Sie sind auf Seite 1von 43

R0 07.04.

10 FIRST ISSUE RK DD
REV. / ISSUE DATE DESCRIPTION PREP APPD

REVISION
PROJECT TITLE

2×800 MW Sri Damodaran Sanjeevaiah


Thermal Power Station
Krishnapatnam, Nellore (Dist.), Andhra Pradesh
OWNER

Andhra Pradesh Power Development


Company Limited
Hyderabad
OWNER'S CONSULTANT

DESEIN Private Limited


Consulting Engineers
New Delhi
BALANCE OF PLANT CONTRACTOR

TATA Projects Limited


Hyderabad

TPL’S CONSULTANT

FICHTNER Consulting Engineers (India)


Private Limited
Chennai
SIGNATURE DATE SWITCHYARD CONTRACTOR

PREPARED RK 07.04.2010 ABB Limited


DESIGNED RK 07.04.2010 PSS - TS, Bangalore
CHECKED DD 07.04.2010 TITLE

DEPT. HEAD DD 07.04.2010 DESIGN BASIS REPORT


PROJ. MGR. RB 07.04.2010 CONTROL & PROTECTION/ SCADA INTERFACE
PRELIMINARY DEPT. ELECT. JOB No. 229081002 SHEET 1 OF 15
RELEASED

TENDER
FOR

DOC. NO. REV. / ISSUE

ENGINEERING X ABB Id. YN1M 301 542-ZAB


P0
CONSTRUCTION TPL Id. TPL-069-ABB-YN1M 301 542 ZAB
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 2 / 19

Table of Contents:
1 Introduction......................…………………………………………………………………....3
2 Technical data................................................................................................................3
3 Description of one and half breaker………………………………………………………..3
4 Master List of Document…………………………………………………………………….6

5 Control, Relay and Metering panels in SCR………………………………………………7

6 Description of bay level Functionality ……………………………………………………..7

6.1 400KV Line control and relay panel.............................................................................7

6.2 ST control and relay panel.........................................................................................10

6.3 400kV Bus-reactor control and relay panel................................................................11

6.4 GT control and relay panel........................................................................................11

6.5 Tie relay panel…………………………………………………………………………….12

6.6 Bus-Bar Protection Panel………………………………………………………………..13

6.7 Tariff Metering Panel……………………………………………………………………..14

6.8 Synchronising Trolley…………………………………………………………………….15

6.8 Back-up control panel………… ………………………………………………………...15

6.11 Substation Automation System ………………………………………………………..17

7 Annexure-A --- Line bay logics

8 Annexure-B --- ST bay logics.

9 Annexure-C --- GT bay logics.

10 Annexure-D --- Interlocking and Synchronising logics

11 Annexure-E --- Annunciation list for Back-up control panel.

12 Annexure-F --- Scada alarms List.

13 Annexure-G --- Trip logic for Bus-bar protection.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 3 / 19

1 Introduction
The 400kV Switchyard provided for evacuation of power generated at Krishnapatnam plant, is of
conventional one and half circuit breaker switching scheme, comprising 2 Nos. of Station transformers, 2
sets of Generator transformers, 2 Nos. of Bus Reactors and 6 Nos. of lines evacuating power to
APTransco grid.

2 Technical Data
Control supply voltages envisaged for different Equipments

i. Control/spring charging of CB - 220V DC


ii. Control of Isolator & ES - 220V DC
iii. Control / Protection panels - 220V DC
iv. AC supply for lighting/heaters - 415/230V AC
v. Scada HMI’s - 230V AC from UPS
vi. Transformer MB’s - 230V AC

3 Description of 1 & ½ breaker system


One and half bus configuration has two main buses with both buses energized during normal
operation.For every two circuits there are three breakers, with each circuit sharing a common centre tie
breaker. This is termed as diameter. Any of the breaker can be removed for maintenance without affecting
the service on the outgoing circuits. Configuration also allows LILO operation without going through the
main bus.Fault on either bus can be isolated without interrupting the service to the outgoing lines.
Four CT arrangement is adopted in each diameter (one set of CT’s on each bus side and two sets of CT’s
in Tie). The bus side and Tie CT’s are summated to measure the outgoing currents, for the feeder
protections, metering (refer Figure-1).
For faults on feeder, protection trip commands are issued to main and tie breakers. Breaker fail protection
is provided for each breaker. In case of breaker stuck during fault, the breaker fail protection will initiate
trip of connected bus, Tie and remote end breakers. Breaker fail of Tie breaker initiates trip of both main
breakers in the diameter and remote end breakers. CT’s on the respective bus side of various bays are
summated for bus protection and no CT switching is involved.
Bus CVT’s are provided on each main bus for metering/synchronizing purposes. This also caters to
metering/ protections of Station transformer bays which does not have dedicated CVT. Selection of bus
CVT’s is done through main &/or tie breakers of corresponding diameter.
Dedicated CVT’s are provided for Line and GT bays for protection, metering and synchronizing purposes.
Besides dedicated EMVT’s are available on the Line and GT bays for tariff metering purposes.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 4 / 19

