Beruflich Dokumente
Kultur Dokumente
List of Tables
Table 1 : List of notified villages for MBSIR area…………………………………………………4
Table 2 : Proposed Land Use detail for MBSIR Area…………………………………………….6
List of Figures
Figure 1 : Map showing Location of MBSIR in Gujarat………………………………………..1
Figure 2 : Map Showing Villages in MBSIR and Road Connectivity for MBSIR………...…2
Figure 3 : Map Showing TP Scheme areas For MBSIR………………………………....……3
Figure 4 : MBSIR area and its external connectivity (Existing)……………………….….….5
Figure 5 : Proposed DP Plan for MBSIR Area…………………………………………….……8
Figure 6 : Proposed External Road connectivity for MBSIR area……………………..........10
Figure 7 : Electrical Substation near Maruti Plant……………………………………………...13
Figure 8 : Existing Industries in MBSIR Region………………………………………………..14
Figure 9 : Work Plan………………………………………………………………………………15
Figure 10 : Cluster A –Zone wise Load Detail……………………………………………………21
Figure 11 : Cluster B –Zone wise Load Detail…………………………………………………...21
Preliminary Electrical Network Planning for MBSIR
1.0 INTRODUCTION
1.1 Background
MBSIR Area is divided in to two clusters (Cluster A and Cluster B); Cluster A covers 3
villages (approx..50.59 sq.km.) and the Cluster B covers 5 villages (approx. 51.50 sq.km.) of
Ahmedabad and Mehsana district and comprises of automobile, manufacturing and auxiliary
industries (see Fig 2). The proposed SIR area is to be developed through 5 Town Planning
Schemes in two clusters (see Fig 3). The SIR is well connected with trade gateways and
falls in the influence zone of proposed Delhi–Mumbai Industrial Corridor (DMIC).
1
Preliminary Electrical Network Planning for MBSIR
Figure 2 : Map Showing Villages in MBSIR and Road Connectivity for MBSIR
2
Preliminary Electrical Network Planning for MBSIR
The main objective of the report is provide the design approach to provision and
accommodate Electrical network requirement like Sub-station space location/space planning
and Electrical Trench/Corridor which needs ducting under the roads. The required space for
the Electrical Sub-station to be reserve in TP Scheme. This ducting shall be provided during
the road construction to avoid the excavation within Road area in future.
3
Preliminary Electrical Network Planning for MBSIR
2.1 General
Mandal Bechraji Special Investment Region (MBSIR) Spread over more than 102 Sq.km and
is well connected with Delhi – Mumbai Industrial Corridor (DMIC) project. Details list of
notified village in proposed MBSIR area are mentioned in Table-1. The MBSIR area is well
connected through National and State highways as well as Railways.
Presently three state highways pass through the proposed SIR namely SH 7 connecting
Becharaji with Ukardi village. SH 133 providing connectivity between Ughroj and Ughrojpura
and SH 19 connecting Hansalpur with Becharaji this state highway provide major entry and
exit points.
Table 1 : List of notified villages for MBSIR area
Study area superadded in two number of cluster, cluster B covers Ughroj, Ughroj nu Paru,
Ukardi, Bhagapura & Shihor and cluster A covers Hansalpur, Sitapur &Chandanki.
The SIR is regionally well connected through National and State highways. National highway
14- 15 connecting Kandla with Palanpur passes through north of the proposed SIR. NH-8
and State highway no. 7 passes from south, and State highway no. 41 connecting
Ahmedabad and Mehsana passes along eastern edge of the SIR. The five major roads
directly connecting SIR with the National and state highways include.
4
Preliminary Electrical Network Planning for MBSIR
Currently three state highways pass through the proposed MBSIR. SH 7 connecting
Becharaji with Ukardi village. SH 133 providing connectivity between Ughroj and Ughrojpura
and SH 19 connecting Hansalpur with Becharaji. These three state highways form a
triangular loop within SIR and also provide major entry and exit points, please see figure 4 &
5.
5
Preliminary Electrical Network Planning for MBSIR
A Urbanizable Area
1 Industrial Area 28.58 27.99%
2 Logistics 2.10 2.05%
3 Knowledge & IT 3.69 3.61%
4 Residential 31.31 30.67%
5 Affordable Housing 3.82 3.75%
6 High Access Corridor 9.46 9.27%
7 Mixed Use 3.76 3.68%
8 Village Buffer 1.91 1.88%
9 Recreation, Sports & Entertainment 5.91 5.79%
10 Proposed Roads & Rail 7.17 7.02%
Total Urbanizable Area 97.71 95.70%
B Non-Urbanizable Area
11 River 0.27 0.27%
12 SSNL Branch Canal 0.28 0.27%
13 Water bodies 3.24 3.17%
14 Gamtal 0.60 0.59%
Total Non-Urbanizable Area 4.39 4.30%
Of the total MBSIR area, about 28.58 sq.km (28%) is under industries use. Around 2.10 sq.km (2.05%)
area has been kept for logistics use whereas about 3.69 sq.km (3.61%) has been kept for Knowledge
& IT land use. Together, these three land uses comprises about 34.37 sq.km which is close to 33.7%
of the total MBSIR area. The industries area includes GIDC area of around 17.25 sq.km.
