Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

Project: Waterfront Integrated Resort Project


Method Statement for Sewer Diversion Pumping
Line Installation

HYUNDAI
ENQillE:ERINQ & C'OifSl'RUCi!ON.

Keangnam
Page: 2 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner: (Private) Limited.

This Version

Authored by:

Name: Manjula Subashana.

Role: Engineer.

Signed: ~- -~ .
Date: 24.06.2014

Authorised for issue by:

Name: Santha amaranath

Role: Manager project

Signed: IJ,~~ii
..... . ~
~
Date: 24.06.2014

Reviewed by:

Name: K. Lee
Role: HSE Manager ~ ~

./' '-'
Signed:
Date: 24.06.2014

Name: K. S. Kim
Role : Construction Manager
Signed:
Date: 24.06~2014
l<~ s fLJ\J\M_ ~

The signed original of this page is retained by the issuing team.Version History

Version
Date Status Changes Overview
0 24/06/2014 For Approval
Page: 3 I 28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

Project: Waterfront Integrated Resort


Ref No: 01 Package: sewer diversion pumping line Date: 24.06.2014
installation
To be read in conjunction with Risk Assessment No. RA 02
To be read in conjunction with Manual Handling Assessment No. MHA 02
To be read in Personal Protective Equipment No. PPE 02
To be read in conjunction with Noise Risk Assessment No. NRA N/A
To be read in conjunction with COSHH Assessments No. COSHH N/A
Activity: Installation of Sewer pumps & pipe line
Location: site boundary (SEE ATTACHED DRAWING)
Times: 06:00- 24:00, Mon to Sunday Duration: 60 Working days
Labour Required:

Engineer

Supervisor

Plumber

Fitter

Helper,
General Operatives :
Helpers will be employed for helping plumbers and fitters .
EQUIPMENT
Tools/Plant Required: Personal Protective Equipment:
Cutting machine Safety Helmet
Compulsory
Welding machine Including chin strap
220 - 240v Drilling machine/ Cutting machine Hi Visual Vest Compulsory
220 - 240v Hand held Grinder Safety Boots Compulsory
Standard Hand Tools
Gloves Used when required
Eye Protection Used when required
Knee Pads Used when required
YES - when noise is
Hearing Protection
83db or over
YES - working above
Safety Harnesses
1.8 m
Persons Responsible for
Project hierarchy for Health and Safety
First Aid
Constriction manager I HKN I Tel: 0776938929 HKN Safety Officer
Page: 4/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

Safety officer : Mr.Mangala (Sub- con) Tel : 0777287194

Engineer : Mr.Manjula (Sub- con) Tel: 0774443457

Technical Officer: Mr.Thilak (Sub- con) Tel : 0786243156

Issue of Safety Training Documentation:


All certificates relevant to this task i.e. Certificates of Competence will be held in HKN Site office for
review and audit.
Emergency Arrangements:
HKN to provide a medical room .
HKN Qualified First Aider- First Aid Kits Site Office & Stores.
Comply with HKN Fire Safety Plan & Fire Prevention and Evacuation Procedures.
Access & Egress:
Glennie Street controlled by HKN.
Access Lighting (safety lighting):
Access lightin9 (safety lighting) is to be provided and controlled by HKN, all access routes Will be
assessed for lighting prior to sub-contractor carrying out works.
Task Lighting:
All task lighting will be supplied and maintained by sub-contractor operatives .
Hazardous Materials and Substances:
N/A. No Substances I chemicals shall be utilized during this task.
Waste Management:
Site: Waste materials will be placed in skips provided by HKN .
HKN will manage and control the disposal of all waste products/material accordingly
Sub-contractor will dispose of own waste accordingly.
Special Control Measures:
All operatives will have undergone HKN, sub-contractor and all other relevant inductions required to
work in this area.
All operatives will be fully briefed on the SSOW compiled for this operation .
All operatives shall receive a daily briefing of works to be carried out that day.
All operatives will read, acknowledge and sign this Safe System of Work before commencing work.
Complete physical exclusion zones with warning signage displayed will be in place prior to works,
commencing and will be maintained by sub-contractor. (HKN to assist with the policing of the
exclusion zones) Only trained (Qualified) operatives will move or operate plant.
Working at Height Considerations:
Pipe laying - pipe laying is carried out approximately 1m depth trench on ground . There is no any
risk related underground pipe laying.
Pump I Valve I pipe installation inside pumping station - pumping pit is having around 6m
depth. Scaffolding will be used for pipe & valve installation inside pumping station. Full body safety
harness will be used by all fitters those who are working above 1.8m height.
Page: 5 I 28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited .

