Sie sind auf Seite 1von 9

Analysis of the building shape

erected in Krakow and its impact on


construction costs
Krzysztof Zima Edyta Plebankiewicz
Section of Technology and Building Section of Technology and Building
Management , Cracow University of Management, Cracow University of
Technology, Krakow, Poland. Technology, Krakow, Poland
e-mail: kzima@izwbit.pk.edu.pl e-mail: eplebank@izwbit.pk.edu.pl

DOI 10.5592/otmcj.2012.1.6 The choice of a particular architectural solution when de-


Research paper
signing a building considerably influences the costs of its
construction. The article presents the methods of evaluating the
degree of complexity of the building shape. On the basis of factors
specifying building shape complexity an analysis of multi-family
buildings in Krakow was conducted. The analysis concerned 40 build-
ings constructed by developers who received their building permit
in the years 2004-2005, and for comparison 30 buildings whose
building permit was issued in the second half of the year 2010. The
study also included the way the grounds were used for the analysed
constructions. The result of the research revealed a slow growth in
the use of plots for building investments in Krakow.

Keywords Introduction
Cost of building, building The choice of a particular architectur- basis of factors specifying build-
shape, multifamily al solution when designing a building ing shape complexity an analysis of
buildings considerably influences the costs of multi-family buildings in Krakow was
its construction (Ferry and Brandon, conducted. The analysis concerned
2007). Generally speaking, the more 40 buildings constructed by devel-
complex the form of the horizontal opers who received their building
projection is, the greater expendi- permit in the years 2004-2005, and
tures for the construction must be 30 buildings whose building permit
paid. One of the reasons is the fact was issued in the second half of the
that the shape of the building influ- year 2010. The aim of the article is to
ences significantly the number of assess the degree of building shape
such construction elements as foun- complexity of Krakows buildings and
dations, walls, ceilings or the roof to compare the changes in building
(Ashworth, 2004). design which could be observed dur-
ing the recent years. The study also
The article presents the basic meth- included the way the grounds were
ods of evaluating the degree of com- used for the analysed constructions.
plexity of the building shape. On the

K. Zima E. Plebankiewicz Analysis of the building shape erected in Krakow and its impact on ... pp 411-419 411
Methods of evaluating Outer partitions, both vertical and tion surface or its cubic capacity is as
the degree of building horizontal, are relatively expensive small as possible, so when designing
complexity elements of the building. Outer walls a low-cost building one should avoid
The evaluation of the buildings con- include in their costs the supporting cross-, letter-L-, letter-T- or letter-H-
struction costs at the design stage walls and curtain walls, plumb lines, shaped buildings.
has a decisive influence on the deci- insulation, outer facing and inner ve-
sions made at subsequent stages. In neer. Then how the complexity (or simplic-
literature one may find a number of ity) of building shape should be meas-
factors deciding on the construction The conclusion is that the smaller the ured? The coefficient specifying the
costs. Kouskoulas and Koehn (1974) surface of the building and the more layout of the building should consist
identified the following independent compact the block of the building is, of variables which have a significant
variables specifying the costs of con- the more advantageous the layout influence on construction costs and
structing a building: location, year of of the building is, as far as construc- are known already at the concept
construction, building type, building tion costs are concerned. A general stage. Such variables may include,