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 5 / 19

The protection are segregated into Group-A and Group-B electrically and physically. Dedicated CT and
CVT cores along with independent DC (from battery/chargers) for each of Group-A and Group-B
protections are provided to achieve redundancy (refer Figure-2)

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 6 / 19

4 Master List of documents

Sl. No Description of the Drawing/Document ABB ID


1. Design Basis Report YN1M301542-ZAB
2. Control & Relay Panel for GT#1 (Bay-401) YN1M301542- AAA,AA,CAA
3. Control & Relay Panel for TIE#1 (Bay-402) YN1M301542- AAB,AB,CAB
4. Control & Relay Panel for LINE#1 (Bay-403) YN1M301542- AAC,AC,AD, CAC
5. Control & Relay Panel for BR#1 (Bay-404) YN1M301542- AAE,AE, CAE
6. Control & Relay Panel for TIE#2 (Bay-405) YN1M301542- AAF,AF,CAF
7. Control & Relay Panel for LINE#2 (Bay-406) YN1M301542- AAH,AG, AH,CAG
8. Control & Relay Panel for ST#1 (Bay-407) YN1M301542- AAI, AI, AJ, CAI
9. Control & Relay Panel for TIE#3 (Bay-408) YN1M301542- AAK,AK,CAK
10. Control & Relay Panel for LINE#3 (Bay-409) YN1M301542- AAL,AL. AM, ,CAL
11. Control & Relay Panel for ST#2 (Bay-410) YN1M301542- AAN,AN,AO, CAN
12. Control & Relay Panel for TIE#4 (Bay-411) YN1M301542- AAP,AP,CAP
13. Control & Relay Panel for LINE#4 (Bay-412) YN1M301542- AAQ,AQ, AR, CAQ
14. Control & Relay Panel for BR#2 (Bay-413) YN1M301542- AAS,AS,CAS
15. Control & Relay Panel for TIE#5 (Bay-414) YN1M301542- AAT,AT,CAT
16. Control & Relay Panel for LINE#5 (Bay-415) YN1M301542- AAU,AU, AV,CAU
17. Control & Relay Panel for GT#2 (Bay-416) YN1M301542- AAW,AW,CAW
18. Control & Relay Panel for TIE#6 (Bay-417) YN1M301542- AAX,AX,CAX
19. Control & Relay Panel for LINE#6 (Bay-418) YN1M301542- AAY,AY, AZ,CAY
20. Backup control panel for Dia #1 YN1M301542- ABA,BA,CBA
21. Backup control panel for Dia #2 YN1M301542- ABC,BC,CBC
22. Backup control panel for Dia #3 YN1M301542- ABD,BD,CBD
23. Backup control panel for Dia #4 YN1M301542- ABE,BE,CBE
24. Backup control panel for Dia #5 YN1M301542- ABF,BF,CBF
25. Backup control panel for Dia #6 YN1M301542- ABG,BG,CBG
26. Busbar Protection Panel. YN1M301542- ABH,BH, BI, CBI
27. Substation Automation panel YN1M301542- ABL,AL,CAL
28. Metering Panel YN1M301542- ABN,BN,CBN
29. Synchronizing trolley YN1M301542- ACA,CA,CCA
30. Mandatory spares YN1M301542- ACB,CB,CCB

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 7 / 19

5 Control, Relay & Metering panels in Switchyard Control Room


Switchyard control room (SCR) will be two storied RCC framed structure. The ground floor will
accommodate cable vault, stores, 220V batteries, toilets etc. The first floor will have relay panels, backup
control panels, metering panels, PLCC panels, SCADA, ACDB & DCDB switchgears, 48V battery &
220/48V battery chargers, office, relay testing room, AHU etc. Cable trays (supported from ground floor
roof) will be provided below relay panels, control panels, metering panels, PLCC panels, ACDB & DCDB
switchgear, batteries. Cooling towers & Condenser water pumps are located on the terrace.

