13
SL NO. PACKAGE EQUIPMENT CENTRE ACTIVITY AT SITE
BOILER -I
2 BOILER & ESP
STRUCTURAL Completed
id fan foundation
modification in progress &
ROTATING EQUIPMENTS foundation work for PA & SA
FAN in progress.
INSULATION No activity
No activity as monitoring
UTILITY WATER PUMP HOUSE basin work yet to start.
Pipe headers of all conveying
COMPRESSOR HOUSE compressors erection in
progress
TURBOGENERATOR No activity
Expansion of tubing in
CONDENSER progress
WATER
7 TREATMENT STRUCTURAL Completed
PLANT
EQUIPMENT ERECTION No activity
DM Water production in
FABRICATION &ERECTION OF PIPING progress for boiler-II hydro
test.
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Erection work
awaiting completion
of fan foundation.
Same as above
Same to continue
Same to continue
Insulation work to
start after hydro test.
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Erection of remaining
small pumps to be
No activity taken up during
erection of panels
Same to continue
Purlin erection to
No activity start after gable wall
completion.