height, building quality and construc- rule says that the simpler the building for example, the above mentioned
tion technology. Brandon (1978) pro- shape is, the lower the unit costs are key factors influencing building costs:
posed using a building shape index, (Selley, 1983). A building of a simple building perimeter and the surface of
the number of storeys, the inner divi- shape has fewer outer walls surround- the building projection. Other factors
sion of the building area coefficient, ing the floor area and a smaller number connected with building shape which
the average height of the storey, the of ceilings. Building shape has, then, influence building costs, that is the
coefficient specifying the percentage a great influence on the total costs of number of right angles, the length of
of the glass area and the compact- construction. This effect concerns not the longer side of the building perim-
ness of the block. Karshenas (1984) only the outer but also the inner load- eter, the sum of all inner angles, etc.
added one more factor to these given bearing walls and partition walls. The are of a slightly lesser importance.
by Brandon, namely the area of the layout of these walls often depends It is necessary to observe that the bulk
construction site. Swaffield and Pas- on the layout of the outer support- of the research into this issue presents
quire (1996) suggested the following: ing walls. The improved layout of the sophisticated methods of evaluating
the percentage of the glass area, the building block makes it possible to im- a buildings construction costs which
length of the building perimeter, the prove the layout of flats and corridors. take into consideration not only the
buildings total height, the volume This should also enhance the relation shape but also other factors, which
measure of the rooms and techni- between the living area and the com- are not included in the present discus-
cal corridors, the volume measure of munication area. Thus one can assume sion. These methods are based on a
the area used up by heating systems, that a square- or rectangle-shaped complicated mathematical apparatus
ventilation and air conditioning. Son- building has the best building layout and are hard to apply. Therefore, for
mez (2004) in his regression model coefficient (Staedman et al., 2009; the estimation of building shapes the
describing the key factors influencing Wing, 1999). authors use the factors proposed by
building shape included: construction Brandon (1978) and Kouskoulas and
timing, locations, the area of the con- Therefore one may ask whether the Koehn (1974).
struction site, the percentage of the shape and size of the building influ-
shared areas, the total area, and the ence energy efficiency. A building los- The example coefficients specifying
number of storeys. It is worth noting es the most of heat through walls and the complexity (or simplicity) of build-
that these studies, except Kouskoulas roof, so the less complex its shape and ing shape include:
and Koehns research, consider build- the more compact its block are, the 1. W/F (Wall to Floor) index
ing shape and its derivatives, such as lower the heat loss is (fewer thermal 2. LBI (Length/Breadth Index) index
building perimeter and the construc- bridges and, generally, smaller con- 3. PSI (Plan/Shape Index) index
tion site area, as key factors influenc- tact area with the surroundings) (Zima, 4. Cooks JC (Cookes JC shape
ing the costs of constructing a build- 2008). Consequently, an energy ef- efficiency) index
ing. Evaluation of the degree of build- ficient building should be designed 5. POP (Perimeter Over Plan) index
ing shape complexity is, therefore, a on the plan of the square or a not very 6. building planning m index
crucial decision element which sig- elongated rectangle. It is crucial that 7. VOLM (Volume - block
nificantly influences the costs of con- the relation between the outer parti- compactness) index
struction and the cost of building use. tions surface and the building projec- 8. Optimum envelope area

