Student # 4: Activity 5

Activity 5: Form Works Estimate


Title: Estimate of Roof Framing Plan
DESCRIPTION MARK QTY. DIMENSION ( m) SURFACE Estimated REMARKS
AREA FS SF (sq.m)
W D L (sq.m)
Roof 3.91 0.10 4.301
Framing RB1 1 0.2 0.3 4.7375 A1' - C1'
RB2 1 0.2 0.3 23.8 19.16 0.10 21.076 D' 1- D' 6
7.16 0.10 7.876 A1-A2, A2-
A3, A3-A4,
A4-A5, A5-
RG1 5 0.2 0.3 4.4 A6
1 0.2 0.3 1.75 1.52 0.10 1.672 A'1-A1
7.32 0.10 8.052 B1-B2, B2-
B3, B3-B4,
RG2 5 0.2 0.3 4.5
B4-B5, B5-
B6
5.06 0.10 5.566 C1-C'1, C'1-
C2, C2-C'2,
C'2-C3, C3-
10 0.2 0.3 1.9 C'3, C'3-C4,
C4-C'4, C'4-
C5, C5-C'5,
RG3 C'5-C6
1 0.2 0.3 1.85 1.6 0.10 1.76 C1'-C1
7.32 0.10 8.052 D1-D2, D2-
D3, D3-D4,
RG4 5 0.2 0.3 4.5
D4-D5, D5-
D6
8.82 0.10 9.702 B1-C1, B2-
C2, B3-C3,
B4-C4, B5-
C5, B6-C6,
RG5 12 0.2 0.3 2.9
C1-D1, C2-
D2, C3-D3,
C4-D4, C5-
D5, C6-D6,
1.884 0.10 2.0724 A1-B1, A2-
B2, A3-B3,
6 0.2 0.3 0.98
A4-B4, A5-
B5, A6-B6
1.74 0.10 1.914 D1-D1', D2-
D2', D3-D3',
6 0.2 0.3 0.9
D4-D4', D5-
D5', D6-D6'
TOTAL ESTIMATED
SURFACE AREA(sq.m)) 72.043

Grade:
Group # Group/Company Name: Activity Title: ACT. #
3 KNL Construction Company Formworks Estimate 5

Prof: Date of Submission: Schedule:


Engr. Merlin Deblois-Herrera 10/06/2017 10:00 11:00
Name:
Course Subject:
Medina, Alyssa Sen S
Cost Engineering Sec 50013

Das könnte Ihnen auch gefallen