Safe scaffolding arrangement with lockable caster wheel.

Confine space ventilation arrangement :


Two ventilation fans will be used to ventilate pumping station as one fan for supply air and other for
exhaust air.

Safe arrangement of ventilation fan.

House keeping
Material storage -
All pipe will be staking safely with proper sporting in a suitable location selected with
safety Engineer/Manager.
Pump, valve and fitting will be installed inside a container to protect prom any
possible damagers.

Pipe laying -
All area will be properly clean every day.
Maintain site avoid to collect water for preventing from Mosquito Breeding .
Page: 6 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

Welfare Facilities:
All Welfare facilities i.e. toilets, changing rooms and resting/eating areas will be provided and
controlled by HKN.

Typical examples of materials listed below:


Upvc pipes, Valves , Pumps, Concrete, Form and Reinforcing bar etc.

Emergency Measures:
Exclusion Zone:
sub-contractor have assessed that for all operations there will be an exclusion zone
constructed with warning signs displayed around the working at height operation where
practicable.
Page: 7 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

TABLE OF CONTENTS

1) Description of works: ... .... ......... ...... ... ............... ....... ...... ........................................................................... 8
2) Scope of work ............................................................................................................................................ 8
3) Sequence of operation: ..................................................... ......................................................................... 8
a) Sequence of pipe line installation: ........ .. ... .... ........... ...... ....... .................. ...... ......... .. .. ......... ... ................... 8
b) Sequence of valve installation : ............... .............................................................. .................................... 8
c) Sequence of pump installation: .......... .. ..... ...... ...... .................. .... ...... ...... .... ...... ....... ............................ .... . 8
4) Pumping station drawing ... .. ... ...... .... ... ... ..... ........ ....... ......... ............ ................ ...... ...................... ....... ... ... . 9
5) Mechanical installation Inside sump .. ............................ ....... ........................... ................ .. ... .... ..... ..... ..... 10
6) Pipe !me mstallatwn Outside Sump ....... ... ................ .... .. ... ................ .................................. ... .... ........ .. ... 12
7) Pipe line installation methodology ........ .......... ..... ...... .. .................... ...... ... ... ....... ..... ...... ....... .. ........ ... ... .. 14
8) Valve Installation ......... ................ .... ........ .. ... ....... .... ....... .... .... .. ......... .... ...... ... ... .. ........ ......... ........ ........... 16
9) Pumps installation .... .. ............. .. ...................................... .... .... ....... .................... ........ ............................. 16
10) Project schedule ........... ..... .. ............... .......... ....................... .... ........ ............. .......................................... .. 18
Page: 8/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

1) Description ofworks:

This SSOW is for Diversion of Sewer pumping line for the Waterfront Integrated Resort project,
Colombo, Sri Lanka .
Before the commencement of the activity an exclusion zone erected with barriers and warning signage
will be established by Sub-contractor at ground level around the work area. The exclusion zone will be
monitored by HKN/ Sub-contractor operatives at all times throughout the operation.

2) Scope of work.
Three numbers of submersible pump installation.
Valve installation.
Pumping pipe line installation.
Testing & commissioning

3) Sequence of operation:
a) Sequence of pipe line installation:
Setting out -+ Excavation -+ inspect material -+ Pipe laying ---*pump & valve installation ----*

Pressure testing ----* Back filling ----* Finish work ----* Final inspection,

b) Sequence ofvalve installation:


Inspect material ----* Setting out for valve installation -+ bracket installation -+ valve &

connecting Pipe ----* pipe header installation ----* test the functionality ----* Finish work ----* Final

inspection,

c) Sequence of pump installation:


Inspect pumps ----* Setting out for pump installation -+ bracket & guide rail installation -+ pump

installation ----* power connection ----*test the functionality ----* Finish work----* Final inspection,
Page: 9/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pum pi ng li ne installation
Owner:
(Private) Limited.