412 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 4 (1)2 012
The W/F index (Brandon, 1978) The Cooks JC shape effectiveness in- Considering technology and realiza-
The W/F index (Wall/Floor Ratio) spec- dex (Kouskoulas and Koehn, 1974) tion costs it is assumed that the most
ifies the ratio between the wall sur- The JC index uses the relation be- economical solutions take the index
face and floor surface. It is assumed tween the perimeter and the surface approximating (but not smaller than)
that the smaller the indexs value is, of the building, and is expressed in 4.
the lower the construction costs will the following way:
be. The shape generating the small- VOLM (block compactness) index
L (Brandon, 1978)
est cost is the square, for which the JC = 1
indexs value is 0. The W/F index is In the case of this index the point
4 F of reference is the shape of a hemi-
expressed by the following formula:
where: L building perimeter calcu- sphere. When specifying the block
W L Ls lated from the contour of the outer compactness of a building one takes
= 100% walls, F the surface of the building into consideration three dimensions
F Ls projection. of the object. The VOLM index is de-
where: L building perimeter calcu- picted by this formula:
lated from the contour of the outer The POP (plan compactness ratio) in-
2
walls, Ls perimeter of the square of dex (Brandon, 1978)
1

the same surface as the building be- In this method the point of reference
3K
3
2x
ing compared. is the shape of the circle, which has
the smallest ratio between the cir-
2
The LBI index (Brandon, 1978) cumference and the surface of the

VOLM =
The LBI index (the Length/Breadth building. For the circle the POP factor
F
Index) assumes that every shape of is 1. The lower the indexs value is the
the building projection is reduced to more complex the building shape will where: K the volume measure of the
a rectangle with the same surface and be. The POP index is depicted by the building, F the surface of the build-
perimeter. For a square the factor has following formula: ing projection.
value 1. The greater the value is, the
more complex shape the building will 2 F Outer walls (their number is speci-
have. The LBI index is expressed by POP = fied in the formulas above by L) are
the following formula: L a costly element, so each change in
The building planning m index the shape of the building causing
L + L 16F
2
(Kouskoulas and Koehn, 1974) the increase in the number of outer
LBI = Since the results of using the various walls per the building projection sur-
L L 16F
2
methods employing the ratio between face unit F will cause the increase of
where: L building perimeter calcu- the building perimeter calculated construction costs. The higher the
lated from the contour of the outer from the contour of its outer walls (L) value of the indexes specified in 1),
walls, F the surface of the building and the surface of the building projec- 2), 3) and 5) and the lower for formula
projection. tion (F) are similar, the methods can 4), the greater the complexity of the
be simplified by using this formula: shape of a building and so are the
The PSI index (Brandon, 1978) construction costs. In the case of the
The PSI index (Plan/Shape Index) is a L VOLM index, the authors assumed a
m=
development of the LBI index and is cube as an optimal solution, thus the
expressed by the following formula:
F optimal value of the block compact-
The m index may take the following ness coefficient is 3.84, which con-
values: stitutes a nominal value one should
G + G 16R
2

