Beruflich Dokumente
Kultur Dokumente
Section A
Q1. You have recently completed a 750 MW power plant with the total cost of AED 270 Million.
You have been assigned to prepare a ball park estimate for new 870 MW powerplant. Historical
information suggests you to use 0.60 Exponent.
3. What is the exponent range typically used for Capacity Factor Method?
a) 0.4 to 0.89
b) 0.5 to 0.85
c) 0.6 to 0.78
d) 0.1 to 1.0
4. As per AACE International classification, this estimation will provide you with what class of
accuracy?
a) Class 5
b) Class 4
c) Class 3
6. If the new project doesn’t have some scope worth 50 Million, which you have completed in the
last project, what will be new project cost?
a) 240 Million
b) 244 Million
c) 248 Million
d) 241 Million
7. If the exponent / proration factor increases, what will be the effect on new project cost?
a) There will be a further increase in new project cost
b) There will be a further decrease in new project cost
c) There will be no effect on new project cost
d) None of the above
Q2. With respect to AACEI and ANSI estimating classification, answer the following seven
questions.
3. An accuracy range of -15% to + 30% for a process industry falls under which class of estimate?
a) Class 1 – Definitive Estimate
b) Class 2 – Definitive Estimate
c) Class 3 - Budget Estimate
d) Class 4 – ROM Estimate
4. If you want to prepare estimation for bidding purpose, what class of estimate would you suggest?
a) Class 3 – Budget Estimate
b) Class 5 – ROM
c) Class 2 – Definitive Estimate
d) Class 4 – Budget Estimate
5. As a contractor what class of estimation you would prepare for lump sum contract?
a) Class 3
b) Class 4
c) Class 5
d) Class 1
6. Of the following, comparatively, which estimate requires least amount of effort to prepare?
a) Forced Detail
b) Definitive Estimate
c) Budget Estimate
d) Detailed Control Estimate
7. An estimate prepared using Capacity factor method falls under what AACEI Estimation class?
a) Class 5
b) Class 4
c) Class 3
d) Order of Magnitude / Ball Park
Plan at End of 2nd Quarter: Tasks 1, 3, 5 and 6 should be completed, Tasks 2 and 4 should be 96
percent complete, and Task 7 should be 51 percent complete.
Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent
complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been
charged to the project.
Calculate the following values (assume that all tasks incur costs uniformly over time):
1. At project initiation, what was the total projected cost of this project (BAC)?
a) $289000
b) $390000
c) $280000
d) $309000
2. On the status date, what is the budgeted cost of work scheduled (PV)?
a) $168570
b) $178540
4. What is the earned value (EV) of this project on the status date?
a) $118900
b) $190000
c) $129000
d) $129800
Section B
01. Given:
BACWP =200
ACWP =120
BCWP =80
CPI =0.666
Assuming that current variances are atypical, and that similar variances will not occur in the future,
the estimate at completion (EAC) is:
a) 120.
b) 160.
c) 200.
d) 240.
02. Given:
BAC =200
ACWP =120
BCWP =80
CPI =0.666
Assuming that current variances are typical of future variances, the estimate at completion (EACWP)
is:
a) 220.
b) 260.
c) 300.
d) 320.
03. The cost baseline has all of the following characteristics EXCEPT:
a) It is a time-phased budget that will be used to measure and monitor cost performance on
the project.
b) It shows the actual cost expenditures throughout the life of the project.
04. The estimate at completion (EAC) is the projected or anticipated total final value for a schedule
activity, WBS component, or project when the defined work of the project is completed. To
determine the EAC, assuming no management intervention, which of the following information is
needed?
a) The Earned Value (BCWP) and the actual Cost to date (ACWPC).
b) The Cost Performance Index (CPI) and the Cost Variance (CV).
c) The Actual Cost to date (ACWPC) and the Cost Performance Index (CPI).
d) The Actual Cost to date (ACWPC) and the Estimate To Complete (ETC).
05. Your schedule analysis has shown that your project has a high likelihood of experiencing a
schedule overrun. You know this because the cumulative BCWP is much:
a) Higher than the cumulative ACWP.
b) Higher than the cumulative BCWS.
c) Lower than the cumulative BCWS.
d) Lower than the cumulative CPI.
06. Which of the following choices indicates that your project is 9% under budget?
a) The cumulative ACWP was 100, and the cumulative BCWP was 110.
b) The cumulative BCWS was 100, and the cumulative ACWP was 110.
c) The cumulative ACWP was 110, and the cumulative BCWP was 100.
d) The cumulative BCWP was 100, and the cumulative BCWS was 110.
07. During the sixth monthly update on a ten-month, $30,000 project, the analysis shows that the
cumulative BCWS is $20,000, the cumulative ACWP is $10,000, and the cumulative BCWP is $15,000.
In planning its action, management can conclude all of the following from these figures EXCEPT:
a) Less has been accomplished than was planned.
b) Less has been spent than planned.
c) Continuing performance at the same efficiency with no management intervention, the
project will probably be completed ahead of schedule and over budget.
10. If cumulative BCWS = 100, cumulative BCWP = 98, and cumulative ACWP = 104, the project is:
a) Ahead of schedule.
b) Headed for a cost overrun.
c) Operating at project cost projections.
d) Likely to come in under budget at completion.