6 Description of Bay Level Protections

6.1 400kV Line Protection & Relay panel:

Panel Location :-- SCR

2 Nos. Relay panels with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

a) Main-1 Distance protection IED – REL670 (Non switched 5 zone with Quadrilateral characteristic)

 Distance protection – 21L1


 Carrier communication logic for distance protection.
 Switch On To Fault (SOTF).
 Power swing Detection.
 Fuse Failure detection.
 Over Current Stub protection (51L1)
 Over-Voltage Protection (59L1)
 Direction Earth Fault Protection (67N1).
 Negative sequence Protection (46L1) – Only alarm and indication.
 Fault Locator
 Disturbance Recorder

b) Main-2 Distance protection IED – REL670 (Non switched 5 zone With Mho characteristic)

 Distance protection – 21L2


 Carrier communication logic for distance protection.
 Switch On To Fault (SOTF).
 Power swing Detection.
 Fuse Failure detection.
 Over Current Stub protection(51L2)
 Over-Voltage Protection (59L2)
 Direction Earth Fault Protection (67N2).
 Negative sequence Protection (46L2) – Only alarm and indication.
 Fault Locator
 Disturbance Recorder

c) Bay control unit, REC670 with binary input/output cards

 Control for Bay level equipment (Circuit breaker, Isolators and Earth switch)
 Synchronising/energising Check
 Auto-reclosure

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 8 / 19

d) Single phase trip relay (3 Nos.) for GR-A/B (21-1 R/Y/B)


e) Single phase trip relay (3 Nos.) for GR-A/B (21-2 R/Y/B)
f) Latch relay with Trip circuit supervision for 3Ph trip GR-A (86A & 95A)
g) Latch relay with Trip circuit supervision for 3Ph trip GR-B (86B & 95B)
h) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-1 (95-1 R/Y/B)
i) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-2 (95-2 R/Y/B)
j) DC supervision relay (2 Nos.) for monitoring of protection DC (80A/B)

The following logics in Annexure-A provides guidelines of scheme functioning

a) Trip matrix
b) Auto-reclose logic
c) Direct Trip Send logic,
The distance protection has selectable communication schemes for permissive carrier intertrip/blocking.
The main 1 & 2 protections are on separate DC (i.e battery/chargers) along with respective 1 & 3 phase
trip units and trip coils 1 & 2.
For faults on line, protection trip commands are issued via trip units to main and tie breakers faulted
phase.
Auto-reclosure facility (either 1 or 3 phase selectable) is available in the bay controller for reclosure under
line faults. Auto reclosure is started for Zone -1 (or) carrier aided trip for faults within the line section. The
main and tie breakers tripped under this event has to be reclosed sequentially. For this purpose “Priority
circuit” feature is available which allows closing of one breaker first ( preferably main breaker) and upon
successful closing of main breaker the tie breaker is allowed to close subsequently.
Besides “Memory” feature is built in the bay controller which prevents auto-reclosing of the breaker which
was open prior to fault occurrence.(Refer Figure-3)
Auto recloser is blocked for definite trips like LBB operation, back-up protection trip, busbar trip, over
voltage trip, zone 2/3 faults, carrier fail, direct trip receive, breaker problems.
In the event of DC fail to the bay controller (having reclosing function), any single phase faults is
converted to three phase trip, due to non availability of auto reclosure.
Protection operated from over voltage, directional earth fault, stub protection, intertrip receive are definite
trips energizing 3 phase lockout relays, which in turn trip the main & tie breaker.
Direct inter trip send is initiated to remote end for local breaker stuck to isolate faulted line section. Direct
trip can also be initiated for manual trip, busbar trip when lines are long.
Necessary contacts are provided from protections for alarm annunciations in backup control panel and
Scada. (Refer Alarm List Annexure-E)

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 9 / 19

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 10 / 19

6.2 400kV Station Transformer Protection & Relay panel:

Panel Location :-- SCR

2 Nos. Relay panels with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

a) Transformer Protection IED, RET670-1

 Transformer differential protection (87ST)


 Over-fluxing protection (99ST)
 Standby Earth fault – HV (51NST)
 Standby Earth fault – LV1 (51SEF1) and
 Standby Earth fault – LV2 (51SEF2).

b) Transformer Protection IED, RET670-2

 Low Impedance TEED differential Protection (87TEED)


 High Impedance Restricted Earth Fault Protection –HV (64ST)
 Directional Over-current and Earth Fault Protection HV (67/50ST & 67/50NST)

c) Bay control unit REC 670 with binary input/output cards, mA modules

 Control for Bay level equipment (Circuit breaker, Isolators and Earth switch)
 Synchronising/energising Check
 Transformer tap raise/lower

d) Latch relay with Trip circuit supervision for 3Ph trip GR-A (86A & 95A)
e) Latch relay with Trip circuit supervision for 3Ph trip GR-B (86B & 95B)
f) High Speed Inter-trip relay 1No.for each LV (86LV1 & 86LV2)
g) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-1 (95-1 R/Y/B)
h) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-2 (95-2 R/Y/B)
i) DC supervision relay (2 Nos.) for monitoring of protection DC. (80A/B)
j) Auxiliary relay with flag indication for Transformer protection like Buchholz, WTI, OTI, LOL, Cooler
trouble, DC fail, OLTC trouble, Fire protection etc required as per ST drg.