PSI = m = 3.54 for a circle strive for. All the values taken by the
m = (3.54 ; 4) for elliptical shapes block compactness coefficient higher
G L 16R
2

m = 4 for a square or lower than 3.84 indicate a greater


where: G the sum of outer perime- m > 4 the remaining rectangular complexity of the block.
ters of each floor divided by the num- and other shapes.
ber of floors, R the gross surface
divided by the number of floors.

K. Zima E. Plebankiewicz Analysis of the building shape erected in Krakow and its impact on ... pp 411-419 413
Evaluation of residential few percent of all new constructions. provides information about the basic
investments undertaken in The characteristic features of the material from which walls (W) and
Krakow analysed multi-family buildings can ceilings (C) were designed.
The study concerned 40 multi-family be found in Table 2. The table also
buildings constructed by developers
VM NoS AB UA AS L
in Krakow for whom building permits
W C
were granted in 2004-2005, and for No.
[m3] [items] [m2] [m2] [m2] [m]
comparison 30 multi-family build- 1 2 3 4 5 7 9 10
ings for which building permits were 1 MAX M 1307.4 2 211.3 282.5 772.0 75.4
given in the second half of the year 2 P M 6850.4 3 626.5 1325.2 904.0 160.0
2010. The study used the records 3 P M 1524.5 3 276.2 559.4 745.0 60.0
from the Office of the City of Krakow, 4 S F 5509.3 3 650.0 2065.7 2317.3 118.3
Faculty of Architecture and Urban 5 S F 5509.3 3 650.0 2065.7 2317.3 118.3
Planning. The authors analysed the 6 S F 5509.3 3 650.0 2065.7 2317.3 118.3
degree of building shape complex- 7 S F 5509.3 3 650.0 2065.7 2317.3 118.3
ity employing the formulas described 8 Ce M 8925.0 3 615.5 1968.8 2215.0 140.0
above, and the way the grounds were
9 Ce M 8044.4 3 619.5 1774.5 2215.0 140.0
used.
10 P M 8471.4 3 1154.6 2398.9 3790.0 153.2
11 P M 8471.4 3 1154.6 2398.9 3790.0 153.2
Description of the investments 12 MAX F 10416.0 3 1195.5 2468.0 6424.5 195.0
with building permits issued in 13 MAX F 10351.0 3 1195.5 2462.9 6424.5 192.0
2004-2005 14 P M 5017.7 4 540.0 1533.4 2440.0 142.0
The analysis concerns 40 multi-
15 P M 5606.0 4 374.0 1161.0 894.0 120.0
family buildings constructed in
16 P M 14514.0 4 1220.1 3074.6 4159.0 156.6
Krakow, which received building
17 P M 1687.0 4 198.5 530.3 787.0 76.9
permits in 2004-2005. The
18 MAX M 13727.0 4 1001.6 3650.5 3942.0 141.9
distribution of the survey sample
19 S M 3150.0 4 244.4 710.5 670.0 63.9
grouped according to the number
20 S M 10133.2 4 896.5 2857.3 3862.0 159.5
of the above-ground storeys is
21 K3 M 13396.5 4 1109.5 3275.2 6336.0 200.0
presented in Table 1.
22 Ce M 12396.4 4 800.0 2734.5 4950.0 180.0
Survey sample 23 P M 6451.0 5 586.5 1994.0 4136.0 155.0
Number of Number of 24 Ce M 10927.6 5 629.0 2410.5 2215.0 150.0
No. %
buildings storeys
25 S M 25903.8 5 1442.1 7359.0 6452.0 242.8
1 1 2.4% 2 26 P M 11427.0 5 842.6 3213.3 5200.0 162.5
2 12 29.3% 3
3 9 22.0% 4 27 P M 10686.0 5 787.2 2977.5 4920.0 166.2
4 6 14.6% 5 28 P M 2325.0 5 155.0 1058.9 485.0 49.8
5 3 7.3% 6
29 S M 24670.0 6 1106.0 6272.5 5041.0 168.0
6 1 2.4% 7
7 1 2.4% 8 30 Ce M 31000.0 6 1090.2 5726.0 8860.0 183.5
8 5 12.2% 9
31 S M 27050.0 7 1106.0 6880.5 5041.0 183.5
9 1 2.4% 11
10 2 4.9% 12 32 FC F 33765.9 8 1075.0 8548.4 3707.0 217.6
33 K3 M 51266.2 9 2544.7 11457.0 9606.0 210.9
Source: Kozik and Zima, 2007, 2008.
34 P M 14361.4 9 582.9 4230.1 2318.4 107.6
Table 1. Distribution of buildings
35 P M 31331.2 9 1184.5 8689.2 4636.9 184.2
grouped according to the number of
the above-ground storeys 36 P M 27516.4 9 1113.8 8141.0 4636.9 184.2
37 P M 14361.4 9 582.9 4230.1 2318.4 107.6

