This PowerPoint will guide you on how to use the workbook, it will not explain
APQP. It simply guides you to take the necessary steps to create a working
APQP workbook.
PACCAR APQP Quality Checklist P ACR
Process Design & QUALITY
Product Design & Product & Process
Plan & Define Program Development
Development Validation
Initiation of the Project Industrialisation
Drawing Release Pre-PPAP
Tooling Order PPAP
Acronyms Summary Sheet Design Information Floor Plan Layout New Process Volume Validation
Low Low Low Low Build Low
Equipment
Part Project Plan DFMEA Process Flow Chart Product Process PPAP
On Time Low Low Low Low
Numbers Quality
Open Actions List Commercial Sourcing DVP Packaging Specs MSA Capacity
Low Low Low Low
Analysis
When you start the workbook you see many tabs at the bottom of your screen.
The tab to navigate through the workbook is the MAIN MENU. From here you
can navigate through the complete workbook. You can return to the main
menu from any screen.
Usage of the APQP Workbook (page 3 of 18)
Getting started
Risk Status of the Project Low Risk Overall Timing Rating On Time Design Responsible? Yes
Team Members Job Title Phone E-mail Address
The Summary tab contains a summary of all information needed to complete the
workbook. In this PowerPoint we will focus on this tab to ensure the workbook
will function in the best possible way.
Usage of the APQP Workbook (page 5 of 18)
Summary Sheet
Supplier Supplier GmBh
Location
Supplier Code
Summary Sheet (step by step)
87654
Supplierstrasse 1, 88888 Lieferung Germany
Risk Assessment
New: Site Technology Process Part X
Fill In the supplier details (see example above) including the risk assessment
(why do we start APQP) and also identify other risks. These risks should be
examined, they could lead to a new APQP for these parts.
Part Name Top pad CF Left Enter the part name (from drawing or project)
QV Build Location DAF Westerlo Enter the location of the Quality Validation build
VV Build Location DAF Westerlo Enter the location of the Volume Validation build
Manufacturing Location DAF Westerlo Enter the location of the location were the part is going to be
manufactured
Design Responsible? Yes Select whether the supplier is design responsible; Select Yes or
No, if you made a mistake use Reset
Use No will blank out some questions, with reset all ratings will
be blanked but comments will stay in.
Fill in the required date and copy to the Vertical Project (can be done by
yourself or the supplier)
Product Design
& Development 8 Design Reviews Low
Drawing Release
Affecting
Planned close Expected close Actual close
APQP Element / Milestone Start date Status Overall
date date date
Timing
Fill in at start of the project for each deliverable the start date and planned close date. Copy
at the beginning of the project the planned close date to expected close date.
Changes to the planning are filled in the expected close date. Status is calculated based on
deviations between planned and expected close date. If a deliverable is completed fill in the
expected and actual close date. If the deliverable is late, but does not affect overall timing,
then fill in No in the column Affecting overall timing.
Usage of the APQP Workbook (page 11 of 18)
Project Plan
Volume Validation Build 1-Jan-16 4-May-16 4-May-16 4-May-16 G Yes When all dates are filled you
PPAP
Volume Validation MRD 1-Jan-16 4-May-16 4-May-16 4-May-16 G Yes
will see that the overall timing
PPAP 1-Jan-16 4-May-16 4-May-16 4-May-16 G Yes
changes color.
Incomplete
No information filled in
Expected close date not filled in
The legend gives you the
G
Y
Expected close date earlier than planned close date
Expected close date within 14 days of planned close date
meaning of the color coding.
R >14 days overdue
Risk Status of the Project Low Risk Overall Timing Rating On Time
The overall timing rating is
copied to the summary sheet.
Usage of the APQP Workbook (page 12 of 18)
Summary Sheet Updating status deliverables
Next step is updating the Risk
Planned Expected Actual
Project Elements Start Date Close Date Close Date Close Date Comments / Actions
Product Design
& Development 8 Design Reviews Low element
Drawing Release
6 Has a Long Term Agreement been agreed and signed? Med The LTA has been signed, but not received back from DAF DAF Purchasing
7
Have the annual volumes for truck production and aftermarket service been determined and
Complete
project
communicated to you? Is your RFQ based on the combined volumes?