The following logics in Annexure-B provides guidelines of scheme functioning

a) Trip matrix
b) HV/LV inter trip logic
c) Voltage selection logic.
The ST protections are grouped and put on seperate DC (i.e battery/chargers) along with respective 3
phase trip units and trip coils 1 & 2.
For faults in transformer, protection trip commands are issued via trip units to main and tie breakers.
Selection of bus CVT is done through main &/or tie breaker of corresponding diameter, and caters to
metering/ protections
Protection operated from differential, REF, Teed, directional over current & earth fault, over fluxing,
standby earth fault (HV & LV) protection, transformer trouble trips energize 3 phase lockout relays, which
in turn trips the HV and Tie breaker. Besides above protection trip is also routed to inter trip the LV
breakers.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 11 / 19

Closing of LV breakers is feasible only when HV side is closed, and LV breakers are tripped in event of
HV side trips.
Necessary contacts are provided from protections for alarm annunciations in backup control panel and
Scada. (Refer Alarm List Annexure-E)

6.3 400kV Bus-Reactor Protection & Relay panel (in APPDCL scope)

Following item is supplied loose, to be mounted in the Protection & Relay panel being supplied by
APPDCL.

a) Bay control unit REC 670

 Control for Bay level equipment (Circuit breaker, Isolators and Earth switch)
 Synchronising/energising Check

6.4 400kV Generator Transformer Relay panel:

Panel Location :-- SCR

1 No. Relay panel with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

a) Transformer Protection IED, RET670

 Transformer over hang differential protection (87OH)

b) Bay control unit REC 670 with binary input/output cards, mA modules

 Control for Bay level equipment (Circuit breaker, Isolators and Earth switch)
 Synchronising/energising Check
 Transformer tap raise/lower

c) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-1 (95-1 R/Y/B)
d) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-2 (95-2 R/Y/B)
e) DC supervision relay (2 Nos.) for monitoring of protection DC (80A/B)
f) Auxiliary relay with flag indication for each phase of Transformer protection like Buchholz, WTI,
OTI, LOL, Cooler trouble, DC fail, OCTC trouble, Fire protection etc required as per GT drg.

The following logics in Annexure-C provides guidelines of scheme functioning

a) Trip matrix
b) Voltage selection logic.

All the GT and generator protection panels are in MELCO scope of supply in Main control room. The
protection trips (Class A,B,C ) is routed to the Switchyard GT relay panel and tie relay panel. The trip
circuit supervision relays are interfaced with the trip contacts received from MELCO panel and routed
to the main breaker & tie breaker.

3 Nos.self reset contacts of 87OH protection operated will be provided to MELCO for their class A trip
logics. GT trouble relays in SCR are provided mainly for alarm contacts to backup control panel and
Scada. No trip logics envisaged in SCR for 87OH and transformer trouble relays.(2 sets of transformer
trouble alarm and trip contacts to be made available from GT to MELCO panel & SCR)

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 12 / 19

Necessary contacts are provided from MELCO protections for alarm annunciations in backup control
panel and Scada. (Refer Alarm List Annexure-E)

6.5 400kV Tie Relay panel:

Panel Location :-- SCR

1No. Relay panel with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

a) Bay control unit REC 670 with binary input/output cards

 Control for Bay level equipment (Circuit breaker, Isolators and Earth switch)
 Synchronising/energising Check
 Auto-reclosure
 Breaker failure protection

b) Single phase trip relay (3 Nos.) for GR-A/B (21-1 R/Y/B)


c) Single phase trip relay (3 Nos.) for GR-A/B (21-2 R/Y/B)
d) Latch relay with Trip circuit supervision for 3Ph trip GR-A (86A & 95A)
e) Latch relay with Trip circuit supervision for 3Ph trip GR-B (86B & 95B)
f) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-1 (95-1 R/Y/B)
g) Trip circuit supervision relays (3 Nos.) for supervision of Breaker Trip coil-2 (95-2 R/Y/B)
h) DC supervision relay (2 Nos.) for monitoring of protection DC (80A/B)