As Table 1 reveals, in the analysed 38 P M 34790.0 11 2079.7 9938.4 12495.0 223.0

period of time the greatest number of 39 P M 23150.0 12 519.5 6196.7 6657.6 104.9
new buildings included those with 3 40 P M 24680.0 12 562.5 6680.7 6700.0 111.5
and 4 storeys. Those with 5 and 9 sto- Source: Kozik and Zima, 2007, 2008
reys constitute several percent of new Table 2. Information about multi-family buildings constructed in Krakow
buildings. Other buildings make up a (building permit 2004-2005)

414 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 4 (1)2 012
VM volume C ceilings Lp W/F LBI JC POP m VOLM
measure Ce ceramics
L perimeter AB area of best value 0 1 0 1 4 3.84
K3 K3 brick building site 1 1.17 4.50 0.30 0.68 5.19 2.17
NoS number of S silikat 2 2.16 8.09 0.60 0.55 6.39 2.21
storeys FC ferroconcrete
3 1.27 3.90 0.24 0.71 4.96 1.84
W walls UA usable area
MAX air-brick P porotherm 4 1.72 3.06 0.16 0.76 4.64 1.84
MAX F filigree 5 1.72 3.06 0.16 0.76 4.64 1.84
AS area surface M monolithic
6 1.72 3.06 0.16 0.76 4.64 1.84
Table 2 shows that the most popu- 7 1.72 3.06 0.16 0.76 4.64 1.84
lar materials for vertical partitions 8 1.96 5.79 0.41 0.63 5.64 2.68
in the analysed period of time were 9 1.96 5.74 0.41 0.63 5.62 2.49
breeze-blocks Porotherm (47.5%), si- 10 2.09 2.71 0.13 0.79 4.51 1.38
likats (22.5%), ceramics (12.5%) and 11 2.09 2.71 0.13 0.79 4.51 1.38
the MAX air-bricks (10.0%). Ceilings 12 2.49 5.78 0.41 0.63 5.64 1.53
were mostly monolithic (82.5%) and 13 2.46 5.53 0.39 0.64 5.55 1.52
filigree panels (17.5%) which allow to 14 1.98 7.20 0.53 0.58 6.11 2.08
form rooms freely as there is no need 15 1.74 7.49 0.55 0.57 6.21 3.24
to use supporting ribs under walls 16 2.13 2.65 0.12 0.79 4.48 1.87
and partition walls, like in the case of 17 1.19 5.26 0.36 0.65 5.46 2.74
suspended beam and block floor. The 18 1.98 2.65 0.12 0.79 4.48 2.20
analysed buildings have the volume 19 1.00 1.52 0.02 0.87 4.09 3.37
measure from 1 000 m2 to over 50 000 20 2.16 4.89 0.33 0.67 5.33 2.00
m2. Buildings of 600 m2, 600-1 000 21 2.54 6.87 0.50 0.59 6.00 1.95
m2 and 1 000-2 000 m2 constitute 22 2.35 8.00 0.59 0.56 6.36 2.57
about 30% of the analysed construc- 23 2.11 8.12 0.60 0.55 6.40 2.27
tions. Buildings with the surface big- 24 2.06 6.80 0.50 0.59 5.98 3.00
ger than 2 000m2 make up no more 25 2.90 8.10 0.60 0.55 6.39 2.33
than 5%. 26 2.19 5.66 0.40 0.63 5.60 2.31
Table 3 shows the distribution of 27 2.22 6.62 0.48 0.60 5.92 2.37
the values of some chosen indexes 28 0.76 1.01 0.00 0.89 4.00 4.35
evaluating the complexity of building 29 2.24 4.14 0.26 0.70 5.05 2.94
shape. 30 2.39 5.54 0.39 0.64 5.56 3.47
31 2.39 5.43 0.38 0.64 5.52 3.13
In Table 3 the numbers in bold are 32 2.69 8.90 0.66 0.53 6.64 3.73
those coefficients which are consid- 33 2.63 1.82 0.05 0.85 4.18 2.08
ered the most advantageous. For W/F 34 1.59 2.58 0.11 0.80 4.46 3.89
index these are the values of up to 35 2.39 4.96 0.34 0.66 5.35 3.22
1.00 found only in 2 buildings. The 36 2.39 5.43 0.38 0.64 5.52 3.14
LBI index of up to 2.00 value is con- 37 1.59 2.58 0.11 0.90 4.46 3.89
sidered advantageous and character- 38 2.73 3.71 0.22 0.72 4.89 1.97
izes only 3 buildings. Also 3 buildings 39 1.56 2.96 0.15 0.77 4.60 6.00
have the advantageous JC index of 40 1.64 3.21 0.18 0.75 4.70 5.78
the value up to 0.10. The most advan-
tageous values of the POP index are Source: authors own data
those between 0.80 and 1.00, pos- Table 3. Coefficients evaluating the shape of the buildings with building per-
sessed by 5 buildings. Almost 60% mits issued in 2004-2005
(58.54%) of the analysed buildings
have the m index greater than 5 which shape which can be considered ideal. can be thought as possessing a sim-
indicates a considerably high degree The analysis of the VOLM index whose ple shape. Yet none of the buildings
of shape complexity, as well as high values of 3.50-4.00 indicate minimal considered simple according to the
costs of construction and later use. complexity of the building block re- surface criterion cannot be thought
Only 9.76% of the buildings has the veals that only 7.32% of the buildings as such according to the VOLM index.

