50 mm50 mm.
Crash barriers
Sometimes walkways are protected from the erring vehicular traffic by crash barriers which act as
insurmountable kerbs and deflect the hitting vehicles back into the traffic lane.
Expansion and roadway joints
To provide for expansion and contraction, joints should be provided at the expansion end of spans, at
other points, where they may be desirable. Joints are preferably sealed to prevent erosion and filling of
debris.
Medians
On expressways and freeways, the opposing traffic flows are separated by median strips. These reduce the
possibility of accidents due to head on collisions.
Super-elevation
The super-elevation of the surface of a bridge on a horizontal curve is provided in accordance with the
applicable standard. This should preferably not exceed 0.06 m per meter, and never exceed 0.08 m per
meter.
e. Substructure
Substructure of a bridge refers to that part of it which supports the structure that carries the roadway or
the superstructure. Thus substructure covers pier and abutment bodies together with their foundations,
and also the arrangements above the piers and abutments through which the superstructure bears on the
structure. The latter are called bearings.
i.Foundation

9
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

A foundation is that part of the structure which is in direct contact with the ground and transmits loads
to it. A footing is that part of the foundation that transmits the loads directly to the soil.
Types of Foundations:
A. Deep Foundations
Deep foundations generally have depth greater than the width. They are constructed by various
special means. They are of following types:
Piles
Piles are essentially giant sized nails that are driven into the subsoil or are placed in after
boring holes in the subsoil. The giant sized nails that are driven into the subsoil or are placed
in after boring holes in the subsoil. The giant sized nails are made of concrete, steel or timber
and can be square, rectangular, circular or H-shaped in section. A group of piles is capped
together at top, usually by a reinforced concrete cap, to support the pier of crapped together
at top, usually by a reinforced concrete cap, to support the pier or abutment body above.
Caissons or wells
Caisson is constructed at open surface level in portions and sunk downwards mechanically by
excavating soil from within the dredge hole all the way till its cutting edge reaches the
desired founding level. The well is then effectively scaled at bottom and at least partly filled
by sand. The surface level and the portions near it are capped. The pier or abutment is then
constructed on the cap.
B. Shallow Foundations
A foundation is shallow if its depth is less than or equal to its width. These are generally placed after
open exaction, and are called open foundations. The design of open foundations is based on complete
subsoil investigations. But in case of low safe bearing capacity of soil, such foundations have to be
disallowed. The selection of the appropriate type of open foundation normally depends upon the
magnitude and disposition of structural loads, requirements of structures (settlement characteristics,
etc.), type of soil or rock encountered, allowable bearing pressures, etc. Where rocky stratum is
encountered at shallow depths, it may be preferable to adopt open foundations because of its
advantage in permitting proper seating over rock and speed of construction work. They are of
following types:
Spread Footing (Isolated footing, combined footing, strip footing)
An isolated footing is a type of shallow foundation used to transmit the load of an isolated
column to the subsoil. This is the most common type of foundation. The base of the column
is enlarged or spread to provide individual support for the load.
A spread footing which supports two or more columns is termed as combined footing. The
combined footing may be rectangular in shape if both the columns carry equal loads, or may
be trapezoidal if they carry unequal loads. If the independent spread footings of two columns
are connected by a beam, it is called strap footing. A strap footing may be used where the
distance between the columns is so great that a combined trapezoidal footing becomes quite
narrow.
The strap footing consists of single continuous R.C. slab as foundation of two or three or
more columns in a row. It is suitable at locations liable to earthquake activities. It also
prevents differential settlement. In order to have better stability a deeper beam is
constructed in between the columns. It is also known as continuous footing.
Mat or Raft Footing
A raft or mast is a footing that covers the entire area beneath a structure and supports all the
walls and columns. When the allowable soil pressure is low or the loads are heavy the use of
spread footings would cover more than one half of the area and it may prove more
economical to use mat or raft foundation. The mat or raft tends to bridge over the erratic
deposits and eliminates the differential settlement. It is also used to reduce settlement
above highly compressive soils, by making the weight of structure and raft approximately to
weight of soil excavated.
ii.Bearing

10
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Bearings are provided in bridges at the junction of the girders or slabs and the top of pier and
abutments. Bearings transmit the load from the superstructure to substructure in such a way that the
bearing stresses developed are within the safe permissible limits. The bearings also provide for small
movements of the superstructure. The movements are induced due to various reasons such as:
Movement of the girders in the longitudinal direction due to variations in the temperature
The deflection of the girder causes rotations at the supports
Due to sinking of the supports the vertical movements are developed
Movements due to shrinkage and creep of concrete
In the case of prestressed girders, prestressing the girders cause movements of girders in the
longitudinal direction
Types of Bearings
a. Fixed Bearings
Fixed bearings permit rotations while preventing expansion. They are of the following types:
Steel Rocker bearing
R.C. Hinge bearing
b. Expansion Bearings
Expansion bearings accommodate both horizontal movements and rotations, they are of
following types:
Sliding Plate bearing
Sliding cum Rocker bearing
Steel Roller cum Rocker bearing
R.C Rocker cum Roller bearing
Elastomeric bearing
Elastomeric Bearing
Elastomeric bearings are widely used in present times as they have less initial and maintenance cost.
Besides occupying a smaller space, elastomeric bearings are easy to maintain and also to replace
when damaged, chloroprene rubber termed as neoprene is the most commonly used type of
elastomer in bridge bearings. Neoprene pad bearings are compact, weather resistant and flame
resistant. Hence, nowadays elastomeric bearings have more or less completely replaced steel rocker
and roller bearings.
iii.Pier
The bridge supports in between the abutment supports are referred to as piers. The choice of
construction of the bridge deck will dictate the choice of the type of pier. If support is required at
intervals across the full width of the bridge deck, then some form of supporting wall or portal frame is
made for the pier. However when deck has some capacity within itself to span transversely at an
intermediate support positions by means of a diaphragm within the depth of the deck, there is wider
choice available for pier.
Simplicity in the formation of a pier not only has the merit of providing easier and more economical
construction, but it is also likely to produce more attractive result. But for some special cases,
complex shapes may be adopted. In this case the bearings are placed at the heads or the feet of the
piers.
Types of Pier
Depending on the type, size and dimensions of the superstructure, the following types of piers are in
general use:
a) Solid type pier
The solid type pier is generally built using brick or stone masonry or concrete. This type with
cut ease water is widely used for river bridges.
b) Trestle type pier
The trestle type pier comprises of a number of reinforced concrete columns with a
concreting cap at the top. The trestle type of pier finds wide applicability in the case of
flyovers and elevated roadways generally used for crossing in city roads.
c) Hammer-head type pier

11
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Hammer-head type of pier consists of a massive single pier with cantilever caps on opposite
sides resembling the head of a hammer. This type of pier is generally suitable for elevated
roadways and when used in river bridges, there is minimum restriction of waterway.
d) Cellular type pier
For the construction of massive piers carrying multilane traffic, it is economical to use cellular
type reinforced concrete piers which results in the savings of concrete. However cellular type
piers require costly shuttering and additional labor for placing of reinforcements. For tall
piers, slip forming work can be adopted for rapid construction.
e) Framed type pier
R.C. type piers are aesthetically superior and rigid due to monolithic joints between the
vertical, inclined and horizontal members. These type of piers are ideally suited to reduce the
span length of main girders on either side of center line of the pier resulting in savings in the
cost of superstructure. However this type of construction requires two expansion joints at
close intervals with increase of maintenance cost.
Forces acting on piers
The various forces to be considered in the design of piers are as follows:
1. Dead load of superstructure and pier.
2. Live load of vehicles moving on the bridge.
3. Effect of eccentric live loads.
4. Impact effect for different classes of loads.
5. Effect of buoyancy on the submerged part of the pier.
6. Effect of wind loads acting on the moving vehicles and the superstructure.
7. Forces due to water current.
8. Forces due to wave action.
9. Longitudinal forces due to tractive effort of vehicles.
10. Longitudinal forces due to braking of vehicles.
11. Longitudinal forces due to resistance in bearings.
12. Effect of earthquake forces.
13. Forces due to collision for piers in navigable rivers.
The stability analysis for the piers is generally made by considering some of the critical forces which
will have significant effect on the stresses developed in the piers.
Design of pier
The salient dimensions of pier like the height, pier width and batter are determined as follows:
a) Height
The top level of pier is fixed to 1 to 1.5m above the high flood level, depending upon the
depth of water on the upstream side. Sufficient gap between the high flood level and top of
pier is essential to protect the bearings from flooding.

b) Pier Width
The top of pier should be sufficient to accommodate the two bearings. It is usually kept at a
minimum of 600 mm more than the outer to outer dimension of the bearing plates.

c) Pier Batter
Generally the sides are provided with a batter of 1 in 20 to 1 in 24. Short piers have vertical
sides. The increased bottom width is required to restrict the stresses developed under loads
within safe permissible values.

d) Cut and Ease Waters


The pier ends are shaped for streamlining the passage of water. Normally the cut and ease
waters are either shaped circular or triangular.

iv.Abutment
Abutments are end supports to the superstructure of a bridge. Abutments are generally built using
solid stone, brick masonry or concrete. An abutment has three distinct structural components:

12
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

a. Breast wall
b. Wing wall
c. Back wall
The design of abutment is done precisely in the same manner as the design of pier. The dimensions
are first determined from the practical point of view and its stability is subsequently tested. The
important additional force which the abutment has to withstand is the earth pressure of the earth
filling behind the abutment. The minimum top width of the abutment should be 3 to 4 feet with the
front batter of 1 in 24 and back batter of 1 in 6. Eddies erode the toes of the bank behind the
abutment and thus the cost of maintenance of the road is increased. In order to overcome this defect
and give the smooth entry and exit to the water, splayed wing walls to the abutment are constructed.
Function
To finish up the bridge and retain the earth filling
To transmit the reaction of the superstructure to the foundation.
Design
Height: Height is kept equal to that of piers.
Abutment batter: The water face is kept vertical or a small batter of 1 in 24 to 1 in 12 is given. The
earth face is provided with a batter of 1 in 3 to 1 in 6 or it may be stepped down.
Abutment width: The top width should provide enough space for bridge bearings and bottom
width is dimensioned as 0.4 to 0.5 times the height of the abutment.
Length of abutment: The length of abutment must be at least equal to the width of the bridge.
Abutment cap: The bed block over the abutment is similar to the pier cap with a thickness of 450
to 600 mm.

Forces acting on abutment


Dead load due to superstructure
Live load due to superstructure
Self weight of the abutment
Longitudinal force due to tractive effort and braking
Forces due to temperature variation
Earth pressure due to backfill
Abutment should be designed in such a way that it can resist the forces mentioned above.

2.3. Idealization and Analysis of bridge structure

2.3.1. Influence Line Diagram


Usually the structures are analysed for loads which do not change their points of application on the
structure. Very often structures have to be analysed for a number of parallel moving loads which keep on
changing their positions on the structure. In such cases the internal stresses in the structure at any given point,
which depend on the positions of the loads, keep on varying as the loads take up different positions on the
structure.
A typical instance is a bridge loaded with a number of moving vehicles, which are then said to constitute a train
of wheel loads. In order to design such structures it is not enough to analyse the structure for a given position
of loads and calculate the stress resultants namely: bending moments, radial and normal shear forces at any
section in a member of the structure. The engineer must know the maximum values of stress resultants, both
positive and negatives, at any section of the structure. Sometimes the designer would even like to know the
maximum deflection at a given point when a structure is subjected to moving loads.
The maximum value of the stress resultants or the deflection at a given section could be found by taking a
number of trial positions of the loads. Such a procedures apart from being time consuming is also uncertain.
The task is very much simplified by using the concept of influence line.

13
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

An influence line is a graph or curve showing the variation of any function such as reaction, bending moment,
shearing force, deflection etc. at a given point of a structure, as a unit load parallel to a given direction, crosses
the structure.
An influence line is thus a relation between the required function at any given point of the structure and the
position of a moving unit load on the structure.
The direction of the moving unit load depends on the nature of loading to be expected in the structure.

Use of Influence Line Diagrams


Using the principle of superposition, the following two types of problems can be solved with the help of
influence lines:
First, if the influence line for a function is known, its value for a given position of a number of parallel
moving loads can be found.
The second application is of far more practical importance, influence lines can be used to locate very
easily that particular position of a number of parallel moving loads on a structure, which will give the
maximum positive or maximum negative value of a function at a given point on the structure.

2.3.2. Pigeauds Method


Pigeauds method is used for the analysis of slabs spanning in two directions.
Analysis of Slab Decks
i) Slabs spanning in one direction
For slabs spanning in one direction, the dead load moments can directly be computed assuming the slab to be
simply supported between the supports. Bridges deck slabs have to be designed for I.R.C. loads, specified as
class AA or A depending on the importance of the bridge. For slabs supported on two sides, the maximum
bending moment caused by a wheel load may be assumed to be resisted by an effective width of slab
measured parallel to the supporting edges,
For a single concentrated load the effective width of dispersion may be calculated by the equation,
be=Kx(1-x/L)+bw
Where, be=Effective width of slab on which load acts
L=Effective span
x=Distance of centre of gravity from nearer support
bw=Breadth of concentration of load
K=a constant depending on the ratio (B/L) and is compiled in IRC:21-2000 for simply supported and
continuous slabs.

ii) Slabs spanning in two directions


In the case of bridge decks with tee beams and cross girders, the deck slab is supported on all four sides and is
spanning in two directions. The moments in two directions can be computed by using the design curves
developed by M. Pigeaud.
The method developed by Pigeaud is applicable to rectangular slabs supported freely on all four sides and
subjected to a symmetrically placed concentrated load as shown in the figure below.
The notations used are as follows:
L=Long span length
B=Short span length
u,v=Dimensions of the load spread after allowing for dispersion through the deck slab
K=Ratio of short to long span=(B/L)
M1=Moment in the span direction
M2=Moment in the long span direction
m1 and m2=coefficient for moment along short and long direction

14
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

=poisons ratio for concrete generally assumed as 0.15


W=Load from the wheel under consideration
The dispersion of the load may be assumed to be at 45 through the wearing coat and deck slab according to
IRC:21-2000 code specifications. Consequently, the effect of contact of wheel or track load in the direction of
span shall be taken as equal to the dimension of the tyre contact area over the wearing surface of the slab in
the direction of slab plus twice the overall depth of the slab inclusive of the thickness of the wearing surface. It
is sometimes assumed to be at 45 through the wearing coat but at steeper angle through the deck slab.
The bending moments are computed as
M1=(m1 + m2) W
M2=(m2 + m1) W

Fig: Dispersion of wheel load through deck slab

Fig: Dispersion of wheel load through wearing coat


The values of the moment coefficients m1 and m2, depend upon parameters (u/B), (v/L) and K.
Curve to compute moment coefficients of slabs completely loaded uniformly distributed load or dead load of
slab for different values of K and 1/K is also given below. The Pigeauds curves used for the estimation of the
moment coefficients m1 and m2 for value of k= 0.9 used in our design also follows.

15
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Fig: Moment coefficients for slabs completely loaded with uniformly distributed load,
coefficient is m1 for K and m2 for 1/K

2.3.3. Hendry-Jaeger Method


In this method, the cross beam can be replaced in the analysis by a uniform continuous transverse medium of
equivalent stiffness. According to this method, the distribution of loading in an interconnected bridge deck
system depends on the following three dimensionless parameters.
12
=A= 4 ( )3

2
=F= ( )
2
1
c=
2
where L = span of the bridge
h = spacing of longitudinal girders
n = no. of cross beams
EI,CJ = flexural and torsional rigidities respectively of one girder
EI1,EI2 = flexural rigidities of the outer and inner longitudinal girders, where these are different
EIt = flexural rigidities of one cross beam
In case of beam and slab bridge without cross beams, nEIt in above equation is to be replaced by L.EIt, where
the latter gives the total flexural rigidity of the slab deck. Normally, for reinforced concrete T-beam bridges,
the flexural rigidities of the outer and inner longitudinal girders will be nearly equal.
The parameter A is the most important of the above three parameters. It is a function of the ratio of the
span to the spacing of longitudinals and the ratio of transverse to longitudinal rigidities. The second parameter
F is a measure of the relative torsional rigidity of the longitudinals and is difficult to determine accurately, due
to uncertainties surrounding the CJ values for practical girder sections.
Graphs giving the values of the distribution coefficients (m) for different conditions of number of
longitudinals (2-6) and two extreme values of F i.e. zero and infinity are available.

mF = m0+(m-m0)
3+

where mF is the required distribution coefficient and m0 and m are respective coefficients for F=0 and F=.
Using the graph this method is applied.

16
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ACQUISITION OF DATA FOR DESIGN


For the purpose of design we adopted the design data provided by LRBP. The
acquisition of data as given in the report prepared by A-One consultancy P .Ltd. is as
below:
3.1 Topographical Survey
Topographical survey was carried out to prepare topographical map for pertinent
information that may be required for design, construction and maintenance.
Centre line of proposed bridge site
The bridge axis as established during site selection was surveyed. The elevation and
co-ordinates of the bore holes along the axis were surveyed.
Bench marks
The reference bench mark was established to start with the survey works. The suitable
and convenient place for starting bench mark was marked as BM1 on the permanent
concrete pillar which is situated near by the bridge site on left bank of the river.

3.2 Geology and Topography


This report on soil investigation of Kerunga Khola Bridge in Chitwan discussed the sub-surface
exploration works carried out at the proposed site and presented the findings of the
investigation. The report is based on two boreholes:
The investigation work included boring, SPT Test, Laboratory tests and Analysis of
various test results to predict the allowable bearing capacity of sub-soil at the proposed
bridge site. The details of the investigation work as well as that of findings of the
analysis carried out are presented.

17
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

3.3 Hydrology
Hydro-Meteorological Data
There was no gauging station in Kerunga Khola. The stream flow data for this river were
not available. Hence the estimation of the flow for this river had to be determined from
other approaches. To determine Design discharge, following methods are used.
1. Rational Method
A typical rational formula is:
Q=A..l
Where, Q= Maximum flood discharge in m3 per second
A= catchment area km2
= peak intensity of rainfall in mm per hour
l = a function depending on the characteristics of the characteristics of
the catchment in producing the peak run-off
0.56
= tc+1
tc= concentration time in hours
= (0.87L3/H)0.385
L= distance from the critical point to the bridge site in kilometers
H= difference in elevation between the critical point and the bridge site
in meters
P= coefficient of run-off for the catchment characteristics
f= a factor to correct for the variation of intensity of rainfall over the area of
catchment
Here, A= 56.3 km2
= .2496 mm/hr
L= 39.8 km
H= 1152.89 m
tc=(0.87L3/H)0.385
= (0.8739.83/1152.89)0.385
=4.42 hr
P= 0.20
f= 0.813

0.560.200.813
l= 4.41+1
=0.0168

Q=A..l
=0.016853.60.2496
=0.8267 m3/sec

18
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

2. Area Velocity Method


A. From Available Field data, cross- section of River is shown figure below.

Average A=49.485m2 Average velocity = 0.203 m/s


Discharge (Q) = 49.48520.203 =20.09m3/sec
Since it is such a small value, we go in our field data

B. From our site Visit & levelling Data, cross-section of River is shown figure below.

Average A=224.58m2 Average velocity = 0.203 m/s


Discharge (Q) =224.5820.203 =91.18m3/sec

3. Empirical Formula
A. Ryves formula
Q= CA2/3
Where, Q= maximum flood discharge in m3 per second
A= catchment area in square kilometers
C= constant depending on the nature of the catchment and location

19
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For flat tracts, take C= 6.8


Now, Q = CA2/3
= 6.8 (56.3) 2/3
= 99.89 m3/sec

B. Modified Dickens Formula


QT= CTA0.75
1185
CT= 2.342 log(0.6T)log( )+4

+6
P=100 +6 , where a= perpetual snow area in sq. km = 0
T= return period in years = 50
A= Catchment area in sq. km= 53.6 sq. km
0+6
P= 10053.6+0 = 11.19
1185
CT= 2.342log(0.650)log(11.19)+4 = 11.00
QT= CTA0.75
= 1153.60.75
= 217.90 m3/sec

C. Fullers Method

Qmax= QT (1+2(2.59)-0.3 )
QT = Qav (1+ 0.8 logT)
Qav= Cf A0.8
Cf =1.03 for Nepal

Qav= Cf A0.8
= 1.0353.60.8
= 24.898 m3/sec
QT = Qav (1+ 0.8 logT)
=24.898(1+0.8log50)
=58.74 m3/sec

Qmax= QT (1+2(2.59)-0.3 )
53.6
= 58.74 (1+2(2.59)-0.3 )
= 106.07 m3/sec

20
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Discharge Calculation table


S.No Method Discharge

1 Rational Method 0.8267 m3/sec

2 Area Velocity Method 91.18m3/sec

3 Ryves formula 99.89 m3/sec

4 Modified Dickens Formula 217.90 m3/sec

5 Fullers Method 106.07 m3/sec

As discharges from Area-velocity method and Ryves method are close to each other, we
consider discharges from these two methods only.
Hence, Design Discharge = (91.18+99.89)/2 = 95.54m3/sec

Calculation of Linear Waterway & Scour Depth:


Linear Waterway = 4.75 = 4.7595.54
= 46.43m

Db = 95.54/46.43 = 2.058

Db2
Scour Depth = 1.34( )^0.33
2.0582
= 1.34( )^0.33
1.25
= 2m
The river at proposed bridge site is in regime condition and water way width is about
46.43m.

3.4 Observation visit and Verification of data


Site visit was arranged at Kerunga Khola Bridge located in Kalyanpur VDC, Chitwan to
verify the data provided during the design.

Survey Observations
We first located the available benchmarks at site and the bridge axis points (Axis Left and
Axis Right). We transferred RL from the benchmark and then carried out leveling work along
the proposed bridge axis to obtain a tentative cross section. We also identified the high
flood marks after consulting with the local people and then transferred RL for the high flood
marks. The linear waterway at the bridge axis c/s was also found out by taping. The
observed data for both bridge sites are as follows:

21
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

BRIDGE SITE SURVEY


LEVELLING DATA
LOCATION: KERUNGA KHOLA
Hydrological Observations

REDUCED
STATIONS CHAINAGE BS IS FS RISE FALL LEVEL(m)
BM1 0.73 137.45
AR 0+000 0.991 0.261 137.189
0+004 1.304 0.313 136.876
0+005.3 1.735 0.431 136.445
0+009 1.701 0.034 136.479
0+012 1.61 0.091 136.57
0+016 1.652 0.042 136.528
0+019 1.755 0.103 136.425
0+024.82 3.075 1.32 135.105
0+026.52 3.431 0.356 134.749
0+030.52 3.37 0.061 134.81
TP-1 1.685 0.362 3.008 137.818
0+035.08 4.06 2.375 135.443
0+038.22 3.895 0.165 135.608
0+041.12 3.65 0.245 135.853
0+043.92 3.17 0.48 136.333
0+047.32 2.79 0.38 136.713
0+051.32 2.175 0.615 137.328
0+053.82 2.07 0.105 137.433
0+057.02 1.61 0.46 137.893
AL 0+060.12 1.2 0.41 138.303
TP-2 1.68 0.648 0.552 138.855

HFL(2059) 1.188 0.492 139.347


SUM 4.095 2.198 7.098 5.201
BS-FS=4.095-2.198=1.897
Rise-Fall=7.098-5.201=1.897

We determined the approximate flow velocity by float method and also measured the linear
waterway 25m u/s and 25m d/s.
KERUNGA KHOLA
Date: 2072/10/16 Time: 11:40 am
Average velocity measurement by Float Method:
Length of stretch: 5.0m

22
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Time taken:
Obs. 1: 23 secs , Obs 2: 26 secs and Obs 3: 25 secs
Average time taken = 24.67 secs
Thus, average velocity = 5/24.67 = 0.203 m/s

Geotechnical Observations
We got to observe geotechnical investigation going on at site. Wash boring method of
investigation was adopted to determine soil profile as well as SPT value. The soil type of site
was also found out.
SITE TYPE OF SOIL
KERUNGA SILTY SAND

23
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

SELECTION OF BRIDGE TYPE


The choice of an appropriate type of bridge and planning of its basic features usually
constitutes a crucial decision to be taken by the bridge engineer. The designer must
consider all the preliminary data made available to him from the detailed investigation
before arriving at a solution. The entire completed structure should be the most suitable to
carry the desired traffic, adequately strong to support the incident loads, economical in first
cost and maintenance and aesthetically pleasing.
There are no hard-and-fast rules that can be used for the choice of bridge types in all cases.
Good design result from the serious search for the best solution for the given situation.
Hence we are proposing two alternative bridge types for each site.
Kerunga khola site
Proposed bridge axis alignment is curved w.r.t the river axis and the H.F.L level is quite
higher in this site.
For this site, we proposed
Prestressed box girder bridge of 60 m span
With an intent of providing a single span without any intermediate piers in
the river i.e. not disturbing the natural waterway, prestressed box girder
bridge is suitable.
Box girder has relatively high torsional rigidity as compared to the simple T-
girder.
With the use of prestressed material and due to full section being effective,
the dead load is reduced and also the quantity of reinforcement necessary
for the bridge structure is reduced.

Steel truss mid span(36 m) with T-girder side spans(12 m each)


Two different materials can be adopted to economize the bridge spans.
Steel truss is economical for the span between 25-300 m.
Prefabrication of steel truss is possible which helps in easy construction.
Simple monolithic construction is possible with T-girder.

Alternative 2 will be adopted.


Though suitable for the given site, a prestressed box girder bridge is deemed to be
more complex in terms of analysis and design. Considering it to be more advanced for our
level of study and as the basics are yet to be comprehended, it shall be looked into only
when we are through with our adopted alternative.
As suggested by our supervisor, a truss superstructure for 36 m span may prove to be
uneconomical and a composite bridge superstructure would have been more appropriate.
But for learning purposes, we stayed on our decision and are implementing the
alternative 2 as proposed in our site.

