1 di/of 72
CIVIL DISCIPLINE
TITOLO TITLE LINGUE DISPONIBILI AVAILABLE LANGUAGE: IT
MF WH Papale
0 1/SEP/11 Emissione - Issued
PEI PEI EGP
REV. DATA DESCRIZIONE PREPARATO CONTROLLATO VALIDATO
REV. DATE DESCRIPTION PREPARED CHECKED VALIDATED
S 25 C L G 3 5 3 6 7 0 0 0 2 3 0 3
CLASSIFICAZIONE PUBBLICO AZIENDALE RISERVATO RISTRETTO RIF. ARCHIVIO 00000000
CLASSIFICATION PUBLIC COMPANY CONFIDENTIAL RESTRICTED ARCHIVE ID
Questo documento contiene informazioni di propriet di Enel Green Power SpA e deve essere utilizzato esclusivamente dal destinatario in relazione
alle finalit per le quali stato ricevuto. E vietata qualsiasi forma di riproduzione o di divulgazione senza lesplicito consenso di Enel Green Power
SpA.
This document is property of Enel Green Power SpA. It is strictly forbidden to reproduce this document, in whole or in part, and to provide to others
any related information without the previous written consent by Enel Green Power SpA.
CODICE CODE
PAGINA PAGE
INGEGNERIA
2 di/of 73
PAGINA PAGE
INGEGNERIA
3 di/of 73
PAGINA PAGE
INGEGNERIA
4 di/of 73
The Contractor shall know and respect all the regulations, ordinances and limitations in force locally with
particularly reference to safety, environment and protection of the territory.
If there are several water and electrical power sources in the adjacent zones, the Contractor shall be
responsible of identifying and procuring their utilization, and to guarantee the supply of these services with
appropriate quality. Any cost for these services shall be exclusively on behalf of the Contractor.
The Contractor shall be sure to have water reservoirs sufficient enough to store a minimum of ten (10) cubic
meters of clean water. These reservoirs can be metallic or plastic.
The Contractor shall provide their own electric generators of diesel or gasoline on site as to fulfill the work
needs; no construction power will be made available by EGP.
The Contractor should submit to the Owner the schemes, locations, dimensions, and descriptions related to
the temporary facilities within the next thirty (30) days after the signing of the Contract.
These facilities shall be functional and built with materials in acceptable condition and of good quality. The
Contractor shall guarantee their durability through the project.
No temporary facilities can be carried out if the Contractor has not obtained the Owners authorization.
a. Construction and supply of comfortable and safe offices, mess halls, and other facilities for the
personnel;
b. Construction and supply of service buildings necessary for carrying out works such as deposits,
workshops, warehouses, and magazine.
PAGINA PAGE
INGEGNERIA
5 di/of 73
The offices shall have sanitary services, electric lightning, illumination, and supply of drinking water,
sewerage, furniture and air-conditioned in all rooms. There is no telephone service at site; the Contractor
must communicate via satellite phone.
The sanitary services will include one washbasin, a toilet, towel holders, soap dispenser, mirror, and floor
drainage.
It is necessary to consider a momentary rainfall of a minimum intensity of 5mm in 5 minutes, and not less
than 50 mm per hour, for the project of temporary drainage of rainfall waters. The area shall be drained by
means of the following devices:
Drainage open gutters
Underground piping network
Drilled piping for water dispersion placed in trenches filled with gravel or other material that allows the
drainage of rainfall water.
The rainfall water drainage pipes shall behaving an expected minimum diameter of 250 mm in order to
avoid the obstruction of the pipes due to the hauling of solid material.
The Contractor will submit to the Supervisor peak rainfall calculations and a scheme that indicates the
location and diameter of the pipes to be used before they are constructed. The Contractor cannot remove
the temporary drainages until the work is finished.
Once the work is finished, all Temporary installations shall be removed without any cost for the Owner. All
necessary repairs should be done for any damage caused by the construction or removal of such
installations.
If by easing the work the Contractor needs to modify the Temporary facilities, or needs to change them to
other place during the process of the work, Owner will not be held responsible for the additional costs.
The Contractor shall be responsible for any work, supply, or installation not mentioned in these
Specifications, but which are necessary to deliver to the Owner the complete office with everything required
for its use.
1.2.8. Sign
The Contractor is required to place a good quality sign at all project access points with the following details:
PAGINA PAGE
INGEGNERIA
6 di/of 73
The Project Director shall approve the design of the sign and it shall be built in such a way that it is kept in
good conditions during the construction of the work.
Before starting the transportation, the Contractor shall elaborate and provide to the Supervisor the list of
equipment, tools, and materials with their main technical features.
Contractor shall submit a plan for review showing the areas where equipment and materials will be stored
on the site.
2. PRELIMINARY WORKS
Such activities should be carried out based on the procedures, tolerance, or any other specifications
mentioned in this document or defined by the Supervisor (EGP representative). Such activities shall be
carried out based on schemes, drawings, or designs.
It is the Contractors responsibility to mark the location of the different works in the site, according to the
drawings or points and levels indicated by the Supervisor before the works start.
The Contractor should observe the levels indicated in the drawings of each work. The Supervisor can verify
the accuracy of the location and levels, but the Contractor is responsible for it. Any work cannot start without
the Supervisors authorization.
The planimetric and topographical position of the references shall be established by means of adequate
instruments approved by the Supervisor, who shall also define the accuracy rates of readings and
calculation, in accordance with the nature of the works.
The topographical works should be referred to the concrete reference monuments placed by others during
the carrying-out of the polygonal bases that are indicated in the drawings submitted by the Owner.
For their guarantee, the Contractor shall place auxiliary or reference benchmarks along the construction
axis, fixed points, and other work areas.
If necessary, the Contractor should carry out the topographic surveying of cross sections along the axis of
installations, structures, piping, equipment, fittings, and chutes, observing the location and elevation
according to drawings, designs, or indication of the Owners Supervisor.
All necessary cross sections shall have a width enough to cover the area of the works to be carried out and
defined by the Supervisor.
CODICE CODE
PAGINA PAGE
INGEGNERIA
7 di/of 73
2.3. CLEARING
2.3.1. Generalities
The clearing in the cutting of trees, the stump pulling, and clearance of all vegetation, shrubs, rotten wood,
tree trunks, removal of fences, stakes, and other obstacles that interfere with the Works.
The Contractor shall know and respect all the regulations, ordinances and limitations in force locally with
particularly reference to safety, environment and protection of the territory.
The material removed in the clearing operation shall be dislodged from the work areas or shall be burned
according to the Supervisors instructions, and then it shall be taken to dumps authorized by the Owner,
prior inspection.
It is forbidden to throw wastes in ravines and creeks; neither any material can be settled in riverbeds or
riverbanks where it can be washed out by water.
The Contractor shall be extremely careful during the burning of combustible elements in order to avoid the
spreading of fire that could cause damages to public or private property.
2.3.2. Limits
The limits of the clearing shall be indicted in the construction plans or shall be settled by the Supervisor.
These limits shall be within the property of the Owner. If at any time it is necessary to make the clearing in
any other area, the Owners Supervisor will authorize it through a field log.
In the areas where the ground is soft, the clearing and cleaning shall be limited to what is needed in the
construction of the Work in order to keep the existing vegetation covering on the largest possible area, as a
measure to avoid erosion
The material removed in the topsoil stripping and cleaning operation shall be cleared away from the area of
permanent works, or it shall be disposed according to the Supervisors instructions.
It is forbidden to throw spoils in ravines and creeks; neither any material can be settled in riverbeds or
riverbanks where it can be washed out by the water.
The surface of the ground that shall be under the earthwork, and in places from where materials shall be
taken for the same, should be clear from tree trunks, roots, and vegetation materials of any kind.
The Contractor shall know and respect all the regulations, ordinances and limitations in force locally with
particularly reference to safety, environment and protection of the territory.
The Contractor is responsible for the site survey and the methodology for the correct dislodging of the
unsuitable material.
3.2. EXCAVATION
CODICE CODE
PAGINA PAGE
INGEGNERIA
8 di/of 73
3.2.1. Objective
This Section refers to the works of excavation, loading, transportation, unloading of plain material and ledge
rock necessary for the Power Plant Unit construction.
Under this item the Contractor shall carry out the earthworks, including dislodging of unsuitable or remaining
material, necessary for the construction to be adjusted to the alignments and cross sections at subgrade
levels. It shall include excavation in lateral enlargements, cut and grading of slopes, compacting, and final
refinement of the cuts.
The Contractor shall perform subgrade inspections to determine if subgrade soils have adequate
compaction and bearing capacity before any fill is placed, using water and proof roll with a heavy truck.
The excavated materials cannot be wasted without the Owner Supervisors written permission. The
excavation for the power plant area platform, tanks in the area, and access road shall be carried out
according to the sections authorized by the Supervisor. EGP will deliver the graded platform to the
Contractor, but some additional excavations on the platform will be required for foundations, etc.
a) Topsoil stripping. It is considered as the discharge of the surface layer of material, up to a depth of 50
centimeters, or up to a depth indicated by the Supervisor
b) Excavation. It consists on the satisfactory discharge and disposal of all the materials that can be
manually removed, by means of excavation machinery or by the use of drilling and explosives.
During the process of excavation, the zone should be kept drained at all times.
c) Disposal of the material from the excavations. All material coming from the excavations shall be
used in priority in the grading of earthworks or fillings, or any other uses, according to the
drawings or indicated by the Supervisor. The remaining and unsuitable materials including
organic soils, clays of high plasticity and soils highly damp, which are impossible to dry, shall be
disposed according to the Supervisors order; furthermore, the Contractor can dislodge
acceptable material if authorized by the Supervisor, as long as the Contractor replace it, in order
to meet the requirements of the project, with material that under the Supervisors judgment it is
equal or superior in quality and without any additional cost for Owner.
1) Unsuitable Material
All the materials that are discharged in the excavations and are unsuitable for the use in
earthworks shall be appropriately settled by the Contractors account and risk in areas shown in
the drawings, unless the Supervisor states or indicates otherwise.
2) Remaining Material
All suitable excavated material that is not necessary for the grading of earthworks, fillings, or any
other uses, shall be considered as remaining material and its disposal shall be done according to
the following methods:
i. Dislodging to zones adjacent to the construction of the project, in lands property of third
parties, prior authorization of the land owner. The Contractor shall be responsible to take
the necessary steps in order to obtain such authorization.
ii. Dislodging in the zone of the project,
d) The materials resulting from the strip topsoil shall be carried immediately after the carrying-out of
such operation to dump zones authorized by the Supervisor, where they do not interfere with the
construction works or cause damages to third parties. In these zones the materials will be disposed
in layers, approximately horizontal.
The approval by the Supervisor will not exempt the Contractor from his responsibility regarding damages
caused by the excavation operations on the work and/or third parties.
Such methods shall indicate: equipment to be used, performing phases, temporary and permanent
bearings, predicted productions, planned and contingency security measures; other information requested
CODICE CODE
PAGINA PAGE
INGEGNERIA
9 di/of 73
by the Supervisor.
The Contractor shall take into account all possible precautions and use the most suitable excavation
methods in order to avoid the breaking of rock and its contingent displacement off the lines of estimated
working area.
The excavations shall be carried out through suitable methods so the final alignments and dimensions are
in accordance with the ones indicated in the Contractor drawings and approved by the Supervisor.
Lines and dimensions of the excavations can be changed in relation to the ones indicated in the drawings,
before and during the performance of the works, and the Contractor will not have the right to any additional
economical compensation.
The Contractor shall take into account all the necessary measures in order to avoid any damage on people
and works in construction or already carried out.
The Contractor should observe all the laws and standards related to the transportation, storage, and use of
explosives. The failure in meeting the fundamental necessary precautions will be reason enough for the
Supervisor to order the suspension of the work because of the Contractor.
The explosive shall be used in such amount and power that it will not cause fissures or damages in the rock
in the proximity of the final lines of excavation or in the existing plant facilities.