The 1 & 3 phase tie trip units and trip coils 1 & 2. are on seperate DC (i.e battery/chargers).
Initiation for tie trip units is from diameter bay protections. The protections in the bays are as listed below.
I. Lines – Distance, Over voltage, directional earth fault, stub protection, negative sequence, inter
trip receive
II. Station transformer - Differential, REF, Teed, directional over current & earth fault, over fluxing,
standby earth fault (HV & LV) protection, transformer trouble trips
III. Generator transformer - The protection trips (Class A,B,C ) from MELCO panels, including 87OH
trip sent from SCR.
IV. Bus Reactor (APPDCL scope) - Differential, REF, Teed, backup impedance, over current & earth
fault, reactor trouble trips
The trip unit in tie issues trip command to tie breakers (single phase trip to faulted phase in case of Line/
all 3 phases in case of ST, GT, BR and definite trips of lines)
Auto-reclosure facility (either 1 or 3 phase selectable) is available in the bay controller for reclosure under
line faults. Auto reclosure is started for Zone -1 (or) carrier aided trip for faults within the line section. The
main and tie breakers tripped under this event has to be reclosed sequentially. For this purpose “Priority
circuit” feature is available which allows closing of one breaker first ( preferably main breaker) and upon
successful closing of main breaker the tie breaker is allowed to close subsequently.
Besides “Memory” feature is built in the bay controller which prevents auto-reclosing of the breaker which
was open prior to fault occurrence.(Refer Figure-3)
Auto recloser is blocked for definite trips like LBB operation, back-up protection trip, busbar trip, over
voltage trip, zone 2/3 faults, carrier fail, direct trip receive, breaker problems.
In the event of DC fail to the bay controller (having reclosing function), any single phase faults is
converted to three phase trip, due to non availability of auto reclosure.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 13 / 19

Breaker fail of Tie breaker initiates trip of both main breakers in the diameter and remote end breakers..
In case of lines direct inter trip send is initiated to remote end for local breaker stuck to isolate faulted line
section. Direct trip can also be initiated for manual trip, busbar trip when lines are long.
In case of station transformer, closing of LV breakers is feasible only when HV side is closed, and LV
breakers are tripped in event HV side trips.
Necessary contacts are provided for alarm annunciations in backup control panel and Scada. (Refer
Alarm List Annexure-E)
.
6.6 400kV Bus bar protection panel:

Panel Location :-- SCR

2 Nos. Relay panels with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

a) Bus-bar Protection IED, REB670 for Main Bus-1 & 2 catering to 6 bays on each bus (87B)

 Low impedance bus differential function.


 Local breaker back-up protection.
 End-Fault Protection
 CT open circuit detection feature:

b) Bus-bar Protection IED, REB670 for Main Bus-1 & 2 catering to 6 bays on each bus (87CH)

 Low impedance bus differential function.


 Local breaker back-up protection.
 End-Fault Protection
 CT open circuit detection feature:

c) Bus-bar Protection IN/OUT selector switch (2 Nos)


d) Latch relay with Trip circuit supervision (24 Nos) for bays (4xx-86)
e) Trip relay reset push button (2Nos)
f) DC supervision relay (2 Nos.) for monitoring of protection DC (80A/B)
g) CT supervision alarm scheme consisting of
i. Alarm reset push button (2Nos)
ii. Electronic hooter (2Nos)
Duplicate bus bar protections are provided for 1 & ½ breaker configuration. The bus bar relays are of
low impedance phase segregated type. CT’s on the respective bus side of various bays are summated
for bus protection and no CT switching is involved. The basic concept is the direct use of kirchoff’s law,
sum of all currents on a bus is zero. The relay algorithm measures the total instantaneous incoming
currents to bus, total instantaneous outgoing currents from bus and instantaneous differential current.
Integrated overall check zone is available for increased security. CT open circuit detection feature is
used to selectively block bus-bar protection in case of CT open circuit conditions, besides initiating
alarm.
Breaker failure protection is available for every bay CT input. The breaker failure protection is initiated
from bay protections. In case of breaker stuck during fault, the breaker fail protection will initiate trip of
connected bus, Tie and remote end breakers. The bus bar operated also initiates the breaker fail
protection to trip the remote end in case of any breaker stuck condition..
The bus bar operated is routed to respective bay protections for auto reclose block (for lines) and
breaker closing circuit interlock for all bays.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 14 / 19

The trip matrix in Annexure-G provides guidelines of scheme functioning

6.7 Tariff Metering panel:

Panel Location :-- SCR

3 Nos. Control panel with dead front and rear access. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 1000 x 2250 x 1000mm (WxHxD) with Base Frame 47mm (H) AV pad 15mm(Tk)
The panel shall have sealing facility.