24
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

STRUCTURAL PLANNING AND


PRELIMINARY DESIGN
For the given span of 60 m, a steel truss of 36 m span will be provided for the
central span and two t-girders of 12 m span each will be provided as side
spans. The abutment and pier shall be provided for depth beyond maximum
scour level and adequate vertical clearance off HFL shall be made available
underneath the decks.
Preliminary Design
T-Beam Bridge
1. Carriageway width = 6 m
2. Width of kerb = 0.6 m on each side
3. Height of kerb = 300 mm = 0.3 m
4. Wearing coat = Take Asphalt Concrete for wearing coat of bridge. Thickness of
wearing coat is taken 50 mm at edge and 92.5 mm at crown of carriage way to give
about 2% camber.
5. RC post of 2252251100 mm no: = 8 posts @ 1.5 m c/c
6. Size of RC slab = 200 mm thickness depth and 150 mm at tip of cantilever slab
7. Main girder:
Width of web (bw) = 300 mm > 250 mm (minimum)
Depth (D) = effective span/12 = 1 m
Number = 3 @ 2 m c/c
8. Fillet size = 150 x 300 mm and angle of inclination = 110
9. Spacing of cross beams = 2.5 m
10. No. of cross beams = 5

25
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

26
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Truss Bridge
1. Height of bridge = L/10 to L/6 = 3.6 to 6 m = Take 6 m
2. Depth of cross beam = B/(15 to 20) = 480 to 360 mm = Take 400 mm (B=7200 mm)
3. Single span of truss member = 4.5 m
4. Depth of stinger (D) = span/20 = 4.5/20 = 0.225 m
5. No. of stringers = 4
6. Spacing of stringers = 2 m
7. Depth of slab = 200 mm
8. Angle of inclination of truss member = tan-1(6/4.5) = 53.13 (preferable 45 to 55)
9. Horizontal clearance = 6 m

27
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ABUTMENT/PIER HEIGHT CALCULATION:

We have,
River bed level = 134.749 m
High flood level = 139.347 m (from field observation)
Maximum scour depth level = 130.749 m
Minimum foundation level=134.749-1.33*4=129.429 m
Calculation:
High flood depth = high flood level river bed level = 139.347 134.749m = 4.598 m
Maximum scour depth up to foundation level= river bed level Minimum foundation
level = 134.749 129.429= 5.32 m
Clearance above HFL = 0.9m (min.)
Take 1.5m considering afflux condition.
Total depth of main girder = 1m
Height of abutment = 4.598 + 5.32+ 1.5 +1 = 12.418 m
Adopted height of abutment = 12.5m

28
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

STRUCTURAL ANALYSIS AND DESIGN


OF BRIDGE COMPONENTS
A. Design of RCC T-Girder (12 m span) bridge
I. Analysis and design of Deck slab
1. Cantilever slab

0.15m

0.70m Wheel of 114 KN


axle of Class A load
0.3m
0.17m
0.35m

0.6m 0.85m

Fig. Cantilever slab with dead and live load

Calculation of dead loads


Weight of railing = (9 0.225 0.225 1.1 25 + 12 3 0.0437) 1.35/12 = 1.59 KN/m
(load acts 0.1625m from tip)
Weight of W.C. = 0.08 0.85 22 1.75= 2.618 KN/m (load acts at 0.425 m from support)
Weight of kerb = 0.6 0.3 25 1.35= 6.075 KN/m (loads acts at 0.25m from tip)
Weight of slab
= 0.17 1.45 25 1.35 = 8.32KN/m (rectangular portion) (0.725m from support)
= 0.5 (0.35 - 0.17) 0.85 25 1.35 = 2.582 KN/m (triangular part) (0.283m from
support)
Calculation of live loads
Live load per unit width of slab is calculated placing a wheel of 114 KN Axle at 0.15 m from
the face of the kerb. Live load per unit width of slab is found by dividing live load by
effective width of slab bef.
bef = 1.2a + b1 3
Where a = 0.2 + 0.5/2 = 0.45 m and b1 = 0.25 + 2 0.08 = 0.45 m
Thus, bef = 0.589 m and 3 = 1.45/3 = 0.483 m
Adopt, bef = 0.483 m
570.4831.51.25
Live load per unit width with impact = = 213.75 KN/m (0.45 m from
0.50.483
support)
Where Impact factor = 1.25 and partial safety factor = 1.5
Design longitudinal bending moment at the face of main girder
Design BM = Max. BM due to dead load + Max. BM due to live load

29
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Mu = (1.59 (1.45 - 0.1625) + 2.618 0.425 + 6.075 1.15 + 8.32 0.725 + 2.582 0.283) +
213.75 0.45
= 16.91 + 96.188 = 113.098 KN-m/m
Maximum transverse bending moment in direction of traffic
Mu = 0.3 BM due to live load + 0.2 BM due to dead load
= 0.3 96.188 + 0.2 19.91
= 32.84 KN-m/m

Design of slab
Check the depth of slab
Depth provided = 350-25-10/2 = 320 mm
113.098 10^6
Balanced depth = = = = 195.85 mm
3.45 1000
Where, Q = 0.36 fck 0.48 (1 -0.416 0.48) = 3.45
Depth provided > Balanced depth so, OK.

Main Reinforcement
Mu,l = 0.36 fck b xu,l (d - 0.416 xu,l)
= 0.36 x 25 x 1000 x 0.48 x 320(320 - 0.416 x 0.48 x 320)
= 354.04 KN
Since Mu,l>Mu , it is designed as SRURS.
0.87415
Xu = 0.36251000
= 0.0401Ast
113,09106
& Ast = 0.87415(3200.4160.0401Ast)
Solving, Ast = 1034mm2 > min. 0.12%
Provide 12mm bars @100mm c/c

Transverse Reinforcement
32.8410^6
d2
= 10003202 = 0.32
Using SP16, Pt = 0.0915% <0.12%
So, provide minimum reinforcement.
Astmin = 0.12x1000x350/100
= 420mm2
Provide 10mm bars @180mmc/c

30
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

2. Restrained Slab

Analysis of slab

Direction
of traffic

Effective span in transverse direction of bridge = 2 0.3 = 1.7 m


Effective span in longitudinal direction of bridge = 3 - 0.25 = 2.75 m

Calculation of Bending Moment due to Dead Load


Bending moment is calculated by using PIGEAUDS METHOD
Dead load due to W.C. and self-wt. of slab (W) = (0.08 22 1.75+ 0.2 25 1.35) 1.7
2.75 + 2 0.5 0.15 0.3 2.75 1.35 = 52.7 KN

BM in shorter span of slab = (m1 + m2) W 0.8 = (0.048+0.15 0.016) 52.7 0.8 =
2.125 kN-m
BM in longer span of slab = (m2 + m1) W 0.8 = (0.016+0.15 0.048) 52.7 0.8 = 0.978
kN-m
Shorter Span
Where, m1 = 0.048, m2 = 0.016 for K = Longer Span = 0.62 and 1 = 1.613, = 0.15

Calculation of Shear Force due to dead load


Max. SF due to dead load in shorter span of slab
= SF due to self-weight of WC & slab with fillet

= + Vufillet
3
1.70
= (0.2251.35+0.08221.75) + 0.250.150.31/22.7525
3
= 5.957 KN (25% of weight fillet)

31
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Calculation of Bending Moment due to IRC Class A Loading


Bending moment is calculated by using PIGEAUDS METHOD
BM due to Wheel I

BM in shorter span = (m1 + m2) W 0.8 = 14.702 KN-m


BM in longer span = (m2 + m1) W 0.8 = 11.649 KN-m
Where, m1 = 0.16, m2 = 0.11 for K =0.6 and m1 = 0.155, m2 = 0.125 for k =0.7
We have, k =1.7/2.75 = 0.62
By interpolation, m1 = 0.159 and m2 = 0.113
+2 0.5+2 0.08 +2 0.25+2 0.08
Also, = = = 0.388 and, = = = 0.149
1.7 2.75
W= 57 IF f = 57 1.25 1.5 = 106.875 KN
BM due to Wheel II
BM in shorter span = (BM of patch I BM of patch II)
BM in longer span = (BM of patch I BM of patch II)

For patch I,

32
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

+2 0.5+2 0.08 +2 2.65+2 0.08


= = = 0.388 and = = = 1.022
1.7 2.75
For k = 0.6, m1 = 0.082, m2 = 0.023 and for k = 0.7, m1 = 0.082, m2 = 0.033
Thus, for k = 0.62, m1 = 0.082 and m2 = 0.025, W = 57 1.25 1.5 = 106.875 KN
BM of patch I in shorter span = (m1 + m2) W 0.8 0.5 2.65 / (0.5 0.25) = 77.715
KN-m
BM of patch I in longer span = (m2 + m1) W 0.8 0.5 2.65 / (0.5 0.25) = 33.805
KN-m

For patch II,

+2 0.5+2 0.08 +2 2.15+2 0.08


= = = 0.388 and = = = 0.84
1.7 2.75
For k = 0.6, m1= 0.095, m2 = 0.03 and for k = 0.7, m1= 0.098, m2= 0.04
Thus, for k = 0.62, m1= 0.0956 and m2= 0.032, W = 57 1.25 1.5 =106.875 KN

33
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

BM of patch II in shorter span = (m1 + m2) W 0.8 0.5 2.15 / (0.5 0.25) = 73.824
KN-m
BM of patch II in longer span = (m2 + m1) W 0.8 0.5 2.15 / (0.5 0.25) = 34.074
KN-m

Thus, due to wheel load II,


BM in shorter span = (BM of patch I BM of patch II) = 0.5 x (77.715 73.824) = 1.945
KN-m
BM in longer span = (BM of patch I BM of patch II) = 0.5 x (33.805 34.074) = -
0.1345 KN-m

Calculation of Shear Force due to IRC Class A Loading


Shear force is calculated by effective width method.
For wheel I,
a = 0.25 + 0.2 + 0.08 = 0.53m

= 0.62 so, = 1.86 (for continuous slab)

b1 = W+2h = 0.25 + 20.08 = 0.41


Then,
bef 1 = a (1- a/l) + b1
= 1.860.53(1-0.53/1.70) + 0.41
= 1.09m
57 57
Load due to wheel I = maximum of (1.09 1.09 0.25 ) 1.25 1.5 2
+
2 2

= 319.03 KN/m
RA = 219.57 KN RB= 99.46 KN

Design shear force due to DL & LL in shorter span = 5.957 + 219.57 0.8 = 181.613 KN

34
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Calculation of Bending Moment due to IRC Class AA Loading


(Tracked Load)

1.01
= = 0.594 for u = 0.85 + 20.08 = 1.01 m
1.70
2.75
= = 1 for v = 3.6 + 20.08 = 3.76 m (limited to 2.75 m)
2.75
For k = 0.62,
m1=0.07 and m2=0.019
Effective load including impact = 3501.251.52.75/3.76= 479.97 KN
So,
BM in shorter span = (0.07+0.150.019) 479.97 = 34.97 KNm
BM in longer span = (0.019 + 0.150.07) 479.97 = 14.16 KNm

(Wheeled Load)

35
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

BM due to wheel I

u = 0.3+ 20.08 = 0.46


v = 0.15+ 20.08 = 0.31
0.46 0.31
= = 0.27 and = 2.75 = 0.113
1.7
From Pigeauds curve for k = 0.6,
m1=0.195 and m2=0.16
w = 62.5 IF gf = 62.5 1.25 1.5 = 117.18KN
So,
BM in shorter span = (m1+m2) w 0.8 =
(0.195+0.160.15) 117.180.8 = 20.53KNm
BM in longer span = (m1+m2) w 0.8 =
(0.16+0.150.195) 117.180.8 = 17.74KNm

BM due to wheel 2

36
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For patch I,

1.5+20.08 0.15+20.08
= = 0.976 and = = 0.112
1.7 2.75
For k = 0.62 0.6, m1 = 0.09 and m2 = 0.08
So,
BM of patch I in shorter span
1
= (m1+m2) w0.80.30.150.151.5
1
= (0.09+0.150.08) 37.50.80.30.150.151.5
= 15.3 KNm
BM of patch I in longer span
1
= (m1+m2) w0.80.30.150.151.5
1
= (0.150.09+0.08) 37.50.80.30.150.151.5
=14.025 KNm
For patch II,

0.9+20.08 0.15+20.08
= = 0.62 and = = 0.113
1.7 2.75
For k = 0.62 0.6, m1 = 0.12 and m2 = 0.11
So,
BM of patch I in shorter span
1
= (m1+m2) w0.80.30.150.151.5
1
= (0.12+0.150.11) 37.50.80.30.150.150.9
=12.29 KNm
BM of patch I in longer span
1
= (m1+m2) w0.80.30.150.151.5
1
= (0.150.12+0.11) 37.50.80.30.150.150.9
= 11.52 KNm
Thus,

BM of wheel load 2 in shorter span = (15.3-12.29) = 1.505 KNm

BM of wheel load 2 in longer span = (14.025-11.52) = 1.25 KNm

BM due to wheel load 4

37
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For patch I,

0.3+20.08 2.55+20.08
= = 0.27 and = = 0.98
1.7 2.75
For k = 0.62 0.6, m1 = 0.095 and m2 = 0.025
So,
BM of patch I in shorter span
1
= (m1+m2) w0.80.30.150.151.5
= (0.095+0.150.025)
1
62.50.80.30.150.302.55
= 83.94 KNm
BM of patch I in longer span
1
= (m1+m2) w0.80.30.150.151.5
1
= (0.150.095+0.025) 62.50.80.30.150.302.55
= 33.36 KNm
For patch II,

0.3+20.08 2.25+20.08
= = 0.27 and = = 0.88
1.7 2.75
For k = 0.62 ~ 0.6, m1 = 0.10 and m2 = 0.03
So,
BM of patch I in shorter span
1
= (m1+m2) w0.80.30.150.32.25
= (0.10+0.150.03)
1
62.50.80.30.150.32.25
= 78.38 KNm
1
BM of patch I in longer span = (m1+m2) w0.80.30.150.302.25
1
= (0.150.10+0.03) 62.50.80.30.150.32.25

38
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

=33.75 KNm
Thus,

BM of wheel load 4 in shorter span = (83.94-78.38) = 2.78 KNm

BM of wheel load 4 in longer span = (33.36-33.75) = -0.195 KNm

BM due to wheel load 3

39
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For patch I,
1.5+20.08 2.55+20.08
= = 0.98 and = = 0.99
1.7 2.75
For k = 0.62 0.6, m1 = 0.049 and m2 = 0.012
So,
1
BM of patch I in shorter span= (m1+m2) w0.80.30.152.551.5
1
= (0.049+0.150.012) 37.50.80.30.151.52.55
=129.54 KNm

1
BM of patch I in longer span= (m1+m2) w0.80.30.152.551.5
1
= (0.150.049+0.012) 37.50.80.30.151.52.55
=49.34 KNm
For patch II,
0.9+20.08 2.55+20.08
= = 0.62 and = = 0.99
1.7 2.75
For k = 0.62 ~ 0.6, m1 = 0.069 and m2 = 0.019
So,
1
BM of patch II in shorter span= (m1+m2) w0.8 0.92.55
0.30.15
1
= (0.069+0.150.019) 37.50.80.30.150.92.55
=109.93 KNm
1
BM of patch II in longer span= (m1+m2) w0.80.30.150.92.55
1
= (0.150.069+0.019) 37.50.80.30.150.92.55
=44.91 KNm

40
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For patch III,


1.5+20.08 2.25+20.08
= = 0.98 and = = 0.88
1.7 2.75
For k = 0.62 0.6, m1 = 0.055 and m2 = 0.018
So,
1
BM of patch III in shorter span= (m1+m2) w0.80.30.151.52.25
1
= (0.055+0.150.018) 37.50.80.30.151.52.25
=129.83 KNm

1
BM of patch III in longer span= (m1+m2) w0.80.30.151.52.25
1
= (0.150.055+0.018) 37.50.80.30.151.52.25
=59.06 KNm
For patch IV,
0.9+20.08 2.25+20.08
= = 0.62 and = = 0.88
1.7 2.75
For k = 0.62 ~ 0.6, m1 = 0.076 and m2 = 0.025
So,
1
BM of patch IV in shorter span= (m1+m2) w0.8 0.92.25
0.30.15
1
= (0.076+0.150.025) 37.50.80.30.150.92.25
=107.66 KNm
1
BM of patch IV in longer span= (m1+m2) w0.80.30.150.92.25
1
= (0.150.076+0.025) 37.50.80.30.150.92.25
=49.14 KNm

Thus,

BM of wheel load 3 in shorter span = (BM of patch I - BM of patch II BM of patch III +
BM of patch IV ) = (129.54 109.93- 129.83 + 107.66) = -0.64 KNm

BM of wheel load 3 in longer span = (BM of patch I -
BM of patch II BM of patch III + BM of patch IV ) =
(49.34 44.91 59.06 + 49.14) = -1.37 KNm

Calculation of Shear Force due to IRC Class AA Loading


(Tracked wheel)

beff = 3.76m ( limited to 2.75 m)

41
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Effective load including impact


2.75
= 350 1.251.53.76
= 479.97 KN

RA=280.93KN
RB=199.04KN

Design SF due to DL and LL in shorter span


= 280.930.8+5.957
= 230.7 KN/m

(Wheeled Load)

For wheel I,
a= 0.15+0.2+0.08=0.43

=1.86 for 1
b1= 0.15+20.08=0.31m
Then, beffI = xa (1- a/l) + b1
= 1.860.43(1- 0.43/1.7)+0.31
= 0.908m
262.5
Effective load due to wheel I = (0.908 0.15 ) 1.251.5
+
2 2

= 443.05 KN/m
For wheel II,
a = 0.67

=1.86 for 1
b1= 0.15+20.08=0.31m
Then, beffII = xa (1- a/l) + b1
= 1.860.67(1- 0.67/1.7)+0.31
= 1.065m
237.5
Effective load due to wheel I = (1.065 0.15 ) 1.251.5
+
2 2

= 231.5 KN/m

RA=422.22KN
RB=252.33KN

Design SF due to DL and LL in shorter span


= 422.220.8+5.957

42
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 343.73 KN/m

Summary
The calculated BMs and SFs may be tabulated as follows:
Load Bending Moment Shear Force Combined Shear
Shorter Span Longer Span (DL+0.8xLL)
Dead Load 2.125 0.978 5.957 -
Live Load
IRC Class A 16.647 0.1345 219.57 181.613
Loading
IRC Class 34.97 14.16 280.93 230.7
AA(Tracked)
IRC Class 24.175 17.425 422.22 343.73
AA(Wheeled)
Total BM 37.095 15.138

Design of slab
Check depth of slab
Effective depth of main reinforcement (d1) = 200-25-10/2 = 170mm
Effective depth of secondary reinforcement (d2) = 200-25-10-10/2
= 160mm
37.095106
dbal = b = 3.451000 = 103.7 mm < 170mm and < 160mm

I.e. dbal < dprov OK


Find reinforcing bars:
Since dbal < dprov , section of slab is designed as singly reinforced under-reinforced section (
SRURS) . In the example, section design has been done by using SP16.
a) Reinforcing bars in shorter and longer direction of slab
In short span,
37.095106
= 10001702 = 1.28
d2
By interpolation (Table 2 of SP16)
0.3920.376 0.376
= 1.281.25
1.31.25
Pt = 0.3856 % > Ptmin = 0.12%
Astreq= 0.3856/100100170
= 655.52 mm2
Provide 10mm bar @ 110mm c/c.
Astprovided = 706.85 mm2

In long span,

43
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

15.136106
= 10001602 = 0.6
d2
Pt = 0.172 % > Ptmin = 0.12%
Astreq = 0.172/100100170
= 275.2 mm2
Provide 10mm bar @ 280mm c/c.
Astprovided = 314.16 mm2

b) Temperature reinforcement
Provide 10 mm bars @300 mm c/c in both direction at top of slab.

Check for shear: K


343.731000
= = = 2.02 N/mm2
1000170
Shear strength of concrete section = 0.46 N/mm2 for M25 and Pt = 0.433 %
Limiting value of Shear Stress , = 3.1 N/mm2 [Refer IS 456 table 19, 20]
Depth factor (K) = 1
Since >, design shear reinforcement.
0.87 0.8741598^2/4170
Sv = (uvuc)bwd= = 100 < 0.75d and <300 mm
(2.020.46)1000170
Adopt Sv = 100mm.
Provide 8mm 9-legged vertical stirrups @100 mm c/c.

II. Analysis and Design of Main Girder


Calculation of dead load on a main girder per running meter of span
1. Weight of wearing coat = 60.08221.75/3 = 6.16KN/m
2. Weight of railing = (90.2250.2251.125+1230.0437) 1.35/12 = 1.59KN/m
3. Weight of kerb = 0.60.3251.35 = 6.075 KN/m
4. Weight of slab:
a. Middle portion=4.30.212251.35
=348.30KN
1 1
b. Fillet=(2 0.150.312425+2 0.150.31.18252) 1.35 = 49.815 KN
c. Cantilever part =(0.60.1712225+0.850.2612225) 1.35 = 261.63KN

659.745
Weight of slab = = = 18.33 KN/m
. 312
5. Weight of web of main beam= 0.30.8251.35 = 8.1KN/m
Total design dead load per main girder
= 6.16 + (1.59+6.075) 2/3 + 18.33 + 8.1
= 37.70 KN/m
6. Self-wt. of Cross girder acts as a point load on main girder.

44
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

2
1. Self-wt. of web of internal cross girder on a girder = 0.25 0.55 1.7 25 1.35 3 =
5.259 KN
2
2. Self-wt. of web of end cross girder on a girder = 0.25 0.3 1.7 25 1.35 3
=2.869 KN

Dead load on main girder

Calculation of maximum BM and SF at critical sections due to DL

Reaction at support (RA) = (5.2593+2.8692+37.712)/2 = 236.96KN

BM at Mid span = RA6 - 2.8696 - 5.2593-37.766/2


= 236.966 - 711.59 = 710.17 KNm
BM at quarter span = RA3 - 2.8693 - 37.733/2
= 236.963 - 178.26 = 532.62 KNm
SF at supports = 236.96 kN

Calculation of maximum BM and SF at critical sections due to LL


(Hendry Jaeger method of Lateral Load Distribution)
End Main Girder
CG of the section(y)
0.17 0.2 1 0.18 1 0.15
0.310.5+1.450.17(1 )+0.850.2(1 )+ 0.180.85(10.17 )+ 0.150.30(10.20 )
2 2 2 3 2 3
= 1 1
0.31+1.450.17+0.850.20+ 0.180.85+ 0.150.30
2 2

= 0.741m
1.450.173 0.850.203 0.3013 0.850.183 0.300.153
I= + 12 + 12 + 36 + 36 +1.450.17(1-0.17/2-0.741)2+0.200.85
12
(1-0.20/2-0.741)2+0.31(0.741-1/2)2+0.50.180.85(0.11-0.741)2+0.90.150.30(0.75-
0.741)2

45
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 0.05557741 m4
Interior Main Girder
CG of the section (y)
0.2 0.8 1 0.15
0.22(0.8+ )+0.30.8 +2 0.150.30(0.8 )
2 2 2 3
= 1
0.22+0.30.8+2 0.150.30
2

= 0.715 m
20.23 0.30.83 0.300.153 0.2 0.8 2
I= + +2 +0.22 (1 - - 0.715)2 + 0.30.8 (0.715 - )
12 12 36 2 2
1
+220.150.30(0.8-0.15/3-0.715)2= 0.0517487m4

Cross girder
End cross girder
CG of the section (y)
0.40 0.20 1 0.15
0.250.40 +1.625.20(0.60 )+ 0.300.15(0.600.20 )
2 2 2 3
= 1
0.250.40+1.6250.2+ 0.300.15
2

= 0.425m
0.250.43 1.6250.23 0.30.153
IT = 12 + + 36 + 0.250.40 (0.425-0.40/2)2 + 1.6250.20 (0.6-0.2/2-
12
0.425)2+1/20.150.30 (0.425-0.35)2 = 0.009462 m4
Intermediate cross girder
Centroid of the section(y)
0.55 0.20 1 0.15
0.250.55 +3.0.02(0.75 )+2 0.300.15(0.750.20 )
2 2 2 3
= 1
0.250.55+3.00.2+2 0.300.15
2

= 0.575m
0.250.553 3.00.23 0.30.153
IT = + 12 +2 36 + 0.250.55 (0.575-0.55/2)2 + 3.00.20 (0.75-0.2/2-
12
0.575)2+21/20.150.30 (0.575-0.5)2 = 0.021526 m4
EIT =E (30.021526 +20.009462) = E0.083502 m4
EI = E 0.05557741 m4 (Taking larger of longitudinal flexural rigidity)

Then,
12 12 12
= 4 ()3EIT/EI = 4 ( 2 )3( E0.083502)/( E 0.05557741) = 39.98
2
= CJ/EIT
2
Take = (for T-beam bridges, having 3 longitudinal girders with a number of cross beams)

Distribution coefficients:
p11= 0.40, p12= 0.32, p13= 0.28
p21= 0.32, p22= 0.34, p23= 0.34
p31= 0.28, p32= 0.34, p33= 0.38
And,

46
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

IF = 1.25 and F = 1.5

1. Class A load

47
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

H1=1.7W
H2=0.5W
H3=1.8W
Reactions:
R1=p11H1+p12H2+p13H3=1.344W
R2=p21H1+p22H2+p23H3=1.326W
R3=p31H1+p32H2+p33H3=1.33W
Reaction Factors:
RF1=1.344
RF2=1.326
RF3=1.330
BM at mid span due to LL

Max. BM= (13.5(0.8+0.25) + 57(3+2.4) + 34(0.85))RF IF F


= 350.875RF1.251.5
= 657.89RF KNm
For End girder, max. BM = 657.89RF3 (max (RF1, RF3))
= 657.891.344
= 884.20 KNm
For Interior girder, max. BM = 657.89 RF2
= 657.891.326

48
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 872.36 KNm
BM at quarter span due to LL

Max. BM = (57(2.25+1.95) + 34(0.875+0.125)) RF IF F


= 273.4RF1.251.5
= 512.625RF
For End girder, max. BM = 512.625RF3 (max (RF1, RF3))
= 512.6451.344
= 688.97 KNm
For Interior girder, max. BM= 512.625RF2
= 512.6251.326
= 679.74 KNm
SF at support due to LL

Max. SF = (57(1+0.9) + 34(0.54+0.292+0.042)) RF IF F


= 138.016RF1.251.5
=258.78RF
For End girder, max. SF= 258.78RF3 (max (RF1, RF3))
= 258.781.344 = 347.80 KNm
For Interior girder, max. SF= 258.78RF2
= 258.781.326
= 343.14 KNm
SF at quarter span due to LL

49
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Max. SF = (57(0.75+0.6) + 34(0.292+0.042)) RF IF F


= 88.306RF1.251.5
=165.57RF
For End girder, max. SF= 165.57RF3 (max (RF1, RF3))
= 165.571.344 = 222.53 KNm
For Interior girder, max. SF= 165.57RF2
= 165.571.326
= 219.55 KNm

2. Class AA wheeled load

50
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

H1=65.31 KN
H2=124.38KN
H3=10.31KN

51
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Reactions:
R1=p11H1+p12H2+p13H3=68.81 KN = 0.344 W (for W= 200KN)
R2=p21H1+p22H2+p23H3=66.69 KN = 0.333 W (for W= 200KN)
R3=p31H1+p32H2+p33H3=64.49 KN = 0.322 W (for W= 200KN)
Reaction Factors:
RF1=0.344
RF2=0.333
RF3=0.322
BM at mid span due to LL

Max. BM= (200(2.7+2.7)) RF IF F


= 2005.4RF1.251.5
=2025RF KNm
For End girder, max. BM= 2025RF1 (max (RF1, RF3))
= 20250.344= 696.60 KNm
For Interior girder, max. BM= 2025RF2
= 20250.333
= 674.33 KNm
BM at quarter span due to LL

52
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Max. BM = (200(2.25+1.95)) RF IF F
= 2004.2RF1.251.5
=1575RF KNm
For End girder, max. BM= 1575RF1 (max (RF1, RF3))
= 15750.344= 541.80 KNm
For Interior girder, max. BM= 1575RF2
= 15750.333
= 524.48 KNm
SF at support due to LL

Max. SF = 200(1+0.9) RF IF F
= 200(1+0.9) RF1.251.5
=712.5RF
For End girder, max. SF= 712.5RF1 (max (RF1, RF3))
= 712.50.344= 245.10 KNm
For Interior girder, max. SF= 712.5RF2
= 712.50.333
= 237.26 KNm
SF at quarter span due to LL

Max. SF = 200(0.75+0.65) RF IF F
= 2001.4RF1.251.5
=525RF
For End girder, max. SF= 525RF1 (max (RF1, RF3))

53
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 5250.344= 180.60 KNm


For Interior girder, max. SF= 525RF2
= 5250.333
= 174.83 KNm

3. Class AA track load

54
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

H1=240.625 KN
H2=192.5 KN
H3=266.875 KN
Reactions:
R1=p11H1+p12H2+p13H3=232.58 KN = 0.665W (for W= 350 KN)
R2=p21H1+p22H2+p23H3=233.19 KN = 0.666W (for W= 350 KN)
R3=p31H1+p32H2+p33H3=234.24 KN = 0.669W (for W= 350 KN)
Reaction Factors:
RF1=0.665
RF2=0.666
RF3=0.669
BM at mid span due to LL

55
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Max. BM= 97.22(2.13.6 + (3-2.1) 1/23.6) RF IF F


= 97.22(2.13.6 + (3-2.1) 1/23.6)RF1.251.5
=1673.40RF KNm
For End girder, max. BM= 1673.40RF3 (max (RF1, RF3))
= 1673.400.669= 1119.50 KNm
For Interior girder, max. BM= 1673.40RF2
= 1673.400.666
= 1114.48 KNm

BM at quarter span due to LL

Max. BM = 97.22(2.13.6 + (3-2.1) 1/23.6) RF IF F


= 97.22(2.13.6 + (3-2.1) 1/23.6)RF1.251.5
=1673.40RF KNm
For End girder, max. BM= 1673.40RF3 (max (RF1, RF3))
= 1673.400.669 = 1119.50 KNm
For Interior girder, max. BM= 1673.40RF2