4) Pumping station drawing

HU';'/Y CUIY 001.13lE S~.U:O c.-.s l IRQ.~ I.W'HCL[ CO'IER

CCN l ROl

""""

I
'/-~ ~

~.""' :
l.u~w~-===~~
TO-;: e2.0m m STAlUl[SS S1([l RUNGS
1:l UOE fl[XIBlf
R.C. CONCRVI:
'c'-Ctw.ltt!;L(S.S)
[ CEi'N l ''S '

$1----~-------T-----------\~-~-
C, ~~
c
''
r-
<
~
~I
.. -Jii50 ~SL ~ I

~~1'=='--if"'l--;:+--w,---~""'""'~'
1
;y,'l . . . " . . . ' : . . PUMP

~-~-E~~R p~~~~~~ ~TATJON SUM.P ~U~P-bEl-~ ~-


"'
< -

___-t
-t-,- i'-"""------------~.--- '--------- .. I. J ------""'
\. __ J .:

"'
'1--

. -.. SEWER PUMPING STATION SUMP PUMP PIPE PLAN


Page: 10/28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

5) Mechanical installation Inside sump


1. Five number of puddle collar will be placed as per the shop drawing , while sump civil works on
going for 3 no of pump discharge lines, overflow line and exhaust line.

2. Pipe laying path will be marked on sump wall as per the shop drawing approved by Engineer.

3. C-Channel will be fixed to sump wall using M12 stud anchors with suitable intervals for pipe

bracket supporting .

4. Pipes will be laid up to inside valve chamber which is located at outside of sump. While laying
pipes flexible couplings install at vertical line.

5. Installed duct foot bend as per approved drawing,

~ I I

I
<J

r;::
I

J )
ll LJ

I I I..- "'\.
t1
u ~ ([ I)
<Q LJir 1f

<J 4 LJ
A <! 4\
Page: 11/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

6. Installed Guide rail as per approved drawing

RC. CONCRETE:

I
I M12 STUD ANCHORS

r-
1 r---r-----r--,
'I
L_

r.-- ..
' - - - - - - - - - - - - .,j / '~_ _ _ _ _ _ _____J
\.._.

Guide rail installation side elevation

R.C. CONCRETE

M12 STUD ANCHORS

100X50X5 'C' -CHANNEL(S.S)

Guide rail installation plan


Page: 12/28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

6) Pipe line installation Outside Sump


Pipe specification:

l n.:~pi re:rj lly rts cun1 11itm eu t tn 9 lv ir ~1 its cus tm ers the b est:. /\ N I O N ha.:J
pi reered th~ m21 r~ fa ul'VC p ipe-s i 1 s.n l et ~ tL hese 1 m.s ure pipe.5
-,re rna mt: c:Ju eo i1 c;..,f rdan{;e vri ~. 1: the SLS l 4 l s anda rd and ISO
9oo 1-200el roduc ce 'ficauc..

AO'JANTAGES
\N'l ON t p:'JC r- rncsum r,.:i es Z..lP?. mn -~ o xr; ! .: l i1rH1 em rorm
[ fvVH(J :;11 i.e ~ll nf::!;.
A~ l O ~ p,i.,p ,. s t~~-is ~ b()th r.uids E.m d ~lkall [lE-1lS, rw i n~J h . mqlmJSkJ 1-r .. F.
Smor lh i 11ar 1(11 SIJ rtf:! G.! r:nlnin IP./'t! 5 lt .g obsl -~ c licm or f! :.J'.(t.l

Pressure rating:

Type 1000 (1 OOOkpa I 1Obar ) will be used for underground piping

2 .m1 to <!i ) frt .,n

P essure eta sses


2 ~0
;J I ll....
G;J t') - "l.f
llJI
Page: 13 I 28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

Pipe connection :

Solvent socket type pipe will be used with the same connection,

TYPES O F P IPES

Rail I=nd (f".;f.}


D IN 1 ~5'"7
HS ?4 9
Page : 14 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

7) Pipe line installation methodology

1. Pipe path will be marked as per the shop drawings approved by the Engineer from pumping
station to existing CMC manhole.

2. Excavation of pipe trenches will be done by using an Excavator Backhoe (Construction of


concrete columns will be done in areas where pipes are running above the ground level).

