The Proven value

Efficient, fast, flexible Smart maintenance approach


and cost effective Extended 33,000-hour combustion and hot gas path
inspection intervals.
The AE94.3A is a quick start gas turbine that can reach
Lowest LCOE (Levelized Cost of Electricity) in F-class.
baseload condition in less than 25 minutes by a fast
Ansaldo Energia offers a full and flexible range of
load ramp, making it suitable for grid support as well.
service solutions, from Transactional Services through
As a result of premix extension from synchronization
to Operation & Maintenance contracts.
to base load, high flexibility is ensured throughout the
Customized service agreements allow customers to
entire operating range, including all transient conditions.
choose the best solution to fit their needs.
A wide selection of fuels can be used, ranging from
natural gas to liquid fuel, with hot fuel change over
capability. Well proven technology
Since 1999, Ansaldo Energia has awarded more than
Environmental sustainable 70 units of AE94.3A, with a capacity of almost 20 GW
both in open and combined cycle.
The Minimum Environmental Load has been reduced
Continuous product improvement, combined with
keeping NOx and CO emissions well below current
consolidated reliability and robustness, have driven an
legal limits.
increase in power output and efficiency values.
AE94.3A
The Proven value

AE94.3A Performance
Natural gas, ISO conditions Power Plant Configuration 1+1 2+1
Power output MW 325 CC Net Output MW
480 960
Efficiency % 40.1 CC Net Efficiency % 59.5 59.5
Exhaust Mass Flow kg/s 750 CC Net Heat Rate (kJ/kWh) 6,050 6,050
Exhaust Temperature °C 589 Plant Turndown - (%) 45 45
GT minimum load % 40 Minimum load
NOx emissions mg/Nm3 ≤ 50
CO emissions mg/Nm 3
≤ 30
General note: Performing data are calculated with 100% methane
Loading rate MW/min 22 (LHV) at ISO conditions, sea water condenser.
Grid Support MW/min up to 45

Worldwide references: decades of experience


The fleet of AE94.3A has an excellent track record of availability, operational flexibility and durability.

> 3,200,000 Cumulated EOH


Africa: Algeria; Tunisia.
74 Units
Asia: China. 7 Open Cycle
Europe: Belgium; France; Greece; Hungary; Italy; Russia; Spain; Turkey. 67 Combined Cycle
Middle East: Syria; UAE; Iran. (14 Single Shaft)

Ansaldo Energia, all rights reserved. The information contained in this document is merely indicative. No representation or warranty is provided, nor should be
relied on, that such information is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances.
Said information is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written
authority, is strictly prohibited.

Ansaldo Energia
Via N. Lorenzi, 8 - 16152 Genoa - Italy - Tel: +39 010 6551 - Fax: +39 010 655 3411 - info@ansaldoenergia.com - ansaldoenergia.com

Das könnte Ihnen auch gefallen