56
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 1673.400.666
= 1114.48 KNm

SF at support due to LL

Max. SF =97.22(1/2 (1+0.7) 3.6) RF IF F


= 297.4932RF1.251.5
=557.80 RF
For End girder, max. SF = 557.80RF3 (max (RF1, RF3))
= 557.800.669 = 373.17 KNm
For Interior girder, max. SF= 557.80RF2
= 557.800.666
= 371.49 KNm
SF at quarter span due to LL

Max. SF =97.22(1/2 (0.45+0.75) 3.6) RF IF F


= 209.9952RF1.251.5
= 393.74 RF
For End girder, max. SF= 393.74RF3 (max (RF1, RF3))
= 393.740.669= 263.41 KNm
For Interior girder, max. SF= 393.74RF2
= 393.740.666 = 262.23 KNm

Summary
The calculated BMs and SFs may be tabulated as follows:

57
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Load Bending Moment (kNm) Shear Force (kN)


Mid-Span Quarter-Span Supports Quarter-Span
Dead Load 710.17 532.62 236.96 119.01
Exterior Girder
Live Load
IRC Class A 884.20 688.97 347.80 222.53
Loading
IRC Class 1119.50 1119.50 373.17 263.41
AA(Tracked)
IRC Class 696.60 541.80 245.10 180.60
AA(Wheeled)

Interior Girder
Live Load
IRC Class A 872.36 679.74 343.14 219.55
Loading
IRC Class 1114.48 1114.48 371.49 262.23
AA(Tracked)
IRC Class 674.33 524.48 237.26 174.83
AA(Wheeled)

1. Design of End Main Girder


Design Section
Thickness of flange (Df)
0.170.6+0.260.85
Average thickness of left part (t1) = = 0.223 m
1.45
0.20.55+0.30.275
Average thickness of left part (t2) = = 0.226 m
0.85
1+2 0.223+0.226
Df = = = 0.224 m
2 2
Effective width of flange (bef)
12
bef = 5 + = + 0.3 = 2.7m > bact = 2.6 m
5
Actual width on right side = 1 m
Adopt bef = 21 = 2 m
CG of section
0.224 0.776
0.2242(0.776+ )+0.30.776
2 2
Y= = 0.717 m
0.2242+0.7760.3
MOI of section
20.2243 0.30.7763 0.224 0.776 2
Ixx = + + 0.2242(1 - - 0.717)2 + 0.30.776(0.717 - ) = 0.0519 m4
12 12 2 2
MOI of actual section of girder about XX axis
Ixxgross = 0.05557741 m4
For End Girder,

58
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Design BM due to LL at mid-span = 1119.50 kNm (Class AA tracked load)


Design BM due to LL at quarter-span = 1119.50 kNm (Class AA tracked load)
Design SF due to LL at mid-span = 373.17 kN (Class AA tracked load)
Design SF due to LL at quarter-span = 263.41 kN (Class AA tracked load)
Design BM due to DL at mid-span = 702.24 kNm
Design BM due to DL at quarter-span = 526.68 kNm
Design SF due to DL at support = 232.11 kN
Design SF due to DL at quarter-span = 119.01 kN
Therefore,
Design BM at mid-span = 1119.50 + 702.24 = 1821.74 kNm
Design BM at quarter-span = 1119.50 + 526.68 = 1646.18 kNm
Design SF at support = 373.17 + 232.11 = 605.28 kN
Design SF at quarter-span = 263.41 + 119.01 = 382.42 kN

Design of section for Bending


Mid-span section
Xu,l = 0.48 d = 0.48912 = 437.76 mm
Where, d = 1000 40 32 32/2 = 912 mm
Since Xu,l > Df, Neutral axis lies in web.
(Considering 40mm clear cover and 3 layers of 32 mm tension bars in main girder)
Find Mu,l = 0.36fckbXu,l(d 0.416Xu,l) + 0.446fck(bef bw)Df(d Df/2 ) = 4259.43
kNm
Mu = 1821.74 kNm
Since Mu < Mu,l, the section is designed as SRURS.
Find Xu considering Xu < Df.
Mu = 0.36fckbefXu(d 0.416Xu)
Or, 1821.74106 = 0.36252000Xu(912-0.416Xu)
Xu = 117.24 mm < Df i.e. N. Axis lies in flange.
Find area of steel for SRUR flanged section when N.A. lies in flange.

Ast,req = 0.87fy(d0.416Xu) = 5845.12 mm2 > Ast,min
Where, Ast,min = 0.2% of bd = 0.002 300 912 = 547.2 mm2 [Refer Cl.305.1, IRC21]
Provide 8-32 mm bar.
6433.98
Ast,prov = 6433.98 mm2 and Pt = 912300 100 = 2.35 % < Pt,max = 2.5 %

Quarter-span section
Mu = 1646.18 kNm
Since Mu < Mu,l, the section is designed as SRURS.
Find Xu considering Xu < Df.
Mu = 0.36fckbefXu(d 0.416Xu)

59
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Or, 1646.18106 = 0.36252000Xu(912-0.416Xu)


Xu = 105.34 mm < Df i.e. N. Axis lies in flange.
Find area of steel for SRUR flanged section when N.A. lies in flange.

Ast,req = 0.87fy(d0.416Xu) = 5251.71 mm2 > Ast,min
Where, Ast,min = 0.2% of bd = 0.002 300 912 = 547.2 mm2 [Refer Cl.305.1, IRC21]
Provide 8-32 mm bar.
6433.98
Ast,prov = 6433.98 mm2 and Pt = 912300 100 = 2.35 % < Pt,max = 2.5 %

Design of section for Shear


Support section
605.281000
= bwd = = 2.21 N/mm2
300912
Where d = 1000 40 32 - 32/2 = 912 mm
For M25 and Pt = 2.35 %, = 0.862 N/mm2 and , = 3.1 N/mm2
Since > , design shear reinforcement.
Take 10 mm 4-legged vertical stirrups for shear reinforcement.
912
Sv = 0.87 Vu, net = 0.874154102/4(2.210.862)300912
= 280.48 mm < 0.75d (= 684 mm) and < 300 mm
Adopt Sv = 270 mm
Provide 10 mm 4-legged vertical stirrups @ 270 mm c/c from support to quarter span.
Quarter-span section
382.421000
= bwd = = 1.40 N/mm2
300912
Where d = 1000 40 32 - 32/2 = 912 mm
For M25 and Pt = 2.35 %, = 0.862 N/mm2 and , = 3.1 N/mm2
Since > , design shear reinforcement.
Take 10 mm 2-legged vertical stirrups for shear reinforcement.
912
Sv = 0.87 Vu, net = 0.874152102/4(1.400.862)300912
= 351.39 mm < 0.75d (= 684 mm) and > 300 mm
Adopt Sv = 300 mm
Provide 10 mm 2-legged vertical stirrups @ 300 mm c/c from quarter to quarter span of
the other side.
Detailing of reinforcement
Since the no. of bars required is same at both mid-span and quarter-span, no curtailment is
done.
Anchorage of main reinforcing bars at supports
Extension of bar beyond the face of support = 23ld
,
Now, ld = 0.7l0, for bars with hook end
5251.71
= 0.7(4632)6433.98 where l0 = n

60
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 841.06 mm
Extension of bar beyond the face of support = 23ld = 23 841.06 = 560.71 mm 561 mm
Side Face Reinforcement
Take 0.1% of web area.
As = 0.001(1000 224)300 = 232.80 mm2
232.80
No. of 8 mm bars required on each face = 3
2 88
4

Provide 3-8 mm on each face.


Check for Limit State of Serviceability in Deflection
(Method of Sufficient Stiffness)

Check

Where,
121000
= = 13.16
912
= 20 (simply supported)
10 10
= = 12
, 5845.12
fs = 0.58fy, = 0.584156433.98 = 218.67 N/mm2
For Pt = 2.35 %, = 0.86
For 2-32 mm compression bars,

2 322
4
Pc = 300912 = 0.588 %
For Pc = 0.588 %, = 1.16
300
For flange, = 0.8 since = 2000 = 0.15
10
So, = 20120.861.160.8 = 13.30

i.e. OK.

Hence, deflection of the girder is under control.

2. Design of Intermediate Main Girder


Design Section
Thickness of flange (Df)
0.35+0.2
0.20.55+ 0.3
2
Average thickness of left part (t1) = = 0.226 m
0.85
Average thickness of left part (t2) = 0.226 m
1+2 0.226+0.226
Df = = = 0.226 m
2 2
Effective width of flange (bef)
12
bef = 5 + = + 0.3 = 2.7m > bact = 2 m
5
Actual width on each side = 1 m

61
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Adopt bef = 21 = 2 m
CG of section
0.226
0.2262(0.774+ )+0.30.7740.774/2
2
Y= = 0.717 m
0.2262+0.7740.3
MOI of section
20.226^3 0.30.774^3 0.226 0.774 2
Ixx = + + 0.2262(1 - 2 - 0.717)2 + 0.30.774(0.717 - ) = 0.0519
12 12 2
m4
MOI of actual section of girder about XX axis
Ixxgross = 0.0517487 m4
For End Girder,
Design BM due to LL at mid-span = 1114.48 kNm (Class AA tracked load)
Design BM due to LL at quarter-span = 1114.48 kNm
Design SF due to LL at mid-span = 371.49 kN
Design SF due to LL at quarter-span = 262.23 kN
Design BM due to DL at mid-span = 725.88 kNm
Design BM due to DL at quarter-span = 544.41 kNm
Design SF due to DL at support = 238.02 kN
Design SF due to DL at quarter-span = 124.92 kN
Therefore,
Design BM at mid-span = 1114.48 + 725.88 = 1840.36 kNm
Design BM at quarter-span = 1114.48 + 544.41 = 1658.89 kNm
Design SF at support = 371.49 + 238.02 = 609.51 kN
Design SF at quarter-span = 262.23 + 124.92 = 387.15 kN

Design of section for Bending


Mid-span section
Xu,l = 0.48 d = 0.48912 = 437.76 mm
Where, d = 1000 40 32 32/2 = 912 mm
Since Xu,l > Df, Neutral axis lies in web.
(Considering 40mm clear cover and 3 layers of 32 mm tension bars in main girder)
Find Mu,l = 0.36fckbXu,l(d 0.416Xu,l) + 0.446fck(bef bw)Df(d Df/2 ) = 4285.48
kNm
Mu = 1840.36 kNm
Since Mu < Mu,l, the section is designed as SRURS.
Find Xu considering Xu < Df.
Mu = 0.36fckbefXu(d 0.416Xu)
Or, 1840.36106 = 0.36252000Xu(912-0.416Xu)
Xu = 118.51 mm < Df i.e. N. Axis lies in flange.
Find area of steel for SRUR flanged section when N.A. lies in flange.

62
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge


Ast,req = 0.87fy(d0.416Xu) = 5908.48 mm2 > Ast,min
Where, Ast,min = 0.2% of bd = 0.002 300 912 = 547.2 mm2 [Refer Cl.305.1, IRC21]
Provide 8-32 mm bar.
6433.98
Ast,prov = 6433.98 mm2 and Pt = 912300 100 = 2.35 % < Pt,max = 2.5 %

Quarter-span section
Mu = 1658.89 kNm
Since Mu < Mu,l, the section is designed as SRURS.
Find Xu considering Xu < Df.
Mu = 0.36fckbefXu(d 0.416Xu)
Or, 1658.89106 = 0.36252000Xu(912-0.416Xu)
Xu = 106.20 mm < Df i.e. N. Axis lies in flange.
Find area of steel for SRUR flanged section when N.A. lies in flange.

Ast,req = = 5294.44 mm2 > Ast,min
0.87fy(d0.416Xu)
Where, Ast,min = 0.2% of bd = 0.002 300 912 = 547.2 mm2 [Refer Cl.305.1, IRC21]
Provide 8-32 mm bar.
6433.98
Ast,prov = 6433.98 mm2 and Pt = 912300 100 = 2.35 % < Pt,max = 2.5 %

Design of section for Shear


Support section
609.511000
= bwd = = 2.23 N/mm2
300912
Where d = 1000 40 32 - 32/2 = 912 mm
For M25 and Pt = 2.35 %, = 0.862 N/mm2 and , = 3.1 N/mm2
Since > , design shear reinforcement.
Take 10 mm 4-legged vertical stirrups for shear reinforcement.
912
Sv = 0.87 Vu, net = 0.874154102/4(2.230.862)300912
= 276.38 mm < 0.75d (= 684 mm) and < 300 mm
Adopt Sv = 270 mm
Provide 10 mm 4-legged vertical stirrups @ 270 mm c/c from support to quarter span.
Quarter-span section
387.151000
= bwd = = 1.415 N/mm2
300912
Where d = 1000 40 32 - 32/2 = 912 mm
For M25 and Pt = 2.35 %, = 0.862 N/mm2 and , = 3.1 N/mm2
Since > , design shear reinforcement.
Take 10 mm 2-legged vertical stirrups for shear reinforcement.
912
Sv = 0.87 Vu, net = 0.874152102/4(1.4150.802)300912

63
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 309.91 mm < 0.75d (= 684 mm) and > 300 mm


Adopt Sv = 300 mm
Provide 10 mm 2-legged vertical stirrups @ 300 mm c/c from quarter to quarter span of
the other side.

Detailing of reinforcement
Since the no. of bars required is same at both mid-span and quarter-span, no curtailment is
done.
Anchorage of main reinforcing bars at supports
Extension of bar beyond the face of support = 23ld
,
Now, ld = 0.7l0 for bars with hook end
,
5294.44
= 0.7(4632)6433.98 where l0 = n
= 847.90 mm
Extension of bar beyond the face of support = 23ld = 23 847.90 = 565.27 566 mm
Side Face Reinforcement
Take 0.1% of web area.
As = 0.001(1000 224)300 = 232.80 mm2
232.80
No. of 8 mm bars required on each face = 3
2 88
4

Provide 3-8 mm on each face.


Check for Limit State of Serviceability in Deflection
(Method of Sufficient Stiffness)

Check
Where,
121000
= = 13.16
912
= 20 (simply supported)
10 10
= = 12
, 5908.48
fs = 0.58fy, = 0.584156433.98 = 221.04 N/mm2
For Pt = 2.35 %, = 0.86
For 2-32 mm compression bars,

2 322
4
Pc = 300912 = 0.588 %
For Pc = 0.588 %, = 1.16
300
For flange, = 0.8 since = 2000 = 0.15
10
So, = 20120.861.160.8 = 13.30 > OK
Hence, deflection of the girder is under control.

64
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

III. Analysis of Cross Beam


1. Intermediate Cross Beam

Self-weight of wearing coat = 0.08x22x1x2x1.75 = 6.16 kN/m


Self-weight of slab = 0.2x25x1x2x1.35 = 13.50 kN/m
Total = 6.16 + 13.50 = 19.66 kN/m
Self-weight of fillet = x0.15x0.3x25x2x1.35 = 1.52 kN/m
Self-weight of cross beam = 0.55x0.25x25x1.35 = 4.64 kN/m
Total = 1.52+4.64 = 6.16 kN/m
19.66 kN/m

6.16 kN/m

Dead Load on Intermediate Cross Beam

Longitudinal Position of Class A Load for Maximum BM and SF

Calculation of max BM at mid-span due to DL and LL


Mu = 6.16x2x - 6.16x1x + 19.66xx2xx1 - x19.66x1x1/3 + 106.875/2x1
= 60.22 kNm
Calculation of max SF at support due to DL and LL
Vu = 6.16x2/2 + x19.66xx2 + 106.875x0.2/2 + 106.875 = 133.553 kN

2. End Cross Beam


Self-weight of wearing coat = x6.16 = 3.08 kN/m
Self-weight of slab = x13.50 = 6.75 kN/m
Total = 3.08 + 6.75 = 9.83 kN/m
Self-weight of fillet = 0.76 kN/m
Self-weight of cross beam = 0.4x0.25x25x1.35 = 3.375 kN/m
Total = 0.76 + 3.375 = 4.135 kN/m

65
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

9.83 kN/m

4.135 kN/m

Dead Load on End Cross Beam

Longitudinal Position of Class A Load for Maximum BM and SF

Mu = 4.135/2x1 - 4.135x1x + 9.83xx2xx1 - x9.83x1x1/3 + 106.875/2x1


= 56.714 kNm
Vu = 4.135x2/2 + x9.83xx2 + 106.875x0.2/2 + 106.875 = 126.613 kN

Design of Cross beams


1. Intermediate Cross beam
Design section
bef = /5 + bw = 2/5 + 0.25 = 0.65m bact = 3 m
d = 750 40 16/2 = 702 mm

Design section for bending


Xu,l = 0.48 d = 336.96 mm
Since Xu,l > Df and Df > 0.43Xu,l, when NA lies in web, we have,
Mu,l = 0.36xfckxbxXu,lx(d 0.416xXu,l ) + 0.446fckx(bef bw)x yf,l x(d yf,l/2 )
Where yf,l = 0.15Xu,l+0.65Df = 180.54mm
Mu,l = 918.523kNm
We have, Mu= 60.22 kNm
Since Mu < Mu,l, section is designed as SRURS.
Mu = 0.36xfckxbefxXu (d 0.416xXu)
Or, 60.22106 = 0.36x25x650xXu (702 - 0.416xXu)
Xu = 14.79 mm < Df
60.2210^6
Ast= 0.87(0.416) = 0.87415(7020.41614.79) =239.70 mm2 < Astmin
Where Astmin = 0.2% of bwd = 0.002 250 702=351.00 mm2
Provide 3-16mm bars as longitudinal bars.

66
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Astprov=603.19mm2, Pt=0.347%
Design for shear
Vu 133.553 1000
= bwd = = 0.76 N/mm2
250 702
Where d = 750 40 16/2 = 702 mm
= 0.41 N/mm2 for M25 and Pt= 0.347 %,
, = 3.1 N/mm2 for M25

Since >, design shear reinforcement.


Take 8mm 2-legged vertical stirrups for shear reinforcement.
0.87d 0.87415(2/482 )702
Sv = (uvuc)bwd = = 414.82mm > 300mm
(0.760.41)250702
< 0.75d = 526.50mm
Adopt Sv = 300mm
Provide 8 mm 2-legged vertical stirrups @ 300 mm c/c.

2. End Cross beam

Design section
bef = /10 + bw = 2/10 + 0.25 = 0.45m bact = 3 m
d = 500 40 16/2 = 452 mm

Design section for bending


Xu,l = 0.48 d = 216.96 mm
Since Xu,l > Df and Df > 0.43Xu,l, when NA lies in web, we have,
Mu,l = 0.36 x fck x b x Xu,l x (d 0.416 x Xu,l) + 0.446 x fck x (bef bw) x yf,l x (d yf,l/2 )
Where yf,l = 0.15Xu,l + 0.65Df = 162.54 mm
Mu,l = 310.97 kNm
We have, Mu= 56.714 kNm
Since Mu < Mu,l, section is designed as SRURS.
Mu = 0.36 x fck x bef x Xu (d 0.416Xu)
Or, 56.714106 = 0.36 x 25 x 450 x Xu (452 - 0.416Xu)
Xu = 31.92 mm < Df
56.714106
Ast = 0.87(0.416) = 0.87415(4520.41631.92) = 358.04 mm2 > Astmin
Where Astmin = 0.2%of bwd = 0.002 250 452 = 226.00 mm2
Provide 3-16mm bars as long bars.
Astprov=603.19mm2, Pt=0.347%

Design for shear


Vu 126.613 1000
= bwd = = 1.12 N/mm2
250 452

67
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Where d = 500 40 16/2 = 452 mm


= 0.41N/mm2 for M25 and Pt = 0.347 %,
, = 3.1 N/mm2 for M25

Since >, design shear reinforcement.


Taking 8mm 2-legged vertical stirrups for shear reinforcement.
0.87d 0.87415(2/482 )452
Sv = (uvuc)bwd = = 204.48 mm < 300mm
(1.120.41)250452
< 0.75d=526.50mm

Adopt Sv = 200mm
Provide 8 mm 2-legged vertical stirrups @ 200 mm c/c.

IV. Design of Elastomeric bearing


Calculation of Loads on Bearing
DL from Superstructure
7. Weight of wearing coat = 6.0 0.08 22 12.25 = 129.36 KN
8. Weight of railing = 2 9 0.225 0.225 1.1 25 + 2 12 3 0.0437 = 28.21 KN
9. Weight of kerb = 0.3 0.6 12.25 2 25 = 110.25 KN
10. Weight of slab = 488.7 + 0.2 7.2 0.25 25 = 497.7 KN
Where
a) Middle portion = 4.3 0.2 12 25 =258 KN
b) Fillet = 1/2 0.15 0.3 12 4 25 + 1/20.15 0.3 1.1 8 25 2 = 36.9
KN
c) Cantilever part = 0.6 0.17 12 2 25 + 0.85 0.26 12 2 25 = 193.80
KN
Weight of web of main girder = 0.3 0.8 12.25 25 3 = 220.5 KN
Weight of web of cross girder = (0.25 0.55 1.7 3 2 + 0.25 0.40 1.7 2 2)
25 = 52.06 KN
Total DL from super structure (Wu) = 1038.08 KN
DL from superstructure on a bearing (DLsup) = 1038.08/6 = 173.01 KN

LL from Superstructure
Maximum LL on a bearing (LL) = Maximum reaction of a main girder = 373.17/1.5 =
250.27 kN

Load due to braking effort [Refer IRC 21: Cl 211.2]


1. Class A load
Braking load = 0.2 (2 114 + 3 68) 2 = 172.8 KN
2. Class AA track load
Braking load = 0.2 700 = 140 KN

68
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

3. Class AA
Braking load = 0.2 400 = 80 KN
Taking braking effort due to Class A loading,
Horizontal Braking load on a bearing (FbrH) = 172.8/6 = 28.8 KN
Braking loads acts at 1.2m above wearing coat.
Point of application of braking load is 2.28 m (1.2+0.08+0.2+0.8) from bearing. It
induces vertical reaction on bearing.
172.8 2.28
Vertical reaction on a bearing due to braking load= 12 3 = 10.94 KN

Wind load [Refer IRC 6: Cl 209.3.5]


Wind load in transverse direction of bridge (FWT) = PZ A G CD = 71.90 KN
Take, Ht. of bridge = 7 m, Basic wind speed = 47 m/s and Plain Terrain
Where, Vz = 27.80 47/33 = 39.59 m/s [Refer Cl. 209, IRC 6]
PZ = 463.70 472/332 = 940.60 N/m2
G = 2 (for span up to 150 m)
CD = 1.3 1.5 = 1.95 [B/ = 7.2, / 6 and more than single girder]
A = (1 + 0.3) 12.25 + 0.225 1.1 9 + 0.0483 (12-9 0.225) 3 = 19.60 m2
Wind load in transverse direction on a bearing (FWT) = 71.90/6 =11.98 KN

Wind load in longitudinal direction of bridge (FWL) = 0.25 FTW = 17.975 KN


Wind load in longitudinal direction on a bearing (FWL) = 17.975/6 = 3.00 KN

Wind load in vert. dir. of bridge (FWV) = PZ A3 G CL = (940.60 10-3) 7.2 12.25
2 0.75 = 124.44 KN
Wind load in vertical direction on a bearing (FWV) = 124.44/6 = 20.74 KN

Seismic Load

Seismic load (FSh) = 2 [Refer Cl. 219, IRC 6]

Take, Seismic Zone - V, Soil Strata - Medium, Damping - 5 %, Bridge Class - Normal
Where,

Ah = h = 2 = 0.225; Z = 0.36, I = 1, R = 2, / = 2.5

W = 1038.08 KN in longitudinal direction
W = 1038.08 + 0.2 2 (2 114 + 3 68) = 1208.63 KN in transverse direction
So,
FShL = 0.225 1035.83= 233.06 KN in longitudinal direction of bridge

69
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

FShT = 0.225 1208.63= 271.94 KN in transverse direction of bridge

Then,
a) Seismic load in transverse direction on a bearing (FShT) = 271.94/6 = 45.32 KN
b) Seismic load in longitudinal direction on a bearing (FShL) = 233.06/6 = 38.84 KN
c) Vertical reaction due to seismic load on support of bridge (FSv)
Seismic loads acts on c. g. of seismic weight. It creates additional vertical load on bearing.
Consider c. g. of seismic weight = 0.9 m from bearing.
V. reaction on a bearing when s. load acts in tr. dir. (FSvT) = 172.97/2 = 86.485 KN
233.06 0.9
Vertical reaction on a bearing when seismic Load acts in long dirn (FSVL) =
12
= 8.74 KN

Load due to temperature variation, creep and shrinkage effect


Maximum horizontal force on a bearing (Fcst) = / G A = 5.44 KN
where,
Strain due to temp., creep and shrinkage = 5 10-4 [Refer IRC 83 Part II Cl. 916.3.4]
Horizontal deformation of bearing ( ) = 510-412.25 103 =3.0625 mm
Shear modulus of elastomer (G) = 1 N/mm2 [Refer IRC 83 Part II, Cl. 915.2.1]
Preliminary height of bearing (h0) = 52 mm
Preliminary effective sectional area of bearing (A) = b l = 238 388 = 92344 mm 2

Load Combinations [Refer IRC 6 Table 1]


Vertical load Horizontal Load
Combination Along Across Along Across Permissible
of load Traffic Traffic Traffic Traffic stress (%)
sup sup
Dl Dl
I
LL LL 100%
[N]
FbrV FbrH
sup sup
Dl Dl
II(A) LL LL
115%
[N+T] FbrV FbrH
Fcst
sup sup
Dl Dl
LL LL
III(A)
FbrV FbrH 133%
[N+ T+ W]
Fcst
FWV F WV FWL F WT
sup sup
Dl Dl
0.2LL 0.2LL
VI
0.5FbrV 0.5FbrH 150%
[N+T+S]
Fcst
FS VL FS VT FS hL FS hT

Calculation of Loads on Bearing According to Combination of Loads

70
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Vertical and horizontal loads subjected to bearing in the direction of traffic are only taken for
design.