3. Levelling of trenches will be done by using sand and concrete slabs in suitable intervals.
Page: 15/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

SEWER PIPING
,,./ -~ .,.\ PIPE
BRACKET DETAIL

4. After laying pipes & installing valves pressure test will be carried out with keeping 24 hours at
working pressure & 2 hours at two times working pressure.

5. After inspection and approval received from the Engineer back filling will be done as per
specifications provided by the Engineer.
Page : 16/28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

8) Valve Installation
1. Valve chamber is located just outside the pump pit as shown in the drawing

\ ~ . .

CAST IRON MANHOLE COVER

110(q PIPE
(
S EWERAG E PU MP

~~/
..
2. Gate valves & Check valves are flanged type and they will be installed to pipe line by using
stainless steel bolts & nut.

9) Pumps installation
1. Two no of (j) 32mm dia SS guide rail will be installed at sump wall using C-channels, M12 stud
anchors.
Page : 17 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

R.C. CONCRETE
M12 STUD ANCHORS
1OOXSOX5 'C' -CHANNEL(S.S)
32 GUIDE RAIL

<J

L---------------~/L---------------~

2. Pumps are supplied with duct foot bends will be placed in side pump pit

.d
/
<j.
SEWERAGE PUMP

L': . . l: .
<i
<'! .

l
' -- -- --- <::j ----.J

3. Testing & commissioning will be carried out after completion of electrical work.

4. As-installed drawings will be submitted on completion.


Page: 18 I 28
Date & Version: 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

10) Project schedule


installation of sewer pumping line from proposed pump station to existing CMC manhole
1Task Name I Duration i Start l Finish i% Como!ete ~ ~~ 21 t June 21
:installation of sewer pumping line from 64 days? Mon 6110113 j Mon 8112.'13 0%!
jproposed pump station to existing CMC
...........i

~...11
;manhole . .
--:c- r~1te"th0c Sti fE:i11ent aPP:jQ;.~ -- . 2V.fS - ~ --- Mi-1' 1ftvt3 (" WeCf6h9h3 .... O%j
Mtit5rHa Approval -- - ----------~--.;- 2 \.~~-~-: Tml /2C!E ; 56~~~~1-~- - - --- --~~
--~ Setti'Wj"CUt-- -- 2days \bn 7/1!13 i Tue7l2s'13 Q%j
E-xcav:itfOri- - ------~---~-ir~rays-~ ~~\itif7!3!1'3 l-Mcn?,\3/l:f -- --O%j
-,e~:;:j;:;g of tre-nChes ..........; 4'"2ti;;-;s rue:;-fJlj rFi:rii1if3 .. .. u%j
ML -p1pei3.0i-~9- . 1oda-;s ...~ . sai7i13i1Ij . rv;on7Ji2i13. - M-Cf%1 ~
v3iveinS't'.l!ation ...... --2 diiYS .... "tue- 7l22~t3 l VJid 7;24h:r o~iJ liil
4 days nm ii:2~/13 ; Sun n2at13 O%i ~
sdayS , tJJon 7m.tl3 l SatEJ2h3 o%!
4aays-- ~ ~ii;:ia.;sTi !f.. --rhu--&.;8Tis-
. 2-saa~-s Tue iiih 3 Fri 7/261'13 '
, e:(haus: & vent piping Tuc- &I 13 Thu 5JE.!1 3 liilil:
I
- f . Testing& commisioning til
" - l lind c~~e r jg

Monitoring:
This Safe System of Works will be monitored regularly by the Installation Supervisor and toolbox talks
held with all operatives to ensure they are kept up to date with its content.
General Note:
Access & Egress will be monitored by Sub-contractor.
Conclusion:
This Safe System of Working and Risk Assessment is provided to ensure that works to be carried out
have been thoroughly assessed and that every step has been taken for the work to be completed in the
safest way possible.
Attachments:
Risk Assessment - Ref: 02
Manual Handling Assessments - Ref: 02
Personal Protective Equipment- Ref: 02
Sewerage diversion system layout drawing.

Assessor: Mr.Manjula Date: 24/06/2014


Approved: Mr.Thilak Date: 24/06/2014
Review:
All reviewing or changes to this document will be made by the Sub-contractor Site Engineer when or if
the circumstances change.
Page: 19 I 28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pump ing line installation
Owner:
(Private) Limited.