The Contractor will submit to the approval of the Supervisor, at least five (5) days in advance, the general
schemes of drilling, load, and explosion for each type of excavation and for each type of rock. The
characteristics of the explosive, distribution and amount of the loads, diameter of the drills, type and number
of the detonators, and the start system will be indicated in the scheme mentioned above.
The Supervisor shall approve or notify the Contractor about his observations, and the Contractor will adapt
his program to the Supervisors indications.
The Supervisor will approve all typical blasting for the excavation.
The Supervisors approval of the methods of explosion, amount and power of the explosives, their storage
and transportation does not exempt the Contractor from his responsibilities regarding contingent damages
caused on people or works due to the use of explosives.
The unstable or loose material that appeared after the blasting, which can become a danger for the
personnel, shall be removed immediately by pickaxes, rods, wedges, water and air jets, suitable for the
Supervisor.
The use of explosive in distances less than 20 meters from the already done structures shall not be
accepted because the vibrations can damage the structures.
After finishing the works, all protection or temporary framework that is left in the work site should be
removed from the excavation area.
3.2.5. Drainage
During the excavations, the Contractor will take into account all the measures necessary to avoid the
formation of pools and to eliminate the runoff of water and puddles on the surface, which can damage
CODICE CODE
PAGINA PAGE
INGEGNERIA
10 di/of 73
structures, cause landslides, and obstruct the areas of work and access.
3.2.6. Landslides
Landslides of materials occurred out from the lines set for the excavations shall be removed and the slopes
shall be stabilized, if necessary, by filling the voids according to the Supervisors dispositions.
If the works carried out by the Contractor causes such a landslide, failing to meet the technical
specifications, these shall be financed by the Contractor and shall be carried out immediately. Before this
situation, the Contractor shall take all the possible precautions and shall use the most suitable excavation
methods in order to avoid landslides out of the lines of excavation indicated in its drawings and approved by
the Supervisor.
When the landslide occurs in a zone assigned to be in contact with concrete, the void left should be filled
with concrete of the type established by the Supervisor.
4.1. GENERALITIES
The Contractor shall examine the nature and distribution of the materials to be consolidated. The
compacting of the terraces that will grade the work shall be carried out according to the cross sections
shown in the drawings and within the tolerances specified in this document.
The Contractor shall know and respect all the regulations, ordinances and limitations in force locally with
particularly reference to safety, earth construction, environment and protection of the territory.
During the process of consolidated filling, the area should be kept well drained at all times.
In the general Earthwork, when the filling is performed over concrete pipes, the use of compacting
equipment shall not be allowed as long as there is not a minimum filling of one meter (1.00 m.) over such
structures.
For earthworks, the granular material will be considered like having the best quality, that is to say, the one
that has the highest unitary dry weights, the highest percentage of materials retained by screen No 200 and
the lowest liquid limits.
Earthworks should be compacted up to a minimum density of ninety five percent (95%) of the maximum
density obtained in the laboratory, following the specific procedures of the norm AASHTO T180-734, D
method.
a) The required minimum of dry density of these materials after compacting shall be expressed in terms
of relative density. The term "relative density" shall be defined as follows:
Wmax and Wmin shall be determined according to ASTM-D2049, "Relative Density of Cohesionless
Soils", or equivalent Chilean standard. Wmax shall be determined by the test method "Damp" or
"Dry", any of which that produces the highest maximum density in the laboratory.
b) The minimum relative density will be 85% percent. Medium relative density will be at least 95%
percent.
c) In order to determine the acceptability of the compacting, the density in the site of earthfill (Wn) shall
be measured not less than 40 centimeters under the surface of a compacted layer.
d) For assigned types of compacting equipment, the following table indicates the thickness of the layers
before the compacting and the number of full free passes required for the compacting, with such
CODICE CODE
PAGINA PAGE
INGEGNERIA
11 di/of 73
moisture content that does not result in the jam of the setting and compacting equipment. A "full
free pass" will be defined as the area entirely covered by a traversing of the specified equipment,
each traversing overlapping the adjacent traversing or compacted area by 0.2 m., by which pass
separate payment shall not be paid. Compaction must meet both the method and performance.
e) The Supervisor can request an increase or decrease in the thickness of the layers. If its necessary to
increase or decrease the thickness of the layer, the number of free passes shall be adjusted in
proportion to the thickness. Satisfactory methods for the compacting of other materials that are not
previously listed can be used, such as caterpillar tractor and vibratory rollers. When such alternative
compacting methods are used, the Supervisor shall determine the appropriate number of free
passes and the maximum thickness of the layers before compacting.
4.2. MA TERIALS
Materials to be used in the construction of earthworks fillings should be of suitable soils, granular materials,
rock and various materials approved by the Supervisor.
All the materials used in the constructions should be clear from leaves, hay, roots, and other perishable
organic materials.
The materials that will be used in the construction of earthfills shall be of granular or rock nature, and
when soils and heterogeneous materials are used, their liquid limit should not exceed thirty (30) or
maximum limits defined by Chilean law, whichever is less. The maximum plasticity index of the soils with
liquid limit shall not exceed the requirements of Chilean law.
The maximum dimension of the stones that can be incorporated in the fillings and earthworks should not be
higher than 3/4 of the height of the compacting layers, except otherwise disposition by the Supervisor. The
quantity of stones with dimension > 0.6 of the height of the layer should not overcome the 20% in volume.
The material placed less than 50 centimeters from drainage pipes and sewers shall be well graded,
without stones with dimensions more than 10 centimeters.
The material shall not be accepted if in the Los Angeles (L.A.) abrasion test, the loss (using gradation A)
surpasses the 20% in weight, for 100 revolutions.
PAGINA PAGE
INGEGNERIA
12 di/of 73
4.3.1. Generalities
Earthworks shall be constructed with materials coming from the excavation, according to these
Specifications and in accordance with the alignments, slopes, profiles, cross sections, and dimensions
indicated in the drawings.
The material for the construction of the earthwork should be placed in consecutive horizontal layers, except
in slopes of solid rock in which only one layer can be placed with enough thickness to allow the work of the
construction equipment, having previously proceeded with the grading of the rock, according to the
indications given by the Supervisor, in order to ensure a satisfactory stability of the earthwork. Hillsides not
made with solid rock or narrow earthfills adjacent to existing slopes should be compacted from the foot of
the slope inwards, at a distance enough to ease field operations of transportation and compacting.
Saturated or unstable materials found shall be removed and placed as specified before.
The Contractor, without additional cost to the Owner, shall replace or repair all the sections of the earthwork
that have been damaged or displaced because of his lack of care or negligence.
a. The layers of such materials should not exceed one (1.00) meter of thickness (loose) and they will be
different depending on the maximum size of the materials that are being placed.
The material should be dumped and spread in order to form with the fragments of the largest rock
the exterior part of the slope of the earthwork and with the smallest fragments of the material
should form the interior part of the earthfill, filling the hollows found.
The maximum thickness of the dumped material shall not exceed the depth at which it has been
deposited by the transportation equipment. It is strictly forbidden to dump material from heights
higher than two meters without being placed in layers as it has been described.
CODICE CODE
PAGINA PAGE
INGEGNERIA
13 di/of 73
b. In general, the rock will be placed in such a way that forms the base of the rock fill to up and down
the cross section, in the slope or side slopes of an earthwork in construction or already made,
which requires a widening or where the surplus of rock can be dumped, or in the side slopes or in
the crest of a compacted earthwork, built with materials that do not consist in rock.
c. Before placing a rock fill above a compacted earth fill, it will be given to its upper part a grade of
approximately ten percent from the center to the sides, and it will be carefully compacted all the
loose material. The rock will be placed in such a way that water cannot drain the voids contained
within the filling material.
d. The rock fill should be placed in layers, in which the height does not exceed one meter and work
should be performed as ordered by the Supervisor. The rock that cannot be incorporated in the
layers of one (1.00) meter of thickness, should be reduced in sized until this is possible, or be
substituted by a volume of equivalent suitable material, according to the same specification,
without any additional cost due to the substitution of materials. Special care should be placed in
the placing of the rock so the side slopes are substantially in accordance with the requirements of
the drawings.
The soil-lime mixture composition shall be fixed in accordance with results of laboratory tests.
Before beginning the intervention, the Contractor should carry out tests upon the different types of mixture
to be used in the works.
The soil-lime mixture is considered suitable if has the following minimum characteristics:
lime initial content >1,5%;
C.B.R. index >30%
reinflation after four (4) immersion days <1,5%
compressive strength Rc>1,2 MPa
In any case, the restoring shall be done according to ASTM D 558 (AASHTO T-134) Relationship Density
Moisture in Mixtures of Soil Cement.
4.4. SETTING
After the discharge, the material shall be spread by means of a bulldozer, shovels, or any other approved
equipment in layers horizontally as possible.
Stone of superior size to that one accepted shall be removed before staring the compacting operations.
The setting should be carried out in such a way to ensure a good homogeneity of the materials and prevent
the segregation.
The water content of the non-classified material of each layer should be able to gain the maximum
compacting rate. Humidifying of the material can be carried out in the site of excavation or in the area of
compacting.
CODICE CODE
PAGINA PAGE
INGEGNERIA
14 di/of 73
The setting of the material directly against the structures, sewers and piping shall be carefully carried out, in
such a way that prevents from damaging the permanent works.
The fill shall not be set in contact with the concrete structures before at least 14 days have passed after the
pouring.
4.5. COMPACTING
In compacting earth fills within narrow places or ditches for pipes and other structures, automatic tamper
equipment can be used, such as pneumatic or gasoline engine tampers, or vibratory tampers.
The non-classified material and the granular material shall be consolidated after the setting.
The dry density of the compacted material should not be less than 95% of the maximum obtained with the
modified Proctor test, determined by the AASHTO T180-734 test, D method.
En each case, the layers of filling or earthwork with non-classified material shall be compacted with no less
than six (6) complete passes with vibratory roller, with a weight of the vibrator drum not less than 15 kg per
axis centimeter, or other roller that makes an equivalent compacting rate. Each pass should overlap the
adjacent one for at least 40 centimeter. The rollers speed should not exceed 2 km/hr.
The zones of the earth fills and earthworks that are not accessible through rollers shall be compacted with
impulse tampers or vibrant plate tampers, until reaching a compacting rate not less than the one specified.
The setting and spread of new material in areas where compacting has not been finished shall not be
allowed.
In the case that during the excavation or compacting of the platform a fumarole is found, the disturbed
material should be overexcavated and restored up to the depth indicated by the Supervisor.
In the restoring with rock in the zone of the fumaroles, the Contractor shall not have the right to any
additional economical compensation.
The compacted filling should begin in the site or sites defined by the Project and approved by the
Supervisor, and it should continue until it is finished according to the drawings and specification.
During the compacted filling process, the zone should be kept well drained at all times.
Slopes, fills and chutes damaged by erosion during the construction of the fillings, should be re-graded by
the Contractor without any additional cost for the proprietor. Dirt or other various materials should not be
dumped or stored over the project.
In the general earthworks, when a filling is carried out over concrete pipes, the use of heavy compacting
equipment shall not be allowed until achieving a minimum fill of one (1.00) meter over such structure.
4.6. MAINTENANCE
The Contractor shall be responsible for the maintenance of the earthworks during and after the construction
until the acceptance of the Work.
In case of landslides or erosion in any part of the earthwork, the Contractor shall remove the material from
the slumped or eroded zoned, and should rebuilt such part of the earthwork.
In case the landslide or erosion is due to the Contractors failure, the material moving and rebuilding of the
fill or earthwork shall be carried out by him, at his costs.
PAGINA PAGE
INGEGNERIA
15 di/of 73
5. CONCRETE WORKS
5 . 2 . CON CR ET E
PAGINA PAGE
INGEGNERIA
16 di/of 73
5.2.2.1. Laboratory
The concrete mixing plant shall be supported by an internal or external laboratory, having at least the
following equipment:
- ambient thermometers (min. and max.) and thermometers for concrete;
- disposable temperature sensors, to be inserted into the concrete castings, and data logger with at least
four channels to register the temperature during the concretes hydration (http://www.hannachile.com/),
to be utilised for large scale castings.