Cluster wise, the industries area in Cluster-A is about 9.5 sq.km while the remaining area of 3.17
sq.km is in Cluster-B. The industries area under GIDC of 17.25 sq.km is also in Cluster-B. The area of
6
Preliminary Electrical Network Planning for MBSIR
around 1.10 sq.km under logistics is in Cluster-A while the equivalent area of 1.0 sq.km is in Cluster-
B. The entire area of 3.69 sq.km under Knowledge & IT land use is located in Cluster-A.
Industrial Zone - The industrial zones are planned strategically along the express corridor to ensure
smooth movement of freight within the SIR. The industrial zones are supported by residential, mixed
use and knowledge and IT zones. One industrial node has been proposed near Hansalpur village at
the intersection of SH-7 & SH-19.
Logistics Zone - Industrial zones are supported by strategically located logistics parks to support the
industries in terms of storage and handling of freight in the SIR. Within the MBSIR two logistic zones
are planned along the main express highway viz. L1 at the intersection of SH-7 and the broad gauge
railway line from Mehsana and Ahmedabad (in proximity to Hansalpur village), and L2 along the
proposed express corridor near SH-133 (in proximity to Ughroj village).
7
Preliminary Electrical Network Planning for MBSIR
8
Preliminary Electrical Network Planning for MBSIR
Knowledge & IT Zone -A Knowledge and IT zone has been proposed within SIR with a view to
facilitate development of research centers, educational Institutes and universities along with IT
industries. The Knowledge and IT zone is planned in the surroundings of a non-perennial water body
in Sitapur village.
Residential Zone- The residential zones within the MBSIR are planned around mixed use & industrial
zones. Residential development will also be allowed in knowledge and IT Zone and Mixed use zones.
The total land area allocated for the residential use is around 31.31 sq. km. (30.67%).In addition to
this around 0.60 sq. km. (0.59%) land will be occupied by existing villages.
Affordable Housing Zone- The Affordable Housing zones are proposed in the village of Hansalpur
and Sitapur of MBSIR and the total land area allocated under this zone is around 3.82 sq. km.
(3.75%).
High Access Corridor- With a view to support higher densities and transit oriented development in
MBSIR it is proposed to develop mixed use corridor along the roads with 60 & 45 m RoW. This zone
is predominantly planned between residential and industrial zones and will facilitate mixed uses
including commercial, offices, recreation, community and residential. A total of 9.46 sq. km. (9.27%)
is proposed under this zone.
Mixed Use Zone - Mixed land use zone has been proposed along the two SSNNL branch canals that
passes through MBSIR. Mixed use development comprising commercial facilities, recreation, and
residential along with linear green zone will facilitate development of vibrant public spaces. Around
3.76 sq.km (3.68%) of area is proposed under mixed use zone along the branch canals.
Recreation, Sports & Entertainment Zone- Around 5.79% of total land area is proposed for
development under recreation, sports and entertainment zone. This zone will allow development of
botanical gardens, nature parks, sports complexes, etc. It is strategically planned along the periphery
of lake, natural drain and canal.
Village Buffer Zone- To integrate the 8 villages falling within MBSIR, buffer zones of 100 m and 200
m around each village has been proposed to accommodate the future growth in these settlements.
Residential, commercial and public facilities will be allowed in this zone.
9
Preliminary Electrical Network Planning for MBSIR
10
Preliminary Electrical Network Planning for MBSIR
Based on the potential of the region, the investment scenario and thrust of the Automobile sector
the following sectors have been identified in the proposed SIR:
Automobile industry
Auto-component Vendor park consisting-
o Heavy engineering
o Light engineering including metal & alloy product
o Electronics
o Service & Ancillary
o Non Polluting industries including Information Technology
Logistics
Further based on the key stakeholder suggestions and reference to the National Manufacturing Zone
Policy, following sectors have also been included in the:
Precision engineering
Wind power equipment manufacturing
Solar power equipment manufacturing
Emerging sector in Automobile sector viz. Electronic Systems Design and Manufacturing
(ESDM)
Apart from above Information Technology sectors have also been proposed.
Floating Employment
As per the Final Development Plan, out of the total employment generated in SIR, about 80% is
proposed to reside within SIR developed residential area, while the rest 20% is assumed as the
floating population.
11
Preliminary Electrical Network Planning for MBSIR
12
Preliminary Electrical Network Planning for MBSIR
At present, the power is supplied to 8 villages by UGVCL and 24 hrs power supply is
available to the existing villages. MSIL has established facility within MBSIR-Cluster - A
(near Hansalpur Village) and a UGVCL has constructed substation to provide power supply
of around 90MVA. Also Honda (a two wheeler company)has established facility near MBSIR-
Cluster A (outside) and UGVCL has provided power supply for the same. Honda Plant
required around 12MVA and UGVCL has provided infrastructure to support upto 14.5MVA.
