HYDRO REPORT

Project Code: CEH/GHP/2017


Customer: Ghalemdi Hydro Ltd.
Job Details: Penstock Pipe & Hydro Mechanical Works

Type of Inspection: Visual Inspection Date of inspection:


Scope of work:
Piece of Inspection: Factory premises Project site Others

Welders No. :
Name of welder:
Base Material:
Type of weld: Fill Material:

Parameter Checked:
Weld Contour: Acceptable Not Acceptable
Weld Filling: UC Incomplete Acceptable Not Acceptable
Smoothness of Joint: Acceptable Not Acceptable
Surface Defects: Acceptable Not Acceptable

Remarks:

NDE Inspector Approved By Witnessed By:


Name Name Name
Level Deg. Deg.
Sign Sign Sign
Date Date Date