Risk Assessment Number: 01 Date:


2. Location
1. Activity: sewerage diversion system
Waterfront project- premises
3. Risks Identified:

1. Poor Access & Egress


2. Lack of Supervision
3. Manual Handling
4. Slips and Trips

4. Persons at Risk:
5. Likely Consequences
1. Persons doing the task
Strains
2. Site personnel

RISK =LIKELIHOOD X SEVERITY


LIKELIHOOD SEVERITY
0 = Zero to very low 0 = No injury or illness
1 = Very unlikely 1 = First aid injury or illness
2 =Un likely 2 = Minor injury or illness
3 =Likely 3 = " 3 day " injury or illness
4 = Very likely 4 = Major injury or illness
5 = Almost certain 5 = Fatality, disablement injury, etc

5. Factor Values: LOW= 1 to 8 MEDIUM= 9 to 16 HIGH= 17 to 25

6. Activity Risk Rating: Likelihood 2 X Severity 1 = Total~

7. Activity Risk Factor: LOW v MEDIUM HIGH

8. Workplace Precautions:

1. Working at Height

Underground piping work is with 1m depth soil trench and working height risk will not be involved
Page: 20/28
Date & Version : 24-06-2014, rev 0 Method statement for sewer diversion
MST-ME-0002
Owner:
Waterfront Properties pumping line installation
(Private) Limited.

2. Falls from height of persons or materials


Not applicable

3. Poor Access and Egress

a. All access routes must be clear of all obstructions. If there is a work activity within the access
route there must be alternative routes available, HKN I Sub-contractor to coordinate.
b. All work areas will be assessed for obstruction prior to works commencing
c. The public I pedestrians must always be separated from plant and Sub-contractor operations
(HKN to control).
d. Access I egress routes are provided and managed by HKN.

4. Lack of Supervision

a. The operations will be fully supervised at all times


b. Only competent operatives will be permitted to operate any Machinery required .
c. Ensure that all planning and preparation is completed by the supervisor at all times before the
operations commence.
d. Only competent operatives who have read and understand the SSOW will be authorised to
participate in these operations.

5. Manual Handling

a. All material is light weight and can be handle by hand.

6. Slips and Trips

a. Access /Egress to the work face must be clear of obstructions and debris at all times by HKN.
b. Rubbish must be placed in a central location and removed at regular intervals by HKN.
+

7. Activity Risk Factor: LOW v MEDIUM HIGH

8. Activities Remaining Risk Rating: Likelihood 2 X Severity 3 =Total~


Page: 21 I 28
Date & Version: 24-06-2014 , rev 0 Method statement for sewer diversion
MST-ME-0002
Waterfront Properties pumping line installation
Owner:
(Private) Limited.

9. Residual Risks Remaining:

1. Human Behaviour: All operatives to undertake relevant training .


2. Lifting Accessory Failure: All lifting accessories have been thoroughly tested and inspected.
3. Mechanical Failure: All mechanical equipment has been inspected before use and use as
per manufacturer's instructions.

10. Legal Requirements:

1. Health & Safety at Work Act


2. Working at Heights Regulations
3. Construction Design Management (COM) Regulations
4. Provision & Use of Works Equipment
5. Management of Health, Safety and Welfare Regulations
6. Lifting Operations and Lifting Equipment Regulations
7. P.P.E Regulations
8. The factories ordinance, no: 45 of 1942

11. Assessment Of Remaining Risk: LOW v MEDIUM HIGH

12. Assessor: Mr.Manjula ~ Date: 24/06/2014

Approval: Mr.Th ilak '~/ Date: 24/06/2014

13. Review: When circumsta~~e~nge.


Page: 22 I 28
Date & Version : 24-06-2014
Method Statement for installation of sewer pumping line proposed pump station MST-ME-0002
Owner: Waterfront Properties
(Private) Limited.

