Beruflich Dokumente
Kultur Dokumente
A Project
Presented
to the Faculty o f
In Partial Fulfillment
Master o f Science
in
Quality Assurance
by
Thomas D. Langston
Summer 2015
ProQuest Number: 1581813
In the unlikely event that the author did not send a complete manuscript
and there are missing pages, these will be noted. Also, if material had to be removed,
a note will indicate the deletion.
Que
ProQuest
ProQuest 1581813
ProQuest LLC
789 East Eisenhower Parkway
P.O. Box 1346
Ann Arbor, Ml 48106-1346
Copyright by
THOMAS D. LANGSTON
2015
PAGE
COPYRIGHT PA G E.................................................................................................................... ii
DEDICATION.............................................................................................................................. iv
A B STR A C T................................................................................................................................. ix
CHAPTER
1. INTRODUCTION.....................................................................................................................1
Background........................................................................................................................ 1
Statement o f the Problem.................................................................................................4
Purpose o f the Study........................................................................................................ 4
Theoretical Basis for the Study....................................................................................... 5
Limitations o f the S tudy..................................................................................................6
2. REVIEW OF LITERATURE.................................................................................................. 8
3. M ETHODOLOGY................................................................................................................. 16
Design o f Investigation.................................................................................................. 16
Population........................................................................................................................ 17
Treatment......................................................................................................................... 17
Data Analysis...................................................................................................................18
v
CHAPTER PAGE
4. RESULTS................................................................................................................................ 27
REFERENCES............................................................................................................................ 34
APPENDICES............................................................................................................................. 38
PAGE
3. Field Observations.................................................................................................................. 20
4. Error Rate................................................................................................................................. 20
PAGE
Construction errors are a serious threat to lattice steel tower structural stability.
Previous research has identified many design and engineering problems, however,
foundation installation errors remain a significant issue. This project investigates the
use o f Lean Six Sigma as a method o f reducing the error rate in tower foundation
construction. The design o f the project follows the Six Sigma DMAIC methodology
and the Lean theory o f waste reduction with a foundation installation manual as the end
product. The manual contains procedures and formulas for tower foundation
installation. The results o f the project showed a significant reduction in the error rate o f
CHAPTER 1
INTRODUCTION
Background
Since September 11, 2001, there has been much discussion o f terrorist plans and
the resulting destruction the country could endure. In particular, the security and
reliability o f the Nation’s electric power grid are often a primary concern. While terrorist
events receive national attention, there are other more significant threats to the free
flowing supply o f electricity in the United States and around the world.
In order to clearly recognize the threats to the national power supply, one must
understand where electricity is generated and how it gets to the end user. Electricity is
created in bulk at hydroelectric dams, wind farms and generating plants that are usually
located near the natural resources used to produce the electricity. The power generated
must be transmitted from the source to the local utility company for distribution to
carried atop transmission line towers or poles. The transmission lines connect utility
substations and generating plants, forming a grid across the country allowing electricity
from multiple sources to be available at several sites to meet the local demand. This
grid.
Generating stations and transmission lines bring electric power to the people, but
what are the quality aspects o f electricity? In their 2013 customer satisfaction study, JD
2
Power (2013) reported reliability and cost are among the most important factors
electrical service in many ways, but from a customer service standpoint, reliability
under set conditions for a specific amount o f time. Both definitions can be applied to the
transmission line and bulk electric supply reliability. In fact, performance o f the
individual parts o f a transmission line will, in part, determine the reliability o f the entire
system.
make up the power grid. Towers hold the wires that allow the transmission o f electricity
and keep the wires located safely above the people and objects they might endanger.
potential for human injury and death. When failures occur, they can be attributed to
sometimes geological failures. The causes o f tower failure often relate to issues such as
A common type o f transmission tower is the lattice steel tower. Lattice steel
towers are used for electrical transmission, as well as communications mediums such as
cellular and broadcast antennas. Davies (2011) studied ninty-six broadcast tower failure
events between 1960 and 2010 and found the number one cause o f failure to be
Newly designed lattice steel towers are proof tested before entering into active
service. The proof test consists o f full-scale construction o f a tower design and load
testing to the point o f failure. Proof testing is common for transmission line towers but
has limitations. According to Paiva, Henriques, & Barros (2013) proof testing does not
reveal “if the foundations are less adequate than ideal” (p.l).
Lattice steel tower foundations are “designed to resist uplift, lateral and
downward forces arising from the weight o f the tower, and the tension within the
conductor wires and wind loading” (Richards, White & Lehane, 2010, p.413).
Geological conditions created during construction such as poor backfill, lack o f adequate
voltage transmission tower foundation failures, Shu, Yuan, Guo, and Zhang (2012)
displacement is a key factor leading to failure in the stability o f towers” (p. 1).
Structural issues such as metal corrosion, metal fatigue, and deficient concrete
material may also contribute to foundation failure. Drilled concrete shaft foundations are
used in transmission line construction projects, as well as bridge and high-rise building
construction, because they can carry huge vertical, lateral, and seismic loads. Drilled
shafts are often easier to install and are more economical than other foundation methods
(Hatch, 2000). During the construction o f drilled shafts Hatch (2000) stated, “despite
care and skill in construction, voids or gaps in the concrete can occur” (p.l). In a study
o f drilled shaft failures Tabsh, O ’Neill, & Nam (2005) found “the presence o f a void that
occupies 15% o f the cross-sectional area will reduce the strength o f the shaft by 19% if
4
the void is within the concrete cover and by 22% if the void penetrates inside the core”
(p.742). Fleming, Weltman, Randolph, & Elson (1992) found drilled shaft defect rates
between 1.5% and 1.9% in samples o f 5000 and 4550 shafts respectively. In the study o f
drilled shaft defects, Fleming, Weltman, Randolph, & Elson (1992) also stated,
Due to errors in handling slurry, concrete, casings, reinforcement cages and other
factors, minor or major defects in piles can be introduced during or after pile
Tower failure is disruptive, costly, and dangerous. The issues that lead to tower
failure are primarily due to special causes such as unusually strong wind storms, extreme
ice loading, or soil erosion. Although design engineers plan for events that could cause
failure, construction errors often remove the safety factors built into the designs. In some
circumstances, construction errors can also be a primary cause o f tower failure. The
The purpose o f this study is to apply Lean Six Sigma theories and tools to the
errors can be reduced or eliminated by developing and implementing processes and tools
that reduce waste and increase accuracy by educating the construction crews performing
the work. Davies (2011) stated that a primary reason for construction errors is that
workers building towers must sometimes make engineering decisions, but frequently
lack the knowledge to do so. This project is intended to prevent rework, increase
productivity, reduce costs, and reduce or eliminate construction errors for transmission
line lattice steel towers. The project will accomplish the task by presenting a process
map and best practices manual in the form o f a footing setting handbook for improving
The project is based on two theories o f quality assurance: Six Sigma and Lean.
manufacturing. Michael George (2002) published “Lean Six Sigma: Combining Six
Sigma Quality with Lean Production Speed,” the first book referring to Lean Six Sigma
and explaining how these two theories can be combined. Together, Lean and Six Sigma
have become a powerful tool to remove errors and wasted efforts from processes. Lean
Six Sigma offers a dual approach for variation reduction and provides customers with a
product that meets their needs precisely. In the construction industry, Lean Six Sigma
can improve precision and lower cost by standardizing production processes and
Variation is present in all processes. There are two types o f variation: special
cause and common cause variation (Deming, 1982). Special cause variation is variation
not caused by the system or process in place. Instead, variation is caused by special
circumstances such as a new worker on site without any training, a broken instrument, or
operator error. Common cause variation is variation inherent in the system or process.