Have you conducted a sub-tier supplier capacity analysis to verify they can meet the annual
8 Complete
volumes for both truck production and aftermarket service?
10 Have you supplied to PACCAR your program timelines and production-intent locations? Complete
Has PACCAR released Prototype purchase orders to support the PACCAR prototype build
11 Med Protype purchase orders are late. DAF Purchasing
program?
Has PACCAR Production Purchase Order(s) been issued to support production tooling for QV and
12 Low Not yet received / not yet required
PPAP by VV?
Have you budgeted sufficient funds to purchase required production, measurement, and test
13 Complete
equipment?
If your shipping location(s) are different from your production site(s), are the vendor codes set up
14 Complete
for all your shipping locations, including those that supply service parts?
15 Do you understand and are you in compliance with REACH legislation? (Europe only) Complete
Low
Legend COMMENTS
N/A N/A
LOW
Task not applicable for this/these part number(s)
HIGH "No," Task not started, or task started but no timing for completion in place.
INCOMPLETE Work sheet has not been fully evaluated at this milestone
Usage of the APQP Workbook (page 14 of 18)
Updating the Action List
Main Menu Summary
PACCAR APQP Quality Checklist
COMMERCIAL SOURCING
Rating
(N/A, L, M, Person
Number Question H, C) Comment / Action Required Responsible
1
Have you, the supplier, been nominated officially by purchasing and is your production plant
audited and approved by PACCAR SQA?
Complete Fill in the checklist. Specify for medium or
2 Have you signed and returned the Non-Disclosure Agreement to PACCAR? Complete high risk levels the issue, action and
3 Have you completed the Supplier Financial Health Questionnaire (N/A for Europe)? Complete responsible person. Copy this information
4 Are Warranty Agreements in place with PACCAR? Complete to the action list to generate one overview
5 Are the requirements from PACCAR Product Development clear and agreed? Complete A TRS mismatch list has been added to the TRS. DAF PD for all open actions for the complete
6 Has a Long Term Agreement been agreed and signed? Med The LTA has been signed, but not received back from DAF DAF Purchasing project.
Have the annual volumes for truck production and aftermarket service been determined and
7 Complete
communicated to you? Is your RFQ based on the combined volumes?
If a section is finished,
Main Menu Summary
Part Styling
Rating
(N/A, L, M, Person
Number Question H, C) Comment / Action Required Responsible
it will show as
1 Have final styling surfaces (geometry, colour, or texture as required) been provided to you? Complete
Have all colour, texture, and QA specifications been communicated and can you achieve them
2 Complete
consistently?
Complete
complete, go to the
Main Menu Summary
Project Plan sheet
Project Plan
0
to fill in the Actual
0
Key to colours
at bottom of
sheet
close date.
Affecting
Planned close Expected close Actual close
APQP Element / Milestone Start date Status Overall
Acronyms Summary Sheet Design Information Floor Plan Layout New Process Volume Validation
Med Low Low Low Build Low
Equipment
Part Project Plan DFMEA Process Flow Chart Product Process PPAP
On Time High Low Low Low
Numbers Quality
Open Actions List Commercial Sourcing DVP Packaging Specs MSA Capacity
Med Low Low Low
Analysis
The Main Menu gives a quick overview of the project. Project elements in yellow
or red need attention.
Usage of the APQP Workbook (page 17 of 18)
Other tools
The APQP workbook contains tools / overviews to be used in the
project:
Part numbers: Overview of part numbers involved. This overview can be
updated to include part number per build phase if required.
BOM-Tooling overview: Overview of sub-components involved including
tooling leadtime and APQP risk status.
Capacity analysis / Run @ rate: Sheet to capture run @ rate results and
areas for improvement
Product Intent Run: Checklist to support SQM to review the process during
the product intent run
Packaging work sheet: Template to be used for PPAP deliverable 17.3
PPAP NA Template
Usage of the APQP Workbook (page 18 of 18)
Using the Workbook
For EU: The supplier should upload the workbook to the DAF portal.
For NA: The supplier should e-mail the workbook to the responsible SQM.
The SQM will review together with the SE team, including the supplier, the
APQP workbook
Supplier will complete the workbook with the remarks and upload or e-mail the
new version
The SQM will approve the workbook and report project risk status to
management