Attach detail risk assessment sheet-02


Sr. Original Risk Rating Revised Risk Rating
Activity Hazard Involved Risk Mitigation Action Rema rks
No. p I v R p I v R
Poor House Slip/ trip/ fall 1. Only authorized entry
1 Setting out 2 2 4 L 1 1 1 L Residual Risk
keeping accident 2. Exercise good house keeping
1. Excavation shall be done only under
permit-to work and all instructions to be
followed ir accordance.
2. Maintain Bcommended slopes to soil
condition and wherever inappropriate
requ ired shoring
Fatality/
2 Excavation Cave-in 2 2 4 L 3. Do not stack excavated soil near the edge 1 1 1 L Residual Risk
suffocation
at least 2 nnates away from the edge.
4. Avoid operating heavy/ vibrating
equipment nearby excavation
5. Close supz rvision required while men at
work on excavated pit
6. Avoid accumulation of water
1. Use of ladders to enter/ exit to excavated
Access/ Egress to Slip/ trip/ fall pit
1 2 2 L 1 1 1 L Residual Risk
working area accident 2. Avoid weL muddy boots
3. Clean ladders regularly
1. Gather inf.Jrmation and close study before
excavatior
Nearby structures Collapse 2 5 10 H 1 5 5 L Residual Risk
2. Monitorin
3. avoid structure basements/ piling if any
Accumulation of Drowning/ 1. Continue de-watering below water table
3 4 12 M 1 3 3 L Residual Risk
water Unfavorable 2. Use of rubber sole boots
Page: 23/28

Date & Version: 24-06-2014


Method Statement for installation of sewer pumping line proposed pump station MST-ME-0002
Owner: Waterfront Properties
(Private) Limited .

Sr. Original Risk Rating Revised Risk Rating


Activity Hazard Involved Risk Mitigation Action Remarks
No. p I v R p I v R
working condition 3. supervisi on
Poor handling of
3 Piping work Miner injury 2 1 2 L 1.Used only well train staff with PPE 1 1 1 L Residual Risk
Pipe installation

1. all new w0rkers/ visitors shall permit to


enter wor~ area only after attending
induction training completed
General New workers/ Unknown
7 2 4 8 M 2. Unless otlilerwise required no visitor shall 1 4 4 L Residual Risk
Arrangements Visitors to site hazards/ risks
be permitt~d at site
3. No Kids shall be permitted to enter site
premises
1. Area of work will be kept clear of any
obstructions debris and all other unwanted
materials.
slip, trip fal l
House keeping 3 2 6 M 2. Working area will be barricaded with only 1 2 2 L Residual Risk
incidents
designated access
3. only authorized personnel to enter work
area
Page: 24/28

Date & Version : 24-06-2014 Method Statement for installation of sewer pumping line proposed pump station MST-ME-0002
Waterfront Properties
Owner:
(Private) Limited .

LEGEND

RISK MATRIX USED

Impact Trivial Minor Moderate Major Extreme

1 2 3 4 5 II P I Probabi lity
1 Low Low Low Medium Medium
2 Low Low ~rnum ~dium II I I Impa ct
3 Low Medium
4 Low Medium I Morllnm II V I Risk Va lue
Aim~ I' 5 1Medium 1 Medium ,.J.'f ., I Risk C l ass ifica~ion
Certain ':t 11'1r ,:: ;~.1 \1 \,.. '"1--~~ 1~ ::} ' ,.,.~.,;:..' II R
Page: 25/28

Date & Version: 24-06-2014


Method Statement for installation of sewer pumping line proposed pump station MST-ME-0002
Waterfront Properties
Owner:
(Private) Limited. ----

M anua I H an dl .mg 0 pera t'Ions R ecor d Can manual handl ing I I No Mark as appropriate
be eliminated? 1 1 ONE ACTIVITY MUST BE HIGHLIGHTED

Project/Premises: Waterfront lnteqrated Project Company : Kent Engineering (Pvt) Ltd MHA: 08- Light Materials
Activity : Construction of Consultant office & Affili ate office Locations: Waterfront premises Materials to be handled : uPVC pipe

~ -~-~-~ ~-~'t ~L_ ~I ~ ~ -~ ~ ~


K ST OOPING LIFTIN G HIGH LIFTING LO W HAN~~~~E~ HILE REPETITIO N REAC HI NG HIG H REAC HIN G LOV\ CAR RYING TW ISTING J:6~~}~~S PUSHING PU LLING