Common cause variation usually cannot be cured by the worker and must be reduced by
o f common cause variation might be a foundation setting chart with error on it. System
errors or common cause variation include typing errors, measuring errors, engineering
calculation errors, or lack o f standard operating procedures. Deming stated that 85% o f
the variation in a process is due to common causes. He later amended this statement to
Using Lean Six Sigma techniques, this project identifies system flaws and
process. With a focus on Lean, the project manual clearly presents a process containing
best practices and all the necessary steps for completing each task.
engineering publications. Nearly every aspect o f tower construction has been studied acid
designing tower components are not the people who construct the towers. Skilled
7
tradesmen such as linemen, surveyors, riggers, ground men, and equipment operators do
the actual construction work. While these men and women are skilled in their particular
trade, some aspects o f tower construction require many disciplines to complete. Most
projects have aspects that are unique to the organization requesting the work to be done.
For these multi-disciplinary tasks, knowledge o f other trade work and specific
information from the organization requesting the work are necessary to optimize the
result.
operates over 15,000 miles o f high-voltage transmission lines across the Northwest. BPA
supplies bulk electric power to local utilities for distribution to homes and businesses.
The most prominent structures in any transmission line are the towers. Transmission line
towers are made up o f many individual parts. This project is limited to the essential
processes for installation and inspection o f transmission line lattice steel tower
foundations. Tower foundations are also referred to in the industry as tower footings. In
transmission lines.
8
CHAPTER 2
REVIEW OF LITERATURE
that could be eliminated using Lean Six Sigma (LSS). According to Al-Aomar, LSS has
not been widely applied in the construction industry. O f the twenty-seven types o f waste
identified in the Al-Aomar study, construction errors were found to be the most common
type o f waste. Inspection is a type o f waste that can be reduced by Lean Six Sigma
methods, but Al-Aomar noted that inspection is not often recognized as waste by the
industry.
Strate and Laplante (2013) demonstrate how the software industry is using Lean
Six Sigma to reduce the need for inspection. Inspecting critical parts o f the process is
more important than continuous inspection or even random inspection. Instead, Quality
Professionals can use Lean Six Sigma to determine the most likely areas for defects and
focus on those areas for inspection. Arumugam, Antony & Douglas (2012) argue the
social sciences tool that has direct applications to quality. Observation is also a Lean tool
because it uses very few resources but can immensely increase value. Arumugam,
Antony & Douglas performed a study and applied their observation technique at key
points with quality improvements as the goal. Using the Six Sigma methodology, the
authors reported that the critical time for observation is during the measure stage o f the
9
Six Sigma process. Results o f the study showed that inspection can be limited without
process. Rather than having full-time inspectors throughout a process, the study suggests
using workers trained to observe critical points to reduce the need for official inspection.
The study also showed that involving both workers and inspectors as observers increased
processes. Sui and Teo (2004) studied two construction companies that implemented
TQM and the results o f those efforts. During the study, both companies benefitted from
TQM. These results were obtained through process improvement and value stream
mapping, which are also used in Lean Six Sigma. Value stream mapping is a quality tool
used to explain the steps in a process visually. Value stream mapping helps identify steps
in a process that may need improvement, or steps that can be eliminated if no value is
added. Once the steps are known, process improvements can be implemented. Some
Quality assurance in the energy industry starts in the design o f the structures that
will be used for the project. Designs are analyzed by engineers using sophisticated
software that calculates loads, structure size needs, and failure analysis. “The design
10
objective for lattice towers is to fulfill the stability criterion and sustainability in the
worst environmental conditions. The transmission line towers are designed against
failure containment loads comprising o f anti cascading loads and tensional and
longitudinal loads” (Ahmed & Maiti, 2012, p .l). After design, “Proof-loading or the full-
scale testing o f towers has traditionally formed an integral part o f tower design”
(Albermania, Kitipomchaib, & Chanb, 2009, p .l). Proof testing is the construction o f all
or part o f a tower design then loading to failure. The results help improve tower designs
construction project, quality assurance is often met through three phase quality control
which was developed by the U.S. Army Corps o f Engineers. Essentially, three phase
quality control requires documentation o f three meetings for each definable feature o f
the work. The three phases and corresponding meetings are Preparatory, Initial, and
Follow-up. In each phase, workers and management review the applicable drawings and
specifications assess current progress. In the Preparatory phase, the intent is to determine
whether or not the project is ready to proceed. Answers are needed to questions such as
“are all materials received and inspected?” In the Initial phase, the meetings cover
readiness to proceed and inspection o f the first work outputs. The Follow-up phase
continues the review o f documentation and progress and determines whether or not the
In addition to endorsing three phase quality control, BPA also subscribes to the
Currently, BPA employs full-time inspectors that practice continuous inspection through
every aspect o f construction. Since 2011, BPA has required prime contractors working
inspectors, each prime contractor for BPA is required to have a quality department and
inspectors. On most BPA construction projects, there are also third party special
inspectors assigned to particular types o f work such as welding, concrete, and equipment
exist (see Appendix A). The National Highway Institute (NHI) Drilled Shaft Foundation
Inspection Manual covers nearly every aspect o f drilled shaft foundation construction.
The NHI manual is used by installers and inspectors to gain knowledge and practical
advice on the best practices and multiple methods for shaft construction; however, the
manual does not contain any information on placing the steel portion o f a tower footing
into a shaft foundation excavation. BPA also has a similar manual called the
Transmission Line and Substation Construction Inspection Manual. The BPA manual
covers all aspects o f transmission line construction, but does not go into detail on every
12
aspect. The manual also does not include the methods and calculations necessary for
footing placement. Information isolation has been observed in many different industries,
and was specifically addressed in an article by Shuang et al. (2009). The article describes
a study conducted in the fast growing shipbuilding industry in China and how
departments that keep information from other stakeholders in the project increase the
overall cost and reduce productivity. Conversely, the article shows how process mapping
and wide distribution o f the process can have dramatic effects on cost reduction and
productivity increases.
This project is the first step in sharing information and reducing variation in the
footing setting process by standardizing the process o f footing installation and offering
methods, calculations, and best practices. Mapping and standardizing the process will
reduce the need for inspection, while empowering workers to create a higher quality
product. Moon (2013) indicates that inspection is not necessarily a good way to ensure a
quality end product. Moon demonstrates that inspection may miss several opportunities
for improvement when used as the sole means o f quality control. Instead o f inspection,
Moon recommends using dynamic quality control and using the workers performing the
tasks as the first line o f defense against defects. The footing setting handbook in
Appendix A gives footing workers the tools not available elsewhere that they need to
implement quality changes that benefit BPA, its stakeholders and the contractors
the 1950s and bringing modem quality theories and methods to the United States.
