1. Lumber shall be of good quality and free from knots and cracks, conforming
to specified sizes and dimensions.
2. Veneers (plywood) thickness and usage shall be required in details as
approved by the Architect.
IV. METHODS
A. SITE / EARTHWORKS
1. Concrete – mix may be done manually using water – tight mixing platforms,
cares shall be taken to avoid segregation.
2. All CHB – cells shall be filled;
3. Concrete shall be poured in dry.
4. Proper concrete – compaction shall be made during pouring.
5. Forms and steel – reinforcement shall be properly braced and supported to
avoid displacement during pouring.
6. Lapping of steel bars, bonds at ends shall conform to ACI Code provisions.
7. All concrete and masonry works shall be done on proper workmanship
considering alignments and quality – to – finish.
1. All material used for finishes on flooring, walling and ceiling, unless otherwise
specified, shall follow finishes – schedule as indicated on
2. Plane. Care shall be considered so as not affected the works of other trades.
3. Design, patterns, color, finish and layout shall have the clearance of the
architect before any work commenced.
F. ELECTRICAL WORKS
All Electrical works shall be done in accordance with all the requirements of the
latest issue of the Philippines Electrical Code, with the rules and regulations of
the Local Enforcing Authorities and the requirements of the local Power
Company.
G. STRUCTURAL STEEL
All works shall be done in accordance with pertinent specifications indicated in
the AISC Manual.
All works required related to the project shall strictly comply to the provisions
under the FIRE CODE OF THE PHILIPPINES (PD 1185)