K. Zima E. Plebankiewicz Analysis of the building shape erected in Krakow and its impact on ... pp 411-419 415
Description of the W C
VM NoS AB UA AS L
investments with building No. [m3] [szt.] [m2] [m2] [m2] [m]
permits issued in 2010 1 2 3 4 5 7 9 10
The next analysis concerned 30 multi- 1 S M 10442.9 5 (6) 499.3 2658.7 1365.0 126.8
family buildings constructed in Kra- 2 nd nd nd 4(5) 314.6 1132.6 1049.0 71.9
kow which received building permits 3 M M 25449.7 11(12) 828.2 5055.1 3229.3 146.2
in the second half of the year 2010. 4 P M 3355.7 5(7) 783.2 348.3 1410.2 123.5
The distribution of the survey sam- 5 P M 4311.0 5(7) 625.5 575.8 1410.2 118.4
ple grouped according to the number 6 P M 4168.2 5(7) 611.2 512.2 1410.2 118.4
of the above-ground storeys is pre- 7 P M 37883.0 9(11) 1289.5 10577.6 2882.0 218.5
8 M M 28140.3 7(8) 943.2 6613.2 2893.8 144.9
sented in Table 4. The characteristic
9 M M 25115.4 7(8) 841.7 5902.3 2893.8 133.8
features of the studied multi-family
10 Y M 5257.2 4(5) 445.3 nd 7158.0 92.6
buildings are shown in Table 5.
11 Y M 5675.2 4(5) 469.1 nd 7158.0 91.1
12 Y M 8393.0 4(5) 520.4 nd 2808.8 102.7
Survey sample
13 Y M 10273.0 4(5) 611.3 nd 3299.8 128.9
No. of No. of
No. % 14 Y M 8089.0 3(4) 560.7 nd 3026.4 111.1
buildings storeys
1 0 0.00% 2 15 Y M 8650.0 3(4) 564.2 nd 3045.0 121.3
2 4 13.33% 3 16 Y M 5551.0 3(4) 395.8 nd 2135.9 86.9
3 8 26.67% 4 17 M M 8643.3 6(7) 464.1 2376.1 5829.0 91.1
4 7 23.33% 5 18 M M 4339.7 6(7) 1850.1 8299.3 nd 295.2
5 5 16.67% 6 19 M M 4410.3 8(9) 1702.1 8432.2 nd 210.1
6 3 10.00% 7 20 M M 2411.5 6(7) 1039.1 4471.8 nd 160.0
7 1 3.33% 8 21 M M 2141.7 6(7) 923.0 3893.0 nd 151.0
8 1 3.33% 9 22 P M 11197.3 5(6) 761.8 3532.4 1406.1 156.8
9 0 0.00% 11 23 P M 4392.9 4 305.7 1320.0 3662.0 114.8
10 1 3.33% 12 24 P M 13483.4 5(6) 856.6 3394.6 2528.8 189.4
25 P M 13532.5 5(6) 859.8 3411.9 2538.0 190.1
Source: authors analysis of the data from
the Office of the City of Krakow, Faculty of 26 P M 10235.1 4(5) 803.4 2528.2 2371.6 186.3
Architecture and Urban Planning 27 P M 10912.7 4(5) 856.6 2712.7 2528.6 187.3
Table 4. Distribution of buildings 28 Y M 760.0 3(3) 123.0 165.1 910.0 47.0
grouped according to the number of 29 M M nd 6(7) 501.8 2 35.9 1890.0 106.5
the above-ground storeys 30 H M nd 7(7) 482.7 nd 1672.3 107.6
VM volume measure L - perimeter P porotherm
NoS number of: above-ground AB area of building site S silikat
storeys (above + below ground UA usable area Y Ytong blocks
Materials most frequently used for storeys) W walls H H+H blocks
AS area surface C ceiling M - monolithic
vertical partitions are breeze blocks
nd no data
Porotherm (33.3%), poured concrete
monolithic walls (30%) and Ytong Source: authors analysis of the data from the Office of the City of Krakow, Faculty of
blocks (26.7%). Ceilings are largely Architecture and Urban Planning
monolithic (96.6%, in one case there Table 5. Data describing multi-family buildings constructed in Krakow (build-
was no data) . The other data in Table ing permits in 2010)
5 describing the buildings under con-
struction are the surface and cubic the JC and POP. Precisely 43.33% of simple shape. As previously, none of
coefficients. the analysed buildings has the co- the buildings considered simple ac-
Table 6 reveals the distribution of the efficient value greater than 5. Only cording to the surface criterion pos-
values of some chosen indexes evalu- 13.33% has the shape which can be sesses a simple shape when analysed
ating the degree of building shape considered very good. As far as the according to the VOLM index.
complexity. VOLM index is concerned, assum- Figures 1a, 1b, 1c depict the influence
ing the same range of complexity as of the change in the building shape
Only one building has the advanta- before, i.e. values between 3.50 and and, consequently, the change in the
geous value of the W/F index. 4 build- 4.00 indicating a building block as factors evaluating building shape and
ings are marked by the LBI index also simple, only 11.11% of the analysed construction costs, as shown in Table
considered advantageous and 7 by buildings can be thought to have a 5.