Although Deming preached that quality could not be inspected into a product, some
increased inspection is that catching flaws gives the organization a chance to fix them
before they get to the customer. Deming’s response was that quality should be built into
organizational changes that improve systems and processes to remove variation. Deming
firmly believed that variation must be understood as having two separate causes, only
one o f which can be corrected by the worker. The most prominent cause o f variation,
produce their work. In many instances, management supplies the tools and procedures
while the workers only carryout the work. In cases where employees are not allowed to
adjust the procedures or process, errors and variation can only be reduced by
management. Inspection may reveal flaws caused by variation, but it is not a cure for the
The goal o f a Lean Six Sigma project is to reduce variation, the cause o f
defective products. The methods used to reduce variation include reduction o f waste in
every aspect o f the process. Several benefits can be realized when waste and defects are
reduced or eliminated. Those benefits include higher profits through efficiency gains,
14
increased job satisfaction, and higher morale. Reducing variation also reduces the need
The book Lean Thinking suggests that value should be derived from the
customer’s point o f view (George, Rowlands & Kastle, 2004). The end user o f the
system o f electrical transmission, homeowners and business owners, care most about
reliability and cost (JD Power, 2013). The immediate customer o f the footing setting
crew is BPA. BPA also greatly values reliability and cost. The element that has the
greatest influence on reliability and cost, with regard to transmission line tower footing
construction o f the rest o f the tower to the specified tolerances without additional
stresses not accounted for in the design. Because all tower parts are pre-made and only
construction and immediately require rework. Minor location inaccuracies are much
more dangerous because they can induce stresses in other parts o f the tower, creating the
Cooper and Moore (2013) describe how a process map is constructed and explain
the parts o f the map. The chemical industry uses process maps to create a comprehensive
overview o f the work. The map is then used to determine the most logical place for
measurements and data collection. Mapping the process also suggests where
improvements can be made and waste removed. A key point in the article is that the
15
process map allows people to understand the relationships between steps. One o f the
deliverables created by this project is a process map for footing installation. The process
map gives a visual demonstration o f the value created for the customer as it flows
through the process. The map distinguishes inspection points allowing inspection as
needed rather than continuously. Distribution o f the process map to those involved with
footing setting prevents information isolation and reduces variation by offering a set way
CHAPTER 3
METHODOLOGY
is known to be one o f the least understood and most problem-prone processes. Engineers
have designed, modeled and tested tower footings. All existing towers are set on some
type o f footing, but formal documentation o f the process for installing these structures is
not readily available. The documentation provided to the installers is accurate but does
not explain exactly how the information should be used. Very tight tolerances have been
developed and implemented for tower footing setting. To complicate the setting process
even further, the footing process contains seven individual elements that a footing setter
must meet in order to place the footing accurately. Those elements are: elevation, plumb,
distance from tower center, distance from footing to footing, rotation o f the tower, twist
o f the footing, and the batter o f the footing angle. After reviewing documentation o f
specification and the finished product. The result o f this information gap is widely
varying processes between crews. Different processes produce inconsistent results and
Design o f Investigation
To address this problem, Lean Six Sigma (LSS) was chosen as the most relevant
quality method to eliminate issues involved with tower footing installation. LSS is
17
wasteful steps in a process to improve quality. The methodology used for this project
The project also draws on the Lean methodology o f waste reduction and specific written
Population
projects underway. The largest transmission line project, consisting o f forty miles o f new
construction, was chosen by BPA management and was examined for the purposes o f
this paper. The transmission line under construction was made up o f lattice steel towers
and footings typical o f BPA projects. The Prime Contractor had hired a specialized firm
as a sub-contractor to install footings ahead o f the crews building the transmission line
towers. The footing contractor assembled two crews consisting o f ground men,
operators, and one footing setter for each crew. Together, the crews averaged completion
o f four footings at one site for each day worked. Sample data was taken over a random
two-week period for the initial assessment and again over another random two-week
Treatment
During the Define stage o f the DMAIC process, the Lean Six Sigma team sought
to discover if the chosen construction project needed improvement, and if so, what
18
would be the best way to improve results. Once the Lean Six Sigma team was on site in
early June, 2014, a schedule for random sampling was chosen. The team decided to
examine every footing installation performed during the two-week period. During the
first two-week sample period, ten tower sites were visited during and after the footings
were installed. During installation, site data, crew notes and field calculations were
collected. After installation at each tower site, measurements were taken and compared
to the site data provided by BPA and to the tolerances defined in the construction
documents.
Through examination o f field notes recorded by the installation crews and site
data supplied by BPA, several issues were determined to have contributed to the high
error rates o f footing installation. The primary issue observed in the field notes was a
lack o f standard methods for calculating field measurements for construction dimensions
used in placing the footing. A second issue found in the documentation was a lack o f
double check o f the field calculations for errors. Another issue that contributed to the
error rates was the use o f incorrect data for the site specified by BPA.
Data Analysis
Each o f the ten sites visited consisted o f four footing installations or processes.
Each footing process consisted o f seven measurable operations. Each operation was
sample period were recorded as errors shown in Table 1. Recorded errors in the second
19
sample are presented in Table 2. The mean number o f errors for each sample was also
Table 1
Table 2
Compiled field observation data is shown in Table 3 and error rates are displayed
in Table 4. During the initial observation period, 39 operation errors were documented
out o f 280 operations total. At least one error was found in 70% o f observed tower sites,
and errors were found in 14% o f the operations performed. The histogram in Figure 1
and graph in Figure 2 display the types o f errors and related percentages.
Table 3
Field Observations
Sites 10
Processes observed 40
Operations per process 7
Total operations observed 280
Total errors observed 39
Table 4
Error Rate
45%
40%
35%
30%
25%
20 %
15%
10%
5%
0%
Calculation P lace/M easu re D ocum entation Excavation C hart d a ta Backfill e rro r
e rro r e rro r e rro r e rro r erro r
The analyze stage o f DMAIC seeks to determine the cause o f the discovered
problem so that selected solutions can be determined to eliminate the problem in its
entirety. Root cause analysis can take many forms such as Change Analysis, Tree
Diagram. The Lean Six Sigma Team used these tools to examine the contributing factors
to errors found in the footing setting process. The team found the root causes to be:
The measurement and analysis phases o f the DMAIC process for this project
revealed such a high error rate in the studied construction project that the prime
contractor issued a stop work order until improvements to the footing process could be
determined, documented, and approved. The improve stage consisted o f the footing sub
contractor benchmarking other projects and examining their processes for suggestions to
the problems.