Consisting of following items

a) 12Nos. Tariff Meter, with ABT feature & meeting the CEA regulations (2 Nos each for 6 Line
bays for Main & Check Metering)
 Accuracy class of 0.2S
 Import/Export MWH and MVARH
 4 Quadrant
 3 phase, 3 element, 4 wire
 Optical port
 Shall have suitable port preferably RS485 for interfacing with Scada/DCS
 Retransmitting contacts

b) 4Nos. Tariff Meter, with ABT feature & meeting the CEA regulations (2 Nos each for 2 GT bays
for Main & Standby Metering)
 Accuracy class of 0.2S
 Import/Export MWH and MVARH
 4 Quadrant
 3 phase, 3 element, 4 wire
 Optical port
 Shall have suitable port preferably RS485 for interfacing with Scada/DCS
 Retransmitting contacts

c) 4Nos. Tariff Meter, with ABT feature & meeting the CEA regulations (2 Nos each for 2 ST bays
for Main & Standby Metering)
 Accuracy class of 0.2S
 Import/Export MWH and MVARH
 4 Quadrant
 3 phase, 3 element, 4 wire
 Optical port
 Shall have suitable port preferably RS485 for interfacing with Scada/DCS
 Retransmitting contacts

d) 1No. Meter reading instrument(MRI) for down loading the data from tariff meter.
e) 20Nos. 3Phase, 3 element, 4 wire, Test terminal block link type for above meters

The Tariff metering data is made available on Scada & also communicate with remote SLDC/RLDC
through COM500 gateway using IEC 60870-5-101 (slave) protocol.

6.8 Synchronising Trolley:

Trolley Location :-- SCR

Mobile Trolley, Degree of protection – IP31

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 15 / 19

Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 750 x 900 x 1050mm (WxHxD)

Consisting of following items

a) Synchronising trolley with plug and trailing cable


b) Check Synchronising relay (25) with associated undervoltage relays
c) Synchroscope
d) Double voltmeter & Double Frequency meter
e) Isolating IVT and Reversing IVT for bright lamp synchronising

6.9 Station Auxiliaries panel:

Panel Location :-- SCR

1No. Relay panel with front transparent perspex door. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 800 x 2250 x 800mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Tk)

Consisting of following items

i) Bay control unit REC 670 with binary input/output cards

 Data collection from switchyard auxiliary equipments

6.10 400kV Back-up Control panel:- Typical for one diameter

Panel Location :-- SCR

1 No. Control panel with dead front and rear access. Degree of protection -- IP54
Paint shade Exterior -- Semi glossy RAL 7032, Interior – Glossy White
Dimension: 1000 x 2250 x 1000mm (WxHxD) with Base Frame 47mm (H) & AV pad 15mm(Thk)

Consisting of following items for each diameter

a) Painted Aluminium strip mimic


b) 8 Nos. Control switch for all Isolators.
c) 3 Nos. Control switch for all Breakers.
d) 22 Nos. ON/OFF indication lamps for Isolators, Switch and breakers.
e) 8 Nos. Semaphore indicators for Earth switch.
f) 3 Nos. Key operated CP-OFF-BCU-SCADA selector switch
g) 3 Nos. Synchronising socket
h) Micro-processor based Annunciation system comprising
i. 3 Sets of Annunciator (20 windows for bay on Bus I+8 for Tie+20 windows for bay on Bus II).
ii. 1 Set Electronic Hooter and Bell for Trip & Non-trip alarms
iii. 3 Nos. Push button for annunciator. (Accept/Reset/Test)
i) DC fail scheme per panel consisting of
i. 1 No. Electronic buzzer
ii. 1 No DC fail indication lamp.
iii. 1 No.DC Alarm relay
iv. 2 Nos. Push button (DC fail test & Accept)

j) Metering consisting of
2Nos. Digital ammeter (direct reading)
2Nos. Digital Voltmeter (direct reading)

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 16 / 19

2Nos Multi-function meter with test terminal block.

k) Bus Metering consisting of


2Nos. Digital Voltmeter reading all 3 phase
2Nos. Frequency meter

Note:- Bus Metering under (i) is provided in only one Back-up Control panel

The back-up control panel has switches for open/close of switchyard breakers, isolators and status
indication. Earth switches are locally controlled (Control level 0) and only status indicated. Besides
bay metering, alarm annunciations, synchronizing of breakers are available on control panel.
Synchronising/Energising check is performed via Synchronising Trolley plugged to synchronizing
socket.

With switchyard equipment Local/Remote switch selected to “Remote” the control authority will be
transferred to respective back-up control panel. Further hierarchy control can be selected from
lockable control switch CP-OFF-BCU-SCADA.