- oven to dry the aggregates samples;
- rigid metal containers (pan, tray) for weighing solid materials;
- complete set of sieves (base set plus series 1, in accordance with EN 12620);
- Ohaus precision mechanical scale, capacity of 20 kg and sensitivity of 0.1 g with set of weights;
- one 50 kg scale, sensitivity of 5 g;
- equipment to measure the sand equivalent and the methylene blue value in accordance with UNI EN 933-
8;
- pycnometers in accordance with UNI EN 1097-6;
- graduate cylinders of various capacities;
- rigid containers for measuring the density of fresh concrete, in accordance with the standard EN 12350;
- ethilic alcohol for measuring the composition of fresh concrete and the water/cement ratio, in accordance
with UNI 6393 (or AASHTO T 318 Water Content of Freshly Mixed Concrete Using Microwave Oven
Drying);
- Abrams cones in accordance with UNI EN 12350-2;
- drum type laboratory cement mixer having a capacity of 100 litres;
- adequate number of cubic moulds, 15-20 cm on the side, complying with the standard EN 12390-1,
manufactured by a company with a certified quality system;
- conditioning water storage thank / moist storage room. capable of ensuring continuously a temperature
within 18 and 22C and a relative humidity of 95%;
- class 1 testing machine for compression tests (minimum 200 t) complying with EN 12390-4;
- sclerometer (or rebound hammer).
PAGINA PAGE
INGEGNERIA
17 di/of 73
All abovementioned documents can be inspected by Enel and the producer must change its operating
procedures as requested by Enel.
In any case, Enels approval does not imply that Enel assumes responsibility and, therefore, it does not
modify or diminish the Contractors responsibility.
On the basis of the above considerations, the concrete mixing plant shall have the characteristics of class
B plants (Enel classification.)
Pre-qualification and qualification tests are compulsory. Checks in accordance with the requirements of
tables 5-1 and 5-6 must be carried out before and during the supply as well as in all cases in which, in
Enels final opinion, there are doubts regarding the materials characteristics and/or performance. The
plants shall be automated and, in any case, shall comply with the instructions contained in the attached
Guidelines.
5.2.4.1. Cement
Portland slag cement (cemento siderurgico) 350 or Portland Pozzolana cement (cemento puzolanico) 350
shall be used (in accordance with standard NCh 0148); the cement shall have a compliance certificate
issued by a qualified laboratory.
The particle size distribution curve of the combined aggregate shall fall within limit grading curves
constructed with tolerances of 10% relative to the design grading curve, which shall be that of Fuller or
Bolomey.
The aggregates maximum nominal diameter shall be the smallest of: the minimum distance between the
reinforcing bars, one fifth of the structures minimum dimension and the bar covers value.
For pumped concrete, the sands fineness modulus, measured in accordance with Appendix B of the
standard UNI EN 12620, shall be between 2.4 and 3.0, and the percentage passing through the 0.25 mm
sieve shall be between 10% and 20% by weight, the percentage passing through the 0.125 mm sieve
shall be between 5% and 10% by weight.
PAGINA PAGE
INGEGNERIA
18 di/of 73
CODICE CODE
PAGINA PAGE
INGEGNERIA
19 di/of 73
The content of material passing through the 0.25 mm mesh sieve, referred to the maximum size of the
aggregate, i
Concentration of fines as a function of the aggregates
maximum size
Maximum size of the aggregates Maximum fines content
(mm) (including cement) kg/m 3
8 525
16 450
32 400
50 350
The compliance of the aggregates and their mixtures with the requirements of the standards cited above
shall be attested by suitable tests performed by an official laboratory, which shall issue the certificate in
the form of a technical report which the Contractor (to his cost) shall submit to Enel.
5.2.4.3. Water
The mixing water shall comply with the requirements listed at point 4 of the standard UNI EN 1008:2003
and the analyses and checks shall be performed utilising the methods indicated thereby.
Water reclaimed from the concrete industrys processes may be used, in accordance with the requirements
at point A.2.1 and those at point A.4 of said standard.
The water shall have the characteristics listed at the attached Table 5-4.
5.2.4.4. Admixtures
The admixtures, whose characteristics shall comply with the requirements of
Tabella 5-4, shall be certified in accordance with the standard EN 934. The utilisation procedures
shall comply with the additives manufacturers requirements.
The admixtures used shall be supplied by a sole manufacturer, which shall certify their compatibility.
The Contractor shall provide the products approved by the Works Management, and their transportation
and storage at the worksite; it shall then utilise them adhering strictly to the utilisation instructions
prescribed by the additives manufacturer.
Superplasticizers
When building the power plants works, all concrete shall be produced utilising a superplasticizer-hardening
accelerator additive with high water reduction/in accordance with UNI 10765:1999:
Type Pozzolith NC 534 http://www.basf-
cc.com.ar/es/productos/aditivosparahormigon/PlastificantesAcelerantes/PozzolithNC534/Documents/Arg P
ozzolithNC534.pdf
Accelerating admixtures
In cold climates (see 5.3) accelerating admixtures must be used in combination with the superfluidifier and
utilising means of heating the concrete. A product of the type
POZZUTEC 20 or MASTERMIX NC 534 shall be used.
(http://www.basf-
Cc.com.br/PT/produtos/aditivos/POZZUTEC20/Documents/POZZUTEC%C2%AE%2020.pdf or
equivalent, complying with the standard EN 934, made up of nitrates, formates, and triethanolamine,
dosed at a rate of about 1-2% of the weight of the concrete.
CODICE CODE
PAGINA PAGE
INGEGNERIA
20 di/of 73
The solution utilised shall be free of chlorides so as not to be aggressive towards the reinforcements.
The admixtures explicitly denominated antifreeze are included within this type of additives.
The Contractor shall provide the accelerator approved by the Works Management, and its transportation
and storage at the worksite; it shall then utilise it adhering strictly to the utilisation instructions prescribed by
the admixtures manufacturer.
Because of the utilisation conditions, the company shall consult with the manufacturing firms with regard
to the combination of the plasticising and accelerating admixtures, in any case submitting its choices to
Enel. The products shall be always available at the worksite.
The Contractor shall verify their chemical-physical characteristics as well as their infrared spectroscopic
analysis attesting that the product utilised during the work meets the specifications declared and verified
when the admixture was adopted in the mixture's design.
Evaporation reducers
A surface evaporation reduction treatment of the CONFILM type from BASF shall be used to correctly cure
the castings of plinths and other horizontal surfaces and to avoid cracks caused by plastic shrinkage, also
when insulating blankets must be installed on the surfaces. The product, type http://www.basf-
cc.com.br/PT/produtos/superficie/CONFILM/Pages/default.aspx, complying with the standard ASTM C 309-
07 type I, shall be sprayed on the surfaces on which continuation of the casting is not planned. The
utilisation of this product will avoid covering the horizontal surfaces with wet nonwoven fabric or plastic
sheets to ensure adequate curing. The use of water is forbidden.
The Contractor shall provide the evaporation reducer approved by the Works Management, and its
transportation and storage at the worksite; it shall then utilise it adhering strictly to the utilisation instructions
prescribed by the admixtures manufacturer.
In the case of architectural concrete, it must be verified that the curing method planned does not yield
defects such as stains, fading, or other.
Enels authorisation is required to utilise any admixtures different from those listed above, and in any case
complying with the types of UNI EN 934-2. Before using them, the Contractor shall submit to Enel a study
and test results showing the type of additive to be used, the expected effects, and the advantaged of the
proposed application.
The pertinent essential information extracted from that included in the appendix ZA of UNI EN 934-2 shall
be included in the certification. The manufacturers must operate with a quality management system
certified in accordance with UNI 9001.
Expanding agents
In special cases and subject to specific approval by the Enels Works Management the use of admixtures
with expanding agents to limit shrinkage can be authorised (Stabilmac from MAC S.p.A. or equivalent)
http://www.basf-
cc.com.br/PT/produtos/grautes/MASTERFLOW490/Documents/MASTERFLOW%20490.pdf
Silicafume
A micro-silica based additive (Silicafume) of the type Rheomac SF 100 shall be used in newly constructed
structures intended to contain water or which in any case come into contact with the systems geothermal
fluids (e.g. new tanks for cooling towers, new reinjection tanks, new first flush diverter, etc.) and wherever
Enel requests it
http://www.basf-admixtures.com/en/products/silica fume/rheomac sf100/Pages/default.aspx the
dosage shall be prescribed by the manufacturer and approved by the Enels Works Management.
CODICE CODE
PAGINA PAGE
INGEGNERIA
21 di/of 73
Tabella 5-5. A homogeneous concrete is a concrete made with the same component materials and
with the same characteristic strength.
5.2.5.1. Durability
Because of the works conditions and peculiarities, all concrete shall be made with slag or pozzolana
cement and with a water/cement ratio of 0.45; moreover, plastic micro-spheres with antifreeze function
shall be added for the parts exposed to the weather. These conditions guarantee the works durability.
5.2.5.2. Requirements for the materials to be used, water content
The materials used to prepare the concrete shall be perfectly suitable and shall be approved by
EnelsWorks Management.
Enel may request concrete with specific colour characteristics to satisfy architectural needs and only for
visible parts after the works and yards are completed.
In any case, the materials must correspond to the requirements of the European Standards, to which
reference is made for the type and number of checks and tests to be carried out on the materials, unless
otherwise specified in this Technical Specification.
The water/cement ratio shall be that given by the design indications and comply with standard EN 206, in
order to produce highly impermeable and compact concrete and to improve resistance to carbonatation
and to chloride attack; only when the design indications are lacking, a water/cement ratio no higher than
0.45 shall be employed for all reinforced concrete elements.
The control of what was described above is carried out, upon request by Enels Works management, by
verifying both the water introduced into the mixture and the inert materials moisture content (method
UNI 6393-1998.)
5.2.5.3. Concrete resisting freeze-thaw cycles
Hollow micro-spheres of the synthetic material Addiment MSC-AER SOLID shall be used for concrete
exposed to the surrounding environment, characterised by low temperature and possibly by freeze-thaw
cycles
CODICE CODE
PAGINA PAGE
INGEGNERIA
22 di/of 73
http://www.addiment.it/pdf prodotti/MSC%20AER%20SOLID.pdf ;
the spheres serve the same function as the air bubbles from aeration; they shall be used in amounts and
with the methods complying with the instructions in the products technical sheet.
The Contractor shall submit to the approval of the Works Manager the devices and methods of application
of the product.
5.2.5.4. Lean and filling concrete
Lean concrete for the foundations footing (lean concrete), for drainpipes support, etc, shall be dosed at a
rate of 150 kg of cement (type NCh 0148 high strength class 32.5 N/mm 2) for each m3 of mixture.
In special cases, Enels Works Management can request the use of lean concrete dosed at a rate of 50 kg
of the allowed cements and with inert material having a maximum size of 10 mm to make fillings etc.
5.2.5.5. Premixed concrete
Enel may authorise the Contractor, upon documented request, to procure premixed concrete from the
areas concrete mixing plants.
The Contractor shall, sufficiently in advance of the start of the pouring, carry out the investigations
required to define in detail the origin and characteristics of the materials to be used. These shall be
submitted to Enel for approval and Enel can demand that test castings and subsequent laboratory tests be
performed, all this at the Contractors expense.
5.2.5.6. Concrete casting off the works
Some items (conduits and/or cover slabs) must be prefabricated in accordance with the designs
requirements or as requested by Enels Works Management, by building light structural concrete products
having a minimum compression strength of Rck 25 N/mm 2 through castings off the works; the Contractor
can make these also outside the worksite.
The cover slabs shall be such that they can be joint-fitted to the works already prepared to receive them.
PAGINA PAGE
INGEGNERIA
23 di/of 73
The Contractor shall perform the tests indicated in the attached Table 5-6 on the samples collected.
After 9 positive results are obtained on each type of concrete tested, the correlations obtained in the pre-
qualification phase shall be used, if appropriate, to make the necessary adjustments to the mixtures, which
will then be understood to be qualified.