The Lean Six Sigma team chose to address the issues discovered in the analyze
stage o f the DMAIC process by creating a step by step procedure manual and process
map. The footing setting handbook, attached in Appendix A, is the result o f those
23
efforts. The handbook is a compilation o f the relevant information gleaned from field
notes and documents created during previous construction projects at BPA. The
knowledge o f the process to all involved with footing setting. The information in the
handbook also gives workers the knowledge to make informed decisions regarding
methods to solve field problems and an accepted way o f documenting progress and
Creating the Footing Setting Handbook. The footing setting handbook created for
this project is intended to address several issues associated with footing errors. Since a
primary cause o f footing installation errors has been determined to be a lack o f standard
methods for calculating field measurements, the Lean Six Sigma team sought to
document a procedure for performing field calculations that had been used on prior BPA
footing installations with success. Field notes and inspector records from footing
installations known to be in service and error free were gathered and mined fo r footing
installation process notes by the team. The process found in Appendix A, the Footing
Setting Handbook, is the result o f that effort. The process in the Footing Setting
verification, but focuses on field calculations. Since information on processes other than
field calculations can be obtained in materials already available to installation crews the
The issues o f incorrect data use in the field and lack o f double checks are also
addressed in the Footing Setting Handbook. The Footing Setting Handbook gives
24
specific examples o f the necessary data footing crews must use to correctly calculate
field measurements. This data is provided by BPA engineers, but the installers need to
be aware o f its purpose and how to convert it to useful information. The Lean Six Sigma
team also included in the Footing Setting Handbook a section specifically offering
alternate methods o f performing the calculations. This is included to give crews options
for double checking themselves as well as options for outside verification o f their
calculations. Together, the sections included in the Footing Setting Handbook address all
o f the primary causes o f errors found in the construction project used for the project.
Procedures were developed and written in the Footing Setting Handbook for the
measurement procedures, and standard methods for field calculations. The improved
procedures for each process and operation were fully put into practice. The information
needed for all processes was distributed to all members o f each crew as well as the
onsite inspection team. In addition to the process tools implemented for improvement,
additional work tools including laser levels were purchased and placed into service.
Although the computer program for footing setting calculations was considered, the cost
o f the program proved to be prohibitive in light o f the results from less expensive
solutions available.
The Lean Six Sigma team continued to visit the construction project as part o f
the quality controls. The team reviewed inspection records and as-built documentation
25
for footings installed through the end o f 2014. A primary control for this project was
training on the information in the Footing Setting Handbook for all inspection staff at the
construction site. This control allowed the Six Sigma team to rely on the inspectors’
expertise and attentiveness to the footings installed. The inspection staff was able to
review and adjust the installation process used by the crews on a daily basis.
Document Control
information recorded in field notes, inspection records and construction data information
retained from previous construction projects completed by BPA and stored in their
Construction Administration Information System (CAIS). Since BPA did not have a
document specific to footing setting field calculation before the footing setting handbook
was created, the handbook in Appendix A is the first o f its kind. After the initial draft o f
the footing setting handbook had been completed, copies were reviewed and approved
by subject matter experts at BPA. The first draft was also reviewed by outside experts
for accuracy. After review, the BPA Construction Management and Inspection
department manager approved the release o f the document for the purposes o f this
project. The footing setting handbook master document is stored in CAIS. Access to the
document is allowed by the site administrator and granted to all involved with BPA
contract construction. Revisions to the document should follow the same document
control procedures already in place for other BPA materials. Revisions require subject
26
matter expert review and acceptance by the process owner, the BPA Construction
CHAPTER 4
RESULTS
Until this project, BPA did not have a written process map for footing setting or
footing inspection. The lack o f a clear process map and standard procedures has led to an
unavailability o f information about footing setting to some workers who may need the
information. In particular, the contracted firm’s quality control representatives often lack
the knowledge necessary for footing setting inspection. BPA’s full-time footing
inspectors have the knowledge, but in the past that knowledge has been passed person to
The process map developed for footing setting and shown in Figure 3 describes
the necessary steps and the decisions needed for successful footing installation. The
simple seven-step process eliminated wasted steps from the process and allowed for
A rrive on site
V erify survey
information
No
O rder
OK?
New
Yes
Start field
calculations
No
Finish depth o f
Finish all A gree with
excavation
calculations inspector
calculation
Finish Excavation
Start footing
placem ent
No
Yes
No
Pass
Inspection
Yes
Backfill
Create A s-built
Once all members o f the footing crew were thoroughly trained on the best
practices and procedures for footing installation (shown in Appendix A), a measurable
improvement was evident. A follow-up study was conducted at the same construction
site and revealed the footing installation error rates were reduced from 14% to 5% o f
operations, as shown in Table 5. Tower sites with errors and procedures with errors also
showed considerable improvement, but did not reach the goal levels stated in the project
charter. The less than ideal results were partially caused by a significant error which was
found during the follow-up study. The error was in the survey operation o f the process
for a single tower site. Survey was not a prominent problem in the initial study, and
therefore was not specifically identified by the Lean Six Sigma team for improvement,
even though it is one o f the critical operations in footing setting. The survey error caused
a cascade effect and resulted in errors in calculation, excavation, placement, and backfill
Table 5
Before After
Sites 10 10
Processes observed 40 40
Operations per process 7 7
Total operations observed 280 280
Total errors observed 39 13
The construction project studied for this project was sampled on two occasions.
The first sample was taken prior to any improvements by the Lean Six Sigma team. The
second sample was taken after distribution o f the Footing Setting Handbook. The
samples were compared using a dependent t test for paired samples to determine if the
results o f the improvement efforts were statistically significant. The dependent variable
in the test is the actual number o f errors measured. The independent variables used were
the knowledge o f the work crews before and after the Footing Setting Handbook was
distributed. The test results for the comparison between before and after measurements
show a statistical significance (p = .02057) with 95% confidence. The data and statistical
Additional Observations
Implementation o f the Lean Six Sigma solutions has resulted in increased flow
time, stakeholder satisfaction, and quality yield for the construction project studied. With
the introduction o f a computerized system for calculations, cycle time and calculation
errors could be further reduced. Since the footing setter is almost always the most
expensive employee, reducing the time required for calculations will reduce the overall
cost per footing. The high number o f required field calculations increases the
opportunity for errors when the math is performed manually. With computerized
calculations, an increase in the setter’s available time for placement activity means a
crew can increase their number o f footings installed per shift increasing the whole crews
31
yield. It is conceivable that a single footing setter could work with two or more crews
with the help of a computer program for setting calculations, thereby at least doubling
the work output o f the setter and lowering the overall cost o f footing installation. In
setting crew sometimes contains typing errors or misprints. In other rare cases, charts
provided to the setting crews by engineering have been found to have errors.
Now that the process map is in place, the problem o f continuous inspection can
installations can be limited to critical points in the process. For this project, BPA did not
authorize a reduction o f inspection staff, nor did they allow inspection to be reduced to
only critical times. The prime contractor for the construction project studied did
improvements allowed them to limit their staff to only two inspectors for the entire
distribution has increased the reliability o f the transmission system. Error rates directly
affect costs. The cost o f rework, maintenance, and failure can be mitigated by reducing
the construction error rate and minimizing time spent during construction. Stakeholder’s
second concern, reliability, can also be directly affected by implementing error rate
reduction solutions. Every process and system contains waste. The waste discovered in
the footing setting process is no different and can be reduced or eliminated if further
CHAPTER 5
The goal o f this project is to improve overall quality and reduce the need for
inspection o f transmission line tower footings. The project provides knowledge and tools
deficiencies before construction, improve their work processes, and prevent errors.
The project followed the Six Sigma methodology o f DMAIC while incorporating
Lean’s emphasis on waste reduction. The results show a clear reduction in errors which
reduces the need for rework. With the reduction o f rework, which costs contractor’s
money, crews can focus on their primary purpose o f building new transmission lines.
