MOP FOR 2G EXPANSION

1 Objective
The objective of this activity is to expand 2G on site

1. Perform health check on Site, including active alarms and vswr


monitoring.

2. Take backup of configurations of IDB

3. Label feeders, E1 cables

4. Pre-install new feeders jumpers, RUS and DUG

5. Call FO to inform about activity

6. Make changes to existing DUG and configure new DUG is any

7. Make feeder and jumper connection changes

8. Call FO to unlock site and confirm that site is up and carrying


traffic

9. Check alarms and monitor vswr

10. Close activity