Each mixture shall be univocally identifiable also in retrospect; to this end, all qualified mixtures must be
suitably identified through the following information:
- date of issue;
- concrete mixing plant(s);
- codes and origins of the raw materials utilised;
- amounts of raw materials to be utilised to make one m 3 of concrete with different dosages of cement per
m3;
- dosages of cement needed to obtain the indicated Rck;
- dosages of additive to obtain the indicated consistencies.
The characteristics of the materials to be used (including, for the cement, the make and the production
plant), as well as the composition, mixing time and preparation procedures of the various mixtures, defined
in the qualification tests, are binding on the Contractor and cannot be modified in any manner without
Enel's prior authorisation.
If the above parameters change, the Contractor must repeat the pre-qualification and qualification tests of
the mixtures.
5.2.6.3. Tests during the work
In general, the tests in the course the work shall be performed in accordance with the standard EN 206,
with the local standard regulations, and with the additional standards requested by Enel and listed
hereafter.
The Contractor shall carry out, in addition to the analyses and tests required by the regulations in effect,
also all those indicated in the following tables, with the frequencies thereby indicated.
- Table 5-2 for the cement;
- Table 5-3 for the inert materials;
- Table 5-4 for the water;
- Table 5-5 for the additives.
- Table 5-6 for the concrete mix.
The original certificates of the tests conducted must be submitted to Enel. Any other tests that the
Contractor might perform within the scope of its responsibilities to ensure the constant quality of the
concrete mix, including the procurement of the components, must be made available upon Enel's request.
The tests required in table 5-6, at the respective frequencies, shall be carried out for each type of concrete
to be utilised in building the works from among the concrete types listed in table 5-1 and, within the scope
of each class, for each homogeneous mixture. Concretes made from the same raw materials and mixed
with the same water/cement ratio and capable of guaranteeing the same characteristic strength are
considered homogeneous.
5.2.6.4. Control of compression strength in the course of the work
Unless otherwise required by Enel, the concrete specimens must be collected at the time of use.
The concretes cube strength shall be checked through "acceptance tests" that shall be performed for each
structure or part of a structure, on all the mixtures utilised.
The samples must be collected in such a way that the important properties and the composition of the
concrete between the moment of sampling and that of pouring cannot change significantly.
In accordance with the standard UNI EN 12390-1 and 2, at least two pairs of test pieces shall be made with
the concrete mixture utilising cube-shaped forms.
The Works Manager or a technician entrusted by him shall identify each test cube with indelible writing on
plastic bands set into the fresh samples surface and non-removable. The samples shall be left in the
forms, protected with a polyethylene sheet, and placed in enclosed spaces at a temperature between 15
and 20oC. After 16 hours, but no more than 3 days, they shall be transferred to the laboratory, removed
from the forms, and placed into a storage moist room at a temperature of 20 2 o C and at a relative
humidity 95%, or else in water at 20 2o C.
For reinforced concrete, the first pair shall be tested at day 7 and the second at day 28. Tests shall be
performed at days 3, 7, and 28 for prestressed reinforced concrete. The average value of the strengths of
each pair shall be designated sample strength.
The sample strength values at day 3 or at days 3 and 7 shall be measured at the Works Management
laboratory and shall be used to compare with the corresponding data obtained in the plants qualification
CODICE CODE
phase, for temporary accounting while waiting for the day 28 data.
If the strengths obtained at days 3 or 7 are lower than the expected values, the Works Management,
while waiting for the official data, can, in its final determination, order the suspension of the pouring and
the company cannot claim any rights as a result of this.
The sample strengths at day 28 shall be determined by the official laboratory in accordance with UNI EN
12390-3 and 4, and shall be used to verify that the strength of the concrete used complies with the design
strength. The statistical method (type B) is used for the verification; the type A method is used only for
volumes of homogeneous mixture smaller than 1500 m3.
An acceptance test of type A refers to an amount of homogeneous mixture no greater than 300 m 3 and
consists of three samples, each performed on a maximum of 100 m 3 of poured concrete. At least one
sample is collected for each day of pouring. The results for each set of three samples must be:
Rm >_ Rck + 3.5
R1 >_ Rck - 3.5
where Rm is the average strength and R1 is the lowest strength for the three samples, while Rck is the
characteristic design strength. The obligation to sample daily can be waived for amounts of homogeneous
mixture lower than 100 m3.
The type B check, referred to a homogeneous mixture, shall be performed at a frequency no lower than
one check for each 1500 m3 of concrete. At least one sample shall be collected for each pouring and a total
of at least 15 samples shall be collected for the 1500 m3.
The following inequalities must be verified:
R1 >_ Rck - 3.5
Rm >_ Rck + 1.48 s
where s is the standard deviation.
Nothing shall be due to the company if the strength Rck is higher than that indicated in the design
documents.
The coefficient of variation v shall not exceed 15%; if the above limit is exceeded, the pre-qualification
and qualification tests must be repeated.
With regard to the compression strength tests, in order to guarantee the univocal correspondence between
the works and/or or parts thereof and the respective control samples, the Contractor shall:
- submit to Enel at least three days in advance, the weekly schedule of pouring and of the related control
sampling, drawn in accordance with the attached model;
WEEKLY SCHEDULE CASTING AND POURING CONTROL Sheet n
SITE RELEVANT TO STANDARD CONCRETE MIX CONTRACTOR
...............................
FROM ................. TILL
CONCRETE MIX CUBIC METERS SAMPL ES
DAT E IT EM ITEM DESCRIPTION TYPE N. CONCRETE NOTES
HOMOGENEUS PO URED CODE
also submit, within three days, the weekly summary of the castings done and of the respective
samplings carried out, drawn in accordance with the attached model;
CODICE CODE
PAGINA PAGE
INGEGNERIA
26 di/of 73
- the structures are protected to prevent fast drying, which would hinder the hydration of the cement at the
surface of the structures;
- the protection and insulation are maintained ensuring the strength development until the strength level
required to remove the supports and forms, 3.5 (5) N/mm 2, is reached;
- abrupt temperature variations are avoided.
5.3.1. Concrete mixing plant
In addition to what was specified above with regard to the mixing plants (see point 5.2.2), the Contractor
shall take the precautions and equipment specifically needed to produce concrete in a cold climate.
Specifically, before the production of the concrete mixture is started, the equipment needed to ensure the
compliance with the limit temperature levels during production must be present at the worksite (Table 5-1 -
Specifications and tests for cement - Sheet 1 of 1):
- heating system for the mixing water (generally avoiding temperatures in excess of 80C and adding the
cement to the mixture only after blending the water and aggregate);
- heating system for the aggregates, for example through steam circulation pipes or direct steam injection,
to be utilised if heating the water is not sufficient to free them from ice and frozen clumps;
- a system to protect the heated aggregates to limit their excessive cooling could be required;
- a heating system by steam injection into the concrete mixture in the mixer is allowed; the Contractor shall
demonstrate that a system to control and verify the water dosage at the end of mixing is put into place.
Table 5-0 - Concrete temperature at the concrete mixing plant and during pouring
In order to obtain the required pouring temperature, the water and aggregate might require heating
(see 5.3.1)
The following equation shall be used to calculate the concrete's temperature from the known
temperatures of the components:
where
CODICE CODE
PAGINA PAGE
INGEGNERIA
27 di/of 73
5.3.2. System for the transportation of the cement mixture to the works
The system shall be adequate to guarantee the specified characteristics of the concrete mixture
until unloading at the site. The requirements concerning the temperature of the concrete in the form
at the moment of unloading, contained in Table 5-1, line 1 shall be complied with.
The concrete mixture shall be transported from the concreting plant to that of use, utilising vehicles and
equipment suitable to avoid the segregation of the various components of the mixture, the deterioration of
the mixture, and its cooling.
5.3.2.1. Efficiency of the cement mixers
The concrete truck mixer shall keep the drum in constant motion from the moment of loading until the
end of unloading; they shall be inspected periodically (each 4,000 m 3 or at least once per month) to verify
the decrease in efficiency due either to accumulation of hardened concrete or binder or to the wear of the
blades.
To this end, a homogeneity test shall be performed monthly; it shall be done on two samples: the first
after having unloaded 20% of the concrete, the second after 80%.
The test shall compare the difference in workability, coarse aggregate content, water content, and
water/cement ratio in the two samples. The difference must not exceed 10% for all values being compared.
5.3.2.2. Precautions to be adopted for transport in cold weather
The minimum temperature of the fresh concrete after pouring shall not be lower than that indicated for
the various conditions at line 1 of the Table 5-1.
The temperature at the concrete mixing station shall therefore be such that it compensates for the cooling.
The foreseeable hourly cooling during transport in a concrete truck mixer is estimated by the equation:
T 0 .25(Tr Ta )
Where Tr is the requested temperature (line 1 in the table) and Ta is the air temperature.
If the concrete mixture arrives at the site at a temperature 4 or more below the required temperature,
the concrete shall not be utilised.
In any case, the concrete must be poured as soon as possible after mixing (or after arriving to the
worksite) in order to minimise the cooling and loss of workability; the concrete mixture shall be unloaded as
near as possible to the place of casting.
5.3.3. Pouring
5.3.3.1. General considerations
The Contractor shall submit the pouring procedure to Enels approval adequately in advance of the start of
pouring; this shall show in particular:
- the pouring methods;
- the planned quantity of concrete to be poured, in m 3;
- the plan for the utilization of the personnel and equipment involved (cement mixing lorries, pumps,
vibrators, etc.);
- the thicknesses and dimensions of the castings;
- the covering times;
- the possible interruptions;
- the curing of the castings with emphasis on the insulation methods and on the minimum times planned
for the removal of the forms.
5.3.3.2. Preparing the Pouring
Before pouring the concrete the foundations should be clear of water. Therefore, wherever is necessary,
the Contractor should install pumps and piping or carry out drainages and other facilities.
At the moment of pouring the concrete, the foundation surfaces should be moist.
Rocky surfaces, corresponding to the final line of the structures foundations, should be carefully washed
and cleaned using compressed water and air.. Every loose rock piece should be removed by hand or by
CODICE CODE
PAGINA PAGE
INGEGNERIA
28 di/of 73
Cracks that cannot be washed and the cavities inaccessible by hoses should be excavated and washed by
hand, leaving them thoroughly clean.
The foundation surfaces in common material should be perfectly leveled, compacted by manual and/or
mechanical means until a firm and homogenous support surface is achieved.
Areas containing clay, silt, and loose materials should be cleaned by taking away such substances until firm
ground is reached.
Before starting the pouring operations, the Contractor shall ensure that the bases and forms are carefully
prepared and that the reinforcements and inserts are carefully set up, so that the castings will be perfectly
regular and in compliance with the design.
Moreover, all materials and devices ensuring that the required concrete temperatures are obtained and
maintained must be at the worksite before pouring begins.
The Contractor shall ask Enel to check the formwork, the reinforcements, and the inserts; it shall also ask
for authorisation to carry out the casting. The lack of said advance authorisation can be sufficient reason
not to accept the castings.
The concrete shall not be poured when it snows or rains.
It is necessary to adopt suitable precautions guaranteeing the perfect execution of the structures because,
for all castings and during all seasons, as stated above, it is possible that the temperature falls below 0C.
Besides complying with the requirements of this specification, the Contractor shall constantly take into
account the recommendation ACI 306-88, Cold Weather Concreting.
PAGINA PAGE
INGEGNERIA
29 di/of 73
- scarification of the fresh castings surface to be done by pressurised water and air jet within a time interval
between the start of setting of the concrete (determined through the ASTM test C 403) and 1.5 said
time, as long as no impression is left on a touch test;
if the above cannot be done within the abovementioned time interval, retarding admixtures can be used by
applying them to the castings surface, without prejudice to the method of verification of the time of
intervention through the touch test;
if the time gap for restarting the pouring is longer, in any case less than 72 hours, it is necessary to
interpose a layer of cement mortar (dosed at 350 kg/m 3 of cement) as a connecting element between the
old and new pouring surfaces.
If the pouring cannot be done within the abovementioned time intervals, the Contractor shall submit to
Enels approval, in the context of the abovementioned pouring procedure, the adoption of specific
measures, such as, for example, the use of resins (epoxy-polyamide or water-compatible epoxy resins) as
a connecting layer between the old and new concrete and/or the use of connection rebar.