416 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 4 (1)2 012
lp W/F LBI JC POP m VOLM The construction costs of individual
best value 0 1 0 1 4 buildings presented in Table 5 were
1 1.81 5.88 0.42 0.62 5.67 3.67 calculated in the investors cost esti-
2 1.12 1.38 0.01 0.88 4.05 nd
mates by means of a simplified tech-
3 2.02 4.22 0.27 0.70 5.08 4.01
nique. Having compared the construc-
4 1.78 2.46 0.10 0.80 4.41 1.10
tion costs of 1 m2 and the building
5 1.72 3.30 0.18 0.75 4.74 1.63
shape factors presented in Table 6,
6 1.72 3.45 0.20 0.74 4.79 1.63
one observes a tendency in the build-
7 2.70 7.11 0.52 0.58 6.08 3.36
ing shape changes depending on the
8 2.01 3.25 0.18 0.75 4.72 3.77
changes of individual factors. Thus
9 1.89 2.98 0.15 0.77 4.61 3.91
altering the values of the JC and POP
10 1.41 2.39 0.10 0.81 4.39 2.61
by 0.1 (e.g. from 0.3 to 0.4) changes
11 1.39 1.89 0.05 0.84 4.20 2.60
construction costs to 3.8% and 7.6%
12 1.53 2.69 0.13 0.79 4.50 3.05
respectively (Figure 1a). In the case
13 1.84 4.58 0.30 0.68 5.21 2.97
of the m, LBI and W/F, altering one of
14 1.64 3.19 0.17 0.76 4.69 2.76
these factors by 1 causes the growth
15 1.75 4.29 0.28 0.69 5.11 2.87
in costs by 0.9%, 3.3% and 4.4% (Fig-
16 1.33 2.35 0.09 0.81 4.37 3.04
ure 1b). Finally, altering the VOLM
17 1.39 1.96 0.06 0.84 4.23 3.48
factor by 0.5 increases construction
18 3.30 9.67 0.72 0.52 6.86 0.55
costs by 4.4%.
19 2.62 4.25 0.27 0.70 5.09 0.61
20 2.16 3.90 0.24 0.71 4.96 0.66
21 2.07 3.92 0.24 0.71 4.97 0.69
The intensity of built-up
22 2.13 5.90 0.42 0.62 5.68 2.52 areas
23 1.68 8.67 0.64 0.54 6.57 3.37 Evaluation of the way a building site
24 2.44 8.35 0.62 0.55 6.47 2.54 was used can be conducted as an in-
25 2.45 8.39 0.62 0.55 6.48 2.54 dex of intensity of built-up areas. It
26 2.41 8.69 0.64 0.54 6.57 2.25 is understood as an index specifying
27 2.42 8.12 0.60 0.55 6.40 2.20 the relationship of the total building
28 0.71 1.99 0.06 0.84 4.24 2.60 site area on a certain location to the
29 1.58 3.35 0.19 0.75 4.76 nd size of the land of that location. For
30 1.59 3.72 0.22 0.72 4.90 nd Polish norm PN ISO 9836 total build-
Source: authors own data
ing site area is defined as the area
Table 6. Coefficients evaluating the shapes of the buildings for which permits taken up by the completed building
were granted in 2010 and is specified by a vertical drop of
the outer edges of the building on the
area surface.
The area of a building site does not
include the following:
the surface of buildings or their
parts situated below the ground;
the surface of secondary elements,
such as outer stairs, outer ramps,
canopies, awnings, roof protru-
sions or outer lighting;
the surface taken up by auxiliary
buildings, e.g. greenhouses, gaze-
boes, or sheds.
As an intensity of built-up areas index
I let us assume the relation between
the building site area Pz and the area
Figure 1a. The relationship between construction costs of the analysed of the plot P t. When analysing how
buildings and the JC and POP factors evaluating building shape. the area in Krakow has been used for