Combination I [N]
Total Vertical load = DLSup + LL + FbrV = 173.01 + 250.27 + 10.94 = 434.22 KN
Total Horizontal load = FbrH = 28.8 KN

Combination II (A) [N+T]


Total Vertical load = DLSup + LL + FbrV = 173.01 + 250.27 + 10.94 = 434.22 KN
Total Horizontal load = FbrH + Fcst = 28.8 + 5.44 = 34.24 KN

Combination III (A) [N+T+W]


Total Vertical load = DLSup + LL+ FbrV + FWV = 173.01 + 250.27 + 10.94 + 20.74 = 454.96
KN
Total Horizontal load = FbrH + Fcst + FWL = 28.8 + 5.44 + 3.0 = 37.24 KN

Combination VI [N+T+S]
Total Vertical load = DLSup + 0.2 LL + 0.2 FbrV + FsvL
= 173.01 + 0.2 250.27 + 0.2 10.94 + 8.74= 233.99 KN
Total Horizontal load = 0.2 FbrH + Fcst + FshL = 0.2 28.8 + 5.44 + 38.84 = 50.04 KN

Design of Elastomeric Pad Bearing for Combination I [N]


Effective Span = 12 m, Total Vertical Load = 434.22 kN, Total Horizontal Load = 28.8 kN

1. Geometrical Design
Nmax = 434.22 kN
Nmin = 173.01 kN
Try Standard plan dimension 250x400 mm for elastomeric bearing (IRC 83 Part II)
From table,
Loaded Area = 92344 mm2
Thickness of individual elastomer layer hi = 12 mm
Thickness of outer layer he = 6 mm
Thickness of steel laminate hs = 4 mm
Adopt 3 internal layers and 4 steel laminates.
Overall Thickness = 3x12+4x4+2x6 = 64 mm
Effective Thickness of elastomer h = 3x12+2x6 = 48 mm
Adopt side cover c = 6 mm
Check for Geometry
1. l0/b0 = 400/250 =1.6 2
2. h = 48 < b0/5 = 50 mm
And > b0/10 = 25 mm
92344
3. Shape factor S = 2(238+388)12 = 6.146 (between 6 and 12)
Nmax 434.221000
4. Bearing Stress in concrete (m) = Loaded Area = = 4.70 MPa
92344

71
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

A1/A2 is limited to 2.
A1
Allowable BS = 0.25 A2 = 0.25 25 2 = 8.84 N/mm2
So,
Bearing stress in concrete Allowable Bearing stress OK

2. Structural Design
1. Check for Translation
Design strain in bearing (d) < 0.7
i.e. d = bd = /h + md = 0.0625+0.312 = 0.3745 < 0.7 OK
where
Shear strain per bearing due to shrinkage, creep and temperature= /h
5104 12103
= = 0.0625
248
28.8103
Shear strain due to longitudinal forces = = 923441 =0.312

2. Check for Rotation


Design rotation in bearing (d) nbi, max
1 1
d = dDL+ dLL = 400 MDL L 10-3 + 400 MLL L 10-3 Igr
Igr
2
= 0.00629
where
L =12 m
MDL = 725.88/1.35 = 537.69 KN-m
MLL = 1119.50/1.5 = 746.33 KN-m
Ec = 5000 fck = 25000 N/mm2
= 0.05557741 m4
= 0.1m= 0.1 439.70 1000/(92344) = 0.476
n=6
bi,max = 0.5 h/(2) = 0.51012/(2386.1462) = 0.00667
nbi, max= 0.0190
d nbi, max OK
3. Check for Friction
Design strain in bearing (d) 0.2 + 0.1m
i.e. 0.2 + 0.1m = 0.2 + 0.1x4.76 = 0.676 > 0.3745 OK
And
Normal stress in bearing (m) > 2 MPa and 10 MPa OK
4. Check for Shear Stress
Total shear stress 5 MPa
i.e. c + h + = 2.849 MPa < 5 MPa OK
where
Shear stress due to compression = 1.5xm/S = 1.5x4.76/6.146 = 1.162 MPa
Shear stress due to horizontal deformation = 0.3745x1 = 0.3745 MPa
Shear stress due to rotation = 0.5x(b/hi)2 x bi,max = 0.5 (238/12)2 0.00667
= 1.312 MPa

72
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Check of Elastomeric Pad Bearing for Combination VI [N + T + S]


Effective Span = 12 m, Total Vertical Load = 233.99/1.50 = 155.99 kN, Total Horizontal Load
= 50.04/1.50 = 33.36 kN
1. Geometrical Design
Nmax = 155.99 kN
Nmin = 173.01/1.50 = 115.34 kN
Designed bearing dimension 250x400 mm
Loaded Area = 92344 mm2
Thickness of individual elastomer layer hi = 12 mm
Thickness of outer layer he = 6 mm
Thickness of steel laminate hs = 4 mm
Adopt 3 internal layers and 4 steel laminates.
Overall Thickness = 3x12+4x4+2x6 = 64 mm
Effective Thickness of elastomer h = 3x12+2x6 = 48 mm
Adopt side cover c = 6 mm
Check for Geometry
I. l0/b0 = 400/250 =1.6 2
II. h = 48 < b0/5 = 50 mm
And > b0/10 = 25 mm
92344
III. Shape factor S = 2(238+388)12 = 6.146 (between 6 and 12)
Nmax 155.991000
IV. Bearing Stress in concrete (m) = Loaded Area = 92344 = 1.69 MPa
A1/A2 is limited to 2.
A1
Allowable BS = 0.25 A2 = 0.25 25 2 = 8.84 N/mm2
So,
Bearing stress in concrete Allowable Bearing stress OK

2. Structural Design
I. Check for Translation
Design strain in bearing (d) < 0.7
i.e. d = bd = /h + md = 0.00625+0.361 = 0.36725 < 0.7 OK
where
Shear strain per bearing due to shrinkage, creep and temperature= /h
5104 12103
= = 0.00625
248
33.36103
Shear strain due to longitudinal forces = = 923441 =0.361
II. Check for Rotation
Design rotation in bearing (d) nbi, max
1 1
d = dDL+ dLL = 400 MDL L 10-3 + 400 MLL L 10-3 Igr
Igr
2
= 0.00629

73
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

where
L =12 m
MDL = 725.88/1.35 = 537.69 KN-m
MLL = 1119.50/1.5 = 746.33 KN-m
Ec = 5000 fck = 25000 N/mm2
= 0.05557741 m4
= 0.1m= 0.1 155.99 1000/(92344) = 0.169
n=6
bi,max = 0.5 h/(2) = 0.51012/(2386.1462) = 0.00667
nbi, max= 0.00676
d nbi, max OK
III. Check for Friction
Design strain in bearing (d) 0.2 + 0.1m
i.e. 0.2 + 0.1m = 0.2 + 0.1x1.69 = 0.369 > 0.36725 OK
And
Normal stress in bearing (m) > 2 MPa and 10 MPa OK
IV. Check for Shear Stress
Total shear stress 5 MPa
i.e. c + h + = 2.091 MPa < 5 MPa OK
where
Shear stress due to compression = 1.5xm/S = 1.5x1.69/6.146 = 0.412 MPa
Shear stress due to horizontal deformation = 0.36725x1 = 0.36725 MPa
Shear stress due to rotation = 0.5x(b/hi)2 x bi,max = 0.5 (238/12)2 0.00667
= 1.312 MPa
Summary: Bearing Design
Provide standard 250x400 mm elastomeric pad bearing.
Overall Thickness = 64 mm
Thickness of individual elastomer layer = 12 mm
No of internal elastomer layers = 3
Thickness of each laminate = 4 mm
No of laminates = 4
Thickness of outer layer = 5 mm

74
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

B. Design of Steel Truss (36 m span) bridge

Effective span = 8@4.5m = 36 m


Roadway width = 6 m
Kerb = 0.6 m
Stringer Spacing = 1.5 m
Adopt IRC Class AA Tracked & Class A vehicles
M25 grade concrete & Fe415 steel
I. Design of Deck Slab
Deck slab shall be designed as a one-way slab.
Analysis may be simplified by considering a single 1.5m span between stringers for mid-span
moment and two spans for positive and negative bending moments as in figures below.
Dead Load
Self-wt. of Deck slab = 0.2x25 = 4.8kN/m2
Self-wt. of wearing coat =.08x22 = 1.76KN/m2
Total dead load = 4.8x1.35 + 1.76x1.75 = 9.56KN/m2

Live Load
Here, only class AA tracked vehicle has been adopted for calculations as it is evidently seen
from the figures that larger moments cannot be induced by other vehicles.
Load = W x f x IF = 350 x 1.5 x 1.1 = 577.5 kN

From figure, Maximum positive moment = 216.563 kNm


And Maximum negative moment = 130.29 kNm
Effective width for the tracked vehicle may be calculated as
beff = (3.6 +2 x 0.08) = 3.76 m
Then, for unit m strip, positive moment = 57.6 kNm/m
And negative moment = 34.652 kNm/m

Design of slab section


Total design moments are

75
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Positive moment = 2.688+57.6 = 60.288 KNm


Negative moment = 2.49+34.652 = 37.142 KNm
Q = 0.36 x 25 x 0.48(1 - 0.416 x 0.48) = 3.46
Effective depth of slab is given by

d =
60.2881000
= 3.46
= 132 mm
Adopt overall depth = 200mm
Effective depth = 200-10/2-25 = 170mm
For SRURS (positive moment), For SRURS (positive moment),
. .
= = 2.086 = = 1.285

Pt = 0.548% Pt = 0.406%
Ast = 0.548x200x1000/100 = 1096 mm2 Ast = 0.406x200x1000/100 = 812 mm2
Use 12mm bars @100mm c/c. Use 12mm bars @130mm c/c.
And use 10mm bars @300mm c/c (Astmin) as distribution bars on top and bottom along
longer direction of slab.

II. Design of stringer beam


Dead load due to self-wt. of slab and wearing coat = 9.56x1.5 = 14.34kN/m
Self-wt. of stringer (assumed) = 1KN/m
Total Dead load = 15.34KN/m
Max. BM = 15.34x4.52/8 = 38.83KNm
Max. SF = 15.34x4.5/2 = 34.52KN
For live load,

Figure: position for Max. BM

Max. BM due to live load = (175x2.25-350x0.5x0.5x1.8)1.5x1.1 = 389.81KNm

76
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Figure: position for Max. SF

Max. SF due to live load = (350x2.7/4.5)x1.5x1.1 = 346.5KN


Designed BM = 389.81+38.83 = 428.64KNm
Designed SF = 346.5+34.52 = 381.02KN
[IS 800:2007 steel code, clause 8.2.1.2]
Md = bZpfy/mo
1. Zp = 428.64x106x1.1/250 = 1.87x106 mm3
Use ISHB450 with Zp = 1.955x106 mm3.
Section Classification
250 250
= = 1, = 213.7 = 9.12 < 9.4 ,
(450213.7)
= = 43.12 < 84
9.8
Section is plastic i.e = 1.0

Check for Moment capacity


Md = bZpfy/mo < 1.2Zefy/rmo
= 1x1955.03x1000x250/(1.1x106) <1.2x1740x250/(1.1x106 )
= 444.32KNm < 474.54KNm OK

Check for Shear capacity


Avfy
Vd=
30
4509.8250
= K
31.1
=578.66KN >381.02KN OK

Check for Deflection


5 3
=
384
W=15.34x4.5+350=419.03KN
5419.03100045003
= 3842105 39200104 < 4500/240

77
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

=6.34mm < 18.75 OK

Check for Web Buckling


450
= 2.5 = 114.8
9.8
For buckling class c, fy = 250
Fcd = 89.04 MPa
Fcdw = (b1+n1) x tw x fcd
= (300+225) x 9.8 x 89.04 b1 = 300mm assumed
= 458.11KN > 381.02 OK

Check for Web Crippling


Fcdc=(b1+n2) x tw x fyw/rmo
Where n2 = 2.5(13.7+15) = 71.75
Fcdc = (300+71.75) x 9.8 x 250/1.1 = 827.99KN > 381.02 OK

III. Design of cross girders


Span of cross girder=6+2x0.6=7.2m
Impact factor=10%
Dead load due to slab and wearing coat=9.56x4.5=43.02KN/m
Dead load due to stringer beam=0.872x4.5x1.35=5.3KN
Add load due to connectors=0.375KN
Total load=5.68KN
Self-wt. of cross girder = (0.2L+1) KN/m = (0.2x7.2+1) x 1.35 = 3.3KN/m
Total UDL = (43.02+3.3) = 46.32 KN/m
Figure b
Max. BM = (180.95x3.6-5.68x3-5.68x1.5-46.32x3.6x3.6x0.5) = 325.71KNm
Max. SF = 180.95KN
For live load class AA tracked

Figure: position for Max. BM

78
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Max. BM = (350x3.6-350x1.025)x1.5x1.1=1487.06KNm

Figure: position for Max. SF

Max. SF = (350x5.4/7.2+350x3.35/7.2)x1.5x1.1= 701.83KN

Designed BM=325.71+1487.06=1812.77KNm
Designed SF=180.95+701.83=882.78KN
Md = bZpfy/mo
Zp = 1812.77x106x1.1/1x250
= 7.98x106mm3
Use IS WPB 600x300x285.47
250 305 (620240)
= =1, = 240 = 3.81 < 9.4 = = 25.71 < 84
21

Section is plastic i.e. =1.0

Check for Moment capacity


Md = bZpfy/mo <1.2Zefy/rmo
=1x8772.31x1000x250/(1.1x106) <1.2x7659.6x250/(1.1x106 )
=1993.7KNm <2088.98KNm ok

Check for Shear capacity


Avfy
Vd =
30
62021250
= K
31.1
=1708.43KN >882.78 ok

Check for Deflection


5 3
=
384

79
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

W = 46.32x7.2+5.68x5+30x2x2x1.1x1.5 = 1516.904KN
51516.904100072003
= < 7200/240
3842105 237447104
=15.52mm< 30 OK

Check for Web Buckling


600
= 2.5 = 71.43
21
For buckling class c, fy = 250
Fcd = 133.76MPa
Fcdw = (b1+n1)x tw x fcd
= (300+310) x 21 x 133.76 b1 = 300mm assumed
= 1713.47KN > 882.78 OK

Check for Web Crippling


Fcdc = (b1+n2)xtwxfyw/rmo
Where n2 = 2.5(40+27) = 167.5
Fcdc = (300+167.5)x21x250/1.1 = 2231.25KN > 882.78 OK

IV. Design of Steel Trusses


Pratt truss of 8 panels of 4.5m each
Span of truss = 36m
Height of truss = 6m
Dead load due to deck slab, wearing coat, stringer beam and cross girder acting at each
node
46.327.2+5.685
= = 181KN
2
Self-wt. of truss = (0.15L+5.5)=0.15x36+5.5=10.9KN/m
Self-wt. at each node point = 4.5x10.9=49.05KN
Total dead load = 181+49.05 = 230.05KN
Live loads: IRC class AA loading, maximum BM is produced when the class AA vehicle is
closer to main girder

80
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Max load transferred at the edge of kerb = (350x4.975/7.2+350x2.925/7.2)x1.5x1.1


= 633.65KN
Average UDL = 633.65/3.6 = 176KN/m

Forces in truss member

1) ILD for U1L0

Load on Right Side (between L1 and L8)


FL0U1xsin 53.13 + R1 = 0
1
FL0U1 = 53.13
Load at L1; R1 = 78
So, FL0U1 = -1.094 kN
Now,
Force due to Dead Load
= 230.05(1.094 + 0.938 + 0.78 + 0.625 + 0.469 + 0.313 + 0.156)
= 1006.7 kN (Comp)
Force due to Live Load
= 176x[ (0.985 + 1.094)x0.45 + (0.985 + 1.094)x3.15]
= 658.63 kN (Comp)
2) ILD for U1U2

81
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Load on right side


FU1U2x6 + R1x9 = 0
9
FU1U2 = 6 R1
Load at L2; R1 = 68
So, FU1U2 = -1.125 kN
Load on left side
FU1U2x6 + R2x4.5 = 0
FU1U2 = -4.5R2
Load at L2; R2 = 28 So, FU1U2 = -1.125 kN
Load at L1; R2 = 18 So, FU1U2 = -0.563 kN
Now,
Force due to Dead Load
= 230.05(0.563 + 1.125 + 0.938 + 0.75 + 0.563 + 0.375 + 0.188)
= 1035.69 kN (Comp)
Force due to Live Load
= 176x[ (1.013 + 1.125)x3.6]
= 677.32 kN (Comp)
3) ILD for U2U3

Now,
Force due to Dead Load
= 1293.8 kN (Comp)
Force due to Live Load
= 846.17 kN (Comp)
4) ILD for U3U4

82
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Now,
Force due to Dead Load
= 1380.3 kN (Comp)
Force due to Live Load
= 902.88 kN (Comp)
5) ILD for L0L1

Fx = 0
FL0L1 + FL0U1 cos 53.13 = 0
FL0L1 = R1 cot 53.13
Load at L1; R1 = 78
So, FU1U2 = 0.656 kN
Now,
Force due to Dead Load
= 603.65 kN (Tens)
Force due to Live Load
= 394.73 kN (Tens)
6) ILD for L1L2

Now,
Force due to Dead Load

83
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 603.65 kN (Tens)
Force due to Live Load
= 394.73 kN (Tens)
7) ILD for L2L3

Now,
Force due to Dead Load
= 1035.69 kN (Tens)
Force due to Live Load
= 677.16 kN (Tens)
8) ILD for L3L4

Now,
Force due to Dead Load
= 1293.801 kN (Tens)
Force due to Live Load
= 846.173 kN (Tens)

(Diagonal Members)
9) ILD for U1L2

Load on Right Side


FU1L2xsin 53.13 - R1 = 0

84
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

1
FU1L2 = 53.13
Load at L2; R1 = 68
So, FL0U1 = 0.938 kN (Tens)
Load on left Side
FU1L2xsin 53.13 + R2 = 0
2
FU1L2 = 53.13
Load at L1; R2 = 18
So, FL0U1 = - 0.156 kN
Now,
Force due to Dead Load
= 230.05(-0.156 + 0.938 + 0.782 + 0.625 + 0.469 + 0.313 + 0.156)
= 503.579 kN (Tens)
Force due to Live Load
Maximum Compression
= 176x[ (0.05 + 0.156)x3.6
= 65.261 kN
Maximum Tension
= 559.79 kN
10) ILD for U2L3

Now,
Force due to Dead Load
= 230.05(- 0.157 0.313 + 0.781 + 0.625 + 0.469 + 0.312 + 0.156)
= 430.884 kN (Tens)
Force due to Live Load
Maximum Compression
= 163.66 kN
Maximum Tension
= 460.31 kN

85
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

11) ILD for U3L4

Now,
Force due to Dead Load
= 230.05(- 0.156 0.313 0.469 + 0.625 + 0.469 + 0.313 + 0.156)
= 143.78 kN (Tens)
Force due to Live Load
Maximum Compression
= 262.63 kN
Maximum Tension
= 361.47 kN
(Vertical Members)
12) ILD for U1L1

Force due to Dead Load


= 230.05x1 = 230.05 kN (Tens)
Force due to Live Load
= 176x (0.6 + 1)x3.6 = 506.88 kN (Tens)
13) ILD for U2L2

86
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Consider section (1)-(1)


Load on left side (between L0 and L2)
Considering right portion
FU2L2 = R2 (Tens)
Load at L0; R2 = 0; FU2L2 = 0
Load at L2; R2 = 28 ; FU2L2 = 0.25 (Tens)

Load on right side (between L3 and L8)


Considering left portion
R1 + FL2U2 = 0
FL2U2 = - R2
Load at L3; R1 = 58 ; FL2U2 = - 0.625 (Tens)
Load at L8; R1 = 0 ; FL2U1 = 0
Now,
Force due to Dead Load
= 230.05 (0.125 + 0.25 0.625 0.5 0.375 0.25 0.125)
= 345.075 kN (Comp)
Force due to Live Load
Maximum Tension
= 176x (0.163 + 0.25)x3.6 = 130.84 kN
Maximum Compression
= 176x (0.533 + 0.615)x3.6 = 366.85 kN
14) ILD for U3L3

Now,
Force due to Dead Load

87
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 230.05x0.5
= 115.025 kN (Comp)
Force due to Live Load
Maximum Tension
= 176x (0.288 + 0.375)x3.6 = 210.04 kN
Maximum Compression
= 176x [(0.533 + 0.615)x0.31 + (0.5 + 0.409)x3.29] = 287.92 kN
15) ILD for U4L4
FU4L4 = 0

Class A Load

FIG. Transverse Positioning Of Class A load

Response Due To Class A loading


Ordinates Of ILD
Class A
13.5 13.5 57 57 34 34 34 34 Force Nature Forcex2.3
load
L0-U1 0.048 0.316 1.094 1.05 0.903 0.79 0.69 0.59 228.204 c 524.8692
U1-U2 0.58 0.72 1.125 1.07 0.89 0.77 0.64 0.52 238.545 c 548.6535
U2-U3 0.95 1.07 1.406 1.33 1.06 0.87 0.69 0.5 289.302 c 665.3946
U3-U4 1.125 1.23 1.5 1.4 1.04 0.79 0.54 0.29 287.5325 c 661.32475
L0-L1 0 0.19 0.656 0.61 0.54 0.48 0.42 0.35 135.587 t 311.8501
L1-L2 0 0.19 0.656 0.61 0.54 0.48 0.42 0.35 135.587 t 311.8501
L2-L3 0.563 0.72 1.125 1.07 0.89 0.76 0.64 0.52 237.9755 t 547.34365
L3-L4 0.96 1.07 1.406 1.33 1.06 0.87 0.7 0.5 289.777 t 666.4871
0 0.16 0.938 0.9 0.74 0.64 0.4 0.43 182.066 t 418.7518
U1-L2
0 0.05 0.156 0 0 0 0 0 9.567 c 22.0041
0 0 0.781 0.474 0.59 0.48 0.38 0.28 130.355 t 299.8165
U2L3
0.16 0.157 0.31 0.04 0 0 0 0 24.2295 c 55.72785
0 0 0.625 0.58 0.43 0.33 0.23 0.12 106.425 t 244.7775
U3-L4
0.31 0.36 0.469 0.18 0 0 0 0 46.038 c 105.8874
U1-L1 0.44 0.28 1 0.77 0 0 0 0 110.61 t 254.403
0 0 0.625 0.59 0.48 0.39 0.3 0.22 116.515 c 267.9845
U2-L2
0.12 0.163 0.25 0.163 0 0 0 0 27.3615 t 62.93145

88
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Ordinates Of ILD
Class A
13.5 13.5 57 57 34 34 34 34 Force Nature Forcex2.3
load
0.26 0.28 0.375 0.14 0 0 0 0 36.645 t 84.2835
U3-L3
0 0 0.5 0.46 0.35 0.26 0.18 0.097 84.878 c 195.2194

The maximum axial loads in each member of the truss are tabulated below:
Members DL kN LL kN DL+LL kN
L0-U1 1006.7 (C) 658.63 (C) 0 1665.33 (C)
U1-U2 1035.69 (C) 677.32 (C) 0 1713.01 (C)
U2-U3 1293.8 (C) 846.17 (C) 0 2139.97 (C)
U3-U4 1380.3 (C) 902.88 (C) 0 2283.18 (C)
L0-L1 603.65 (T) 394.73 (T) 0 998.38 (T)
L1-L2 603.65 (T) 394.73 (T) 0 998.38 (T)
L2-L3 1035.69 (T) 677.16 (T) 0 1712.85 (T)
L3-L4 1293.80 (T) 846.17 (T) 0 2139.97 (T)
U1-L2 503.579 (T) 559.79 (T) 65.262 (C) 1063.369 (T)
U2-L3 430.884 (T) 460.31 (T) 163.66 (C) 891.194 (T)
U3-L4 143.78 (T) 361.47 (T) 262.63 (C) 505.25 (T)
U1-L1 230.05 (C) 506.88 (C) 0 736.93 (C)
U2-L2 345.075 (C) 366.85 (C) 130.84 (T) 711.925 (C)
U3-L3 115.025 (C) 287.92 (C) 210.04 (T) 402.945 (C)
U4-L4 0 0 0 0

Properties of Bolt and Gusset Plate


BOLT
Diameter of bolt = M20 bolts of the product grade C
Property class = 10.9 (for steel truss bridge)
From table,
Ultimate tensile strength of bolt material (fub) =1040 Mpa
Yield strength of bolt material (fyb) =940 Mpa.

GUSSET PLATE
Adopt 20 mm thickness.
Ultimate tensile strength of plate (fu) = 410 Mpa.
Yield strength of plate (fy) =250 Mpa.

89
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

V. Design of Truss Joints


In structures like bridges where the load on connections can undergo many cycles of
reversal, fatigue of bolts can become critical if the connection is allowed to slip with each
reversal. So slip resistant connections is designed. Therefore, slip is not permitted at
ultimate load.
Slip Resistance
The design frictional force produced by a bolt at the interface of the connecting parts is
given by,
Vdsf = Vnsf/mf
where Vnsf = the nominal frictional capacity produced by a bolt
= f x n c x K h x Fo
In which,
f = the coefficient of friction or slip factor, usually 0.55
nc = the number of effective interfaces offering frictional resistance = 1
Kh = 1.0 for standard clearance
mf = 1.25 for slip resistance designed at the ultimate load
Fo = the minimum bolt tension (proof load) =Anb x fo
Anb = the net tensile stress area of the bolt
For M20 bolt, Anb = 245 mm^2
fo = the proof stress = 0.7xfub
fub = the ultimate tensile strength of the bolt material
fo = 0.7xfub = 0.7x1040
= 728 MPa
Then, Vnsf = 0.55 x 1 x 1.0 x(245x728)
= 98098 N
Vdsf = Vnsf/ mf
= 98098/1.25
= 78478.4 N
The detailed calculations for connections design at each joint has been provided in the
Annex.

Summary: Truss Joint Connections


The connection details have been tabulated below:
Members Total Load kN Section Provided Bolt Arrangement
L0-U1 1665.33 (C) DC250 3x4
U1-U2 1713.01 (C) DC250 3x4
U2-U3 2139.97 (C) DC300 3x5
U3-U4 2283.18 (C) DC300 3x6
L0-L1 998.38 (T) DC250 3x3
L1-L2 998.38 (T) DC250 3x3

90
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

L2-L3 1712.85 (T) DC300 3x4


L3-L4 2139.97 (T) DC300 3x5
U1-L2 1063.37 (T) 4-ISA 70x70x10 2x4
U2-L3 891.19 (T) 4-ISA 65x65x10 2x3
U3-L4 505.25 (T) 4-ISA 55x55x8 2x2
U1-L1 736.93 (C) 4-ISA 100x100x10 2x3
U2-L2 711.93 (C) 4-ISA 100x100x10 2x5
U3-L3 402.95 (C) 4-ISA 80x80x10 2x2
U4-L4 0 4-ISA 80x80x10 2x2

VI. Consideration of Wind Load on Member Stresses


Members No. Depth(mm) Width(mm) Face(m) Area(m2)
1. Top chords 4 316 300 0.316 5.688
2 266 300 0.266 2.394
2. Bottom chords 4 316 300 0.316 5.688
4 266 300 0.266 4.788
3. End posts 2 266 300 0.266 3.99
4. Verticals 7 300 212 0.212 8.904
5. Diagonals 2 300 152 0.152 2.28
2 300 142 0.142 2.13
2 300 122 0.122 1.93
6. Gusset plates
area @ 0.5m2 for
70.5 m2 @ top - - - - 3.5
90.5m2 @ bottom - - - - 4.5
7. Deck structure - - - - 29.844

Case (I) Bridge is unloaded


1
Wind load acting on top chord = Wind load acting on top chord + 2 wind load on
1
verticals + 2 wind load on diagonals and end posts + wind load on top gusset
1
= Pz G CD (Area of top chord + 2 (areas of end post + verticals + diagonals) +
1
top gusset) + Pz G CD (Area of top chord + 2 (areas of end post + verticals + diagonals)
+ top gusset)
1
= 940.60 2(5.668+2.394 + 2(3.99+5.544+2.28+2.13+1.83)+3.5)(1.776+0.876 1.776)
= 121.90 KN

91
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

1
Wind load acting on bottom chord = Wind load acting on bottom chord + 2 wind load on
1
verticals + 2 wind load on diagonals and end posts + wind load on bottom gusset
1
= Pz G CD( Area of bottom chord + 2 (areas of end post + verticals + diagonals) +
1
bottom gusset + deck structure area) + Pz G CD (Area of bottom chord + 2 (areas of
end post + verticals + diagonals )+ bottom gusset)
= 940.60 x2 (1.776x (5.688+4.788+0.5(3.99+5.544+2.28)+4.5+29.844 )+ 0.876x
1.776(5.688+4.788+0.5(3.99+5.544+2.28)+4.5)
= 230.598 KN

[Chandra, 1981]
Overturning effect due to wind when the bridge is unloaded
Taking moment about the level of bearings,
2Rx7.5 = 121.90 x6.158+ 230.598 x 0.158
Or, R = 52.47 KN
Thus, 2R = 104.95 KN
Due to the overturning effect, a thrust of 104.95 KN acts downward on leeward
girder,

92
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Increase in stress in central top chord member U3U4 of leeward girder is given by,
1 104.95
= 2 x 1.5x36x 36
= 78.71 KN (C)
Increase in stress in central bottom chord member L3L4 of the leeward girder is given
by,
1 104.95
= 2 x 1.406x36x 36
= 73.78 KN (T)

(i) Lateral effect of top chord bracing when bridge is unloaded


Wind pressure acting on top lateral bracing is shown in figure.

The top chord of leeward girder are subjected to tension due to lateral effect of top
bracing.
Therefore, the force in these members decrease.
Decrease in force in central top chord member due to top lateral bracing is,
121.9027 1
= x
8 7.5
= 54.855 KN (T)

(ii) Lateral effect of bottom chord bracing when the bridge is unloaded
Wind load acting on bottom bracing is shown in figure.

93
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

The bottom chord members of leeward girder are subjected to tension.


