Forming of Formworks
G D,E 10 16 26 31 41 15
and Scaffoldings
Positioning of steel
H E,F 15 31 46 31 46 0
reinforcement
Plumbing and Water
I D,E 15 30 45 30 45 0
Pipe connections
J Dummy - 0 0 0 0 0 0
Pouring of Footing and
K H,G 5 36 41 36 41 0
Column
L Removal of Forms K 1 37 38 37 38 0
CHB Laying and
M K 15 51 66 51 66 0
Backfilling
Ground Leveling for
N K 10 46 56 46 56 0
Floor Slab
Pouring of concrete for
O N 8 54 62 54 62 0
floor slab
P Dummy - 0 0 0 0 0 0
Positioning of steel
Q reinforcement for 2nd O 20 74 94 74 94 0
floor
Forming of formworks
R and scaffolding for 2nd O 10 64 74 74 84 10
floor
Plumbing and Water
S Pipe connections for 2nd O 15 69 84 84 99 15
floor
Pouring of concrete for
T Q,R 10 84 94 139 149 55
2nd floor flor slab
Pouring of concrete for
U T 10 94 104 94 104 0
2nd floor clolumn
V CHB Laying for 2nd floor U 15 109 124 109 124 0
W Dummy - 0 0 0 0 0 0
Roof framing and Roof
X V,U 9 118 127 119 128 1
sheets
Y Construction of staircase U 3 97 100 97 100 0
EE Final work and Cleaning DD, CC, BB, AA 3 147 150 147 150 0
Critical Path:
A-D-F-H-H-K-N-O-Q-T-U-V-Z-DD-EE = 150 days
3+1+15+15+5+10+8+10+10+10+15+15+20+3= 150 days
List of Work
LIST ACTIVITIES PREDECESSOR DURATION
A Clear Lot - 3
D Delivery of Materials A 1
E Excavation C 5
3 11
B-1 L-1 R-10
1 2 5 8 9 10 13 14 15
9
4 6 12
I-15
Legend:
Predecessor
Dummy
A (Letter)- 1 (Number) Activities- Duration
17w 18w 19w 20w 21w 22w 23w 24w 25w 26w 27w 28w 29w 30w
18
Y-3
16 17 19 20 22 23
16 22
21
X-9 CC-5
22
AA-5
22
BB-5
BAR CHART (MANPOWER)
12
11 10 10 10 10
10
9 E
O
8 7 7
7 N
MANPOWER
6 F 5 5
D K T
5 H Q
4 3 C G R
3 L M
2 A B I S
Legend:
A (letter) : Activities
1 : No. of men
12
11
10 10
9 Z
V X
U
DD
EE
AA
Y
CC
BB
18w 19w 20w 21w 22w 23w 24w 25w 26w 27w 28w 29w 30w
ACTIVITIES WITH MANPOWER LIST
COST (500/PERSON)
10 19,000.00 177,500.00
11 25,000.00 202,500.00 400,000.00
12 17,500.00 220,000.00
13 12,500.00 232,500.00
14 12,500.00 245,000.00 300,000.00 TCL
15 12,500.00 257,500.00
16 20,000.00 277,500.00
17 25,000.00 302,500.00 200,000.00
18 25,000.00 327,500.00
19 25,000.00 352,500.00
20 23,500.00 376,000.00 100,000.00
21 22,500.00 398,500.00
22 22,500.00 421,000.00
23 25,500.00 446,500.00 0.00
24 27,500.00 474,000.00 0 5 10 15 20 25 30 35
25 27,500.00 501,500.00
26 29,000.00 530,500.00 DURATION (WEEKS)
27 30,000.00 560,500.00
28 30,000.00 590,500.00
29 30,000.00 620,500.00
30 24,200.00 644,700.00
12000