DAILY ACTIVITY REPORT (MECHANICAL- CPP) DATE-16.08.

13
SL NO. PACKAGE EQUIPMENT CENTRE ACTIVITY AT SITE

Monorail beam erection work


1 CHP PRIMARY CRUSHER/COAL SHED in progress &rafter bracing
erection in progress

Sheeting work started&final


TRANSFER HOUSE 1 welding in progress

TRANSFER TOWER 2 No activity

CONVEYOR 1A & 1B Gallery-5 welding in progress

Trussel TR-3 chequered plate


CONVEYOR 2A &2B for flooring erection in
progress

CONVEYOR 3A &3B No activity


CONVEYOR 4A & 4B No activity

CONVEYOR 5A & 5B No activity

SECONDARY CRUSHER HOUSE No activity

BOILER -I
2 BOILER & ESP
STRUCTURAL Completed

PRESSURE PART Completed

ROTATING EQUIPMENTS Completed

HOT AIR DUCTING Completed

COLD AIR DUCTING Completed


Sand filling for RDO in
FLUE GAS DUCTING progress.
FUEL PATH Completed

SA FAN delivery side duct


INSULATION insulation In progress

ESP Placing of insert plates for


flooring in progress
BOILER -II

STRUCTURAL Bunker welding in progress

DM water filling for internal


PRESSURE PART hydro.

id fan foundation
modification in progress &
ROTATING EQUIPMENTS foundation work for PA & SA
FAN in progress.

HOT AIR DUCTING No activity

COLD AIR DUCTING No activity


ID FAN ducting erection
FLUE GAS DUCTING &welding work in progress

burner ducting work in


FUEL PATH progress & MDC welding in
progress.

INSULATION No activity

Emitting electrode erection in


ESP progress & hopper erection in
progress.

Side sheeting work in


LP PIPING RAW WATER PUMP HOUSE progress
3
CLARIFIER WATER PUMP HOUSE No activity

Erection of remaining 4 nos


CW AND ACW PUMP HOUSE of columns in progress.

No activity as monitoring
UTILITY WATER PUMP HOUSE basin work yet to start.
Pipe headers of all conveying
COMPRESSOR HOUSE compressors erection in
progress

FIRE FIGHTING SYSTEM

LDO SYSTEM No activity

Fabrication of racks between


PIPE RACK clarified water pump house
&main rack, in progress.

250 mmcooling water


makeup pipeline erection in
progress ,400mm ACW pipe
FABRICATION &ERECTION OF PIPING painting wrapping in progress
& fabrication of 1400mm
bends completed.
COOLING FANS ,GEAR BOXES PROPELLER SHAFT
4 No activity
TOWER & STRUCTURALS

DISTRIBUTION PIPE LINES No activity

DRIFT ELIMINATORS & SPLASH No activity


GUARDS

STRUCTURAL Staircase erection in progress


5 TG BUILDING
TURBINE No activity

TURBOGENERATOR No activity
Expansion of tubing in
CONDENSER progress

Condensate float tank


AUXILLARIES received & unloaded in crane
bay.
Fabrication of boiler feed
FABRICATION &ERECTION OF PIPING pump delivery line taken up

Overhead oil tank erection


LUBE OIL SYSTEM completed.

6 ASH SILO STRUCTURAL Staircase erection in progress

Insert plates for hopper liner


ERECTION OF EMBEDED PLATES & plate have been completed &
OPENING placing of edge angle for
opening in progress.

ASH HANDLING EQUIPMENT No activity


Insert plates for pipe line
ASH TRANFER PIPE LINE fixing in progress.

WATER
7 TREATMENT STRUCTURAL Completed
PLANT
EQUIPMENT ERECTION No activity

DM Water production in
FABRICATION &ERECTION OF PIPING progress for boiler-II hydro
test.

Truss erection work


CHEMICAL HOUSE completed
DATE-16.08.13
PLANNED FOR TOMORROW REMARK

Hoppers, railings &


chutes for feeder
Same to continue breaker awaited at
site

All matreials received


Same to continue at site

Same to continue

Same to continue

Civil foundation work


yet to be completed
Trussel fabrication
completed & gallery
to be received.

Material not received


at site

Civil work yet to be


completed

Same to continue
Same to continue

Same to continue

Same to continue

Same to continue

Erection work
awaiting completion
of fan foundation.

Same as above
Same to continue

Same to continue

Insulation work to
start after hydro test.

Same to continue

same to continue ,&pump


erection work to start after
sheeting.

Purlins still awaited.

allignment of columns to be Purlins still awaited.


completed
Same to continue

Civil foundation work


No activity to start.fabricated
tank awaited at site

Same to continue

400mm ACW pipe painting


wrapping to continue &
fabrication of bends inside
cooling tower forbay ot be done.
Civil work yet to be
completed &
No activity mobilisation to be
started by Paltech

No activity same as above

No activity same as above

Same to continue

Same to continue

All other available


Erection of condensate float equipments have
tank to be taken up. been placed in
position.
Same to continue

Same to continue

Same to continue

Same to continue
Erection of remaining
small pumps to be
No activity taken up during
erection of panels

Same to continue

Purlin erection to
No activity start after gable wall
completion.