Therefore, the forces in these members increase.
Increase in force in central bottom chord member due to bottom lateral bracing is,
230.59836 1
= x
8 7.5
= 138.36 KN (Tension)

Case (II) Bridge is loaded


When the bridge is loaded with the vehicles, then the weight of the vehicle
counter act the wind load acting on the truss members. So, this case is not shown here.
Thus,
Total T on L3L4 = 2139.97 + 73.78 + 138.36 = 2352.1 kN < 3165.45 kN OK
And,
Total C on U3U4 = 2283.18 + 78.71 54.855 = 2307 kN < 2952.6 kN OK

VII. Consideration of Seismic Force


Sections Weight (kN/m) No. Length (m) Total (kN)
Bottom Part
Deck - - - 2015.47
Stringer - - - 156.96
Cross girder - - - 184.66
DC 300 1.092 8 4.5 39.31
DC250 0.984 8 4.5 17.71
4 3.75 14.76
ISA 70x70x10 1.004 4 3.75 15.06
ISA 65x65x10 0.94 4 3.75 14.1
ISA 55x55x8 0.7 4 3.75 10.5
ISA 60x60x10 0.876 14 3 36.792
ISA 65x65x8 0.07 16 8.75 9.8
(bracing)
Live Load 1108
Total 3626.7

Top Part
DC 300 1.092 8 4.5 39.31
DC250 0.984 4 4.5 17.71
4 3.75 14.76
ISA 70x70x10 1.004 4 3.75 15.06
ISA 65x65x10 0.94 4 3.75 14.1

94
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ISA 55x55x8 0.7 4 3.75 10.5


ISA 60x60x10 0.876 14 3 36.792
ISA 45x45x5 0.034 12 8.75 3.57
(bracing)
Total 151.8

Zone factor (z) = 0.36 (for zone V)


D = 3626.7+151.8 = 3778.5 KN
F = k = 115.89 KN/m (from conjugate beam analysis)
Time period (T) = 2(D/1000F)0.5
= 0.3611 sec
From code,
Sa/g = 2.5 (for soil type II and T= 0.3611 sec <0.4sec)
Importance factor (I) = 1 (for normal bridge)
Ah = Z/2xI/Rx Sa/g
0.36 1
= 4 2.5
2
= 0.1125
For Bottom part,
Feq = Ah x Seismic Weight
= 0.1125 x 3626.7
= 408 KN
For Top part,
Feq = Ah x Seismic Weight
= 0.1125 x 151.8
= 17.1 KN

VIII. Design of Bracings


Design of Top Bracing
Load due to Wind effect will be considered.

95
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Design Load=54.24KN

Based on yielding, Ag = /0
54.241000
= 250/1.1

= 238mm2
Adopt <45x45x5, Ag = 428 mm2 (It may be difficult in bolting for smaller sections.)
Check for Rupture
Gusset Thickness =12mm, M20 bolts of grade 10.9
fus=410MPa , fub=1040MPa
fys=250MPa, fyb=940MPa

Slip Resistance=78478.4N
54.24103
No. of Bolts = =1
78478.4
Adopt 2 Bolts.

= 1.4 0.076

= 1.4 - 0.076x45/5x250/410x(45+25-5)/50
= 0.858
0.9 0.9(452.5)5410 0.858(452.5)5250
Tdn = + = + = 104.2 kN > 54.24 kN OK
1 0 1.25 1.1

Design of Bottom Bracing


Load due to Seismic effect will be considered.

96
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Designed AF=208.16KN
208.16
Based on yielding, Ag=/0 =250/1.1 =916mm2

Adopt <65x65x8,Ag=976mm2
Check For Rupture
208.1610^3
No. of Bolt= = 2.65
78478.4
Adopt 3 Bolts
= 1.4-0.076x65/8x250/410x(65+35-8)/100
= 1.05>0.7
0.9
Tdn = +
1 0
0.9390410 1.05610250
= +
1.25 1.1
= 260.7KN>208.16KN
Where Anc=(65-4-22)x10=390
Ago=(65-4)x10 =610
Block Shear
Avg=150x10=1500 mm2
Avn=(150-1.5x22)x10=1170mm2
Atg=30x10=300mm2
Atn=(30-0.5-22)x10=75mm2
1500250 0.975410 0.91170410 300250
Tdb= + or +
31.1 1.25 31.25 1.1

=218.96 or 267.58
=218.96KN>208.16KN ok

97
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Design of Portal Bracing

Design of members bc, de


Design tension, T = 250.89 kN
250.89103
Ag required = = 250 = 1103.92 mm2
0 1.1

Use <65x65x10 with Ag = 1200 mm2


For M20 bolts of property class 10.9,
Vnsf = 78478.4 kN
250.8910^3
No of Bolts = = 3.2
78478.4
Take 4 bolts.
Check for Rupture
65 250 65+3510
= 1.4 0.076 10 410 = 1.22 > 0.7 and <1.4
150
0.9 0.910(60225)410 1.2210(655)250
Tdn = + = +
1 0 1.25 1.1
= 264.676 kN > 250.89 kN OK
Check for Block Failure
Avg = 200x10 = 2000 mm2
Avn = (200 3.5x22)x10 = 1230 mm2
Avg = 30x10 = 300 mm2
Avg = (30 0.5x22)x10 = 190 mm2
2000250 0.9190410 0.91230410 300410
Tdb = + or +
1.13 1.25 1.253 1.1

= 318.52 or 277.82 kN
= 277.82 kN > 250.89 kN OK

Design of member bf
Design Compression = 247.84 kN

98
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Assume fcd = 60 MPa


247.84103
Ag required = = 4130.67 mm2
60
Try <150x150x20 with Ag = 5620 mm2 and rv = 29.3 mm
Now,
7200
= = 245.73
29.3
1+2 150+150
= = 7.5
2 220
250
= ( )0.5 = 1
2 2 2105 0.5
( 250 )0.5 = ( ) = 88.86
250

245.73
vv = 2 0.5
= = 2.76
( ) 88.86
250
1+2
2
= 2 0.5
= 0.08
( )
250

From Table 12 of IS code,


k1 = 0.20, k2 = 0.35, k3 = 20
e = 1 + 2 2 + 3 2 = 1.73
From Table 7 of IS Code, = 0.49 for buckling class c
Then,
= 0.5[1 + ( 0.2) + 2 ] = 2.37
1
= [+(2 2 )0.5 ] = 0.25

fcd = x0 = 56.96 Mpa

Strength = fcdxAg = 56.96x5620 = 320.1 kN >247.84 kN OK


247.8410^3
No of Bolts = = 3.2
78478.4
Take 4 bolts.
Check for Rupture
150 250 150+7520
= 1.4 0.076 410 = 0.9 > 0.7 and <1.4
20 150
0.9 0.920(1502210)410 0.920(15010)250
Tdn = + = +
1 0 1.25 1.1
= 1269.4 kN >> 250.89 kN OK
Check for Block Failure
Avg = 200x20 = 4000 mm2
Avn = (200 3.5x22)x20 = 2460 mm2
Avg = 75x20 = 1500 mm2

99
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Avg = (75 0.5x22)x20 = 1280 mm2


4000250 0.91280410 0.92460410 1500410
Tdb = + or +
1.13 1.25 1.253 1.1

= 902.7 or 978.3 kN
= 902.7 kN 250.89 kN OK

Design of Sway Bracing

Load on sway braces = 33.97 kN (T/C)


Use <45x45x5 with two bolts at each end as sway bracing.

IX. Design of Connections


Design of connection (cross beam and stringer connection)
Different plane connection:
Shear force from one stringer (Vu) = 381.02 KN
Total shear for connection design = shear from two stringers = 2x381.02 = 762.04 kN
Moment from stringer (Mu) = 428.64 KNm
Design Moment = 60% of Mu = 0.6x428.64 = 257.184KNm
For M20 bolts of grade 10.9, we know the following properties:
fyb = 940 N/mm2
fub = 1040 N/mm2
Nominal Frictional strength of bolt (Vnsf) = fxnexkhxFo
Here, f = the coefficient of friction or slip
ne = the number of effective interfaces offering frictional resistance(i.e 2)
kh = 1.0 for standard clearance
Fo = the minimum bolt tension (proof load = Anbxfo)
Anb = the net area of the bolt
fo = the proof stress = 0.7xfub = 0.7x1040 = 728
fub = the ultimate tensile strength of the bolt material

100
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

So, Fo = 245 mm2 x 728 N/mm2 = 178360 N


Then, Vnsf = 0.52x2x1x178360
= 185.49 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 185.49/1.25 = 148.39 KN
Now,
6
No. of bolts required (n) =

Where,
Tdb= Tdf = Tnf/ mf
1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnb fybxAsbx
= 0.9x1040x245 940x314x1.25/1.1
= 229.32 KN 335.41 KN
So, Tdf = 229.32/1.25 = 183.456 KN
p = pitch distance = 2.5d = 2.5x20 = 50mm
No. of vertical rows (m) = 2
6257.184106
Therefore, n= 250183.456103 = 9.17 10
To arrange 10 no. of bolts in a single line is not adjustable and not okay with our problem, so
we try again with M27 bolts.
Frictional strength of bolt (Vnsf) = fxnexkhxFo
where Fo = Anbxfo = 459 mm2 x 728 N/mm2 = 334152 N
So, Vnsf = 0.52x2x1x334152
= 347.52 KN
Design strength of bolt (Vdsf) = Vnsf/mf = 347.52/1.25 = 278.01 KN
6
Now, No. of bolts required (n) =

Tdb= Tdf = Tnf/ mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnb fybxAsbx
= 0.9x1040x459 940x573x1.25/1.1
= 429.624 KN 612.07 KN
So, Tdf = 429.624/1.25 = 343.699 KN
p = pitch distance = 2.5d = 2.5x27 = 67.5mm
Adopt p = 70mm
No. of vertical rows (m) = 2
6257.184106
Therefore, n= 270343.699103 = 5.66 6 bolts
Total no. of bolts in same plane = 2x6 = 12
Check:
762.04
Shear force in extreme critical bolt, Vb = = = 31075 KN
212

101
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

yi2 = 2(352+1052+1752)
= 85750 mm2
M = M/2 = 257.184/2 = 128.59 KNm
Yn = 175 mm
128.59106 175
Tensile force in extreme critical bolt (Tb) = = = 262.43 KN
yi2 85750
Combined shear and tension equation:
2 2
() + () 1
63.50 2 262.43 2
= (148.39) + (343.699)
= 0.766 < 1 OK
Above value 0.766 which is less than 1 shows that the design connection we designed is okay.

Stringer and angle section connection (same plane connection)


Adopt 24mm HSFG bolt of grade 12.9 having following properties:
fyb = 1100 N/mm2
fub = 1220 N/mm2
Then,
Frictional strength of bolt (Vnsf) = fxnexkhxFo
Where Fo =Anbxfo = 353 mm2 x (0.7x1220) N/mm2 = 301462 N
Vnsf = 0.52x2x1x301462
= 313.52 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 313.52/1.25 = 250.82 KN
6
No. of bolts required (n) =

Tdb= Tdf = Tnf/ mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnb fybxAsbx
= 0.9x1220x353 940x452x1.25/1.1

102
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 387.594 KN 428.82 KN
So, Tdb = 387.594/1.25 = 310.07 KN
p = pitch distance = 2.5d = 2.5x24 = 60mm
No. of vertical rows (m) = 2
6257.184106
Therefore, n= 260250.82103 = 7.16 8 bolts
The arrangement of 8 bolts in a single vertical line is not adjustable as required spacing
between the bolts is not sufficient.
So, trying with M36 HSFG bolts,
Frictional strength of bolt (Vnsf) = fxnexkhxFo
Where Fo =Anbxfo = 817 mm2 x (0.7x1220) N/mm2 = 697718 N
So, Vnsf = 0.52x2x1x697718
= 725.63 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 725.63/1.25 = 580.5 KN
6
No. of bolts required (n) =

Tdb= Tdf = Tnf/ mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnb fybxAsbx
= 0.9x1040x817 940x1018x1.25/1.1
= 7640412 KN 1087.41 KN
Tdf = 764.712/1.25 = 611.77 KN
p = pitch distance = 2.5d = 2.5x36 = 90mm
No. of vertical rows (m) = 2
6257.184106
Therefore, n= 290580.5103 = 3.84 4 bolts
Hence, 4 bolts in each vertical line can be arranged with required spacing.

103
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Design of connection (cross beam and truss)


Different plane connection:
Shear force from one cross beam (Vu) = 882.78KN
Total shear for connection design = shear from one cross beam = 1x882.78 =
882.78kN
Moment from s (Mu) = 1812.77 KNm
Design Moment = 60% of Mu = 0.6x1812.77 = 1087.662 KNm
For M20 bolts of grade 10.9, we know the following properties:
fyb = 940 N/mm2
fub = 1040 N/mm2
Nominal Frictional strength of bolt (Vnsf) = fxnexkhxFo
Here, f = the coefficient of friction or slip
ne = the number of effective interfaces offering frictional resistance(i.e 2)
kh = 1.0 for standard clearance
Fo = the minimum bolt tension (proof load = Anbxfo)
Anb = the net area of the bolt
fo = the proof stress = 0.7xfub = 0.7x1040 = 728
fub = the ultimate tensile strength of the bolt material
So, Fo = 245 mm2x728 N/mm2 = 178360 N
Then, Vnsf = 0.52x1x1x178360
= 92.745 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 92.745/1.25 = 74.196 KN
Now,
6
No. of bolts required (n) =

Where,
Tdb= Tdf = Tnf/mf
1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnbfybxAsbx
= 0.9x1040x245 940x314x1.25/1.1
= 229.32 KN 335.41 KN
So, Tdf = 229.32/1.25 = 183.456 KN
p = pitch distance = 2.5d = 2.5x20 = 50mm
No. of vertical rows (m) = 4
61087.662106
Therefore, n= 450183.456103 = 13.336 14
To arrange 14 no. of bolts in a single line is not adjustable and not okay with our problem, so
we try again with M27 bolts.
Frictional strength of bolt (Vnsf) = fxnexkhxFo
Where Fo =Anbxfo= 459 mm2x728 N/mm2 = 334152 N
104
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

So, Vnsf = 0.52x1x1x334152


= 173.76 KN
Design strength of bolt (Vdsf) = Vnsf/mf = 173.76/1.25 = 139.008 KN
6
Now, No. of bolts required (n) =

Tdb= Tdf = Tnf/mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnbfybxAsbx
= 0.9x1040x459 940x573x1.25/1.1
= 429.624 KN 612.07 KN
So, Tdf = 429.624/1.25 = 343.699 KN
p = pitch distance = 2.5d = 2.5x27 = 67.5mm
Adopt p = 70mm
No. of vertical rows (m) = 4
61087.662106
Therefore, n= 470343.699103 = 8.234 9 bolts
To arrange 9 no. of bolts in a single line is not adjustable and not okay with our problem, so we
try again with M30 bolts.
Frictional strength of bolt (Vnsf) = fxnexkhxFo
whereFo =Anbxfo= 0.78x706.85 mm2x728 N/mm2 = 401382.44 N
So, Vnsf = 0.52x1x1x401382.44
= 208.72 KN
Design strength of bolt (Vdsf) = Vnsf/mf = 208.72/1.25 = 166.976 KN
6
Now, No. of bolts required (n) =

Tdb= Tdf = Tnf/mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnbfybxAsbx
= 0.9x1040x0.78x706.85 940x706.85x1.25/1.1
= 516.06 KN 755.044 KN
So, Tdf = 755.044/1.25 = 604.035 KN
p = pitch distance = 2.5d = 2.5x30 = 75m
No. of vertical rows (m) = 4
61087.662106
Therefore, n= 475604.035103 = 6 bolts
Total no. of bolts in same plane = 4x6 = 24
Check:
882.78
Shear force in extreme critical bolt,Vb = = = 36.78 KN
24
yi2 = 4(37.52+112.52+187.52)
= 196875 mm2
M = M/2 = 1087.662/2 = 543.831 KNm

105
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Yn = 187.5 mm
543.831106 187.5
Tensile force in extreme critical bolt (Tb) = = = 517.93 KN
yi2 196875
Combined shear and tension equation:
2 2
() + () 1
36.78 2 517.93 2
= (74.196) + (604.35)
= 0.98 < 1 OK
Above value 0.98 which is less than 1 shows that the design connection we designed is okay.

Cross beam and angle section connection (same plane connection)


Adopt 24mm HSFG bolt of grade 12.9 having following properties:
fyb = 1100 N/mm2
fub = 1220 N/mm2
Then,
Frictional strength of bolt (Vnsf) = fxnexkhxFo
Where Fo =Anbxfo= 353 mm2x(0.7x1220) N/mm2 = 301462 N
Vnsf = 0.52x2x1x301462
= 313.52 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 313.52/1.25 = 250.82 KN
6
No. of bolts required (n) =

Tdb= Tdf = Tnf/mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnbfybxAsbx
= 0.9x1220x353 940x452x1.25/1.1
= 387.594 KN 428.82 KN
So, Tdb = 387.594/1.25 = 310.07 KN
p = pitch distance = 2.5d = 2.5x24 = 60mm
No. of vertical rows (m) = 2

106
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

61087.662106
Therefore, n= 260250.82103 = 14.72 15 bolts
The arrangement of 15 bolts in a single vertical line is not adjustable as required spacing
between the bolts is not sufficient.
So, trying with M36 HSFG bolts,
Frictional strength of bolt (Vnsf) = fxnexkhxFo
Where Fo =Anbxfo= 817 mm2x(0.7x1220) N/mm2 = 697718 N
So, Vnsf = 0.52x2x1x697718
= 725.63 KN
Design Strength of bolt (Vdsf) = Vnsf/mf = 725.63/1.25 = 580.5 KN
6
No. of bolts required (n) =

Tdb= Tdf = Tnf/mf


1
Tnf = nominal tensile strength of bolt = 0.9xfubxAnbfybxAsbx
= 0.9x1040x817 940x1018x1.25/1.1
= 7640412 KN 1087.41 KN
Tdf = 764.712/1.25 = 611.77 KN
p = pitch distance = 2.5d = 2.5x36 = 90mm
No. of vertical rows (m) = 2
61087.662106
Therefore, n= 290580.5103 = 7.9 8 bolts
Hence, 8 bolts in each vertical line are to be arranged but our dimension of cross beam doesnt
fit all the bolts. So we are trying 3 vertical lines.
61087.662106
n= 490580.5103 = 5.58 6 bolts
Hence, 6 bolts in each vertical line can be arranged with required spacing.

X. Design of Elastomeric bearing for truss


Calculation of Loads on Bearing

107
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

2. DL from Superstructure
From calculation table seismic force in bracing
Total DL from super structure (Wu) = 2776.2 KN
DL from superstructure on a bearing (DLsup) = 2776.2/4 = 694.05 KN

3. LL from Superstructure
Transverse positioning of class A vehicle:
Distribution factor for one bearing = 0.88W+0.64W+0.52W+0.28W
=2.32W
Longitudinal positioning of class A vehicle:
Total load = 2.32W
= 2.32[57(1+0.966)+34(0.85+0.764+0.68+0.6)+13.5x0.042]
= 2.32x211.025
= 489.58 KN

4. Load due to braking effort


Class A load
Braking load = 0.2 (2 114 + 4 68 + 2 27) 2 = 221.6 KN
Class AA track load
Braking load = 0.2 700 = 140 KN
Class AA
Braking load = 0.2 400 = 80 KN
Taking braking effort due to Class A loading,
Horizontal Braking load on a bearing (FbrH) = 221.6/4= 55.4 KN
Braking loads acts at 1.2m above wearing coat.
Point of application of braking load is 2.1 m (1.2+0.08+0.2+0.62) from bearing. It
induces vertical reaction on bearing.
221.6 2.1
Vertical reaction on a bearing due to braking load= 36 2 = 6.46 KN

5. Wind load
From the wind calculation of bracing,
Wind load acting on the top chord = 121.90 KN
Wind load acting on the bottom chord = 230.598 KN
Total wind load acting on the truss = 121.90 + 230.598 = 352.498 KN
Wind load in transverse direction on a bearing (FWT) = 352.498/4 = 88.1245 KN

108
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

d) Wind load in longitudinal direction of bridge (FWL) = 0.25 FTW= 88.1245 KN


Wind load in longitudinal direction on a bearing (FWL) = 88.1245/4 = 22.031 KN

e) Wind load in vert. dir. of bridge (FWV) = PZ A3 G CL = 940.6 7.8 36.3 2 0.75
= 399.48 KN
Wind load in vertical direction on a bearing (FWV) = 399.48/4 = 99.87 KN

6. Seismic Load

Seismic load (FSh) = 2 [Refer Cl. 219, IRC 6]

Take, Seismic Zone - V, Soil Strata - Medium, Damping - 5 %, Bridge Class - Normal
Where,

Ah = h= 2 = 0.225; Z = 0.36, I = 1, R = 2, /= 2.5

W = 2670.5 KN in longitudinal direction
W = 2670.5 + 0.2 2 (2 114 + 4 68 + 2 27) = 2892.10 KN in transverse direction
So,
FShL = 0.225 x 2670.5= 600.86 KN in longitudinal direction of bridge
FShT = 0.225 2892.10= 650.72 KN in transverse direction of bridge

Then,
f) Seismic load in transverse direction on a bearing (FShT) =600.86/4 =150.22 KN
g) Seismic load in longitudinal direction on a bearing (FShL) = 650.72/4 =162.68 KN
h) Vertical reaction due to seismic load on support of bridge (FSv)
Seismic loads acts on c. g. of seismic weight. It creates additional vertical load on bearing.
Consider c. g. of seismic weight = 0.5 m from bearing.
600.86 0.5
V. reaction on a bearing when s. load acts in tr. dir. (FSvT) = =20.03 KN
7.5
650.72 0.5
Vertical reaction on a bearing when seismic Load acts in long dirn(FSVL) =
36
=4.52 KN

7. Load due to temperature variation, creep and shrinkage effect


Maximum horizontal force on a bearing (Fcst) = / G A = 26.23 KN
where,
Strain due to temp., creep and shrinkage = 5 10-4 [Refer IRC 83 Part II Cl. 916.3.4]
Horizontal deformation of bearing ( )=510-436.3 103 =9.075 mm
Shear modulus of elastomer (G) = 1 N/mm2 [Refer IRC 83 Part II, Cl. 915.2.1]
Preliminary height of bearing (h0) = 52 mm
Preliminary effective sectional area of bearing (A) = b l = 308 388 = 150304 mm 2

Load Combinations [Refer IRC 6 Table 1]

109
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Vertical load Horizontal Load


Combination Along Across Along Across Permissible
of load Traffic Traffic Traffic Traffic stress (%)
sup sup
Dl Dl
I
LL LL 100%
[N]
FbrV FbrH
sup sup
Dl Dl
II(A) LL LL
115%
[N+T] FbrV FbrH
Fcst
sup sup
Dl Dl
LL LL
III(A)
FbrV FbrH 133%
[N+ T+ W]
Fcst
FWV F WV FWL F WT
sup sup
Dl Dl
0.2LL 0.2LL
VI
0.5FbrV 0.5FbrH 150%
[N+T+S]
Fcst
FS VL FS VT FS hL FS hT

Calculation of Loads on Bearing According to Combination of Loads

Vertical and horizontal loads subjected to bearing in the direction of traffic are only taken for
design.

Combination I [N]
Total Vertical load = DLSup + LL + FbrV = 694.05 + 489.58 + 6.46 = 1190.09 KN
Total Horizontal load = FbrH = 55.4 KN
Combination II (A) [N+T]
Total Vertical load = DLSup + LL + FbrV = 694.05 + 489.58 + 6.46 = 1190.09 KN
Total Horizontal load = FbrH + Fcst = 55.4 + 26.23 = 81.63 KN

Combination III (A) [N+T+W]


Total Vertical load = DLSup + LL+ FbrV + FWV = 694.05 + 489.58 + 6.46 + 99.87 = 1289.96
KN
Total Horizontal load = FbrH + Fcst + FWL = 55.4 + 26.23 + 22.03= 103.66 KN

Combination VI [N+T+S]
Total Vertical load = DLSup + 0.2 LL + 0.5 FbrV + FsvL
= 694.05 + 0.2 489.58 + 0.5 6.46 + 4.52= 795.20 KN
Total Horizontal load = 0.5 FbrH + Fcst + FshL = 0.5 55.4 + 26.23 + 162.68 = 216.61 KN

Design of Elastomeric Pad Bearing for Combination I [N]


Effective Span = 36 m, Total Vertical Load = 1190.09 kN, Total Horizontal Load = 55.4 kN

110
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Geometrical Design
Nmax = 1190.09 kN
Nmin = 55.4 kN
Try Standard plan dimension 320x500 mm for elastomeric bearing (IRC 83 Part II)
From table,
Loaded Area = 150304 mm2
Thickness of individual elastomer layer hi = 10 mm
Thickness of outer layer he = 5 mm
Thickness of steel laminate hs = 3 mm
Adopt 3 internal layers and 4 steel laminates.
Overall Thickness = 3x10+4x3+2x5 = 52 mm
Effective Thickness of elastomer h = 3x10+2x5 = 40 mm
Adopt side cover c = 6 mm
Check for Geometry
l0/b0 = 500/320 =1.5625 2
h = 40 < b0/5 = 64 mm
And > b0/10 = 32 mm
150304
Shape factor S = 2(308+488)10 = 9.44 (between 6 and 12)
Nmax 1163.6651000
Bearing Stress in concrete (m) = Loaded Area = 150304 = 7.74 MPa
A1/A2 is limited to 2.
A1
Allowable BS = 0.25 = 0.25 30 2 = 10.61 N/mm2
A2
So,
Bearing stress in concrete Allowable Bearing stress OK

Structural Design
Check for Translation
Design strain in bearing (d) < 0.7
i.e. d = bd = /h + md = 0.225+0.369 = 0.594 < 0.7 OK
where
Shear strain per bearing due to shrinkage, creep and temperature= /h
5104 36103
= = 0.225
240
55.4103
Shear strain due to longitudinal forces = =1503041 =0.369

1. Check for Rotation


Design rotation in bearing (d) nbi, max

2. Check for Friction


Design strain in bearing (d) 0.2 + 0.1m
i.e. 0.2 + 0.1m = 0.2 + 0.1x7.74 = 0.974 > 0.594 OK
And

111
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Normal stress in bearing (m) > 2 MPa and 10 MPa OK

3. Check for Shear Stress


Total shear stress 5 MPa
i.e. c + h + = 2.687 MPa < 5 MPa OK
where
Shear stress due to compression = 1.5xm/S = 1.5x7.74/9.44 = 1.23 MPa
Shear stress due to horizontal deformation = 0.594x1 = 0.594 MPa
Shear stress due to rotation = 0.5x(b/hi)2 x bi,max = 0.5 (308/10)2 0.00182
= 0.863 MPa

Check for Combination VI [N + T + S]


Effective Span = 36 m, Total Vertical Load = 795.20 kN, Total Horizontal Load = 216.61 kN
Geometrical Design
Nmax = 795.20/1.5 = 530.133 kN
Nmin = 216.61/1.5 = 144.41 kN
Try Standard plan dimension 320x500 mm for elastomeric bearing, as for Combination I [N]
From table,
Loaded Area = 150304 mm2
Thickness of individual elastomer layer hi = 10 mm
Thickness of outer layer he = 5 mm
Thickness of steel laminate hs = 3 mm
Adopt 3 internal layers and 4 steel laminates.
Overall Thickness = 3x10+4x3+2x5 = 52 mm
Effective Thickness of elastomer h = 3x10+2x5 = 40 mm
Adopt side cover c = 6 mm
Check for Geometry
1. l0/b0 = 500/320 =1.5625 2
2. h = 40 < b0/5 = 64 mm
And > b0/10 = 32 mm
150304
3. Shape factor S = 2(308+488)10 = 9.44 (between 6 and 12)
Nmax 530.1331000
4. Bearing Stress in concrete (m) = Loaded Area = 150304 = 3.53 MPa
A1/A2 is limited to 2.
A1
Allowable BS = 0.25 A2 = 0.25 30 2 = 10.61 N/mm2
So,
Bearing stress in concrete Allowable Bearing stress OK

Structural Design
1. Check for Translation

112
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Shear strain per bearing due to shrinkage, creep and temperature= /h


5104 36103
= = 0.225
240
144.41103
Shear strain due to longitudinal forces, md = = 1503041 =0.961
Design strain in bearing (d) < 0.7
i.e. d = bd = /h + md = 0.225+0.961 = 1.186 < 0.7 NOT OK

2. Check for Rotation


Design rotation in bearing (d) nbi, max

3. Check for Friction


Design strain in bearing (d) 0.2 + 0.1m
i.e. 0.2 + 0.1m = 0.2 + 0.1x3.53 = 0.553 > 1.186 NOT OK
And
Normal stress in bearing (m) > 2 MPa and 10 MPa OK

4. Check for Shear Stress


Total shear stress 5 MPa
i.e. c + h + = 2.61 MPa < 5 MPa OK
where
Shear stress due to compression = 1.5xm/S = 1.5x3.53/9.44 = 0.561 MPa
Shear stress due to horizontal deformation = 1.186x1 = 1.186 MPa
Shear stress due to rotation = 0.5x(b/hi)2 x bi,max = 0.5 (308/10)2 0.00182
= 0.863 MPa
Hence, the bearing fails. Try 400x800 elastomeric pad bearing to fulfill the failed criteria.