K. Zima E. Plebankiewicz Analysis of the building shape erected in Krakow and its impact on ... pp 411-419 417
building investments one notices a
small increase in its use. The average
intensity of built-up areas in the case
of buildings for which permits were
given in 2010 was 27.8%, while the
percentage in 2004-2005 was 25.2%
(Table 7).

The intensity of built-up areas index


ranged between 6.2% and 55.5% in
the case of buildings with building
permit granted in 2010, and between
7.8% and 69.3% for buildings with the
permit issued in 2004-2005. One no-
Figure 1b. The relationship between construction costs of the analysed build- tices a tendency to increase the use of
ings and the m, LB and W/F factors evaluating building shape. the building site, probably due to the
smaller number of available plots in
Krakow, the growing competition on
the building market and high prices of
estates.

Conclusions
Analysing the change in the shape of
the buildings constructed in Krakow
in the years 2004/2005 and in 2010,
a certain improvement can be noticed.
Slightly more 2010 buildings have the
most advantageous values of the LBI,
JC and POP factors. The noticeable
tendency is specified by the m index
for buildings with the 2004-2005 per-
Figure 1c. The relationship between construction costs of the analysed build- mit equal to 5.48 (58.54% of very com-
ings and the VOLM factor evaluating building shape. plex shapes) and for newer buildings
No. 2010 2004 No. 2010 2004 No. 2010 2004 with the 2010 permit 5.16 (43.33% of
1 8.3% 27.4% 15 54.2% 41.8% 29 nd 21.9% complex shapes). This gradual im-
2 25.6% 69.3% 16 33.9% 29.3% 30 44.7% 24.4% provement in the compactness of the
3 13.5% 37.1% 17 33.9% 25.2% 31 - 12.3% building block is shown by the VOLM
4 18.5% 28.0% 18 55.5% 25.4% 32 - 21.9% index.
5 18.5% 28.0% 19 44.4% 36.5% 33 - 29.0%
6 18.5% 28.0% 20 43.3% 23.2% 34 - 26.5% A slow growth in the use of plots for
7 30.0% 28.0% 21 8.0% 17.5% 35 - 25.1% building investments in Krakow is
8 6.2% 27.8% 22 nd 16.2% 36 - 25.5% noticeable, which is caused by the in-
9 6.6% 28.0% 23 nd 14.2% 37 - 24.0% creasing experience of designers, who
10 18.5% 30.5% 24 nd 28.4% 38 - 25.1% are forced by investors to maximize
11 18.5% 30.5% 25 26.6% 22.4% 39 - 16.6% the profits from the use of the plot.
12 33.9% 18.6% 26 28.9% 16.2% 40 - 7.8% The average intensity of built-up areas
13 33.9% 18.6% 27 32.6% 16.0% 41 - 84% in the case of buildings with the 2010
14 36.6% 22.1% 28 29.1% 32.0% average 27.8% 25.2% permit is 27.8%, while in the case of
Source: authors analysis of the data from the Office of the City of Krakow, Faculty of the buildings with the 2004/2005
Architecture and Urban Planning permit 25.2%. The intensity index
Table 7. The intensity of built-up areas index for multi-family building ranged between 6.2%-55.5% in the
investments in Krakow case of the buildings with the 2010

418 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 4 (1)2 012
[3] Ferry, D.J. and Brandon P.S. (2007), Cost cost estimation of building projects
permit, and 7.8%-69.3% in the case
planning of building, Wiley-Blackwell, with regression analysis and neural
of the buildings with the 2004/2005 Oxford, 8th ed. networks, Canadian Journal of Civil
permit. [4] Karshenas, S. (1984), Predesign Engineering, No. 31, pp. 677683.
cost estimating method for multistory [10] Staedman, P., Evans, S. and Batty, M.
What is even more noticeable is de- buildings, Journal of Construction (2009), Wall area, volume and plan depth
signing buildings having costs in Engineering and Management, 110(1), in the building stock, Building Research
mind, which translates into construct- pp. 7986. & Information, 37: 5, pp. 455 467.
ing buildings simpler in shape to [5] Kouskoulas, V. and Koehn, E. (1974), [11] Swaffield, L.M. and Pasquire, C.L.
decrease the costs of construction. Predesign cost-estimation function for (1996), A critique of mechanical and
Clients preferences as well as le- buildings, Journal of the Construction electrical services cost planning: existing
Division, ASCE, 100(CO4), pp. 589604. methods and published information,
gal requirements, i.e. the obligation
[6] Kozik, R. and Zima, K. (2007), Analysis Journal of Financial Management of
of preparing energy certificates for
of housing investments realized by Property and Construction, 1(3), pp. 23-41.
buildings, which has been in force
developers, Scientific Papers of Gdansk [12] Wing, C.K. (1999), On the issue of plan
since January 2009, cause greater University of Technology, No. 605, Land shape complexity: plan shape indices
care for possible loss of heat. Engineering No. LXI, Gdask, pp. 23-30 revisited, Construction Management
(in polish). and Economic, No 17, pp. 473-482.
References [7] Kozik, R. and Zima, K. (2008), Analysis [13] Zima, K. (2008), Influence of building
[1] Ashworth, A. (2004), Cost studies of and evaluation of developer projects in shape on the construction cost,
buildings, Trans-Atlantic Pubns, 4th ed. 15th Annual European Real Estate Society Scientific Papers of the Institute of
[2] Brandon, P.S. (1978), A framework Conference, ERES, UE in Krakow, Book of Building Engineering of the Wrocaw
for cost exploration and strategic cost Abstracts, Krakow 8-21, pp. 76. University of Technology No. 91, series:
planning in design, Chartered Surveyor [8] Selley, L.H. (1983), Building Economics, Studies and Materials No. 20, Technology
Building and Quantity Surveying Macmillan, London, 3rd ed. and management in construction,
Quarterly, 5(4), pp. 60-63. [9] Sonmez, R. (2004), Conceptual Wrocaw, pp. 155-162 (in polish).

K. Zima E. Plebankiewicz Analysis of the building shape erected in Krakow and its impact on ... pp 411-419 419

Das könnte Ihnen auch gefallen