The reduction o f wasted time and reduced costs should be reflected in the bids for future
projects, lowering overall transmission line construction costs and keeping electric rates
lower due to those savings. This results in satisfying one o f the primary stakeholder
project. Errors in construction lead to failures that create an unreliable power grid. The
reduction o f errors achieved by this project has reduced the likelihood o f failure due to
construction errors on the construction project studied. Further quality improvements can
project.
33
Future Investigations
The methods used for improvement o f the tower foundation installation process
can be used for other aspects o f tower construction such as steel erection, wire stringing,
and wire sagging. Common cause variation could be reduced to near zero by use o f
computer calculations rather than relying on human calculation. Figure 3 illustrates the
process developed as part o f this project. The process map should be available to all
workers involved with footing setting and distributed to workers on all BPA projects that
require lattice steel tower footings. To reduce field calculations and the associated
potential errors, BPA should require contractors to use total station transits with the
ability to laser measure distances on an angle. This tool would reduce the need for many
field calculations and provide more accurate measurements on steep and difficult terrain.
BPA and its contract footing firms should also provide footing setters with a
computer program that automatically calculates field setting values using input from the
setter and the design documents provided. Microsoft Excel has been used as a platform
for programs endorsed by BPA that calculate wire sagging dimensions and a similar
REFERENCES
Ahmed, S., & Maiti, P. (2012). Analysis o f lattice steel towers using STAAD Pro.
Albermania, F., Kitipomchaib, S., & Chanb, R. (2009). Failure analysis o f transmission
Arumugam, V., Antony, J., & Douglas, A. (2012). Observation: a Lean tool for
improving the effectiveness o f Lean Six Sigma. The TQM Journal, 24(3), 275-
287.
Caldeira, E. (2014). What are the USACE three phases o f control? First Time Quality.
Cooper, T., & Moore, C. (2013). Use process mapping to improve quality. Chemical
docview/1429679273?accountid=458
Davies, D. (2011). North American tower failures: Causes and cures. [PowerPoint
pelements.com/pdf/public/dave_davies_tower_failure_handout.pdf
Deming, W. E. (1982). Out o f the crisis. (9th ed.) Cambridge, MA: The MIT Press.
36
Engineering Study.
Fleming, W.G.K., Weltman, A.J., Randolph, M.F., & Elson, W.K. (1992). Piling
engineering (2nd ed.). New York, NY: Blackie/Halsted Press, John Wiley &
Sons.
George, M. (2002). Lean Six Sigma: Combining Six Sigma quality with Lean production
George, M., Rowland, D., & Kastle, B., (2004). What is Lean Six Sigma? N ew York,
NY: McGraw-Hill.
Hatch, S. (2000). Practical research answers real-life questions. Public Roads, 64(3), 36-
58
JD Power. (2013). 2013 Electric utility residential customer satisfaction study. Retrieved
from http://www.jdpower.com
Paiva, F., Henriques, J., & Barros, R. C. (2013) Review o f transmission tower testing
Richards, D. J., White, D. J., & Lehane, B. M. (2010). Centrifuge modeling o f the
Shuang-liang, Y., Hong-xia, S., Pei-lan, S., & Chun-guang, L. (2009). Research on
/docview/208612866?accountid=458
Smith, L. (2009). W hat’s preventing prevent? Six Sigma Forum Magazine, 6-7.
Strate, J. D., & Laplante, P. A. (2013). Using Lean Six Sigma to reduce effort and cost in
Sui Pheng, L., & Teo, J. (2004). Implementing Total Quality Management in
Tabsh, S., O ’Neill, M., & Nam, M. (2005). Shear strength o f drilled shafts with minor
INSPECTION HANDBOOK
40
Authorship
This document has been prepared by Thomas Langston for Bonneville Power
Administration.
Further Information
For further information about this document please contact Thomas Langston at
tdlangston@bpa.gov.
Information System (CAIS) website for the most recent version o f this document at
https://bpa.epm-hosting.com.
and operates high-voltage transmission lines across the Northwest, supplying bulk
electric to local utilities for distribution to homes and businesses. The electricity BPA
supplies is transmitted over power lines supported primarily by lattice steel tower
structures. Transmission line construction has divisions including road building, site
preparation, footing installation, tower construction, and wire stringing. Each o f the
work divisions have several processes that crews follow to meet the needs o f the project.
This handbook was created to map the standard process for steel tower footing
construction with a primary focus on footing setting. In addition, the handbook offers
alternate methods for calculating some o f the more difficult dimensions as well as a
excavation, setting, and backfill. A typical footing consists o f a base material, a large
piece o f angle iron, and the connecting hardware such as small steel plates, nuts and
bolts. Different footing types are determined by their base material. Plate footings use a
steel plate base; shaft footings have a concrete shaft base and grillage footings have a
system o f steel beams as a base. Rock footings are composed o f the angle iron placed
into concrete within a drilled hole in a rock substrate. The process for excavation
depends on the type o f base the footing will be set into. As with excavation, the backfill
process is dependent on the type o f base material for the footing. Since all types o f steel
tower footings use the same process for setting the stub angle, the scope o f this
handbook is limited to the setting process which can be used no matter which type o f
footing is installed.
Definition o f Terms
“A” distance: measurement between the tower center hub and the Working Point.
“B” distance: perpendicular measurement from the centerline between two adjacent
“C” distance: measurement from the Tower Center Hub to the vertical centerline o f the
footing excavation (not a setting dimension, the “C” distance is an excavation dimension
only).
Batter: degree o f incline slope o f the stub angle expressed as a fraction or decimal per
foot o f rise.
Elevation: height above a given level such as sea level or the tower center hub. See also
Footing: the lowest steel section o f a transmission line tower leg composed o f the stub
Footing Stub: steel angle portion o f the footing (excludes the base material or plate).
Instrument Height (IH): Measurement from Tower Center Monument to Transit. Also
Plumb: deviation or lack thereof o f the stub angle from perfectly vertical.
Rotation: deviation o f the four tower leg footings as a unit from the specified orientation
clockwise or counterclockwise.
Tower Center Hub: Survey monument placed at the center o f tower location for a tower
site.
Twist: rotation o f the individual footing stub within the foundation either clockwise or
counterclockwise.
Working Point: point at which elevation measurements are taken for the footing. Located
Working Point Elevation (WPE): height o f the working point above sea level.
The mission o f the footing crew is to place the footing stub angles accurately in
the locations specified by the transmission line design documents. Accurate placement
ensures constructability o f the tower. Accurate placement also prevents rework and
maintains the structural integrity o f the tower. Major footing location inaccuracies
prevent further construction and require immediate rework so that tower construction
may continue. Minor location inaccuracies are much more dangerous because they can
induce stresses on other parts o f the tower, creating the potential for ultimate failure.
Accurate placement is the key to footing setting success. With accuracy in mind, BPA
has developed tight tolerances for footing placement. The chart in Table A1 shows the
Table A l.