Loaded Area = 305744 mm2


Thickness of individual elastomer layer hi = 12 mm
Thickness of outer layer he = 6 mm
Thickness of steel laminate hs = 4 mm
Adopt 3 internal layers and 4 steel laminates.
Overall Thickness = 3x12+4x4+2x6 = 64 mm
Effective Thickness of elastomer h = 3x12+2x6 = 48 mm
Adopt side cover c = 6 mm
Check for Geometry
A. l0/b0 = 800/400 =2 2
B. h = 48 < b0/5 = 80 mm
And > b0/10 = 40 mm
305744
C. Shape factor S = 2(388+788)12 = 10.83 (between 6 and 12)
Nmax 530.1331000
D. Bearing Stress in concrete (m) = Loaded Area = 305744 = 1.734 MPa
A1/A2 is limited to 2.
A1
Allowable BS = 0.25 A2 = 0.25 30 2 = 10.61 N/mm2

113
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

So,
Bearing stress in concrete Allowable Bearing stress OK

Structural Design
E. Check for Translation
Shear strain per bearing due to shrinkage, creep and temperature= /h
5104 36103
= = 0.188
248
144.41103
Shear strain due to longitudinal forces, md = = 3057441 =0.472
Design strain in bearing (d) < 0.7
i.e. d = bd = /h + md = 0.188+0.472 = 0.66 < 0.7 OK

F. Check for Rotation


Design rotation in bearing (d) nbi, max

G. Check for Friction


Design strain in bearing (d) 0.2 + 0.1m
i.e. 0.2 + 0.1m = 0.2 + 0.1x1.734 = 0.3734 > 0.66 OK
And
Normal stress in bearing (m) > 2 MPa and 10 MPa OK

H. Check for Shear Stress


Total shear stress 5 MPa
i.e. c + h + = 1.59 MPa < 5 MPa OK
where
Shear stress due to compression = 1.5xm/S = 1.5x1.734/10.83 = 0.240 MPa
Shear stress due to horizontal deformation = 0.66x1 = 0.66 MPa
Shear stress due to rotation = 0.5x(b/hi)2 x bi,max = 0.5 (388/12)2 0.00132
= 0.69 MPa

114
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Summary: Bearing Design


Provide standard 400x800 mm elastomeric pad bearing.
Overall Thickness = 64 mm
Thickness of individual elastomer layer = 12 mm
No of internal elastomer layers = 3
Thickness of each laminate = 4 mm
No of laminates = 4
Thickness of outer layer = 6 mm

115
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

C. Design of RCC Abutment


1. Planning and Preliminary Design

A. Selection of Type of Abutment


Abutment may be of masonry or reinforced cement concrete. Masonry is technically /
economically feasible up to 5m height of abutment. In the particular case, abutment is
greater than 5 m height. So reinforced concrete wall type abutment has been selected.

B. Material Selection
Following materials are to be taken for the construction of the abutment:
M20 grade of concrete for abutment stem and dirt wall
M25 grade of concrete for abutment cap
Fe 415 HYSD bars for all RC work

C. Geometry of Abutment
Seating width = 0.515 m
Minimum seating width = 305 + 2.5 span + 10 Ht. of abutment [Ref. Cl. 219.9, IRC 6]
= 305 + 2.5 12 + 10 12.5 = 460 mm
Seating width Bearing width + 150 mm + Projection of cap + Width of Expansion Joint
0.25 + 0.15 + 0.075 + 0.04 = 0.515 m
Width of Expansion joint 12 103 0.000011/ C 50 C = 3.3 mm
5 10-4 12 103 = 3 mm and
20 mm
Adopt 40mm

Height of dirt wall = Depth of girder + height of bearing thickness of approach slab
= 1 + 0.052 0.3
= 0.752 m

Thickness of dirt wall = 0.25 m

Where, Thickness of dirt wall, tdw 200 mm and Height of Dirt wall/7= 0.752/7 = 0.107 m

Width of stem of abutment = 1.25 m


Width of stem 12.5/10=1.25
Width of stem thickness of dirt wall + seating width projection = 0.515 + 0.25 -0.075 =
0.69 m

Thickness of footing = 2 m

116
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Thickness of footing H/8 = 12.5/8 = 1.56 m

Width of footing (B) = 9.5 m

B 0.75H = 0.7512.5 = 9.37 m


B Area of footing / length

1.5 Length of footing
434.223
= 1.5 3005.2
= 1.25 m

Thickness of abutment cap = 300 mm


Minimum thickness of cap = 200mm

Length of abutment = 5.2 m


Length of abutment C/C distance between external girders + Width of bearing + 2
Clearance
= 4 m + 0.4 m + 2 0.4 m = 5.2 m
Size of Approach slab = 3.5 m 6 m 0.3 m

117
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Cross section of Abutment

II. Analysis and Design of Abutment Cap


Check thickness of abutment cap for punching shear

434.22 1.5 1000 434.22 1.5 1000
Where, = (2 400+2 d+2 250+2 d) d = (2 400+2 252+2 250+2 252) 252 = 1.12 N/mm2

=1.25 N/mm2, =1+=1, =0.25 = 0.2525 = 1.25


d= 300 40 16/2 = 252 mm
Take area of steel AS = 1 % of area of cap and distribute these bars equally at top and
bottom of cap. [Refer IRC 78 CL. 716.2]

As in longitudinal direction of abutment


= 1% of 300 1325 = 3975 mm2,
As on one side = 3975/2 = 1987.5 mm2
Take 12 mm bar, n = 17.57, Adopt n =18

As in transverse direction of abutment
= 1% of 300 5200 = 15600 mm2
As on one side = 15600/2 = 7800 mm2
Take 12 mm bar n = 68.96, Adopt n = 69
In transverse direction bars are provided in the forms of stirrups.
In addition, two layers of mesh reinforcement, each consisting 6 mm @ 75 mm c/c in both
directions one at 20 mm and other at 100 mm from the top of cap are provided directly
under the bearing.

118
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

III. Analysis and Design of Abutment Stem

Load Calculation
1. DL from superstructure [Refer bearing design]
Total DL from superstructure = 1038.08 KN
1038.08
Load on an abutment per unit length (DLSS) = = 99.81 KN/m
5.22

2. Weight of approach slab [Take half of total weight of approach slab]

= 0.3 3.5 6 25 1/2 = 78.75 KN


Load on an abutment per unit length (DL Ap.S) = 78.75/5.2 = 15.14 KN/m

3. LL from superstructure
373.17 2+371.49
Maximum LL = (LLexterior girder 2 + LLinterior girder)/1.5 = = 745.22 KN
1.5
Load on an abutment per unit length (LL) = 745.22/5.2 = 143.375 KN/m

4. Load from Braking Effort [Refer bearing design]


Horizontal braking load per unit length (FbrH) = 172.8 / (5.2 2) = 16.635 KN/m
Vertical reaction due to braking load per unit length (FbrV) = 10.94x3/5.2 = 6.314 KN/m

5. Wind Load [Refer bearing design]


Transverse Wind load per unit length, FWT = 71.90 / (5.2 2) = 6.913 KN/m
Longitudinal Wind load per unit length, FWL = 17.975/ (5.2 2) = 1.728 KN/m
Vertical Wind load per unit length, FWV = 124.44 / (5.2 2) = 11.965 KN/m

6. Seismic Load due to the DL and LL from superstructure

119
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge


Seismic load (FSh) = 2 W [Refer Cl. 219, IRC 6]

FShL = 233.06/ 1.5 = 155.373 KN in longitudinal direction of bridge
FShT = 271.94/1.5 = 181.293 KN in transverse direction of bridge
Take, Seismic Zone - V, Soil Strata - Medium, Damping - 5 %, Bridge Class - Normal
Z I Sa
Where, Ah = h = R = 0.15; Z = 0.36, I = 1, R = 3, = 2.5
2 g
W = 1035.83 KN in longitudinal direction
W = 1208.63 KN in transverse direction
Seismic load in transverse direction per unit length, FShT = 181.293/ (5.2 2) = 17.432 KN/m
Seismic load in longitudinal direction per unit length, FShL = 155.373/(5.2 2) = 14.94 KN/m
Vertical reaction due to seismic load on support of bridge (FSVT) = 172.97/ (5.2 2) =16.632
KN/m
Vertical reaction on abutment per unit length when seismic load acts in longitudinal
direction, (FSVL) = 155.373 0.9 / (12 5.2) = 2.241 KN /m

7. Load due to temperature variation, creep & shrinkage effect



Load on three bearings due to CST = o G A
3.0625
= 1 250 400
52
= 17.67 KN
Load per unit length FCST = 17.67/5.2 = 3.398 KN/m

8. Self-Weight of abutment
Self-weight = (0.752 0.25 + 0.3 1.325 + 1.25 9.148) 5.2 25
= 1562.67 KN
Load per unit length, DLAb = 1562.67/5.2 = 300.51 KN/m

9. Seismic load due to the self-weight of abutment


Z I Sa
FS Abt hT = FS Abt hL = 2 R W
g
0.36 1
= 3 2.5 1562.67
2
= 234.4 KN
Load per unit length, FS Abt hL = 234.4/5.2 = 45.08 KN/m

10. Load due to static earth pressure


Load due to static earth pressure is found by Coulombs theory.
PA= 0.5 gsoil H2 KA
= 0.5 20 (10.5)2 0.226 (KA = 0.226)
= 249.17 KN/m

120
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

cos2 ( ) 1
where, KA = cos2 cos2( + ) 1 2
= 0.226
sin (+)sin( i ) 2
(1+( ) )
cos(i)cos( +)

=37, i = 0, = 2/3 37 24.67, = 0, soil = 20 KN/m3, H= 12.5 m

Horizontal component of load per unit length PEPH(s) = PA cos (24.67) = 226.42 KN/m
Vertical component of load per unit length PEPV(s) = PA sin (24.67) = 104 KN/m

11. Load due to dynamic earth pressure


Load due to active earth pressure has been found by Mononobe Okabe Theory
PA= 0.5 gsoil H2 KAdyn = 403.52 KN
cos2 ( ) 1
where , KAdyn = (1 aV) cos cos2 cos2( + + ) 1 2
= 0.366
sin (+)sin( i) 2
(1+( ) )
cos(i)cos( ++)

=37, i = 0, = 2/3 37 24.67, = 0


ah = 0.15, aV = 0.15 2/3 = 0.10
h
= tan-1( 1v ) = 7.77 & 9.47

Horizontal component of load per unit length PEPH(D) = PA cos (24.67) =366.68 KN/m
Vertical component of load per unit length PEPV(D) = PA sin (24.67) = 168.42 KN/m

12. Surcharge load


1.2 m earth fill from road surface is taken as surcharge load.
Psur = KA soil h W = 0.226 20 1.2 10.5 = 56.95 KN/m
Horizontal component of load per unit length PsurH = Psur cos (24.67) = 51.75 KN/m
Vertical component of load per unit length PsurV = Psur sin (24.67) = 23.77 KN/m

13. Backfill weight on heel slab of footing


WBF = (12.5 2 0.3) 6.25 5.2 20
= 6630 KN
Load per unit length WBF = 6630/5.2 = 1275 KN/m
14. Weight of footing
WFooting = 2 9.5 5.2 25 = 2470 KN
Load per unit length WFooting = 2470/5.2 = 475 KN/m

Analysis of Abutment Stem


Responses of abutment at bottom and at 4 m from the bottom for basic combination and
seismic combination of loads have been calculated. Loads taken are vertical and longitudinal
loads. Although seismic and wind load in transverse direction are greater than seismic and

121
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

wind load in longitudinal direction, reduction in earth pressure and other loads in transverse
directions make the longitudinal directions load critical.
[Annex B, Table 3.2, IRC 6-2010]

Responses of abutment at its bottom in basic combination of loads


Distanc Eccentricity
Load e from Pu Muy
f
(KN) bottom x (KN) Mux (KN Hx Hy
(m) (m) y (m) (KN-m) -m) (KN) (KN)
DLss 87.38 1.35 -0.210 117.963 -24.77
DLwc 12.43 1.75 -0.210 21.7525 -4.57
DLAp.s 15.14 1.35 -0.5 17.8875 -5.93
LL 143.375 1.5 -0.210 215.0625 -45.16
12.5-1-
2=
FbrH 16.635 1.15 9.5 0 181.74 19.13
FbrV 6.314 1.15 -0.210 7.2611 -1.525
FwL 1.728 1.5 9.5 0 24.624 2.592
Fcst 3.398 1.5 9.5 0 48.42 5.097
DLAb 300.51 1.35 0 405.69 0
PEPV(S) 104 1.5 -0.625 156 -97.5
0.42*1
0.5=4.2
PEPH(S) 226.42 1.5 8.4 0 0 1200.12 339.63
PsurV 23.77 1.2 -0.625 30.156 -16.5858
12.5/2 -
PsurH 51.75 1.2 2=4.25 0 0 265.8906 62..1
Total 971.77 1524.75 428.55

Responses of abutment at its bottom in Seismic Combination of loads


Distance Eccentricity Muy
Load Pu
f from x Mux (KN- Hx Hy
(KN) (KN)
bottom(m) (m) y (m) (KN-m) m) (KN) (KN)
DLss 87.38 1.35 -0.210 117.963 -24.77 0
DLwc 12.43 1.75 -0.210 21.75 -4.568 0
DLAp.s 15.14 1.35 -0.5 20.439 -10.22 0
LL 143.375 0.2 -0.210 28.675 -6.022 0
FbrH 16.635 0.2 9.5 0 0 31.61 3.327
FbrV 6.314 0.2 -0.210 1.263 -0.265 0
FshL 14.94 1.5 9.5 0 0 212.895 22.41

122
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Distance Eccentricity Muy


Load Pu
f from x Mux (KN- Hx Hy
(KN) (KN)
bottom(m) (m) y (m) (KN-m) m) (KN) (KN)
vL
Fs 2.241 1.5 -0.210 3.362 -0.706 0
Fcst 3.398 1 9.5 0 0 32.281 3.398
DLAb 300.51 1.35 0 405.69 0 0
FS
hL
Abt 45.08 1.5 4.25 0 0 287.385 67.62
PEPV(D) 168.42 1 -0.625 168.42 -105.263 0
PEPH(D) 366.68 1 5.04 0 0 1848.067 366.68
PsurV 23.77 0.2 -0.625 4.754 -2.971 0
PsurH 51.75 0.2 4.25 0 0 43.988 10.35
Total 772.316 2301.441 473.785

Responses of abutment at 4 m from its bottom in basic combination of loads


Distance Eccentricity
Load Pu
f from Mux Muy Hx Hy
(KN) (KN)
bottom(m) x (m) y (m) (KN-m) (KN-m) (KN) (KN)
DLss 87.38 1.35 -0.210 117.963 -24.77
DLwc 12.43 1.75 -0.210 21.7525 -4.57
DLAp.s 13.25 1.35 -0.5 17.8875 -5.93
LL 143.375 1.5 -0.210 215.0625 -45.16
12.5-1-2-
4=
FbrH 16.615 1.15 5.5 0 0 105.1 19.10725
FbrV 6.314 1.15 -0.210 7.2611 -1.525
FwL 1.728 1.5 5.5 0 0 14.26 2.592
Fcst 3.398 1.5 5.5 0 0 28 5.097
DLAb 175.51 1.35 0 349.245 0
PEPV(S) 39.85 1.5 -0.625 56 -37.36

0.42*(10.5-
4)=2.73
PEPH(S) 86.77 1.5 0 0 355.32 130.15
PsurV 14.7 1.2 -0.625 17.65 -11.03

123
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Distance Eccentricity
Load Pu
f from Mux Muy Hx Hy
(KN) (KN)
bottom(m) x (m) y (m) (KN-m) (KN-m) (KN) (KN)

PsurH 32.04 1.2 3.25 0 0 125 38.45


Total 802.82 497.335 195.4

Responses of abutment at 4 m from its bottom in Seismic Combination of loads


Distance Eccentricity Muy
Load Pu
f from Mux (KN- Hx Hy
(KN) (KN)
bottom(m) x (m) y (m) (KN-m) m) (KN) (KN)
DLss 87.38 1.35 -0.210 117.963 -24.77 0
DLwc 12.43 1.75 -0.210 21.75 -4.568 0
DLAp.s 15.14 1.35 -0.5 20.439 -10.22 0
LL 143.375 0.2 -0.210 28.675 -6.022 0
FbrH 16.635 0.2 5.5 0 0 31.61 3.327
FbrV 6.314 0.2 -0.210 1.263 -0.265 0
FshL 14.94 1.5 5.5 0 0 212.895 22.41
vL
Fs 2.241 1.5 -0.210 3.362 -0.706 0
Fcst 3.398 1 5.5 0 0 32.281 3.398
DLAb 175.512 1.35 0 236.94 0 0

(12.5-0.3-
0.752-2-
FS AbthL 26.33 1.5 4)/2= 2.724 0 0 107.58 39.495
PEPV(D) 64.54 1 -0.625 64.54 -40.338 0

(12.5-2-
H(D)
PEP 140.52 1 4)*0.6= 3.9 0 0 548.028 140.52
PsurV 32.04 0.2 -0.625 6.408 -4.005 0
(12.5-2-
PsurH 14.72 0.2 4)/2 = 3.25 0 0 9.568 2.944
Total 501.34 851.09 212.094 0

Design of Abutment Stem


Results of analysis shows that maximum design axial load (Pu = 971.77 KN) is less than 0.1 f ck
Ac (0.1 20 1000 1100 10-3 = 2200 KN ).

124
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For the case, where Pu 0.1 fck Ac, compression member is treated as a flexure
member. So, abutment stem has been designed as a cantilever slab.
Since design bending moment is higher in seismic combination of loads, design of abutment
stem has been carried out for seismic combination of loads only.

Design of bottom section


Check depth of slab
d = D CC /2 = 1250 50 25/2 = 1187.5 mm
2301.441106
= = = 912.2 mm
2.7661000

where Q = 0.36 fck 0.48 (1 0.416 0.48) = 2.766


dprov > dbal OK
Find reinforcing bars
Since dprov > dbal, section is designed as Singly Reinforced Under-Reinforced Section
(SRURS). So, section design has been carried out by using SP 16.
a. Main vertical bars (vertical bars in the side of backfill)
2301.441106
Find = 1000(1187.5)2 = 1.63, pt = 0.503%
2
sreq. = 0.00503 10001187.5 = 5973.125mm2
Provide 32 mm bar @ 130 mm c/c, sprov. = 6434 mm2, ptprov. = 0.54 %
By increasing dia., effective depth d decreases.
Initially if we use 32mm dia., d=1250-50-32/2 = 1184mm

= 1.64
2
As per SP 16, (pt)req. = 0.508% < ptprovided(=0.54%)

b. Outer vertical reinforcement (vertical bars in the side of river)


[Refer detailing criteria of IRC 112-2011 and IS 4]
Take 0.12 % of gross sectional area of abutment as outer vertical reinforcement
As = 0.12/100 10001184 = 1421 mm2
Provide 16 mm bar @ 140 mm c/c, stprov = 1436.15 mm2, ptprov.= 0.13 %

c. Horizontal Reinforcement
Take, As = 0.1% of stem area of abutment or 25% of main vertical bars
= 0.001 1250 9136 = 11420 mm2
11420
As on each face of abutment = = 5710 mm2
2
Provide 29 - 16 mm @300mm c/c on each face of abutment
Check bottom section for shear
Check uv K uc
Where,

125
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

473.785103
uv = y/ = = 0.4 N/mm2
10001184
uc = 0.493 N/mm2 for M20 and pt = 0.54 %
uc.max = 2.8 N/mm2
K =1 [Refer table 19 & 20, IS 456]
uv< K uc, shear reinforcement is not required.

Design of abutment section at 4 m from its bottom


Check depth of slab
d = D CC /2 = 1250 50 25/2 = 1187.5 mm
Mu 851.09106
dbal = = = 554 mm
Qb 2.7661000

Where, Q = 0.36 fck 0.48 (1 0.416 0.48) = 2.76


dprov > dbal OK
Find Reinforcing bars
Since dprov > dbal, section is designed as Singly Reinforced Under-Reinforced Section (SRURS).
Section design has been carried out by using SP 16.
a. Main vertical bars (vertical bars in the side of backfill)
851.09106
Find 2 =1000(1187.5)2 = 0.6, pt = 0.172 % > pt min = 0.12%
Asreq = 0.172/10010001187.5 = 2043mm2
Provide 25 mm bar @ 240 mm c/c, Asprov = 2045 mm2, ptprov = 0.172%
Curtail two-third of main vertical bars (bars designed for bottom section of abutment) at 5.2
m (4m + d) from the bottom of abutment

IV. Design of Dirt Wall


Design the dirt wall as a cantilever slab of span 0.764 m. Consider basic combination and
seismic combination of loads to determine the responses of dirt wall.
Here seismic combination is considered for design. Dirt wall have been designed as a
cantilever slab of unit width. Detailing of wall is carried out prescribed by IRC 112 - 2011 Cl.
16.3.
Surcharge load = 1.2 20 KADYN 0.764 1 = 6.71 KN/m
Load due to earth pressure = KADYN 20 0.7642 1=2.14 KN/m
Seismic load due to weight of dirt wall (Ah W) = 0.15 0.764 0.25 25 1 = 0.72 KN/m
Mu at bottom = 6.71 .764/2 + 2.14 0.6 .764 + 0.72 0.764/2 = 3.82 KN-m
Use M20 grade concrete,
3.82106
=10002042 = 0.09, pt = 0.085 % < pt min = 0.12 %
2
Take pt = 0.12% Ast = 0.12/1001000250 = 300 mm2
Provide 12 mm bar @ 200 mm c/c at both sides of dirt wall
Provide 10 mm bar @ 250 mm c/c as horizontal reinforcement
Check bottom of slab for shear

126
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Total shear at bottom of dirt wall = 6.71 + 2.14 + 0.72 = 9.57 KN


9.57103
Nominal Shear Stress = = 1000204 = 0.05N/mm2
< K uc, no shear reinforcement requires.

127
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Stability Check
Stability of abutment is checked for overturning and sliding. In the following table
overturning moment and restoring moment about the toe of footing of abutment and
shear at the base of footing have been calculated.
Stability check for basic combination of loads
f
Overturning Restoring
Load Over Lever Arm Moment Moment Shear Vertical
KN/m Turning Restoring m kNm kNm Force kN Load kN
DLss 87.38 0.95 2.835 0 235.34 0 83.01
DLwc 12.43 1 2.835 0 35.24 0 12.43
DLAp.s 13.25 0.95 3.125 0 39.34 0 12.59
LL 143.375 0 2.835 0 0 0 0

12.5-1=11.5
FbrH 16.615 1.15 219.73 0 19.10725 0
FbrV 6.314 0 2.835 0 0 0 0
FwL 1.728 1.5 11.5 29.8 0 2.592 0
Fcst 3.398 1.5 11.5 58.62 0 5.097 0
DLAb 258.7 0.95 2.625 0 645.13 0 245.77
V(S)
PEP 116.22 0 3.25 0 0 0 0
0.42*12.5
H(S)
PEP 253.03 1.5 =5.25 1992.6 0 379.545 0
PsurV 25.13 0 3.25 0 0 0 0

PsurH 54.71 1.2 12.5/2=6.25 410.325 0 65.652 0


WBF 1275 0.95 6.375 0 7721.72 0 1211.25
Wfooting 475 0.95 4.75 0 2143.44 0 451.25
Total 2711.075 10820.7 471.99 2016.3

Total Overturning moment = 2711.075 KN-m


Total Restoring moment= 10820.7 KN-m
Total Shear at base of footing= 471.99 KN
Total Vertical Load at base of footing = 2016.3 KN
Check
10820.7 KNm
a. Total Overturning moment = = 4 > 2 (Safe in overturning)
2711.075 KNm

2016.3tan 37
b. Total Shear at base
= = = 3.22> 1.5 (Safe in sliding)
471.99

Stability check for seismic combination of loads

128
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

f
Overturning Restoring Shear
Load Over Lever Arm Moment Moment Force Vertical
KN/m turning restoring (m) kNm kNm kN Load kN
DLss 87.38 0.95 2.835 0 235.34 0 83.01
DLwc 12.43 1 2.835 0 35.24 0 12.43
DLAp.s 15.14 0.95 3.125 0 44.95 0 14.38
LL 143.375 0 2.835 0 0 0 0
12.5-1=
FbrH 16.635 0.2 11.5 38.26 0 3.327 0
FbrV 6.314 0 2.835 0 0 0 0
FshL 14.94 1.5 11.5 257.72 0 22.41 0
FsvL 2.241 0 2.835 0 0 0 0
Fcst 3.398 0.95 11.5 37.12 0 3.23 0
DLAb 300.51 0.95 2.625 0 749.4 0 285.48
36.05

(9.148/2+2)
FS AbthL 45.08 1.5 = 6.574 444.53 0 67.62 0
PEPV(D) 168.42 0 3.25 0 0 0 0
PEPH(D) 366.68 1 8.3 3043.44 0 366.68 0
PsurV 23.77 3.25 0 0 0 0
PsurH 51.75 6.25 0 0 0 0
WBF 1275 0.95 6.375 0 7721.72 0 1211.25
Wfooting 475 0.95 4.75 0 2143.44 0 451.25
Total 3821.07 10930.09 499.32 2057.8

Total Overturning moment = 3821.07KN-m


Total Restoring moment= 10930.08 KN-m
Total Shear at base of footing= 499.32 KN
Total Vertical Load at base of footing = 2057.8 KN
Check
10930.08 KNm
a. Total Overturning moment = = 2.86 > 2 (Safe in overturning)
3821.07KNm

2057.8tan 37
b. Total Shear at base
= = = 4.12> 1.5 (Safe in sliding)
499.32

Thus, Abutment is safe in stability for basic and seismic combination of loads.