Yes I INa Y es INO INo jNo INo YES I Yes J Yes I NO INo

-'-N
~ -~ ~~ \>kt ~ ~~~~yr . ~~ u\1= ~
n ~~ ~ <~<>~.~ :D9 ~-

~~-GR; r Y ~ ~ ~
BULKY 1 UN W IELDLY DIFFICULT TO G RIP HOT COLD HE AVY LI G HT SHA RP I A BR AS IV E UN STA BLE ECCE NTRIC SH A PE

jNo NO INo INo NO Y::s I IN o NO INo

~ ~ ~~- ~~-- =-- ~


r (~ *((q: J~)) ~~ Cl"U ~
Q HOT
O 'Ct~" ~ ~ CO LD HU M ID W INDY DU STY NO ISY V IB RAT ING O BSTRU CTIO NS STEP S SPAC E SLO PES SUR FAC ES

N Y ES I jNo YES !No YES I !No !No jNo jNo !N o NO !No


p ~ "'"" ..... " " 18.,. 55? ,~ """ Risk Facto;r: I HIGH I I MED I LOW I
~
E

0
N
"''oFoRuNusuAL
-

TRENGTH,HEIGHT,E TC .
~ ~ ~ ~~ ~ ~ ~
TRAINING
(1
REQ UIR ED
P.P.E .
TO BE W ORN
'
.
18 T 0 ssY RS ?.
..
I '.}

Meo lcALcoNoln oN
OR H I STORY
"14
TE AM LI FT ING
Coot"l M"'"'"
All opmti"" '""''"'' ;, thl ' " ' h'"e ""dectkeo M'""'' H'"dtlog T,;,;o g. All
PPE recuired for this task wi ll be provided and used.

INO YES I Y ES YES I INO I NO


Assessed by: Mr.Thilak -:~ Date: l 4
1
h June 2014
Page: 26 I 28

Date & Version : 24-06-2014 Method Statement for sewer diversion pumping MST-CN-0002
Waterfront Properties
line installation
Owner:
(Private) Limited.

Personal Protective Equipment 02 Company: Kent Engineering Date: 21 1h June 2014

Activity: sewerage diversion system Location: Refer to Attachment

PPE Risk Assessment

Compulsory 0 +@+8+0 +0+ 0+&


Nature ofRisk(s) Typical PPE Considerations
A Falls of Materials 0+0 YES
B Striking Against 0 +0+0 YES

c Flying Particles 0 +6 YES

D Molten Liquid N/A N/A

E Cuts and abrasions 0 YES


F Hazardous Fumes/Dust 6+8 YES

G Working at Height ~ YES


H MoVIng Vehlcles/Piartt ~+@ YES

I Noise ~ YES

J Working over/adjacent to water N/A N/A

K Working in Cold Weather N /A N/A

M
PPE Requirements

~ Head
~

w- Eye Hearing
~ d~
~
Foot
' rteCrJY
Hand/Arm
e c~
Body
~

~p
Resp. Fall
Restraint
Life Jacket
(buoyancy
~ Hig
h Vi sibility
Vest
aid)

0 @ @) 0 0 0 & (i) 0
WHEN WHEN WHEN WORKI NG AT MANDATORY
REQUI RED REQUIRED REQUIRED HEIGHT

Other Control Measures Implemented:


Site Safety Inspections, Revision ofPPE requirement to be monitored and assessed and if required amended

PPE Inspection/Maintenance Arrangements:


All PPE is to be visually inspected on a daily basis prior to commencing works.
Fall restraints to be inspected in line with manufactures recommendation and inspection registers update.

Training/Instruction Required in Safe Use ofPPE


Verbal Instruction YES Written Instruction
Tool Box Talk YES ON METHOD Specialist Training
STATEMENT
Page: 27 I 28

Date & Version: 24-06-2014 Method Statement for sewer diversion pumping
MST-CN-0002
Waterfront Properties line installation
Owner:
(Private) Limited.

Issued by: Mr.Thilak Perera Approved by: K. Lee

Designation: Assistant General Manager Designation: HKN Safety Manager

Date: 24th June 2014 Date: 24th June 2014

PPE Risk assessment Record Ref: PPE-01


Page: 28 I 28

Date & Version: 24-06-2014 Method Statement for sewer diversion pumping
MST-CN-0002
Waterfront Properties line installation
Owner:
(Private) Limited.

Key Plan

Pumping station