For cold joints
If the Contractor requests it, Enel can authorise restarting the pouring at positions not envisaged by the
design. To this end, the Contractor shall submit to Enels approval, with adequate advance relative to the
start of the pouring, a study showing the position of the proposed joints, the pouring sequence, and the
precautions that it intends to adopt to guarantee the continuity of the castings, also by inserting connection
reinforcements.
In any case, it will be necessary to clean the surface by scarification with pressurised water and air before
pouring.
It must be verified, in this case too, that the temperature of the already hardened concrete is at least 2C.
PAGINA PAGE
INGEGNERIA
30 di/of 73
- during the colder months, precautions shall be employed aimed at preventing the freezing of the
concrete even if the pouring or night temperature reaches very low values (see 5.3.5.2, 5.3.5.3, 5.3.5.5).
These precautions must later ensure the curing and maturation.
The time of protection against freezing can be calculated on the basis of the concretes curing degree.
The concrete can withstand a freeze-thaw cycle when its compression strength has reached 5 N/mm 2 (ACI
3.5, v.5.1)
The protection is necessary also at the end of the curing, after the forms have been removed, to stop the
premature drying of the concrete surface, which is facilitated by the wind and dry climate. Drying decreases
the durability and strength characteristics and can induce cracks from plastic shrinkage. For this purpose,
the following shall be used:
- anti-evaporating agents to be applied to the fresh concretes surface as soon as it has been finished, see
5.2.4.4 insulating films.
Using water is neither allowed nor possible. Keeping the formwork up protects the surfaces in contact
with it.
5.3.5.2. Curing
The concrete must be carefully protected and cured, especially in the outer areas, in order to achieve its
expected potential performance. Curing of the concrete must start as soon as possible after its compaction
and finishing, together with the protection.
The concretes curing process shall ensure that the temperature in the structure stays constantly above
the limits of line 1 of Table 5-1, for the time needed for the required maturation and to reach the minimum
resistance of 5 MPa. Under some conditions, a suitable insulation can be sufficient to achieve this
objective, because the hydration of the cement generates heat.
The strength of structural elements having strength requirements at the time of removal of the forms
and supports shall be specified by the designer.
5.3.5.3. Curing methods
The curing methods, which must suit the various climatic conditions, shall be agreed upon in advance
with Enel before work starts at the site.
Correct curing can be obtained by insulating or heating the structures:
- by utilising insulating forms;
- by leaving the forms in place;
- by covering with insulating blankets the surfaces exposed to the atmosphere after the forms are
removed, see 5.3.5.5;
- by building enclosed shelters around the structures to be protected
- by utilising heating methods through steam circulation within said shelters;
- utilising electrically heated blankets;
- by heating the concrete after pouring through the Joule effect, with pre-inserted insulated electrical
conductors.
These methods can be utilised individually or in combination with each other, taking into account
the specific climatic conditions.
Table 5-3 - Minimum duration of curing time in days for exposure classes
XC1, XC2, XF1, XA1, XC3 and XD1 (2 and 5a)
CODICE CODE
PAGINA PAGE
INGEGNERIA
31 di/of 73
Concretes temperature ~
Ambient
during aging y 5 10 15
In the cases where the concrete is exposed to severe abrasion or exposure conditions, that is in
the exposure classes XF2, XD2, XF3, XA2, XC4, XA3, and XD3, the curing time must be extended.
5.3.5.5. Insulation
The insulation type shall be chosen depending on its thermal resistance, in accordance with the
indications of the tables in Appendix A. These tables allow obtaining the needed insulation R value for
walls and aboveground slabs, or for thin elements lying on the ground, as a function of the structures
thickness, minimum air temperature, and cement dosage.
If the forms are made of wood, their thermal resistance is added to that of the insulation.
It is possible to use folding insulating blankets of the type:
http://www.pregis.com/LinkClick.aspx?link=brochures%2FPregis Concrete Curing Brochure 10-
07.pdf&tabid=519&mid=688
The forms must prevent the loss of heat from the pouring, in order to ensure a regular development of
the strength. To this end, it is necessary to use insulated forms of the type:
http://www.maxkatzbag.com/mkb/blankets.html
Figure 1 Guide for the maximum value of T between the surface and centre of the casting
PAGINA PAGE
INGEGNERIA
32 di/of 73
5.3.6. Tolerances
The following tolerances are allowed for the castings:
Verticality
- surfaces and edges of pillars, columns, and walls: 6 mm for each 3 m, with a maximum of 25 mm for the
entire height;
- architectural corner pillars, grooves of the vertical joints and other architectural vertical characteristics: 6
mm for each 6 m, with a maximum of 12 mm for the entire height;
Planarity
- slabs: 6 mm each 3 m, 9 mm each 6 m, with a maximum of 18 mm for the entire length;
- beams, sills, parapets, horizontal grooves and other architectural horizontal lines: 6 mm each 6 m, with a
maximum of 25 mm for the entire length;
Planar measurements
- variation of the buildings lines from each required position and of the positions relative to pillars and
walls: 6 mm each 6 m, with a maximum of 12 mm for the entire length;
Dimensions
- cross-sections of pillars and beams, thickness of slabs and walls: -6 +12 mm;
- foundation structures: -6 +50 mm;
- dimensions and positions of holes and openings on slabs and walls: -6 +6 mm.
5.3.7. Casting of special structures
Special structures are those which, because of their special characteristics, such as their large size and/or
their large thickness and/or the presence of a high proportion of metal reinforcement and because of the
special requirements that they must meet, require a detailed advance study of the composition of the
concrete mixture and of the pouring operations, which the Contractor must submit to Enels approval in a
timely fashion.
PAGINA PAGE
INGEGNERIA
33 di/of 73
at 48 cm from the centre, that is, at 2 cm from the surface and from point F.
alignment of termocouples
C F
Enel can request the use of disposable metal forms for some re-starts of castings (massive foundation
castings, etc.) These forms, made of ribbed metal lattice, shall be made of galvanised cold-rolled steel
ribbon, no less than 0.5 mm thick having a load to rupture over 380 N/mm 2 and major yield strength of 300
N/mm2, of the type:
http://www.ferracciaio.it/pernervometal.calcestruzzi.html
The installation procedures, including the equipment necessary for support and anchoring, shall
comply with the requirements of the forms manufacturing firm and shall be approved by Enel.
The possible tie-rods and/or parts thereof (not-removable) shall be made of metal.
After the forms are struck, the metal bindings and non-removable tie-rods shall be cut to a depth of at least
40 mm under the finished surface and the hole shall be adequately sealed with a suitable mortar of a type
CODICE CODE
PAGINA PAGE
INGEGNERIA
34 di/of 73
approved by Enel.
A similar seal shall be made for the holes of the removed bindings and/or tie-rods.
In the case of waterproof walls, the non-removable tie-rods, which must be of a type approved by Enel,
shall have elements capable of preventing water infiltration.
The forms supports shall be made in such a way that, when the forms are struck, the load on the
structures is applies with appropriate gradualism.
For some specific forms, the Contractor shall deliver the design of the forms to Enel, before the
corresponding work is started. The Contractor shall design and install the forms (including the associated
support structures) so that the values of the required tolerances are not exceeded in the castings.
Enel can request that some concrete surfaces have the required degree of finish (F1 or F2.) The surface
with the F1 degree of finish (surfaces of exposed structural concrete) shall be such that, relatively to a 1.5
m straight edge, they show continuous departures no greater than 10 mm and abrupt departures no greater
than 2 mm.
The surface with the F2 degree of finish (surfaces of concrete to be painted) shall be such that, relatively to
a 1.5 m straight edge, they show continuous and abrupt departures no greater than 2 mm.
The finish of the surface impression of the supports, compared in accordance with the standard CIB Report
No 24 (attach figures), shall be at least:
grade 2: for surfaces to be treated with a transparent water repellent protection;
grade 3: for surfaces to be over-painted with pigmented film-forming protections.
In any case, the requested degrees of finish shall be obtained not by adding material to the thickness, but
with suitable internal surfaces of the forms (planed wood, plywood lining, etc.)
The surface cohesion of the surface to be painted with thickness coatings will be over 1.5 M Pa tensile
strength of the type:
http://www.defelsko.com/applications/adhesion strength/adhesion-testing.htm ?)
Enel can request that some concrete surfaces (side surfaces of water conduits and other channelling
works) have a roughness no greater than the CPS 4 grade measured in accordance with the ICRI
(International Concrete Repair Institute) standard.
http://www.jdtechnical.com/Surface Prep-JD.htm
The Contractor shall insert suitable splines in the forms of aboveground concrete castings in order to obtain
smoothed edges.
Fretted sheet steel can be used as disposable formwork when pouring slabs for metal structure buildings.
5.4.5. Tolerances
The Contractor shall build the formworks in such a way that the tolerance values required at the preceding
section 5.3.6 are not exceeded.
CODICE CODE
PAGINA PAGE
INGEGNERIA
35 di/of 73
PAGINA PAGE
INGEGNERIA
36 di/of 73
http://www.bekaert.com/es-MX/Functional/Search/Contact%20Search.aspx?countryID={9FDA7C95-9CE6-
493C-8885-ED633F0DB4CA}
shall consist of drawn steel treads having a minimum strength of 1,100 N/mm 2 and, depending on the type
and use of the concrete, they shall be 25-60 mm long and 0.5-1 mm in diameter.
The fibres can be supplied loose or combined in bundles of 25-30 treads bound together with glue that
disintegrates either normally or quickly and soluble in the mixing water; moreover, they shall be formed at
the ends in order to guarantee adhesion to the concrete mixture.
The weights to be used per cubic metre of concrete, which can vary depending on the type and use of the
concrete, shall be determined by Enel after the tests for the qualification of the concrete have been
performed.
The fibres shall be delivered to the worksite in sealed containers and added to the dry mixtures( both of
concrete and gunite) by introducing them directly into the concrete mixer; the fibres must be distributed into
the mass during mixing, by homogeneous dispersion into the quantity of concrete prepared. The system to
introduce and mix the fibres must be approved by Enel.
5.6. MORTARS
5.7. JOINTS
Joints are intended as discontinuities of concrete structural elements due to execution reasons (seams of
CODICE CODE
PAGINA PAGE
INGEGNERIA
37 di/of 73
pouring), structural causes (need to free displacements) and in those works made to restore the structural
continuity and/or guarantee the hydraulic tightness of the works.
Compliance of the materials to the prescriptions and intended uses of joints shall be certified by the
Manufacturer's data sheets.
In particular, the ability of the joint material to bear temperature cycles and the minimum temperature in the
intended use conditions is to be certified.
Enel reserves the right to check the compliance of supplied material with the above mentioned data sheets;
in this case, the Constructor shall arrange samplings, transport and performance of tests at the official
laboratory, at his own expenses.
The Contractor shall ensure that all materials chosen to make the joints are suitable to operate within the
foreseen temperature range and shall submit the corresponding documents and certificates to Enel's
approval.
PAGINA PAGE
INGEGNERIA
38 di/of 73
PAGINA PAGE
INGEGNERIA
39 di/of 73
PAGINA PAGE
INGEGNERIA
40 di/of 73
elastic or elastic-plastic sealants, as connection elements (fillers) of structural parts for which relevant
displacements are not foreseen, i.e. elastic products for dilation joints able to bear repeated cycles of
compression and traction.
Sealings have to be made following the general instructions and indications of the data sheet of the sealant
manufacturer.
The space to be filled is to be obtained by arranging wood splints or other material with the planned section
on the formworks, before pouring. A separator made of tape or expanded polyethylene rod with closed
cells is to be inserted at the bottom of the joint. In order to obtain an appropriate sealing section, in any
case of a width not lower than 1 cm and not higher than 5 cm, it should be positioned into the space at the
depth indicated by the Manufacturer (usually between 1/4 and 1/2 of the thickness to be sealed in case of
elastic sealants, higher in case of elastic-plastic or plastic ones). The sealant is to be laid down as a
"bridge" on the separator and is to be treated in order to obtain a concave upper surface, using appropriate
shielding tapes in order to avoid dirtying. If required by the specific sealant of support status, before the
sealant, a specific primer can be applied on the surfaces.
