Sie sind auf Seite 1von 8

Budget Quotation for Malaysia External Warehouse

Please - complete and return by Tues 1st August


Locatuon: 13, Jalan Trompet 33/8, Section 33, HICOM Industrial Area, 40400,
Shah Alam, Selangor Darul Ehsan

Electrical
Install newWorks
DB board to create independent supplies for all electrical Comments
requirements within warehouse (lighting, FLT charging, Ventilation, Stretch
wrapper and A/C units). Remove risk of supply interruptions from isolation
occuring within other extents of site.
reused)
Install Cabinet and terminate large incoming cables to provide lock out & prevent
risk of electrocution, if cables made live from other area of site
Test/recommission existing 4 x external high level flood lights - allow for some
relocation to give maximum illumination of external areas (current location may
create shadowing under door canopies)
Test recommission existing internal high bay lighting and relocate switches to
doorways/office area
Install 2 x Double strip fluorescent tubes under each door canopy (4 units total)
Install 3 x Ventilation fans into existing openings, and removed external ductwork
to improve air flow.
Provide new single phase power supply to Stretch wrapper location
Provide new 3 phase power supply for future FLT charging
Provide additional 10 x double sockets at various location around warehouse
walls (internal)
Provide Power supplies to 3 x 2.5 HP air con units
Provide 10 x double sockets to various locations within Office space
1 x Phone line to be provided in Office area

Subtotal
Civil Works
Remove 12m x 10m platform - dismantle and transfer to storage (landlord
storage) for future reuse
Office/Cold Store Option 1 - Strip out /remove existing offices and overhead
mezz platform.
Install new cold store area with Office area above.
Cold Store and office to be created using Porta cabin solution.
Cold store requires storage for around 20 Pallets.
Cooling to be provided by 2 x 2.5 hp Aircon unit - to be supplied and installed
Office will also require 1 x 2.5 hp Aircon unit - to be supplied and installed
Office Cold Store Option 2 -Convert 2 of the existing 3 offices into cold store
area
Install Double door FLT access to cold store area
Cold store requires storage for around 20 Pallets.
FLT must be able to access area and pick/move pallets, without damage to walls
and ceilings
Cooling for cold store to be provided by 2 x 2.5 hp Aircon units - to be supplied
and installed.
Refit remaining Office, into warehouse office space
Office will require 1 x 2.5 hp Aircon unit - to be supplied and installed

Subtotal
HSE
doors TBC
Provide 6 x Fire Extinguishers (locations to be agreed)
Provide 4 Steel U Barriers (approx 1200 x 1000 x 100mm Diameter) for
FLT/Doorway protection
Supply and install Drain Channel covers to cover min 5m of drain either side of
main access door ways (4 areas in total). Covers must be in sections to ensure
easily removable for inspection/cleaning
CCTV - 8 channel systems - installation of cameras and recording system
Standards
Floor marking for walkways as per Fosroc Standards
Allowance for HSE signage
Allowance for 50m of handrail/pedestrian barriers - location to be confirmed
Safety barrier protection for new DB board as per Fosroc standards
Install emergency shower / eyewash station.

Subtotal
Other

Subtotal
GRAND TOTAL

Comments/assumptions

Changing Rooms/ Showers at existing Shah Alam Factory


Loading ramp at exsiting factory and not required at external warehouse
Data connections not required - all picking orders/paperwork to rasied from
existng factory
CURRENCY
RM

Cost
Budget Quotation for Malaysia External Warehouse

Please - complete and return by Tues 1st August


Locatuon: 13, Jalan Trompet 33/8, Section 33, HICOM Industrial Area, 40400,
Shah Alam, Selangor Darul Ehsan

Electrical
Install newWorks
DB board to create independent supplies for all electrical Comments
requirements within warehouse (lighting, FLT charging, Ventilation, Stretch
wrapper and A/C units). Remove risk of supply interruptions from isolation
occuring within other extents of site.
reused)
Install Cabinet and terminate large incoming cables to provide lock out & prevent
risk of electrocution, if cables made live from other area of site
Test/recommission existing 4 x external high level flood lights - allow for some
relocation to give maximum illumination of external areas (current location may
create shadowing under door canopies)
Test recommission existing internal high bay lighting and relocate switches to
doorways/office area
Install 2 x Double strip fluorescent tubes under each door canopy (4 units total)
Install 3 x Ventilation fans into existing openings, and removed external ductwork
to improve air flow.
Provide new single phase power supply to Stretch wrapper location
Provide new 3 phase power supply for future FLT charging
Provide additional 10 x double sockets at various location around warehouse
walls (internal)
Provide Power supplies to 3 x 2.5 HP air con units
Provide 10 x double sockets to various locations within Office space
1 x Phone line to be provided in Office area

Subtotal
Civil Works
Remove 12m x 10m platform - dismantle and transfer to storage (landlord
storage) for future reuse
Office/Cold Store Option 1 - Strip out /remove existing offices and overhead
mezz platform.
Install new cold store area with Office area above.
Cold Store and office to be created using Porta cabin solution.
Cold store requires storage for around 20 Pallets.
Cooling to be provided by 2 x 2.5 hp Aircon unit - to be supplied and installed
Office will also require 1 x 2.5 hp Aircon unit - to be supplied and installed
Office Cold Store Option 2 -Convert 2 of the existing 3 offices into cold store
area
Install Double door FLT access to cold store area
Cold store requires storage for around 20 Pallets.
FLT must be able to access area and pick/move pallets, without damage to walls
and ceilings
Cooling for cold store to be provided by 2 x 2.5 hp Aircon units - to be supplied
and installed.
Refit remaining Office, into warehouse office space
Office will require 1 x 2.5 hp Aircon unit - to be supplied and installed

Subtotal
HSE
doors TBC
Provide 6 x Fire Extinguishers (locations to be agreed)
Provide 4 Steel U Barriers (approx 1200 x 1000 x 100mm Diameter) for
FLT/Doorway protection
Supply and install Drain Channel covers to cover min 5m of drain either side of
main access door ways (4 areas in total). Covers must be in sections to ensure
easily removable for inspection/cleaning
CCTV - 8 channel systems - installation of cameras and recording system
Standards
Floor marking for walkways as per Fosroc Standards
Allowance for HSE signage
Allowance for 50m of handrail/pedestrian barriers - location to be confirmed
Safety barrier protection for new DB board as per Fosroc standards
Install emergency shower / eyewash station.

Subtotal
Other

Subtotal
GRAND TOTAL

Comments/assumptions

Changing Rooms/ Showers at existing Shah Alam Factory


Loading ramp at exsiting factory and not required at external warehouse
Data connections not required - all picking orders/paperwork to rasied from
existng factory
CURRENCY
RM

Cost

5,450

1,200
900