There are three documents provided by BPA engineers that are essential for
footing setting: the tower type document (Figure A l), which contains a setting
dimension chart for that specific design (Figure A2), the Steel Tower List (Figure A3),
and the Tower Site Datasheet (Figure A4). The tower type document gives the setter
information such as size o f the footing stub and horizontal and vertical setting
K i i x r c w l i . M T . 'S t.
D IM ENSIO NS FOR 6 0 1BODY DIMENSIONS FOR 8 0 ' BODY DIM ENSIO NS FOR IOC?BODY
LEG
PLATE a ROCK PLATE ROCK PLATE 8 ROCK PLATE ROCK PLATE a ROCK PLATE ROCK
EXT
A B C C A B C C A B C C
5 '-0 ‘’ 15.246 10.839 17.660 16.440 18.781 13.339 21. 190 19.970 22.317 15.839 24.730 23.510
7 '- 6 ” 15.688 11.151 18.100 16.880 19.223 13.651 21.640 20.420 22.759 16. 151 25. 170 23.950
io' - o" 16. 130 11.464 18.540 17.320 19.665 13.964 22.080 20.860 23.201 16.464 25.610 24.390
12'-6" 16.571 II .776 18.980 17.760 20. 107 14.276 22.520 21.300 23.643 16.776 26.060 24.830
l5‘- 0 “ 17.013 12.089 19.430 18.210 20.549 14.589 22.960 21.740 24.085 17.089 26.500 25.280
17'-6" 17.455 12.401 19.870 18.650 20.991 14.901 23.400 22.180 24.526 17.401 26.940 25.720
so
CM
22'-6" 18.339 13.026 20.750 19.530 21.875 15.526 24.290 23.070 25.410 18.026 27.820 26.600
25'-0" 18.781 13.339 21.190 19.970 22.317 15.839 24.730 23.510 25.852 18.339 28.270 27.040
27 - 6° 19.223 13.651 21.640 20.420 22.759 16. 151 25.170 23.950 26.294 18.651 28.710 27.490
30 '-0“ 19.665 13.964 22.080 20.860 23.201 16.464 25.610 24.390 26.736 18.964 29.150 27.930
32‘-6" 20. 107 14.276 22.5 20 21.300 23.643 16.776 26.060 24.830 27. 178 19.276 29.590 28.370
S
14
«
20.549 14.589 22.960 21.740 24.085 17.089 26.500 25.280 27.620 19.589 30.030 28.810
0
1
37’-6" 20.991 14.901 23.400 22.180 24.526 17.401 26.940 25.>20 28.062 19.901 30.480 29.250
24.968 17.714 27.380 26. 160 28.504 20.214 30.920 29.700
o
0
4 2 -6 " 21.875 13.526 24.290 23.070 25.410 18.026 27.820 26.600 28.946 20.526 31.360 30.140
4 5 -0 ” 22.317 15.839 24.730 23.510 25.852 18.339 28.270 27.040 29.388 20.839 31.800 30.580
N o
*-
<0 0
22.759 16.151 25.1 70 23.950 26.294 18.65 1 28.710 27.490 29.830 21.151 32.240 31.020
i
23.20 1 16.464. 25.61 0 24.390 26.736 18.964 29.150 27.930 30.272 21.464 32.680 31.460
1
Figure A2. Setting Dimension Chart. Reprinted from “Anchor Setting Dimensions,” by
Bonneville Power Administration, 2006. Reprinted with permission.
The Steel Tower List gives the tower type, foundation base material, footing
type, and location o f the tower along the line. The Tower Site Datasheet gives elevations
for the four footings and the elevations o f the survey monuments for the tower.
2 .2 0 - 0 0 .C 1 0 0 0 , 0 148K 1 6 0 3 0 . 0 2 7 . 5 2 7 . 5 3 0 . 0 PL A T E EA RTH
2 JO * 0 0 . 0 1 0 0 0 . 0 14B K 1 6 0 3 0 . 0 27 . 3 2 7 . 5 3 0 .0 PI A T E EARTH
Figure A3. Steel Tower List. Reprinted from “Construction Data and Stringing
Instructions,” by Bonneville Power Administration, 2014. Reprinted with permission.
. __ __ . ___ ..... —
STATION WORKING POINT ELEVATIONS AND DIFFERENCES TO GROUND OFFSET COND POT/PI
WP. 1 DIF WP.2 DIF WP.3 DIF WP.4 DIF ELEV ELEV
279+36.QRK 389 70 2.1 392.20 1.7 392.20 2.8 387.20 2.0 462.8 388.09
177+44.?AH
185*50.0 40C.20 1 .5 400.20 1.3 400.20 0.9 400.20 0.2 479,8 398.98
198*00.0 400.00 1.0 4 02.50 1.4 402.50 1.5 400.00 I.2 483.4 J5S..81
209+00.0 385.60 o.s 338.10 1 3 388.10 1.4 385.60 0.6 459.C 385.91
220+00.0 367.30 0.4 370.00 1.5 370.00 1.1 367.50 0.9 440.9 367.8S
2 30*00.0 361.20 0.3 363.70 0.2 363.70 1.5 36'. .20 0.9 434.6 361.82
Figure A4. Tower Site Data. Reprinted from “Construction Data and Stringing
Instructions,” by Bonneville Power Administration, 2014. Reprinted with permission.
Site Survey
A site survey is the first step toward setting a footing. A licensed surveyor
verifies the tower location and installs a tower center hub or monument marking it with
the date, tower location and owner information. The initial survey and tower locate are
often performed by BPA and can be completed years before the start o f construction. At
the start o f construction, another surveyor confirms the existing monument locations
July 2014 revOO
48
then places stakes at the four footing center locations for each tower along with a cut or
fill depth for elevation. The staking information is recorded on a tower staking sheet
which is later given to the setter and the setting crew for reference, calculations, and
Figure A5. Tower staking sheet. Reprinted from “Site Survey,” by Bonneville Power
Administration, 2014. Reprinted with permission.
Once on site with tools, equipment and materials, the footing setter starts work
by verifying the survey information on the staking sheet and additionally staking offsets
for later reference. The first calculation the setter figures is the depth to which the
operator will need to excavate. The depth calculation is made by subtracting the height
o f the footing and ground elevation difference from the working point elevation (WPE).
The WPE for each leg o f the tower is given in the Tower Site Data document. Once the
footing excavation depth from ground level is known, the operator can begin excavation.