In general, the two components, resin and hardener, are mixed before application on the support; the
mixture shall be perfectly homogeneous, of uniform color and shall harden without shrinking.
The structural adhesive is to be applied with a brush, spatula or airless system on a clean surface, free of
deposits and friable parts.
The Contractor shall correct, with the help of the supplier, the mixture composition in order to adapt it to the
conditions of wettability of the support.
The adhesive shall be a viscous liquid able to penetrate, also in terms of capillarity, into concrete pores and
to adhere permanently after hardening, in order to form a superficial layer sufficiently compact to receive
the next renewal pouring.
The same product is to be able to bind tightly, even if in different ways, to possible steel rods and other
metallic works.
In order to obtain the necessary layer, the Contractor shall pay particularly attention to the application of
the adhesive, considering that the support surface could present an alternation of more or less porous
areas and other very uneven ones where the use of the tool is even more difficult.
The laying down of the adhesive, in the quantities indicated in the project, shall be performed so to allow
the application of renewal mortars within the periods indicated in the data sheets.
CODICE CODE
PAGINA PAGE
INGEGNERIA
41 di/of 73
If adhesives are irritant, the Contractor shall require the staff to use protection equipment such as specific
gloves and glasses; if the work is carried out indoor, ensure adequate ventilation.
PAGINA PAGE
INGEGNERIA
42 di/of 73
MINIMUM CHARACTERISTIC
STRENGTH AT 28 DAYS EXPOSURE
[N/mm2] CLASSES
NOTES
CEMENT TYPE AGGRES- MINIMUM
TYPE GRADE USE
EN 197-1 SIVENESS CONSISTENCY
on cylindrical on cubic
EN 206-1
samples (fck) samples (Rck)
C20/25 20 25 - - 5
CEM IIV
C25/30 25 30 Normal XC1-XC2
Moderate XA1-XD1
Ordinary foundation structures, including
C S3/S4
1 retailing walls and floors
C30/37 30 37 XA2-XD2
CEM IIIV High
XF3 4
Moderate XA1-XC3-XD1
Ordinary elevation structures: beams,
E XF1 S4 pillars, suspended slabs, fire-barrier
C30/37 30 37 CEM IIIV walls (retailing walls excluded)
High XS1-XD2-XA2-XC4 1
XF3 4
PAGINA PAGE
INGEGNERIA
43 di/of 73
High XF1
Moderate XA1-XC3-XD1
C30/37 30 37
I CEM IIIV XS1-XD2-XA2-XC4 S4 (*) 1 Waterproofed basins and canals
High
XF3 4
Moderate XA1-XC3-XD1
L C30/37 30 37 S4/S5 Diaphragms and piles
CEM IIIV High XS1-XD2-XA2-XC4
1
C35/45 35 45 Very high XA3-XD3-XS2-XS3
LC 8/9 8 9
LC 16/18 16 18
Notes:
1 use sulfate resistant cement in exposure class XA2 and
2 the characteristic strength before formworks removal shallXA3;
be adequate to formwork type used and advancing procedure;
3 mixtures not subject to qualification tests;
4 with 3% of air for exposure class XF3;
5 not important reinforced concrete structures (water drains covered, sub-bases floors) or provisional structures;
(*) maximum aggregate size <20mm.
MAXIMIUM WATER/CEMENT RATIO AND MINIMUM DOSAGE OF CEMENT SHALL COMPLY WITH EN 206-1
CODICE CODE
PAGINA PAGE
INGEGNERIA
44 di/of 73
Notes:
1: Frequency during works per class of concreting plant: every 1000 m 3 or every month
S: test can be carried out at Site Laboratory or Supplier Laboratory;
O: Official Laboratory
In all cases that conform to standard regulation in force, Enel reserves the right to accept tests at
non-Official/Authorised Laboratories at its choice.
CODICE CODE
PAGINA PAGE
INGEGNERIA
45 di/of 73
PAGINA PAGE
INGEGNERIA
46 di/of 73
PAGINA PAGE
INGEGNERIA
47 di/of 73
PAGINA PAGE
INGEGNERIA
48 di/of 73
Tabella 5-4 Specifications and tests for admixtures - Fluidifying, aerating, superfluidifying,
accelerating admixtures Sheet 1 of 1
TESTS
CHARACTERISTICS
PAGINA PAGE
INGEGNERIA
49 di/of 73
Tabella 5-5 - Specifications and tests for reinforced concrete Sheet 1/1
PAGINA PAGE
INGEGNERIA
50 di/of 73
Tabella 5-6 - Specifications and tests for grouts and concretes for filling and anchoring
embedments - sheet 1 of 1
CHARACTERISTICS TESTS
LABORATORY
ACCEPTABILIT DURING FREQUENCY
DESCRIPTI DURING DURI NO
Y STANDARD EXECUTI DURING FOR
ON QUALIFICATION NG TES
LIMITS ON EXECUTION QUALIF. EXEC.
Air content ACI 211.1.74 1 per sample C C (1)
table 5.2.3 EN 12350-7 YES YES (2)
Consistency 1 for each pouring (1)
(slump or EN 12350 YES YES and C C
pouring) EN 12350 1 for each sample
Maintenance EN 12350 EN 12350 YES NO - (1)
of C -
consistency
Quantity of EN 12350 EN 12350 YES YES Every 5 samples (1)
C C
bleeding
Volume EN 12350 EN 12350 YES YES 1 per sample C C (1)
density (3)
Compressio (1) at least 1 every 5 m3 (1)
n strength at YES YES and at least 1 for C C (4)
7 days of EN 12390 every day of pouring (5)
ageing
Compressio No less than the at least 1 every 5 m3 (1)
n strength at average and at least 1 for (5)
YES YES C U
28 days of strength for the EN 12390 every day of pouring
ageing foundation
Temperature From 1 a day and 1 per (1)
of poured +5C to 25C ACI 301 YES YES sample C C (4)
concrete
Sheet 1 of 1
Notes:
(1) U = official test - C = site test
Except in cases where the law requires testing by official laboratory, Enel reserves the right to
accept/object to the fact that tests which must be carried out in an official laboratory are conduction in
another laboratory recognised as suitable by Enel.
(2) Table 5.2.3 related to non air entrained concrete
(3) The limit is valid during qualification: during execution, the volume density must be equal to that
obtained during qualification with a tolerance of 50 kg/m3
(4) The acceptability limits are defined after the qualification tests;
(5) Each test must be conducted on two samples the sides of which measure: 10cm for aggregates with a
maximum diameter of 6mm; 15cm for aggregates with a maximum diameter of 15 mm.
CODICE CODE
PAGINA PAGE
INGEGNERIA
51 di/of 73
Tabella 5-7 - Specification and testing of improved adherence steel systematically inspected at
each casting in the plant electrowelded mesh Sheet 1/1
CHARACTERISTICS TESTS
FREQUENC LABORATORY
ACCEPTABILIT DURING DURING
DESCRIPTIO STANDAR Y DURING FOR DURIN NOTE
Y QUALIFICATIO EXECUTIO
N LIMITS D N N EXECUTION QUALIF G S
. EXEC.
Yield stress [*] [*] YES YES (2) P/U U/A (1)
(2)
(3)
(4)
Tensile stress [*] [*] YES YES (2) P/U U/A (1)
(2)
(3)
Stretching [*] [*] YES YES (2) P/U U/A (1)
(2)
(3)
Bending [*] [*] YES YES (5) P/U U/A (1)
(2)
(3)
adherence [*] [*] YES YES (5) U U/A (1)
(2)
C (3)
Checking [*] [*] YES YES (2) P/U U/A (1)
dimensions (2)
and marking C (3)
Notes:
(1) U = Official laboratory - A = Authorised laboratory - C = site laboratory P =
Manufacturers laboratory
(2) The qualification tests (certification and marking of the rods) and the tests during execution
must comply with the requirements stated in the applicable standards and codes;
(3) For each steelworks and for each batch chosen by the Project Supervisor;
(4) Determine the ultimate stress for permanent distortion at 0.2%, if the ultimate yield stress cannot
be clearly identified;
(5) During qualification: Beam test; during execution: Calculation of LR
Appendice A
++++++++++++++
+++++++++++
PAGINA PAGE
INGEGNERIA
52 di/of 73
CODICE CODE
++++++++++++++++
PAGINA PAGE
INGEGNERIA
54 di/of 73
formworks. The scales shall be clearly removed from the exposed surfaces. The concrete that is damaged
or has honeycombing shall be removed up to solid concrete by means of chisel, and in areas prominently
exposed, an initial cut of 25 mm in depth shall be made with a diamond drill around the area with
honeycombing. The affected area shall be removed by chisel up to sound concrete and shall be replaced
with mortar or concrete, as specified. No repair of defects shall be done until the Supervisor checks it. The
methods used to repair each individual defective area in the formed concrete shall be approved. Wherever
the gradual and abrupt irregularities overcome the limits specified in the bosses shall be reduced by
bushhammering and polishing. The filling with dry mortar shall be used for hollows that have a minimum
depth of 25 mm and a width equal or bigger than the depth, for hollows left by the removal of the fasteners
of the lashing rods of the formworks, and for the cuts of narrow groves for the repair of cracks. An adhesive
resin for polysulphide-epoxic concrete shall be applied to all concrete surfaces immediately after the setting
of the dry mortar or concrete for repairs.
The concrete repair will be made using the cementitious mortar MASTERPATCH 21, by:
http://www.basf-
cc.cl/es/productos/REPARACION/MEMBRANASDEREPARACION/MASTERPATCH21/Pages/default.aspx
or equivalent. The application shall be in accordance with the manufacturers instructions. All materials,
procedures, and operations used in the repair of concrete shall be done as ordered.
All fillings shall be properly adhered to the surface of the hollows; they shall be solid and free from cracks by
shrinking and hollow areas. They should be duly cured and in concordance with the color of the adjacent
concrete after the fillings have been cured and dried. All the fillings should have enough Portland cement in
order to produce the same color of the concrete to which they will adjust. The cost of all the materials, labor,
and equipment used in the repair of the concrete shall be on the Contractors account.
Any structure that does not comply with the lines and levels within the tolerances mentioned below shall be
repaired or removed, and without any additional cost, the Contractor shall build it again. The repairs shall be
carried out according to this Specification.
ELEVATION TOLERANCE
d. Flaws in the thickness of the structural elements such as beams, columns, walls shall not
overcome 0.5 cm per meter.
e. Flaws in the central axis, angles, and elevation of the formed, embedded blocks, sleeves or any
other object embedded in the concrete structures: 0.3 cm.
CODICE CODE
PAGINA PAGE
INGEGNERIA
55 di/of 73
a. a. The requirements of the pertinent Chilean standards shall always be met as well as the more
stringent requirements of this chapter, if provided.
NCh 203 Of
2006 Acero para uso estructural
NCh 204 Of 77 Acero. Barras laminadas en caliente para hormign armado.
NCh 211 Of 70 Barras con resaltes en obras de hormign armado.
Mallas de acero de alta resistencia. Condiciones de uso en hormign
NCh 219 Of 77 armado.
b. Generalities. The Contractor shall detail, supply, cut, bend, and set the reinforcing steel as
necessary. All the reinforcement shall be free from scab, loose or scaled rust, oil, grease, and
other covering that can destroy its adherence to the concrete.
c. Cut and Bending. The reinforcing steel can be bent in the factory or in the field. All bending shall be
according to approved practical norms and shall be carried out by means of approved mechanical
methods. The heating of the reinforcement for bending is not allowed
d. Type. Unless it is ordered otherwise, reinforcing steel shall comply with ASTM A-615
"Specifications for Deformed Biller-Steel Bars for Concrete Reinforcement", grade 40, as indicated
in the drawings. The Supervisor can order the tests that are necessary to determine the conformity
of all the reinforcement with the corresponding norms and quality for the proposed used without
any cost for the Owner.
e. Relationship of the Reinforcement with the Concrete Surfaces. The drawings shall indicate the free
spaces from the edge of the master reinforcement up to the surface of the concrete.
f. For the Anchoring and Overlapping of the Reinforcement, the indications of the Regulation ACI
318-83, on developing and overlapping lengths of the reinforcement, should be followed.
g. All the reinforcement shall be corrugated, except bar# 2; corrugations shall comply with the
minimum requirements for deformed steel bars for concrete reinforcement (ASTM A-305) or
Chilean equivalent.
h. The Contractor shall submit the guarantee of the steel to be used, issued by the manufacturer,
without exempting him from any responsibility when the field and lab tests indicate otherwise.
i. Transportation and storage. Reinforcing steel should be dispatched in common bundles duly
marked, and the bars cannot be bent to ease the transportation. Reinforcing steel should not be
stored at ground level, but over platforms, stringers, or other supports in order to prevent its
contamination and rusting. The steel that is stored should be protected against mechanical
damages and surface deterioration.
