DISTRICT : SRIKAKULAM
CIRCLE : SRIKAKULAM
DIVISION : TEKKALI
SUB-DIVISION : ICHAPURAM
MANDAL : KAVITY
NMENT OF ANDHRA PRADESH
Est.Cost.Rs.3.00 lakhs
As per the instructions of the instructions of the Dy.Exe.Engineer,PR,Ichapuram and as per the
request of the Hon'ble MLA,Ichapuram,an estimate is prepared for "Construction of Indore Stadium at Kavity"
with an estimated amount of Rs.3.00 lakhs
1.Construction of 7.50X11.70m size room with AC sheet roofing over Steel truss with 5.50m height
The estimate is prepared as per the current SSR,i.e.2004-2005 rates and the work will be carried
out as per APDSS after obtaining administrative sanction
Est.Cost:Rs.3.00 lakhs
TOTAL 3.00
Asst.Executive Engineer
PR(spl),Ichapuram
LS------------
DETAILED-CUM-ABSTRACT ESTIMATE
Est.Cost:Rs.3.00 lakhs
2 Cement Concrete(1:4:8) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
3 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for beams,Columns.Pedastals
4 R.R.Masonry in CM(1:6) using Rough stone(OTG) including cost and conveyance of all materials
and all labour charges etc.
5 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for plinth beams
8 Brick Masonry in CM(1:6) using 2nd class Bricks including cost and conveyance of all materials
and all labour charges etc.
11 Plastering with CM(1:5) 12mm thick including all materials and all labour charges etc.complete
for Brick masonry
12 Flooring with CC(1:6:10) 80mm thick,CC(1:2:4) 40mm thick and top finished with CM(1:3) 7mm thck
including all materials and all labour charges etc.complete
For room 1X1 5.27 3.00 ---- 15.81Sqm 1175.81 10Sqm 1859
13 Cost,supply and fabrication charges of steel including cost of binding wire and all labour
charges etc.complete
TOTAL 98985
C.L
7.5 11.1
0.46 0.46
7.96 11.56 39.04
-0.46 -0.23
7.5 11.33 37.66
DATA SHEET
Est.Cost.Rs.3.00 lakhs
1 Earth work exacavation and depositing on the bank with an initial lead and lift for loamy and clayey
soils as per SS-20B by manual labour
2 Sand filling in foundations including watering and ramming including cost and conveyance of all materials
and all labour charges etc.complete
4 Cement Concrete(1:6:10) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
5 Cement Concrete(1:4:8) mix using 40mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
6 CC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
7 RCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing charges
8 R.R.Masonry in CM(1:6) using Rough stone(OTG) including cost and conveyance of all materials
and all labour charges etc.
9 Brick Masonry in CM(1:6) using 2nd class Bricks including cost and conveyance of all materials
and all labour charges etc.
10 Plastering with CM(1:5) 20mm thick including all materials and all labour charges etc.complete
11 Plastering with CM(1:5) 12mm thick including all materials and all labour charges etc.complete
12 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for beams,Columns.Pedastals
13 VRCC(1:2:4) mix using 20mm HBG chips including cost and conveyance of all materials
and all labour charges including machine mixing and vibrating charges but excluding cost and
fabrication charges of steel for plinth beams&lintels
S.No Quantity Description of item Rate Per Amount
1.00Cum Cost of RCC(1:2:4) 2318.06 1.00Cum 2318.06
1.00Cum Centring charges 561.00 1.00Cum 561.00
Add TOT@4% 115.16
TOTAL 2994.22
14 Flooring with CC(1:6:10) 80mm thick,CC(1:2:4) 40mm thick and top finished with CM(1:3) 7mm thck
including all materials and all labour charges etc.complete
15 Cost,supply and fabrication charges of steel including cost of binding wire and all labour
charges etc.complete
S.No Description of item Name of the quarry Lead in Kms Initial Conveyance Seinorage Blasting Muncipal Deduct Total
MR CT Total Cost charges Border stacking
Allowance
1 Sand for filling Bahuda river 7.80 0.00 7.80 28.00 94.90 36.00 0.00 0.00 (-)3.70 155.20
2 Sand for Mortar Bahuda river 7.80 0.00 7.80 71.00 94.90 36.00 0.00 0.00 (-)3.70 198.20
3 40mm HBG metal-SS5 Rattakanna 18.10 0.00 18.10 269.00 148.00 45.00 53.00 0.00 (-)6.10 508.90
4 20mm HBG metal-SS5 Rattakanna 18.10 0.00 18.10 470.00 148.00 45.00 53.00 0.00 (-)6.10 709.90
5 Bricks Local 0.00 0.00 0.00 1250.00 0.00 0.00 0.00 0.00 (-)0.00 1250.00
6 Rough stone(OTG) for RR Rajapuram 5.20 0.00 5.20 92.50 103.10 45.00 0.00 0.00 (-)6.10 234.50
Masonry
1.Certified that the above leads are correct to the best of my knowledge
Kavity
Quarry
3/5 Rajapuram
227/2
1.5Km
Quarry
Rattakanna
5.73
Beams 0.23X0.23
Beams 0.23X0.23
ROOM
3.23 (3.00x3.00m size) Varandah(3.00X2.50m)
Columns 0.23X0.23
PLAN
Asst.Exe.Engineer Deputy.Exe.Engineer
PR,Ichapuram PR,Ichapuram
ommunity Hall at Kesaripada