While the excavation process is under way, the setter continues calculating. The rest o f
the crew assembles the stub angle and prepares for installation o f the footing.
are not individually given in the construction documents. Engineers give the setter
specific dimensions such as the WPE, but they do not give many o f the necessary
the firm contracted to set the footings, and that they are part o f their contract bidding
competitive edge by way o f means and methods specific to their firm. In addition to
means and methods, the height o f the transit, once set, is a variable that virtually
installation. The setter must calculate construction dimensions based on the design
dimensions given. The construction dimensions needed include the height o f transit to
WPE, the sloped “A” distance and the double “B” distance. The sloped “A ” distance is
measured from the transit placed directly over tower center to the working point. This
measurement is different from the “C” distance because o f the angle on which the stub
angle and legs are placed to create the pyramid-like shape o f the tower. Both the “C”
distance and the “A” distance are given on the footing chart but both are given on a
horizontal plane. The “A” distance is pictured in Figure A l and shown in the chart in
Figure A2. For footing installation, these distances are almost never horizontal because
o f the height o f the transit and the elevation o f the working points both o f which can
vary from site to site and footing to footing. The “B” distance is given on the chart and is
a horizontal measurement from one footing, to the centerline between it, and the next
footing o f that tower. For footing installation, the double “B”, or distance from footing to
footing, must be calculated. In addition to simply adding the two “B” distances together,
the setter must calculate the elevation differences between the footings to get a sloped
double “B” distance. He must also account for “A” distance differences because o f the
batter o f the footings. The batter moves footings closer to tower center as they rise in
elevation and farther away as they lower in elevation. The triple calculation required to
obtain the double “B” is the most error prone calculation in footing setting. Once
calculated and measured, the purpose o f the double “B” is to verify that all other
dimension tolerances have been met. Due to the possibility o f error in calculation,
footing setters perform the calculations at least twice. At the same time, the quality
control inspector also calculates the numbers. Once the two are in agreement, the process
can continue.
Initial Measurements and Calculations. The first measurement the footing setter
takes is the Instrument Height (IH) or Measure Up (MU). This step is common to all
survey operations and consists o f measuring from a survey monument up to the height o f
the transit once it is set up and leveled. For footing setting, the IH is the measurement
from the Tower Center Monument up to the transit. The IH added to the Tower Center
The next step is to calculate the Rod measurement. The Rod measurement is the
difference in elevation between the Height o f Instrument (HI) and Working Point
Elevation (WPE). As the footing setter does the math and calculates the construction
setting dimensions, they will also create a dimension sheet similar to the one shown in
Table A2. The information in Table A2 is compiled from the construction documents,
staking sheet and setter’s calculations. This document is used as a reference guide while
Calculating the Sloped “A” distance. The sloped “A” distance is calculated using
the Pythagorean Theorem: A 2+ B 2= C 2. The A 2 side and B 2 side o f the right triangle
consist o f the chart “A” dimension and the calculated Rod dimension. The C 2part o f the
Example: In Table 2, tower station 230+00.0 footing 1, the chart “A” distance is
19.665 feet. The Rod for tower station 230+00.0 footing 1 is 5.8 feet.
A 2+ B 2 = C 2
19.6652 + 5.82 = C 2
386.7122 +33.64 = C 2
V420.3522 = V c 1
Calculating the Double “B” Distance. Calculating the double “B” starts with
considering the elevation difference, if any, between two adjacent footings in a particular
tower. If both footing W PE’s are at the same elevation, the two chart “B” distances can
be added to obtain the double “B” as shown for footings one and four in Table A2. If the
leg lengths and W PE’s between two adjacent footings are different, such as in footings
one and two shown in Table A2, further calculation is necessary to correct for the
difference in elevation and “A” distance. As the footing is raised or lowered in elevation,
it moves either closer or further from tower center because o f the pyramid shape o f
tower legs. The change in “A” distance o f a footing also lengthens or shortens the double
Two calculations are required for the double “B” dimension. This accounts for
the elevation difference and the “A” distance difference. Both calculations use the
Pythagorean Theorem (A 2 + B2 = C 2). In the first calculation, the two chart “B”
distances are added to make the A 2number. The elevation difference between the two
formula. B in the second A2 + B2 = C 2 formula is the difference between the two chart
“B” distances. C in the second A2 + B2 = C 2 formula is the double “B” for those two
tower legs.
Example: For tower station 230+00.0 footing 1, the chart “B” distance is 13.964
feet. The chart “B” distance for footing 2 is 13.651 feet. Added together, the two “B”
distances equal 27.651. The elevation difference between them is 2.5 feet.
a 2+ b 2= c 2
27.6512 + 2.52 = C 2
762.5882 +6.25 = C 2
a / 768.8382 = 4c2
27.72793 = C = “A” for second A 2+ B 2 = C 2 formula. The difference between the two
chart “B” distances is 0.313 feet and is used as B in the second A " + B 2= C 2 formula.
a 2+ b 2= c 2
21.1219V + 0.3132= C 5
768.8382 + 0.097969 = C :
a / 768.9362 = 4c2
Leg# 1 2 3 4
Leg Length 30’ 27.5’ 27.5’ 30’
WPE 361.2 363.7 363.7 361.2
Rod 5.8’ 3.3’ 3.3’ 5.8’
Chart “A” 19.665 19.223 19.223 19.665
Sloped “A” 20.5’ 20.08’ 20.08’ 20.5’
Chart “B” 13.964 13.651 13.651 13.964
Excavation
There are four types o f steel tower footing base materials: plate, grillage, shaft,
and rock. Excavation for the tower footing depends entirely on the footing type. Footing
excavation is a separate process not covered in detail in this handbook. Plate and
Grillage footings are excavated using heavy equipment such as excavators. Shaft and
Rock footings are drilled. Plate, Grillage and Rock footing excavation is explained in
detail in the project specific technical specifications and the Master Agreement technical
Placement
Placement o f the stub angle starts once the excavation and setting calculations
are complete. With direction from the footing setter the crew moves the assembled stub
angle into place. The stub angle is set to the correct batter and twist as well as the
calculated dimensions. The batter angle for the stub is found on the tower type
a given change o f elevation much like the pitch o f a sloped roof. Twist is simply the
orientation o f the face o f the stub angle directly toward tower center. In order to meet the
tolerances o f all seven setting dimensions, crews manipulate the stub angle, measure,
and repeat until all dimensions match the setter’s numbers and the tolerances listed in
Table A l. At this point, backfill begins locking the stub angle into place with soil, rock
Backfill
As with excavation, backfill methods depend on the footing type and base
material. Plate and Grillage footings are backfilled with soil. Details o f soil backfill are
covered in the project specific technical specifications and the Master Agreement
technical specifications. Rock footings are backfilled with grout. Grouting is covered in
the project specific technical specifications and the Master Agreement technical
specifications. Shaft footings are backfilled with concrete. The National Highway
Institute’s Drilled Shaft Inspection Handbook is an excellent resource for shaft backfill
information.
July 2014 revOO
Location Verification or As-built
The staking sheet shown in Figure A5 is used to record as-built dimensions after the
footings are set but before the rest o f the tower is constructed. Each o f the setting
dimensions is measured and recorded on the back side o f the staking sheet. Recording
the final dimensions gives the crew a chance to check the physical dimensions o f the
footing to the setting tolerances shown in Table A l. As-built staking sheets are delivered
Batter. The batter o f a tower leg and therefore the footing stub is located on the
tower type drawing. In cases where the batter is not listed or when a double check for
drawing accuracy is desired, the following formula can be used to calculate the batter.
View the chart for the footing in question. Choose the “A” distance for any two different
leg heights. Choosing leg heights that are 10 feet different makes the math very easy.