129
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

V. Analysis and Design of Spread Footing

Responses of footing at its base in basic combination of loads


Distance Eccentricity Muy'
Load Pu
f from x' y' Mux' (KN- Hx' Hy'
(KN) (KN)
bottom(m) (m) (m) (KN-m) m) (KN) (KN)
DLss 87.38 1.35 1.92 117.963 226.49
DLwc 12.43 1.75 1.92 21.7525 41.76
DLAp.s 15.14 1.35 1.625 17.8875 33.21
LL 143.375 1.5 1.92 215.0625 412.92
12.5-2=
FbrH 16.635 1.15 10.5 0 0 200.87 19.11
FbrV 6.314 1.15 1.92 7.2611 13.94
FwL 1.728 1.5 10.5 0 0 27.22 2.592
Fcst 3.398 1.5 10.5 0 0 53.52 5.097
DLAb 300.51 1.35 2.125 405.69 862.1
PEPV(S) 104 1.5 1.5 156 234
0.42*11.5=
H(S)
PEP 226.42 1.5 4.83 0 0 1640.42 339.63
PsurV 23.77 1.2 1.5 30.156 42.786
12.5/2-
PsurH 51.75 1.2 1=5.25 0 0 326.025 62.1
-
WBF 1153.2 1.35 1.625 1556.82 -2529.83
Wfooting 318.75 1.35 0 430.3125
Total 2958.9 1585.43 428.529

Responses of footing at its base in seismic combination of loads


Distanc Eccentricity
Load e from Pu Muy
f bottom
(KN) x (KN) Mux (KN- Hx Hy
(m) (m) y (m) (KN-m) m) (KN) (KN)
DLss 87.38 1 1.92 87.38 167.77
DLwc 12.43 1 1.92 12.43 23.87
DLAp.s 15.14 1 1.625 15.14 24.602
LL 143.375 0.2 1.92 28.675 55.056
FbrH 16.635 0.2 10.5 34.934 3.327
FbrV 6.314 0.2 1.92 1.263 2.424
FshL 14.94 1.5 10.5 235.31 22.41
FsvL 2.241 1.5 1.92 3.362 6.654

130
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Distanc Eccentricity
Load e from Pu Muy
f bottom
(KN) x (KN) Mux (KN- Hx Hy
(m) (m) y (m) (KN-m) m) (KN) (KN)
Fcst 3.398 1 10.5 35.68 3.398
DLAb 300.51 1 2.125 300.51 638.584
FS AbthL 45.08 1.5 5.574 376.913 67.62
PEPV(D) 168.42 1 1.5 168.42 252.63
H(D)
PEP 366.68 1 7.3 2676.764 366.68
PsurV 23.77 0.2 1.5 4.754 7.131
PsurH 51.75 0.2 5.25 54.337 10.35
- -
WBF 1275 1 1.625 1275 2071.875
Wfooting 475 1 0 475 0
Total 2371.754 2520.784 473.785
Upward pressure of soil
Basic Combination
Pu Mux 2958.9 1585.434.75
pu = *y =
A Ixx 9.5 71.45
=416.8 KN/m2 or 206 KN/m2 < ultimate bearing capacity of soil
(=1.5x300 KN/m2)
1
Ixx = 12 * 9.53 = 71.45 m4
Seismic Combination
Pu Mux 2371.754 2520.7844.75
pu = *y =
A Ixx 9.5 71.45
= 417.24 KN/m2 or 82.08 KN/m2 < ultimate bearing capacity of soil
(=1.5x300 KN/m2)
Critical section for BM

Critical section for SF


d=2m

II II I
V M M

2
416.8 KN/m
2
206 KN/m

465.65
2
KN/m
Soil Upward Pressure
131
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Analysis of Footing
372.42+416.8 2
BMmax at IM = 2 2 = 789.22 KNm
2
206+344.7 6.25
BMmax at IIM = 6.25 = 5377.9 KNm
2 2
206+344.7
SMmax at IIv = 4.25 = 1170.24 KN
2

Design of Footing
Check depth of footing
Mu 5377.910^6
dbal = Qb = = 1396 mm
2.761000

Since d > dbal , design as SRURS.


Adopt D = 2000mm
Find Reinforcing Bar
o Find bottom reinforcing bars @ critical section IIM
Provide reinforcement in 2 layers, d = 2000-60-20 = 1920 mm
5377.9 10^6
=
^2 1000(20006020)^2
=1.46 pt = 0.444 % (from SP 16)
Astreqd = 0.444 % of (1000* 1920) = 8525 mm2
Provide 2 layers of 20 mm dia @ 70 mm c/c, Astprovided = 8976 mm2
o Bottom Reinforcing bars @ IM
789.22 10^6
= = 0.211, Thus pt = 0.085%
^2 1000(20006010)^2

Astreqd = 0.085 % of (1000* 1930) =1621.2 mm2


Astmin = 0.12 % of bD = 2400 mm2, adopt Ast = 2400 mm2
Provide a layer of 20 mm dia bars @ 130 mm c/c , As provided = 2416 mm2

o Top distribution Bars


Take Astmin = 0.12 % of bD = 2400 mm2, adopt Ast = 2400 mm2
Provide a layer of 20 mm dia bars @ 130 mm c/c, Astprovided = 2416 mm2

Check for One Way Shear


Vu 1170.24103
Nominal Shear = = = 0.6 MPa
bd 1000(20006010)
c = 0.48 MPa for M20 and pt = 0.45 % and c,max = 2.8 MPa
Since v > c, shear reinforcement is needed.
Design of hat reinforcement in slab
0.87 0.87415158^2/41930
Sv = (uvuc)bwd= = 440 > 0.75d and >300 mm
(1.0740.46)10001930
Adopt Sv = 300mm.
Provide 8 mm 15-legged vertical stirrups @300 mm c/c.

Check Development Length beyond the face of abutment


[IRC 21 cl. 305.6.3]
Design development length ld = 12l0
Where 1 = 1 for straight ends

132
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge


2 =
= 0.99

l0 = 46 = 920 mm
Thus, ld = 910.8 mm
Shorter length of footing provided beyond the face of abutment = 2000 75 = 1925 mm
Since provided length > ld, additional anchorage for bars are not required.

133
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

D. Design of RCC Solid Pier


1) Planning and preliminary design
i. Selection of type of pier
For the bridge, we have selected solid pier. Hammer head pier, though have been popularly
used in bridges in Nepal, is technically unsuitable for the zone of high seismicity due to its
higher center of gravity. Hence, that type of pier has been avoided.

ii. Material Selection


Following materials are used in the pier:
o M20 grade of concrete for pier stem
o M30 grade of concrete for pier cap
o Fe 415 HYSD bars for all RC work

iii. Geometry of Pier


Size of Pier cap =
Length of Cap (L)
L = c/c distance of external main girders + bearing widths + 2 0.05
= 7.5 + 0.8 + 2 0.4 + 2 0.05
= 9.20 m
Width of Cap (B)
B = 4 150 + bear. widths
= 4 150 + 250 + 400= 1250 mm

Thickness of Cap (T)


T = 0.5 m thick

Check the thickness of cap for punching Shear (Below bearing of truss)

Vu 1190.09 1.5 1000
Where, = b0 d = 2 (400 + 800+450 + 450 ) 450 = 0.944 N/mm2
= Maximum Vertical load from bearings 1.5 [From bearing design]
d = 500 40 20/2 = 450 mm, effective depth of cap below bearing
= 0.25fck = 0.25 30 = 1.369 N/mm2
= 1
thickness of cap is safe for punching shear.

Check the thickness of cap for punching Shear (Below bearing of T-girder)

Vu 434.22 1.5 1000
Where, = b0 d = 2 (400 + 250+450 + 450 ) 450 = 0.467 N/mm2

134
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= Maximum Vertical load from bearings 1.5 [From bearing design]


d = 500 40 20/2 = 450 mm, effective depth of cap below bearing
= 0.25fck = 0.25 30 = 1.369 N/mm2
= 1
thickness of cap is safe for punching shear.

Stem

Length of stem (L) = Length of pier cap 2 x 0.05 m = 9.10 m


Width of stem at top = 1150 mm
Width of stem at bottom = 1700mm

II. Load Calculation


1. DL from superstructure (without WC)

From RC-Tee Bridge, Total DL = (1038.08 129.36)


= 908.72 KN
From Truss Bridge, Total DL = (2776.2 383.33)
= 2392.87 KN
DL on pier from both span (DLSS) = (908.72 + 2392.87)/2 = 1650.79 KN

2. Weight of Wearing Coat


DL due to WC = (129.36 + 383.33)/2 = 256.34 KN

3. Live load from superstructure (LL)


a. LL due to class AA tracked load = (700/3.6) 1.25 Area in the ILD
= 700/3.6 1.25 3.42
= 831.25 KN
b. LL due to class AA wheeled load = (200 + 200 0.967 + 200 + 200 0.9)
1.25
= 966.75 KN
c. LL due to class A Loading = 2 (27 (0.542 + .633) + 114 (0.9 + 1) + 68
(0.88 + 0.797 + 0.714)) 1.25
= 1027.28 KN

Take LL = 1027.28 KN

4) Load from Braking Load

135
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

From Conjugate Beam Method


Stiffness of each Pier = 119.93 m-1
Stiffness of each Abutment = 74.15 m-1
d. Total Class A loads possible on 60 m span = 4 x 554
= 2216 KN

e. Total class AA tracked load possible = 700 KN


f. Total class AA tracked load possible = 400 KN
Taking Class A loads on overall bridge, Braking load = 0.2 2216
= 443.2 KN
119.93
Horizontal braking load acting on pier ( FbrH) = 2 119.93+2 74.15 443.2
= 136.936 KN
From SAP2000 analysis,

Vertical braking load acting on pier ( FbrV) = 18.62 KN

5. Wind load (Superstructure) [From Bearing Design]


From RC-Tee Bridge,
FWT = 71.90 KN
FWL = 17.975 KN
FWV = 124.44 KN

From Truss Bridge,


FWT = 365.04 KN
FWL = 91.26 KN
FWV = 396.18 KN

For Pier,

136
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

FWT = (71.90 + 365.04) = 218.47 KN


FWL = (17.975 + 91.26) = 54.612 KN
FWV = (124.44 + 396.18) = 260.31 KN

6. Wind load (Sub Structure - dry season)


Pd = 940.60 N/mm2
9100
For t/b = 1150+1700 = 6.38 > 4 &
2
11500
h/b = 1150+1700 = 7.07
2

CD = 0.9
A = (1.15 + 1.7) 11 = 15.67 m2

Wind load in transverse direction of bridge FWT (sub) = Pd A G CD


= 940.60 15.67 2 0.9 = 26.53 KN
Wind load in longitudinal direction FWL(sub)= 0.25 FWT (sub) = 6.63 KN

7. Seismic load (Super Structure)


Sa
Seismic load = 2 W
g
Where,
Z = 0.36, I = 1, R = 4, / = 2.5
Sa
= 0.1125
2 g
WLTruss = 2776.2 KN
WLRC-Tee = 1035.83 KN

WLOverall = WLTruss + 2 WLRC-Tee


= 2776.2 + 2 1035.83
= 4847.86 KN

Maximum LL on Overall Bridge = 2216 KN (from calculation of Braking Load)

WTOverall = 4847.86 + 0.2 2216 = 5291.06 KN

Longitudinal Seismic weight concentrating on a pier,


119.93
WLPier = 2 119.93+2 74.15 4847.86
= 1497.69 KN

137
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Sa
Seismic load in longitudinal direction of bridge (FSL) = 2 WLPier
g
= 0.1125 1497.69
= 168.49 KN
Sa
Seismic load in transverse direction of bridge (FST) = 2 WTPier
g
= 0.1125 (WTTruss + WTRC-Tee)/2
= 0.1125 (2892.1 + 1208.63)/2
= 230.66 KN
V.Reaction due to seismic load in longitudinal direction (FSvL) = FSvL Truss+ FSvL RC-Tee
= 4.52 2 + 8.74 3
= 35.26 KN
vT
V.Reaction due to seismic load in transverse direction (FS ) = FSvT Truss+ FSvT RC-Tee
= 20.03 + 86.485
=107.32 KN

8. Seismic load (Sub Structure)


Seismic loads due to self-weight of pier in longitudinal and transverse direction of bridge are
equal

FST(Sub) = FSL(Sub) = 2 Wpier = 0.1125 3709.81 = 417.35 KN

Where,
Sa
Z = 0.36, I = 1, R = 4, = 2.5

Wpier =1/2 (1.15 + 1.7) 11 9.1 25+.5 x 1.25 x 9.2 x 25 = 3709.81 KN

9. Load due to temperature variation, creep and shrinkage effect


FCST = FCSTTruss bearing 2 - FCSTRC-Tee bearing 3
= 26.23 2- 5.44 3
= 36.14 KN

10. Self-Weight of Pier


Wpier =1/2 (1.15 + 1.7) 11 9.1 25+.5 x 1.25 x 9.2 x 25 = 3709.81 KN

11. Load due to Water Current


FWCT = 52 K (V cos20)2 A
= 52 1.5 (1.5 0.203 2 cos20)2 14.5
= 1.82KN

FWCL = 52 K (V sin20)2 A
= 52 1.5 (1.5 0.203 2 sin20)2 91
138
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 1.51 KN

12. Load due to hydrodynamic pressure


FhydL = C ah W = 0.74 0.1125 6503.88 = 541.45 KN

Where, ah= = 0.1125
2
C = 0.74 for / = 7.47, [Refer Table 9.10, Swami Saran, Design of Sub Structure]
W = (9.1/2)2 10 10 = 6503.88 KN
FhydT = C ah W = 0.74 0.1125 165.13 =13.75 KN
W = (1.45/2)2 10 10 = 165.13 KN

13. Load due to buoyancy


Fbuoy = Submerged vol. of pier gw = (1.2 + 1.7) 10 9.1 10 = 1319.5 KN

III. Analysis and Design of Pier Cap

Maximum Shear Force (S.F) at face of pier stem (Basic combination)


SF at face due to DL from superstructure, LL from superstructure, VL and Self wt. of Cap
= (1650.79 1.35 + 256.34 1.75) + 1027.28 1.5 + (18.62 1.15 + 260.31 1.5) + (9.2
1.25 0.5 25 1.35)
= 4824.02 KN

Design
Check thickness of pier cap for punching shear under a (truss) bearing

4824.02 1000 4824.02 1000
Where, = (2 400+2 d+2 800+2 d) d = (2 400+2 452+2 800+2 452) 452
= 2.536 N/mm2
=1.369 N/mm2, =1+=1 , =0.25 = 0.2530 = 1.369 N/mm2
d= 500 40 16/2 = 452 mm
Hence not safe
Take thickness of pier cap =800 mm
d=752 mm
4824.02 1000 4824.02 1000
= (2 400+2 d+2 800+2 d) d = (2 400+2 752+2 800+2 752) 752
=1.186 N/mm2

Take area of steel AS = 1 % of area of cap and distribute these bars equally at top and
bottom of cap.

As in transverse direction of pier cap

139
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

= 1% of 800 1250 = 10000 mm2,


As on one side = 10000/2 = 5000 mm2
Take 30 mm bar, 8 nos
Spacing = 156 mm Adopt 140 mm.
30 dia @ 140 mm c/c.

As in longitudinal direction of pier cap
= 1% of 800 9100 = 72800 mm2
As on one side = 72800/2 = 36400 mm2
Take 30 mm bar n = 52 nos
Spacing = 175 mm, Adopt 150 mm
30 dia @ 150 mm c/c.
In transverse direction bars are provided in the forms of stirrups.
In addition, two layers of mesh reinforcement, each consisting 6 mm @ 75 mm c/c in both
directions one at 20 mm and other at 100 mm from the top of cap are provided directly
under the bearing.

IV. Analysis and Design of Pier Stem


In the example, responses of pier at bottom for basic combination and seismic combination
of loads have been calculated. Loads taken are vertical and longitudinal loads in first case
and vertical and transverse loads in second case.

140
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Case I
Basic combination of loads
CASE I --Basic combination of loads

Distance Eccentricity Hx
Load Pu Mux Muy Hy
f from x (KN
(KN) y (m) (KN) (KN-m) (KN-m) (KN)
bottom(m) (m) )
1650. 1.3 2228.56
DLss 0 0
79 5 7
DLw 1.7
256.34 448.595 0 0
c 5
136.93 1.1 1858.22 157.476
FbrH 11.8 0
6 5 2 4
1.1
FbrV 18.62 21.413 0 0
5
966.632
FwL 54.612 1.5 11.8 0 81.918
4
Wpie 3709.8 1.3 5008.24
0 0
r 1 5 4
12.139 1.8
FwcT 1.82 1 6.67 0 0 0
4 2
2/3*10=6.6
FwcL 1.51 1 0 10.0717 1.51
7
Fbuo - 0.1 -
0 0
y 1319.5 5 197.925
7508.89 2834.92 12.139 1.8 240.904
Total without LL
3 6 4 2 4
1.25/2-
0.125- 362.470
LL' 690.42 1.5 1035.63
.15=0.3 5
5
8544.52 3197.39 12.139 1.8 240.904
Total with LL'
3 6 4 2 4
1027.2
LL'' 1.5 0 1540.92 0
8
9049.81 2834.92 12.139 1.8 240.904
Total WITH LL''
3 6 4 2 4

i. When loaded on only one span ii. When loaded on both span

Total Axial Load (Pu) = 8544.523 KN Total Axial Load (Pu) = 9049.813 KN
Total Mux = 3197.396 KN-m Total Mux = 2834.926 KN-m
Total Muy = 12.1394 KN-m Total Muy = 12.1394 KN-m
Total Hx = 1.82 KN Total Hx = 1.82 KN
Total Hy = 240.9044 KN Total Hy = 240.9044 KN

141
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Case I
Seismic combination of loads
CASE I -- Seismic Combination of Loads

Distance Eccentricity
Load Pu
f from x Mux Muy Hx Hy
(KN) (KN)
bottom(m) (m) y (m) (KN-m) (KN-m) (KN) (KN)
DLss 1650.79 1 1650.79 0 0
DLwc 256.34 1 256.34 0 0
FbrH 136.936 0.2 11.8 0 323.169 27.3872
FbrV 18.62 0.2 3.724 0 0
FsL 168.49 1 11.8 0 1988.182 168.49
FSVL 35.26 1 35.26 0 0
L
Fs(sub) 417.35 1 5.9 0 2462.365 417.35
FhydL 541.45 1 5 0 2707.25 541.45
Wpier 3709.81 1 3709.81 0 0
FWCT 1.82 1 6.67 0 0 12.1394 1.82 0
L
FWC 1.51 1 6.67 0 10.0717 1.51
Fbuoy -1319.5 0.15 -197.925 0 0
Total without LL 5457.999 7491.038 12.1394 1.82 1156.187
'
LL 690.42 0.2 0.35 138.084 48.3294 0
Total with LL' 5596.083 7539.367 12.1394 1.82 1156.187
LL'' 1027.28 0.2 205.456 0
Total WITH LL'' 5663.455 7491.038 12.1394 1.82 1156.187

i. When loaded on only one span ii. When loaded on both span

Total Axial Load (Pu) = 5596.083 KN Total Axial Load (Pu) = 5663.455 KN
Total Mux = 7539.367 KN-m Total Mux = 7491.038 KN-m
Total Muy = 12.1394 KN-m Total Muy = 12.1394 KN-m
Total Hx = 1.82 KN Total Hx = 1.82 KN
Total Hy = 1156.187 KN Total Hy = 1156.18 KN

142
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Case II
Basic combination of loads

Distance Eccentricity
Load Pu
f from x Mux Muy Hx Hy
(KN) (KN)
bottom(m) (m) y (m) (KN-m) (KN-m) (KN) (KN)
DLss 1650.79 1.35 2228.567 0 0
DLwc 256.34 1.75 448.595 0 0
FbrH 136.936 1.15 11.8 0 1858.222 157.4764
FbrV 18.62 1.15 21.413 0 0
FwT 218.47 1.5 11.8 0 0 3866.919 327.705
Wpier 3709.81 1.35 5008.244 0 0
FwcT 1.82 1 6.67 0 0 12.1394 1.82 0
FwcL 1.51 1 6.67 0 8.6372 1.51
Fbuoy -1319.5 0.15 -197.925 0 0
Total without LL 7508.893 1866.859 3879.058 329.525 158.9864
LL' 690.42 1.5 0.35 1035.63 284.7983
'
Total with LL 8544.523 2151.657 3879.058 329.525 158.9864
LL'' 1027.28 1.5 0 1540.92 0
Total WITH LL'' 9049.813 1866.859 3879.058 329.525 158.9864

i. When loaded on only one span ii. When loaded on both span

Total Axial Load (Pu) = 8544.523KN Total Axial Load (Pu) = 9049.813 KN
Total Mux = 2151.657 KN-m Total Mux = 1866.859 KN-m
Total Muy = 3879.058 KN-m Total Muy = 3879.058 KN-m
Total Hx = 329.525 KN Total Hx = 329.525 KN
Total Hy = 158.986 KN Total Hy = 158.986 KN

143
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Case II
Seismic combination of loads
CASE II -- Seismic Combination of Loads

Load f Distance Eccentricit Pu Mux Muy Hx Hy


(KN) from y (KN) (KN-m) (KN-m) (KN) (KN)
bottom( x y (m)
m) (m
)
DLss 1650.7 1 1650.79 0 0
9
DLwc 256.34 1 256.34 0 0
FbrH 136.93 0.2 11.8 0 323.169 27.3872
6
FbrV 18.62 0.2 3.724 0 0
FsT 230.66 1 11.8 0 2721.78 230.6
8 6
FSVT 107.32 1 107.32 0 0
Fs(sub) 417.35 1 5.9 0 2462.36 417.35
T
5
FhydT 13.75 1 5 0 68.75 13.75
Wpier 3709.8 1 3709.81 0 0
1
FWCT 1.82 1 6.67 0 0 12.1394 1.82 0
FWCL 1.51 1 6.67 0 10.0717 1.51
Fbuoy - 0.1 - 0 0
1319.5 5 197.925
Total without LL 5530.05 2864.35 2733.92 232.4 459.997
9 6 7 8 2
LL' 690.42 0.2 0.35 138.084 48.3294 0
Total with LL' 5668.14 2912.68 2733.92 232.4 459.997
3 5 7 8 2
LL'' 1027.2 0.2 205.456 0
8
Total WITH LL'' 5735.51 2864.35 2733.92 232.4 459.997
5 6 7 8 2

i. When loaded on only one span ii. When loaded on both span

Total Axial Load (Pu) = 5668.143 KN Total Axial Load (Pu) = 5735.515 KN
Total Mux = 2912.685 KN-m Total Mux = 2864.356 KN-m
Total Muy = 2733.927 KN-m Total Muy = 2733.927 KN-m
Total Hx = 232.48 KN Total Hx = 232.48 KN
Total Hy = 459. 997 KN Total Hy = 459. 997 KN

144
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Design and Detailing of Pier Stem at bottom


Check slenderness ratio of column
Effective Length 1.2 11.8 1000
Slenderness Ratio of Column = Radius of gyration = = 42.78 > 30
331

Design Pier stem


Design pier stem as a biaxially loaded long column.
I. Longitudinal Reinforcement
As critical case is difficult to know, we simply calculate longitudinal reinforcement for all the
cases and accept the percent of steel that satisfies every cases.

For Case I, Basic condition (i),


Pu = 8544.523 KN
Mux = 3197.396 KN-m
Muy = 12.1394 KN-m

Take full width of Pier, D=1.15 m (along y- direction) and unit length B=1 m (along x-
direction)
Hence,
Pu = 8544.523/9.1 = 938.96 KN
Mux = 3197.396/9.1 = 351.36 KN-m
Muy = 12.139/9.1 KN-m =1.334 KN-m
Calculating accidental eccentricities,

ey,min = 500 +30 > 5% of D= 57.5 mm
= 14.16/500 + 1.15/30
= 0.0667m
= 66.7 mm

ex,min = 500 +30 > 5% of B= 50 mm
= 14.16/500 +1/30
= 61.65 mm

Moment due to accidental eccentricities,


Mux,e = Pu ey,min
= 938.96 61.65/1000
= 57.88 KN-m

Muy,e = Pu ex,min
=938.96 66.67/1000
=62.6 KN-m

145
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

As the column is long, additional Bending Moment acts, given as


Max = k Max
May = k May

D
Max = ( )2
2000
938.96 1.15 14.16
= ( 1.15 )2
2000
=81.85 KN-m

B
May = ( )2
2000
938.96 1 14.16
= ( 1 )2
2000
= 94.13 KN-m


k= 1

Puz = 0.446fckBD + (0.75fy 0.446 fck)pBD (Take p= 1.8%)


= 0.446 20 1000 1150 + (0.75 415 0.446 20) 1.8/100 1000 1150
=16516.23 KN

Pb = k1 x fck B D + k2 p B D
d = Clear cover +diameter of transverse reinforcement + diameter of longitudinal
reinforcement/2
= 40 + 10 + 32/2
= 66 mm

d/D = 66/1150 = 0.06 , Take 0.05


From Table 60, SP16, for d/D = 0.05 & Rectangular section
k1 = 0.219

For d/D = 0.05, fy = 415 N/mm2 and rectangular section with reinforcement distributed
equally on to opposite sides,
k2 = 0.096

Pb = k1 x fck B D + k2 p B D
= 0.219 20 1000 1150 + 0.096 1.8 1000 1150
= 5235.72 KN

146
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge


k= 1

16516.23938.96
= 16516.235235.72
=1.381
Take k = 1

Max = k Max = 1 81.85 = 81.85 KN-m


May = k May = 1 94.13 = 94.13 KN-m

Now, Mux= Mux + Max


= 351.36+81.85
= 433.21 KN-m

Muy = Muy,e + May


= 1.334 + 94.13
= 95.46 KN-m

938.96 1000
Now, B D = 20 1000 1150 = 0.041

p/fck = 1.8/20 = 0.09


d/D = 0.06, Take 0.05 & d/B = 0.066, Take 0.05
fy = 415 N/mm2
From SP-16 chart 31,
,
= 0.170
B D2
Mux,l = 4496.5 KN-m

,
= 0.17
B2 D
Muy,l = 3910.00 KN-m

an = 0.667 + 1.667 Pu/Puz 1 & 2


= 0.762
Take an=1

Now, for p to satisfy,



(,)an + (,)an 1
433.21 95.46
0r, (4496.5)1 + ( 3910 )1 1
0.121 1 OK

147
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Case Condition Pu(KN) Mux(KNm) Muy(KNm Mux,e Muy,e Max May p(%)
I Basic I 938.9586 351.3622 1.334 57.8868 62.62854 81.87719 94.17754 1.8
I Bacic II 938.9586 236.4458 426.2701 57.8868 62.62854 81.87719 94.17754 1.8
I Seismic I 614.9542 828.5019 1.334 37.91192 41.01744 53.624 61.6799 1.8
I Seismic II 622.8729 320.0753 300.4315 38.40011 41.54562 54.31451 62.47415 1.8
II Basic I 994.4849 311.5303 1.334 61.31 66.33215 86.71909 99.74684 1.8
II Bacic II 994.4849 205.1493 426.2701 61.31 66.33215 86.71909 99.74684 1.8
II Seismic I 622.6874 823.1932 1.334 38.38868 41.53325 54.29834 62.45554 1.8
II Seismic II 630.2764 314.7644 300.4315 38.85654 42.03943 54.9601 63.21672 1.8

(Mux'/Mux,l)n + (Muy'/
Case Condition Max' May' Mux' Muy' Pu/fckBD Mux,l/fckBD2 Muy,l/fckB2D n Mux,l Muy,l
Muy,l)n

I Basic I 81.87719 94.17754 433.2394 95.51154 0.0408 0.17 0.17 1 4496.5 3910 0.1208
I Basic II 81.87719 94.17754 318.323 520.4477 0.0408 0.17 0.17 1 4496.5 3910 0.2039
I Seismic I 53.624 61.6799 882.1259 63.0139 0.0267 0.16 0.16 1 4232 3680 0.2256
I Seismic II 54.31451 62.47415 374.3898 362.9057 0.0271 0.16 0.16 1 4232 3680 0.1871
II Basic I 86.71909 99.74684 398.2494 101.0808 0.0432 0.17 0.17 1 4496.5 3910 0.1144
II Basic II 86.71909 99.74684 291.8684 526.0169 0.0432 0.17 0.17 1 4496.5 3910 0.1994
II Seismic I 54.29834 62.45554 877.4915 63.78954 0.0271 0.16 0.16 1 4232 3680 0.2247
II Seismic II 54.9601 63.21672 369.7245 363.6483 0.0274 0.16 0.16 1 4232 3680 0.1862

148
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

For 1m Strip of pier, Ast = 1.8 % 1150 1000 = 20700 mm2


20700
Taking 32 mm on two faces, n = 32 2
= 12.86
2 ( )
2
1000
Spacing = 12.86 = 77.71 mm
32 mm @ 75 mm c/c

b. Transverse Reinforcement

The transverse reinforcement of pier stem has not been governed by shear force. So,
transverse reinforcement is provided by detailing rules. [From IRC 112, Cl. 16.2]
Take lateral tie of = 10 mm (/4)
Spacing of tie (Sv) Width of pier = 1150 mm
12 32 = 384 mm
200 mm
Provide spacing of tie (Sv) = 200 mm.
For potential plastic hinge region i.e. 1200 mm from the bottom of pier,
Spacing of tie (Sv) 5 40 = 200 mm
(1200 2 100)/5 = 200 mm
Adopt spacing of tie (Sv) = 200 mm for potential plastic hinge region.