The deposits should be constructed in such a way that inactive storage is not produced and the
Contractor should use the steel according to the chronological order of its arrival to the site.
5.13. BEARINGS
The laid reinforcement shall be fixed in its location by means of concrete bearings, spacers and ties. The
bearings should have enough strength to hold firm the reinforcement during the pouring operation. Bearings
should be placed in such a way that they are not exposed or contribute in any degree to the coloring or
deterioration of the concrete.
a. Tolerance in the thickness of the concrete embedment of the reinforcements: 6 mm, for less than 50
mm of embedment and 10 mm for more than 50 mm of embedment.
CODICE CODE
PAGINA PAGE
INGEGNERIA
56 di/of 73
Unless it is indicated otherwise, distance among the bars is measured between the axes of the same.
Reinforcing steel includes all relative expenses, in particular, the supply, transportation, storage, tests, cuts,
bending, cleaning, setting, spacers, waste, bearings, bonds, fastening wire, and any other necessary
element.
5.15.2. Tolerances
The specified nominal dimensions are affected by deviations in the phases of
- production (thickness, length, straightness, planarity, or other dimensions after production of a
precast unit)
- erection (local placing, verticality, horizontality, or other characteristics of the construction assembly
after installation)
- construction (a measure arising from a combination of production, setting out, site work and
erection tolerances).
The tolerance is the sum of the absolute values of upper and lower permitted deviation. The recommended
maximum production tolerance on maximum deviations on length of precast elements is:
L
l(1 0 )40 mm
1000
where L is the nominal length in mm.
The required production tolerances shall be specified in the design drawings.
CODICE CODE
PAGINA PAGE
INGEGNERIA
57 di/of 73
5.15.4. Connections
PAGINA PAGE
INGEGNERIA
58 di/of 73
necessary, the details should be such that inspection (to ensure that this has been done) can be
carried out without undue difficulty.
Connections should be designed to maintain the standard of protection against weather, fire (where
applicable) and corrosion required for the remainder of the structure.
Joints transmitting mainly compression should be designed to resist all the forces and moments implicit in
the assumptions made in analysing the structure as a whole and in designing the individual member to be
joined.
Joints transmitting shear may be assumed affective if the joint is grouted with a suitable concrete or mortar
mix and the appropriate condition is satisfied. Keyed dry joints may be used if very accurate execution is
assured.
Where continuity of reinforcement is required through the connection, the jointing method used should be
such that the assumptions made in analysing the structure and critical sections are realized.
Particular attention and special provisions should be taken for joints having serviceability requirements
related to insulation or water tightness.
5.15.4.2. Bearing
The integrity of a bearing for precast members is dependent upon two essential safeguards:
an overlap of reinforcement in reinforced bearings;
a restraint against loss of bearing through movement.
The detailed design of the sleeve and the method of manufacture and assembly should be such as to
ensure that the ends of the two bars can be accurately aligned into the sleeve. The concrete cover provided
for the sleeve should be not less than that specified for normal reinforcement.
Where there is a risk of the threaded connection working loose, e.g. during vibration of in situ concrete, a
locking device should be used. Acceptable methods for joining threaded bars include the following:
- the threaded ends of bars are jointed by a coupler having left-and-right-hand threads. This type
of threaded connection requires a high degree of accuracy in manufacture in view of the
difficulty of ensuring alignment;
- one set of bars are welded to a steel plate drilled to receive the threaded ends of the second set
of bars: the second set of bars are fixed to the plate by means of nuts;
- threaded anchors are cast into a precast unit to receive the threaded ends of reinforcement.
Resin adhesives
CODICE CODE
PAGINA PAGE
INGEGNERIA
59 di/of 73
Resin adhesives may be used to form joints subjected to compression but not to resist tension or shear.
They should only be used where they are adequately protected against the effects of fire.
Other types
Any other type of connection that can be shown to be capable of carrying the ultimate loads acting on it may
be used. Amongst those suitable for resisting shear and flexure is the prestressing across the joint.
Particular attention should be paid to detailing the joint and joint reinforcement to prevent premature splitting
or spalling of concrete in the ends of the precast members.
-
5.15.6. Examples
Some examples of possible precast construction for the works here considered are sketched below.
It must be noted that structures for liquid retaining works (tanks, reservoirs, etc.) generally need ample cast-
in-situ parts, able to connect monolithically the precast elements and safeguard the continuity of the joints
for their lifetime and the integrity of waterproofing layers.
CODICE CODE
_
Ene! Engineering & Construction S.25.CL.G.35367.00.023_0
PAGINA PAGE
INGEGNERIA
Green Power 60 di/of 73
IB reinforcing
bars
concrete
--,,0ETAILA cast insitu
_______ + +
V LJ-k1 NI
.. .. .. .. ..
..
..
,,, tendons
.. ---- -- ----
,
1 precast
l elements
3 I
-
, 3
3 ------- _,3=-----,
'I N
_ 480 1 480
FRONTAL VIEW
tenduns
PLAN - DETAIL C
BU_ _
DETAIL
SECTION B-B
SECTION A-A threaded anchor rods
p r e c a st
c o n rt n g
beam
precast plinth
precast retaining
precast retaining wall
e emen s wall element
A
bolted top
connenction for H>3.0m
foundation mat
cast insitu
CODICE CODE
PAGINA PAGE
INGEGNERIA
63 di/of 73
6. MASONRY WORKS
a. Plaster
b. Finish
c. Polish
d. Bushhammering
6.2. GENERAL
The Contractor shall submit to the Supervisors approval the samples of all the materials to be used. The
materials that are not approved shall be removed from the Work Site in a maximum time of twenty-four (24)
hours.
b. The concrete structures shall be roughened before plastering for the best adherence of the plaster.
All surfaces shall be carefully cleaned and wetted. The drill holes to place piping, boxes,
anchorages, etc., shall be preferably made before plastering; a wall shall not be finished if the
holes have not been patched and pointed and the plasters have been finished.
c. Plasters should be carefully cured keeping them wet, for at least 8 days, after they are finished.
The finish should be applied in complete panels, which surface is totally wet.
d. The plastered and finished walls shall be clear, clean, stainless, vertical, without cracks or abrupt
irregularities.
e. The walls indicated by the Supervisor shall be finished. In order to obtain a good finish, sand
should be screened dry in a 1/32 screen. The finishes shall be done with a finishing by metal or
wood trowel, followed by a sponge smoothing. In order to carry out the finish, the wall shall be well
plastered and meted up to saturation. Then non-fine surfaces shall be carefully sandpapered until
a fine texture is obtained, before they are painted.
f. When drillings are done on the walls or slabs as to place piping, plumbing fixtures, etc., after the
surface is plastered, the whole panel should be thoroughly finished again in order to avoid any
stain or restoring evidence.
g. Polishes are made with cement paste, smoothing them with sponge. In order to carry out the
polish, the wall should be well-plastered, finished, and wetted up to saturation. Polish should be
carried out over fresh finish and its final finish should not exhibit grooves or any other type of
defectiveness.
6.4. BUSHHAMMERING
Concrete bushhammering shall be made in a homogenous form, with the density and penetration indicated
by the Supervisor, for which the Contractor shall make a sample of 1.0 m2.
CODICE CODE
PAGINA PAGE
INGEGNERIA
64 di/of 73
The installation of floors directly on natural soils of any kind shall not be accepted. All bricklaying shall be
seated on a base of concrete or gravel duly compacted, with a minimum thickness of 5 cm.
7.2. INSTALLATION
Cement brick floor of 30 cm X 30 cm and 23 mm minimum thickness, with a wear layer of 2 mm thick.
a. The material, shape, dimensions, color, design of the bricks shall be those indicated in the
drawings or indicated by the Supervisor. The quality of the floor tiles shall be the best that is
manufactured or marketed in the country.
b. The mortar to be used is 1:4 parts of cement and sand respectively; both sand and cement shall
comply with that related to concrete.
c. In order to install cement bricks, a mortar layer of 2 cm average shall be used, but at any time it
should be less than 1.5 cm. The surface of the base and the brick surface shall be wetted before
placing the mortar, which shall thoroughly fill the area covered by each brick.
The bricklaying surface shall be perfectly flat. The joints among cement bricks shall be clear,
straight, and without butts.
d. Cement brick floors should be mortared with gray cement whitewash, in a proportion of 1 part of
cement per 10 of water.
e. In all areas to lay brick, it shall make sure that the cuttings are located in the intersection of the
floor and the less visible walls.
8. BLOCK PAVING
8.2.1. Template
Over the base a loose layer of fine and clean sand shall be set with a thickness not less than 3 cm, or
higher than 5, which should not have more than 3% of material screened by the 200 mesh and no more
than 10 % should be hold by the No. 4 screen; the sand surface that is not yet compacted should be similar
to the finished surface.
The sand layer shall be compacted after the setting of the stone-paving block, applying them a vibrator by
means of a slab vibrator.
Sand Seal: The sand with which the joints are filled shall be free from organic matter and contaminants and
should have the following grading:
CODICE CODE
PAGINA PAGE
INGEGNERIA
65 di/of 73
No.8 - 100
No.50 15 - 40
No.100 - 10
No.200 0 - 15
At the moment of using the sand, this one shall be dry and loose enough for the sealing of the joints, so it
can penetrate into the joints by means of sweep.
As for the sand to penetrate in the joints, a broom or plane with long and hard hairs shall be useful,
sweeping repeatedly and in different directions a moderate amount of sand.
A surplus of sand shall be left spread over the entire surface of the finished block paving for at least two
weeks, so traffic and possible rainfalls help to place the sand and with this to consolidate the seal.
Once the stone paving blocks are settled and the joints packed with mastic, it is convenient to roll over them
whether a metallic or pneumatic float, or instead of this, loaded trucks until the right level and settlement of
the stone paving blocks is reached. If necessary, a vibrator roller will help with the settlement of the joint
packing with mastic.
The filling of joints should be repeated until perfect joint packing is achieved, necessary for the stabilization
of the stone paving blocks. The filling of the joints should be repeated until a perfect packing is achieved,
which is necessary for the stabilization of the stone paving blocks.
In places where certain hollows appear, which overcome the indicated tolerance, or stone paving blocks
have been damaged, these ones shall be removed correcting the defectiveness and repeating the indicated
construction process.
Every 3 meters maximum, anchors should be used in ramps and slopes higher than 5%. These shall
consist in glue with mortar in proportion 1 cement, 4 sand, a line of stone paving blocks along the width of
the ramps and/or slopes. Mortars in the joints packing should not be used in these anchorages.
9.2. GENERAL
Structural members, frameworks, etc., shall be properly aligned and spaced. Surface irregularities and
diversions shall not be allowed (buckling, distortion, flaws in alignment, verticality, horizontality, or
parallelism)
The Contractor shall take the suitable steps for the performance of all interdependent works (for example:
settlement of columns, pitch of metallic beams through concrete structures, etc.)
9.3. LABOR
The process of manufacturing and fixture of al the metallic structure shall comply with the specifications
AISC and AWS in their most recent editions. Workers assigned to this task should be qualified, and the
CODICE CODE
PAGINA PAGE
INGEGNERIA
66 di/of 73
Contractor shall replace any worker whose capacity is judged as poor by the Owners Supervisor.