Next, subtract one “A” distance from the other “A” distance and divide the sum by the
vertical difference between the two leg lengths. The final step is to convert the decimal
1.768/ 10 = 0.1768
“B” distance. Errors in chart data for tower footings are rare, although not
impossible. There are several methods for double checking chart data and calculated
Usually the calculated dimension is only slightly different from the chart dimension. If a
A double check for the chart “B” distance involves simple algebra based on
simple geometry as shown in Figure A6. To check the chart “B” distance, multiply the
chart “A ” distance by 0.7071 then add the thickness o f the stub angle steel. The
thickness o f the stub angle steel has to be added because the chart “A” distance is
measured at the working point but the “B” distance is measured to the outside o f the stub
B2+ B2= A2
2 B2 = A2
42 B = A
B = —42 A
2
B = 0.7071 A
Footing
A distance
B
Tower Center
B
Double “B” Alternate Calculation M ethod. As with checking the chart “B”
distance, the “A ” distance and thickness o f the stub angle steel can be used in the
following formula to calculate the double “B” as an alternate method where HD is the
Leg 1, chart “A” distance: 19.665 plus steel thickness 0.125ft - 19.79
Leg 2, chart “A” distance: 19.223 plus steel thickness 0.125ft = 19.348
19.792 + 19.3482 = H D 2
391.6441 + 374.3451 = H D 2
a / 765.9892 = HD
27.67651 = HD
H D 2 + Elevation Difference2 = B B 2
27.676512 + 2 . 5 2 = B B 2
765.9892 +6.25 = B B 2
a /7712392 = BB
27.79 = BB
and the number o f variables in those calculations. There is no question as to why footing
setting is highly specialized, and footing setters are rare individuals in the power line
construction trade. One might ask themselves why the dimensions needed to set a
footing are not found in the construction documents. The answer is that field conditions
and the tools used to overcome them vary. The single variable o f the transit height can
differ 12 inches or more from one setup to another. The reason for the variance is site
conditions. The site may be on the side o f a mountain where one leg o f the transit is
three feet below the other sides and the tower center monument is eighteen inches higher
Eliminating variables from the calculations such as human error would greatly
reduce the chance o f errors in the final setting process. Computer programs such as
Microsoft Excel were designed for this purpose. Excel, on its own, will calculate the
numbers if a footing setter can use it in the field but without a software structure for
footing setting it is little more than a large calculator. Luke 2.0, shown in Figure A7, is a
software package designed by a BPA inspector that operates in Excel and is designed
ROP D O W N LIST
3 i John Smith POT&BM T.C. ELE. LINE N U M . # # # /# SERIAL NUMBER 'OW ERTYPE BODY H‘ STATION
4 Error
5 ROTATED/SQUARE POT/PI T.C. ELEV. TOWER TYPE BODY HT ANGLE OEC--MIN OFFSET
6
7 TOWER CENTER ELEVATION | SOIL FOOTING TYPE SPAN AHEAD CONDUCTOR ELEV
12 SITE DATA
14 ! W .P. ELEVATION
Figure A7. Luke 2.0. Reprinted from “Luke 2.0,” by Luke Hatfield 2014. Reprinted with
permission.
The program uses a few simple inputs from the footing setter and produces a
complete set o f construction dimensions, as well as as-built fields, tolerance checks, and
Figure A7 shows the main page o f Luke 2.0. The footing setter needs only to
input the Instrument Height and the tower location. The program uses that information
and information about the line construction project and produces a working footing
setting dimension sheet as shown in Figure A8. The program also contains other useful
information generated from the preprogrammed data and additional inputs from the
footing setter including graphical representations o f the tower legs and a slope
ENTER VALUE
"A" DIMENSION
"B” DIMENSION
ANDARD C DIMENSION
13 MCONC'C” DIMENSION
23 1 TO 3 2 TO 4
32■BSBBHHIHBH
33 1 TO 2 2 TO 3
P CALC. INCHES >
3 TO 4
2.12
4 TO 1
Figure A8. Luke 2.0 Footing Setting Dimensions. Reprinted from “Luke 2.0,” by Luke
Hatfield 2014. Reprinted with permission.
With the purchase o f the program, a license is granted for a specific period and
includes programming for a single line construction project. Extensions o f the license
period and additional line construction programming services are available from the
copyright owner.
REFERENCES
Dimensions.
Technical Specification.
Bonneville Power Administration. (2014). [Steel Tower List] Construction Data and
Stringing Instructions.
PROJECT CHARTER
Project Charter
voltage transmission line towers are an integral part o f the power grid. Towers hold the
wire that allows transmission o f electricity and keep the wires located safely above the
people and objects they might endanger. BPA operates 15,000 miles o f transmission line
and builds approximately 200 miles o f new transmission line per year. BPA is focused
on safety first and reliability next. BPA believes a reduction in construction errors will
Tower failures result in damage to property, as well as the potential for human
injury and death. When failures occur, they can be attributed to several types o f causes
often relate to issues such as poor design, unusual or extreme loading, or construction
errors.
A common type o f transmission tower is the lattice steel tower. Lattice steel
towers are used for electrical transmission as well as communications mediums such as
cellular and broadcast antennas. Studies have shown that 31% o f tower failures can be
attributed to construction errors. Newly designed lattice steel towers are proof tested
before entering into active service. The proof test consists o f full-scale construction o f a
tower design and load testing to failure. Proof testing is common for transmission line
towers but has limitations and does not reveal flaws in foundations. Studies have
revealed high foundation defect rates with several types o f errors and flaws. Internal
The purpose o f this study is to reduce the error rate in the construction o f
developing and implementing processes and tools that reduce waste and increase
accuracy by educating the construction crews performing the work. Studies have shown
that a major reason for construction errors is that crews building towers must make
engineering decisions but frequently lack the knowledge to do so. This project is
intended to prevent rework, increase productivity and reduce costs. The project is also
steel towers. The project accomplishes this goal by presenting a process map and best
practices manual for improving the construction quality o f transmission line tower
foundations.
BPA would like to reduce the transmission line tower foundation error rate on
completed foundations to less that 1%. BPA would also like to reduce the error rate for
work in progress on foundations to less than 10%. In addition to reducing rework, these
improvements will increase safety and overall reliability o f the power grid. The
improvements should also reduce the cost o f construction for new power lines.
Email: tdlangston@bpa.gov
LukeH.
LenS.
This project will map, revise and implement a best practices process for
The missions are to reduce the transmission line tower foundation error rate on
completed foundations to less than 1%, to reduce the error rate for work in process on
foundations to less than 10%, and to reduce the error rate for work in progress on
Problem Statement
An internal study at BPA concluded that foundation error rates were 14% for individual
footing setting operations in each process and as high as 70% for the entire process o f
This project will examine the current processes, tools, and materials used in
foundation construction. The team will determine the best practices and any new
technologies that may increase the accuracy o f installation then document them into a
handbook for distribution to workers in the field. The team will oversee the
Business Need
BPA’s commitment to reliability o f the bulk electric system is also written into
federal law and enforced by regulatory agencies. Reducing error rates and thus
from this project are safety o f the general public as well as overall cost savings by
Deliverables
Resources
The project requires sponsor support for the use o f the project leader
(approximately 20 percent) and for the core team members on a part time basis
(approximately 5%) for the duration o f the project. Purchase o f new technology items
Table 1
Sum 68.975
Variance= 1.7686
Table 2
Sum 24.775
Variance= 0.6353
Summary Values
N 40 40 40
Sum 39 13 26
df = 39
t = 2.41
P = 0.2057