149
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

DRAWINGS

General Arrangements Drawing No. 1


General Elevation Sheet No. 1
General Plan Sheet No. 2

T-Girder (12m span) Drawing No. 2


Plan Sheet No. 1
Transverse Section Sheet No. 2
Longitudinal Section Sheet No. 3
Reinforcement Detailing in Transverse Section Sheet No. 4
Reinforcement Detailing along Main Girder Sheet No. 5
Reinforcement Detailing in Cross Girders (X-Section) Sheet No. 6
Reinforcement Detailing along Cross Girders Sheet No. 7
Top Reinforcement in Deck Slab Sheet No. 8
Bottom Reinforcement in Deck Slab Sheet No. 9
Transverse Section Overall Detailing Sheet No. 10

Steel Truss (36m span) Drawing No. 3


Elevation and X-Section Sheet No. 1
Deck Slab Reinforcement Detailing Sheet No. 2
Details at Truss joints I Sheet No. 3
Details at Truss joints II Sheet No. 4
Details at Truss joints III Sheet No. 5
Top and Bottom Bracing Sheet No. 6
Portal and Sway Bracing Sheet No. 7
Steel Sections Used Sheet No. 8

Elastomeric Bearings for T-Girder and Truss Drawing No. 4

Abutment Drawing No. 5


Reinforcement Detailing in X-Sections Sheet No. 1
Reinforcement Detailing in L-Sections Sheet No. 2
Reinforcement Detailing in Spread Footing and Dirt Wall Sheet No. 3

RCC Solid Pier Drawing No. 6


Plan and Elevations Sheet No. 1
Reinforcement Detailing in Pier Cap Sheet No. 2
Reinforcement Detailing along X-Sections Sheet No. 3

150
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

APPROXIMATE ESTIMATES
APPROXIMATE ESTIMATE OF QUANTITY IN T-BEAM BRIDGE
Item Measurement
Description of work Quantity Unit
no No Length Breadth Height
1 M25 grade concrete for superstructure

1.1 Deck slab (restrained) 2 12.25 4.3 0.2 21.07

1.2 Deck slab (cantilever) 4 12.25 1.45 0.17 12.0785

T-beam main girders


1.3 6 12.25 0.3 0.8 17.64
(rectangular)
1.4 Cross girder (interior) 12 1.7 0.25 0.55 2.805
1.5 Cross girder (exterior) 8 1.7 0.25 0.4 1.36
1.6 Railing post 18 0.225 0.225 1.1 1.002375
1.7 Kerb 4 12.25 0.6 0.3 8.82
1.8 Wearing coat 2 12.25 6 0.0875 12.8625

1.9 Fillet (Interior) of main girder 8 12.25 0.3 0.15 2.205

1.10 Fillet (Interior) of cross girder 32 1.7 0.3 0.15 1.224

1.11 Fillet (exterior) T-beam 4 12.25 0.85 0.15 3.12375


1.12 Approach slab 2 3.5 6 0.3 12.6

1.13 Railing post in Approach slab 8 0.225 0.225 1.1 0.4455

Total= 97.237 m3
2 Formwork
2.1 T-Girder bottom 6 12.25 0.3 22.05
2.2 T-Girder side 12 12.25 0.8 117.6
2.3 Interior fillet of T-girder 8 12.25 0.335 32.83
2.4 End Cross girder bottom 8 1.7 0.25 3.4
2.5 End Cross girder side 8 1.7 0.4 5.44
2.6 interior Cross girder bottom 12 1.7 0.25 5.1
2.7 Interior Cross girder side 12 1.7 0.55 11.22
2.8 Exterior fillet of T-girder 4 12.25 0.863 42.287
2.9 interior fillet of cross beam 32 1.7 0.34 18.496
Deck slab (restrained)
2.10 2 12.25 2.2 53.9
Bottom

151
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

APPROXIMATE ESTIMATE OF QUANTITY IN T-BEAM BRIDGE


Item Measurement
Description of work Quantity Unit
no No Length Breadth Height
Deck slab (cantilever)
2.11 4 12.25 0.6 29.4
Bottom
2.12 Deck slab (cantilever) sides 8 12.25 0.17 16.66
2.13 Railing post 26 0.225 1.1 6.435
2.14 approach slab bottom 2 3.5 6 42
2.15 approach slab side 4 3.5 0.3 4.2
sq.
Total= 411.018
m

3 Steel work in superstructure 1% of concrete work 7.633 MT

4 48.3 mm GI pipe in railing 12 14.25 171 rm.

5 Concrete work in abutment


5.1 Abutment foundation 2 5.2 8.5 2 176.8
5.2 Abutment portion (stem) 2 5.2 1.1 8.25 94.38
5.3 Abutment cap 2 5.2 1.175 0.3 3.666
5.4 Abutment Dirt wall 2 5.2 0.25 0.752 1.9552
Total= 276.801 m3
6 Steel work in abutment 1% of concreting (Mt) 21.729 MT

7 Pcc in pier
7.1 Well foundation Not Calculated
Area of Trap. Sec.=
7.2 Pcc in stem 2 9.15 242.475
0.5x(1.1+1.065)x9.8=13.25
7.3 Pcc in Pier cap 2 9.25 1.2 1.3 28.86
Total 271.335 m3
8 Steel works in pier 2% of concreting quantity 42.599 MT

Approximate estimate for T-Beam Bridge:


Total Concrete work in Superstructure=97.237m3
Rebar for Superstructure = 7.633MT
GI pipe=171 m
Cost of concrete work = 97.237x12,000 = Rs. 11,66,844 /-
Cost for GI pipe = 171x760 = Rs 1,29,960 /-
Cost of rebar in slab = 7.633x95000 = Rs.7,25,135 /-

152
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Total cost of bridge Superstructure = Rs. 20,21,939 /-


Cost per meter length (Superstructure) = Rs. 84,248 /-

APPROXIMATE ESTIMATE OF QUANTITY IN TRUSS


No uni
Item no. Description of work L B H Qty.
. t
1 M20 grade concrete for superstructure
0.
1.1 For slab 1 36 6 43.2
2
0.
1.2 For kerb 2 36 0.6 12.96
3
1.
1.3 For railing post 18 0.225 0.225 1.00238
1
Total = 57.1624 m3

2 48.3 mm GI pipe in railing 6 36 216 rm

1% of concrete
3 Steel rod for RCC and slab 4.487 MT
work

4 Steel for truss


4.1 Main truss 31.42 MT
4.2 Bottom bracing 4.606 MT
4.3 Top bracing 5.88 MT
4.4 Stringer 15.7 MT
4.5 Cross girder 18.46 MT
Total= 76.066 MT

Approximate estimate for Truss bridge:


Total Concrete work = 57.162m3
Rebar for slab = 4.487MT
Cost for GI pipe = 216x760=Rs 1,64,160 /-
Steel work in steel truss = 76.066 MT
Cost of concrete work = 57.162x12,000 = Rs. 6,85,944 /-
Cost of steel work in truss = 76.066x1,30,000=Rs.98,88,580 /-
Cost of rebar work in slab = 4.487x95,000=Rs. 4,26,265 /-
Total cost of bridge superstructure = Rs.1,10,00,789 /-
Cost per meter length = Rs. 3,05,578/-

153
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Cost of Substructure:
Total concrete work in abutment & pier = 548.136m3
Total rebar work in abutment & pier = 64.328MT
Cost of concrete work = 548.136x12,000 = Rs.65,77,632/-
Cost of rebar work in slab = 64.328x95,000 = Rs. 61,11,160 /-
Total cost of bridge Substructure = Rs.1,26,88,792 /-

154
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

CONCLUSION AND RECOMMENDATIONS


With our relentless effort for about a year, we finally have concluded our
final year project work entitled Design of Bridge over Kerunga Khola. This
would not have been possible without the valuable guidance from our
supervisor to understand some difficult concepts of Bridge Analysis and Design.
It was our teamwork that helped us overcome the lengthy design procedures
and surpass our own expectations towards the final year project. The field visit
helped us collect a real time experience to be a Bridge Engineer while the
incorporation of two different superstructure types helped us explore the
possibilities in bridge design in terms of safety, economy and aesthetics. The
report encompasses all our work and has been prepared with the best of our
knowledge and skills.
The project work is apparently complete but we have not been able to
include analysis results from SAP2000 in this report. As the use of computers
helps make structural analysis easier and quicker, use of computer packages
along with manual calculations cannot be averted and hence, their use highly
recommended. But it should be forethought that the results from such software
are only as reliable as the knowledge and acquaintance that the user has of the
software thus needing a very meticulous application.
This hereby concludes our final year project work.

155
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

BIBLIOGRAPHY
3. Victor, D.J. 2012. Essentials of Bridge Engineering, Oxford and IBH Publishing
Company Pvt. Ltd., New Delhi
4. Design Examples Provided by Asso. Prof. N.C. Sharma, IOE, Pulchowk
5. Krishnaraju, N. Design of Bridges, Oxford and IBH Publishing Company Pvt. Ltd., New
Delhi
6. Chandra, R. 1981. Design of Steel Structures Vol. II, Standard Book House, New Delhi
7. Jain, A.K. 2002. Reinforced Concrete Limit State Design, Nem Chand and Bros,
Roorkee, India (Reprint 2009)

Codes/Standards
1. IRC: 6-2014
2. IRC 21-2000 Concrete Bridge
3. Nepal bridge standard-2067, Government of Nepal, Ministry of Physical Planning
and works, Department of Roads
4. Standard specification of roads and bridges, Government of Nepal, Ministry of
Physical Planning and works, Department of Roads
5. IRC 83-1987(part II)
6. IRC 78-2000 Foundations and substructures
7. IRC 5-1998 Loads and Stresses

156
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

ANNEXES
Detail Design of Connections at Truss Joints
We have, for M20 HSFG bolts,
Slip Resistance = 78478.4 kN

Joint L3
Member L2-L3
Axial force =1712.85 KN
No. of bolts= 1712.85x10^3/(2x78478.4)
= 11
Provide 12 bolts.
Try double channel section of DC300.

Check:
1. Design strength due to yielding of gross section:
Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 2x45.64+2x30x0.8
=139.28 cm^2
fy= yield strength of the material
=250 Mpa
m0=partial safety factor for the yielding =1.1
Tdg=139.28x100x250/(1.1x1000)
=3165.45 KN >1712.85 KN ok

2. Rupture strength of the channel section


Tdn = 0.9xAncxfu/ m1+Agofy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fu x m0)/(fy x m1)
in which
w = width of outstanding leg =90mm
bs = shear lag width = w+wt-t
= 90+75-13.6 = 151.4mm
Lc = length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc = net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4 - 0.076x(90/13.6)x(250/410)x(151.4/150)
=1.09 > 0.7
< 1.44

157
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Tdn = 0.9x{7.8x(300-3x22-13.6)} x410/1.25+1.09x {2x(90-7.8/2)x13.6}250/1.1


= 1087.6KN > 856.42KN (1712.85/2=856.42) OK

Member L3-L4
Axial force =2139.97 KN (T)
No. of bolts= 2139.97x10^3/(2x78478.4)
= 14
Provide 15 bolts
Try double channel section of DC300.
Check:
1. Design strength due to yielding of gross section:
Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 2x45.64+2x30x0.8
=139.28 cm^2
fy= yield strength of the material
=250 Mpa
m0=partial safety factor for the yielding =1.1
Tdg=139.28x100x250/(1.1x1000)
=3165.45 KN >2139.97 KN ok

2. Rupture strength of the channel section


Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =90mm
bs=shear lag width =w+wt-t
=90+75-13.6 = 151.4mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(90/13.6)x(250/410)x(151.4/200)
=1.168 >0.7
<1.44

Tdn=0.9x{7.8x(300-3x22-13.6)} x410/1.25+1.168x{2x(90-7.8/2)x13.6}250/1.1
= 1129.158KN >1069.985KN (2139.97/2=1069.985) OK

Member U2-L3

158
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Axial force = 891.194 KN(T)


No. of bolts= 891.194 x10^3/(2x78478.4)
=6
Provide 6 bolts
Try with angle section 4-ISA 55x55x8.
Check
1. Rupture strength of a single angle connected through one leg and affected by shear
lag is given by
Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =55
bs=shear lag width =w+wt-t
=55+30-8 = 77mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =100mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(55/8)x(250/410)x(77/100)
=1.155 >0.7
<1.44
Tdn=0.9x{8x(55-22-8/2)} x410/1.25+1.155x{8x(55-4)}250/1.1
= 175.58KN <222.8KN (891.194 /4=222.8) Not safe

Try with 4-ISA 60x60x10


1. Rupture strength
=1.4-0.076x(60/10)x(250/410)x(60+35-10)/100
=1.1637 >0.7
<1.44
Tdn=0.9x{10x(60-22-10/2)} x410/1.25+1.1637x{10x(60-5)}250/1.1
= 242.88KN >222.8KN (891.194 /4=222.8) safe

2. Design strength due to yielding of gross section:


Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 4x1100+300x8
=6800 mm^2
fy= 250 Mpa
m0=partial safety factor for the yielding =1.1
Tdg=6800x250/(1.1x1000)
=1545.45 KN >891.194 KN ok
3. Block failure
The block shear strength of a bolted connection is the least of

159
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Where Avg and Avn are the minimum grosss and net areas in shear along the bolt line parallel to line of
action of force respectively.
Atg, Atn are the minimum grosss and net areas in tension from the bolt hole to the edge of a plate,
perpendicular to the line of action of force
Avg=50x3x10 =1500 mm^2
Avn=(50x3-2.5x22)x10 =950 mm^2
Atg=25x10 =250 mm^2
Atn=(25-22/2)x10 =140 mm^2
Tdb={1500x250/(1.1x3)+0.9x140x410/1.25}x4/1000 =952.6KN
Or ={0.9x950x410/(1.25x3)+250x250/1.1}x4/1000 = 875 KN
Least Tdb=875 KN<891.194KN Not safe

Try with 4-ISA 65x65x10


1. Rupture strength
=1.4-0.076x(65/10)x(250/410)x(65+35-10)/100
=1.129 >0.7
<1.44

Tdn=0.9x{10x(65-22-10/2)} x410/1.25+1.129x{10x(65-5)}250/1.1
= 266.13KN > 222.8KN (891.194 /4=222.8) safe

2. Design strength due to yielding of gross section:


Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 4x1200+300x8
=7200 mm^2
Tdg=7200x250/(1.1x1000)
=1636.4 KN >891.194 KN ok
3. Block failure
The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Avg=50x3x10 =1500 mm^2
Avn=(50x3-2.5x22)x10 =950 mm^2
Atg=30x10 =300 mm^2
Atn=(30-22/2)x10 =190 mm^2
Tdb={1500x250/(1.1x3)+0.9x190x410/1.25}x4/1000 =1011.6KN
Or ={0.9x950x410/(1.25x3)+300x250/1.1}x4/1000 = 920.4 KN
Least Tdb=920.4 KN>891.194KN Safe

Member L3-U3
Axial force = 402.945 KN(C)

160
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

No. of bolts=402.945 x10^3/(2x78478.4)


=4
Provide 4 bolts
Try with angle section 4-ISA80x80x10
with A = 9600 mm2 and ry = 30.1 mm
Check for Compression capacity
0.8600
For = = 159.47 and buckling class c,
3.01
fcd = 53.3 MPa
So, Pd = fcdxAg = 510.72 kN >402.945 kN OK
1. Rupture strength of angle section
=1.4-0.076x(80/10)x(250/410)x(80+45-10)/50
=0.54 >0.7
<1.44
Tdn= 0.9x{10x(80-22-10/2)} x410/1.25+0.7x{10x(80-5)}250/1.1
= 168.39KN >100.73KN (402.945 /4=100.73) safe

2. Block failure
The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Avg=50x2x10 =1000 mm^2
Avn=(50x2-1.5x22)x10 =670 mm^2
Atg=40x10 = 400 mm^2
Atn=(40-22/2)x10 = 290 mm^2
Tdb={1000x250/(1.1x3)+0.9x290x410/1.25}x4/1000 = 867.3KN
Or ={0.9x670x410/(1.25x3)+400x250/1.1}x4/1000 = 820.4 KN
Least Tdb = 820.4 KN > 402.945 KN safe

JOINT U2
Member U2-L2
Axial force = 711.925 KN
No. of bolts= 711.925 x10^3/(2x78478.4)
=5
Provide 6 bolts
Try with angle section 4-ISA100x100x10
with A = 112 cm2 and ry = 3.8 cm

Check for Compression capacity


0.8600
For
= 3.8
= 126.32 and buckling class c,
fcd = 77.76 MPa
So, Pd = fcdxAg = 870.9 kN > 711.925 kN OK

1. Rupture strength of single angle section

161
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

=1.4-0.076x(100/10)x(250/410)x(100+60-10)/100
= 0.71 >0.7
<1.44
Tdn=0.9x{10x(100-22-10/2)} x410/1.25+0.71x{10x(100-5)}250/1.1
= 368.8 KN >178KN (711.925/4 = 178) safe

2. Block failure
The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Avg=50x3x10 =1500 mm^2
Avn=(50x3-2.5x22)x10 =950 mm^2
Atg=40x10 =400 mm^2
Atn=(40-22/2)x10 =290 mm^2
Tdb={1500x250/(1.1x3)+0.9x290x410/1.25}x4/1000 = 1129.7KN
Or ={0.9x950x410/(1.25x3)+400x250/1.1}x4/1000 = 1011.28 KN
Least Tdb= 1011.28 KN > 711.925 KN safe

Member U1-U2
Axial force =1713.01 KN (C)
No. of bolts= 1713.01x10^3/(2x78478.4)
= 11
Provide 12 bolts
Try double channel section of DC250
Check:
1. Design strength due to yielding of gross section:
A = 112 cm2 and ry = 11.18 cm
Check for Compression capacity
0.8600
For = = 53.67 and buckling class c,
11.18
fcd = 177.49 MPa
So, Pd = fcdxAg = 2236.37 kN > 1713.01 kN OK

Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 2x39+2x30x0.8
=126cm2
fy= yield strength of the material
=250 Mpa
m0=partial safety factor for the yielding =1.1
Tdg=126x100x250/(1.1x1000)
=2863.64KN >1713.01 KN ok

2. Rupture strength of the channel section


Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0

162
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =80mm
bs=shear lag width =w+wt-t
=80+50-14.1 = 115.9mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(80/14.1)x(250/410)x(115.9/150)
=1.197 >0.7
<1.44

Tdn=0.9x{7.2x(250-3x22-14.1)} x410/1.25+1.197x{2x(80-7.2/2)x14.1}250/1.1
= 947.23KN >856.505KN (1713.01/2=856.505) safe

Member U2-U3
Axial force =2139.97 KN (C)
No. of bolts= 2139.97x10^3/(2x78478.4)
= 14
Provide 15 bolts
Try double channel section of DC300
Check:
3. Design strength due to yielding of gross section:
A = 140.6 cm2 and ry = 11.64 cm
Check for Compression capacity
0.8600
For = = 30.93 and buckling class c,
11.64
fcd = 210 MPa
So, Pd = fcdxAg = 2952.6 kN > 2139.97 kN OK

4. Rupture strength of the channel section


Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =90mm
bs=shear lag width =w+wt-t
=90+75-13.6 = 151.4mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg

163
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

t=thickness of the angle


=1.4-0.076x(90/13.6)x(250/410)x(151.4/200)
=1.168 >0.7
<1.44

Tdn=0.9x{7.8x(300-3x22-13.6)} x410/1.25+1.168x{2x(90-7.8/2)x13.6}250/1.1
= 1129.158KN >1069.985KN (2139.97/2=1069.985) OK

JOINT U1
Member L0-U1
Axial force =1665.33 KN (C)
No. of bolts= 1665.33x10^3/(2x78478.4)
= 11
Provide 12 bolts
Try double channel section of DC250
Check:
1. Design strength due to yielding of gross section:
A = 112 cm2 and ry = 11.18 cm
Check for Compression capacity
0.8600
For = = 53.67 and buckling class c,
11.18
fcd = 177.49 MPa
So, Pd = fcdxAg = 2236.37 kN > 1713.01 kN OK

2. Rupture strength of the channel section


Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =80mm
bs=shear lag width =w+wt-t
=80+50-14.1 = 115.9mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(80/14.1)x(250/410)x(115.9/150)
=1.197 >0.7
<1.44

Tdn=0.9x{7.2x(250-3x22-14.1)} x410/1.25+1.197x{2x(80-7.2/2)x14.1}250/1.1
= 947.23KN >832.665KN (1665.33/2=832.665) safe

164
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Member U1-L1
Axial force = 736.93 KN (C)
No. of bolts= 736.93 x10^3/(2x78478.4)
=5
Provide 6 bolts
Try with angle section 4-ISA 100x100x10
Strength on yielding = 870.9 kN > 736.93 kN OK
Check:
(a) Rupture strength of single angle section
=1.4-0.076x(100/10)x(250/410)x(100+60-10)/100
= 0.71 >0.7
<1.44
Tdn=0.9x{10x(100-22-10/2)} x410/1.25+0.71x{10x(100-5)}250/1.1
= 368.8 KN >178KN (711.925/4 = 178) safe

(b) Block failure


The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Avg=50x3x10 =1500 mm^2
Avn=(50x3-2.5x22)x10 =950 mm^2
Atg=40x10 =400 mm^2
Atn=(40-22/2)x10 =290 mm^2
Tdb={1500x250/(1.1x3)+0.9x290x410/1.25}x4/1000 = 1129.7KN
Or ={0.9x950x410/(1.25x3)+400x250/1.1}x4/1000 = 1011.28 KN
Least Tdb= 1011.28 KN > 711.925 KN safe

JOINT L2
Member L1-L2
Axial force =998.38 KN (T)
No. of bolts= 998.38x10^3/(2x78478.4)
=7
Provide 9 bolts
Try double channel section of DC250
Check:
1. Design strength due to yielding of gross section:
Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 2x39+2x30x0.8
=126cm2
fy= yield strength of the material
=250 Mpa

165
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

m0=partial safety factor for the yielding =1.1


Tdg=126x100x250/(1.1x1000)
=2863.64KN >998.38 KN ok

2. Rupture strength of the channel section


Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =80mm
bs=shear lag width =w+wt-t
=80+50-14.1 = 115.9mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(80/14.1)x(250/410)x(115.9/150)
=1.197 >0.7
<1.44

Tdn=0.9x{7.2x(250-3x22-14.1)} x410/1.25+1.197x{2x(80-7.2/2)x14.1}250/1.1
= 947.23KN > 499.19KN (998.38/2=499.19KN) safe

Member U1-L2
Axial force = 1063.369 KN (T)
No. of bolts= 1063.369 x10^3/(2x78478.4)
=7
Provide 8 bolts
Try with angle section 4-ISA 70x70x10
Check:
1. Rupture strength(for single angle)
=1.4-0.076x(70/10)x(250/410)x(70+40-10)/150
=1.1837 >0.7
<1.44
Tdn=0.9x{10x(70-22-10/2)} x410/1.25+1.1837x{10x(70-5)}250/1.1
= 301.801KN >265.84KN (1063.369KN /4=265.84KN) safe

2. Design strength due to yielding of gross section:


Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 4x1300+300x12
=8800 mm^2
fy= 250 Mpa

166
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

m0=partial safety factor for the yielding =1.1


Tdg=8800x250/(1.1x1000)
=2000KN >1063.369KN ok
3. Block failure
The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Where Avg and Avn are the minimum gross and net areas in shear along the bolt line parallel to line of
action of force respectively.
Atg, Atn are the minimum gross and net areas in tension from the bolt hole to the edge of a plate,
perpendicular to the line of action of force
Avg=50x4x10 =2000 mm^2
Avn=(50x4-3.5x22)x10 =1230 mm^2
Atg=30x10 =3000 mm^2
Atn=(30-22/2)x10 =190 mm^2
So,
Tdb={2000x250/(1.1x3)+0.9x190x410/1.25}x4/1000 =1274.078KN
Or ={0.9x1230x410/(1.25x3)+300x250/1.1}x4/1000 = 1111.262 KN
Least Tdb=1111.262 KN > 1063.369 KN safe

Joint L0
Member L0-L1
Axial force =998.38 KN (T) ( same as member L1-L2)
No. of bolts= 998.38x10^3/(2x78478.4)
=7
Provide 9 bolts
Provide double channel section of DC250

JOINT U3
Member U3-U4
Axial force =2283.18 KN (C)
No. of bolts= 2283.18x10^3/(2x78478.4)
= 15
Provide 15 bolts
Try double channel section of DC300
Check:
1. Design strength due to yielding of gross section:
A = 140.6 cm2 and ry = 11.64 cm
Check for Compression capacity
0.8600
For = = 30.93 and buckling class c,
11.64
fcd = 210 MPa
So, Pd = fcdxAg = 2952.6 kN > 2139.97 kN OK

2. Rupture strength of the channel section

167
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =90mm
bs=shear lag width =w+wt-t
=90+75-13.6 = 151.4mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =150mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(90/13.6)x(250/410)x(151.4/200)
=1.168 >0.7
<1.44

Tdn=0.9x{7.8x(300-3x22-13.6)} x410/1.25+1.168x{2x(90-7.8/2)x13.6}250/1.1
= 1129.158KN >1141.59KN (2283.18/2=1141.59KN) OK

Member U3-L4
Axial force = 505.25 KN (T)
No. of bolts= 505.25 x10^3/(2x78478.4)
=4
Provide 4 bolts
Try with angle section 4-ISA 55x55x8
Check:
Rupture strength of a single angle connected through one leg and affected by
shear lag is given by
Tdn=0.9xAncxfu/ m1+xAgoxfy/ m0
Where =1.4-0.076x(w/t)x(fy/fu)x(bs/Lc)
but 0.7 (fux m0)/(fyx m1)
in which
w= width of outstanding leg =55
bs=shear lag width =w+wt-t
=55+30-8 = 77mm
Lc=length of end connection, i.e., distance between the outermost bolts or length of the weld along the
direction of load =100mm
Anc=net sectional area of the connected leg
Ago=gross area of the outstanding leg
t=thickness of the angle
=1.4-0.076x(55/8)x(250/410)x(77/100)
=1.155 >0.7
<1.44

168
Design of Bridge Over Kerunga Khola, Chitwan 2069 AB Bridge

Tdn= 0.9x {8x(55-22-8/2)} x410/1.25+1.155x{8x(55-4)}250/1.1


= 175.58KN < 126.313KN (505.25 /4=126.313KN) safe

2. Design strength due to yielding of gross section:


Tdg=Agxfy/ m0
Ag=gross area of the cross section
= 4x818+300x12 (size of plate may be reduced)
=6872 mm2
fy= 250 Mpa
m0=partial safety factor for the yielding =1.1
Tdg=6872x250/(1.1x1000)
=1561.81 KN >505.25 KN ok
3. Block failure
The block shear strength of a bolted connection is the least of
Tdb=Avgxfy/(m0x3)+0.9xAtnxfu/m1
Or =0.9xAvnxfu/(m1x3)+ Atgxfy/m0
Avg=50x2x8 =800 mm^2
Avn=(50x2-1.5x22)x8 =536 mm^2
Atg=25x8 =200 mm^2
Atn=(25-22/2)x8 =112 mm^2
Tdb={800x250/(1.1x3)+0.9x112x410/1.25}x4/1000 =552.14KN
Or ={0.9x536x410/(1.25x3)+250x200/1.1}x4/1000 = 547.23 KN
Least Tdb=547.23 KN> 505.25 KN safe

169

Das könnte Ihnen auch gefallen