DAILY ACTIVITY REPORT (MECH

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B
1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE


BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART
2 BOILER & ESP
ROTATING EQUIPMENTS

HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING


FUEL PATH

INSULATION

ESP

TG TO BOILER INTERCONNECTION

RAW WATER PUMP HOUSE


CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM
PIPE RACK

FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS

DECK RAILING WORK.


STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER

5 TG BUILDING AUXILLARIES

FABRICATION &ERECTION OF PIPING

LUBE OIL SYSTEM

AC DUCTING WORK
STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL

EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 20
(HAZEMAG)
2 THERMAX 160
3 GPR 21
4 APT 12
5 SUVENDU SAHU 4
JOSEPH
6 0
CONSTRUCTIONS
7 ION EXCHANGE 4
EPORT (MECHANICAL- CPP) DATE-19.09.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW

Final welding of Vertical bracing in progress. Erection Same to continue


of feeder breaker platform assembly is in progress.

Sheeting work & Final welding completed . No activity

Erection of staircase column


Rework on the main columns of transfer tower-2 is in
to be taken up. Rework of
progress. Fabrication & welding of staircase column main columns to be
completed. continued.

Column grouting work completed.


Erection & Welding of handrailing is in progress. Welding of handrailing will be
Grouting of all the columns completed. coninued.

Foundation bolts to be placed.

Erection process to be taken


Levelling of ramp for trussel erection completed. up.

Assembly work of Structures completed & final same to continue


welding is in progress.

Casting of half portion of 17.0 M slab completed. Civil work to continue.


All fabrication scraps being
cut for use & house keeping
Final painting work in progress. work to continue. Painting
work to continue.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation of Economiser casing ,PA duct,pipes ,SA Duct


header connecting to furnace taken up & is in progress.
Insulation of duct connecting ID FAN to chimney in Same to continue
progress.

No activity

Final painting work in progress. Erection of monorail


support structure & monorail for ID FAN completed & Same to continue
final welding is in progress.

Welding of supporting structures in progress. Erection welding of supporting


of steam vent support completed. Erection &welding of structures for pipes to
IBD Vent is in progress. continue.
Erection of ID FAN-3 completed & alignment is in
progress. ID FAN-4 foundation modification in progress
& foundation work for SA FAN completed. Erection of Same to continue
base frame of PA FAN-3 & 4 completed & alignment is
in progress. Erection of base frame of SA FAN-3 & SA
FAN-4 in progress .

Fabrication work of SA fan delivery line in progress.


wind box erection completed. Erection & welding of PA Same to continue
Duct connecting to windbox is in progress.

Erection & welding of secondary air duct fitting work in Same to continue
progress .

Welding work at ID FAN ducting in progress. Welding &


Erection of economiser casing in progress. Connecting Same to continue
duct from furnace to economiser work is in progress.
MDC welding in progress. Erection & welding of MDC
Bypass to ash seperator is in progress. Fixing of ceramic Same to continue
cyclones pipes in MDC is in progress.

Insulation work to be taken up.

Assembly of pent house structure is in progress.


Emitting electrode erection in progress. Assembly &
welding of 1st,3rd fields Hopper completed. Erection of Same to continue
1st & 3rd field hopper completed.Assembly of 2nd field
hopper is in progress.

Erection & Welding of connecting beams from TG to


Boiler at 14.4 M LVL completed. Erection & welding of Same to continue
tie beams is in progress. Erection of cable rack
supporting columns at 4 M LVL is in progress.

Both Raw water pump sole plates Assembly work to be taken


positioned,levelled,grouted & curing is under progress. up.
Erection &welding of longitudinal tie completed. Grouting work will be
Grouting of columns is in progress. continued.

Erection of cooling water pump(CW) base frame


No activity
completed.

No activity as monitoring basin work yet to start.

No activity

Fire fighting pumps have reached transporters Fixing of Fire Sensor Cables
Godown.GPR informed and freight clearance by GPR is and Conduits to continue.
awaited

Clearing of the Cooling Tower materials for foundation Same to continue


layout is completed & excavation work in progress.
Fabrication of remaining pipe racks completed & Alignment of pipe rack near
painting work is in progress. Erection of pipe rack Boiler completed.Erection of
supporting column near boiler completed. Fabrication
of remaining cable rack completed & shifted near boiler cable rack supports to be
taken up.
for erection.

Wrapping coating of 1400NB Pipes for CW line is


under progress. Welding of bend at cooling tower
puddle pipe completed. Assembly of suction line of CW Same to continue
inlet completed & welding is in progress. Assembly of
1400 NB pipe near cooling tower started.

All materials shited close to Cooling Tower Same to continue

No activity Shifting to continue

No activity Shifting to continue

Railing work at deck nearing completion.


Final welding of staircase & Fixing of chequered plates
for steps completed. Fixing of handrailing to be taken
up.

Temporary platform for fixing bolts of turbine


started.TG Floor being Cleaned to start Erection Same to Continue
Activities of Turbine.

Blue matching of bearing pedestal is in progress. Same to Continue

Expansion work of tube end & welding of vaccum pipes


to condenser completed.

Positioning & Alignment of condensate float tank


completed.

Fabrication of boiler feed pump delivery line in No activity


progress.

Fabrication & Erection of lube oil pipe line & pipe


supports is in progress. Same to continue

Insulation work of 10.5 M control room roof


completed.Erection of AC duct & rapping of insulation Same to continue
is in progress.
Final welding is in progress & fixing of gratings Fixing of handrailing to be
completed. taken up.

No activity No activity

No activity

No activity

Completed

Erection of Two numbers of pumps for ultra filter with Pipe assembly work to be
all pipe fittings is in progress. Shifting of MGF taken up. Alignment of
connecting pipes completed & Shifting of sand bags to chemical dosing pumps to
cooling tower in progress. 6 nos chemical dosing Pumps start.
of chemical house were shifted to chemical house.

No activity

Erection of purlins completed & levelling completed. No activity


No activity
3
REMARK

Hoppers, railings & chutes for feeder


breaker awaited at site. Party has been
followed up.

Follow up on for Short Post and


stringers for inclined ramp.
Idler frames & Idler not received at
site.

Civil foundation work yet to be


completed

Trussel fabrication completed & gallery


to be received.party not despatching
further materials despite of repeated
reminders. Rigorous followup required
as party is not able to provide any
evidence of work in progress.

Civil work yet to be completed


Refractory work to be taken up during
the next week.
Balance Erection work awaiting
completion of fan foundation.
Plastering work of Raw water pump
house is in progress which will be
completed and pump erection work
shall start.
Alignment of base frame to be taken
after erection of suction line to pump.

Pipe fittings awaited at site.

Cables & conduits of fire sensors at TG


Building 10.5M control room roof have
reached Site

Civil foundation work to


start.fabricated tank awaited at site
Civil work yet to be completed &
mobilisation to be started by
Paltech.Paltech to mobilise site by
15/9/13.

same as above

same as above

West side railing work of cooling tower


staircase to be taken up after
completion of deck railing.
Work stopped to give way for
completion of civil work.

Erection Work to start

All other available equipments have


been placed in position.

IBR Approval awaited

Materials indented for supply of


cooling water to A.C.Units
Sheeting work to be done after
completion of grouting of anchor bolts
of purlins.