Tested by Witnessed by

Siemens S.A.E Client :EETC


Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 1 of 8
Commissioning certificate 12/2014

Customer : EETC

Plant : Maghagha 500 kV S/S Contract-No.:

Feeder : B05+R2

MLFB - No.: 7SJ80315EB001FC0

Serial.-No.: In = 1 A f= 50 Hz UH = 220 V
dc
1. Relay Settings:
A printout of the relay settings is attached.

2. Secondary Injection Test Set Up:


Where secondary tests are to be performed, a three-phase test equipment
providing test currents recommended (e.g. Omicron CMC 156 for manual
and automatic testing). The phase angle between current phases should
be continuously controllable.

3. Measurements Test:
Connection:
Injection was done through test switch.
Injection Values:
3 currents with the rated values and balanced angels are injected according
to the following table:
N.B.: Tripping should be prevented from stopping the injection.
Current Voltage
Magnitu Angle Magnitud Angle
de () e ()
R 1A 0 57.735V 0

Phase S 1A -120 57.735V -120

T 1A 120 57.735V 120

Measured Values: A print out of the measured values is attached

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 2 of 8
4. (Directional) Over Current Protection Test:
Test Procedure:
OMICRON Quick CMC Test module is used to inject currents on each phase
individually.
Pick up value is recorded when the tester stops injection by the stop contact.
For measuring the trip time , a value equals at least 1.5 times pick up value
should be injected.

Pick Up Test:

Set Values Measured values

Phase Isett. (A) Ipick up (A)

Directional Non- Directional


R-N 1.18 1.17 1.17
S-N 1.18 1.17 1.17
T-N 1.18 1.165 1.17

N.B: Drop out value is 1.115 Amp (Reset Factor = 95%)

Time Test:
At twice the current setting
Set Values Measured values

Phase T (Sec.) T (Sec.)

Directional Non- Directional Directional Non-Directional


R-N 1 3.0 1.040 3.032
S-N 1 3.0 1.038 3.031
T-N 1 3.0 1.038 3.029

Directional Test:

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 3 of 8
To simulate a fault on phase- A, the voltage of this phase is reduced while the other two phases are
healthy. The current of that phase is greater than the pick up value (1.23 A).The angle of this current is
changed in steps to rotate around the reference voltage V ref (rotated). The results are shown
in the following figure:
Phase Fault Rotation. Angle Measured Forward Zone
R +45 +39 / 0 /-128
S +45 +39 / 0 /-128
T +45 +39 / 0 /-128

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 4 of 8
Reverse
V Forward
T

VR

Reverse

Vref
VS rotated

Forward Vref

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 5 of 8
5. (Directional) Earth Fault Protection Test:
Test Procedure:
OMICRON Quick CMC Test module is used to inject currents and voltages on
each phase individually.
Pick up value is recorded when the tester stops injection by the stop contact.
For measuring the trip time, a value equals at least 1.5 times pick up value
should be injected.

Pick Up Test:

Set Values Measured values

Phase Isett. (A) Ipick up (A)

Directional Non-Directional
N 0.32 0.315 0.315
N.B Drop out is 0.285 Amp (Reset Factor = 90.5%)

Measured
Set Values
values
Phase 3Vo (V) 3Vopick up (V)

Reduce VR= 57.73


voltage at VS= 57.73 5 4.87
any phase VT= 52.86

Time Test:
At twice the current setting
Set Values Measured values

Phase T (Sec.) T (Sec.)

Directional Non-Directional Directional Non-Directional


N 1.0 3.0 1.038s 3.034

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 6 of 8
Directional Test:

To simulate a fault on phase- A, the voltage of this phase is reduced to a value cause a polarizing voltage
(3Vo) > 5 V. while the other two phases are healthy. The current of that phase is greater than the pick up
value (0.12 A).The angle of this current is changed in steps to rotate around the reference voltage V ref
. The results are shown in the following figure:
(rotated)

Rotation. Angle Measured Forward Zone


-45 +38 / 0 /-128

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 18 -09-2016 Date: 18-09-2016
Signature Signature

Page 7 of 8
5. Function Test:
LEDs Operation Tested According to setting OK
O/P Function Tested :

BO Destination
D.O.C Alarm RTK Alarm
BO3
Signal
K350 in +R2 K640 Lock Out
BO1
RTK Alarm
D.E.F Alarm RTK Alarm
BO4
Signal
K630 Lock Out
B02 K340 in +R1
RTK Alarm
Watch RTK Alarm
K323
Dog

6. Test Plug Facility:


Current Transformer shorting facility. OK
Voltage Transformer Isolating. OK
Isolating alarm and trip signals. OK