Hard wired interlocks are built in bay marshalling kiosk (BMK) and command issued from back-up
control panel (Control level 1). All control cables from SCR to equipment are made through BMK.

Control of generator transformer breaker as well as synchronizing is only from main control room in
TG building. Necessary VT supplies will be extended from switchyard to Main Unit control room for
synchronizing purposes.Similar philosophy is applicable for the Tie breaker (GT-Tie-Line diameter)
when exclusively functioning as generator breaker (i.e Not as normal tie). Hard wired signal from
GCP identifying tie breaker being used as generator breaker to provided, to block tie breaker
operation from switchyard.

The following logics in Annexure-D & E provided guidelines for Scheme functioning
a) Breaker closing logic
b) Breaker synchronising logic
c) Isolator & earth switch interlocking logic
d) Alarm annunciation list

6.11 Substation Automation System:

The SAS provides facility to monitor the complete 400kV Switchyard Protections, Control &
Synchronization of the Bay equipments from Switchyard control room as well as from Main control
room. However a simultaneous control from both the control rooms is not possible.

The SAS is based on ABB make MicroSCADA Pro software running on a redundant hot standby
mode on two industrial PCs with Microsoft Windows 2003 server Operating System. In addition the
SAS system, integrated Gateways are also provided on IEC 60870-5-101 (Slave) protocol and OPC
(SAS as Server) connectivity for interfacing to Main plant DCS.

System Architecture

For safety and availability reasons the SAS is based on a decentralized architecture and on a concept
of bay-oriented, distributed intelligence. Functions are decentralized, object-oriented and located as
close to the process as possible.

The SAS layout is structured in two levels:


 Station level and
 Bay level
Please refer SAS Architecture diagram (ABB Doc No: YN1M301542-CZM)
We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 17 / 19

Station Level
The hardware of the station level system provided for the 400kV Switchyard control room consists of
the following:
The SAS conforms to IEC 61850 standards and has a decentralized architecture consisting of the
following main functional parts:

Switchyard Control Room:


 Dual Operator work station-OWS in Hot-Standby mode
 Laptop (Configuration and parameterization)
 Intelligent Electronic Devices (IED) for bay control and monitoring
 Intelligent Electronic Devices (IED’s) for bay station protection
 Managed switched fibre-optic Ethernet LAN in fault tolerant ring architecture to ensure highest
availability
 Integrated Gateway for remote communication to RLDC/SLDC (Communication infrastructure
between SAS and RLDC/SLDC is not in our scope). The communication to RLDC uses IEC
60870-5-101 (slave) protocol, with the remote centre as the master and the local gateway as the
slave. It is possible to control and monitor the local station from remote control centres; however
remote control centre will decide the default control point.
Main Control Room:
 Operator work station-OWS with dual headed monitors.
 Engineering and Disturbance Recorder Station-EWS with dual head monitors. In case of failure of
OWS at Main control room EWS shall act as OWS.
 The substation LAN is extended to the Main Plant control room through fibre optic communication
equipmen
 Remote communication to Main Plant DCS on OPC Connectivity
 Dot Matrix printer for alarms and events
 Colour laser printers for graphics and report
 Gateway for remote communication to BOP & TG DCS on OPC Connectivity
 GPS receiver is provided to synchronize the time of SAS including the IEDs for protection and
control. This GPS master clock is independent of the station computers and gateways, and it
synchronizes all devices via inter bay bus using SNTP protocol as defined by the IEC 61850
standards.

A redundant PC based HMI (Main/standby controller / Operator work station) enables local station
control through the software package MicroSCADA Pro, which contains an extensive range of SCADA
functions. The operator workstation HMI depicts the complete 400kV switchyard real time graphic
mimic diagram. Within the SAS it is possible to work from both Operator workstations at any point of
time and with the failure of Main controller the operations can be monitored from the Standby
Controller.
The SCADA system is having special user functions such as station single line diagram, overviews,
control of circuit breakers and isolators, alarm lists and event lists, logging of historical data for trends
and reports.
Within the SAS, inter bay bus provides independent station-to-bay and bay-to-bay data exchange.
Disturbance evaluation software and MicroSCADA application is provided in the Main Control Room.
The application server automatically downloads the DR data from the IEDs in the pre-defined time
intervals. The downloading of DR data can also be done manually on operator’s request.

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 18 / 19

An authorization mechanism prevents system access to unauthorized users and allows assignment of
a number of authorization levels. This makes certain functions accessible only to those users who
have the required level of authorization.

