Contractor: DUBAI
Document Number:
Work Location:
Proposed Duration:
Signature: Date:
2
Approvals:
Designation
Project Manager
Sr. Project Engineer
Sr. Site Engineer
Safety Officer & Safety Watch
Supervisor
QC Engineer
Surveyor
Mason
Helpers
Machine operators
This method statement applies for construction of new wall. The construction incudes excavation of
soil, compaction of soil, steel and formwork, casting of concrete, backfilling and laying of
waterproofing material.
3
Equipment / Tools/ Certificates Required:
Back Hoe loader - Diesel Operated - Will be submitted along with the
PTW.
A) General:
Trakhees modification NOC/COC1 & XXXX work permit shall be obtained before start of
any activity at the premises.
All personnel shall attain the XXX safety induction.
XXX personnel will jointly visit the site to identify the exact locations where the temporary
bund wall has to be constructed based on approved drawings and site survey by XXX
surveyor. (For site survey & field measurement separate approved MSRA will be followed).
XXX will prepare hot work and cold permit as required and get it approved from XXX as
required.
Barrication will be provided in the area.
B) Construction:
The area for constructing the new bund wall will be marked and the area will be barricaded.
After the completion of soil improvement required depth (As shown in drawing) below
foundation will be achieved by mechanical excavation.
Levels will be checked to confirm the depth of excavation.
300mm soil/Road base will be backfilled and compacted with water to attain 98%MDD.
1000 gauge polythene sheet will be provided before casting PCC.
Formwork will be provided for the PCC.
75mm thick PCC will be poured onto the polythene sheet.
After the curing period a 1.5mm thick self-adhesive Bitustick membrane will be provided on
the concrete as part of the water proofing process.
25mm thick screed concrete will be poured on the waterproofing membrane for concrete
protection.
4
Rebar steel will be cut and bend in the laydown area and brought to the construction site. The
rebar steel will be tied as shown in the drawing by using binding wire.
Cover blocks of 50mm will be provided as cover.
Shuttering and formwork will be made in the laydown area.
Shuttering will be placed to cover the rebar steel as shown in the drawing.
Concrete for the foundation will be poured using a concrete pump.
The concrete will be cured for 7 days from the day of casting and shuttering will be prepared
for the walls.
The bund wall will be casted in two lifts.
All construction joints will be provided with water stoppers.
Scaffold will be provided for any concrete works above 1.5 mtrs height.
Water proofing material will be provided upto the existing ground level on one side and till
the grade slab level in the side that is facing the tanks.
Soil will be backfilled in layers of 300 and compacted to 95%MDD.
I. General Requirements
Trained and competent scaffolders to be deployed for works.
Proper housekeeping to be done to minimize the risk of slips trips and falls and to keep the
working environment tidy and free from obstruction.
Proper housekeeping will be done regularly.
Responsibility Matrix:
SI # Activity Performed By
1. Gas monitor
5. Issuing of PTW
7. Obtain PTW
5
Safety Precautions:
6
management on site.
Scaffolding Safety requirement shall strictly be followed.
Follow emergency response plan.
Accident and incident reporting procedure as per XXX incident reporting and
investigation procedure shall be followed.
Extra caution will be taken while working inside the live terminal, all existing XXX
facility shall be protected by using safe means of arrangements & XXX
operation/Maintenance instructions to be followed.
ATTACHMENTS:
a. Risk Assessments
b. Drawing References