STRAIGHTENING
Straightening and leveling, when necessary, should be performed by devices acting by pressure. The use
of local hot is prohibited
MACHINING OPERATIONS
Surfaces of cuts can be rough, provided it shows tearing, shooting, lack of material or burrs.
Cutting oxygen is allowed as long as regular.
Irregular cuts must be passed through with grinders.
Shears cutting of steel plate with thickness <_22 mm is allowed, while for greater thicknesses is required
cutting flame.
The shearing of rolled profiles having dimensions <_150 mm is admitted. Profiles of higher dimensions will
be cut by saw only.
Drilling punch through to final diameter is permitted for thickness <_12mm. Perforations on thickness >12
mm should be carried out with a drill or by subsequent reaming of the hole punched.
The use of the torch for the execution of the holes is prohibited.
For the bolts tightening should be used hand torque wrenches, with or without the torque limiter mechanism
or pneumatic wrenches with torque limiter; all of this however must be such as to ensure an accuracy to the
tightening of not less than 5%.
WELDING
The following procedures may be used:
- automatic submerged arc welding;
- automatic or semiautomatic welding under gas protection (CO2 or its mixture);
- manual welding with coated electrode.
For the use of automatic or semiautomatic welding methods the contractor must demonstrate and
document the approval of the procedures obtained by organizations certified and able to establish:
- the ability to perform the main types of joints provided in the structure with a good aspect and without
internal defects, to be verified radiographically or by rupture tests on the joint;
- the tensile strength of butt-jointed must be assessed by sample transversal to the joint and that must
not be inferior to the base material one;
- the capacity of deformation of the joint, to be ascertained by test pieces which will be able to bend at
180 on the spindle equal to 3 times the thickness, for steels up to 430N/mm2 yield strength and 4
times the thickness for steels of higher characteristics;
- the resilience that must be tested at -30 C.
The samples for tensile, bending, resilience and for other mechanical tests (if deemed necessary) must be
drawn from butt welded pieces and will be chosen for this purpose the most significant thicknesses of the
structure.
With each welding process Vickers hardness HV 30 in the heat affected zone of the base metal does not
exceed the value of 350 N/mm2. When the need for thick or ambient temperature so require, it will be
necessary to apply a suitable preheating.
The welds must be performed by workers sufficiently trained in the use of related equipment and
compliance with the conditions laid down in the approval process.
If welding is carried out manually, exclusively electrodes approved and classified by the base material must
be used.
Welds made with coated electrodes must be performed by workers who have passed the qualification tests
for the class of electrode type and the welding positions provided.
The use of non-basic electrode is not allowed except for welding elements.
The electrodes must be dried in an oven at temperature of 420 C for two and a half hours and stored in
sealed containers until the moment of their use.
PAGINA PAGE
INGEGNERIA
67 di/of 73
Radiographic examination is usually conducted when the thickness exceeds 40 mm, while the ultrasound
examination is reserved for lower thicknesses.
Similar investigations spot may sometimes be required for full penetration welds in areas subjected to
compression.
Bead welds of the main structures can be tested with magnaflux in the percentage (to be established) of
their total development.
The evaluation of the results of such investigations shall be conducted in accordance with the requirements
in the reference standards.
PREASSEMBLY AT WORKSHOP
For complex structure the preassembly at workshop is appropriate, before the assembly on yard. The
preassembly can be multi-stage, as long all the connections are checked.
In the case of complex structures built in series, the only sample can be mounted in the test, provided that
the drilling is performed with a mask or with equivalent processes (for example, drilling in line numerically
controlled).
The Supervisor shall order the tests he considers necessary to determine the acceptability of the welded
joints, which shall be on the Owners account.
In particular the contractor must carry out all the geometric control on the structure and all the non
destructive test on the bolted and welded joint, as prescribed by the standard.
Tolerances of 1 are allowed on the length of each element of the structure (both vertical and horizontal)
without the sum of the tolerances of adjacent elements.
The maximum out-of-plumb allowed for the interplane is 3,5 and for the total height of the building is
1,5.
CODICE CODE
PAGINA PAGE
INGEGNERIA
68 di/of 73
The damage caused by failure of these tolerances will be charged to the Contractor
The Contractor shall correct, on his account, any defectiveness detected in the manufacturing or fixture of
the metallic structure, which shall not be a reason to extend the term of the contract.
9.6. SAMPLES
All necessary samples of the materials specified in this document shall be provided upon request of the
Owners Supervisor.
b. Before starting any work, the entire adjacent work shall be examined, of which the work the work
included in this Section somehow depends, in order to ensure perfect carrying-out and fitting.
Indeed, starting in these areas or surfaces constitutes acceptance of the same and then the
Contractor assumes responsibility for the flaws it may have.
a. Anchorages. Anchorages shall be properly installed by means of legs fixed in concrete, or bolts
fixed in lead plugs, or expansion bolts, as necessary in relation to the dimension of the pieces and
their use.
b. Fixture. The structural steel fixture shall be carried out according to the methods previously
approved by the Supervisor.
The Contractor shall provide all the heavy and light equipment in enough quantities to allow the
performance of the fixture according to the established program.
During the fixture of the structures, the Contractor shall verify the accuracy of the levels and verticality of
the same, as specified.
For the joint of the structures, the bolts shall be installed according to the requisites of the specifications
ASTM A-325, A-490.
Bolts should perfectly fit and have a length to project them at least 3 millimeters over the nut when they are
tied, and the thread be dented in the part that is projected. The heads of bolts and threads shall be
hexagonal.
Columns and other elements that rest in plates over the concrete bases shall be supported by means of
steel lifts or wedges until they are well aligned, graded and revised.
After the grading, the hollows left shall be filled with mortar without contraction, or as indicated by the
Supervisor.
In any case paint shall be applied over surfaces with oxide, dust, grease, or any other strange material.
When finishing the manufacture, all metallic work should be applied with two coats of paint in the workshop
(one of priming and the other of finish), the retouching in the work and one final finish coat of rust-resisting
paint in the work
All steel structure, after its manufacturing, shall be perfectly cleaned by efficient means of loose scales,
CODICE CODE
PAGINA PAGE
INGEGNERIA
69 di/of 73
oxidation, splash, slag or deposition, welding compounds, oil, dust, and other strange particles. The contact
surfaces in the workshop shall be clean before their assembly, but they shall not be painted. Surfaces that
shall be in contact and subject to fixation in the work shall not be painted in the workshop, nor the surfaces
and parts adjacent to the connection welding in work, which are found at a distance of at least two (2)
inches to each side of the joints.
The priming paint coat shall be high quality rust-resisting, such as Excello Rustop, which is produced by
Sherwin Williams or an equivalent.
The finish paint shall have a base of Enameloid of Sherwin Williams, or an equivalent available in Chile.
Each coat of paint shall slightly vary in color in relation to the previous coat, in order to control the
application of coats.
Before the fixture, all the metallic structure should be painted with rust-resisting paint (one coat) and the
second coat shall be applied prior authorization of the Supervisor and shall be retouched, wherever is
necessary, for the final delivery of the work.
Welding shall be carried out with a mixture of tin and lead in the proportion approved by the Supervisor, with
the laps suitable to avoid cracks in the material of the welding. Before starting the welding, surfaces shall be
cleaned with muriatic acid.
Welding in direction to the grade of the gutter shall not be allowed. Gutters shall be placed over the metallic
supports indicated in the drawings, with uniform grades towards the outlet cones in order to avoid the
formation of pools. Overloading and striking of the gutters shall be avoided as not to cause them any dents.
Downspout shall be in PVC piping and shall be fixed to the wall by means of clamps.
CODICE CODE
PAGINA PAGE
INGEGNERIA
70 di/of 73
Gutters shall be connected to the PVC downspouts by means of galvanized sheet cylinders, gage # 26,
which shall be welded to the gutter with tin and lead weld, and clinched for better stability.
The cylinders shall be fitted to the internal diameter of the downspout and shall penetrate it at least 20
centimeters. The internal diameter of the downspout should not be reduced in more than 0.5 centimeters of
diameter.
The water tables shall be placed wherever is necessary, even if it is not specified in the drawings. The water
tables shall be installed wherever is necessary.
EGP is providing the preliminary Geotechnical information available in the area. It is scope of work of the
Contractractor to execute the detailed geotechnical investigations in the area of construction of the power
plant: The Contractor is in charge to realize the geotechnical survey and to produce the geotechnical report
of each element inside the power plant. The geotechnical report must include the loads on the foundations,
retaining works, slopes. It must include the mathematical model of the soil and the step by step calculation
of bearing capacity, stability and settlements. The geotechnical survey plan will be checked and approved
by EGP.
The geotechnical survey must include at least the following tests:
- 10 boreholes 30m deep,
- SPT each 1,5m in every borehole,
- 10 CPT tests of 30m depth,
- laboratory tests :30 edometric and 30 consolidated drained triaxial tests if the soil is sampled.
The geotechnical test plan must be approved by EGP.
Each foundation must be designed considering the geotechnical informations coming from the site
investigations.
The foundation can be shallow foundations or pile foundation, in both cases the calculation of the
foundations must be done controlling:
- Bearing capacity (in drained and undrained conditions)
- Settlements (in drained and undrained conditions)
- Liquefaction
Shallow foundations must be designed considering all the loads coming from the equipments and
structures and sized considering the reduction of settlements.
The level of foundation must be checked by a Geotechnical Engineer
The piles can be drilled piles or continuous auger piles, in both cases they must be reinforced with steel
bars along all the pile
In the design of pile foundation it is not possible to consider that a part of the loads go on the slab: all the
loads must be given to the piles.
CODICE CODE
PAGINA PAGE
INGEGNERIA
71 di/of 73
The pile foundation can be designed using analytical models but the Contractor must perform some design
tests on pile in order to confirm the calculations: design load test.
The design load test must be executed until the breakage of the pile and it have to be executed with
frequency of 1 tests for 20 designed piles, during the test the Contractor must measure the load and the
displacement of the head of the pile
After the construction of the piles, the Owner will chose some piles (1 each 20 realized piles) and the
Contractor must execute the trial load test on these piles applying a load 1,5 times the design service load
after the execution of the not destructive test to check the integrity of the piles. During the test the
Contractor must measure the load and the displacement of the head of the pile
All the costs for the tests on the piles are in charge to the Contractor.
TWO-COAT PLASTER
Two-coat plaster shall be realized of the rough cast plaster referred to in paragraph
30.1 above and by an upper layer of mortar (floating coat), spread with a fine trowel,
chosen, at EGPs discretion, from one of the following types:
a) lime mortar: 0.6 m3 of lime per m3 of aggregate material;
b) hydraulic lime mortar: 600 kg of lime per m3 of sand.
The surface of the finished plaster shall be such that, with respect to a 2 metre long
ruler, there are deviations no greater than 2 mm. The overall thickness, however, shall
not be less than 15 mm.
PAGINA PAGE
INGEGNERIA
72 di/of 73
The surface of the finished plaster shall be such that, with respect to a 2 metre long ruler, there are
deviations no greater than 2 mm. The overall thickness, however, shall not be less than 15 mm.
PREMIXED PLASTER
Premixed plaster shall be applied directly on all surfaces, except on precast elements articles, with a tunnel
system.
The premixed plaster shall be vermiculite-based, of the "Monocote" or "Ready" type, and shall be applied
with a thickness of no less than 15 mm.
The finished surface shall be perfectly smooth and uniform and such that, with respect to a 2 metre long
ruler, there are deviations not greater than 1mm.
PAGINA PAGE
INGEGNERIA
73 di/of 73
- EN
- UNI EN
- ISO
- EN ISO
- ASTM
- ACI
- etc.
in particular, when it is required by the technical specifications and when the local standards dont cover all
the cases.
In case of conflict between the international standards, the technical specifications and the local standards,
the Contractor must inform previously EGP that will decide which standard have to be used. The Contractor
must inform EGP also when he need to use standards not included in the Technical Specifications.
The design shall be in accordance with the latest editions of the standards, in effect at the date of
signature of the Contract or required by local permitting authority.