The control hierarchy and control levels of the SAS shall be based on the logical structure of the SAS,
shown below

Control level 4(Limited) If required

Control level 3 Substation level (SAS-HMI)

Control level 2 Bay control Unit

Control level 1 Backup Control panel

Control level 0 Switchyard equipment

Transfer of control authority from Level 0 to Level 1

Local/Remote switch is provided in the Switchyard equipment. When the switch is set to Remote, the
control authority will be transferred to the respective back-up control panel

Transfer of control authority from Level 1 to Level 2

For all bays Local-CP-OFF-BCU-SCADA switch is provided on the backup control panel. When the
switch is set to BCU, the control authority will be transferred to the respective BCU. Synchronizing/
Energising check is performed in the BCU.

Transfer of control authority from Level 2 to Level 3

Local-CP-OFF-BCU-SCADA switch is provided on backup control panel. When the switch is set to
SCADA, the control authority will be transferred to SCADA HMI.

Transfer of control authority from Level 3 to Level 4.

Level 4 control authority is used only if required.

Bay Level
A bay comprises of one circuit breaker and associated disconnectors, earth switches and instrument
transformers. At bay level, the IEDs provide all bay level functions like control (command outputs),
monitoring (status indications, measured values) and protection. The IEDs are directly connected to
the primary equipment without any need for additional interposing devices or transducers.

Each bay control IED is independent of the others and its functioning is not affected by any fault
occurring in any of the other bay control units of the station.

Ethernet switches are provided for Bay level connection in the SAS System. The connection from
each IED to the switch is by a single fibre optic link. The switches are connected in a fault tolerant ring

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
Identification No.
DESIGN BASIS REPORT
YN1M301542-ZAB
CONTROL & PROTECTION/SCADA INTERFACE
Department: Author: Status: Date: Language: Revision: Page:

PS SA kannan FOR APPROVAL 16.02.2010 en 00 19 / 19

topology. At the station level, to provide communication redundancy, two Ethernet switches are used
to connect the redundant HMI and other station level equipment.

The data exchange among bay level IEDs and between bay level and station level take place via the
fibre-optic inter bay bus according to IEC 61850-8-1 standard. The use of fibre-optic LAN guarantees
disturbance-free communication.

Though, at station level, the entire station is controlled and supervised from the station HMI, it is
possible to control and monitor the bay from the bay level, when the control authority is set
appropriately. The decentralized architecture ensures that station wide interlocking is available even
when the station computer fails.

Clear control priorities prevent the initiation of simultaneous operation of a single equipment from
more than one of the various control levels, i.e. MCR, SCADA, BCU, CP or Equipment level. The
priority is on the lowest enabled control level. The operation also depends on the status of other
functions like interlocking, synchrocheck, etc., as applicable.

6.12 UPS System:

a. Uninterruptible power supply system will cater to critical AC loads like SCADA operator stations
in switchyard control room.
b. UPS will be of “parallel redundant with static bypass to regulated supply” with 2x100% SMF
battery, 2x100% battery charger, inverter, static bypass switch, and regulated AC sinusoidal
supply.
c. UPS battery will be Lead acid type and will be rated for 1 hour backup.
d. The supply required for the computers in Main control room shall be taken from UPS supply
available in main control room.
e. UPS will be single phase and rated for connected loads and with a loading factor of 1.25.
f. Output voltage waveform will be sinusoidal (<1% accuracy over entire load) with AC harmonic
content 230V+/-5% total & +/-3% for any single harmonic. Frequency regulation will be +/-0.5%

We reserve all rights in this document and in the information therein. Reproduction, use or disclosure to third parties without express authority
is strictly forbidden.
© ABB PSS - T&D SS
ANNEXURE - A

LINE BAY

INDIA
ANNEXURE - A

LINE BAY

INDIA
ANNEXURE - B

ST BAY

INDIA
ANNEXURE - B

ST BAY

INDIA
ANNEXURE - C

GT BAY

INDIA
ANNEXURE - D

LINE BAY

INDIA
ANNEXURE - D

TIE BAY (TYPE-1)

INDIA
ANNEXURE - D

TIE BAY (TYPE-2)

INDIA
ANNEXURE - D

ST BAY

INDIA
ANNEXURE - D

GT BAY

INDIA
ANNEXURE - D

LINE & TIE BAY

INDIA
ST BAY

INDIA
GT BAY

INDIA
KEYS
INITIATING SIGNAL -COMMUNICATION
INITIATING SIGNAL -HARDWIRED/COMMUNICATION
RECEIVING SIGNAL -HARDWIRED/COMMUNICATION
RECEIVING SIGNAL -COMMUNICATION
TRIP SIGNAL

INDIA

Das könnte Ihnen auch gefallen