13
Preliminary Electrical Network Planning for MBSIR
14
Preliminary Electrical Network Planning for MBSIR
To achieve the objective of making provision of utilities duct within the proposed RoW
various parameters and consideration needs to be taken or formed before finalizing the
design. Population estimation, demand calculations, technology assessment and
requirement of service provider needs to be assessed.
The utilities which required to be put under the proposed RoW under the ducts are Power,
ICT and GAS. Below are the broad methodology to assess the space requirement and
provision underneath the RoW.
15
Preliminary Electrical Network Planning for MBSIR
Power Supply
To provide the infrastructure for power transmission and distribution, the demand needs to
be calculated. The proposed land use distribution plays a critical role in calculation of power
demand. The power demand for residential areas will be calculated based on the population
estimation. The power demand for remaining land uses (i.e. Industrial, Logistics etc.) will be
calculated based on the area designated.
Once the demand is estimated, physical infrastructure requirement will be worked out to
assess the number of 400/220kV sub stations, 220/66kV sub stations and number of
66/11kV substation for both the clusters of MBSIR. This will also guide to determine the size
of duct required under the various RoWs for power distribution will be done during the
preliminary design.
16
Preliminary Electrical Network Planning for MBSIR
The Electrical Network will be installed by service provider and technology may changes due
to longer Development plan.
17
Preliminary Electrical Network Planning for MBSIR
Considering the estimated population and various land uses planned for the MBSIR, the estimated
power requirement for
Cluster A (TP-1, TP 2 & TP-3) is 526.61 MW (with 0.6 diversity factor -316MW including
Maruti Plant),
for Cluster B (TP4 & TP5) is 247.54 MW (with 0.6 diversity factor-149MW)
for GIDC is 478.62 MW (with 0.6 diversity factor-287MW.
Combined the total power requirement for MBSIR is 752MW (with consideration of 0.6 diversity
factor). Major components for power infrastructure are:
18
Preliminary Electrical Network Planning for MBSIR
19
Preliminary Electrical Network Planning for MBSIR
Power Source and Transmission: The power for MBSIR will be tapped from the nearby available
sources to the Main Receiving Sub Station. The alignment will be finalize during preliminary design
and discussion with relevant authority.
6.3 Main Receiving Sub Station (MRSS) and other Sub stations- Capacity, Area
requirement and proposed location
Based on the load estimation, TP scheme boundary and phasing plan, land use and present practise
in Gujarat for power transmission and distribution, following criteria as been proposed
Substation capacity
Sr. Substation (Voltage Rating) Area Requirement
(load up to)
1 400kV /200KV 200-600MW 400m X 400m (16Ha)
250m x 250m (8 Ha
2 220kV /66kV 200 MW
preferred)
75m x 75m (1 Ha
3 66kV 50-80MW
preferred)
4 11kV 5 MW 5m x 5m
Based on above criteria, the following substations has been proposed. The following table shows the
plot survey number and required area for the same.
Refer to estimated power load and other criteria as mentioned in load calculation sheet, a number
of substation of different rating has been proposed ass listed below. Below table shows the
Substation rating with proposed location. This was discussed with TP Scheme consultant.
There are two MRSS has been proposed. One MBSS in Cluster A and another for Cluster B in TP 4.
These MRSS will transmit the power to 66kV substation. ..Further, a 11kV substations will be plan for
distribution the power in the respective zones.
A Power Zoning has been done based on consideration of one 66kV substation for each zone. The
Substation location has been proposed with consideration of Bigger road access and available Govt
Land within proposed TP Scheme. The map shows the location of 66kV Sub stations in all the TP
Schemes of Cluster A and Cluster B.
Cluster A
A total Cluster A demand estimated approx.250kW (with considering 0.6 diversity factor) and for the
we have proposed following substation
Refer Annexure 1 for Cluster-A Zoning plan which shows the Zoning boundary, Location of 66kV
substation for each Zone, and 220kV substation
20
Preliminary Electrical Network Planning for MBSIR
Summary of Cluster A
Note:
Power Demand are Calculated Excluding Maruti Plant
Cluster B
A total Cluster B demand estimated approx.. 150kW (with considering 0.6 diversity factor) and for
the we have proposed following substation. Estimated load are excluding GIDC area
Refer Annexure 2 for Cluster-B Zoning plan which shows the Zoning boundary, Location of 66kV
substation for each Zone and 220kV substation
Summary of Cluster B
Note:
Power Demand are Calculated Excluding GIDC area
21
Preliminary Electrical Network Planning for MBSIR
Distribution Network: An underground distribution network has been planned to run the 66kV to
33kV/11kV distribution lines.
A 11kV substation location shall be provided through out MBSIR area in TP Scheme
Metering: Every household/connection will have a meter which helps 100% coverage, reducing
power wastage, theft and losses.
The construction of the Electrical network shall be in line with overall MBSIR Phasing plan
22